The State Of Jharkhand vs M/S Alternative For India Development
- Citation2023 SCC OnLine Jhar 1055
Ratio decidendi
The rule this decision rests on
Where an arbitrator construes the terms of a contract in a reasonable manner that fits within the scope of possible interpretations on the facts before him, a court exercising judicial review under Section 34 of the Arbitration and Conciliation Act, 1996 cannot set aside the award merely because it disagrees with that construction or would have preferred a different interpretation; reappreciation of evidence or substitution of the court's view for the arbitrator's is impermissible. The scope of judicial review under Section 34 of the Arbitration and Conciliation Act, 1996 is confined to whether the award violates the public policy of India (understood as the fundamental policy of Indian law, the interests of India, or conflict with basic notions of justice or morality), whether it exhibits patent illegality appearing on the face of the award, or whether it is perverse; interference is warranted only where the award's findings are arbitrary, capricious, perverse, or shock the conscience of the court, or where illegality goes to the root of the matter, not where it is merely trivial. Where a party is obligated under an agreement to take a specific action—such as issuing an operational certificate—and that party fails to do so due to its own fault or negligence, the other party cannot be denied contractual benefits that depend upon that action; the defaulting party cannot take advantage of its own wrong by relying on the condition it has failed to satisfy. Where 99% of the contractual obligations have been performed by a contractor out of the 100% required (594 Common Services Centres established out of 600), and the remaining 1% is attributable to circumstances beyond the contractor's control or to the fault of the other contracting party, the denial of revenue support payments tied to performance would not be justified by the arbitrator's award, as the contractor's substantial performance cannot be defeated by the other party's failure to issue the required certificate due to technical defects in systems introduced by that same party.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
against the judgment dated 25.06.2018 passed in
Commercial (REVOC) Case No. 05 of 2017 by the Presiding
Officer, Commercial Court, Ranchi, whereby and
whereunder the said case filed on behalf of the present 2
appellant under Section 34 of the Arbitration and
Conciliation Act, 1996 for setting aside the part of the
arbitral award dated 02.06.2017 and additional award
dated 07.07.2017 passed in Arbitration Case No. 01 of
2016 by learned Sole Arbitrator, whereby the claimant
awarded with revenue support for the total number of 594
Common Services Centres @ Rs. 3284/- per Common
Service Centres per month calculated from 26.11.2012 to
25.06.2016 totaling to Rs. 7,91,61,051/- plus interest upon
the same as per the prime lending rate of State Bank of
India for the applicable period to be calculated from
November, 2012 till actual payment to the claimant, as well
as the part of the impugned arbitral award dated
02.06.2017, whereby against the counter claim of
Rs.13,40,63,107/-only Rs.9,47,706/- with lump sum
amount of Rs. 2,00,000/- only awarded to the opposite
party (appellant) as well as against the order dated
11.08.2017 passed in the Arbitration Case No. 01 of 2016
by the learned Sole Arbitrator rejecting the application
under Section 33 (4) of the Arbitration and Conciliation Act,
1996 filed on behalf of the opposite party (present
appellant) has been dismissed by the learned Commercial
Court, Ranchi by the judgment dated 25.06.2018 passed in
Commercial (REVOC) Case No. 05 of 2017.
3
2. The brief facts of the case which are required to be
enumerated, reads hereunder as :-
The Government of Jharkhand intended to provide
convenient and speedy Government Services to the citizens,
using Information and Technologies Communication
through Common Services Centers (CSCs). The CSCs will
be utilized as efficient distribution channels through which
the Government of Jharkhand can offer its services,
information and schemes etc. to citizens in a cost effective,
sustainable and efficient manner. To undertake the delivery
of Government Services on a Public Private Partnership
basis, the Government of Jharkhand intends to appoint
Service Centre Agencies (SCAs) to roll out and manage the
CSCs in the State of Jharkhand and offer revenue support
to the SCAS, as mutually agreed and accepted by the State
Designated Agency (SDA) through the SCA's Financial Bid.
Therefore for the purpose of providing the said
services, such as issuance and preparation of Aadhar Card,
Voter ID, Caste Certificates, residential certificates etc., the
SCA was required to be engaged for the setting up such
CSCs, at least one CSC in a Panchayat, in the different
districts / division of the State. The Common Services
Centers are also known as Pragya Kendra.
Therefore, a tender for rolling out and operation of
around 4500 Common Service Centres in 5 divisions of the 4
State of Jharkhand was floated. Accordingly, M/s
Alternative For India Development, respondent herein,
submitted its technical and commercial bid for 600 CSCs in
Palamau Division in response to the tender and the said
bid was accepted by the SDA.
Thereafter, the Master Service Agreement (MSA) was
entered into on 11th April, 2007 for establishing 600 CSCs
in Palamau Division. It has been mentioned in the Request
for Proposal (RFP) that in each Panchayat of the Palamau
Division at least one CSC was to be established, roll out
and made operational. There were 600 Panchayats in the
entire Palamau Division. As such, at least / minimum 600
nos. of CSCs were essentially required to be rolled out and
operated by the SCA in the Palamau Division in accordance
with RFP, the bid documents and the Agreement.
Clause-2.3 of the MSA provided for roll out of CSCs,
the schedule for completion of Rollout with cumulative
percentage of minimum number of CSCS in each division to
be rolled out. As per the said clause of MSA, the 100% of
the CSCs i.e. 600 in numbers, were to be rolled out within
12 months. It has also been mentioned at Clause 2.3(a)
that the SCA shall set up and operationalize the CSCs at its
own cost and expense within 12 months from the Effective
Date.
5 Clause-3.1(f) clearly mentions that the SCA would
not be eligible for the revenue of GOJ, support unless the
CSCs have been rolled out within the specified timeframe
and are certified as operational by the SDA. Clause 3.1 (f)
also provides that only upon setting up CSCS and making
operational 50% of the said CSCs, the SCA shall be eligible
for 50% of the revenue support for the said operational
CSCs and the balance 50% shall be deferred till the roll out
of 100% CSCs.
As per the Master Service Agreement (MSA)
executed on 11th April, 2007, Alternative for India
Development, the respondent herein, was to roll out all the
600 CSCs within 12 months with effect from 11th April,
2007 but the respondent failed to meet the target.
Thereafter, vide Supplementary agreement dated
03.09.2012 wherein maximum period of completion of roll
out of CSCs by the SCA was extended to 66 months from
the effective date which was completed on 10th October,
2012. The respondent failed to complete 100% roll out, i.e.
roll out of 600 CSCs in Palamau division, till the date of
termination of agreement.
It is the case of the appellant that since M/s.
Alternative For India Development failed to set up and
made operational at least 50% of the CSCs during the
stipulated period, as such, was not eligible for any revenue 6
support since the Government of Jharkhand has incurred
heavy loss due to failure in roll out of required number of
CSCs in Palamau division.
The Revenue support for operational CSCs were
calculated and the non-roll out penalty, non-operational
penalty were imposed as per the provisions of MSA. The
JAP-IT had paid revenue support to the respondent for the
period September 2012 to March 2013. It was found that
Non Rollout and Non-operational penalty amount for period
of April, 2013 to December, 2013 was higher than the
payable revenue support amount, thus, no revenue support
amount found to be due for payment to the respondent.
It is the case of the appellant that non-performance
of the contractual obligation by the SCA was the reason for
the termination of the MSA vide order dated 27.06.2016.
However, said termination of MSA, forfeiture of bank
guarantee and blacklisting is not related to revenue
support.
