Miss Lucy
← All judgments

Union Of India vs Pradeep Vinod Construction Co.

Supreme Court14 November 2019Hrishikesh Roy · A.S. Bopanna · R. Banumathi

Ratio decidendi

The rule this decision rests on

When an agreement specifically provides for appointment of named arbitrators under defined contractual procedures, a court exercising power under Section 11 of the Arbitration and Conciliation Act, 1996 should appoint arbitrators in accordance with the terms of the agreement rather than appointing independent arbitrators, provided the party responsible for appointment has had a reasonable opportunity to do so. Where a public institution such as the Railways has failed or delayed unreasonably in appointing an arbitrator as required by the contract, and a contractor has approached the court for appointment under Section 11 of the Act, the court may in its discretion appoint either a named arbitrator as per the contract or, if necessary, an independent arbitrator; but the burden lies on the contractor to demonstrate such failure or unreasonable delay, and the proper course is to first exhaust or invoke the contractual appointment mechanism before the court appoints independently. For arbitral proceedings where the request for appointment of an arbitrator was made before the coming into force of the Arbitration and Conciliation (Amendment) Act, 2015 on 23 October 2015, the provisions of the unamended Principal Act, 1996 shall apply unless the parties agree otherwise, and the Amendment Act shall not be applied retroactively to such proceedings. Questions regarding whether documents such as final payment bills, discharge certificates, supplementary agreements recording "accord and satisfaction," or "No Claim" certificates were executed under duress, compulsion, or undue influence are matters of evidence that fall within the jurisdiction of the arbitrator to examine and adjudicate, and are not matters to be determined by the court at the stage of considering whether to appoint an arbitrator.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.6400 OF 2016

UNION OF INDIA ...Appellant

VERSUS PRADEEP VINOD CONSTRUCTION COMPANY …Respondent

With

CIVIL APPEAL NO.6420 OF 2016

UNION OF INDIA ...Appellant

VERSUS M/S. BM CONSTRUCTION COMPANY …Respondent

JUDGMENT

R. BANUMATHI, J.

These appeals arise out of the impugned judgments dated

15.05.2015 and 02.02.2015 passed by High Court of Delhi in

Arbitration Petition No.168 of 2015 and Arbitration Petition No.531

of 2014 in and by which the High Court appointed an independent Signature Not Verified Digitally signed by arbitrator for adjudication of disputes between the parties, instead of MADHU BALA Date: 2019.11.14 14:10:16 IST Reason:

directing appointment of arbitrator as per Clause 64 of General

1 Conditions of Contract (GCC) which stipulates that Railways’

Officers should be appointed as Arbitrator.

2. Brief facts which led to filing of these appeals are as under:-

Facts in CA No.6400/2016:-

On 14.07.2010, Northern Railways awarded the contract for

misc. civil engineering works such as construction of duty huts at

L-xings, water supply arrangements, provision of station name

boards etc. in connection with Rewari-Rohtak New Line to the

respondent. The total cost of the work at accepted rate came to

Rs.5,30,31,369.30. The work was finally completed on 31.03.2012.

According to the appellant, final payments were made by the

appellant to the respondent vide bill bearing Vr.No.00356/104/C/TKJ

dated 06.05.2014. On the same day i.e. on 06.05.2014, parties also

entered into a supplementary agreement which recorded full accord

and satisfaction as on 06.05.2014. In the meanwhile, on

05.05.2014, respondent sent a letter to the appellant alleging that

under the compulsion of circumstances, it had to sign the so-called

final bill without protest as desired by the administration, otherwise

heavy financial loss would have been caused to respondent and it

may not be in a position to tender and execute further works. The

respondent averred that a sum of over Rs.1.50 crores still remains

2 to be paid to the respondent and calling upon the appellant to make

the payment within 90 days. The respondent vide its letter dated

05.05.2014 invoked arbitration clause as contained under Clause

64 of General Conditions of Contract.

