State Of Orissa vs M/S Samantary Constn.Pvt.Ltd.
- Neutral2015 INSC 655
Ratio decidendi
The rule this decision rests on
1. An award under the 1996 Arbitration and Conciliation Act may be set aside on the ground of patent error, perversity, or non-application of mind, but not merely because it is erroneous or because a different view could be taken on the merits; the court does not sit in appeal to reassess or reappreciate evidence. 2. The expression "public policy of India" under the Act encompasses fundamental policy of Indian law, the interest of India, justice or morality, or conduct that is patently illegal, and includes principles of fair, reasonable and objective decision-making without arbitrariness, adherence to natural justice, and decisions based on due application of mind and rational grounds. 3. Where an arbitrator awards compensation for loss caused by wrongful seizure of machinery or equipment on the basis of hire charges, the arbitrator must ascertain the total value of the machinery, as hire charges may provide a basis for determining compensation but such compensation cannot normally exceed the price of the equipment itself, and failure to conduct such examination constitutes non-application of mind rendering the award perverse. 4. Section 81 of the 1996 Act, which concerns conciliation, applies only where conciliation has been commenced under Section 62 by written invitation and the parties have appointed a Conciliator following the statutory procedure; where no such procedure has been followed, a document does not fall within Section 81's scope and cannot be excluded as inadmissible evidence merely on that ground. 5. An arbitrator is not bound by the technical rules of evidence and must follow the principles of natural justice; Section 19(4) of the Act empowers an arbitral tribunal to determine the admissibility, relevance, materiality and weight of evidence, and the tribunal's decision on these matters is final.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.2991 OF 2007
STATE OF ORISSA … APPELLANT
VERSUS
M/S. SAMANTARY CONSTN. PVT. LTD. & ANR. … RESPONDENTS
JUDGMENT
ADARSH KUMAR GOEL, J.
1. The question raised in this appeal is whether any interference is
called for with the award dated 29 th June, 2003 on the basis of objections
of the appellant-State of Orissa.
2. The Respondent-Company (“the Contractor”) was awarded the work
of “Construction of Mahanadi Barrage on the Right Side from the Right
Divide Wall including Right Head Regulator”
vide Agreement dated 11th February, 1986 at approximate cost of Rs.5
crore.
Signature Not Verified The project was to be completed by 11 th November, 1987. Digitally signed by Sarita Purohit Date: 2015.09.15 However, within the said period only 24.99% work was executed. Further 10:13:28 IST Reason: 1 extension of time was granted upto 21st March, 1988. Till then, only
36.81% of the work was executed. In these circumstances, vide letter
dated 21st April, 1988, the contract was terminated under Clause 46 of
the General Conditions of Contract. The work executed till then was only
47.67%.
3. The Contractor made a claim for Rs.6.99 crore towards its dues. The
dispute was referred to the Arbitration. Retired Justice B.K. Behera (‘the
Arbitrator’) vide award dated 29th June, 2003 upheld the claim of the
Contractor to the extent of Rs.4.45 crore. The Arbitrator also allowed
counter claim of the Department to the extent of Rs.1.37 crores.
4. The Contractor had raised 26 items of claim, out of which 21 were
rejected and five were accepted. The major item of claim was Item No.18
against which award of Rs.3 crore was made. The said claim was towards
hire charges of the machinery and equipment as follows :
“The various machineries which were purchased by the claimants against sanction of advance from the respondents along with the own machineries of the claimants and those brought on hire from the private parties have been seized by the respondents. The respondents are to pay hire charges on each machinery as calculated in Annexure-P for the period those machineries are detained by the respondents. The hire charges of the machineries calculated till 31-10-1989 amount to Rs.68,44,332.00.”
5. The Annexure referred to above, is as follows :
Sl. No. Description of plants and Nos. Period Rate/each Amount in machineries Day Rs. Rs.
1 2 3 4 5 6 2 1 L&T poclain (Excavator) 1 21.4.88 7,475.00 44,77,525.00 to 31.10.89 = 559 days 2 Hand Winch 6 -do- 210.00 1,17,390.00 3 Derrick for sheetpiling 1 -do- 70.00 39,130.00 4 Vibrator for concreting 2 -do- 48.00 26,832.00 5 Concrete Mixer 4 -do- 648.00 3,62,232.00 (Jay Pee) 6 Wee Point Pump with 5 -do- 2405.00 13,44,395.00 accessories 7 Diesel Pump (ship) 6 -do- 517.00 2,89,003.00 8 Electric Pump Pan (ship) 6 -do- 175.00 97,825.00 9 Trucks 4 21.4.88 to 500.00 90,000.00 4.6.88 = 45 days 68,44,332.00
N.B. This amount has been calculated till the preparation of this claim statement, i.e. up to 31-10-89 and the actual amount shall be arrived at after taking into consideration the period from 1-11-1989 till the date of handing over all the aforesaid plants and machinery by the respondents to the claimants.