The revenue support was main issue in the
arbitration proceedings. The prayer of the claimant (present
respondent) for additional award in relation to the forfeiture
of bank guarantee, termination of MSA by placing reliance
upon the order passed by the Hon'ble High Court of
Jharkhand in W.P. (C) No. 3103 of 2016 dated 22.06.2017
was having no relevancy in the matter in context. Therefore, 7
the prayer of the claimant for an additional award has been
rejected by the Sole Arbitrator on 11.08.2017.
It is the case of the appellant that L.P.A. No. 405 of
2017 filed on behalf of JAP-IT before this Court against the
order dated 22.06.2017 passed in W.P. (C) No. 3103 of
2016 has been disposed of on 19.03.2018.
The claimant (present respondent) moved the
Hon'ble High Court in Arbitration Application No. 01 of
2016 in which final order dated 15.07.2016 was passed
and the sole Arbitrator was appointed.
Thereafter the claimant filed statement of claim
along with documents before the Arbitrator. The appellants,
being the opposite parties, filed their statement of defense
dated 07.10.2016 alongwith all relevant documents also
giving point wise reply of the claim petition.
It is the further case of the appellants that since
considerable amount was to be realized from M/s
Alternative for India Development on account of non-roll
out, non-operational penalty and also towards liquidated
damages for not confirming and not performing in terms of
the MSA, therefore, a counter claim also made by JAP-IT
dated 07.10.2016 before the learned Sole Arbitrator
claiming an amount of Rs. 13,40,63,107/- including
liquidated damages of Rs. 1,16,16,000/-. 8
After hearing the parties, an Arbitral Award has
been passed on 02.06.2017 in Arbitration Case No. 01 of
2016 by the Sole Arbitrator holding the respondents (the
appellant herein) entitled for an amount of Rs.9,47,706/-
towards the claim made under the head of the 70% share of
the amount received by the Claimant from the citizens by
offering the government services plus a lump sum amount
of Rs. 2,00,000/- for the delay caused in disbursement of
the said amount of the share of the State Government.
Further, the respondent has been awarded with right to
impose non-roll out penalty for the total 6 number of CSCs
for the period from 26th November, 2012, the date when
Claimant had rolled out 594 CSCs to 26th June, 2016, the
date of termination of the MSA, which comes to
Rs.7,84,800/-.
Further, direction has been given that after the
deduction of the amounts awarded to the Respondents as
well as after deduction of the amount already paid to the
Claimant by way of Revenue Support, i.e. Rs. 60, 66,912 for
the period from October, 2012 till March, 2013, the
Claimant is awarded with Revenue Support for the total
number of 594 CSCs @ of Rs. 3284/- per CSC per month
calculated from 26th November, 2012 to 25th June, 2016,
i.e., Rs.7,58,80,510/- plus interest upon the same within a
period of two months.
9
Thereafter, an application was filed under Section
33 (1) (a) of the Arbitration and Conciliation Act, 1996 on
behalf of the claimant, in which the learned Arbitrator
passed a supplementary award dated 07.07.2017 by adding
an amount of Rs. 32,80,541/- observing that the awarded
amount be read as Rs.7,91,61,051/- and the amount
awarded has been modified to the said extent.
The claimant filed another application under
Section 33(4) of the Arbitration and Conciliation Act, 1996
to pass additional award for refund of Rs.47,28,960/-
towards the bank guarantee submitted by the claimant
which was forfeited which has been held to be not
maintainable and accordingly dismissed.
Being aggrieved and dissatisfied with the said part
of the arbitral award dated 02.06.2017 passed by the
learned Arbitrator an Arbitration Case No. 01 of 2016,
whereby the claimant awarded with revenue support for
total number of 594 Common Service Centres as well as
Supplementary Award dated 07.07.2017 as also against the
rejection of the part of the counter claim and against the
order dated 11.08.2017 passed in the said Arbitration Case
No. 01 of 2016 by the learned Sole Arbitrator, the appellant
filed an application under Section 34 of the Arbitration and
conciliation Act, 1996 being the Commercial (REVOC) Case 10
No. 05 of 2017 before the learned Commercial Court,
Ranchi.
The learned Commercial Court heard the
application learned Commercial Court, Ranchi has passed
the judgment on 25.06.2018 dismissing the said petition.
Being aggrieved with the judgment dated
25.06.2018 passed in Commercial (REVOC) Case No. 05 of
2017 by the learned Commercial Court, Ranchi, the instant
Commercial Appeal has been preferred.
3. Mr. Sachin Kumar, learned Additional Advocate
General appearing for the appellant State, has submitted
that the work in question, i.e., 600 Common Service
Centres was ought to be completed and had to be made
operative and to that effect a certificate was required to be
given by the authority concerned and it is only thereafter
the revenue support was to be given to the claimant, as
would appear from the condition stipulated under
Condition No.3.1(f) of the Master Service Agreement.
But, herein, the centre has not been completed in
entirety, rather only 594 centres have been installed and it
has not been made operative since no revenue has been
transmitted to the State Exchequer and, therefore, there
was no certificate of making the centres operational as was
required to be given in view of the condition stipulated for
the purpose of providing revenue support. 11
But the learned Arbitrator, without taking into
consideration the aforesaid aspect of the matter, has
passed the Award in favour of the respondent concerned
and hence the very issue of the condition as contained
under Condition No.3.1(f) has been given go-bye and,
therefore, it is against the public policy and the Award
suffers from perversity.
The further contention has been raised that the
learned Arbitrator has further erred in passing the Award
in the counter claim by holding the appellant State entitled
to meager amount of Rs.9,47,706/-
According to the learned counsel for the appellant,
the learned Arbitrator ought to have decided the counter
claim by passing an Award commanding upon the claimant
to compensate the State Exchequer by making payment of
the amount which ought to have been collected through the
people at large way of extending the benefit from the
centres. But, instead of doing so, the Award has been
passed in favour of the claimant directing the State
appellant to make payment of Rs.7,91,61,051/- and hence,
the very aspect of the matter of putting State Exchequer at
loss has not been appreciated.
The contention has been made that on these
grounds the Award has been challenged before the forum
available under Section 34 of the Arbitration and 12 Conciliation Act, 1996, but the learned court has also not
appreciated the aforesaid fact and merely on the basis of
the reason that the forum available under Section 34 is
having very little scope to exercise the power of judicial
review so far as the finding recorded by the Arbitral
Tribunal is concerned. But the issue which is being raised
as a ground, as referred hereinabove, ought to have been
considered by the forum exercising the power conferred
under Section 34 of the Act, 1996.
Learned counsel for the appellant, in support of his
argument, has relied upon the judgment rendered by
Hon'ble Apex Court in the case of Ssangyong Engineering
and Construction Company Limited v. National
Highways Authority of India (NHAI) reported in (2019)
15 SCC 131.
Learned counsel for the appellant, in the backdrop
of the aforesaid premise, coupled with the reliance put
upon the judgment rendered by the Hon'ble Apex Court in
the case of Ssangyong Engineering and Construction
Company Limited v. National Highways Authority of
India (NHAI) (Supra) has contended that the order
impugned dated judgment dated 25.06.2018 passed in
Commercial (REVOC) Case No. 05 of 2017 suffers from
patent illegality and, hence, not sustainable in the eyes of
law.
13
4. Per contra, Mr. Harendra Kr. Mahato, learned
counsel appearing for the claimant, the respondent herein,
has submitted that the learned Arbitrator has considered
each and every aspect of the matter, if the Award will be
looked into, more particularly paragraph 12 and 27 thereof.
According to the learned counsel for the claimant,
the respondent herein, the learned Arbitrator has
considered the condition stipulated at Condition No. 2.1(a)
i.e. (i) for completion of 600 centres; and Condition
No.3.2(a)(i) that a certificate is to be given of making the
centres operational.