3. The appellant issued a reply dated 25.07.2014 rejecting the

arbitration claim of the respondent, taking the stand that the

respondent had signed the final bill and also signed the

supplementary agreement which clearly stipulates that it was

agreed between the parties that the respondent has accepted the

said sums mentioned therein in full and final satisfaction of all dues

and claims under the principal agreement.

4. The respondent thereafter filed Arbitration Petition No.168 of

2015 under Section 11 of the Arbitration and Conciliation Act, 1996

before the High Court for appointment of an arbitrator. Upon

consideration of contention of the parties, the learned Single Judge

held that the question whether the discharge certificate and

supplementary agreement were signed by the respondent under

duress, would require evidence to be led and is therefore, required

to be examined by the arbitrator. So far as the appointment of

arbitrator is concerned, the High Court held that since the Railways

failed to appoint an arbitrator despite invocation of the arbitration

3 clause by the respondent on 05.05.2014, the Railways forfeited its

right under the arbitration clause and the learned Judge appointed

Mr. Ram Prakash(Retd.), District and Sessions Judge as the sole

arbitrator instead of directing the appointment of arbitrator as per

Clause 64 of the General Conditions of Contract.

Facts in CA No.6420/2016:-

5. An agreement dated 17.01.2012 was entered into between

the Northern Railways and the respondent for construction of two

lane road over bridge in lieu of L-xing near Muradnagar Railway

Station at a cost of Rs.4,21,69,176.25/-. The work was completed

on 03.08.2013. According to the Railways, the respondent received

full and final payment vide final bill bearing Vr.No.280 dated

29.01.2014 and also signed a supplementary agreement dated

01.03.2014 acknowledging full and final settlement of all claims. It

was also provided in this supplementary agreement that the

principal agreement shall stand finally discharged and the arbitration

clause contained therein shall cease to exist. The respondent vide

letter dated 15.01.2014 raised two claims and requested for

appointment of arbitrator. The Railways informed the respondent

that the claims of the respondent are not referable to arbitration as

the same are covered under “excepted matter”. The respondent-

4 contractor on 28.08.2014 also sent a “No Claim” letter to the

Railway stating that it has no claim towards the Railways and

requested for release of security deposit made by it.

6. The respondent thereafter filed Arbitration Petition

No.531/2014 under Section 11 of the Arbitration and Conciliation

Act, 1996 seeking appointment of an arbitrator. The High Court

held that though the appellant claims that the disputes raised by the

respondent are in the nature of “excepted matters” but that the

issue can be examined by the arbitrator. With those findings, the

court appointed Mr. H.K. Chaturvedi, advocate as Sole Arbitrator

and directed that arbitration shall take place under the aegis of the

Delhi International Arbitration Centre.

7. Mr. Bharat Singh, learned counsel appearing for the appellant-

Union of India-Railways submitted that the request for appointment

of arbitrator was made before the Amendment Act, 2015 (w.e.f

23.10.2015) and hence, the proceedings will have to be proceeded

in accordance with the pre-amended provision of the Act, 1996. It

was submitted that the High Court erred in appointing an

independent arbitrator instead of directing the General Manager,

Railway administration to appoint an arbitrator as per the terms and

5 conditions of Clause 64 of GCC which stipulates that “excepted

matters” cannot be referred to arbitration.

8. Per contra, Mr. Shantanu Kumar and Ms. Geetanjali Mohan,

learned counsel for the respondent(s) submitted that once the

appellant has failed to appoint an arbitrator under the terms of the

agreement before the petition under Section 11(6) of the Arbitration

Act, 1996 being filed before the Court, the authority forfeits its right

of appointing an arbitrator and it is for the Chief Justice/Designate

Judge to appoint an independent arbitrator under Section 11(6) of

the Act. It was further submitted that Section 11(6) empowers the

court to deviate from the terms of the agreement, if required, by

appointing an independent arbitrator. Insofar as the contention that

the respondent(s) have already received the final bill and issued “No

Claim” letter to the Railway, the learned counsel for the

respondent(s) submitted that “No Claim” certificate was issued

under compulsion and it is nothing but due to undue influence by

the authorities and it is open to the arbitrator to adjudicate by

examining the bills which is furnished for payment and in such

circumstances, it cannot be said to be an “excepted matter”.

