The Chief Engineer, Water Resources Department & Ors. vs Rattan India Power Ltd. Through Director & Ors.
- SCC(2023) 19 SCC 410
- Neutral2023 INSC 35
- SCR[2023] 3 SCR 1014
Ratio decidendi
The rule this decision rests on
A party to a contract who has signed an agreement stipulating a definite amount of consideration, and who has issued an undertaking to pay that amount, is estopped from thereafter challenging or seeking reduction of the contractual consideration on the ground that a different rate prevailed at some earlier date of administrative approval or sanction. The rights and liabilities of the parties to a contract crystallize on the date of entry into the agreement, and accordingly the rate applicable on that date governs the parties' obligations, not the rate applicable on any antecedent date of in-principle approval or sanction. Where differential treatment of similarly placed parties is alleged in the context of administrative action affecting a contract, the Court will not interfere with the contractual terms on this ground where the Government provides a reasonable and sufficient explanation for the differential treatment based on material distinctions in the circumstances of each case.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
CIVIL APPEAL No. 8550 of 2022 ARISING OUT OF SLP (C) No. 28161 of 2016
THE CHIEF ENGINEER, WATER RESOURCES DEPARTMENT & ORS. ....APPELLANT(S)
VERSUS
RATTAN INDIA POWER LIMITED THROUGH ITS DIRECTOR & ORS. ...RESPONDENTS(S)
JUDGMENT
PAMIDIGHANTAM SRI NARASIMHA, J.
1. The short question which arises for our consideration in the
present case relates to whether a party to a contract is entitled to
question the amount of consideration after signing the contract.
By adverting to the facts of the case, we have held that Respondent
No.1 is estopped from doing so because the Appellant, in all its
communications, had sought for an amount of Rs.1,00,000 as
irrigation restoration charges i.e., consideration for diversion of Signature Not Verified Digitally signed by Sanjay Kumar Date: 2023.01.13
water for industrial use, which was earlier reserved for irrigational 15:53:57 IST Reason:
purposes. Even the contract entered into between the parties Page 1 of 16 prescribed the same amount. In fact, Respondent No.1 agreed to
the pay the consideration by issuing an undertaking on the date
of signing of the contract. In any case, this contractual dispute
concerning the reduction of irrigation restoration charges, was
contested by the parties in an earlier Writ Petition before the High
Court of Judicature at Bombay, and the High Court by its order
dated 22.11.2012 had dismissed the challenge. This is the second
round of litigation on the same issue.
2. This appeal by the State of Maharashtra is against the
judgment of the Division Bench of the High Court of Judicature at
Bombay at Nagpur1, whereby the High Court has reduced the
‘irrigation restoration charges’ which the Respondent herein has
contracted to pay, from Rs.1,00,000 per hectare to Rs.50,000 per
hectare. This has the effect of reducing the total liability of the
Respondent towards irrigation restoration charges from Rs. 232.18
Crores to Rs.116.09 Crores.
3. The matter before us concerns the levy of ‘irrigation
restoration charge’ by the Appellant as per Government Resolution
dated 01.03.2009. The Respondent and other similarly placed
1 In WP No. 4968 of 2015 dated 05.05.2016. Page 2 of 16 companies use water for industrial purposes, which is otherwise
reserved for irrigation of agricultural land. The usage of water for
industrial purposes is seen as loss of water for irrigation, and in
order to compensate for the same, the said charge is levied and
collected by the Appellant. These charges are levied after taking
into account the total number of hectares which will be deprived
of irrigation due to the diversion of water for industrial use.
4. The other cost levied by the Appellant is the ‘capital
expenditure charge’. This charge is used towards the construction
and maintenance of dams. The payment of this charge is optional.
Therefore, in the present case, we are not concerned with the levy
and payment of the ‘capital expenditure charge’.
Facts:
5. On 21.02.2004, the Irrigation Department of the State of
Maharashtra came up with a circular wherein it was prescribed
that when water is diverted for non-irrigation purposes, then the
entity using such water shall pay a sum of Rs.50,000 per hectare
as irrigation restoration charges. The circular stated that no water
shall be diverted unless an agreement is entered into between the
concerned industry and the government.
Page 3 of 16
6. Sophia Power Company Ltd.2, the predecessor of Respondent
No.1 herein, intended to set up a 2640MW thermal power plant.
For that purpose, a communication dated 12.12.2007 was sent by
SPCL to the Maharashtra Industrial Development Corporation to
confirm the availability of 240 million liters of water per day to
facilitate the smooth running of the thermal power plant. Pursuant
to the application made by SPCL, a high-powered committee
constituted by the State of Maharashtra in its meeting held on
21.02.2008, granted in-principle approval for the usage of water
by SPCL. This in-principle approval was subject to SPCL paying
capital contribution and irrigation restoration charges. The high-
powered committee named the Appellant herein as the
implementing agency.
