State Of M.P. & Anr vs Anshuman Shukla

Supreme Court6 August 2014T.S. Thakur · V. Gopala Gowda · C. Nagappan

Ratio decidendi

The rule this decision rests on

When a special law prescribes a period of limitation that differs from those in the Schedule to the Limitation Act, 1963, Sections 4 to 24 of the Limitation Act shall apply to that special law unless those sections are expressly excluded by the special law itself; a mere specification of a period of limitation is insufficient to exclude these sections unless the special law contains language that constitutes an express exclusion, and the legislative intent must be examined even where no express exclusion is stated. Section 5 of the Limitation Act is applicable to Section 19 of the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983, which prescribes a three-month period for applications for revision by aggrieved parties; since Section 19 contains no express language excluding Sections 4 to 24 of the Limitation Act, and the High Court is conferred with suo motu revisional power at any time (indicating no intent to bar applications filed beyond the prescribed period where sufficient cause exists), the High Court has authority to condone delay in filing revision petitions under Section 5 of the Limitation Act.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1
REPORTABLE
IN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.3498 OF 2008
STATE OF M.P. & ANR. ……APPELLANTS
Vs.
ANSHUMAN SHUKLA ……RESPONDENT
WITH
CIVIL APPEAL NO. 1145 OF 2009
J U D G M E N T
V.GOPALA GOWDA, J.
Civil Appeal No.3498 of 2008 arises out of order
dated 30.6.2005 in C.R.No.1330 of 2003 passed by the
Page 12

Division Bench of the Madhya Pradesh High Court at

Jabalpur relying on the judgment and order dated

13.4.2005 passed by the Full Bench of the Madhya

Pradesh High Court in C.R.No.633 of 2003 etc. The

connected Civil Appeal No.1145 of 2009 arises out of

judgment and order dated 4.7.2006 passed by the

Division Bench of the Madhya Pradesh High Court at

Jabalpur in C.R.No.1 of 2006.

2. Civil Appeal No.3498 of 2008 was heard by a

Division Bench of this Court, wherein by way of

judgment dated 12.05.2008, it was opined that the case

of Nagar Palika Parishad, Morena v. Agrawal

Construction Company1 was not correctly decided and,

thus, the matter required consideration by a larger

bench. It was further opined that the record of the

case be placed before the Hon’ble the Chief Justice of

India for constituting an appropriate Bench. That is

1

2004 (II) MPJR SN 55

Page 2 3

how this matter has come up for consideration before

us.

3. As both the appeals are identical, for the sake of

convenience, we would refer to the necessary facts of

C.A.No.3498 of 2008 which are stated hereunder:

The respondent filed a petition under Section 7 of

the Madhya Pradesh Madhyastham Adhikaran Adhiniyam,

1983 (hereinafter referred to as “the Act of 1983”)

raising certain claims about the works contract

executed between the parties. The petition was partly

allowed by the Madhya Pradesh Arbitration Tribunal vide

its award dated 18.6.2003. An amount of Rs.6,05,624/-

with interest @12% per annum was awarded from

24.04.1998 till the date of realisation.

4. Being aggrieved, the appellants filed a Civil

Revision No.1330 of 2003 before the High Court of

Madhya Pradesh under Section 19 of the Act of 1983,

along with an application under Section 5 of the

Page 3 4 Limitation Act, 1963 (hereinafter referred to as the

“Limitation Act”) to condone the delay in filing the

revision.

5. The High Court observed in its order dated

07.05.2004 in the Revision that the view expressed by

the Division Bench of the High Court in Nagar Palika

Parishad, Morena v. Agrawal Construction Company2

required consideration by a larger Bench on the

question of:

“Whether Provision of Section 5 of the Limitation Act is applicable to revision filed under Section 19 in the High Court?”

6. After the reference was made, the matter in

Nagarpalika Parishad, Morena (supra) came up for

consideration before a division bench of this Court.

While dismissing the petition at the threshold, it was

observed in an order dated 27.08.20043:

2

2004 MLJ 374

3

Page 4 5

“……In our view there is no infirmity in the impugned judgment. The authority in the case of Nasiruddin and Ors. v. Sita Ram Agarwal (2003) 2 SCC 577 has been correctly followed. Same view has also been taken by this Court in the case of Union of India v. Popular Construction Co. (2001) 8 SCC 470.

