Som Datt Builders-Ncc-Nec(Jv) vs National Highways Auth.Of India
- SCC(2025) 6 SCC 757
- Neutral2025 INSC 113
- SCR[2025] 2 SCR 203
Ratio decidendi
The rule this decision rests on
Where an arbitral award has been rendered after reasonable interpretation of contract terms based on the facts before the tribunal, and that award has been upheld or substantially upheld by a court exercising jurisdiction under Section 34 of the Arbitration and Conciliation Act, 1996, an appellate court exercising jurisdiction under Section 37 of the same Act must show great restraint and may only interfere where the award is perverse, based on no evidence, ignores vital evidence, or shocks the conscience of the court as a matter of patent illegality going to the root of the matter; mere disagreement with the arbitrator's interpretation of contract terms, however plausible an alternative interpretation may be, is not a ground for appellate interference under Section 37.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
2025 INSC 113 REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2058 OF 2012
SOMDATT BUILDERS –NCC – NEC(JV) APPELLANT(S)
VERSUS
NATIONAL HIGHWAYS AUTHORITY OF INDIA & ORS. RESPONDENT(S)
JUDGMENT
UJJAL BHUYAN, J.
Heard learned counsel for the parties.
2. This civil appeal by special leave is directed against the
judgment and order dated 17.11.2009 passed by the High Court
of Delhi at New Delhi (‘High Court’) in FAO(OS) No. 427 of 2007
[National Highways Authority of India Vs. Som Datt Builders-NCC-
NEC(JV)].
2.1. By the aforesaid judgment, the High Court allowed the
appeal of the respondent-National Highways Authority of India Signature Not Verified Digitally signed by KAVITA PAHUJA Date: 2025.01.27 18:23:51 IST Reason:
(‘respondent’ or ‘NHAI’ hereinafter) under Section 37 of the 2 Arbitration and Conciliation Act, 1996 (briefly ‘the 1996 Act’
hereinafter). It may be mentioned that respondent had
challenged, by way of the aforesaid appeal, the judgment and
order of the learned Single Judge in OMP No. 316/2005 dated
29.08.2007 whereby the learned Single Judge dismissed the
application filed by NHAI under Section 34 of the 1996 Act for
setting aside the award dated 03.06.2005 passed by the Arbitral
Tribunal.
3. The matter relates to execution of a contract awarded
by NHAI to the appellant regarding the work of four laning and
strengthening of the existing two lane section between Km.
470.000 and Km. 38.000 on NH-2 (construction package II-B) near
Kanpur in the State of Uttar Pradesh under World Bank Loan
Assistance.
4. At the outset, it would be apposite to advert to the
relevant facts.
5. Following a process of open bid tender, the related
contract was allotted by NHAI to the appellant vide the contract
agreement dated 27.03.2002 who undertook to execute the work
at the contract price of Rs. 4,961,183,599.00. Appellant is a joint
venture of Somdatt Builders Pvt. Ltd., Nagarjuna Construction 3
Company and Navayug Engineering Company Limited having its
principal place of business at East of Kailash, New Delhi.
6. A joint venture between Consulting Engineering
Services (I) Ltd. and BECA International Consultants Ltd. was
appointed by NHAI as the Engineer of the project in terms of the
contract agreement to supervise the construction work.
7. It was a unit rate contract comprising of a detailed Bill
of Quantities (BOQ). The BOQ contained description of the items
of the work to be executed by the appellant as contractor and the
estimated quantity of each item. The rates of each BOQ item were
to be filled in by the contractor (appellant).
8. The contract agreement provided for a mechanism of
dispute resolution at the first instance through a Dispute Review
Board (‘DRB’) prior to the parties availing of their remedy by way
of arbitration. A three-member panel of DRB was constituted
comprising of one member appointed by each of the two parties
and the third member appointed by the aforesaid two members.
9. While executing the contract, a dispute arose between
the parties in respect of item No. 7.07 of the BOQ which provided
for reinforced earth structure including soil reinforcing geogrid 4
with all fixtures and accessories complete as per approved design
and drawing of specialised firm and matters connected therewith.
The dispute was not really in respect of the nature of the work to
be performed but was the consequence of the geogrid/geotextile
material exceeding the BOQ quantities in the contract. In
essence, the dispute relates to power of the Engineer to revise the
rates given in the BOQ in the event of increase in actual
quantities. This was contested by the appellant.
10. Appellant raised the aforesaid dispute before the DRB
contending that the Engineer/Employer was intending wrongful
application of Clause 52.2 of the Conditions of Particular
Application (COPA) for downward revision of rates for BOQ item
No. 7.07 (ii) of geogrid for quantity in excess of BOQ quantity.
DRB heard both the sides and deliberated upon the issue in
detail. DRB vide its decision dated 15.03.2004 recommended that
quantities of geogrid required limited to the facia area provided in
the BOQ have to be paid as per the BOQ rates.
11. Respondent NHAI was not satisfied with the aforesaid
decision of DRB and invoked the arbitration clause in the contract
agreement whereafter the dispute was referred to arbitration
before an Arbitral Tribunal comprising of three arbitrators: one 5
arbitrator appointed by each of the two parties and the third
arbitrator appointed by the two arbitrators so appointed. It is on
record that each of the arbitrators were technical experts
conversant with the nature of the contract. Arbitral Tribunal, by
a majority of 2:1, passed the award dated 03.06.2005. Arbitral
Tribunal held that the quantity of geogrid given at the tender
stage by NHAI was wrong. Therefore, the increase in quantity was
a mere increase to meet the requirement for completion of the RE
wall work which was indicated by the RCC facia quantity at the
tender stage. There was no change in the design but mere
increase in the quantity beyond the BOQ quantity which did not
attract Clause 52.2. In this context, Arbitral Tribunal held that
the Engineer does not possess the power to revise the rates for
additional quantity of geogrid required for actual execution of
work as per the approved design. Upholding the
recommendations of DRB, Arbitral Tribunal held that variation in
terms of Clause 51.1 was not established and directed NHAI to
pay the appellant for the actual quantity of geogrid required to be
executed to complete the work of RE wall as per the approved
design at the BOQ rate.
