The Vice Chairman and Managing Director, City and Industrial Development Corporation of Maharashtra Ltd. vs Shishir Realty Pvt Ltd
- SCC(2022) 16 SCC 527
- Neutral2021 INSC 796
- SCR[2021] 10 SCR 1146
Ratio decidendi
The rule this decision rests on
1. In judicial review of administrative decisions concerning government contracts and tender processes, the court must evaluate the decision against the standards of legality, procedurality, proportionality and arbitrariness—not merely substantive merits. While the court accords discretion to administrative authorities and exercises restraint in interfering with tender decisions, it retains supervisory jurisdiction to ensure that such decisions are free from arbitrariness, bias, mala fides and violation of the rule of law. 2. Where an administrative enquiry is conducted into alleged irregularities in a tender without providing prior notice and hearing to the affected parties, and a show-cause notice is issued post-facto merely to sanctify conclusions already reached, the procedural defect vitiates the enquiry and the order based upon it, as it violates the principles of natural justice which are foundational to the rule of law. 3. When an administrative authority renders an order cancelling a contract on specified grounds, the validity of that order must be judged solely by the reasons actually recorded in the order and cannot be supplemented by fresh reasons advanced in affidavits or submissions during litigation. 4. A bidder who discloses at the time of tender that a partnership firm's registration is pending, and whose technical bid is accepted by the administrative authority's legal team after consideration, cannot subsequently be disqualified on the ground that the firm was not registered at the time of bidding, particularly where the authority has accepted substantial lease premiums in reliance on the allotment. 5. Contractual provisions providing that a lessee may apply for change of land use and that the administrative authority may permit such change at its discretion authorize the authority to grant such changes; where the authority has exercised this power and accepted change of user fees, it cannot subsequently revoke the change on the ground that no such power existed. 6. Contractual clauses permitting transfer or assignment of rights with prior written permission of the administrative authority are not voided by a technical defect in the sequence of execution (such as the transfer occurring on the day after execution of the agreement to lease rather than after) where the lease premium has been paid in full and the authority has acquiesced in the transfer. 7. The doctrine of promissory estoppel applies to the Government and public authorities even in the exercise of their executive and contractual functions. Where the Government makes a promise or grants a concession knowing or intending that it will be acted upon, and the promisee acts in reliance and alters his position, the Government cannot be released from its obligation merely by claiming public interest. The burden lies on the Government to demonstrate through material evidence, facts and figures that enforcing the promise would substantially prejudice public interest; a blanket allegation of loss to the treasury unsupported by concrete evidence cannot displace the doctrine of promissory estoppel. 8. Where a Government authority succeeds an earlier administration and seeks to cancel or revoke contractual arrangements made by its predecessor, it cannot do so merely on the basis of change of political leadership or a desire to reverse prior decisions without establishing that the prior arrangements were contrary to statutory provisions, were unreasonable, or were against established policy. The state, being a continuing body bound by rule of law, cannot simply change its position through a change in the executive head absent legal justification. 9. Fairness and good faith standards applicable to contracts entered into by public authorities mandate that such authorities conduct themselves in a non-arbitrary manner during performance of contractual obligations. The constitutional guarantee against arbitrariness under Article 14 requires the State to act in a fair and reasonable manner unless public interest demands otherwise, and the degree of compromise of any private legitimate interest must correspond proportionately to the public interest claimed. 10. A public authority cannot justify post-hoc reversal of a tender allotment and cancellation of a contract on grounds of alleged loss to the public exchequer or changed circumstances without placing material evidence on the record establishing such loss or prejudice, and cannot invoke public interest as a blanket justification to escape contractual obligations where the promisee has acted in reliance on the authority's representations and undertakings.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS. 39563957 OF 2017
THE VICE CHAIRMAN & MANAGING DIRECTOR, CITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LTD.& ANR. …APPELLANTS
VERSUS
SHISHIR REALTY PRIVATE LIMITED & ORS. ETC. …RESPONDENTS
WITH
CIVIL APPEAL NOS. 39593961 OF 2017
SANJAY KUMAR SURVE …APPELLANT
VERSUS
THE STATE OF MAHARASHTRA & ORS. ETC. …RESPONDENTS
JUDGMENT
N. V. RAMANA, CJI
1. Signature Not Verified Digitally signed by Vishal Anand These Civil Appeals arise out of the impugned judgment Date: 2021.11.29 17:47:00 IST Reason:
dated 06.12.2013 passed by the High Court of Judicature at 1 Bombay in Writ Petition No. 702 of 2011, Writ Petition No.
5245 of 2011, and Public Interest Litigation No. 55 of 2011.
2. At the outset, a brief sketch of the facts is necessary for
determining the issue. On 11.06.2008, the appellants in
Civil Appeal Nos. 39563957 of 2017 (City and Industrial
Development Corporation of Maharashtra, for short
“CIDCO”) called for a tender for lease of land within its
jurisdiction, for purposes of development of necessary
infrastructure such as Hotels etc., around Navi Mumbai
Airport. Respondent M/s Metropolis Hotels was one of the
bidders.
3. Before approval of the tender, technical qualifications of the
bidders were scrutinized and approved by the CIDCO’s legal
team on 25.07.2008 in the following manner:
“Metropolis Hotels is a Partnership firm consisting of M/s SunnSand Hotel Pvt. Ltd. and Shishir Realty Pvt. Ltd having their share 30% each. A short question arises for the determination is whether Board Resolution of the partnership firm is required to be annexed with the offer.
It appears from the technical bid of M/s Metropolis Hotels that the said bid is signed by both the partners jointly. Section 4 of the Indian 2 Partnership Act 1932 defines ‘Partner’ and ‘Partnership’ is the relation between persons who have agreed to share the profits of a business carried on by all or any of them acting for all. Persons who have entered into partnership with one another are called individually “partners” and collectively “a firm”, and the name under which their business is carried on is called the “Firm Name”. Partnership is not created by status and arises from contract. In the Indian Partnership Act, 1932, there are no directors, and all the partners are jointly and severally responsible for all the acts of the firm.
In view of this Board Resolution is not required. Therefore, the remarks appearing on the scrutiny sheet at Sr. No. 19, requires to be ignored and technical offer should be accepted.”
On 25.07.2008, the financial bids were opened, which stood
as under:
SL. NAME OF OFFEROR RATE QUOTED (RS. REMARKS NO. PER SQ MTRS.)
1. M/s. Metropolis Hotel 60,085.10 1st Highest (Respondent no.1 in C.A. No. 3957 of 2017)
2. M/s. Indian Hotels Co. 55319.15 2nd Highest Ltd.
3. M/s. SunNSand 49,361.70 3rd Highest Hotels Pvt. Ltd.
4. M/s. L&T Leela Venture 48,063.90 4th Highest Co.
3 4. On 25.07.2008, M/s. Indian Hotels Company Ltd., who were
H2 in the bidding process, wrote to CIDCO, objecting to the
eligibility of the highest bidder in the following manner:
“3. We are informed that the highest bidder is a partnership firm and has relied on the experience of one of this partners to satisfy the eligibility norm. The same partner has also bid on its own. This amounts to multiple bidder with the same experience being concerned for more than one bid.”
