Miss Lucy
← All judgments

Samaj Parivartana Samudaya vs State Of Karnataka .

Supreme Court26 August 2022C.T. Ravikumar · Hima Kohli · N.V. Ramana

Ratio decidendi

The rule this decision rests on

Where an earlier judicial ceiling or production limit was imposed in response to a specific situation of environmental crisis and illegal activity, and that situation has substantially changed through the passage of time and the implementation of remedial measures including scientific assessment of reserves, preparation of rehabilitation and restoration plans, and establishment of regulatory frameworks, the court may relax such limits by raising them to an intermediate level—balancing the legitimate concerns of environmental conservation and intergenerational equity against the changed circumstances and the need for economic development—rather than either maintaining the original limit or accepting complete removal of all restrictions. The principle of sustainable development requires that conservation of ecology and environment proceed in balance with economic development, and this balance must be maintained even when modifying restrictions that were justified by different factual circumstances.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION

IA No. 10973/2018, 83141/2017, 72931/2017 and 218/2014 IN WRIT PETITION (CIVIL) NO. 562 OF 2009

SAMAJ PARIVARTANA SAMUDAYA AND ORS. .....PETITIONERS

VERSUS

STATE OF KARNATAKA AND ORS. ..... RESPONDENTS

ORDER

1. The present hearing is in continuation of our earlier hearing and

order dated 20.05.2022, whereby this Court had considered and

granted certain reliefs relating to the sale and export of iron ore

in the Districts of Bellary, Tumkur and Chitradurga in the State

of Karnataka. In the said order, we had specifically left open the

question of the lifting/relaxation of the ceiling limit for

production of iron ore in the abovementioned Districts and had

sought an opinion from the Oversight Authority appointed by this Signature Not Verified Digitally signed by Rajni Mukhi Date: 2022.08.26 15:11:30 IST

Court vide order dated 21.04.2022. The observations made by Reason:

1

this Court were as follows:

“22….For the present, we propose to confine the scope of this order to examining the twin prayers made by learned counsel for the applicants namely, permission to sell the unsold stock of iron ore already excavated without resorting to the process of eauction conducted through the Monitoring Committee and for lifting the ban on export of iron ore/pellets from the districts of Bellary, Chitradurga and Tumkur situated in the State of Karnataka. Although certain submissions were made by the parties regarding lifting of the ceiling limit for total production of iron ore, at this juncture we are not inclined to decide the said issue.

32. With respect to the submissions of the parties in relation to the lifting of the ceiling limit for production of iron ore for mining leases in the Districts of Bellary, Chitradurga and Tumkur, we are of the considered opinion that it would be expedient to obtain an opinion from the Oversight Authority appointed by this Court vide order dated 21st April, 2022 about the same before deciding the said issue.

We request the Oversight Authority to take inputs from the stakeholders, including the CEC and the Monitoring Committee, and to send his opinion to this Court preferably within a period of 4 weeks.”

2. On the last date of hearing, this Court took on record the Report

filed by the learned Oversight Authority and had directed that

copies of the same be made available to the parties whereafter,

the matter was posted for considering the issue of lifting of ceiling

limit.

3. Heard Mr. Prashant Bhushan, learned counsel appearing on

2 behalf of the original petitioner and Mr. Dushyant Dave, learned

senior counsel appearing on behalf of Federation of Indian

Mineral Industries, South.

4. Mr. Prashant Bhushan submitted that the ceiling limits were

imposed in view of the earlier CEC recommendation and the

report of the learned Lokayukta, which suggested that the rate of

mining of iron ore in the State of Karnataka was unsustainable

and would result in exhaustion of the iron ore deposits in the

State of Karnataka within 30 years. This as per the learned

counsel would seriously impact the goal of inter­generational

equity. Lastly, he submitted that as the learned Oversight

Authority has sought additional information regarding the

infrastructural capacity before giving an opinion as to the

viability of lifting of the ceiling limit, this Court should presently

refrain from passing any orders at this juncture.