The learned Arbitrator has considered the aforesaid
condition and considering the fact that 594 centres have
already been installed out of 600 which is near about 99%
and hence only because 1% of the centre has not been
installed the benefit of revenue support cannot be denied to
be given to the respondent.
The learned Arbitrator has further considered the
second condition of certificate to be given by the agency
making the centres operational but the said certificate was
to be given by the S.D.A., the agency concerned and hence,
giving the certificate with respect to making the centre
operational was the duty of the agency and if such
certificate was not given by the agency for which the
claimant cannot be made to suffer.
14
Learned Arbitrator has further considered the stand
of the claimant as referred at paragraph 12 of the Award
wherein it has been admitted by the State that in order to
make out the operational process more easier and
transparent OMT/E-Nagrick/E-Taal systems have been
adopted.
The State has taken the plea that aforesaid software
system since has been found to be faulty and hence the
certificate could not be given.
Learned counsel for the claimant, therefore, has
taken the ground that if the learned Tribunal has
considered the very condition as contained in Condition No.
2.1(a) i.e. (i) for completion of 600 centres; and Condition
No.3.2(a)(i) that a certificate is to be given of making the
centres operational. However, learned Tribunal has passed
the Award by taking into consideration the fact that 99% of
the centres has been installed and the Certificate of making
the centre operational since has not been given due to the
faulty software system, as per the admission made by the
agency, as would appear from the discussion made in
paragraph 12 of the Award and in that view of the matter if
the Award has been passed in favour of the claimant, the
same cannot be said to suffer from an error.
in that view of the matter, it cannot be said that the
Award is against the public policy.
15
The further contention has been made that the
scope of judicial review either under Section 34 or the
Arbitration and Conciliation Act, 1996 or under Section
13(1A) of the Commercial Courts Act is very limited and the
same can only be exercised if the Award is found to be
contrary to the public policy and the Award suffers from
perversity. But, none of the condition is available herein
and by taking into consideration the aforesaid fact the
learned court while exercising the power under Section 34
of the Act, 1996 if has declined to interfere with the arbitral
Award, the same cannot be said to suffer from an error.
Learned counsel appearing for the respondent has
relied upon the judgment Associate Builders v. Delhi
Development Authority reported in (2015) 3 SCC 49, Oil
& Natural Gas Corporation Ltd. V. Saw Pipes Ltd.
reported in (2003) 5 SCC 705 and Navodaya Mass
Entertainment Limited v. J.M. Combines reported in
(2015) 5 SCC 698.
5. We have heard learned counsel for the parties,
perused the documents available on record as also the
finding recorded by the learned Arbitrator and the learned
court while exercising the power under Section 34 of the
Act, 1996.
6. This Court, before appreciating the argument
advanced on behalf of the parties, deems it fit and proper to 16
refer the position of law regarding the power of judicial
review in the arbitral Award.
In the case of Associate Builders v. Delhi
Development Authority reported in (2015) 3 SCC 49, the
Hon'ble Apex Court while dealing with the scope of judicial
review in the matter of an arbitral Award has taken into
consideration the judgment passed in McDermott
International Inc. v. Burn Standard Co. Ltd., (2006) 11
SCC 181 and has held at para 22 which is required to be
referred herein which reads hereunder as :-
22. In McDermott International Inc. v. Burn Standard Co.
Ltd. [(2006) 11 SCC 181] , this Court held:
"58. In Renusagar Power Co. Ltd. v. General Electric Co. [1994 Supp (1) SCC 644] this Court laid down that the arbitral award can be set aside if it is contrary to (a) fundamental policy of Indian law; (b) the interests of India; or (c) justice or morality. A narrower meaning to the expression 'public policy' was given therein by confining judicial review of the arbitral award only on the aforementioned three grounds. An apparent shift can, however, be noticed from the decision of this Court in ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705] (for short 'ONGC'). This Court therein referred to an earlier decision of this Court in Central Inland Water Transport Corpn. Ltd. v. Brojo Nath Ganguly [(1986) 3 SCC 156] wherein the applicability of the expression 'public policy' on the touchstone of Section 23 of the Contract Act, 1872 and Article 14 of the Constitution of India came to be considered. This Court therein was dealing with unequal bargaining power of the workmen and the employer and came to the conclusion that any term of the agreement which is 17
patently arbitrary and/or otherwise arrived at because of the unequal bargaining power would not only be ultra vires Article 14 of the Constitution of India but also hit by Section 23 of the Contract Act, 1872. In ONGC [(2003) 5 SCC 705] this Court, apart from the three grounds stated in Renusagar [Renusagar Power Co. Ltd. v. General Electric Co., 1994 Supp (1) SCC 644] , added another ground thereto for exercise of the court's jurisdiction in setting aside the award if it is patently arbitrary.
59. Such patent illegality, however, must go to the root of the matter. The public policy violation, indisputably, should be so unfair and unreasonable as to shock the conscience of the court. Where the arbitrator, however, has gone contrary to or beyond the expressed law of the contract or granted relief in the matter not in dispute would come within the purview of Section 34 of the Act. However, we would consider the applicability of the aforementioned principles while noticing the merits of the matter.
60. What would constitute public policy is a matter dependent upon the nature of transaction and nature of statute. For the said purpose, the pleadings of the parties and the materials brought on record would be relevant to enable the court to judge what is in public good or public interest, and what would otherwise be injurious to the public good at the relevant point, as contradistinguished from the policy of a particular Government.
Further, the Hon'ble Apex Court in the case of PSA
SICAL Terminals Pvt. Ltd. Vs Board of Trustees of V.O.
Chidambranar Port Trust Tuticorin and Others
reported in 2021 SCC OnLine SC 508, has taken the
similar view which has been observed at paragraph 43 of
the judgment which is being referred hereunder as:-
18 43. It will thus appear to be a more than settled legal position, that in an application under Section 34, the court is not expected to act as an appellate court and reappreciate the evidence. The scope of interference would be limited to grounds provided under Section 34 of the Arbitration Act. The interference would be so warranted when the award is in violation of "public policy of India", which has been held to mean "the fundamental policy of Indian law". A judicial intervention on account of interfering on the merits of the award would not be permissible. However, the principles of natural justice as contained in Section 18 and 34(2)(a)(iii) of the Arbitration Act would continue to be the grounds of challenge of an award. The ground for interference on the basis that the award is in conflict with justice or morality is now to be understood as a conflict with the "most basic notions of morality or justice". It is only such arbitral awards that shock the conscience of the court, that can be set aside on the said ground. An award would be set aside on the ground of patent illegality appearing on the face of the award and as such, which goes to the roots of the matter. However, an illegality with regard to a mere erroneous application of law would not be a ground for interference. Equally, reappreciation of evidence would not be permissible on the ground of patent illegality appearing on the face of the award.
In a recent judgment passed in Reliance
Infrastructure Ltd. Vs State of Goa reported in 2023
SCC OnLine SC 604, the Hon'ble Apex Court has 19
reiterated its view and has observed at paragraph 48 which
reads hereunder as :-
"48. In MMTC Limited (supra), this Court took note of various decisions including that in the case of Associate Builders (supra) and exposited on the limited scope of interference under Section 34 and further narrower scope of appeal under Section 37 of the Act of 1996, particularly when dealing with the concurrent findings (of the Arbitrator and then of the Court). This Court, inter alia, held as under:--
"11. As far as Section 34 is concerned, the position is well-settled by now that the Court does not sit in appeal over the arbitral award and may interfere on merits on the limited ground provided under Section 34(2)(b)(ii) i.e. if the award is against the public policy of India. As per the legal position clarified through decisions of this Court prior to the amendments to the 1996 Act in 2015, a violation of Indian public policy, in turn, includes a violation of the fundamental policy of Indian law, a violation of the interest of India, conflict with justice or morality, and the existence of patent illegality in the arbitral award. Additionally, the concept of the "fundamental policy of Indian law" would cover compliance with statutes and judicial precedents, adopting a judicial approach, compliance with the principles of natural justice, and Wednesbury [Associated Provincial Picture Houses v. Wednesbury Corpn., [1948] 1 K.B. 223 (CA)] reasonableness. Furthermore, "patent illegality" itself has been held to mean contravention of the substantive law of India, 20
contravention of the 1996 Act, and contravention of the terms of the contract.