On 04.08.2008, these objections were considered by the law
officers of the CIDCO and subsequently rejected.
5. On 07.08.2008, the CIDCO issued a letter of allotment in
favour of M/s. Metropolis Hotels. Being the highest bidder,
M/s. Metropolis Hotels was accordingly, allotted Plot No. 5,
admeasuring about 47,000 sq. mtrs., for construction of a
fivestar hotel near the proposed Navi Mumbai Airport.
6. Thereafter, on 29.12.2009, M/s. Metropolis Hotels
Respondent no.1, by way of a letter to CIDCO, applied for
change of user of 34,000 sq. mtrs. of the said plot to
commercialcumresidential use. On 11.02.2010, this
request for change/expansion of user of Plot No.5 was
4 considered and subsequently permitted only for 23,000 sq.
mtrs.
7. On 11.03.2010, M/s. Metropolis Hotels requested for
subdivision of the Plot No.5 into two, i.e. 24,000 sq. mtrs.
for the fivestar hotel and 23,000 sq. mtrs. for the
residentialcumcommercial plot. By way of a letter dated
29.03.2010, CIDCO demarcated the said plot as requested,
forming Plot No.5 (admeasuring 24,000 sq. mtrs.) and Plot
No.5A (admeasuring 22,999.08 sq. mtrs). M/s. Metropolis
Hotels also requested assignment of their rights in respect of
the plot on which the residentialcumcommercial user was
permitted, i.e. Plot No.5A. Assignment of this plot to M/s.
Shishir Realty Private Ltd. was approved by CIDCO in its
letter dated 30.03.2010, wherein it referred to the said
assignee as one of the partners in the original allotment.
8. On 30.03.2010, the CIDCO executed two separate lease
deeds in respect of the two plots, i.e. Plot No. 5 and Plot No.
5A. M/s. Shishir Realty Private Ltd. took further steps for
mortgaging their plot with the permission of the CIDCO and
obtained loan for development of the said plot for
5 commercialcumresidential user. Thirdparty rights were
also created.
9. As complaints were made regarding irregularities in
allotment of plots of land, change of user and deviation from
the terms and conditions of the tender, a preliminary
enquiry was held by the Principal Secretary, Urban
Development Department as per the directions of the State
Government of Maharashtra. Based on such enquiry, the
newly appointed Vice Chairman issued a showcause notice
dated 06.12.2010 to M/s. Metropolis Hotels and M/s.
Shishir Realty Private Ltd.(respondentslessees) as to why
the lease deeds which were executed in their favour should
not be cancelled on account of breach of tender conditions
by M/s. Metropolis Hotels. It may be relevant to note
observations made in the show cause notice which inter alia
read as under:
“13. Since the tenders were invited for grant of lease of fivestar hotel plot, only bidders interested in development of 5star Hotel participated in the bidding process. Had the Corporation invited tenders with residential + commercial use of the plot, several bidders could have participated in the bidding process and the Corporation might have fetched higher 6 revenue. Due to change of user and sub division of the plot contrary to the terms and conditions of invitation of offer, several eligible bidders were deprived and also caused financial loss to the public exchequer. Besides this, due to change of user and subdivision of the plot, the basic object of development of 5 star hotel is frustrated.
14. For the bench or benches (sic) of the terms and conditions of tender and letter of allotment dated – 07.08.2008, you are hereby called upon to show cause as to why the Corporation should not cancel or revoke the agreements concluded vide Letter of Allotment dated 07.08.2008 and Agremeents to lease dated 30.03.2010, in respect of Plot No.5, 2 admeasuring 24,000 m in favour of M/s.
Metropolis Hotels and Plot No.5A, admeasuring 23,000 m2 in favour of M/s. Shishir Realty Pvt. Ltd.”
10. Vide order dated 16.03.2011, the Vice Chairman, CIDCO,
cancelled the lease deeds, pursuant to the enquiry. The
issues under consideration, as identified in the said order,
are reproduced as under:
SL. FINDING ISSUES NO. S
1. Whether M/s. Metropolis Hotels was eligible to participate in the bidding process for allotment of 5 No Star Hotel Plot, in accordance with Clause 4(c) of the invitation of offer?
7
2. Whether change of user for part of the plot admeasuring 23,000 m2 and subdivision of plot in breach Yes of the terms and conditions represented in the Tender document and letter of allotment?
3. Whether transfer of part of the subdivided plot of admeasuring 23,000m2 with change of user in favour of M/s. Shishir Realty Pvt.
Ltd. before execution of agreement No to lease was consistent with Condition No.16 of the General Terms and Conditions of Tender and Condition No.21 of the letter of allotment?
4. Whether change of user and sub division of plot has adversely Yes affected the object of development of 5 Star Hotel in Navi Mumbai?
5. Whether change of user and sub division of plot and transfer of part [No] of the plot was legal, just and proper?
11. Pertaining to the first issue of the eligibility of M/s.
Metropolis Hotels to participate in the bidding process, the
order held that Clause 4(c) of the tender document obligated
the bidders to have a registered partnership firm. It
concluded that since M/s. Metropolis Hotels was not
registered, on the date of submission of the bid, they were
ineligible for bidding. Accordingly, their offer was void ab
8 initio. The second reason provided was that M/s. SunN
Sand Hotels, being partners in M/s. Metropolis Hotels, could
not have submitted a separate bid, which also vitiated the
bid made by Metropolis Hotels.
12. On the aspect of whether subdivision of the plots and
change of land use were consistent with the terms and
conditions of the tender document and letter of allotment,
the order observed that offers were invited for fivestar
hotels and subdivision/change of use could not have been
permitted as such changes were not conducive to public
interest and were against express terms and conditions
mentioned within the agreement.
13. On the third issue of whether transfer of part of the sub
divided plot to Shishir Realty Pvt. Ltd was consistent with
terms of the tender and letter of allotment or not, the order
observed that the terms of the allotment letter read with the
General Terms and Conditions clearly showed that the
transferee should fulfil all eligibility criteria prescribed in the
invitation of offer. As there was nothing on record to
establish that M/s. Shishir Realty Pvt. Ltd. had fulfilled 9 such criteria, the transfer was held to be in violation of such
terms and conditions.
14. On the aspect of whether the change of user and sub
division of the plot adversely affected the object of
development of a fivestar hotel, the order noted that the
change of user and subdivision of plots were in
contravention of the terms and conditions initially offered.
Due to such changes, the basic object of development of a
fivestar hotel in Navi Mumbai was frustrated.
15. On the aspect of whether allotment of the plot, change of
land use, and subdivision of plots was arbitrary, illegal, and
unjustified, the order noted that the deviations could be
categorized as major deviations from the terms and
conditions mentioned in both the tender documents and
letter of allotment. Such deviation frustrated the basic
purpose of development of a fivestar hotel. Therefore, it was
concluded that the aspect of promissory estoppel against the
CIDCO would not be applicable as specific terms of the
tender and letter of allotment were deviated. Further, such
deviations were not in public interest. Accordingly, the two
10 lease deeds in favour of the respondentslessees were
cancelled.