6
12. The aforesaid award dated 03.06.2005 was challenged
by the respondent-NHAI under Section 34 of the 1996 Act which
was heard and decided by a learned Single Judge of the High
Court. Learned Single Judge examined the contours of Clauses
51.1, 51.2, 52.1, 52.2, 52.3 and 55.1 and came to the definite
conclusion that there was no change in the design. The BOQ rate
would apply since the matter was one of mere change in quantity.
By the judgment and order dated 29.08.2007, learned Single
Judge of the High Court found no merit in the application filed by
NHAI under Section 34 of the 1996 Act and dismissed the same.
13. It was thereafter that NHAI as the appellant preferred
the appeal before a Division Bench of the High Court under
Section 37 of the 1996 Act. The Division Bench examined the
primary contention of NHAI that under the contractual terms, all
variations in quantity beyond the tolerance limits set out in the
contract, whether arising as a result of issuance of instructions
by the Engineer or arising even without the issuance of
instructions, were open to renegotiation of the rates by the
Engineer. By the judgment and order dated 17.11.2009
(‘impugned judgment’), Division Bench agreed with the contention 7
of NHAI and set aside the award of the Arbitral Tribunal as well
as the order of the learned Single Judge.
14. Being aggrieved, the contractor (appellant) preferred
the related special leave petition. On 14.12.2009, this Court had
issued notice and passed an interim order staying encashment of
the bank guarantee subject to the appellant renewing it for a
period of one year. Vide order dated 10.02.2012, this Court
granted leave and directed continuance of the interim order.
Hence the civil appeal.
15. Contention of the appellant is that it is NHAI who had
provided the wrong quantity in respect of item No. 7.07 of the
BOQ on the basis of which appellant had tendered. Upon approval
of the design by the Engineer when the increased quantity
became known in April, 2003, the Engineer held that BOQ rate
would be payable for the entire quantity which was not acceptable
to NHAI. The increase in quantity was not as a result of any
change in the design or as a result of any instructions given by
the Engineer. The enhancement in the quantity was necessitated
because wrong information was furnished by the respondent at
the stage of tender itself. On dispute being raised, this position
was accepted by the DRB and thereafter by the Arbitral Tribunal. 8
Application filed by the respondent under Section 34 of the 1996
Act for setting aside of the arbitral award was rightly rejected by
the learned Single Judge of the High Court. Division Bench of the
High Court fell in error and committed a manifest mistake in
overturning the technical findings of the three authorities below
while exercising limited jurisdiction under Section 37 of the 1996
Act.
16. Counter affidavit has been filed by respondent NHAI.
Reliance has been placed on Clauses 51 and 52 of COPA. Clause
51 of COPA has two parts: 51.1 and 51.2. Clause 51.1 covers
instructed variations which includes any increase or decrease in
the quantity of work. As per Clause 51.2, for increase or decrease
in quantity of any material, instructions of the Engineer are not
required. A combined reading of Clauses 51.1 and 51.2 would
indicate that though increase or decrease in the quantity of any
work may be without instructions but it nonetheless remains a
variation. Once it is a variation, Engineer has got the power to fix
a new rate. This power is traceable to Clause 52.1, which does
not make any distinction between instructed variation or
uninstructed variation; on the other hand, it provides that all
variations referred to in Clause 51 are to be valued by the 9
Engineer. In case of instructed variation only, notice is required
to be given in terms of the second proviso to Clause 52.2. If this
be the position, view taken by the Division Bench of the High
Court is the correct one and calls for no interference.
17. Mr. Arvind Minocha, learned senior counsel for the
appellant, at the outset submits that the core issue involved in
this appeal is the justification or otherwise of the decision of the
Division Bench of the High Court upsetting concurrent findings
of three authorities while exercising jurisdiction under Section 37
of the 1996 Act. He submits that the dispute raised by the
appellant was decided in its favour by the DRB comprising wholly
of technical experts. Arbitral Tribunal again comprising of
technical persons passed the award in favour of the appellant by
confirming the decision of the DRB. When the respondent filed
application under Section 34 of the 1996 Act for setting aside of
the award, learned Single Judge of the High Court dismissed the
same and affirmed the award passed by the Arbitral Tribunal.
17.1. Learned senior counsel submits that scope of
interference by the appellate court under Section 37 of the 1996
Act is extremely limited. None of the grounds for invocation of
jurisdiction under Section 37 of the 1996 Act were satisfied. 10
Learned Single Judge while exercising jurisdiction under Section
34 of the 1996 Act had repelled the challenge of the respondent
to the arbitral award. View taken by the learned Single Judge is
a plausible view, if not the only possible view. Therefore, Division
Bench committed a manifest error in setting aside the arbitral
award as well as the order passed by the learned Single Judge
affirming the same.
17.2. Adverting to the facts of the case, learned senior
counsel submits that the scope of the contract involved
construction of 50 Kms. of road, service roads on both sides,
drains, 17 main bridges, 65 culverts and 20 under-passes. The
51 Kms. stretch of road included raised carriageway of about 22
Kms. having Reinforced Concrete wall (RCC wall) on both sides
for 9.5 Kms. and Reinforced Earth wall (RE wall) for about 12
Kms. with concrete facia panels. After the award of work, the
design of the wall was to be done by the appellant based on the
design criteria given in the contract with the approval of the
Engineer appointed by the respondent. The item RE wall is
mentioned at item No. 7.07 in the BOQ having three sub-items:
(i) RCC facia wall on both sides, (ii) filter media, (iii) geogrid. 11
17.3. He submits that dispute in the present matter relates
to the sub-item geogrid as the respondent had given a wrong
estimate of the quantity in respect of geogrid while correct
quantities were given for the other two sub-items. This mistake
was detected when the design was prepared by the appellant and
approved by the Engineer. When the quantity of material in
respect of geogrid increased, the Engineer decided that the BOQ
rate would be applicable for the increased quantity of geogrid.