12. It is only if one of these conditions is met that the Court may interfere with an arbitral award in terms of Section 34(2)(b)(ii), but such interference does not entail a review of the merits of the dispute, and is limited to situations where the findings of the arbitrator are arbitrary, capricious or perverse, or when the conscience of the Court is shocked, or when the illegality is not trivial but goes to the root of the matter. An arbitral award may not be interfered with if the view taken by the arbitrator is a possible view based on facts.
13. It is relevant to note that after the 2015 Amendment to Section 34, the above position stands somewhat modified. Pursuant to the insertion of Explanation 1 to Section 34(2), the scope of contravention of Indian public policy has been modified to the extent that it now means fraud or corruption in the making of the award, violation of Section 75 or Section 81 of the Act, contravention of the fundamental policy of Indian law, and conflict with the most basic notions of justice or morality. Additionally, sub-section (2-A) has been inserted in Section 34, which provides that in case of domestic arbitrations, violation of Indian public policy also includes patent illegality appearing on the face of the award. The proviso to the same states that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.
14. As far as interference with an order made under Section 34, as per Section 37, is concerned, it cannot be disputed that such 21
interference under Section 37 cannot travel beyond the restrictions laid down under Section 34. In other words, the court cannot undertake an independent assessment of the merits of the award, and must only ascertain that the exercise of power by the court under Section 34 has not exceeded the scope of the provision. Thus, it is evident that in case an arbitral award has been confirmed by the court under Section 34 and by the court in an appeal under Section 37, this Court must be extremely cautious and slow to disturb such concurrent findings."
It is evident from the judicial pronouncements
referred hereinabove, that the appellate court while
exercising the power regarding the illegality and propriety of
the arbitral Award is not supposed to reappraise the
evidence as also interference to the arbitral Award does not
intend a review of the merits of the dispute, rather, it is
limited to the situations whether the findings of the
Arbitrator are arbitrary or capricious or perverse or when
the conscience of the court shocks or when the illegality is
not trivial but goes to the root of the matter.
Further, an arbitral Award may not be interfered
with if the view taken by the Arbitrator is a possible view
based on facts.
7. So far as the fact of the given case is concerned, the
Government of Jharkhand, for convenient and speedy
Government Services to the citizens, through Common 22
Services Centers (CSCs) such as issuance and preparation
of Aadhar Card, Voter ID, Caste Certificates, residential
certificates etc., decided that at least one CSC in a
Panchayat, in the different districts / division of the State
should be established and, therefore, a tender for rolling
out and operation of around 4500 Common Service Centres
in 5 divisions of the State of Jharkhand was floated.
Accordingly, M/s Alternative For India Development,
respondent herein, submitted its technical and commercial
bid for 600 CSCs in Palamau Division in response to the
tender and the said bid was accepted by the SDA.
Thereafter, Agreement was entered into on 11th
April, 2007 for establishing 600 CSCs in Palamau Division.
There were 600 Panchayats in the entire Palamau Division.
As such, at least / minimum 600 nos. of CSCs were
essentially required to be rolled out and operated by the
SCA in the Palamau Division.
Clause-3.1(f) of the contract stipulates that the SCA
would not be eligible for the revenue support of
Government of Jharkhand, unless the CSCs have been
rolled out within the specified timeframe and are certified
as operational by the SDA. Clause 3.1 (f) also provides that
only upon setting up CSCs and making operational 50% of
the said CSCs, the SCA shall be eligible for 50% of the
revenue support for the said operational CSCs and the 23
balance 50% shall be deferred till the roll out of 100%
CSCs.
As per the Agreement, Alternative for India
Development, the respondent herein, was to roll out all the
600 CSCs within 12 months with effect from 11th April,
2007 but the respondent failed to meet the target.
Thereafter, vide Supplementary agreement dated
03.09.2012 wherein maximum period of completion of roll
out of CSCs by the SCA was extended to 66 months from
the effective date which was completed on 10th October,
2012. The respondent failed to complete 100% roll out, i.e.
roll out of 600 CSCs in Palamau division, till the date of
termination of agreement.
It is the case of the appellant that since M/s.
Alternative For India Development failed to set up and
made operational at least 50% of the CSCs during the
stipulated period, as such, was not eligible for any revenue
support since the Government of Jharkhand has incurred
heavy loss due to failure in roll out of required number of
CSCs in Palamau division.
The Revenue support for operational CSCs was
calculated and the non-roll out penalty, non-operational
penalty were imposed as per the provisions of the
Agreement. The JAP-IT had paid revenue support to the
respondent for the period September 2012 to March 2013. 24
It was found that Non Rollout and Non-operational penalty
amount for period of April, 2013 to December, 2013 was
higher than the payable revenue support amount, thus, no
revenue support amount found to be due for payment to
the respondent.
The revenue support was main issue in the
arbitration proceedings wherein prayer was made by the
claimant for additional award has been rejected by the Sole
Arbitrator on 11.08.2017.
The claimant (respondent herein) moved before this
Court in Arbitration Application No. 01 of 2016 in which
final order dated 15.07.2016 was passed and the sole
Arbitrator was appointed.
Thereafter the claimant filed statement of claim
along with documents before the Arbitrator. The appellants,
being the opposite parties, filed their statement of defense
dated 07.10.2016 alongwith all relevant documents.
After hearing the parties, the Arbitral Award has
been passed on 02.06.2017 in Arbitration Case No. 01 of
2016 by the Sole Arbitrator holding the respondents (the
appellant herein) entitled for an amount of Rs.9,47,706/-
towards the claim made under the head of the 70% share of
the amount received by the Claimant from the citizens by
offering the government services plus a lump sum amount
of Rs. 2,00,000/- for the delay caused in disbursement of 25
the said amount of the share of the State Government.
Further, the respondent has been awarded with right to
impose non-roll out penalty for the total 6 number of CSCs
for the period from 26th November, 2012, the date when
Claimant had rolled out 594 CSCs to 26th June, 2016, the
date of termination of the MSA, which comes to
Rs.7,84,800/-.
Further, direction has been given that after the
deduction of the amounts awarded to the Respondents as
well as after deduction of the amount already paid to the
Claimant by way of Revenue Support, i.e. Rs. 60, 66,912 for
the period from October, 2012 till March, 2013, the
Claimant is awarded with Revenue Support for the total
number of 594 CSCS @ of Rs. 3284/- per CSC per month
calculated from 26th November, 2012 to 25th June, 2016,
i.e., Rs.7,58,80,510/- plus interest upon the same within a
period of two months.
Thereafter, an application was filed under Section
33 (1) (a) of the Arbitration and Conciliation Act, 1996 on
behalf of the claimant, in which the learned Arbitrator
passed a supplementary award dated 07.07.2017 by adding
an amount of Rs. 32,80,541/- observing that the awarded
amount be read as Rs.7,91,61,051/- and the amount
awarded has been modified to the said extent. 26
The claimant filed another application under
Section 33(4) of the Arbitration and Conciliation Act, 1996
to pass additional award for refund of Rs.47,28,960/-
towards the bank guarantee submitted by the claimant
which was forfeited which has been held to be not
maintainable and accordingly dismissed.