5. On the other hand, Mr. Dushyant Dave, Senior Advocate

submitted that the present regime relating to iron ore mining in

the State of Karnataka, with Court imposed ceiling limits, has

been in existence for over a decade. When the ceiling limit was

first imposed, the Court was confronted with a vastly different

3 situation, where there was rampant illegal mining activity taking

place in the State of Karnataka. The said situation has now been

remedied through series of orders passed by this Court. As a

result, all illegal mining in the area has been halted and several

ameliorative measures have been taken for the improvement of

the environment and ecology of the region. In such

circumstances, the learned Senior Advocate submitted that the

present mining lease holders, who are complying with all the

laws, are being unfairly penalized for the illegalities that were

committed a decade ago. Such ceiling limits has resulted in a

discriminatory situation where mining lease holders in the State

of Karnataka are governed by one legal regime, while those in

other States of the country are governed by a completely different

regime.

6. At this juncture, it might be relevant, to highlight the history of

the ceiling limits on production of iron ore through various Court

orders. On 29.07.2011 and 26.08.2011, this Court had imposed

a ban on mining in the districts of Bellary, and Chitradurga and

Tumkur, respectively based on the report of the Centrally

Empowered Committee (‘CEC’).

4

7. On 13.04.2012, this Court had accepted some of the

recommendations contained in the Report dated 13.03.2012 of

the CEC, including the following recommendation:

“B) a ceiling of 25 Million Metric Tonnes (MMT) for total production of iron ore from all the mining leases in District Bellary may be prescribed. A ceiling of 5 MMT for production of iron ore from all the mining leases in Districts Chitradurga and Tumkur together may be prescribed” (emphasis supplied)

8. The above position was reiterated by this Court vide judgment

dated 18.04.2013, wherein the underlying set of petitions were

disposed.

9. Vide judgment dated 14.12.2017, while dealing with certain

applications seeking enhancement/lifting of ceiling cap. This

court had permitted to increase the same from 25 MMT to 28

MMT with respect to Bellary District, and from 5 MMT to 7 MMT

for Chitradurga and Tumkur Districts collectively, based on a

fresh report of the CEC dated 14.07.2017. Certain observations

made by this Court for granting the relaxation merit reiteration:

“16. The cap fixed by this Court by Orders dated 5.08.2011 and 1.09.2014 was in a situation where there was virtually no control or effective regulatory measures as to the maximum output that could be generated by a particular mine.

There was no scientific study of the iron ore reserves allocated to a particular mine in the

5 lease granted. As a result, it was virtually a free for all exercise designed to achieve the maximum profit within the shortest possible time frame. There was rampant and illegal mining with encroachments into forest land, particularly for use as overburdened dumps resulting from excessive mining. This had led to environmental and ecological depredation to an extent that necessitated judicial intervention to resolve a situation which is the normal course may have fallen within the executive domain. It is on the basis of the intervention by the Court that R&R Plans have been prepared for each mine by an expert body, ICFRE, based on a scientific study of various parameters including mining reserves. R&R Plans have been drawn up specifying a particular/permissible limit for each mine on the basis of limitations of reserves, dumping areas, available infrastructure etc. Accordingly, recommendations have been made for increase of MPAP for 13 different category ‘A’ mines and also for increase of MPAP in respect of 2 leases held by the public sector lessee, i.e., NMDC. Similarly, 10 mines are anticipated to undertake operations within a short time….The solution offered by the Court has to be realistic. Therefore, it is the various features of the current scenario on the ground as highlighted in the report of the CEC that would deserve a close look/consideration. In this regard, we may also take note of the fact that the assessment of reserves has also changed over the years and today the iron­ore reserves across the State of Karnataka, comprising of haematite and magnetite reserves, is to the tune of 10.071 BMT (Billion Metric Tonnes). All these reasons impel us to accept the recommendations of the CEC for enhancement of the cap for category A and B Mines in the 3 district of Bellary, Tumkur and Chitradurga as well as the recommendations with regard to MPAP of NMDC and MML, as mentioned in paragraph 12

6 hereinabove, with the further direction that all pending proposals for enhancement of MPAP shall be decided without delay, naturally, subject to the cap as above.” (emphasis supplied)

10. It is in light of the above set of facts that the submissions made

by learned counsel ought to be considered. In 2017, this court

was of the view that the situation had vastly changed in the State

of Karnataka and had therefore allowed an increase in the ceiling

limit. We are now in the year 2022. It can be no one’s case that

the situation subsisting in the State of Karnataka currently, is

the same as had existed when the underlying petition was first

taken up, or when the Court had passed the order in 2017,

relaxing the ceiling limit to some extent.