16. Aggrieved by the cancellation of the lease deeds, M/s.
Metropolis Hotels and Shishir Realty Pvt. Ltd., challenged
the aforesaid order of the Vice Chairman, CIDCO, through
two writ petitions being Writ Petition No. 702 of 2011 and
Writ Petition No. 5245 of 2011 before the High Court of
Judicature at Bombay. Separately, a PIL was also filed
challenging the allotment of the plot in question, change of
land use, and subdivision of the said plot.
17. The High Court, vide impugned order dated 06.12.2013,
while quashing the aforesaid cancellation order passed by
CIDCO, held that the change of land use and subdivision of
the plot had taken place with due authorization of the
CIDCO. Further, it held that the CIDCO was not able to
show any concrete violations which go to the root of the
matter. Finally, the High Court held that, without producing
any pressing need on record, the CIDCO is precluded and
estopped on the doctrine of promissory estoppel from
canceling the allotment.
11
18. Aggrieved by the impugned judgment, the CIDCO and PIL
petitioner appellant in C.A. Nos. 39593961 of 2017 have
filed separate appeals before this Court.
19. Mr. Rakesh Dwivedi, learned Sr. Counsel, appearing on
behalf of the CIDCO, has argued that:
a) The High Court judgment cannot be sustained as the
same was delivered ignoring blatant violations and
illegalities committed during the tender process.
b) Primarily, the bid by M/s. Metropolis Hotels itself was
illegal as it has only registered subsequent to the
allotment, which is a clear violation of clause 4(c) and
8(b) of the tender document.
c) Moreover, subsequent to the award of the contract, M/s.
Metropolis Hotels went beyond the tender conditions
and expanded the usage to residentialcumcommercial.
Additionally consequent to change of usage, the M/s.
Metropolis Hotels subdivided the plot and executed a
fresh lease in favour of Shishir Realty Pvt. Ltd. The
aforesaid acts were in breach of the original allotment
letter.
12
d) This Court while concerned with distribution of State
largesse, should ensure that no arbitrariness,
favouritism has taken place.
e) The Respondents cannot claim any relief based on the
doctrine of promissory estoppel as being a creature of
equity, it must yield when the equity so requires.
Considering it would be inequitable to hold the
Government to the promise made by it, the Court should
not raise an equity in favour of the promisee and enforce
the promise against the Government.
f) It is well settled legal proposition that the private
interest would always yield place to the public interest.
Considering, the irregularities committed by the
respondents, it is expedient to revoke the allotment in
favour of the Respondents especially when no grave
prejudice will be caused to the allottee.
20. Mr. Atmaram Nadkarni, learned Sr. Counsel, appearing on
behalf of the State of Maharashtra while supporting the
submissions made by CIDCO, has argued that:
13
a) This court, in a catena of judgments, has held that the
representations made to the public by way of tender
conditions and policies cannot be changed arbitrarily
after the allotment.
b) The rules of the game cannot be changed once the game
is played.
21. Mr Harinder Toor, learned Counsel, appearing on behalf of
the PIL petitionerappellant in C.A. No. 39593961, has
argued that:
a) The PIL petitioner/appellant is a social activist and is
involved in the business of construction services.
b) The change of land use is in violation of clause 15 of the
letter of allotment, which mandated that the allotted
land shall be used only for the construction of a five star
hotel.
c) The change of land use was illegal and arbitrary.
d) The subdivision of plots was also invalid.
22. Dr. Abhishek Manu Singhvi, learned Senior Counsel,
appearing on behalf of Shishir Realty Pvt. Ltd., argues that:
a) M/s.Metropolis Hotels was a partnership firm and had
applied for registration. When bid was made, they had 14 declared the same to CIDCO. The enforcing committee
received the bid being fully aware that the application for
registration of partnership firm was pending before the
registrar and decided to go with their bid as it was Rs.23
crore higher than the next bid.
b) Additionally, the enquiry that was conducted against the
said allocation was in complete abrogation of natural
justice. No notice was issued to the respondents during
the pendency of the enquiry. Even while accepting the
report of the Principal Secretary, no hearing was given to
the respondents.
c) Not only is CIDCO bound by the principles of estoppel,
but they have also failed to prove any losses attributable
to the respondent.
d) CIDCO has only raised bald allegations of collusion with
management. Had there been any real apprehension of
collusion or financial losses arising out of this
transaction, the State would have taken criminal
action/disciplinary actions against the erring officials.
15 However, CIDCO have failed to place anything on record
to prove the same.
23.Mr. Mukul Rohatgi, Learned Senior Counsel, appearing on
behalf of M/s. Metropolis Hotels argues that:
a) The purpose of construction of a fivestar hotel has been
frustrated considering the fact that the same was
contingent on the coming up of Navi Mumbai Airport.
b) Without there being an airport, it would be commercially
absurd to construct a fivestar hotel in the middle of
nowhere.
c) The bidding process was conducted in 2008, when there
was a huge recession both globally and in India. The
tender had attracted M/s. Metropolis Hotels because it
was stated that the Navi Mumbai Airport would be built
near the concerned plot, and the area would be declared a
Special Economic Zone. However, the promises of the
tender document were not fulfilled and hence, an
application for change of user was made. The 1997 policy
allows for a change of user and hence, there is no
illegality.
16 d) There is no violation of any condition of the tender
document concerning subdivision of plots.
e) Moreover, even after the allotment was made the
respondents have complied with the due procedure and
have paid the requisite fees. After accepting the requisite
charges to the tune of Rs. 321 crores, the cancellation of
the allotment after 13 years is not only highly inequitable
but will also cause grave prejudice to the respondents.
f) He disputes the bonafides of the PIL petitioner.
24. Heard learned counsels from both sides.
25. Before we delve into analysis of the case, it is pertinent to
examine the role of Constitutional Courts in reviewing the
tender process. The Constitution of India allows the
government to enter into contracts and perform certain
commercial activities. Due to increase in government
business, there is a requirement of this Court to uphold
certain discretion accruing to the government and disallow
certain conduct in light of prevailing circumstances. Merely
instilling an agency with discretion may not be prohibited by
the Constitution, rather it is unfettered use of such
17 discretion, that is prohibited; the Constitution frowns upon
those decisions which are taken in gross abuse of law.
English Courts have developed many legal standards for
evaluating administrative decisions, one of them being
enumerated in the case of Council of Civil Service Unions
v. Minister for the Civil Service, [1985] AC 374, wherein
Lord Diplock has summarized the grounds of challenging
such decisions under the broad heads of illegality,
irrationality, procedural impropriety and legitimate
expectation. Beyond these grounds, a recent development in
the form of proportionality has further increased the scope
of judicial review.
26. Being governed under “rule of law” every action of the State
or its instrumentality while exercising its executive powers
must met the aforesaid requirements. While recognising the
existing principle of freedom to enter or not to enter into
contracts by the state and its instrumentalities, the manner,
method and motive behind the aforesaid decision can be
subjected to judicial review on the touchstone of equality,
fairness, proportionality and natural justice. The decision of
18 the executive must strike a balance with the alleged
violation with that of the penalty imposed.