Being aggrieved and dissatisfied with the said part
of the arbitral award dated 02.06.2017 passed by the
learned Arbitrator an Arbitration Case No. 01 of 2016,
whereby the claimant awarded with revenue support for
total number of 594 Common Service Centres as well as
Supplementary Award dated 07.07.2017 as also against the
rejection of the part of the counter claim and against the
order dated 11.08.2017 passed in the said Arbitration Case
No. 01 of 2016 by the learned Sole Arbitrator, the appellant
filed an application under Section 34 of the Arbitration and
conciliation Act, 1996 being the Commercial (REVOC) Case
No. 05 of 2017 before the learned Commercial Court,
Ranchi.
The learned Commercial Court heard the
application and passed the judgment on 25.06.2018
dismissing the said petition.
Being aggrieved with the judgment dated
25.06.2018 passed in Commercial (REVOC) Case No. 05 of 27
2017 by the learned Commercial Court, Ranchi, the instant
Commercial Appeal has been preferred.
It is evident from the record that the agreement has
been entered which contains several conditions. One of the
conditions is for the purpose of giving revenue support to
the claimant.
8. Learned counsel appearing for the appellant since is
questioning the arbitral Award as also the order passed by
the learned court in exercise of power conferred under
Section 34 of the Act, 1996 that the Award so passed by
casting liability upon the State appellant due to the
negligence in not giving the revenue support even after
completion of the entire centres and the centres have not
become operational.
Therefore, this Court, instead of dealing with other
conditions, is now confining to deal with the condition
which pertains to extending the benefit of revenue support
in favour of the claimant which is available at Condition
No.2.1 of the Agreement which is being referred hereunder
as :-
"2.1 Scope of the MSA
a) The SCA mandated to establish around 600 number of CSCs in Palamu Division of the State of Jharkhand. The GoJ will provide a variety of Government Services through the CSCs. These centres are proposed to be set up in the panchayat bhawans or suitable spaces available or at alternate 28
locations preferably near the same. The SCA shall be responsible for identifying such locations with the guidance of the SDA.
b) The GoJ will extend revenue support to the SCA as agreed mutually under this MSA.
c) The details of the Palamu division and the revenue support sought is as follows :
Sl. Name of Approx Revenue Support Required No. Division No. of from JAP-IT in Indian CSCs Rupees per CSC per proposed month over the 4 year period
1 Palamu 600 3284
It is evident that for the purpose of giving revenue
support, two conditions have been stipulated in the
condition as referred hereinabove. The first is that the
centre, 600 in number, is to be set up and the second
condition is that the centre is to be made operational and to
that effect a certificate is to be given by the S.D.A., the
agency concerned, the State functionary herein.
The claim of the claimant is that out of 600 centres,
594 centres have been set up, however, it was not within
the period as agreed in pursuance to the agreement dated
11th April, 2007 but subsequent thereto, a supplementary
agreement has been enreached in between the parties
whereby extension of 66 months have been granted under
which out of 600 centres, 594 centres have been set up.
But no revenue support has been given and a dispute arose
which was finally referred to the Arbitrator by appointing 29
Arbitrator by the High Court in exercise of power conferred
under Section 11(6) of the Arbitration and Conciliation Act,
1996.
The claimant has taken the plea that there is no
laches on his part and out of 600 centres, 594 centres have
been set up and the operation certificate which was to be
given by the S.D.A. has not been given and, therefore, the
revenue support, which, as per the agreement the claimant
was entitled, since has not been given, the claimant has
been made to suffer and hence the Award is prayed to be
passed in his favour.
9. While on the other hand, the State appellant has
also filed counter claim on the pretext of the fact that the
revenue which was to be generated by virtue of setting up
of the agency has not been transmitted to the State
Exchequer due to the laches committed on the part of the
claimant and, hence they are entitled for the damages.
10. The learned Tribunal has considered various aspect
of the matter. The documents have been adduced. The
learned Tribunal, in order to adjudicate the issue, has
formulated following issues :-
(i) Whether the Claimant is entitled to the claim raised by it in the petition of Claim and whether the same is payable in law or on facts in terms of the Master Service Agreement and the Supplementary Agreement?
(ii) Whether the Supplementary Agreement dated 03.09.2012 has merged with the main Master Service 30
Agreement dated 11.04.2007 and whether the parties are bound by the terms of the Master Service Agreement as well as the Supplementary Agreement dated 03.09.2012?
(iii) Whether the Respondents have relinquished or waived the provisions of the Master Service Agreement in relation to the payment of the revenue support amount by the Respondent to the Claimant?
(iv) Whether the Respondents are barred by Principle of estoppels from relying on the provisions of Master Service Agreement relating to the payment of the revenue support amount by the Respondent to the Claimant?
(v) Whether the Claimant has performed its part of the contract and / or whether it has breached / violated any of the terms of the contract entered into between the parties particularly Clause 4.2(b) of the Contract as alleged by the Respondent?
(vi) Whether an amount of Rs.8,52,07,100/- is payable by the Respondents to the Claimant towards the revenue support as claimed by it?
(vii) Whether an amount of Rs. 2,79,62,132/- is payable by the Respondents to the Claimant as Escalation Cost as claimed by the Claimant?
(viii) Whether the Claimant is entitled to interest @ 15% on delayed payment i.e. Rs. 3,97,92,689/- till the date of filing of the Claim Petition as claimed by it?
(ix) Whether an amount of Rs.13,40,63,107/- is payable by the Claimant to the Respondent by way of Counter Claim on account of revenue collected from the citizens for government services, non-rollout penalty amount, non-operational penalty amount, offsetting amount, liquidated damages as claimed by the Respondent in terms of the Master Service Agreement read with Supplementary Agreement dated 03.09.2012 and whether the amount aforesaid is at all admissible to be paid by the Claimant to the Respondent and whether the Claimant was required to 31
roll out 600 Common Service Centers in accordance with the provisions of Master Service Agreement dated 11.04.2007 read with Supplementary Agreement dated 03.09.2012?
The State appellant is only concerned with issue
No.(ix) which pertains to revenue support in the light of
non-compliance of the condition stipulated under Condition
No.2.1(a) of the Master Service Agreement.
The learned Tribunal has considered the aforesaid
condition and by taking note of the fact that out of 600
centres, 594 centres have been installed which is almost
99% of the work in entirety and hence came to the
conclusion that if 1% of the centres has not been set up,
the claimant cannot be denied the benefit of revenue
support.
The learned Arbitrator has considered the second
condition regarding certificate to be given of making the
centres operational, that is the ground taken by the State
appellant that in absence of certificate of making the
centres operational, there cannot be revenue support to be
given to be claimant.
The learned Arbitrator has considered the stand of
the State appellant in order to assess that by whom the
operational certificate was to be given, whether it was to be
given by the State or if the State has not given, whether the
claimant can be held responsible for that so as to put him 32
at financial loss by not giving the benefit of revenue
support.