7. On 25.07.2008, the Vidarbha Irrigation Development
Corporation granted final approval for the usage of water by SPCL’s
thermal power plant, subject to SPCL paying a sum of Rs.549.98
Crores comprising of Rs.317.8 Crores as capital costs and
Rs.232.18 Crores as irrigation restoration charge. Irrigation
restoration charge stood at Rs.232.18 Crores since the total
number of hectares which would be deprived of irrigation due to
2 hereinafter referred to as ‘SPCL’.
Page 4 of 16 the diversion of water to SPCL’s thermal power plant was 23219
hectares. This essentially meant that SPCL was directed to pay
Rs.1,00,000 per hectare as irrigation restoration charge, as against
the prevalent rate of Rs.50,000 per hectare. Be that as it may, on
16.08.2008, the Appellant informed SPCL that it would be
reserving the required quantity of water, subject to SPCL paying a
sum of Rs.549.98 Crores. A demand letter to that effect was also
issued by the Appellant on 26.09.2008.
8. Notably, on 01.03.2009, the Water Resources Department of
the Government of Maharashtra increased the irrigation
restoration charges from Rs.50,000 to Rs.1,00,000 per hectare.
This circular came into effect from 01.04.2009.
9.1 On 25.01.2011, Respondent No.1 for the first time issued a
letter to the Minister, Water Resources Department, Government
of Maharashtra, in protest against the levy of Rs.1,00,000 as
irrigation restoration charges. It was of the view that since many
other power manufacturers were given exemption from paying the
capital contribution charge and the irrigation restoration charge,
it may also be exempted from paying the said charges. Pending
consideration of this request, Respondent No.1 requested that they
may be allowed to enter into an agreement for supply of water as
Page 5 of 16 mandated by the circular dated 21.02.2004. Without entering into
an agreement, they could not have drawn water from the dam.
9.2 Respondent No.1 again sent a letter on 25.02.2011, where it
stated that they may be allowed to pay irrigation restoration charge
at Rs.50,000 per hectare in five equal instalments because, when
the in-principle allocation was made and when the final approval
was given, the prevalent rate of irrigation restoration charge was
Rs.50,000. A similar letter was again sent by Respondent No.1 to
the Appellant on 01.06.2011, whereby in addition to the aforesaid
request, Respondent No.1 also asked for an extension to enter into
an agreement. In response, through its letter dated 08.06.2011,
the Appellant granted extension till 31.05.2012 to execute an
agreement. However, the Appellant made no commitments on the
other request raised by Respondent No.1 – waiver/reduction of the
irrigation restoration charge.
10. Since Respondent No.1 did not receive any reply on the
request concerning waiver/reduction of the irrigation restoration
cost, it sent a fresh communication on 10.05.2012 seeking
reduction of the said charge and also seeking permission to pay
the same in 5 equal instalments. The Appellant responded to this
request on 17.05.2012, by stating that there shall be no reduction
Page 6 of 16 in the irrigation restoration charge. That said, the option of paying
the said charge in 5 equal instalments was granted.
11. Ultimately, on 22.05.2012, the Appellant and Respondent
No.1 entered into a water supply agreement. Notably, this
agreement states that Respondent No.1 shall pay a sum of
Rs.1,00,000 as irrigation restoration charge. This agreement
indicates consensus ad idem on the amount to be paid towards
irrigation restoration. In fact, on the same day, Respondent No.1
also issued an undertaking to deposit the irrigation restoration
charge at the rate of Rs.1,00,000 per hectare in 5 equal
instalments.
12. Six months after signing the water supply agreement,
Respondent No.1 initiated writ proceedings before the High Court
of Judicature of Bombay challenging the communicated dated
16.08.2008 and the demand letter dated 26.09.2008. By its order
dated 22.11.2012, a division bench of the Bombay High Court
refused to quash the communications on the ground that the
Respondent No.1 had accepted its liability to pay irrigation
restoration charge at the rate of Rs.1,00,000 per hectare by signing
the agreement dated 22.05.2012. The High Court was of the view
that it could not pass any order which would obviate compliance
Page 7 of 16 of the agreement. However, the High Court held that Respondent
No.1’s plea for reduction of the irrigation restoration charge shall
be decided within a period of 8 weeks, and if the same is decided
favorably, then it would be open for Respondent No.1 to pursue
appropriate remedies in law – to seek a refund or adjust the excess
amount paid.