11. This is also clear from the changed stance of the State of

Karnataka and the CEC before this Court. In 2017, the CEC had

recommended a cumulative increase in the ceiling limit up to 5

MMT, whereas now, the CEC supports the view that the ceiling

limit need not to continue. The State of Karnataka, in 2017, had

submitted before this Court that the ceiling limit may be raised to

40 MMT, and gradually increased later to 50 MMT. However, the

State of Karnataka is now in favor of a complete removal of the

7 ceiling limit.

12. In fact, it appears that the CEC, the State of Karnataka, the

Ministry of Steel, Union of India, Karnataka Iron and Steel

Manufacturers Association (‘KISMA’) and the mining lease

holders are all ad idem that the changed situation on ground

warrants a complete removal of the ceiling limits that were

imposed by this Court to ensure protection of the environment

and keeping in mind the principles governing intergenerational

equity. The response dated 10.04.2022 of the CEC (viz. CEC

Report No. 3 of 2022) on the issue of lifting of ceiling limits merits

reproduction and is extracted herein below:

“17. This Hon’ble Court by orders dated 05.08.2011 and 01.09.2014 had fixed a production cap of 25 MMT in respect of District Bellary and 5 MMT in respect of Districts Chitradurga and Tumkur. This Hon’ble Court by Judgement dated 14.12.2017 enhanced the production cap to 28 MMT in respect of District Bellary and 7 MMT for Districts Chitradurga and Tumkur.

The availability of iron ore as approved in the R&R plans currently exceeds the limit of 35 MMT per annum fixed by this Hon’ble Court. As per the latest data furnished by the Monitoring Committee, currently 34 category ‘A’ and ‘B’ mining leases are in operation with an approved MPAP of 36.31 MMT. An Additional 9 Category “C” mining leases and 4 Category “A”

8 and “B” expired leases, which were e­auctioned, are operational with MPAP of 5.54 MMT and 2.41 MMT respectively. Another 4 mining leases located in Districts Bagalkote and Davanagere have production capacity of 6.29 lakh MT per annum and 60000 MT per annum respectively. The production of iron ore in these two Districts is not affected by the orders of this Hon’ble Court. The sum of approved annual production capacity of iron ore in Karnataka as on 31 . 03.2022 adds upto 44.949 MMT. In addition, there are 5 Category “C” and 2 expired Category “A” & “B” mines which have been e­auctioned by the state but the execution of lease agreements are pending in respect of these 7 mines as on 31.3.2022.

… …

23. Keeping in view the facts highlighted in the preceding paragraphs, it is for consideration of this Hon’ble Court whether the restrictions on production and sale of the iron ore in the three Districts Bellary, Chitradurga and Tumkur imposed following the total ban on mining are required to be reviewed and if agreed upon by this Hon’ble Court the following may please be considered

(i) Vacation of the orders of this Hon’ble Court directing sale of iron ore through e­ auction conducted by the Monitoring Committee, and which ore has been produced by the lessees after resumption of mining operation. However, the sale of balance old stock of iron ore, including sub­grade iron ore available on the date of imposition of ban on mining be continued through e­auction. The Monitoring Committee be directed to dispose all the

9 balance old stock through e­auction before 31st July 2022. If any stock over which the lessee has the ownership right is left unsold the lessee may be allowed to dispose of it.

(ii) The collection of 10 per cent of the sale value from all the lessee except NMDC and 20% of sale value from NMDC towards their contribution to the SPV may be discontinued.

(iii) Vacation of the orders on total ban on export of iron ore and pellets from the districts of Bellary, Chitradurga and Tumkur.

(iv) Vacation of the orders on fixing district level caps on production of iron ore in respect of Category ‘A’ and Category ‘B’ mines from the financial year 2022­2023.

