Satish Sabharwal And Ors. vs State Of Maharashtra And Ors.
- SCC(1986) 2 SCC 362
- AIRAIR 1987 SC 652
Ratio decidendi
The rule this decision rests on
When a government authority cancels a permission granted for use of land for a non-agricultural purpose, and such cancellation is legally valid, the authority remains liable to compensate the person to whom the permission was granted for the reasonable costs actually incurred by that person in setting up the project in reliance on the permission, calculated up to the date the cancellation proceedings commenced. Where compensation for costs incurred in reliance on a validly cancelled permission is awarded as of a specific date, and such costs included borrowed funds on which interest accrued, the compensating authority must also pay interest on the entire compensation amount from the date of commencement of cancellation proceedings until actual payment, calculated at the actual rate charged by the lender on the borrowed portion and at 15 per cent per annum on the person's own funds invested in the project. Where a person has incurred costs in setting up a project pursuant to a permission later cancelled, and compensation is awarded for those costs, the compensating authority must reimburse reasonable ongoing charges for security, insurance, and site maintenance of the project assets from the date cancellation proceedings commenced until the assets are taken over by the authority, assessed on the basis of expert professional evaluation of such charges.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
1. These cross appeals arise out of the Judgment dt. 24th August, 1984 delivered by the High Court of Bombay in W.P. 4232 of 1983. The High Court by its Judgment upheld the order Dt. 25th November, 1983 passed by the Govt. of Maharashtra cancelling the permission granted by the Addl. Collector, Thane to the petitioners on 5th April, 1982 to use the land bearing Survey No. 70, 44, 42, 40/2, 41 and 45 situate in Bhiwandi for non-agricultural purpose of abattoir, meat processing and cold storage. The High Court however while upholding the impugned order dt. 25th November, 1983 directed the Govt. of Maharashtra to pay to the petitioners compensation for the cost incurred by them in setting up the project of abattoir, meat processing and cold storage upto 7th October, 1983 being the date when the show-cause notice was issued by the State Govt. for cancellation of the permission. The State of Maharashtra was aggrieved by that part of the judgment which directed the State Govt. to pay compensation to the petitioners while the petitioners were aggrieved by that part of the judgment which upheld the impugned order dt. 25th November, 1983. The State of Maharashtra therefore preferred C.A. 4875/84 with special leave obtained from this Court while the petitioners obtained special leave to appeal and preferred C.A. 256/85. Whilst these cross appeals were pending before this Court the proceedings continued before the High Court for quantifying the amount of compensation payable by the State Govt. to the petitioners under the Judgment of the High Court. Two reputed firms of Chartered Accountants namely, Batliboi & Purohit and Haribhakti & Co. were appointed by the Govt. to advise and assist them in the quantification of the amount of compensation and after holding a detailed inquiry, they submitted a report and this report was filed by the State Govt. in Court. The High Court on the basis of this report made by the two firms of Chartered Accountants and after hearing objections to the report from both sides passed an Order dt. 3rd July, 1985 holding that the cost incurred by the petitioners upto 7th October, 1983 amounted to Rs. 3,42,12,179.73 and after deducting the value of the machinery removed by the petitioners since 7th October, 1983 the total compensation payable by the State Govt. to the petitioners came to Rs. 3,22,51,538.90. This order made by the High Court was also assailed in the two cross appeals before us.
2. We may point out that the petitioners had obtained over-draft facility from the Punjab National Bank and interest was payable by them to the Punjab National Bank on the amount of the over-draft loan. Since the amount of the over-draft loan borrowed by the petitioners had gone into the project and therefore formed part of cost of the project, the amount of the over-draft loan together with interest payable upto 7th October, 1983 was taken into account in arriving at the figure of Rs. 3,22,51,538.90, as the amount of compensation payable to the petitioners. Since the State of Maharashtra contended in the appeal preferred by them that no amount was payable by the State Govt. to the petitioners by way of compensation, the Punjab National Bank which has interest in supporting the Judgment of the High Court filed Transfer - Petition No. 1 of 1986 and appeared to contest the appeal of the State Govt. in order to protect its right.
3. We have heard the learned advocates appearing on behalf of the petitioners, the State Govt. and the Punjab National Bank at great length. We are of the, view that the Judgment dt. 24th August, 1984 passed by the High Court is correct and C.A. No. 4785 of 1984 filed by the State of Maharashtra must be dismissed. Civil Appeal No. 256 of 1985 preferred by the petitioners must also be dismissed to the extent that it challenges the judgment of the High Court upholding the impugned Order dt. 25th November, 1983 and directs payment of compensation by the State Govt. to the petitioners for the cost incurred by the petitioners on the project upto 7th October, 1983. We uphold the view taken by the High Court that a sum of Rs. 3,22,51,538.90 is payable by the State Govt. to the petitioners by way of compensation. But admittedly this amount of compensation has been calculated as on 7th October, 1983. The High Court has not taken into account interest for the period subsequent to 7th October, 1983 and has stated that "the petitioners are always at liberty to request Hon'ble the Supreme Court to award interest on the costs after 7th October, 1983 till payment. We express no opinion in the matter." It is obvious that the petitioners are entitled to interest on the costs for the period subsequent to 7th October, 1983, since they have suffered loss by reason of the failure of the State Govt. to pay the amount of compensation which, on the view taken by the High Court and affirmed by us, was payable by the State Govt. to the petitioners as on 7th October, 1983. We therefore direct the State Govt. to pay to the petitioners interest payable to the Punjab National Bank at the actual rate charged by the Bank from 8th October, 1983 until payment. So also the State Govt. shall pay to the petitioners interest @ 15% per annum on the sum of Rs. 1,47,64,302 representing the petitioners' own funds invested in the project and such interest shall be calculated from 8th October, 1983 upto payment. The State Govt. shall also pay to the petitioners as and by way of security, insurance and site maintenance charges a sum of Rs. 25,000/- per month from 8th October, 1983 upto the date when the land, building machinery and equipment of the petitioners is taken over by the. State Govt. against payment of compensation. We have taken the rate of Rs. 25,000/- per month since this rate has been suggested by the two firms of Chartered Accountants appointed by the State Govt.
4. We are making this order disposing of the two civil appeals and transfer case, since any delay in disposal of these cases would mullet the State Govt. in payment of further compensation by way of interest and security insurance and site maintenance charges. Wo shall give our reasons for making this Order in due course.
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free