27. This Court, in many of its orders reviewing tender
conditions, has vouched for providing sufficient discretion
and independence to administrative authorities so as to
enable them to perform their duties in the interest of the
public. Further, the observation of judicial restraint while
reviewing such contracts is a continuing trend which can be
seen in a catena of cases.1 The power of judicial review
accorded to Constitutional Court of India and its jurisdiction
is supervisory.
28. This court in the case of M/s Star Enterprises v. City and
Industrial Development Corporation of Maharashtra
Ltd., (1990) 3 SCC 280 reiterated the aforesaid concerns
and stated the necessity of judicial review even with respect
to the commercial transactions undertaken by the State.
This court held as follows:
“10. In recent times, judicial review of administrative action has become expansive and is becoming wider day by day. The traditional limitations have been
1 Municipal Corporation, Ujjain v. BVG India Ltd., (2018) 5 SCC 462 19 vanishing and the sphere of judicial scrutiny is being expanded. State activity too is becoming fast pervasive. As the State has descended into the commercial field and giant public sector undertakings have grown up, the stake of the public exchequer is also large justifying larger social audit, judicial control and review by opening of the public gaze; these necessitate recording of reasons for executive actions including cases of rejection of highest offers. That very often involves large stakes and availability of reasons for actions on the record assures credibility to the action; disciplines public conduct and improves the culture of accountability. Looking for reasons in support of such action provides an opportunity for an objective review in appropriate cases both by the administrative superior and by the judicial process.”
(emphasis supplied)
29. In this context, this Court in Tata Cellular v. Union of
India, 1994 (6) SCC 651, observed certain principles
elucidated as under:
“94.The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative action.
20 (2) The court does not sit as a court of appeal but merely reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which itself may be fallible.
(4) The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract.
Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides.
(6) Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure.”
(emphasis supplied)
21
30. These principles acquire importance as the efficacy of
commercial activities in the public sector increases greatly.
It appears that public interest litigation has opened a large
window to entertain any tender, regardless of scale, which
are now sought to be challenged as a matter of routine.
Such disruption could hardly have been the objective of
expanding the need of Constitutional Review. Close scrutiny
of minute details, contrary to the view of the tendering
authority, makes execution of contracts in the public sector
a cumbersome exercise. Often, it is the case that parties
entertain the idea of a longdrawnout litigation at the very
threshold itself. The purpose of imbibing the spirit of
competition in a process such as that of the bidding process,
is lost in this meandering exercise and delays suffered due
to pending litigation. This causes great disadvantage to the
government and public sector in general. This Court, in
appropriate cases while interpreting the contract, can
restrict the review mechanism by not inuring to the
interpretation so provided by third parties or parties
competing for the tender, unless the impugned
22 interpretation is shown to be gross abuse of law. 2 The object
of judicial review cannot be that in every contract where
some parties lose out, a second opportunity is provided to
such parties to pick holes so as to disqualify successful
parties, on grounds which even the party floating the tender
find to be without merit. With this brief background on the
standard of judicial review, we may analyze the case at
hand.
31. At the outset, the respondentslessees have argued that
entire process of cancellation of the tender stood vitiated as
it was based on the enquiry conducted by the Principal
Secretary, Urban Development Department, without
affording a chance to be heard.
32. It is borne from the records that, upon receiving the certain
complaints, the State Government initiated enquiry against
the alleged irregularities during the tender process. On
18.09.2010, the Shishir Realty Private Ltd. received an order
from the Navi Mumbai Municipal Corporation directing them
2 B. S. N Joshi & sons Ltd. v. Nair Coal Services Ltd., (2006) 11 SCC 548 23 not to carry any further construction and stay the
development.
33. On 03.11.2010, the enquiry committee submitted its report
to the State Government recommending the cancellation of
tender. On 19.11.2010, the State Government accepted the
findings of the enquiry committee and directed CIDCO, to
implement the findings of the enquiry committee.
34. Shishir Realty Private Ltd. has placed on record letter dated
23.12.2010 addressed to the Urban Development
Department and CIDCO, stating that he was shocked to see
a newspaper report stating that a committee appointed by
the State Government has recommended the cancellation of
the allotment done in their favour. The aggrieved
Respondent challenged the aforesaid recommendation as it
was passed without affording an opportunity of hearing
themthe aggrieved party.
35. Subsequent to the aforesaid letter, on 28.12.2010, the
Respondentslessees received a showcause notice dated
back to 06.12.2010. The respondentslessees submitted
their responses on 30.12.2010, 13.01.2011 and on 24 19.02.2011. Finally hearing was given to the respondent on
03.03.2011. Thereafter, finally on 16.03.2011, the CIDCO
cancelled/revoked the letter of allotment and the
subsequent permissions. Vide the aforesaid order, the
Manager (Town Services) was also directed to take over
possession of the plots within 15 days.
36. The perusal of the materials produced on record shows that
the initiation of the enquiry by the Principal Secretary,
Urban Development Department was suomotu, without any
natural justice being provided for the respondentslessees.
After arriving at a conclusion, a showcause notice was
issued by CIDCO to sanctify the enquiry. The aforesaid fact
of postdecisional hearing just to sanctify the process of
cancellation is clearly evidenced in the order dated
16.03.2011, passed by the Vice Chairman and Managing
Director CIDCO, cancelling the tender in the following
terms:
“1. The Government of Maharashtra through the Principal Secretary, Urban Development Department conducted enquiry into the irregularities in allotments of plots, change of user and deviation of the terms and conditions of 25 the tender made by the then Vice Chairman and Managing Director, CIDCO, during the period from Ist October, 2009 to 31st March, 2010. The Principal Secretary Urban Development Department conducted the enquiry and submitted his report to the State Government on 03.11.2010. The change of user, subdivision and transfer of part of plot no. 5, Sector 46A, Nerul, to M/s Metropolis Hotels was also covered in the enquiry conducted by the Principal Secretary, Urban Development Department. The State Government accepted the findings and recommendations of the enquiry committee and directed the Managing Director, CIDCO, vide letter dated 19.11.2010, to implement the findings and recommendations of the Principal Secretary, Urban Development Department. The Principal Secretary has recorded his findings about the irregularities in acceptance of tender and breach of tender conditions, change of user, subdivision of plot and further transfer of part of the plot and further recommended cancellation of the tender process.
2. Although the State Government issued directions to cancel the entire tender process, it was felt necessary to re examine the entire issue for allotment of land …. by conducting an enquiry and giving opportunity of hearing to the parties.”
26
37. Such illegal procedure adopted, clearly vitiates the
subsequent order by the ViceChairman, due to the
irregularity, which goes to the root of the matter. The
conduct of the appellant authorities indicate that the
enquiry was not conducted with an open mind. The pre
existing findings of the Principal Secretary recommending
the cancellation of allocation has the potential to color the
entire proceedings held subsequently just to meet the
procedural requirements.