The Special Leave Petition stands dismissed with no order as to costs.”

7. The full bench of the High Court in the order dated

13.04.2005, held that the dismissal of a special leave

petition at the threshold stage by the Supreme Court is

a binding precedent, and must be followed by the courts

below. It was however also observed that no specific

time limit can be fixed for exercising the suo motu

revisional power under Section 19 of the Act of 1983.

It was further held that the power has to be exercised

within reasonable time which depends upon the nature of

the order to be revised and other facts and

circumstances of the case. The full bench of the High

Court directed to place the revision petition before

2004(II) MPJR SN 374

Page 5 6

the appropriate bench for consideration in accordance

with law.

8. The Civil Revision No. 1330 of 2003 which was

barred by time of 80 days was dismissed by the High

Court for the reasons given by the Full Bench in its

order dated 13.04.2005.

9. Being aggrieved by the order of the High Court, the

appellants filed a special leave petition before this

Court against the dismissal of revision. The Division

Bench of this court vide order dated 12.05.2008 was of

the opinion that the case of Nagar Palika Parishad,

Morena (supra) had been incorrectly dismissed at the

threshold and that the same requires consideration by a

larger Bench and further directed that the records of

the case be placed before the Hon’ble the Chief Justice

of India for constituting an appropriate Bench. Thus,

the matter came before us for consideration.

10. First of all, in order to appreciate rival legal

submissions, it would be necessary to consider Section

Page 6 7

19 of the Act of 1983, which relates to revision and

its limitation, which reads as under :-

“19. High Court’s power of revision –(1)- The High Court may suo motu at any time or on an application made to it within three months of the award by an aggrieved party, call for the record of any case in which an award has been made under this Act by issuing a requisition to the Tribunal, and upon receipt of such requisition the Tribunal shall send or cause to be sent to that Court the concerned award and record thereof. (2) If it appears to the High Court that the Tribunal –

(a) has exercised a jurisdiction not vested in it by law; or

(b) has failed to exercise a jurisdiction so vested; or

(c) has acted in exercise of its jurisdiction illegally, or with material irregularity;

or (d) has misconducted itself or the proceedings; or (e) has made an award which is invalid or has been improperly procured by any party to the proceedings,

the High Court may make such order in the case as it thinks fit.

(3) The High Court shall in deciding any revision under this section

Page 7 8

exercise the same powers and follow the same procedure as far as may be, as it does in deciding a revision under Section 115 of the Code of Civil Procedure, 1908(No.5 of 1908).

(4) The High Court shall cause a copy of its order in revision to be certified to the Tribunal.

Explanation.-For the purposes of this section, an award shall include an “interim” award.”

11. Following submissions were made by the learned

counsel for the parties in support of their claim.

12. Learned counsel on behalf of the appellants

contended that the High Court failed to consider that

the revision petition has been preferred under Section

19 of the Act of 1983 and the delay of 80 days should

have been condoned by it.

13. It was further contended by the learned counsel on

behalf of the appellants that the High Court should

have considered that provision of Section 5 of the

Limitation Act, would be applicable while entertaining

a revision petition under Section 19 of the Act of

Page 8 9

1983. There was also failure on the part of the High

Court for having not exercised the suo motu revisionary

powers under the Act in the circumstances of the case.

14. It was further contended that the judgments

referred in the Full Bench order before the High Court

are not applicable in the circumstance of the case.

15. Regarding Section 19 of the Act of 1983, it was

contended by the learned counsel that the proviso to

Section 19 was added only in the year 2005 though the

issue is concerned with the pre-amendment provision,

when such proviso, specifically conferring power to

condone delay was not there.

16. It was also contended that the question - whether

the Arbitral Tribunal constituted under the Act is a

“Court” or not, need not be decided as Section 19(3) of

the Act of 1983 provides that while exercising the

power of revision, the High Court will exercise the

same powers and will follow the same procedures as it

Page 9 10

does in deciding a revision under Section 115 of the

Civil Procedure Code.