17.4. After the appellant commenced the work, the
respondent was making the monthly payment for the said item as
per the BOQ rate. After a new Engineer was appointed by the
respondent, it was decided that the rate for the increased quantity
of geogrid should be renegotiated.
17.5. Thereafter, the matter was referred by the appellant to
the DRB which decided in favour of the appellant. DRB held that
variation in terms of Clause 51.1 was not established and
recommended payment of geogrid at the BOQ rate for the entire
quantity.
17.6. Respondent did not accept the above
recommendations of the DRB and invoked the arbitration clause 12
in the contract. Arbitral Tribunal, comprised wholly of technical
persons, by a majority of 2:1 held that increase in the quantity of
geogrid for erection of the RE wall as per the approved design
could not be termed as a variation in terms of Clause 51.1.
Further holding that the Engineer did not have the power to revise
the rate qua the BOQ rate for the additional quantity of geogrid
required for execution of the work as per the approved design,
Arbitral Tribunal directed payment as per the BOQ rate for the
additional quantity.
17.7. In the application filed by the respondent under section
34 of the 1996 Act for setting aside of the arbitral award, the
challenge centred around Clauses 51 and 52 only. Learned Single
Judge rejected the challenge of the respondent and upheld the
arbitral award. After the award was confirmed by the learned
Single Judge under Section 34 of the 1996 Act, the Division
Bench acting as the appellate court was not at all justified to
overturn the concurrent findings of three adjudicating fora while
exercising extremely limited jurisdiction under Section 37 of the
1996 Act.
17.8. He further submits that the interpretation given by the
Division Bench is not only contrary to Clause 51.1 and the proviso 13
to Clause 52.2 but renders those provisions completely otiose.
Division Bench misdirected itself by stretching the meaning of the
word variation by referring to dictionary meanings whereas the
said expression has to be understood in the context of the
relevant clauses of the contract. Division Bench failed to
appreciate that in so far automatic increase in the quantity is
concerned, the rate which is payable is the one as agreed in the
BOQ. If any other rate is to be fixed, the same can be considered
only in case of instructed variation provided 14 days prior notice
before commencement of the work is given which was admittedly
not done in the present case. In this connection he places reliance
on a Delhi High Court judgment in the case of NHAI vs. M/s ITD
Cementation India Limited1.
17.9. On the limited scope of interference under Section 37
of the 1996 Act, learned senior counsel for the appellant has
placed reliance on the following decisions:
(i) S.V. Samudram Vs. State of Karnataka2, (ii) M/s. Hindustan Construction Company Ltd. Vs. M/s NHAI3
1 (2009) 113 DRJ 176 2 (2024) 3 SCC 623 3 (2024) 2 SCC 613 14
(iii) Reliance Infrastructure Ltd. Vs. State of Goa4
(iv) Konkan Railway Corporation Limited Vs. Chenab Bridge Project Undertaking5
(v) M/s Larsen Air Conditioning and Refrigeration Company Vs Union of India6
(vi) MMTC Ltd. Vs. Vedanta Limited7
(vii) MP Power Generation Company Ltd. Vs. Ansaldo Energia SPA8
18. Per contra, Mr. Krishnan Venugopal, learned senior
counsel appearing for NHAI submits that Division Bench of the
High Court has rightly set aside the arbitral award finding the
same to be perverse.
18.1. He submits that the core issue involved in the present
appeal is whether the arbitral award dated 03.06.2005 goes
contrary to the only interpretation of Clauses 51 and 52 of the
General Conditions of Contract (GCC) read with COPA as
contained in the contract dated 27.03.2002 executed between the
parties.
4 (2024) 1 SCC 479 5 (2023) 9 SCC 85 6 2023 INSC 708 7 (2019) 4 SCC 163 8 (2018) 16 SCC 661 15
18.2. Learned senior counsel submits that subject matter of
the dispute relates to BOQ item No. 7.07 (II) i.e. geogrid. Due to
change in design of the RE wall, quantity of geogrid increased
almost by 300 percent during execution. Since the twin
conditions contemplated under Clause 52.2 were being fulfilled
i.e. overall quantity of geogrid executed by more than 25 percent
from the estimated quantity and the cost of geogrid being more
than 2 percent of the contract value, the rate for the additional
quantity of geogrid was required to be reworked. Therefore, the
present case is that of instructed variation under Clause 51.1(a)
for which the appellant was also notified on 28.10.2003 fulfilling
the requirement of 14 days’ notice contained in Clause 52.2.
18.3. Referring to the arbitral award, Mr. Venugopal submits
that contrary to the evidence on record and contrary to the
relevant clauses of the contract, Arbitral Tribunal held that it was
not a case of instructions issued by the Engineer but a case of
automatic increase of quantity. Referring to Clause 51.1(a), he
submits that increase or decrease in quantity is also a variation
and as per Clause 51.2, no instructions are required for such
increase or decrease of quantity though the same continues to be
a variation.
16
18.4. Even assuming but not admitting that the Engineer did
not issue any notice to the appellant then also, according to Mr.
Venugopal, a bare reading of Clause 52.2 would make it apparent
that for a non-instructed variation, the condition of giving 14
days’ notice would not apply.
18.5. Learned senior counsel also submits that the
contention of the appellant that the quantity of geogrid had
increased due to negligence and wrong mentioning of figures by
the respondent is totally fallacious in as much as Clause 55.1 of
the contract clarifies that the quantity set out in the contract are
the estimated quantities only.