13. In compliance of the order passed by the High Court, the
Water Resources Department of the State of Maharashtra
considered the request of Respondent No.1 for reduction of the
irrigation restoration charge, and through its order dated
29.01.2013, rejected the said request. The reason given by the
Department was that the State had never committed to any
reduction and also that Respondent No.1 itself had signed the
agreement dated 22.05.2012, which stipulated Rs.1,00,000 per
hectare as the irrigation restoration charge. Immediately
thereafter, the Appellant also issued a demand letter.
14. Aggrieved by the rejection of its representation, Respondent
No.1 preferred a writ petition before the High Court of Judicature
of Bombay at Nagpur challenging the decision dated 29.01.2013.
The High Court by the impugned order, allowed the writ and
directed Respondent No.1 to pay irrigation restoration charges at
Page 8 of 16 Rs.50,000 per hectare. The High Court came to this conclusion by
holding that the rate prevailing on the date on which the in-
principle approval was granted by the high-powered committee
would determine the cost of irrigation restoration charge. The High
Court was of the view that since the total quantity of water used
and total loss of water for irrigation was calculated on the date of
grant of in-principle approval, it would be appropriate for the rate
prevailing as on that date to govern the irrigation restoration
charge. It is this order which is impugned before this Court.
Submissions of the parties:
15. Shri Chander Uday Singh, learned Senior Counsel appearing
for the Appellant contended that the impugned order is in the teeth
of the agreement dated 22.05.2012 entered into between the
Appellant and Respondent No.1. It is his case that the after
accepting Rs.1,00,000 as irrigation restoration charges,
Respondent No.1 is not entitled to challenge it. The substance of
his argument was that a contract is sacrosanct and it must be
respected.
16. Shri Gopal Jain, learned Senior Counsel appearing for
Respondent No.1 contended that – (i) it is the rate prevailing on the
date of grant of in-principle approval by the high-powered Page 9 of 16 committee which would govern Respondent No.1. It is his case that
the irrigation restoration charge is directly linked to the date of
approval/sanction, and on the relevant date, since the circular
dated 21.02.2004 was applicable, the Appellant could have only
levied Rs.50,000 per hectare as irrigation restoration charges; (ii)
a few similarly placed companies were given the relief which
Respondent No.1 was seeking; (iii) the undertaking given by
Respondent No.1 after signing the agreement was not an
unconditional one. This undertaking was subject to the outcome
of the numerous representations made by Respondent No.1 for
reduction of the irrigation restoration charge; (iv) the Government
Circular dated 01.03.2009 will apply prospectively and will not
apply to ongoing contracts. Shri Jain contended that if the said
circular is given retrospective effect, then it would undermine
certainty.
Analysis
17. In the present case, the Appellant and Respondent No.1 had
entered into an agreement on 22.05.2012. This agreement
categorically stated that Respondent No.1 would pay a sum of
Rs.1,00,000 per hectare towards irrigation restoration charge.
Therefore, the Respondent No.1 is not justified in challenging the
Page 10 of 16 levy of Rs.1,00,000 when it itself had agreed to the same. In fact,
on the same day, Respondent No.1 had also issued an undertaking
that it would pay the stipulated sum within a specific period of
time. We may note here that right from the very beginning i.e., in
the sanction order, the demand notice and in all its letters, the
Appellant had stipulated a sum of Rs.1,00,000 per hectare as
irrigation restoration charges. All these communications get
subsumed in the agreement dated 22.05.2012. Therefore, we are
of the view that signing the agreement and issuing an undertaking
would estop Respondent No.1 from challenging the levy of
Rs.1,00,000 as irrigation restoration charges.
18. We are not impressed with the argument of Shri Gopal Jain
that it is the rate prevailing on the date of grant of in-principle
approval which would govern Respondent No.1. The rights and
liabilities of the parties stand crystallized on the date of entering
into the agreement, which is 22.05.2012. Therefore, the rate
prevailing on 22.05.2012 would govern the parties.
19. On the aspect of differential treatment, Respondent No.1
alleges that it has been discriminated when compared to eight
other companies. This allegation is denied by the Government and
they have explained this aspect in their rejoinder filed before this
Page 11 of 16 Court and also in the counter and sur-rejoinder filed before the
High Court. By referring to these records, we have noted that in as
many as four power generators are concerned, the in-principle
approval granted in their favor has itself been cancelled as they
had failed to execute an agreement with the Appellant. A Central
Government undertaking was given an exemption since the power
produced by the said company was to be used for public benefit.
One company was charged Rs.50,000 since the agreement was
entered into on 22.09.2008, and as on that date, the prevalent rate
was Rs.50,000 per hectare. Further, one other power generator
was given an exemption because there was no loss of irrigation
potential due to diversion of water. Another company was charged
Rs.50,000 per hectare since the water to be diverted in favor of the
said company was minimal and more importantly, that particular
area was not a water deficit area. In comparison, Respondent No.1
is drawing a high amount of water from an area where water is a
scarce resource. This is a reasonable and sufficient explanation.