24. However the system of determination of the Maximum Permissible Annual Production (MPAP) being fixed through the R&R Plans and Supplementary Environment Plans, after ensuring the scientific and sustainable mining and after taking into account the mining reserves available within the lease area and after following the standards stipulated under various environmental and mining statutes, as approved in order dated 13.4.2012 and judgement dated 18.4.2013 of this Hon’ble Court, may continue. All mining leases to operate strictly adhering to such MPAP, as may be fixed /refixed.”

13. The Monitoring Committee, without directly alluding to the issues

10 raised by the others with respect to why the ceiling limit should

be maintained or lifted, has highlighted a separate concern, viz.,

the infrastructural incapacity to transport the iron ore excavated

if the ceiling limits were to be raised. It is in this context that the

learned Oversight Authority appointed by this Court expressed

his inability to conclude on the said issue. The learned Oversight

Authority, in his report dated 29.07.2022, observed as follows:

The Oversight Authority as at present in unable to express its firm opinion in the matter in view of the conflicting reports submitted by Central Empowered Committee and the Monitoring Committee. It is not for the Oversight Authority to express any opinion as to whether the Monitoring Committee has exceeded its brief in joining an issue with Central Empowered Committee by pleading for continuation of the ceiling limit. Be it as it may, it is just and necessary to gather some further evidence in the matter of ‘current available road infrastructure’, ‘existing as well as improvements made to transport infrastructure’. There is no evidence as such made available for the perusal of the Oversight Authority as to what are the developments that have taken place between today and 20.05.2022 i.e. when the Hon’ble Supreme Court of India passed the Orders referred to hereinabove.

14. Mr. Prashant Bhushan, learned counsel appearing on behalf of

the original petitioner, is therefore the sole objector to the request

11 of lifting of the ceiling limit, on principles. The motivating concern

behind the objection appears to be the anxiety that lifting of the

ceiling limit may spiral into the same situation that had resulted

in this Court’s judicial intervention in the first place. Learned

counsel submitted that such an order of lifting the ceiling limit

might lead to unmitigated mining activity in the State of

Karnataka, setting the clock back entirely and resulting in

regression of the entire state of affairs.

15. The concerns of the original petitioner and the Monitoring

Committee merit due consideration of this Court. Much good

work has been done in the State of Karnataka, because of the

action initiated by the original petitioner and the subsequent

judicial interventions by this Court. In fact, it is this progress

made steadily over the past decade that weighed with this Court

to even consider the relief regarding raising of the ceiling limit

sought by the present applicants. The concerns raised by the

original petitioner, of possible over excavation and its adverse

impact on intergenerational equity, must be balanced against the

concerns of the other parties, as the principles of sustainable

development also comes into play.

12

16. This Court has generally accepted the recommendations of the

CEC when it comes to the ceiling limit. In the present case, the

CEC has recommended a complete relaxation of the ceiling limit.

But we are not inclined to allow the same in toto. Rather, the

situation merits a cautious approach, keeping in view the

concerns raised and to ensure that any changes in the situation

with respect to the mining activity in the State of Karnataka is

brought about gradually, we are of the opinion that the ceiling

limit of iron ore mining may be raised from 28 MMT to 35 MMT

for District Bellary, and from 7 MMT to 15 MMT for Chitradurga

and Tumkur Districts collectively.

17. Conservation of the ecology and the environment must go hand

in hand with the spirit of economic development and the fine

balance between the two goals is what is sought to be achieved

even now.

18. IA Nos. 83141/2017, 72931/2017 and 218/2014 are disposed of

on the above terms. As far as IA No. 10973/2018 is concerned,

13 the same relates to directions to the CEC and Monitoring

Committee regarding deciding applications for enhancement of

MPAP in terms of the earlier orders of this Court. The same may

be considered by the Court on the next date of hearing.

...........................CJI.

(N.V. RAMANA)

…...........................J. (HIMA KOHLI)

…...........................J. (C.T. RAVIKUMAR) NEW DELHI;

AUGUST 26, 2022.

14

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free