18.6. He would therefore contend that this is not a case of
plausible interpretation but a case of adopting an interpretation
which is contrary to the only possible interpretation of the
contractual clauses. Arbitral Tribunal has rewritten the contract
by ignoring the plain and simple language of the relevant clauses
and the parties’ intentions besides overlooking the evidence on
record which is legally impermissible. All these aspects were
raised by the respondent in its application under Section 34 of
the 1996 Act but the learned Single Judge failed to consider the
same by placing reliance on a South African judgment which is 17
clearly distinguishable in the facts of the present case. Therefore,
Division Bench of the High Court acting as the appellate court
under Section 37 of the 1996 Act rightly interfered in the matter
by setting aside the arbitral award.
18.7. Learned senior counsel has placed reliance on the
following decisions to buttress his submissions:
(i) Associate Builders Vs. DDA9 (ii) Ssangyong Engineer and Construction Company Ltd. Vs. NHAI10
(iii) PSA Sical Terminals Private Ltd. Vs. Board of Trustees
of V.O. Chidambranar Port Trust Tuticorin11
18.8. Learned senior counsel further submits that the
judgment in the case of NHAI Vs. M/s ITD Cementation India
Limited, cited and relied upon by the appellant, is not applicable
to the facts of the present case. Firstly, the judgment is by a Single
Bench whereas the impugned order has been passed by a Division
Bench which is also later in point of time. Secondly, the said
judgment does not deal with the power of the Engineer to fix a
new rate in terms of Clause 52.
9 (2015) 3 SCC 49 10 (2019) 15 SCC 131 11 (2023) 15 SCC 781 18
18.9. He finally submits that the present appeal is devoid of
any merit and the same is therefore liable to be dismissed by this
Court.
19. Submissions made by learned counsel for the parties
have received the due consideration of the court.
20. At the outset, it would be relevant to advert to Clauses
51 and 52 of the GCC read with COPA. Clauses 51 and 52 are as
under:
Alteration, Additions and Omissions 51.1 Variations (GCC) The Engineer shall make any variation of the form, quality or quantity of works or any part thereof that may, in his opinion, be necessary and for the purpose, or if for any other reason it shall, in his opinion, be appropriate, he shall have the authority to instruct the Contractor to do and the Contractor shall do any of the following:-
(a) increase or decrease the quantity of any work included in the Contract.
(b) omit any such work (but not if the omitted work is to be carried out by the Employer or by another contractor),
(c) change the character or quality or kind of any such work,
(d) change the levels, lines, position and dimensions of any part of the works,
(e) execute additional work of any kind necessary for the completion of the works, or
(f) change any specified sequence or timing of construction of any part of the works.
19 No such variation shall in any way vitiate or invalidate the Contract, but the effect, if any, of all such variations shall be valued in accordance with Clause 52.
Provided that where the issue of an instruction to vary the works is necessitated by some default of or breach of contract by the Contractor or for which he is responsible, any additional cost attributable to such default shall be borne by the Contractor.
51.2 Instructions for Variations (GCC) The Contractor shall not make any such variation without an instruction of the Engineer.
Provided that no instruction shall be required for increase or decrease in the quantity of any work where such increase or decrease is not the result of an instruction given under this Clause, but is the result of the quantities exceeding or being less than those stated in the Bill of Quantities.
52.1 Valuation of Variations (GCC) All variations referred to in Clause 51 and any additions to be Contract Price which are required to be determined in accordance with Clause 52 (for the purposes of this Clause referred to as “varied work”), shall be valued at the rates and prices set out in the Contract if, in the opinion of the Engineer, the same shall be applicable. If the contract does not contain any rates or prices applicable to the varied work, the rates and prices in the Contract shall be used as the basis for valuation so far as may be reasonable, failing which, after due consultation by the Engineer with the Employer and the Contractor, suitable rates or prices shall be agreed upon between the Engineer and the Contractor. In the event of disagreement, the Engineer shall fix such rates or prices as are, in his opinion, appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to enable on- 20
account payments to be included in certificates issued in accordance with Clause 60.
(COPA) Where the Contract provides for the payment of the Contract Price in more than one currency, and varied work is valued at, or on the basis of, the rates and prices set out in the Contract, payment for such varied work shall be made in the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price. Where the Contract provides for payment of the Contract Price in more than one currency, and new rates or prices are agreed, fixed, or determined as stated above, the amount or proportion payable in each of the applicable currencies shall be specified when the rates or prices are agreed, fixed, or determined, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the actual or expected currencies of cost (and the proportions thereof) of the inputs of the varied work without regard to the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price. 52.2 Power of Engineer to fix Rates (GCC) Provided that if the nature or amount of any varied work relative to the nature or amount of the whole of the works or to any part thereof, is such that, in the opinion of the Engineer, the rate or price contained in the Contract for any item of the works is, by reason of such varied work, rendered inappropriate or inapplicable, then, after due consultation by the Engineer with the Employer and the Contractor, a suitable rate or price shall be agreed upon between the Engineer and the Contractor. In the event of disagreement the Engineer shall fix such other rate or price as is, in his opinion, appropriate and shall notify the Contractor accordingly, with a copy to the Employer. Until such time as rates or prices are agreed or fixed, the Engineer shall determine provisional rates or prices to 21
enable on-account payments to be included in certificates issued in accordance with Clause 60.
(COPA) Where the Contract provides for the payment of the Contract Price in more than one currency, the amount or proportion payable in each of the applicable currencies shall be specified when the rates or prices are agreed, fixed or determined as stated above, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the actual or expected currencies of cost (and the proportions thereof) of the inputs of the varied work without regard to the proportions of various currencies specified in the Appendix to Bid for payment of the Contract Price. (GCC) Provided also that no varied work instructed to be done by the Engineer pursuant to Clause 51 shall be valued under Sub-Clause 52.1 or under this Sub-Clause unless, within 14 days of the date of such instruction and, other than in the case of omitted work, before the commencement of the varied work, notice shall have been given either:
(a) by the Contractor to the Engineer of his intention to claim extra payment or a varied rate or price, or
(b) by the Engineer to the Contractor of his intention to vary a rate or price. (GCC) (COPA) Provided further that no change in the rate or price for any item contained in the Contract shall be considered unless such item accounts for an amount more than 2 percent of the Contract Price, and the actual quantity of work executed under the item exceeds or falls short of the quantity set out in the Bill of Quantities by more than 25 percent.