9. We have heard the learned counsel appearing for the parties.

We have carefully considered the contentions of both the parties

and perused the impugned judgment and materials on record.

6

10. The respondent(s) are registered contractors with the

Railways and they are claiming certain payments on account of the

work entrusted to them. The request of the respondent(s) for

appointment of arbitrator invoking Clause 64 of the contract was

declined by the Railways stating that their claims have been settled

and the respondent(s) have issued “No Claim” certificate and

executed supplementary agreement recording “accord and

satisfaction” and hence, the matter is not referable to arbitration.

Admittedly, the request for referring the dispute was made much

prior to the Amendment Act, 2015 which came into force w.e.f.

23.10.2015. Since the request for appointment of arbitrator was

made much prior to the Amendment Act, 2015 (w.e.f. 23.10.2015),

the provision of the Amended Act, 2015 shall not apply to the

arbitral proceedings in terms of Section 21 of the Act unless the

parties otherwise agree. As rightly pointed out by the learned

counsel for the appellant, the request by the respondent(s)-

contractors is to be examined in accordance with the Principal Act,

1996 without taking resort to the Amendment Act, 2015.

11. Insofar as the applicability of the provisions of the Principal

Unamended Act, 1996, after referring to SP Singla Pvt. Ltd. v. State

of Himachal Pradesh and another (2019) 2 SCC 488, in Union of

7 India v. Parmar Construction Company 2019 (5) SCALE 453, it was

held as under:-

“26. We are also of the view that the Amendment Act, 2015 which came into force, i.e. on 23rd October, 2015, shall not apply to the arbitral proceedings which has commenced in accordance with the provisions of Section 21 of the Principal Act, 1996 before the coming into force of Amendment Act, 2015, unless the parties otherwise agree.

27. In the instant case, the request was made and received by the Appellants in the concerned appeal much before the Amendment Act, 2015 came into force. Whether the application was pending for appointment of an arbitrator or in the case of rejection because of no claim as in the instant case for appointment of an arbitrator including change/substitution of arbitrator, would not be of any legal effect for invoking the provisions of Amendment Act, 2015, in terms of Section 21 of the principal Act, 1996. In our considered view, the applications/requests made by the Respondent contractors deserves to be examined in accordance with the principal Act, 1996 without taking resort to the Amendment Act, 2015 which came into force from 23rd October, 2015.”

12. In order to appreciate the contention of the parties, it is

necessary to refer to Clause 64 of the General Conditions of

Contract (GCC) which reads as under:-

“64. (1) Demand for Arbitration:

64. (1) (i) In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the "excepted matters" referred to in

8 Clause 63 of these Conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration.

64. (1) (ii) The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute(s) or difference(s) in respect of which the demand has been made, together with counter claims or set off, given by the Railway, shall be referred to arbitration and other matters shall not be included in the reference.

……….

64. (3) Appointment of Arbitrator:

64. (3) (a)(i) In cases where the total value of all claims in question added together does not exceed Rs. 25,00,000 (Rupees twenty five lakh only), the Arbitral Tribunal shall consist of a Sole Arbitrator who shall be a Gazetted Officer of Railway not below JA Grade, nominated by the General Manager. The sole arbitrator shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by GM. {Authority: Railway Board's letter No. 2012/CE-I/CT/ARB./24, Dated 22.10./05.11.2013}

