Satish Babu Dasari vs K.Gopi Prasad
- Citation2025 SCC OnLine TS 2432
Ratio decidendi
The rule this decision rests on
An unregistered agreement to sell immovable property, regardless of notarization, cannot convey title or ownership; only a registered sale deed can effect a valid transfer of title in immovable property. On an application for temporary injunction under Order XXXIX Rules 1 and 2 of the Code of Civil Procedure, where the plaintiff adduces documentary evidence of prima facie title through registered sale deeds and of possession through electricity bills, tax payment receipts, and police complaints of interference, and the defendant produces no credible evidence of possession or title, the court must grant the temporary injunction, notwithstanding the plaintiff's failure to mark exhibits before the trial court if those exhibits are later properly marked before the appellate court. A failure by the trial court to consider documentary evidence of title and possession because the documents were not marked as exhibits before it is an error that an appellate court may correct by allowing the documents to be marked and reconsidering the application for temporary injunction on the basis of such evidence.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
revision petitioner and Sri.N.M.Krishnaiah, learned counsel for the
respondent. Perused the record.
2. This Civil Revision Petition is preferred aggrieved by the order
dated 13.11.2024 in C.M.A. No.08 of 2024 passed by the learned VI
Additional District Judge, Ranga Reddy District at Kukatpally, (for
short, 'the Appellate Court'), wherein, the C.M.A. is filed challenging
the dismissal order dated 15.03.2024 in I.A. No. 588 of 2023 in
O.S. No. 480 of 2023 on the file of learned Principal Junior Civil
Judge-cum-VIII Additional Metropolitan Magistrate, Ranga Reddy
District, Kukatpally, (for short, 'the Trial Court') filed under Order
XXXIX Rule 1 and 2 of the CPC seeking temporary injunction
against the defendant and his agents from interfering with the
peaceful possession and enjoyment of the plaintiff over the suit
schedule property, has been dismissed.
3. The revision petitioner is the defendant and the respondent is
the plaintiff before the Trial Court. For the sake of convenience, 2 RY,J crp_3951_2024
hereinafter, the parties will be referred to as arrayed before the
Trial Court in O.S. No. 480 of 2023.
4. The brief facts of the case are that the plaintiff filed a suit in
O.S. No. 480 of 2023 for perpetual injunction with respect to the
suit schedule property consisting of plot Nos.154, 155, 172 and
173, each plot admeasuring 150 sq. yards., in Block No.111, in
southern part land in Survey No.78 (i.e., 78-B, as per internal
division), total admeasuring 600 sq. yards, having plinth area of
100 sq. feet ACC, situated at Hafeezpet village, Serilingampally
Mandal, Ranga Reddy District. The plaintiff claims to be the
absolute owner and possessor of the suit schedule property having
purchased the same from M/s. Cyrus Investment Limited,
represented by its GPA holder namely Dr. P.S.Prasad vide GPA
No.543 of 1996 represented by his SPA holder namely P.V.S. Sarma
under registered sale deeds document bearing Nos.508 of 2015 and
506 of 2015 dated 31.07.2014. The land in Survey No. 78 of
Hafeezpet village is subject matter of C.S. No.14 of 1958 before the
High Court of Andhra Pradesh and in the final decree, the plaintiff's
vendor got land in Survey No.78 of Hafeezpet village and was
delivered with vacant physical possession. The plaintiff raised
compound wall surrounding the suit schedule property to protect it
from land grabbers. Temporary room was constructed for the 3 RY,J crp_3951_2024
purpose of usage by watchman and also to protect the suit
schedule property. Taking advantage of the plaintiff's absence, the
defendant started illegal attempts to occupy the suit schedule
property and the same were time and again restrained by the
watchman. When the defendant tried to occupy the suit schedule
property with the help of anti-social elements on 27.11.2021, the
said attempts were restrained and the suit for perpetual injunction
is filed. Along with the suit, I.A. No. 588 of 2023 was filed seeking
temporary injunction to restrain the defendant from causing
interference with the possession of the plaintiff over the suit
schedule property. The defendant opposed the I.A. alleging that the
plaintiff did not approach the Court with clean hands as there are
complicated litigations which are not reported and there is no
information as to on what basis the possession of land in Survey
No.78 of Hafeezpet was delivered to the plaintiff in final decree in
C.S. No. 14 of 1958. No evidence is filed by the plaintiff to prove
his possession over the suit schedule property. The defendant is
paying the electricity bills for plot Nos.1508 and 1511 in Survey
No.78 which were purchased by him under a notarized agreement
of sale dated 22.12.2005. There was no final lay out for the land in
Survey No.78. The plaintiff made attempts to occupy the plot
Nos.1508 and 1511 in Survey No.78 with the help of his friends 4 RY,J crp_3951_2024
and therefore, a suit in O.S. No. 388 of 2019 is filed on the file of
learned III Additional Junior Civil Judge, Kukatpally and the same
is pending. In this context, the defendant denied all the allegations
made by the plaintiff.
