The State Of Jharkhand vs Gopal Prasad Mandal

Supreme Court14 August 2019Sanjiv Khanna · Indu Malhotra

Ratio decidendi

The rule this decision rests on

When a court order in a public interest proceeding contains directions framed in general terms regarding the completion of a public work without specifying a particular location in a manner that renders the instruction incapable of performance, the order should not be interpreted strictly and pedantically to require compliance at one particular location if the purpose of the order — the completion of the public work to benefit the intended beneficiaries — has been substantially achieved, even if the work has been completed at a different but substantially similar location acceptable to the affected beneficiaries. Contempt of court proceedings will not lie where a government authority, although it could have sought clarification from the court regarding the interpretation of its order, demonstrates substantial compliance with the essential purpose of the court's directions by completing the public work in question within the prescribed time frame in a manner that resolves the original grievance and is acceptable to the beneficiaries, notwithstanding deviation in the specific location of the work from what may have been originally contemplated.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

NON-REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 3990 OF 2009

STATE OF JHARKHAND & ORS. ….. APPELLANT(S)

VERSUS

GOPAL PRASAD MANDAL ….. RESPONDENT(S)

JUDGMENT

SANJIV KHANNA, J.

Present appeal by the State of Jharkhand is directed against

the order dated 27.08.2008 passed by the High Court of Jharkhand in

Contempt Case (Civil) No. 43 of 2008 titled Gopal Prasad Mandal v.

The State of Jharkhand and Others, inter alia directing as under:

“Since the land in question is still without a road, we find substance in the plea of the petitioner in this contempt petition. Although the respondents might have constructed the road elsewhere, they were duty bound to construct the road on the land in regard to which the order was passed. Hence, the respondents are directed to comply the order dated 9.5.2007 and inform this Court within a period of one month as to what steps have been taken for construction of the Signature Not Verified road in pursuance to the order dated 09.5.2007.

Digitally signed by The counsel for the respondents raised on NEELAM GULATI Date: 2019.08.14 17:03:44 IST

objection that the order sought to be complied does Reason:

not indicate any specific land on which the road had to be constructed.

Civil Appeal No. 3990 of 2009 Page 1 of 6 In our view, the order which is sought to be complied in terms of the order of the writ petition and the land on which the road was to be constructed has specifically been indicated. Hence, the Counsel for the Respondents shall explain it to the respondents– authorities regarding the identification of the land on which the road was to be constructed. Thus, the objection raised has no substance and hence it is rejected.

Let this matter be listed again on 24 th September, 2008.”

2. This Court by order dated 17.11.2008 had issued notice on the

Special Leave Petition filed by the State of Jharkhand with a direction

to file a counter affidavit and the contempt proceedings before the

High Court were stayed until further orders. The matter has remained

pending since then.

3. Contempt proceedings arise from Public Interest Writ Petition (C) No.

6956 of 2006 that were filed before the High Court of Jharkhand with

the following prayers:

“(i) Issuance of appropriate order(s) and/or direction(s) upon the respondents to show cause as to why and under what compelling circumstances, the respondents have till date not constructed the approach road connecting village “Koradih” under Circle Sarwan, P.O. Sabejor, P.S. Sarwan, Sub- Division and district Deoghar to the “Deoghar – Madhupur” Main Road which would facilitate and benefit more than 10,000/- villagers of neighbouring more than 15 villages in transportation and movement to the nearest market, main town and district headquarters as well as enable them to avail better medical facility in Sadar Hospital at Deoghar Town and other well equipped private hospitals and for which the respondents have already acquired 13 decimal of land under due process of law vide L.A. Case No. 11/2003

Civil Appeal No. 3990 of 2009 Page 2 of 6 – 04 as far back as in 2004 when construction of said approach road was duly sanctioned.

(ii) For issuance of appropriate order(s) and/or direction(s) upon the respondents to construct and build the said approach road connecting village Koradih to the Deoghar – Madhupur Main Road in right earnest on the stretch of land measuring 13 decimals of plot No.3, J.B. No. 5, Thana No.243 village Koradih under Sarath Block, district Deoghar acquired vide L.A. Case No. 11/2003-04 and duly sanctioned in the year 2004.