52.3 Variations Exceeding 15 per cent (GCC) 22
If, on the issue of the Taking-Over Certificate for the whole of the works, it is found that as result of :
(a) all varied work valued under Sub-Clauses 52.1 and 52.2 and
(b) all adjustments upon measurement of the estimated quantities set out in Bill of Quantities, excluding provisional sums, dayworks and adjustments of price made under Clause 70.
But not from any other cause, there have been additions to or deductions from Contract Price which taken together are in excess of 15 per cent of the “Effective Contract Price” (which for the purposes of this Sub- Clause shall mean Contract Price, excluding provisional sums and allowance for dayworks, if any) then and in such event (subject to any action already taken under any of Sub-Clauses of this Clause), after due consultation by the Engineer with the Employer and the Contractor, there shall be added to or deducted from Contract Price, such further sum as may be agreed between the Contractor and Engineer or, failing agreement, determined by the Engineer having regard to the Contractor’s site and general overhead costs of the Contract. The Engineer shall notify the Contractor of any determination made under this Sub-Clause, with copy to the Employer. Such sum shall be based only on the amount by which such additions or deductions shall be in excess of 15 per cent of the Effective Contract Price.
(COPA) Where the Contract provides for the payment of the Contract Price in more than one currency, the amount or proportion payable in each of the applicable currencies shall be specified when such further sum is agreed or determined, it being understood that in specifying these amounts or proportions the Contractor and the Engineer (or, failing agreement, the Engineer) shall take into account the currencies (and the proportions thereof) in which the Contractor’s site and general overhead cost of 23
the Contract were incurred without being bound by the proportions of various currencies specified in the Appendix to Bid payment of the Contract Price.
21. DRB while rejecting the contention of NHAI was of the
view that the design of geogrid is contingent to the height and
area of facia panel within the prescribed length mentioned in the
BOQ and based on the parameters/specifications as prescribed
in the agreement, there was no change in the concept or design.
Basically, the design submitted by the appellant was approved
and accepted by the Engineer. Since the work was done as per
the valid approved design, plea taken by NHAI that there was a
change of form in terms of the wall heights and length of RE wall
could not be evidenced by NHAI. After an in-depth analysis, DRB
concluded that there was no change of form but only a working
arrangement. The design having been approved after the full
knowledge of the Engineer that enhancement in quantity to a
large extent was involved and accordingly, the matter was referred
by the Engineer for allocation of funds. Therefore, there was no
variation as per Clause 51.1 or Clause 51.2 and hence payment
as per the BOQ rate should be made for the entire quantity.
Though NHAI had contended that appellant had changed the form
and varied the design, this could not be proved in any way. 24
Therefore, DRB held that variation in terms of Clause 51.1 could
not be established. As such, DRB recommended that quantities
of geogrid required, limited to the facia area, should be paid as
per the BOQ rates.
22. As already noticed, the DRB recommendations were
not acceptable to NHAI which thereafter invoked the arbitration
clause. Arbitral Tribunal comprised of three arbitrators; one each
appointed by the two parties who thereafter appointed the third
arbitrator. All the three arbitrators were technical experts.
Arbitral Tribunal referred to Clause 67.1 of the GCC which says
that recommendations of the DRB shall be binding on both
parties giving prompt effect to it until and unless the same is
revised by the Arbitral Tribunal. Arbitral Tribunal, therefore, was
of the view that NHAI should have complied with the DRB
recommendations which was subject to outcome of the arbitral
award. However, NHAI failed to do so. Thereafter, Arbitral
Tribunal framed the core issue to be considered viz. whether as
per the contract, Engineer has the right to revise the rate for
additional quantities of geogrid in excess of the BOQ quantities
which are required for actual execution of the RE wall as per
approved design. After thorough examination of the rival claims, 25
Arbitral Tribunal recorded the finding that the quantity of geogrid
given at the tender stage which was part of the responsibility of
NHAI was found to be erroneous. Therefore, the increase in
quantity was merely to meet the requirement for completion of
the RE wall which was indicated by the RCC facia quantity at the
tender stage. NHAI had admitted the fact that the design evolved
by the appellant’s consultant met the specified criteria. In other
words, there was no change in the design and NHAI could not
establish the same before the Arbitral Tribunal which held as
follows:
8.3 In a contract of the type in question which is an item rate contract based on the price schedule of provisional quantities the ultimate contract amount can be ascertained when all the work done in terms of the contract is finally measured and the contract amount computation done on the. basis of the prices and rates set out in the Bill of Quantities. The contract between the parties, therefore, is a frame work which determines the parties rights and obligations. The scope of work in this case was indicated by RCC facia quantity as mentioned hereinbefore which determines the length of the RE Wall to be constructed for raised carriage way and the quantity of other sub-item i.e. the geogrid quantity to be used is contingent to the facia quantity. Both the parties knew about the scope of work of RE Wall in this manner and both knew that it 26
was impossible to determine the ultimate contract amount before the completion of RE Wall work and if ultimate quantity exceeds the BOQ quantity, it will be an automatic change and shall be paid at BOQ rate in such type of measurement contracts where the quantities are provisional and ultimate quantities required for completion of the work are to be executed and paid as per the quoted rate.
8.4 The fact that ultimate measured amount of work performed is different from estimated quantity is irrelevant because both the parties contracted on the basis that the ultimate quantity may increase or decrease.