5. Upon considering the evidence of both the parties, the Trial
Court dismissed the I.A. Aggrieved by the same, the plaintiff
preferred C.M.A. before the Appellate Court. The Appellate Court
allowed the C.M.A. setting aside the dismissal order of the Trial
Court and granted temporary injunction in favour of the plaintiff.
Aggrieved by the same, the present civil revision petition is
preferred.
6. In the grounds of the revision, the defendant pleaded that the
plaintiff did not establish prima face title, balance of convenience,
irreparable loss and hardship for granting relief of injunction. The
suit schedule property claimed by the plaintiff and the defendant
are different and without proper identification, the Trial Court was
not inclined to grant temporary injunction and the Appellate Court
did not consider the same. There are no circumstances warranting
interference with the finding of the Trial Court for granting
injunction. The defendant contended that his possession is
established as the plaintiff is a friend of Sanjeeva Reddy and 5 RY,J crp_3951_2024
Venkat Raju against whom he filed a suit in O.S. No. 388 of 2019
who are attesting witnesses to sale documents of the plaintiff. The
defendant has been in possession of his properties from 2005 and
therefore, the order of the Appellate Court is not sustainable.
Lastly, it is pleaded that the Appellate Court cannot come to a
conclusion solely on the basis of certified copies of the documents
which do not pertain to the property claimed by the plaintiff and
without going into the documentary evidence which establishes the
possession of the defendant over the suit schedule property. It is
pleaded that as on the date of filing of the suit, the plaintiff failed to
establish his possession. Therefore, the Trial Court rightly
dismissed the I.A. but the Appellate Court erroneously reversed the
same.
7. During the arguments, learned counsel for the defendant
claimed that the defendant is in possession of the property and was
carrying out construction activity and the same is evident from the
affidavit filed by the plaintiff while seeking temporary injunction in
I.A. No. 588 of 2023 and the Trial Court has noticed the same that
there was already construction of the defendant and there was
intention of further construction which was sought to be prevented
by the plaintiff and therefore, has rightly dismissed the I.A.
Further, it is argued that the Appellate Court has relied upon the 6 RY,J crp_3951_2024
oral argument of the plaintiff that there was a typographical error
about further construction in the suit schedule property and that
there is no construction but attempts to make construction and on
the basis of said arguments, the C.M.A. has been allowed. It is
argued that the plaintiff does not have possession, balance of
convenience and there is no likelihood of irreparable loss as he is
not in possession of the suit schedule property.
8. Learned counsel for the plaintiff argued that the plaintiff is in
possession of the suit schedule property having constructed a
compound wall and a room for watchman in the suit schedule
property. Further, when there was interference from the defendant,
suit for perpetual injunction has been filed in O.S. No. 480 of 2023.
The plaintiff is claiming title and ownership under registered sale
deeds dated 31.07.2014, whereas, the defendant is claiming title
under a notarized agreement of sale dated 22.12.2005 which has
no legal validity. Further, it is argued that there was a failure to
mark the documents before the Trial Court and the said error is
rectified by marking the documents before the Appellate Court by
filing petition under Order XLI Rule 27 of the CPC. After
considering the documentary evidence, since there is no
documentary evidence produced on behalf of the defendant, on the
basis of the documentary evidence produced by the plaintiff, the 7 RY,J crp_3951_2024
C.M.A. is allowed. Further, it is argued that there was a
typographical mistake in the affidavit about carrying on further
construction when there were attempts to make construction by
the defendant and therefore, it is argued that the Appellate Court
did not commit any error in granting temporary injunction and as
such, there are no grounds to interfere with the order passed by the
Appellate Court.
9. In support of the arguments, learned counsel for the plaintiff
relied upon the judgment of the Hon'ble Supreme Court in Vinod
Infra Developers Limited v. MahaveerLunia and Others 1,
wherein, reference is made to the case of Cosmos Co-Operative
Bank Limited v. Central Bank of India and Others 2 and held
that title and ownership of immovable property can only be
conveyed by a registered sale deed. Further, in M.S.
Ananthamurthy v. J.Manjula 3, the Hon'ble Supreme Court held
that an unregistered agreement to sell does not and cannot by itself
create or transfer any right, title, or interest in immovable property. Further, in M.S. Ananthamurthy (Supra) reference is made to
Suraj Lamp and Industries Private Limited v. State of
1 2025 INSC 772 2 2025 SCC OnLine SC 352 3 2025 INSC 273 8 RY,J crp_3951_2024
Haryana 4, wherein it is held that title and ownership cannot be
conveyed to power of attorney and that relevant paragraph is
extracted and produced below:
47. It is settled law that a transfer of immovable property by way of sale can only be by a deed of conveyance. An agreement to sell is not a conveyance. It is not a document of title or a deed of transfer of deed of transfer of property and does not confer ownership right or title. In Suraj Lamp (Supra) this Court had reiterated that an agreement to sell does not meet the requirements of Sections 54 and 55 of the TPA to effectuate a 'transfer'.