38. Natural justice is an important aspect while reviewing the
administrative orders. Providing effective natural justice to
affected parties, before a decision is taken, it is necessary to
maintain rule of law. Natural justice is the sworn enemy of
intolerant authority. Any attempt by authority to circumvent
the requirement of providing effective hearing before
reaching a conclusion, cannot pass the muster. Coming to
the facts herein, the postdecisional hearing given to the
respondentlessee is reduced to a lipservice, which cannot
be upheld in the eyes of law.
27 39. As a first step of judicial review, we need to note that when
statutory functionaries such as CIDCO render an order
based on certain grounds, its validity must be judged by the
reasons so mentioned and cannot be supplemented by fresh
reasons in the shape of an affidavit or otherwise. 3 To this
extent, we agree with the submission of Dr. Abhishek Manu
Singhvi, that the scope of this Court is limited. Hence, we
will only consider the impugned order of CIDCO dated
16.03.2011 and the reasoning supplied therein.
40. At this juncture, it is pertinent to consider certain
allegations of violation raised by the appellant authorities.
The first aspect for the consideration of this Court is
whether M/s. Metropolis Hotels Ltd. was disqualified from
participating in the bidding process. The impugned order
dated 16.03.2011 of CIDCO provides two reasons: the first
being that M/s. Metropolis Hotels was not a registered
partnership firm while applying for the tender process, and
the second that one of the partners of M/s. Metropolis
3 Mohinder Singh Gill v. Chief Election Commissioner, New Delhi, (1978) 1 SCC 405.
28 Hotels, namely M/s. SunNSand Hotels Pvt. Ltd, had
submitted a separate bid.
41. The perusal of the bid document clearly indicates that the
respondent M/s. Metropolis Hotels at the time of applying
for the bid had duly disclosed that the firm had already
applied for registration and had also forwarded the
Registration Form and Partnership Deed along with the
tender documents. Subsequently, on 16.01.2009 the
Registrar of the firms issued the certificate of registration in
favour of the respondent M/s. Metropolis Hotels.
42. Having considered the communication and legal opinion
tendered before accepting the highest bid, CIDCO’s law
officers did their due diligence, who opined that
partnerships being creatures of contracts, the requirement
of Board resolutions and other technical objections raised
were not an essential condition. Therefore, at this stage it
may not be equitable to review such issues in detail.
43. Moreover, after accepting the lease premium of
Rs.282,39,99,700/ and a transfer fee of Rs. 1,38,56,000/,
the appellant authority cannot contend that the 29 respondentslessees lacked the eligibility to contend in the
tender. The respondentslessees also pointed out that, being
the highest bidder with a margin of Rs. 23 crores over the
second highest bidder, the appellant authority did not go
into the technicalities behind the matter. Even, the High
Court while passing the impugned judgment has
commented that the appellant was aware about the pending
registration, and even assented to the same as no objections
were raised while assessing the technical bids.
44. The second objection which the CIDCO in its order notes as
under:
“Apart from this, M/s. SunNSand Hotels Pvt. Ltd., one of partners of M/s. Metropolis Hotels also submitted separate offer in the bidding process. Such multiple offers were submitted by M/s. SunNSand Hotels Pvt. Ltd. with a view to get the land allotted. On this count also, the offer of M/s. Metropolis Hotels stand vitiated, and the concluded agreement is liable to be terminated.”
45. In our considered opinion, the aforesaid paragraph does not
indicate sufficient reasons. There is no reason provided as to
what provision of law such bids violate. Further, there is no
concrete allegation or adjudication on the suggested
30 cartelization. There is no reasoning considered as to why
such a practice was harmful to public interest. We may note
that such considerations are important elements of party
autonomy and commercial freedoms while framing the
contract, which is not within the purview of judicial review.
As there is no such law or contract provision which bars
such conduct, the considerations undertaken by the order of
CIDCO are extraneous and the same cannot be accepted.
46. The second aspect considered by the appellant (CIDCO)
was the change of land use. According to CIDCO, such
change of land use was not permitted under the contract.
Therefore, it was argued to be not valid. On the contrary, the
respondents have argued that not only CIDCO was
authorized to change the usage but also the Clause 19 of the
allotment letter provided that development of the plot was
governed under the General Development Control
Regulations for Navi Mumbai which also had similar
provisions. Moreover, the respondentslessees contended
that, this was not the first instance of change of usage. To
support the said averment, the respondentslessees placed
31 strong reliance upon the decision of this Court in the
identical matter of CIDCO Maharashtra Ltd. v. M/s.
Shree Ambica Developers, in C.A. No.7581 of 2012. This
Court held therein:
“We have as a measure of abundant caution examined the relevant official record which was produced before us by Mr. Bhasme, counsel appearing for the appellant. While the application for change may have been filed only a few days after the auction was conducted, the same was processed at different levels giving an opportunity to officials dealing with specialised fields to record their opinion on the permissibility of the proposed change. From a perusal of the notings recorded on the file, we are satisfied that the change was found to be permissible in – accordance with General Development Control Regulations. We must say to the credit of M/s Lalit and Bhasme that they did not question the correctness of the views recorded by the officers, who examined the permissibility of a change as prayed for by the company. It was not their contention that the change was against the development plan that could have made the same untenable in law, nor was there any suggestion that any one of the functionaries associated with the decision making process had played a fraud on the statute or the exercise of power vested in him. It is true that the official record produced before us, does not reveal that the question of financial implications, if
32 any, involved in the change which could and perhaps ought to have been examined was examined by any one at any stage. But so long as the appellant did not make absence of such a consideration a ground for cancellation of change in use, we cannot help leave alone permit the Corporation to add the same as a ground for supporting the order recalling – the grant of the change. The order passed by the Corporation/its Managing Director cancelling the earlier change was based entirely on the alleged absence of authority vested in it to direct such a change.”
(emphasis supplied)
47. Upon the perusal of the above cited decision, we are of
the opinion that the aforesaid opinion is squarely applicable
in the present case. Although the argument made by the
CIDCO is attractive at the outset, a deeper analysis makes it
clear that such argument is devoid of merit. In this context,
it may be necessary to note certain clauses contained in the
Tender Document and Allotment Letter:
“4. Who is eligible to offer to acquire plot
(a) A person competent to contract under the Indian Contract Act is eligible to make offer to acquire plot.
(b) A company incorporated under the Indian companies Act, 1956 is eligible to make offer to acquire plot.
33 (c) A partnership firm registered under Indian Partnership Act, 1932 is eligible to offer to acquire plot. Offer shall be signed by all partners and enclosed with a true certified copies of Deed of Partnership and certificate of registration.
(d)A public trust registered under Public Trust Act, 1950 and also registered under Society Registration Act, 1860 is eligible to offer to acquire plot.
(e) A Cooperative society registered under the Maharashtra Cooperative Societies Act, 1960.
The Offer form must be signed by the Chairman or the Hon. Secretary of the society without which it will be held invalid. The authorization of general body must be enclosed with the offer.
