Miss Lucy
← All judgments

Renew Power Limited vs Bangalore Electricity Supply Company Ltd

Karnataka High Court13 March 2019S.Sujatha

Ratio decidendi

The rule this decision rests on

The statutory exemption from wheeling and banking charges granted by the Karnataka Electricity Regulatory Commission to renewable energy projects commissioned before 31 March 2018 for a ten-year period cannot be withdrawn or modified by the Commission through an executive order prior to completion of that ten-year term where the exemption formed the basis of the regulated entities' investment decisions, absent an overriding public interest and a proper regulation made under Section 181 of the Electricity Act, 2003 with requisite legislative procedure. Where a State through its regulatory instrumentality has made clear representations and assurances to investors that they will receive concessional charges (including exemption from wheeling and banking charges) for a specified period, those entities may invoke the doctrine of promissory estoppel against the State to prevent withdrawal of such concessions before the promised period expires, provided the entities have relied on those representations by making substantial investments and cannot be restored to their prior position without loss. The sub-classification of renewable energy projects into those commissioned on or before 31 March 2017 and those commissioned after that date, while withdrawing benefits from the latter group, constitutes arbitrary discrimination violating Article 14 of the Constitution where all projects within the control period 1 April 2013 to 31 March 2018 were originally treated as a homogeneous class and where such sub-classification lacks any intelligible differentia rationally connected to the legislative objective. While the Electricity Act, 2003 confers power on the Commission to determine tariff "from time to time" under Section 62, where a settled statutory contract has been executed between the regulated entities and the Commission based on a prior tariff order, and where no party to the contract has requested modification, the power to revisit tariff can only be exercised prospectively through a fresh regulation under Section 181 and not through an executive order, as a regulation has general application and can override existing contracts whereas an order is specific. Writ petitions challenging orders of a specialized tribunal such as a regulatory commission remain maintainable under Article 226 notwithstanding the availability of an alternative statutory appeal remedy where the order is alleged to be without jurisdiction, violative of natural justice, arbitrary and capricious, or violative of fundamental constitutional rights.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