64. (3) (a)(ii) In cases not covered by the Clause 64(3)(a) (i), the Arbitral Tribunal shall consist of a Panel of three Gazetted Railway Officers not below JA Grade or 2 Railway Gazetted Officers not below JA Grade and a retired Railway Officer, retired not below the rank of SAG Officer, as the arbitrators. For this purpose, the Railway will send a panel of more than 3 names of Gazetted Railway Officers of one or more departments of the Railway which may also include the name(s) of retired Railway Officer(s) empanelled to work as Railway Arbitrator to the contractor within 60 days from the day when a written and valid demand for arbitration is received by the GM. Contractor will be asked to suggest to General Manager at least 2 names out of the panel for appointment as contractor's nominee within 30 days from the date of dispatch of the request by Railway. The General Manager shall appoint at least one out

9 of them as the contractor's nominee and will, also simultaneously appoint the balance number of arbitrators either from the panel or from outside the panel, duly indicating the 'presiding arbitrator' from amongst the 3 arbitrators so appointed. GM shall complete this exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the names of contractor's nominees. While nominating the arbitrators, it will be necessary to ensure that one of them is from the Accounts Department. An officer of Selection Grade of the Accounts Department shall be considered of equal status to the officers in SA grade of other departments of the Railway for the purpose of appointment of arbitrator.

64. (7) Subject to the provisions of the aforesaid Arbitration and Conciliation Act, 1996 and the Rules thereunder and any statutory modifications thereof shall apply to the arbitration proceedings under this Clause.”

13. It is seen from the above that under Clause 64(1) of GCC, if

there is any dispute or differences between the parties or the

respective rights and liabilities of the parties on any matter in

question or any other ancillary dispute arising from the terms of the

contract or if the railway administration fails to make a decision

within the time stipulated thereon, then in any such case, but except

in any of the “excepted matters”, the General Manager may

nominate the officer by designation as referred to under Clause

64(3)(a)(i) and a(ii) respectively with further procedure being

prescribed for the sole arbitrator or the Arbitral Tribunal to adjudicate

the dispute/differences arising under the terms of the contract

between the parties.

10

14. In Union of India and another v. M.P. Gupta (2004) 10 SCC

504, Union of India and another v. V.S. Engineering (P) Ltd. (2006)

13 SCC 240, Union of India v. Singh Builders Syndicate (2009) 4

SCC 523 and in a catena of judgments, the court held that

whenever the agreement specifically provides for appointment of

named arbitrators, the appointment of arbitrator should be in terms

of the contract. After referring to M.P. Gupta, in V.S. Engineering, it

was held as under:-

“3. The learned Additional Solicitor General appearing for the appellant Union of India has pointed out that as per clauses 63 and 64 of the General Conditions of Contract, this Court in no uncertain terms has held that the Arbitral Tribunal has to be constituted as per the General Conditions of Contract, the High Court should not interfere under Section 11 of the Act and the High Court should accept the Arbitral Tribunal appointed by the General Manager, Railways. In this connection, the learned ASG invited our attention to a decision of this Court directly bearing on the subject in Union of India v. M.P. Gupta (2004) 10 SCC 504 wherein a similar question with regard to appointment of the Arbitral Tribunal for the Railways with reference to clause 64 of the General Conditions of Contract came up before this Court and this Court held that where two gazetted railway officers are appointed as the Arbitral Tribunal, the High Court should not appoint a retired Judge of the High Court as a sole arbitrator and the appointment of sole arbitrator was set aside. The conditions of clauses 63 and 64 of the General Conditions of Contract are almost analogous to the one we have in our hand. In that case also relying on clause 64 of the contract a three-Judge Bench presided over by the Chief Justice of India observed as follows: (SCC p.

505, para 4)

11 “4. In view of the express provision contained therein that two gazetted railway officers shall be appointed as arbitrators, Justice P.K. Bahri could not be appointed by the High Court as the sole arbitrator. On this short ground alone, the judgment and order under challenge to the extent it appoints Justice P.K. Bahri as sole arbitrator is set aside. Within 30 days from today, the appellants herein shall appoint two gazetted railway officers as arbitrators. The two newly appointed arbitrators shall enter into reference within a period of another one month and thereafter the arbitrators shall make their award within a period of three months.””