18. General CIDCO reserves the rights to amend, revoke or modify the above conditions at its discretion as well as to reject any or all offers without assigning any reasons.
… General Terms and Conditions prescribed for disposal of plots by open offer.
….
….
15. Application of General Development Control Regulation for Navi Mumbai The development of land will be governed by the prevailing provision contained in the General Development Control Regulation of Navi Mumbai. Any modification to the said Regulation and in particular to the Floor Space Index and change of use of the land shall not be made lessee (sic). If he so desires, may 34 apply for the application of the modified regulation of the General Development Control Regulation to CIDCO. The Corporation may at its sole discretion, apply the modification of such regulation on payment of (1) Development charges (2) Additional premium and (3) other charges if any as may be decided by the Corporation from time to time. (…)
16. Transfer of assignment of rights The intending lease can transfer or assign his rights, interests of benefits which may accrue to him from the Agreement with the prior written permission of the Corporation and on payment of such transfer charges as may be prescribed by the Corporation from time to time. Such permission can however be granted only after the agreed lease premium and any other amount required has been paid in full and after execution of Agreement to lease. In case of transfer of plot, the Transferee should fulfill all eligibility conditions prescribed in condition 4 of the invitation of offer.”
Conditions provided in the Allotment letter:
19. Application of General Development Control Regulation for Navi Mumbai The development of land will be governed by the prevailing provisions contained in the General Development Control Regulation of Navi Mumbai. Any modification to the said regulation and in particular to the Floor Space index and charge of use of the land shall not be made automatically applicable but the intending lessee, if you so desire, may apply for the application of the modified regulation of the
35 General Development Control.
(emphasis supplied)
Clause 15 of the tender document and the corresponding
Condition 19 of the allotment letter, allows for such
modification. Although the language used in the aforesaid
clause is contradictory, this Court needs to interpret the
same to harmonize and eliminate any absurdity. 4 If the
interpretation supplied by CIDCO, by reading Clause 15 (m)
and (n) of allotment letter with Clause 15 of the tender
document in isolation, is accepted, then the phrase ‘If he so
desires, may apply for the application of the modified
regulation of the General Development Control Regulation to
CIDCO’, as occurring under Clause 15 of the tender
document, is rendered redundant. In this context, the
aforesaid clause needs to be interpreted to mean that,
‘lessee cannot apply for change of land use as a matter of
right, rather, CIDCO, on its discretion could grant such
‘change in land use’ on satisfaction based on material
considerations’.
4Ramana Dayaram Shetty v. International Airport Authority of India, AIR 1979 SC 1628.
36
48. The contradictory contractual clauses, seen within various
documents issued by CIDCO, have led to this seemingly
unending dispute, which required more than a decade to be
settled. This only emphasizes the importance of due
diligence and careful drafting, which could have avoided
such type of litigation in the first place.
49. In the same breath, the CIDCO has fairly conceded that the
power of change of land of use does exist with CIDCO and
has, on multiple occasions, been used to change the land
use pattern. Most importantly, in the present case, after
accepting the change of user fee, the authorities cannot
postfacto question the same.
50. In this case, the plots fell in the zone of commercialcum
residential area, and through the contract, this condition
was earmarked for construction of a fivestar hotel. As seen
from the records, the respondentslessees sought dilution of
this condition basing on the fact that the airport, which was
supposed to come up near the area had not materialized;
similarly situated hotels were lossmaking endeavors; and a
general economic slump. Further, the order of the CIDCO 37 dated 11.02.2010 clearly indicates the reasons as to the
change in land use in view of prevailing circumstances in
the following manner:
“The plot was aid (sic) in August 2008 for development of a Five Star Hotel along with the allied activities and it received a price of Rs.60085.10 per sq. mtr. The plot was initially with 1.5 FSI which was increasable to FSI 2.0 as per Government Policy. For the period prior and after the date of sale instances of sale of plots by tender for various usages are keep as C/351 to C/377. It is well know fact that the real estate markets in the later part of the year 2008 literally crashed and the downward trend of 25% to 30% was noticed across various real estate markets and segments. As a result of this, the Board had also decided to bring down the prices of NRI PhaseII PatII by 10% as well as rescheduling the installments. Also the DPC rates were brought down to 10%. The sale instances on the file show that the prices of residential and commercial lands during that period were comparable or some cases lower than the plot in question. But nonetheless the fact of depressed market cannot be ignored. In cases of some of the plots which are sold at higher rates, the Bidders did not pay the first installment and therefore their EMD’s were forfeited and in some cases on their request references have been made to the government for extension of time for payment.”
From the aforesaid reasoning, CIDCO has not been able to
show as to how the its own order was illegal or arbitrary.
38 Moreover, they have not been able to identify whether the
consideration taken by CIDCO at that time was deficient.
The prevailing circumstances and changes in the factual
conditions need to be appropriately considered. In our
considered opinion, it may be noted that delay in
construction of NaviMumbai airport, economic slump and
lossmaking endeavors by similarly situated hotels are
‘material considerations’ and the order has appropriately
taken the same into account.
51. The last submission on this aspect which the learned senior
counsel for the CIDCO, Shri Rakesh Dwivedi, takes is that
the relaxation of land use was made under the policy of
1997 which has been substituted by a new policy in 2004.
However, such submission is patently wrong, considering
the fact that the letter dated 11.02.2010 specifically alludes
to the expanded policy of 2004 whereby additional
categories of land use were added. It is mentioned in the
letter that the policy of the CIDCO was not to impose any
limit on the user of an area out of allotted area which can be
converted. In light of the aforesaid discussion, the change of
39 land use from fivestar hotel to partly residentialcum
commercial purpose cannot be said to be illegal or arbitrary.
52. The third aspect which needs to be considered is the
legality of subdivision of plots and subsequent transfer of
rights. It has been contended that the terms of the tender
and letter of allotment do not allow such transfer. However,
on perusal of the aforementioned Clause 16 of the General
Terms and Conditions and the corresponding Condition 21
of the allotment letter, it is clearly revealed that the allottee
was permitted to transfer or assign his rights, interests or
benefits with prior written permission of the Corporation
and on payment of such transfer charges as may be
prescribed by the Corporation. Both the clause and the
condition have further stipulated that such permission
could be granted only after the agreed lease premium has
been paid in full and after execution of agreement to lease.
In the present case, agreed lease premium was paid in full.
However, agreement to lease was made on the very next day,
i.e. on 30.03.2010. In our view, merely because the
agreement to lease was executed on the very next day, the
40 assignment and transfer would not be invalidated. Such
breach cannot in itself be termed as a fundamental to annul
the tender, especially after receiving the lease amount,
CIDCO cannot question the subsequent transfer. We can
only state that such clause can be construed as a warranty
alone rather than a condition, in light of the circumstances.
The CIDCO, being a public body, had a duty to act fairly.
Having acquiescence of the facts and allowing such transfer,
they ought not to have taken such a hypertechnical view on
contractual interpretation. In light of the aforesaid
reasoning, we do not find any substantial reason sought to
be adduced by the CIDCO to differ from the High Court.