(iii) for any other relief(s) as the petitioner may be found entitled in law.”

Grievance raised in the Writ Petition was concerning delay in

construction of the approach road connecting village Koradih located

in Deoghar District with the Deoghar-Madhupur main road,

inconveniencing more than 10,000 villagers belonging to over 15

neighbouring villages. It was alleged that private land admeasuring

13 decimals had been acquired in 2004 for constructing the

connecting road.

4. The High Court vide order dated 17.04.2007 in this PIL had directed

the Deputy Commissioner, Deoghar to file an undertaking giving a

time frame for completing the construction of the road. Accordingly,

supplementary affidavit dated 09.05.2007 was filed by the Additional

Collector, Deoghar on behalf of the Deputy Commissioner, Deoghar

wherein he had given an assurance and commitment that the road

shall be completed within five or six months after removing

encroachment, etc. Thereupon, the writ petition was disposed of vide

Civil Appeal No. 3990 of 2009 Page 3 of 6 order dated 09.05.2007 of the High Court directing that the

construction of the road in question will be completed within five or

six months.

5. The respondent had thereafter initiated contempt proceedings

contending that the appellant authorities had not complied with the

High Court order dated 09.05.2007 as they had constructed the

connecting road on an alternate land, and not on the private land of

13 decimals acquired for this purpose.

6. In response, the appellant authorities had filed an affidavit stating that

in light of the aforesaid High Court order, the matter had been

considered and an enquiry was made by the Sub-Divisional Officer,

Madhupur at the instance of the then Deputy Commissioner, Deoghar

as there was resistance and agitation by some villagers against

acquisition of 13 decimals of land. Land owners had refused to

accept payment. Accordingly, a proposal had been sent by the

Deputy Commissioner to the appropriate authority of the Revenue

Department for withdrawal of the emergent acquisition proceedings.

To resolve the multiple opposing concerns, the Additional Collector

along with the Deputy Commissioner, Deoghar and Circle Officer of

Sarwan Block and Circle Officer of Sarath Block had persuaded the

villagers that an existing rural path would be converted into a

motorable road. Accordingly, within the time frame mentioned in the

Civil Appeal No. 3990 of 2009 Page 4 of 6 supplementary affidavit, encroachments made by the inhabitants of

the villages were removed, and an alternative approach road

admeasuring 700 feet approximately in length was constructed

connecting the village Koradih with the Deogarh-Madhupur main

road. The road, if constructed on 13 decimals of land would have

been about 300 feet in length. The difference in length being about

400 feet would clearly show that the change was marginal and was

not inconvenient. In any case, it was acceptable to the villagers.

7. In view of the explanation given by the authorities and also the fact

that the road had been constructed, we do not see any good ground

and reason for the High Court to have passed the impugned order

and directions. The object behind the PIL was to ensure that the

connected road is constructed, which has been constructed timely

though at a location different to the original in view of the settlement

amongst the villagers. We do not think the order dated 09.05.2007

passed in the PIL should be read strictly in a pedantic manner to be

construed as a direction that the road had to be constructed at one

particular location. Road was to be constructed for the benefit of the

villagers for which the authorities had taken steps in view of the

grievances of the villagers and an amicable solution after discussion

was found and accepted.

Civil Appeal No. 3990 of 2009 Page 5 of 6

8. Though one would agree that in case of doubt, the authorities should

have approached the court for clarification and appropriate directions,

albeit this failure would not justify contempt of the court proceedings.

In fact, there is compliance of the court’s directions without the matter

getting escalated and the controversy was resolved. Recording the

aforesaid, we allow the present appeal and set aside and quash the

order dated 27.08.2008 and the contempt proceeding in Contempt

Case (Civil) No. 43 of 2008. We clarify that we have not commented

on the land acquisition proceedings in respect of the 13 decimals of

land.

No costs.

......................................J. (INDU MALHOTRA)

......................................J. (SANJIV KHANNA) NEW DELHI;

August 14, 2019.

Civil Appeal No. 3990 of 2009 Page 6 of 6

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free