17. It was further contended by the learned counsel

appearing on behalf of the appellants that the order in

the case of Nagarpalika Parishad, Morena (supra) does

not lay down the correct legal position. The order was

passed sub-silentio and is per incurium as it neither

considers the aforesaid legal issues and submissions

nor does it take into account the relevant legal

provisions and the Scheme of the Act or various case

laws on the point. The judgments relied on by this

Court in the case of Nagarpalika Parishad, Morena

(supra) are not applicable to the issues arising here

and are distinguishable on facts.

18. On the other side, in the counter affidavit filed

by the respondents in the connected C.A. No. 1145 of

2009, it is stated that the appellants have been trying

to mislead this Hon’ble Court by stating that the

Application was preferred under Section 5 of the

Limitation Act. However, by a bare perusal of the

Page 10 11

application for the condonation of delay, it can be

seen that the application was preferred under the

amended provisions of Section 19 of the Act. The

benefit of the amended Section 19 of the Act could not

be given to the appellants as the provisions were not

made with retrospective effect. The amendment came into

effect on 29.08.2005, much after the expiry period to

prefer an application under Section 19 of the Act. The

High Court has very rightly held that the Revision was

time barred. Since no such provision existed on the

date of filing of application for condonation of delay,

the appellants were not entitled to get the delay

condoned.

19. We have heard the learned counsel for the parties

and with reference to the above factual and rival legal

contentions urged on behalf of the parties the

following points would arise for our consideration:

1)Whether the provisions of Limitation Act are

applicable to the provisions of Madhya Pradesh

Madhyastham Adhikaran Adhiniyam, 1983?

Page 11 12

2)What Order?

Answer to Point No.1

20. The Madhya Pradesh Madhyastham Adhikaran Adhiniyam,

1983 came into force with effect from 01.03.1985. It

was enacted to provide for the establishment of a

Tribunal to arbitrate on disputes to which the State

Government or a Public Undertaking (wholly or

substantially owned or controlled by the State

Government), is a party and for matters incidental

thereto or connected therewith.

21. The Arbitral Tribunal is constituted in terms of

Section 3 of the Act of 1983, for resolving all

disputes and differences pertaining to works contract

or arising out of or connected with execution,

discharge or satisfaction of any such works contract.

22. Section 7 of the Act provides for reference to

Tribunal. Such reference may be made irrespective of

whether the agreement contains an arbitration clause or

not. Section 7-A of the Act provides for the

Page 12 13

particulars on the basis whereof the reference petition

is to be filed.

23. Section 19 of the Act confers the power of revision

on the High Court. It provides that the aggrieved party

may make an application for revision before the High

Court within three months of the date of the award.

This Section was amended in 2005, to confer the power

on the High Court to condone the delay. Since this

dispute pertains prior to 2005, thus, the provision of

the unamended Act shall apply in the present case.

24. The Limitation Act, 1963 is the general legislation

on the law of limitation.

25. Section 5 of the Limitation Act provides that an

appeal may be admitted after the limitation period has

expired, if the appellant satisfies the court that

there was sufficient cause for delay.

26. Section 29 of the Limitation Act is the saving

section. Sub-section (2) reads as follows:

Page 13 14

“(2) Where any special or local law prescribes for any suit, appeal or application a period of limitation different from the period prescribed by the Schedule, the provisions of section 3 shall apply as if such period were the period prescribed by the Schedule and for the purpose of determining any period of limitation prescribed for any suit, appeal or application by any special or local law, the provisions contained in sections 4 to 24 (inclusive) shall apply only in so far as, and to the extent to which, they are not expressly excluded by such special or local law.”

Sub section (2) thus, provides that Sections 4 to 24 of

the Limitation Act shall be applicable to any Act which

prescribes a special period of limitation, unless they

are expressly excluded by that special law.

27. This Court in the case of Mukri Gopalan v.

Cheppilat Puthanpuravil Aboobacker4 examined the

question of whether the Limitation Act will apply to

the Kerala Buildings (Lease and Rent) Control Act,

1965. While holding that the appellate authority under

4

(1995) 5 SCC 5

Page 14 15

the Kerala Act acts as a Court, it was held that since

the Act prescribes a period of limitation, which is

different from the period of limitation prescribed

under the Limitation Act, and there is no express

exclusion of Sections 4 to 24 of the Limitation Act, in

the above (Lease & Rent) Control Act, thus, those

Sections shall be applicable to the Kerala Act.