53. Ultimately, we need to consider whether there was any
illegality or unfairness in the aforesaid transaction. Learned
senior counsel representing the appellants have submitted
that allowing subdivision of plots with change in land use,
had caused substantive loss to the State largesse, as many
people would have shown a proclivity to buy land with
different land use. On the contrary, the learned senior
counsel representing the Respondentslessees have stated
41 that the allotment, change in land use and transfer have
taken place in accordance with law. There is no substantial
deviation as sought to be projected by the appellants herein.
The appellants herein have sought to invoke the doctrine of
promissory estoppel to argue that the CIDCO could not have
walked out of the bargain, merely because of the possibility
of larger profits. It is pertinent to note that, the CIDCO has
failed to prove any losses suffered.
54. When a contract is being evaluated, the mere possibility of
more money in the public coffers, does not in itself serve
public interest. A blanket claim by the State claiming loss of
public money cannot be used to forgo contractual
obligations, especially when it is not based on any evidence
or examination. The larger public interest of upholding
contracts and the fairness of public authorities is also in
play. Courts need to have a broader understanding of public
interest, while reviewing such contracts.
42
55. In Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517,
it was held as under:
“22… The tenderer or contractor with a grievance can always seek damages in a civil court. Attempts by unsuccessful tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted. Such interferences, either interim or final, may hold up public works for years, or delay relief and succour to thousands and millions and may increase the project cost manifold.
(emphasis supplied)
56. Similarly, this Court in the case of Andhra Pradesh Dairy
Development Corporation Federation v. B. Narasimha
Reddy, (2011) 9 SCC 286 held as under:
“40. In the matter of the Government of a State, the succeeding Government is duty bound to continue and carry on the unfinished job of the previous Government, for the reason that the action is that of the “State”, within the meaning of Article 12 of the Constitution, which continues to subsist and therefore, it is not required that the new Government can plead contrary to the State action taken by the previous Government in
43 respect of a particular subject. The State, being a continuing body can be stopped from changing its stand in a given case, but where after holding enquiry it came to the conclusion that action was not in conformity with law, the doctrine of estoppel would not apply. Thus, unless the act done by the previous Government is found to be contrary to the statutory provisions, unreasonable or against policy, the State should not change its stand merely because the other political party has come into power. “Political agenda of an individual or a political party should not be subversive of rule of law.” The Government has to rise above the nexus of vested interest and nepotism, etc. as the principles of governance have to be tested on the touchstone of justice, equity and fair play.”
(emphasis supplied)
57. In the present case, it was argued by the respondents that
with the change in the executive head in CIDCO, enquiry
was initiated against the allotment made in favour of the
respondent M/s. Metropolis Hotel during the tenure of the
earlier executive head. Even the inquiry, that was conducted
against the respondentslessees stood vitiated as no proper
notice or hearing was given to them before passing the
impugned order. Additionally, from the above analysis it 44 clear that the change of usage and the subsequent division
was wellwithin the statutory limitations. Therefore, the
earlier undertakings taken by the appellantauthorities
cannot be set aside with the change of person in power,
without any rhyme or reason. After all one cannot change
the rules of the game once it has started.
58. From the contradictory submissions asserted before this
Court and the concessions given regarding practice of
CIDCO to allow change in land use in other cases, clearly
points to a ‘regime revenge’. Such conclusion reached herein
is further buttressed by the fact that no inquiry or
disciplinary proceedings were initiated against the earlier
ViceChairman, whose orders have been annulled. Such
phenomenon is clearly detrimental to the constitutional
values and rule of law.
59. As the last leg of the submission, the respondentslessees
have claimed that considering they have acted upon the
directions of the appellant authority and have duly paid the
requisite amounts to the tune of Rs. 321.32 crores, CIDCO
is bound by the doctrine of promissory estoppel. On the 45 contrary, principles of estoppel do not apply if enforcing the
promise would lead to the prejudice of public interest.
60. Before we delve into the aforesaid arguments, it is
imperative for us to go to have a look at certain decisions of
this Court. This Court in the case of Motilal Padampat
Sugar Mills Co. Ltd. v. State of Uttar Pradesh, (1979) 2
SCC 409 laid down the necessity of the government being
bound by the principles of promissory estoppel in the
following words:
“24. … The law may, therefore, now be taken to be settled as a result of this decision, that where the Government makes a promise knowing or intending that it would be acted on by the promisee and, in fact, the promisee, acting in reliance on it, alters his position, the Government would be held bound by the promise and the promise would be enforceable against the Government at the instance of the promisee, notwithstanding that there is no consideration for the promise and the promise is not recorded in the form of a formal contract as required by Article 299 of the Constitution. … It is indeed difficult to see on what principle can a Government, committed to the rule of law, claim immunity from the doctrine of promissory estoppel… It 46 was laid down by this Court that the Government cannot claim to be immune from the applicability of the rule of promissory estoppel and repudiate a promise made by it on the ground that such promise may fetter its future executive action. If the Government does not want its freedom of executive action to be hampered or restricted, the Government need not make a promise knowing or intending that it would be acted on by the promisee and the promisee would alter his position relying upon it. But if the Government makes such a promise and the promisee acts in reliance upon it and alters his position, there is no reason why the Government should not be compelled to make good such promise like any other private individual. The law cannot acquire legitimacy and gain social acceptance unless it accords with the moral values of the society and the constant endeavour of the Courts and the legislature, must, therefore, be to close the gap between law and morality and bring about as near an approximation between the two as possible. The doctrine of promissory estoppel is a significant judicial contribution in that direction. But it is necessary to point out that since the doctrine of promissory estoppel is an equitable doctrine, it must yield when the equity so requires. If it can be shown by the Government that having regard to the facts as they have transpired, it would be inequitable to hold the Government to the promise made by it, the Court would
47 not raise an equity in favour of the promisee and enforce the promise against the Government. The doctrine of promissory estoppel would be displaced in such a case because, on the facts, equity would not require that the Government should be held bound by the promise made by it. When the Government is able to show that in view of the facts as have transpired since the making of the promise, public interest would be prejudiced if the Government were required to carry out the promise, the Court would have to balance the public interest in the Government carrying out a promise made to a citizen which has induced the citizen to act upon it and alter his position and the public interest likely to suffer if the promise were required to be carried out by the Government and determine which way the equity lies. ….The burden would be upon the Government to show that the public interest in the Government acting otherwise than in accordance with the promise is so overwhelming that it would be inequitable to hold the Government bound by the promise and the Court would insist on a highly rigorous standard of proof in the discharge of this burden.” (emphasis supplied)
In the aforesaid case, this Court held that it would not be enough
for the Government to merely state that public interest requires
that the Government should not be compelled to carry out the
promise. It is imperative that the Government when seeking
48 exoneration from liability of enforcing contract, must satisfy the
Court as to how public interest overrides the necessity of
enforcing the contract. The aforesaid opinion has been reiterated
in the case Union of India v. Godfrey Philips India Ltd., (1985)
4 SCC 369 :
“12.There can therefore be no doubt that the doctrine of promissory estoppel is applicable against the Government in the exercise of its governmental, public or executive functions and the doctrine of executive necessity or freedom of future executive action cannot be invoked to defeat the applicability of the doctrine of promissory estoppel. …
13. Of course we must make it clear, and that is also laid down in Motilal Sugar Mills case[(1979) 2 SCC 409 : 1979 SCC (Tax) 144 : (1979) 2 SCR 641] that there can be no promissory estoppel against the Legislature in the exercise of its legislative functions nor can the Government or public authority be debarred by promissory estoppel from enforcing a statutory prohibition. It is equally true that promissory estoppel cannot be used to compel the Government or a public authority to carry out a representation or promise which is contrary to law or which was outside the authority or, power of the officer of the Government or of the public authority to make. We may also point out that the doctrine of promissory estoppel being an equitable doctrine, it must yield when the
49 equity so requires; if it can be shown by the Government or public authority that having regard to the facts as they have transpired, it would be inequitable to hold the Government or public authority to the promise or representation made by it, the Court would not raise an equity in favour of the person to whom the promise or representation is made and enforce the promise or representation against the Government or public authority. The doctrine of promissory estoppel would be displaced in such a case, because on the facts, equity would not require that the Government or public authority should be held bound by the promise or representation made by it.” (emphasis supplied)
61. Therefore, although the appellants are right in claiming that
Government cannot be compelled to perform its
undertaking, but equity demands that the Government must
place on record sufficient material on record to claim such
exemption. The aforesaid opinion was affirmed by this Court
in the case of Vasantkumar Radhakisan Vora (Dead) by
His LRs. v. Board of Trustees of the Port of Bombay,
(1991) 1 SCC 761. The court held therein:
“20. When it seeks to relieve itself from its application the government or the 50 public authority are bound to place before the court the material, the circumstances or grounds on which it seeks to resile from the promise made or obligation undertaken by insistence of enforcing the promise, how the public interest would be jeopardised as against the private interest. It is well settled legal proposition that the private interest would always yield place to the public interest.”