(verbatim reproduced)
10. The order dated 15.03.2024 passed by the Trial Court
indicates that the documents relied upon by the plaintiff were not
exhibited but a reference is made to documents produced in proof
of the title i.e., registered sale deeds dated 31.07.2014. Further,
the Trial Court held that there is no proof to show that there is a
room with electricity connection in the suit schedule property.
Lastly, reliance is placed on the averments of the affidavit that the
defendant is carrying on construction in suit schedule property and
arrived at a conclusion that the defendant is not in possession of
the suit schedule property and therefore, dismissed the I.A. No. 588
of 2023. When it comes to adjudication of the C.M.A., the plaintiff
got marked Ex.A.1 to A.11 to prove both title as well as possession.
4 (2012) 1 SCC 656 9 RY,J crp_3951_2024
The documents consists of Ex.A.1 which is the certified copy of sale
deed bearing document No.506 of 2015 dated 31.07.2014; Ex.A.2,
the certified copy of sale deed bearing document No.508 of 2015
dated 31.07.2014; Ex.A.3, the original electricity bill; Ex.A.4, online
bill enquiry of electricity connection; Ex.A.5, the copy of common
order passed in W.P. Nos.14881 and 14885 of 2020 wherein, a
direction was given to the GHMC to grant construction permission
to the plaintiff; Ex.A.6, the copy of complaint given to the Police
about the interference on the part of the defendant; Ex.A.7, the
copy of crime petition acknowledgment dated 30.03.2024; Ex.A.8,
the GHMC fees intimation letter dated 17.12.2021; Ex.A.9, the
GHMC payment receipt dated 23.12.2021; Ex.A.10, the copy of the
Hon'ble Supreme Court order in SLP Nos. 15677 and 15678 of
2020 and Ex.A.11, the copy of plaint in O.S. No. 480 of 2023. These
documents were held to prove the prima facie case of title and
possession in favour of the plaintiff.
11. Coming to the further construction by the defendant, it is
clarified that due to a mistake the words 'further construction' were
mentioned in the affidavit filed by the plaintiff. Therefore, the
Appellate Court came to a conclusion that the plaintiff has shown
prima facie case of title and possession through registered sale
deeds dated 31.07.2014, online bill enquiry of electricity 10 RY,J crp_3951_2024
connection, GHMC fees intimation letter dated 17.12.2021 and
payment of tax to GHMC in receipts dated 23.12.2021. The plaintiff
has shown the case of interference on the part of the defendant by
producing Exs.A.6 and A.7 acknowledgment. On the basis of said
documentary evidence and clarification given about the 'further
construction' by the defendant, the Appellate Court granted
temporary injunction in favour of the plaintiff with respect to the
suit schedule property by setting aside the order dated 15.03.2024
passed by the Trial Court in I.A. No. 588 of 2023.
12. Having perused the record and considering the arguments,
this Court sees that due to failure to mark the exhibits in proof of
title and possession, the Trial Court has dismissed the I.A. When
said lacuna was rectified before the Appellate Court by adducing
the documentary evidence, the case of the plaintiff was
strengthened. Further, as per the own averments of the defendant,
title is claimed through a notarized agreement of sale dated
22.12.2005 which has no legal validity to claim title. Even in case
title is not considered, the defendant has to produce credible
evidence to show his possession to deny relief to the plaintiff.
Further, the plaintiff through Ex.A.5, the copy of common order
passed in W.P. Nos.14881 and 14885 of 2020 wherein, a direction
was given to the GHMC to grant construction permission to the 11 RY,J crp_3951_2024
plaintiff; Ex.A.8, the GHMC fees intimation letter dated 17.12.2021
and Ex.A.9, the GHMC payment receipt dated 23.12.2021, has
demonstrated that he was making construction by obtaining
relevant sanctions. The aforementioned documents show plaintiff's
attempts at construction. While so, there is no evidence on the part
of defendant to show possession or construction or even 'further
possession'. In fact, the defendant failed to mark exhibits on his
behalf before the Trial Court as well as the Appellate Court.
Therefore, when there is no contra evidence to rebut the claim
made by the plaintiff seeking temporary injunction under Exs.A.1
to A.11, this Court sees no reason to interfere with the order
passed by Appellate Court. Hence, there are no merits in the civil
revision petition and the same is liable to be dismissed.
13. Accordingly, the Civil Revision Petition is dismissed. There
shall be no order as to costs.
Miscellaneous Petitions, if any pending, shall stand closed.
___________________ RENUKA YARA, J Date: 29.10.2025 gms
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free