22.1. On the above basis, Arbitral Tribunal concluded that
the change in quantity did not constitute a variation so as to
attract the provisions of Clause 52.2, further noting that this
clause clearly provides that it would be applicable only in respect
of varied work instructed to be done by the Engineer as per Clause
51 and that the present was not a case where such instructions
were required. While upholding the interpretation of the appellant
of Clauses 51 and 52, Arbitral Tribunal held that the Engineer
does not possess the power to revise the rates for additional
quantity of geogrid required for actual execution of the work as
per the approved design. Arbitral Tribunal upheld the
recommendations of DRB and passed the following award:
27 (i) The variation in terms of Clause 51.1 is not established.
(ii) Claimant (NHAI) was directed to pay the Respondent (Som Datt Builders - NCC-NEC- JV) the actual quantity of geogrid required to be executed to complete the work of RE wall as per the approved design at the BOQ rate.
23. DRB had recorded a finding of fact that there was no
change in the concept or design. As a matter of fact, the design
prepared and submitted by the appellant was approved by the
Engineer whereafter the related work was executed as per the
approved design. On the basis of such finding of fact, DRB
interpreted Clauses 51 and 52 to hold that there was no
instructed variation and, therefore, the excess quantity of geogrid
required while executing the work, limited to the facia area,
should be paid as per the BOQ rates. Arbitral Tribunal reiterated
the aforesaid finding of fact and affirmed the interpretation given
by the DRB. On that basis, Arbitral Tribunal concluded that the
change in quantity did not constitute a variation so as to attract
the provisions of Clause 52.2. Arbitral Tribunal concurred with
the DRB that the Engineer did not have the competence to revise
the rates for the additional quantity of geogrid required for
execution of the work as per the approved design. 28
24. In the proceedings under Section 34 of the 1996 Act,
learned Single Judge examined Clauses 51 and 52 in detail and
thereafter opined that the decision of the Arbitral Tribunal could
not be faulted. Analysis of Clause 51.1 read with the other clauses
would indicate that the variations referred therein are instructed
variations. In the present case, Clause 52 would not come into
play since the same arises only in the case of instructed
variations. Learned Single Judge noted with approval the finding
of the Arbitral Tribunal that the ultimate measured work
performed was different from the estimated quantity but the
parties had contracted on the basis that such quantity may
increase or decrease. There was no change in the design in view
of the clear admission of NHAI before the DRB that the design was
reviewed and found according to the specified criteria and that
NHAI was unable to establish any change in the design. Learned
Single Judge while exercising jurisdiction under Section 34 of the
1996 Act after analysing Clauses 51 and 52 held that the Arbitral
Tribunal had reached the conclusion that the second para of
Clause 52.2, which mandates that the said provision would be
applicable only for varied work instructed to be done by the
Engineer as per Clause 51, was not attracted to the facts of the 29
present case, and therefore, the Engineer did not give any notice
of 14 days of his intention to vary the rate. Since the matter fell
within the domain of uninstructed variations, there was no need
to give 14 days’ notice which is the requirement in the case of
instructed variation.
24.1. Learned Single Judge also referred to a decision of the
Appellate Division of the South African Court in Grinaker
Construction (TVL) Ltd Vs. Transvaal Provincial Administration12,
where similar contractual clauses came up for interpretation.
Learned Single Judge agreed with the interpretation given by the
South African Court that automatic increase or decrease in the
quantity did not form part of the variation.
24.2. Learned Single Judge highlighted the aspect that the
interpretation given to the aforesaid clauses was also the
interpretation arrived at by the DRB as also by the Arbitral
Tribunal. The contractual clauses have been interpreted by
technical people who were well conversant with the nature of the
dispute and for this reason also greater weight has to be given to
such a view. Learned Single Judge held that once a contracted
price is provided and the quantities are held to be tentative, any
12 1982 (1) AD 78 30
increase or decrease in quantity must be governed by the same
price. It is only in respect of any instructed variation arising from
the instruction of the Engineer on account of any additional work
or less work that there can be some element of renegotiation and
determination in terms of Clauses 51 and 52 of the GCC.
Therefore, learned Single Judge concurred with the view taken by
the Arbitral Tribunal which had affirmed the view of the DRB.
25. Learned Single Judge also reiterated the well-
recognised principle in arbitration that the court exercising
jurisdiction under Section 34 of the 1996 Act does not sit as a
court of appeal over the decision of an arbitral tribunal, further
reiterating the proposition that a contract has to be interpreted
by the arbitrator who is the chosen judge of the parties. So long
as the view of the arbitrator is a plausible one though it may not
be the only possible view, there should be no interference by the
court under Section 34 of the 1996 Act.
26. According to us, learned Single Judge had adopted the
correct approach and had rightly declined to interfere with the
award of the Arbitral Tribunal affirming the decision of the DRB.
27. Let us now deal with the impugned order. Division
Bench of the High Court exercising jurisdiction under Section 37 31
of the 1996 Act acknowledged that primarily it was for the Arbitral
Tribunal to interpret the contractual terms and if the
interpretation given by the Arbitral Tribunal is a plausible one,
then the court would not interfere with the award merely because
according to the court, another interpretation is preferable.
Having said that, Division Bench examined Clauses 51 and 52 of
the contract. Instead of interpreting the aforesaid clauses in the
contractual context, Division Bench went into the dictionary
meaning of the expression ‘variation’ and opined that variation
would mean the difference between what is provided for or
contemplated in relation to the work under the contract and what
is the final effect or outcome. Such variation or outcome may be
or may not be the result of an instruction given by the Engineer.