The learned Arbitrator has further considered the
stand of the appellant wherein it has been admitted that
the operational certificate could not be given due to change
in the system, as would appear from the discussion so
made at paragraph 12 of the Award passed by the learned
Arbitrator, for ready reference, paragraph 12 is quoted
hereunder as :-
"12. Further, the Learned Senior Counsel for the Claimant, arguing upon the penal provisions under the MSA emphasized on the point that, as a consequence of the execution of the Supplementary Agreement, the entire Clause 2.3(b) stood deleted and thereby no penal provisions remained enforceable under the MSA. Therefore, non-operational penalty and or non-roll out penalty cannot be levied as there is no provision in the MSA regarding penalty for the same and therefore the schedule to the MSA which speaks about penalty is of no avail. Further he contended that, the Respondent has calculated the non-operational penalty on the basis of reports of E- Nagrik software which in itself was faulty and not provided for in the MSA. Accordingly the Claimant is not liable to pay any amount towards penalty for non- roll out or non operationality of any CSCs. Therefore, Respondent cannot rely on the penalty clause which stood deleted after the execution of the Supplementary Agreement; therefore the Respondent cannot bank upon something which does not exist in the MSA. Further by citing Clause 3.2(a)(i) of the MSA, the Claimant stated that, it had to submit certificate from JAP-IT or designated agency certifying that all the 33
CSCs have been rolled out and are operational but the Respondent never issued a single certificate in respect of the same rather they alternatively introduced Online Monitoring Tool for certifying CSCs. He further submitted that, the fact that the OMT/E- Nagrick/E- Taal systems introduced by the Respondent at subsequent stages of Agreement period were non- functioning and not reliable, was also recorded in the internal CSC review meeting held on 14.05.2017 in the chamber of the Principal Secretary, Department of IT."
The learned Arbitrator, after taking into
consideration the admission on the part of the State, that
due to the glitch in the software, the operational certificate
could not be given, has given specific finding at paragraph
27 of the Award wherein it has been held that if it is the
admission on the part of the State appellant that the
operational certificate could not be given due to
introduction of the new software which has been found to
be faulty, therefore, for the fault on the part of the State,
the claimant cannot be allowed to suffer, for ready
reference paragraph 27 of the Award is being quoted and
referred hereunder as :-
"27. Further, under Clause 2(a) which provides for the scope of the MSA states that, the SCA is mandated to establish 600 numbers of CSCs in the Palamu Division of State of Jharkhand. Further the Clause 2(c) goes on to provide the details of the Palamu Division and the revenue support sought for the same. The 3rd row of the table provided in the said clause which deals with the number of CSCs reads as - "approx no of CSC's proposed". Therefore, after analysing the MSA in its 34
entirety, I am of the view that, under various clauses in the said MSA the roll-out and operations of the CSCs are indicated in percentile calculation and the same is not practically possible without the figures being certain or exact. I am therefore certain that, it is evidently clear from the wordings and interpretation of the terms of the MSA in total that, the SCA was required to roll-out a total of 600 CSCs, since all the calculations made under the MSA, may it be for revenue support or for imposition of penalty was provided in percentage manner and the same percentile figure cannot be obtained unless and until the figure out of which it has to be derived is certain or exact."
The learned Arbitrator on the basis of the aforesaid
fact, has passed the Award holding therein that the
appellant itself is at fault in not giving operation certificate
who is only to give certificate as per the stipulation made
under Condition No.3.2(a)(i) and, therefore, for the fault
committed by the Agency, the claimant cannot be allowed
to suffer and, accordingly, passed the Award in favour the
claimant.
11. The argument of the learned counsel for the
appellant that the Award is contrary to the public policy
and suffers from perversity, which according to our
considered view, cannot be said to have substance, reason
being that if the condition has been enshrined in the
agreement, it is incumbent upon the parties to comply it in
strict sense. Either of the parties, if do not comply with the 35
condition and due to such non-compliance no relief can be
sought for by such party who is at fault.
Herein, the condition stipulated at Condition No.
2.1(a) i.e., for completion of 600 centres; and Condition
No.3.2(a)(i) that a certificate is to be given of making the
centres operational.
12. So far as the completion of 600 centres are
concerned, out of 600 centres, 594 centres have already
been installed, i.e., 99% of the work and hence denial of the
revenue support only if 1% centres have not been set up,
the same has been held to be not justified by the learned
Arbitrator as also the learned court while refusing to
interfere with the Award in exercise of power conferred
under Section 34 of the Act, 1996, which according to our
considered view, cannot be said to suffer from an error, it is
for the reason that there cannot be any deviation from the
agreement and if condition has been stipulated, the same
has to be adhered to.
The plea is being taken on behalf of the State
appellant that the operational certificate is not available
and hence the learned Arbitrator or the forum under
Section 34 of the Act, 1996 ought to have taken into
consideration the aforesaid fact.
13. There is no denial that it ought to have been
considered but the fact herein is that the operational 36
certificate if was required to be given by the State and when
the State is admitting the fact that due to the technical
glitch in the new software introduced for giving operation
certificate which establishes that the laches is on the part
of the State and the law is well settled that if the laches is
on the part of the party, such party cannot be allowed to
take advantage of its wrong/illegality as has been held by
Hon'ble Apex Court in the case of Kusheshwar Prasad
Singh vs. State of Bihar and Ors., (2007) 11 SCC 447,
wherein at paragraphs-14, 15 and 16, the Hon'ble Apex
Court has observed as under:
"14. In this connection, our attention has been invited by the learned counsel for the appellant to a decision of this Court in Mrutunjay Pani v. Narmada Bala Sasmal [AIR 1961 SC 1353] wherein it was held by this Court that where an obligation is cast on a party and he commits a breach of such obligation, he cannot be permitted to take advantage of such situation. This is based on the Latin maxim commodum ex injuria sua nemo habere debet (no party can take undue advantage of his own wrong).
15. ... This Court (at SCC p. 142, para 28) referred to Broom's Legal Maxims (10th Edn.), p. 191 wherein it was stated:
"It is a maxim of law, recognised and established, that no man shall take advantage of his own wrong; and this maxim, which is based on elementary principles, is fully recognised in courts of law and of equity, and, indeed, admits of illustration from every branch of legal procedure."
16. It is settled principle of law that a man cannot be permitted to take undue and unfair advantage of his own wrong to gain favourable interpretation of law. It is sound principle that he who prevents a thing from being done shall not avail himself of the non-performance he has 37
occasioned. To put it differently, "a wrongdoer ought not to be permitted to make a profit out of his own wrong"."
So far as the question of public policy is concerned,
there is not dispute that the interference would be
warranted if the Award is in violation of the public policy of
India. The Hon'ble Apex Court in the case of Oil & Natural
Gas Corporation Ltd. v. Saw Pipes Ltd. (Supra), has
been pleased to observe as under paragraph 31 that the
expression public policy of India, as contained in Section
34, would now be the fundamental policy of Indian Law, as
explained in para 18 and 27 of Associate Builders v.
Delhi Development Authority reported in (2015) 3 SCC
49, i.e., the fundamental policy of Indian Law would be
related to Renusagar [Renusagar Power Co. Ltd. v. general
Electric Co. (1994) Supp (1) SCC 644] understanding of this
expression. Paragraph 31 of the judgment rendered in
public policy of India. The Hon'ble Apex Court in the case of
Oil & Natural Gas Corporation Ltd. v. Saw Pipes
Ltd.(Supra) is quoted hereunder as :-
"31. Therefore, in our view, the phrase "public policy of India" used in Section 34 in context is required to be given a wider meaning. It can be stated that the concept of public policy connotes some matter which concerns public good and the public interest. What is for public good or in public interest or what would be injurious or harmful to the public good or public interest has varied from time to time. However, the award which is, on the face of it, patently in violation of statutory provisions cannot be said to be in public 38
interest. Such award/judgment/decision is likely to adversely affect the administration of justice. Hence, in our view in addition to narrower meaning given to the term "public policy" in Renusagar case [1994 Supp (1) SCC 644] it is required to be held that the award could be set aside if it is patently illegal. The result would be
-- award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of trivial nature it cannot be held that award is against the public policy. Award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court. Such award is opposed to public policy and is required to be adjudged void."