6. It is not necessary to refer to the other items of dispute as learned
counsel for the parties have raised contentions mainly in respect of Item
No.18.
7. The Arbitrator held that the seizure of the machinery and other
equipments was illegal as termination of contract itself was illegal. The
Contractor was therefore, entitled to hire charges as per Government
rates which amounted to Rs.5 crores but since no men were employed to
maintain the machines and no oil was used, the fair amount of claim to be
upheld was Rs.3 crores.
3
8. The appellant filed objections under Section 34 of the Arbitration and
Conciliation Act, 1996 (“the Act”) to the award including the award of Rs.3
crores against the above Item No.18 in favour of the Contractor.
9. The District Judge held that the Arbitrator committed gross illegality
in awarding the amount of Rs.3 crore with interest @ 18% p.a. from the
date of award till the date of payment. The termination of the agreement
was not justified in absence of lack of diligence on the part of the
Contractor. The claim of the Contractor was to the extent of Rs.
68,44,332/- against which award of Rs.3 crore could not be made. The
letter of the Engineer-in-Chief to the Government could not be looked into
in support of the stand of the Contractor.
10. The District Judge accepted the objection and held that the claimed
amount was Rs. 68,44,332/- which was calculated upto 31 st October,
1989. There was no tangible material beyond oral submission of the
Contractor to substantiate the claim.
11. The High Court reversed the said view. It was observed that the
claim was not limited to Rs. 68,44,332/- as erroneously assumed. The
claim was for the entire period for which the Contractor was deprived of
the machinery and the equipment. Calculation of figure of Rs.
68,44,332/- was till 31st October, 1989. It was further observed that the
scope of Section 34 of the Act was limited to patent illegality or total
perversity on the face of the record. The Court could not substitute its
own decision for the decision of the Arbitrator on merits. Reliance was
4 placed on the decisions of this Court in M/s. Trading Co. vs.
Government of Kerala1, Coimbatore Distt. Podu Thozillar Samgam
vs. Balasubramania Foundry2, State of Rajasthan vs. Puri
Construction Co.3, Bhagbati Oxygen Ltd. vs. Hindustan Copper
Ltd.4, Hindustan Construction Co. Ltd. vs. State of Jammu and
Kashmir5, Oil Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.6 and
Olympus Superstructures Pvt. Ltd. vs. Meena Vijay Khetan7.
12. As regards the objection of the appellant against the admissibility of
letter of the Engineer-in-Chief dated 21 st July, 1991, it was observed that
authenticity of the said document was not disputed. The said Chief
Engineer was in charge of the project and he had given his report after
thorough verification of the work done. The Arbitrator was not debarred
from looking into the same. The Arbitrator was not bound by the
technical rules of evidence and was to follow the principles of natural
justice. Section 19(4) of the Act empowered the Tribunal to determine
admissibility, relevance, materiality and weight of evidence of a
document. The said letter showed that termination of the contract was
not justified as the Contractor had not neglected or failed to execute the
work with due diligence and had also not violated any of the provisions of
the contract. The Contractor had reasonable grounds for the delay and
the entire delay was not attributable to the Contractor. The Contractor
1 1989 (2) SCC 38 2 1987 (3) SCC 723 3 1994 (6) SCC 485 4 2005 (6) SCC 462 5 1992 (4) SCC 217 6 2003 (5) SCC 705 7 1999 (5) SCC 651
5 had completed most difficult part of the work and there was justification
for further extension of time.
13. We have heard learned counsel for the parties.
14. Principal contention raised on behalf of the appellant is that the
District Judge rightly upheld the objection against the award in
respect of Item No.18. The claim based on hire charges could not
be for indefinite period and could in no case exceed the price of the
machinery and other equipment. Moreover, the contract itself
provides for idling charges and the Contractor could at best claim
the said charges for the machinery and the equipment. It was also
submitted that termination of the contract itself was justified and
the Contractor wrongly relied upon the report of the Chief Engineer
which was inadmissible in view of Section 81 of the Act. Reference
was made to Explanation to Section 34 to the effect that if the award was
in violation of Section 81, the same will be in conflict with the public
policy of India which is a ground for setting aside the award under Section
34(2)(b)(ii).
15. Learned counsel for the respondents-Contractor supported the view
taken by the High Court. It was pointed out that Section 81 of the Act
had no relevance as the said section was in part III dealing with
conciliation. The conciliation commenced, under Section 62, by
acceptance of a written invitation to conciliate and if the parties
6 thereafter appoint a Conciliator who proceeds as per the procedure laid
down under the said Chapter of the Act. No such procedure having been
followed, the letter of the Chief Engineer cannot be treated to be covered
by Section 81 of the Act. The said letter could not be treated to be
irrelevant or inadmissible in evidence. In any case, the decision of the
Arbitrator with regard to its admissibility and reliability had to be
accepted as final.
16. Having considered the rival submission and perused the record, we
are of the view that the appeal deserves to be partly allowed.