It has further been observed that the instruction issued by the
Engineer to the contractor does not necessarily mean that the
contractor should carry out a ‘variation’. It may relate to
performance of one or more of the specific acts enumerated in
Clause 51.1. According to the Division Bench, variation in
quantity, even when it is not a result of an instruction given under
Clause 51.1 by the Engineer to the contractor does not cease to
be a variation within the meaning of that expression used in 32
Clause 51.1. Division Bench, therefore, opined that there is no
basis or underlying principle stated either by the Arbitral Tribunal
or by the learned Single Judge that only if the variation is the
result of instruction given by the Engineer under Clause 51.1,
rates and prices of the BOQ items in question would be open to
renegotiation and not otherwise; variation in quantity, even when
it is not a result of an instruction given by the Engineer to the
contractor under Clause 51.1, does not cease to be a ‘variation’
within the meaning of the expression used in Clause 51.1.
27.1. Division Bench disagreed with the observations of the
Arbitral Tribunal as upheld by the learned Single Judge that even
if there was error in estimating the quantity of geogrid while
preparing the BOQ, that by itself would not lead to the conclusion
that NHAI cannot seek renegotiation of the rates even if the actual
quantity exceeds by over 300 percent. The contract does not
provide that NHAI should suffer on account of the estimated
quantities mentioned in the BOQ turning out to be way off the
mark when the contract is executed.
27.2. It was on the above basis, Division Bench held that
there is no reason as to why variation in quantity beyond the
limits set out in the contract, whether instructed or not 33
instructed, should not lead to renegotiation of the rates at the
instance of either party. That would be the only fair, reasonable
and equitable way to work the contract.
27.3. Division Bench, therefore, held that interpretation of
the contractual terms given by the Arbitral Tribunal and accepted
by the learned Single Judge cannot be accepted as a plausible
interpretation. Division Bench observed that such interpretation
is unreasonable and wholly implausible and that the arbitral
award is opposed to the public policy of India, shocking the
conscience of the court. Therefore, the order of the learned Single
Judge as well as the arbitral award were set aside.
28. We are afraid we cannot accept such sweeping
conclusions reached by the Division Bench. Interpretation given
by the Division Bench to the plain language of Clauses 51 and 52
is not at all a plausible one, not to speak of being the only possible
interpretation and, therefore, committed a manifest error in
interfering with an arbitral award in a proceeding under
Section 37 of the 1996 Act when the learned Single Judge did not
find any justification at all to interfere with the arbitral award
within the limited scope under Section 34 of the 1996 Act. A
closer look at Clauses 51 and 52 would clearly show that the view 34
taken by DRB and Arbitral Tribunal, both comprised of technical
experts, is the correct one which was acknowledged by the
learned Single Judge.
29. As per Clause 51.1, Engineer has the competence to
make any variation of the form, quality or quantity of works,
either wholly or any part thereof, if in his opinion, it is necessary
to do so. In that event, Engineer has the authority to instruct the
contractor to carry out the same and the contractor shall in such
event would be under an obligation to do what is contemplated in
sub-clauses (a) to (f) thereunder, such as, increase or decrease in
the quantity of any work included in the contract, etc.. Clause
51.1 clarifies that such instructed variation shall not vitiate or
invalidate the contract, but such variation shall be valued in
accordance with Clause 52. What Clause 51.2 indicates is that it
is not open to the contractor to make such variation without any
instruction from the Engineer. Proviso to Clause 51.2 is relevant.
It says that no instruction from the Engineer would be required
for the increase or decrease in the quantity of any work where
such increase or decrease is not the result of any instruction
given under Clause 51.1 but is the result of the quantities
exceeding or being less than those stated in the BOQ. 35
30. Clause 52.2, on the other hand, mentions that all
variations referred to in Clause 51 (which means instructed
variations) shall be valued at the rates and prices in the contract,
if in the opinion of the Engineer, the same is applicable. If the
contract does not contain any rates or prices applicable to the
varied works, the rates and prices in the contract shall be used
as the basis for valuation so far it may be reasonable. If this is
not possible, then the Engineer shall carry out the valuation after
due consultation with the Employer and the contractor. The GCC
proviso to Clause 52.2 says that no varied work instructed to be
done by the Engineer shall be valued under Clause 52.1 or under
Clause 52.2 unless 14 days’ notice is given by either of the parties.
31. The further proviso under COPA to Clause 52.2 says
that no change in the rate or price for any item contained in the
contract shall be considered unless such item accounts for more
than 2 percent of the contract price and the actual quantity of the
work executed under the item exceeds or falls short of the
quantity set out in the BOQ by more than 25 percent.
32. The aforesaid provision is not a mandate for change in
the rate or price for any item contained in the contract, if such
item accounts for an amount which is more than 2 percent of the 36
contract price and the actual quantity of work executed under the
item exceeds or falls short of the quantity set out in the BOQ by
more than 25 percent. Rather, it is an enabling provision which
enables either of the parties to consider change in the rate or price
of any item mentioned in the contract, in the event, the above two
conditions are fulfilled.
33. In so far Clause 51.1 is concerned, the variation
contemplated thereunder relates to the form, quality or quantity
of the works which in the opinion of the Engineer is necessary. In
the present case, there is a clear finding of fact by two authorities
i.e. DRB and the Arbitral Tribunal, both comprised of technical
experts, that there is no variation either in the form or quality or
quantity of the works. What actually happened is that at the time
of execution of the contract pertaining to the RE wall, the geogrid
required turned out to be much more than the estimated figure
given in item No. 7.7 of the contract. It is in this backdrop that
both the fact finding authorities held that there was no variation
in terms of Clause 51.1 and that the Engineer did not have the
competence to renegotiate the price or rate of the geogrid for the
excess quantity of geogrid required.
37
34. As already discussed above, this is clearly a plausible
view. In fact, according to us, it is the correct interpretation of
Clause 51 made by the DRB and the Arbitral Tribunal. As such,
learned Single Judge rightly declined to interfere with the award
under Section 34 of the 1996 Act. If that be the position, there
was no justification at all for the Division Bench of the High Court
to set aside the award under Section 37 of the 1996 Act.