It has further been observed that the public policy
of India is now constricted to be first; Award is contrary to
the fundamental policy of Indian Law as understood in
paragraph 28 of the Associate Builders v. Delhi
Development Authority (Supra), which reads hereunder
as:-
28. In a recent judgment, ONGC Ltd. v. Western Geco International Ltd. [(2014) 9 SCC 263 : (2014) 5 SCC (Civ) 12] , this Court added three other distinct and fundamental juristic principles which must be understood as a part and parcel of the fundamental policy of Indian law. The Court held: (SCC pp. 278-80, paras 35 & 38-40) "35. What then would constitute the 'fundamental policy of Indian law' is the question.
The decision in ONGC [(2003) 5 SCC 705 : AIR 2003 39
SC 2629] does not elaborate that aspect. Even so, the expression must, in our opinion, include all such fundamental principles as providing a basis for administration of justice and enforcement of law in this country. Without meaning to exhaustively enumerate the purport of the expression 'fundamental policy of Indian law', we may refer to three distinct and fundamental juristic principles that must necessarily be understood as a part and parcel of the fundamental policy of Indian law. The first and foremost is the principle that in every determination whether by a court or other authority that affects the rights of a citizen or leads to any civil consequences, the court or authority concerned is bound to adopt what is in legal parlance called a 'judicial approach' in the matter. The duty to adopt a judicial approach arises from the very nature of the power exercised by the court or the authority does not have to be separately or additionally enjoined upon the fora concerned. What must be remembered is that the importance of a judicial approach in judicial and quasi-judicial determination lies in the fact that so long as the court, tribunal or the authority exercising powers that affect the rights or obligations of the parties before them shows fidelity to judicial approach, they cannot act in an arbitrary, capricious or whimsical manner. Judicial approach ensures that the authority acts bona fide and deals with the subject in a fair, reasonable and objective manner and that its decision is not actuated by any extraneous consideration. Judicial approach in that sense acts as a check against flaws and faults that can render the decision of a court, tribunal or authority vulnerable to challenge.
***
38. Equally important and indeed fundamental to the policy of Indian law is the principle that a 40
court and so also a quasi-judicial authority must, while determining the rights and obligations of parties before it, do so in accordance with the principles of natural justice. Besides the celebrated audi alteram partem rule one of the facets of the principles of natural justice is that the court/authority deciding the matter must apply its mind to the attendant facts and circumstances while taking a view one way or the other. Non- application of mind is a defect that is fatal to any adjudication. Application of mind is best demonstrated by disclosure of the mind and disclosure of mind is best done by recording reasons in support of the decision which the court or authority is taking. The requirement that an adjudicatory authority must apply its mind is, in that view, so deeply embedded in our jurisprudence that it can be described as a fundamental policy of Indian law.
39. No less important is the principle now recognised as a salutary juristic fundamental in administrative law that a decision which is perverse or so irrational that no reasonable person would have arrived at the same will not be sustained in a court of law. Perversity or irrationality of decisions is tested on the touchstone of Wednesbury [Associated Provincial Picture Houses Ltd. v. Wednesbury Corpn., (1948) 1 KB 223 :
(1947) 2 All ER 680 (CA)] principle of reasonableness. Decisions that fall short of the standards of reasonableness are open to challenge in a court of law often in writ jurisdiction of the superior courts but no less in statutory processes wherever the same are available.
40. It is neither necessary nor proper for us to attempt an exhaustive enumeration of what would constitute the fundamental policy of Indian law nor is it possible to place the expression in the 41
straitjacket of a definition. What is important in the context of the case at hand is that if on facts proved before them the arbitrators fail to draw an inference which ought to have been drawn or if they have drawn an inference which is on the face of it, untenable resulting in miscarriage of justice, the adjudication even when made by an Arbitral Tribunal that enjoys considerable latitude and play at the joints in making awards will be open to challenge and may be cast away or modified depending upon whether the offending part is or is not severable from the rest."
(emphasis in original) It requires to refer herein the paragraph 33 of the
judgment rendered in the case of Associate Builders v.
Delhi Development Authority (Supra) for the purpose of
consideration of the argument advanced on behalf of the
appellant in order to assess as to whether the learned
Arbitrator or the learned court exercising the power under
Section 34 of the Act, has acted contrary to the public
policy of India, for ready reference, paragraph 33 is quoted
hereunder as :-
"33. It must clearly be understood that when a court is applying the "public policy" test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score [ Very 42
often an arbitrator is a lay person not necessarily trained in law. Lord Mansfield, a famous English Judge, once advised a high military officer in Jamaica who needed to act as a Judge as follows:"General, you have a sound head, and a good heart; take courage and you will do very well, in your occupation, in a court of equity. My advice is, to make your decrees as your head and your heart dictate, to hear both sides patiently, to decide with firmness in the best manner you can; but be careful not to assign your reasons, since your determination may be substantially right, although your reasons may be very bad, or essentially wrong".It is very important to bear this in mind when awards of lay arbitrators are challenged.] . Once it is found that the arbitrators approach is not arbitrary or capricious, then he is the last word on facts. In P.R. Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd. [(2012) 1 SCC 594] , this Court held:
"21. A court does not sit in appeal over the award of an Arbitral Tribunal by reassessing or reappreciating the evidence. An award can be challenged only under the grounds mentioned in Section 34(2) of the Act. The Arbitral Tribunal has examined the facts and held that both the second respondent and the appellant are liable. The case as put forward by the first respondent has been accepted. Even the minority view was that the second respondent was liable as claimed by the first respondent, but the appellant was not liable only on the ground that the arbitrators appointed by the Stock Exchange under Bye-law 248, in a claim against a non-member, had no jurisdiction to decide a claim against another member. The finding of the majority is that the appellant did the transaction in the name of the second respondent and is therefore, liable along with the second respondent. Therefore, in the absence of any ground under Section 34(2) of the Act, it is not 43
possible to re-examine the facts to find out whether a different decision can be arrived at."
In this regard, paragraph 42.3 and paragraphs 43
to 45 of the aforesaid judgment are also relevant which are
quoted hereunder as :-
"42.3. (c) Equally, the third subhead of patent illegality is really a contravention of Section 28(3) of the Arbitration Act, which reads as under:
"28.Rules applicable to substance of dispute.--(1)-(2)*** (3) In all cases, the Arbitral Tribunal shall decide in accordance with the terms of the contract and shall take into account the usages of the trade applicable to the transaction."
This last contravention must be understood with a caveat. An Arbitral Tribunal must decide in accordance with the terms of the contract, but if an arbitrator construes a term of the contract in a reasonable manner, it will not mean that the award can be set aside on this ground. Construction of the terms of a contract is primarily for an arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something that no fair-minded or reasonable person could do.
43. In McDermott International Inc. v. Burn Standard Co. Ltd. [(2006) 11 SCC 181] , this Court held as under:
"112. It is trite that the terms of the contract can be express or implied. The conduct of the parties would also be a relevant factor in the matter of construction of a contract. The construction of the contract agreement is within the jurisdiction of the arbitrators having regard to the wide nature, scope and ambit of the arbitration agreement and they cannot be said to have misdirected themselves in passing the award by taking into consideration the 44
conduct of the parties. It is also trite that correspondences exchanged by the parties are required to be taken into consideration for the purpose of construction of a contract. Interpretation of a contract is a matter for the arbitrator to determine, even if it gives rise to determination of a question of law.
113. Once, thus, it is held that the arbitrator had the jurisdiction, no further question shall be raised and the court will not exercise its jurisdiction unless it is found that there exists any bar on the face of the award."