(emphasis supplied)
62. The learned senior counsel, Mr. Rakesh Dwivedi, has sought
to argue that promises made to the respondentslessees are
contradicted by the representation given to the general
public, that the land was being allotted for construction of a
5star Hotel. He has sought to create an exception of public
interest as a limit to promissory estoppel.
63. As we have noted earlier, there is no substantial violation
portrayed by the appellants herein with respect to allotment
of the scheduled land. Further, the tender documents, as
analyzed above, make it clear that the CIDCO had the power
to change the land use, subdivide and transfer the plots
and accordingly, has been carried out in terms of the same.
In this context, we may only observe that ‘good faith 51 standards’ applicable in Government contracts, serve an
important purpose in reinforcing the ‘reliance interest’ in
contracts.
64. Even, the High Court while passing the impugned judgment
has correctly held that respondentslessees have acted
pursuant to the permission granted by CIDCO. Moreover,
after getting the commencement certificate and other
necessary clearances, the respondentslessees borrowed a
substantial sum of money from other financial institutions
for the development of the plot. However, due to the ongoing
dispute, no development could take place for the past
decade.
65. It is admitted as per record that the respondent M/s.
Metropolis Hotel was the highest bidder. Moreover, the
appellants failed to bring anything on record to prove that
the state exchequer has suffered losses pursuant to the said
allotment. Nothing has been produced on record, the public
interest that will be prejudiced if the respondentslessees are
allowed to go ahead with the said project. On the contrary,
52 the respondentslessees acting in furtherance of the
assurances given by the authorities, obtained huge financial
assistance. Equity demands that when the State failed to
produce an iota of evidence of either financial loss or any
other public interest that has been affected, it should be
compelled to fulfill its promises. In fact, it is respondents
lessees who shall be gravely prejudiced if the order of
cancellation is upheld by this Court after investing a
significant amount and facing prolonged litigation.
66. Lastly, the PIL petitionerAppellant in C.A Nos. 39593961 of
2017 has tried to argue the case on the same lines as that of
the CIDCO. The public interest as sought to be shown in his
PIL, is doubtful, in light of his involvement in the business
of construction service. Moreover, the tone and tenor of the
notice dated 12.01.2009, issued by the PIL Petitioner to the
CIDCO, threatening the concerned officers with criminal
prosecution under Sections 405, 406, 420 read with Section
120(b) of IPC, inter alia, on the ground of allowing
partnership firm, which was in the process of registration, to
bid, needs to be viewed with some suspicion. In fact, the
53 nonprosecution of the erring officials for the alleged
mismanagement and irregularities is quite telling.
67. Before we state the conclusions, this Court would like to
reiterate certain wellestablished tenets of law pertaining to
Government contracts. When we speak of Government
contracts, constitutional factors are also in play.
Governmental bodies being public authorities are expected
to uphold fairness, equality and rule of law even while
dealing with contractual matters. It is a settled principle
that right to equality under Article 14 abhors arbitrariness.
Public authorities have to ensure that no bias, favouritism
or arbitrariness are shown during the bidding process. A
transparent bidding process is much favoured by this Court
to ensure that constitutional requirements are satisfied.
68. Fairness and the good faith standard ingrained in the
contracts entered into by public authorities mandates such
public authorities to conduct themselves in a nonarbitrary
manner during the performance of their contractual
obligations.
54
69. The constitutional guarantee against arbitrariness as
provided under Article 14, demands the State to act in a fair
and reasonable manner unless public interest demands
otherwise. However, the degree of compromise of any private
legitimate interest must correspond proportionately to the
public interest, so claimed.
70. At this juncture, it is pertinent to remember that, by merely
using grounds of public interest or loss to the treasury, the
successor public authority cannot undo the work
undertaken by the previous authority. Such a claim must be
proven using material facts, evidence and figures. If it were
otherwise, then there will remain no sanctity in the words
and undertaking of the Government. Businessmen will be
hesitant to enter Government contract or make any
investment in furtherance of the same. Such a practice is
counterproductive to the economy and the business
environment in general.
71. From a consideration of the aforesaid facts and
circumstances, it is clear that there is an element of abuse
of bureaucratic power behind subsequent change in the
55 tender allotment. After conducting a tender process and
receiving money, the Government backtracked which led to
this present prolonged litigation. The impugned order of
CIDCO, inter alia, annulling the allotment on hyper
technical grounds cannot be sustained for being contrary to
the doctrine of fairness. The reasons stated in the aforesaid
order are perverse and perse based on extraneous
considerations. As analyzed above, we are not able to
identify any substantive violation of law or tender
conditions, which mandate annulling the allotment and
subsequent arrangements, thereby proving the conduct of
the appellant authority to be disproportionate.
72. In light of the above discussion, we find no merit in the
appeal of the appellants herein. Accordingly, these civil
appeals are dismissed with costs.
56
73. Pending applications, if any, stand disposed of.
...........................................CJI.
(N.V. RAMANA)
..............................................J. (VINEET SARAN)
..............................................J. (SURYA KANT)
NEW DELHI;
NOVEMBER 29, 2021
57
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free