While examining the provisions of Section 29(2) of

the Limitation Act, it was observed:

“8. A mere look at the aforesaid provision shows for its applicability to the facts of a given case and for importing the machinery of the provisions containing Sections 4 to 24 of the Limitation Act the following two requirements have to be satisfied by the authority invoking the said provision:

(i) There must be a provision for period of limitation under any special or local law in connection with any suit, appeal or application.

(ii) The said prescription of period of limitation under such special or local law should be different from the period prescribed by the schedule to the Limitation Act.”

Page 15 16

28. It was further held that if the two above

conditions are satisfied, then the following

implications would follow:

“9. If the aforesaid two requirements are satisfied the consequences contemplated by Section 29(2) would automatically follow. These consequences are as under:

(i) In such a case Section 3 of the Limitation Act would apply as if the period prescribed by the special or local law was the period prescribed by the schedule.

(ii) For determining any period of limitation prescribed by such special or local law for a suit, appeal or application all the provisions containing Sections 4 to 24(inclusive) would apply insofar as and to the extent to which they are not expressly excluded by such special or local law.” [emphasis laid by this Court]

29. Further, in the case of Hukumdev Narain Yadav v.

Lalit Narain Mishra5, a three judge Bench of this

court, while examining whether the Limitation Act would

be applicable to the provisions of Representation of

People Act, observed as under:

5

(1974)2 SCC 133

Page 16 17

“17. ....but what we have to see is whether the scheme of the special law, that is in this case the Act, and the nature of the remedy provided therein are such that the Legislature intended it to be a complete code by itself which alone should govern the several matters provided by it. If on an examination of the relevant provisions it is clear that the provisions of the Limitation Act are necessarily excluded, then the benefits conferred therein cannot be called in aid to supplement the provisions of the Act. In our view, even in a case where the special law does not exclude the provisions of Sections 4 to 24 of the Limitation Act by an express reference, it would nonetheless be open to the Court to examine whether and to what extent the nature of those provisions or the nature of the subject-matter and scheme of the special law exclude their operation.”

30. According to Hukumdev Narain Yadav (supra), even if

there exists no express exclusion in the special law,

the court reserves the right to examine the provisions

of the special law, and arrived at a conclusion as to

whether the legislative intent was to exclude the

operation of the Limitation Act.

31. Section 19 of the Act of 1983 prescribes a period

of limitation of three months. This limitation period

Page 17 18

finds no mention in the schedule to the Limitation Act.

Further, Section 19 does not expressly exclude the

application of Sections 4 to 24 of the Limitation Act,

1963.

32. We now turn our attention to the case of Nasiruddin

and Ors. (supra), on which reliance was placed by this

court in the case of Nagarpalika Parishad, Morena

(supra), while dismissing the Special Leave Petition.

The issue in that case was whether the deposit of rent

under section 13(4) of the Rajasthan Premises (Control

of Rent and Eviction) Act, 1950 by a tenant is an

application for the purpose of Section 5 of the

Limitation Act.

33. While examining the nature of the deposit by

tenant, it was held:

“46. ...the deposit by the tenant within 15 days is not an application within the meaning of Section 5 of the Limitation Act, 1963. Since the deposit does not require any application, therefore, the provisions of Section 5 cannot be extended where the default takes place in complying

Page 18 19

with an order under Sub-section (4) of Section 13 of the Act.”

34. Further, explaining as to why Section 5 of the

Limitation Act is not applicable, the Court observed:

“The provisions of Section 5 of the Limitation Act must be construed having regard to Section 3 thereof. For filing an application after the expiry of the period prescribed under the Limitation Act or any special statute a cause of action must arise. Compliance of an order passed by a Court of Law in terms of a statutory provision does not give rise to a cause of action. On failure to comply with an order passed by a Court of Law instant consequences are provided for under the statute. The Court can condone the default only when the statute confers such a power on the Court and not otherwise. In that view of the matter we have no other option but to hold that Section 5 of the Limitation Act, 1963 has no application in the instant case.” [emphasis laid by this Court]

It is evident on a plain reading of the judgment in

that case, that the reason why Section 5 of the

Limitation Act was said to be inapplicable to the

Rajasthan Act, Section 13(4), was because of the nature

of the specific provision in question. It was held that

Page 19 20 Section 5 of the Limitation Act is not applicable to

Section 13(4), as the deposit of rent by the tenant

cannot be said to be an application for the purpose of

Section 5 of the Limitation Act. This case cannot be

said to be relevant to the facts of the present case,

as Section 5 of the Limitation Act has got application

for the purpose of Section 19 of the Act of 1983, and

the cause of action accrued to the appellant when the

Tribunal passed the award.