44. In MSK Projects (I) (JV) Ltd. v. State of Rajasthan [(2011) 10 SCC 573] , the Court held:
"17. If the arbitrator commits an error in the construction of the contract, that is an error within his jurisdiction. But if he wanders outside the contract and deals with matters not allotted to him, he commits a jurisdictional error. Extrinsic evidence is admissible in such cases because the dispute is not something which arises under or in relation to the contract or dependent on the construction of the contract or to be determined within the award. The ambiguity of the award can, in such cases, be resolved by admitting extrinsic evidence. The rationale of this rule is that the nature of the dispute is something which has to be determined outside and independent of what appears in the award. Such a jurisdictional error needs to be proved by evidence extrinsic to the award.
45. In Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran [(2012) 5 SCC 306], the Court held:
"43. In any case, assuming that Clause 9.3 was capable of two interpretations, the view taken by the arbitrator was clearly a possible if not a plausible one. It is not possible to say that the arbitrator had travelled outside his jurisdiction, or 45
that the view taken by him was against the terms of contract. That being the position, the High Court had no reason to interfere with the award and substitute its view in place of the interpretation accepted by the arbitrator.
44. The legal position in this behalf has been summarised in para 18 of the judgment of this Court in SAIL v. Gupta Brother Steel Tubes Ltd. [(2009) 10 SCC 63] and which has been referred to above. Similar view has been taken later in Sumitomo Heavy Industries Ltd. v. ONGC Ltd. [(2010) 11 SCC 296] to which one of us (Gokhale, J.) was a party. The observations in para 43 thereof are instructive in this behalf.
45. This para 43 reads as follows: (Sumitomo case [(2010) 11 SCC 296] '43. ... The umpire has considered the fact situation and placed a construction on the clauses of the agreement which according to him was the correct one. One may at the highest say that one would have preferred another construction of Clause 17.3 but that cannot make the award in any way perverse. Nor can one substitute one's own view in such a situation, in place of the one taken by the umpire, which would amount to sitting in appeal. As held by this Court in Kwality Mfg. Corpn. v. Central Warehousing Corpn. [(2009) 5 SCC 142] the Court while considering challenge to arbitral award does not sit in appeal over the findings and decision of the arbitrator, which is what the High Court has practically done in this matter. The umpire is legitimately entitled to take the view which he holds to be the correct one after considering the material before him and after interpreting the provisions of the agreement. If he does so, the decision of the umpire has to be accepted as final and binding.'"
46 14. It is evident from the aforesaid judgment that the
construction of the terms of the contract is primarily for an
Arbitrator to decide, unless the arbitrator construes the
contract in such a manner that no fair-minded or
reasonable person would, in short, that the Arbitrator's
view is not even a possible view to take. If the Arbitrator
wanders outside the contract and deals with matters not
allotted to him, he commits an error of jurisdiction.
This ground of challenge will now fall within the
new ground under Section 34(2-A).
Further, re-appreciation of evidence which is what
an appellate court is permitted to do, cannot be permitted
under the ground of patent illegality appearing on the face
of Award.
The paragraph 42.1 of the judgment rendered in the
case of Associate Builders v. Delhi Development
Authority (Supra) laid down that mere contravention of the
substantive law in India itself is no longer a ground
available to set aside an arbitral Award. Paragraph 42.2 of
the aforesaid judgment, however, would remain for an
Arbitrator gives no reason for an Award and contravenes
Section 31(3) of the 1996 Act that would certainly amount
to patent illegality on the face of the Award.
The Hon'ble Apex Court has further observed
therein that a decision which is perverse, as understood in 47
paragraph 31 and 32 of the Associate Builders v. Delhi
Development Authority (Supra), will no longer being a
ground for challenge a public policy of India would certainly
amount to patent illegality appearing on the face of the
Award.
Thus, a finding based on no evidence at all or an
Award which ignores vital evidence in arriving at its
decision would be perverse and liable to be set aside on the
ground of patent illegality.
Additionally, the finding based on documents taken
behind the back of the parties by the Arbitrator, would also
qualify as a decision based on no evidence in as much as
such decision is not based on evidence laid by the parties,
therefore, would also have to be categorized as perverse.
15. It is, thus, evident that the settled legal position is
that in an application under Section 34 of the Act, 1996,
the court is not expected to act as an appellate court and
re-appreciate the evidence. The scope of interference would
be limited to the ground provided under Section 34 of the
Act, 1996. The interference would be so warranted when
the Award is in violation of the public policy of India which
has been held to be a fundamental policy of Indian law.
Further, the arbitral Award can also be interfered
with if it shocks the conscience of the court as also the
Award would be set aside on the ground of patent illegality 48
appearing on the face of the Award and if the decision is
perverse.
16. This Court, having considered the proposition laid
down by the Hon'ble Apex Court in the aforesaid judgment
and coming back to the Award passed by the learned
Tribunal, has found that the Award has not been passed by
giving go-bye to the condition stipulated in the agreement,
rather, thoughtful consideration has been given by the
learned Tribunal regarding the condition stipulated under
Condition No. 2 and having discussed the same at
paragraph 27, the Award has been passed on 02.06.2017.
17. This Court, thus, is of the view after going through
the Award passed by the learned Arbitrator that there is no
error on the face of it, it does not suffer from perversity and
it is not against the public policy.
18. This Court, after considering the order passed by
the court exercising the power under Section 34 of the Act,
1996 has found therefrom that the learned court has
considered the fact in entirety as also has considered the
scope of judicial review by taking note of the judgment
rendered in the case of Oil & Natural Gas Corporation
Ltd. v. Saw Pipes Ltd. (Supra) which pertains to
interference to be shown in a case of violation of public
policy/perversity or if there is any error on the face of the 49
Award, but the learned court has not found any error on
the face of the Award and the Award having not been found
contrary to the public policy and does not suffer from the
perversity, rather, the learned court, by taking note of the
consideration so made by the learned Arbitrator, has given
specific finding that the Award suffers from no error.
19. This Court, on the basis of the discussion made
hereinabove, is of the view that the Award passed by the
learned Tribunal as also the order passed by the learned
court in exercise of power under Section 34 of the Act,
1996, suffer from no error.
20. So far as the ground agitated that the Award of
counter claim awarding meager amount is concerned,
according to the considered view of this Court, the learned
sole Arbitrator has awarded Rs.9,47,706/- towards the
claim made under the head of the 70% share of the amount
received by the Claimant from the citizens by offering the
government services plus a lump sum amount of
Rs.2,00,000/- towards the delay caused in disbursement of
the said amount of the share of the State Government.
The aforesaid finding, therefore, suggests that it is
not that there is no order on counter claim, as has been
argued, rather, the order has been passed on the counter
claim awarding Rs.9,47,706/- towards the claim made
under the head of the 70% share of the amount received by 50
the Claimant from the citizens by offering the government
services plus a lump sum amount of Rs.2,00,000/- towards
the delay caused in disbursement of the said amount of the
share of the State Government, therefore, the counter claim
has also been considered and Award has been passed
holding the State entitled for the aforesaid amount of
Rs.9,47,706/- plus Rs.2,00,000/-.
21. This Court, taking into consideration the fact that
the Award passed by the learned sole Arbitrator since
suffers from no error, having not found to be contrary to
public policy, therefore, is of the view that the order passed
by the learned court under Section 34 of the act, 1996
requires no interference in exercise of power of judicial
review.
22. Accordingly, the instant appeal fails and is
dismissed.
23. Consequently, pending interlocutory applications
also stand dismissed.
(Sujit Narayan Prasad, J.)
I agree
(Ratnaker Bhengra, J.) (Ratnaker Bhengra, J.)
Birendra/ A.F.R.
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free