20. We are not satisfied with the approach adopted by the High
Court when Respondent No.1 itself has willfully and deliberately
entered into an agreement knowing fully well the legal and
business consequences. In fact, the relief claimed in this Writ
Page 12 of 16 Petition is similar to the prayer in the Writ Petition which was
disposed of on 22.11.2012. Even in that proceeding, Respondent
No.1 had raised similar arguments. They were countered by the
State by contending that there existed an agreement between the
parties which stipulated a sum of Rs.1,00,000 as irrigation
restoration charges, and pursuant to this agreement, Respondent
No.1 had even issued an undertaking. After taking note of the
contentions, the High Court held as follows:
“5. The record before the Court would indicate that even prior to the execution of the agreement the Petitioners had by a letter dated 12 May 2010 accepted the liability to pay an amount of Rs. 232.18 crores in five instalments. However, since a representation had been submitted to the Government for charging of irrigation restoration charges at the rate of 50,000/- per hectare instead of Rs.1 lakh per hectare, the Petitioners stated as follows:
“Without prejudice to IPL's right made in the representation which is pending with the State Government, it is confirmed that IPL will be willing to execute the agreement before 31st May 2012 on the conditions mentioned at 2 a) & 2 b) above. However, we will like to clarify that in the event of our representation at 1 is decided in our favour, the amount payable towards irrigation restoration charges will stand reduced accordingly and the instalments paid/payable by us will be suitably adjusted/modified.”
6. The agreement which was executed thereafter contemplates that the Petitioners would pay irrigation restoration charges at the rate of Rs. 1 lakh per hectare to Government together with interest and that the decision of the Government on the representation dated 25 January 2011 submitted for the reduction of the irrigation restoration Page 13 of 16 charges would bind the parties. The Petitioners have besides the representation dated 25 January 2011, followed up with subsequent representations which are still pending one of which is the representation dated 30 June 2011 (Exhibit “I”). The Petitioners have moved these proceedings virtually at the end of the deadline for the payment of the second instalment which falls due on 21 November 2012. If this petition were to be instituted much before the approaching deadline, directions could have been issued for the disposal of the representation well in time before the approaching deadline for the second instalment.
In these circumstances and particularly in a contractual area where the parties are governed by an agreement dated 22 May 2012 in support of which the Petitioners have also tendered an undertaking, it will not be possible for the Court to pass any order which would obviate compliance with the agreement….”
The High Court merely directed the concerned authority to take a
decision on the representations made by Respondent No.1 within
a period of eight weeks, and if the same came to be decided in the
favor of Respondent No.1, then Respondent No.1 could take such
measures in law to seek a refund. It is evident that the High Court
refrained from granting a stay on the payment of the second
instalment. In compliance with the direction of the High Court, the
Government considered the matter and it rejected the
representation on 29.01.2013. In that view of the matter, we are of
the opinion that the High Court committed an error in entertaining
a fresh writ petition, which effectively claimed the same reliefs as
of the previous one. The High Court committed a mistake in not
Page 14 of 16 only entertaining the writ petition, but also in supplanting its view
over that of the contract.
21. As has been noted above, irrigation restoration charges were
to be paid by Respondent No.1 in five installments.
S. No. Due Date Amount
1st Installment 22.05.2012 Rs.46,43,80,000
2nd Installment 21.11.2012 Rs.60,13,44,725
3rd Installment 21.05.2013 Rs.56,70,98,175
4th Installment 21.11.2013 Rs.53,28,51,625
5th Installment 21.05.2014 Rs.49,85,35,075
Clause 4 of the undertaking dated 22.05.2012 which was issued
by Respondent No.1 stated that if there is a delay in making the
payment, then penal interest @12% p.a. shall be levied. The
records before us indicate that that only two instalments have been
paid. Therefore, we direct that the balance amount due and
payable towards irrigation restoration charge shall pe paid by
Respondent No.1 on or before 30.06.2023. Further, interest @ 12%
Page 15 of 16 p.a. shall be payable from the date the instalment/payment fell
due till the date of the impugned order i.e., 05.05.2016.
22. In conclusion, we allow the Civil Appeal No. 8550 of 2022
arising out of SLP (C) No. 28161 of 2016 and set aside the
impugned final judgement and order dated 05.05.2016 passed by
the High Court of Judicature of Bombay at Nagpur in W.P. No.
4968 of 2015.
23. Parties shall bear their own costs.
……………………………….J. [S. RAVINDRA BHAT]
……………………………….J. [PAMIDIGHANTAM SRI NARASIMHA]
NEW DELHI;
JANUARY 13, 2023
Page 16 of 16
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free