35. We now direct our attention to the second case i.e.

Union of India v. Popular Construction (supra)on which

reliance was placed by this Court while dismissing the

Special Leave Petition in the case of Nagarpalika

Parishad, Morena (supra). The issue therein was

whether Sections 4 to 24 of the Limitation Act would

be applicable to Section 34 of the Arbitration Act,

1996.

36. The wording of Section 34(3) of the Arbitration

Act, 1996, reads thus:

Page 20 21

“34. (3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:

Provided that if the court is satisfied that the applicant was

prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter."

[emphasis laid by this Court]

While examining the provision of Section 34, the Court

in Popular Construction case (supra) observed as

under:

“8. Had the proviso to Section 34 merely provided for a period within which the Court could exercise its discretion, that would not have been sufficient to exclude Sections 4 to 24 of the Limitation Act because "mere provision of a period of limitation in howsoever peremptory or imperative language

Page 21 22

is not sufficient to displace the applicability of Section 5.” [emphasis laid by this Court]

While holding that Section 5 is not applicable to

Section 34(3), it was held that the presence of the

words “but not thereafter” operate as an express

exclusion to Section 5 of the Limitation Act.

“12. As far as the language of Section 34 of the 1996 Act is concerned, the crucial words are 'but not thereafter' used in the proviso to sub-section (3). In our opinion, this phrase would amount to an express exclusion within the meaning of Section 29(2) of the Limitation Act, and would therefore bar the application of section 5 of that Act. Parliament did not need to go further. To hold that the Court could entertain an application to set aside the Award beyond the extended period under the proviso, would render the phrase 'but not thereafter' wholly otiose. No principle of interpretation would justify such a result.” (Emphasis laid down by the Court)

37. Section 19 of the Act of 1983, does not contain any

express rider on the power of the High Court to

Page 22 23

entertain an application for revision after the expiry

of the prescribed period of three months. On the

contrary, the High Court is conferred with suo moto

power, to call for the record of an award at any time.

It cannot, therefore, be said that the legislative

intent was to exclude the applicability of Section 5 of

the Limitation Act to Section 19 of the Act of 1983.

38. In our opinion, it is unnecessary to delve into the

question of whether the Arbitral Tribunal constituted

under the Act is a Court or not for answering the issue

in the present case, as the delay in filing the

revision has occurred before the High Court, and not

the Arbitral Tribunal.

Answer to Point No.2

39. In light of the reasons recorded above, we are of

the opinion that the case of Nagar Palika Parishad,

Morena (supra) was decided erroneously. Section 5 of

the Limitation Act is applicable to Section 19 of the

Act of 1983. No express exclusion has been incorporated

Page 23 24

therein, and there is neither any evidence to suggest

that the legislative intent was to bar the application

of Section 5 of the Limitation Act on Section 19 of the

Act of 1983. The cases which were relied upon to

dismiss the Special Leave Petition, namely Nasiruddin

(supra) and Popular Construction (supra) can be

distinguished both in terms of the facts as well as the

law applicable, and thus, have no bearing on the facts

of the present case.

40. For the reasons stated supra, we answer the points

framed by us in the affirmative in favour of the

appellants. The impugned judgments and orders are set

aside and both the appeals are allowed. The delay in

filing revision petitions is condoned and the cases are

remanded to the High Court to examine the same on

merits. We request the High Court to dispose of the

cases as expeditiously as possible.

………………………………………………………………………J.

Page 24 25

[T.S. THAKUR]

………………………………………………………………………J. [V. GOPALA GOWDA]

………………………………………………………………………J. [C. NAGAPPAN]

New Delhi, August 6, 2014

Page 25

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free