17. Undoubtedly, the award of the Arbitrator may not be interfered with
on the ground that the same was erroneous or on the ground that a
different view could be taken on merits of the controversy. In considering
an objection to the award, the Court does not sit in appeal over the
decision on merits. However, patent error or perversity could certainly
provide basis for interference.
18. In Saw Pipes Ltd. (supra), it was held that the expression ‘public
policy of India’ has to be construed as being consistent with :
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
7 19. In ONGC vs. Western Geco International Ltd.8, it was observed
that the expression ‘fundamental policy of Indian law’ refers to the
principles providing basis for administration of justice and enforcement of
law in this country which included judicial approach, i.e. not acting
arbitrarily or whimsically and acting in a fair, reasonable and objective
manner without taking into account any extraneous consideration,
following the principles of natural justice, i.e. taking a decision by due
application of mind and by recording reasons and taking rational decision
which can be decided on the touchstone of Wednesbury9 .
20. In P.R. Shah, Shares & Stock Brokers (P) Ltd. vs. B.H.H.
Securities (P) Ltd.10, it was observed that dealing with an objection to
an award, a court does not sit in appeal over the award by reassessing or
reappreciating the evidence.
21. The above principles are well recognized and have been reiterated
recently in Navodaya Mass Entertainment Ltd. vs. J.M. Combines11
and Associate Builders vs. Delhi Development Authority12.
22. Coming to the present case, while we do not find any merit in the
contention that Section 81 of the Act vitiated the award on account of
inadmissibility of the letter of the Chief Engineer, we do find merit in the
contention that there is non application of mind in awarding the amount
of Rs.3 crores towards the hire charges. Under the 1996 Act, the award
8 2014 (9) SCC 263 9 Associated Provincial Picture Houses Ltd. vs. Wednesbury Corpn. (1948) 1 KB 223 : (1947) 2 ALL ER 680 (CA) 10 2012 (1) SCC 594 11 2015 (5) SCC 698 12 2015 (3) SCC 49
8 is required to be a reasoned one unless the parties agree that no reasons
are to be given or the award is based on agreement (Section 31(3)). The
Arbitrator ought to have ascertained the total value of the machinery.
Any reasonable person dealing with a claim on account of loss caused by
the wrongful seizure of machinery or equipment will certainly enquire
into the total value thereof. The hire charges may, at times furnish the
basis for determining the compensation but such determination cannot
normally exceed the price of the equipment as the loss caused cannot
normally be more than the price of the equipment itself. In absence of
such examination, the award can certainly be held to be perverse or
based on non application of mind. In this view of the matter, either the
parties have to be left free to have this issue re-determined which may
further delay the matter or we may ourselves determine the claim based
on the material on record. The latter course has been suggested by
learned counsel.
23. Learned counsel for the appellant has pointed out that as per
invoice of purchase of the excavator, the price was Rs.27,34,134.75. In
respect of the said machinery, claim of the Contractor is Rs.44,77,525/-
only upto 31st October, 1989 out of the total claim of Rs.68,44,332/-. The
claim could not be upheld beyond the price even if depreciation was not
considered. On that basis total claim under Item No.18, on the date of
the seizure could not exceed Rs.50 lakhs which appears to be the price of
the machinery.
9
24. Taking an overall view including the interest component upto the
date of award (as the interest has been awarded only from the date of
award) claim of the Contractor could be assessed at
Rs. 1 crore 25 lakhs. We are conscious that we are not to substitute our
opinion for that of the Arbitrator but since this part of the Award is
outrightly perverse and not based on application of minds, we modify the
award in respect of Item No.18 to Rs.1 crore 25 lakhs as on the date of
the award instead of Rs.3 crores. Subject to this modification, the award
is upheld in all other respects. Final calculation and adjustment may be
made accordingly before the Executing Court.
24. The appeal is partly allowed to the above extent.
…………..……..…………………………….J. [ ANIL R. DAVE ]
…………..….………………………………..J. [ ADARSH KUMAR GOEL ]
NEW DELHI SEPTEMBER 11, 2015.
10
ITEM NO.1A COURT NO.3 SECTION XIA (For Judgment)
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
Civil Appeal No(s).2991/2007
STATE OF ORISSA Appellant(s)
VERSUS
M/S SAMANTARY CONSTN.PVT.LTD.& ANR. Respondent(s)
Date : 11/09/2015 This appeal was called on for pronouncement of Judgment today.
For Appellant(s) Mr. Sibo Sankar Mishra,Adv.
For Respondent(s) Ms. Manjula Gupta,Adv.
UPON hearing the counsel the Court made the following O R D E R
Hon'ble Mr. Justice Adarsh Kumar Goel pronounced Reportable judgment of the Bench comprising Hon'ble Mr. Justice Anil R. Dave and His Lordship.
The appeal is partly allowed in terms of the signed Reportable judgment.
Pending application, if any, stands disposed of.
(Sarita Purohit) (Sneh Bala Mehra) Court Master Assistant Registrar
(Signed Reportable Judgment is placed on the file)
11
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free