The court, however observed in para (6) that in the case of public

institutions which are slow in responding to the request made by the

contractor for appointment of an arbitrator, the power of the High

Court to appoint an arbitrator under Section 11 is not taken away.

The failure of the authorities in appointing an arbitrator and when

the contractor approached the court for appointment of an arbitrator

under Section 11 of the Act, it will then be in the discretion of the

Chief Justice/designated Judge to appoint a railway officer as per

the contract or a High Court Judge.

15. Considering the various matters of railway contracts and

setting aside the appointment of independent arbitrators, after

referring to M.P. Gupta and V.S. Engineering and other judgments,

in Parmar Construction Company, this Court set aside the

appointment of the independent arbitrator and directed the General

Manager of the Railways to appoint arbitrator in terms of Clause 12 64(3) of the agreement. In paras (44) and (45), this Court held as

under:-

“44. To conclude, in our considered view, the High Court was not justified in appointing an independent arbitrator without resorting to the procedure for appointment of an arbitrator which has been prescribed under Clause 64(3) of the contract under the inbuilt mechanism as agreed by the parties.

45. Consequently, the orders passed by the High Court are quashed and set aside. The Appellants are directed to appoint the arbitrator in terms of Clause 64(3) of the agreement within a period of one month from today under intimation to each of the Respondents/contractors and since sufficient time has been consumed, at the first stage itself, in the appointment of an arbitrator and majority of the Respondents being the petty contractors, the statement of claim be furnished by each of the Respondents within four weeks thereafter and the arbitrator may decide the claim after affording opportunity of hearing to the parties expeditiously without being influenced/inhibited by the observations made independently in accordance with law.”

The ratio of the above decision squarely applies to the case in

hand. When the agreement specifically provides for appointment of

named arbitrators, the appointment should be in terms of the

agreement. The High Court, in our view, was not right in appointing

an independent arbitrator ignoring Clause 64 of the General

Conditions of Contract.

16. Insofar as the plea of the appellant that there was settlement

of final bill/issuance of “No Claim” letter, the learned counsel for the

appellant has drawn our attention on Clause 43(2) – Signing of the

13 “No Claim” Certificate and submitted that as per Clause 43(2), the

contractor signs a “No Claim” certificate in favour of the railway in

the prescribed format after the work is finally measured up and the

contractor shall be debarred from disputing the correctness of the

items covered under the “No Claim” certificate or demanding a

clearance to arbitration in respect thereof. On behalf of the

respondent, it has been seriously disputed that issuance of “No

Claim” certificate as to the supplementary agreement recording

accord and satisfaction as on 06.05.2014 (CA No.6400/2016) and

issuance of “No Claim” certificate on 28.08.2014 (CA No.6420/2016)

that they were issued under compulsion and due to undue influence

by the railway authorities. We are not inclined to go into the merits

of the contention of the parties. It is for the arbitrator to consider the

claim of the respondent(s) and the stand of the appellant-railways.

This contention raised by the parties are left open to be raised

before the arbitrator.

17. In the result, the impugned judgments dated 15.05.2015 and

02.02.2015 of the High Court of Delhi in Arbitration Petition No.168

of 2015 and Arbitration Petition No.531 of 2014 are set aside and

these appeals are allowed. The appellant is directed to appoint the

arbitrator in terms of Clause 64(3) of the agreement within a period

14 of one month from today under intimation to the respondent(s)-

contractors. As soon as the communication of the appointment of

arbitrator is made to the respondent(s), the statement of claim be

filed by the respondent(s) within six weeks thereafter and the reply

of the appellant to be filed within four weeks thereafter. The

arbitrator shall proceed with the matter in accordance with law and

decide the claim after affording sufficient opportunity of hearing to

both parties expeditiously preferably within a period of four months.

………………………..J. [R. BANUMATHI]

………………………..J. [A.S. BOPANNA]

….………………………..J. [HRISHIKESH ROY]

New Delhi;

November 14, 2019

15

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free