35. Though learned counsel for the parties had cited a
number of decisions at the time of hearing, it is not necessary to
refer to and discuss each one of them. However, reference to a few
of the judgments would suffice.
36. In MMTC Ltd. Vs. Vedanta Ltd.13, this Court held that
as far as Section 34 is concerned, the position is well settled that
the court does not sit in appeal over an arbitral award and may
interfere on merits only on the limited ground provided under
Section 34(2)(b)(ii) i.e. if the award is against the public policy of
India. Even then, the interference would not entail a review on the
merits of the dispute but would be limited to situations where the
findings of the arbitrator are arbitrary, capricious or perverse or
when the conscience of the court is shocked or when the illegality
13 (2019) 4 SCC 163 38
is not trivial but goes to the root of the matter. An arbitral award
may not be interfered with if the view taken by the arbitrator is a
possible view based on facts. As far as interference with an order
made under Section 34 by the court under Section 37 is
concerned, it has been held that such interference under Section
37 cannot travel beyond the restrictions laid down under Section
34. In other words, the court cannot undertake an independent
assessment of the merits of the award and must only ascertain
that the exercise of power by the court under Section 34 has not
exceeded the scope of the provision.
37. What is public policy of India has been explained in
Ssangyong Engineer and Construction Company Ltd. (supra). It
means the fundamental policy of Indian law. Violation of Indian
statutes linked to public policy or public interest and disregarding
orders of superior courts in India would be regarded as being
contrary to the fundamental policy of Indian law. It would also
mean that the arbitral award is against basic notions of justice or
morality. An arbitral award can be set aside on the ground of
patent illegality i.e. where the illegality goes to the root of the
matter but re-appreciation of evidence cannot be permitted under
the ground of patent illegality.
39
38. In PSA Sical Terminals Private Ltd. (supra), this Court
reiterating the well settled principles held as under:
40. It will thus appear to be a more than settled legal position, that in an application under Section 34, the court is not expected to act as an appellate court and reappreciate the evidence. The scope of interference would be limited to grounds provided under Section 34 of the Arbitration Act. The interference would be so warranted when the award is in violation of “public policy of India”, which has been held to mean “the fundamental policy of Indian law”. A judicial intervention on account of interfering on the merits of the award would not be permissible. However, the principles of natural justice as contained in Sections 18 and 34(2)(a)(iii) of the Arbitration Act would continue to be the grounds of challenge of an award.
The ground for interference on the basis that the award is in conflict with justice or morality is now to be understood as a conflict with the “most basic notions of morality or justice”. It is only such arbitral awards that shock the conscience of the court, that can be set aside on the said ground. An award would be set aside on the ground of patent illegality appearing on the face of the award and as such, which goes to the roots of the matter. However, an illegality with regard to a mere erroneous application of law would not be a ground for interference. Equally, reappreciation of evidence would not be permissible on the ground of patent illegality appearing on the face of the award.
40
41. A decision which is perverse, though would not be a ground for challenge under “public policy of India”, would certainly amount to a patent illegality appearing on the face of the award. However, a finding based on no evidence at all or an award which ignores vital evidence in arriving at its decision would be perverse and liable to be set aside on the ground of patent illegality.
39. In Reliance Infrastructure Ltd. (supra), this Court
referring to one of its earlier decisions in UHL Power Company Ltd.
Vs. State of Himachal Pradesh14, held that scope of interference
under Section 37 is all the more circumscribed keeping in view
the limited scope of interference with an arbitral award under
Section 34 of the 1996 Act. As it is, the jurisdiction conferred on
courts under Section 34 of the 1996 Act is fairly narrow.
Therefore, when it comes to scope of an appeal under Section 37
of the 1996 Act, jurisdiction of the appellate court in examining
an order passed under Section 34, either setting aside or refusing
to set aside an arbitral award, is all the more circumscribed.
40. Again in M/s Larsen Air Conditioning and Refrigeration
Company (supra), this Court reiterated the position that Section
37 of the 1996 Act grants narrower scope to the appellate court
14 (2022) 4 SCC 116 41
to review the findings in an arbitral award if it has been upheld
or substantially upheld under Section 34.
41. This Court in M/s. Hindustan Construction Company
Ltd. (supra) declared that it is the settled jurisprudence of the
courts in the country that arbitral awards which contain reasons
especially when they interpret contractual terms ought not to be
interfered with lightly. An error in the interpretation of
contractual terms by an arbitrator is an error within his
jurisdiction and would, therefore, not be a ground to interfere
with an arbitral award.
42. As already discussed above, the Arbitral Tribunal had
interpreted Clause 51 in a reasonable manner based on the
evidence on record. This interpretation was affirmed by the
learned Single Judge exercising jurisdiction under Section 34 of
the 1996 Act. Therefore, Division Bench of the High Court was
not at all justified in setting aside the arbitral award exercising
extremely limited jurisdiction under Section 37 of the 1996 Act
by merely using expressions like ‘opposed to the public policy of
India’, ‘patent illegality’ and ‘shocking the conscience of the court’.
As reiterated by this Court in Reliance Infrastructure Ltd. (supra),
it is necessary to remind the courts that a great deal of restraint 42
is required to be shown while examining the validity of an arbitral
award when such an award has been upheld, wholly or
substantially, under Section 34 of the 1996 Act. Frequent
interference with arbitral awards would defeat the very purpose
of the 1996 Act.
43. For all the aforesaid reasons, we are of the unhesitant
view that the impugned order cannot be sustained. Accordingly,
judgment and order dated 17.11.2009 passed by the Division
Bench of the High Court is hereby set aside and the arbitral award
dated 03.06.2005 is restored. Consequently the appeal is allowed.
However, there shall be no order as to cost.
………………………………J. [ABHAY S. OKA]
...……………………………J. [UJJAL BHUYAN] NEW DELHI;
JANUARY 27, 2025.
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free