RIN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 13TH DAY OF MARCH, 2019
BEFORE
THE HON'BLE MRS.JUSTICE S.SUJATHA
W.P.Nos.23158 - 23162/2018 & 23449 - 23457/2018,C/WW.P.No.22838/2018, W.P.Nos.22841 - 22842/2018W.P.Nos.23069 - 23070/2018,W.P.Nos.23078 & 23119/2018,W.P.Nos.23080 & 23118/2018,W.P.No.23085/2018,W.P.Nos.23086 & 23116/2018,W.P.Nos.23108 - 23109/2018,W.P.No.23242/2018, W.P.No.23696/2018,W.P.No.23700/2018, W.P.No.23851/2018,W.P.Nos.23990 - 23995/2018,W.P.Nos.24248 - 24259/2018,W.P.No.25090/2018, W.P.No.26480/2018,W.P.No.28622/2018, W.P.No.53531/2018 ANDW.P.No.39329/2018 (GM - KEB)
IN W.P.Nos.23158 - 23162/2018 & 23449 - 23457/2018:
BETWEEN :
1. RENEW POWER LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT 138, ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP. BY ITS MANAGER.
2. RENEW SAUR URJA PRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTERED-2-
OFFICE AT 138, ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP BY ITS MANAGER.
3. RENEW WIND ENERGY (BUDH 3)PRIVATE LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITSREGISTERED OFFICE AT 138,ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP BY ITS MANAGER.
4. RENEW SAUR VIDYUT PRIVATE LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT 138, ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP. BY ITS MANAGER.
5. RENEW WIND ENERGY (KARNATAKA)PRIVATE LTD., A COMPANY REGISTEREDUNDER THE PROVISIONS OF THECOMPANIES ACT, 2013 HAVING ITSREGISTERED OFFICE AT 138,ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP. BY ITS MANAGER.
6. RENEW WIND ENERGY (AP) PRIVATE LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT 138, ANSAL CHAMBERS-II,BHIKAJI CAMA PLACE, DELHI-110066REP. BY ITS MANAGER.
7. CLEAN MAX ENVIRO ENERGYSOLUTIONS PRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTERED-3-
OFFICE AT 33, ASHOKA APTS,RUNGTA LANE, NEPEAN SEA ROAD,MUMBAI-400006REP BY ITS HEAD, BUSINESSDEVELOPMENT (SOUTH INDIA)
8. CLEAN MAX POWER PROJECTSPRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT 16, 1ST FLOOR,PRABHADEVI INDUSTRIAL ESTATE,VEER SAVARKAR ROAD,PRABHADEVI, MUMBAI-400025REP. BY ITS HEAD, BUSINESSDEVELOPMENT (SOUTH INDIA)
9. CLEANMAX IPP2 PRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT 13 A, FLOOR-13,PLOT-400, THE PEREGRINE APARTMENT,KISMAT CINEMA, PRABHADEVI,MUMBAI 400025REP. BY ITS HEAD, BUSINESSDEVELOPMENT (SOUTH INDIA)
10. CLEAN MAX MERCURY POWERPRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT 13 A, FLOOR-13,PLOT-400, THE PEREGRINE APARTMENT,KISMAT CINEMA, PRABHADEVI,MUMBAI-400025REP. BY ITS HEAD, BUSINESSDEVELOPMENT (SOUTH INDIA)
11. CLEAN MAX PHOTOVOLTAICPRIVATE LIMITEDA COMPANY REGISTERED UNDER-4-
THE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT 13 A, FLOOR-13,PLOT-400, THE PEREGRINE APARTMENT,KISMAT CINEMA, PRABHADEVI,MUMBAI-400025REP. BY ITS HEAD, BUSINESSDEVELOPMENT (SOUTH INDIA)
12. RFE BELGAUM SOLARPRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013 HAVING ITS REGISTEREDOFFICE AT D-43, JANPATH,SHYAM NAGAR, JAIPUR,RAJASTHAN-302019REP. BY ITS DIRECTOR
13. AMP SOLAR SOLUTIONPRIVATE LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF THECOMPANIES ACT, 2013HAVING ITS REGISTEREDOFFICE AT 309, THIRD FLOOR,RECTANGLE ONE,BEHIND SHERATON HOTEL,SAKET, NEW DELHI - 110017REP. BY ITS DIRECTOR
14. BAGMANE GREEN POWER LLPA LIMITED LIABILITY PARTNERSHIPINCORPORATED UNDER THE PROVISIONSOF THE LIMITED LIABILITY PARTNERSHIPACT, 2008 HAVING ITS REGISTEREDOFFICE AT A BLOCK, 8TH FLOOR,LAKE VIEW BUILDING,BAGMANE TECH PARK,C V RAMAN NAGAR,BENGALURU-560093. ...PETITIONERS
(BY SRI ADITYA SONDHI, SENIOR ADV. FORSRI KUSUM RANGANATH, ADV.)-5-
AND :
1. BANGALORE ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT K.R. CIRCLE, BENGALURU-560001(REP BY ITS MANAGING DIRECTOR)
2. CHAMUNDESHWARI ELECTRICITYSUPPLY CORPORATION LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT NO.29,KAVERI GRAMEENA BANK ROAD,HINKAL, VIJAYANAGAR 2ND STAGE,MYSURU-570019(REP BY ITS MANAGING DIRECTOR)
3. MANGALORE ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT MESCOM BHAVANA,KAVOOR CROSS ROAD, BEJAI,MANGALURU-570004(REP BY ITS MANAGING DIRECTOR)
4. HUBLI ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT P.B. ROAD,NAVANAGAR, HUBBALI-580025(REP. BY ITS MANAGING DIRECTOR)
5. GULBARGA ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDER-6-
THE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALABURAGI - 585101(REP BY ITS MANAGING DIRECTOR)
6. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN,K.G.ROAD, BENGALURU-560009(REP BY ITS MANAGING DIRECTOR)
7. KARNATAKA ELECTRICITYREGULATORY COMMISSIONNO.16, C-1, MILLERS TANK BED AREA,VASANTH NAGAR,BENGALURU - 560052 ...RESPONDENTS
(BY SRI SHAHBAAZ HUSSAIN, ADV. FOR R-1;SRI S.S.NAGANAND, SENIOR ADV. FORSRI S.SRIRANGA, ADV. FOR R-2 & R-5;SMT.M.C.NAGASHREE, ADV. FOR R-3;SRI MURUGESH V. CHARATI, ADV. FOR R-4;SRI H.V.DEVARAJU, ADV. FOR R-6;SRI B.N.PRAKASH, ADV. FOR M/s LAWYER INC. FOR R-7.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER, DATED 14.05.2018, PASSEDBY THE RESPONDENT NO.7 (PRODUCED HEREIN ASANNEXURE AC).
IN W.P.No.22838/2018:
BETWEEN :
AVAADA SUSTAINABLE ENERGYPRIVATE LIMITED (KERC)HAVING ITS CORPORATE OFFICE AT:3RD FLOOR, PTI BUILDING,-7-
4, PARLIAMENT STREET,NEW DELHI - 110001.(REP. THROUGH ITS AUTHORIZED SIGNATORYMr. PRABHAT KUMAR.
HAVING ITS REGISTERED OFFICE AT:HUBTOWN, SOLARIS, 4TH FLOOR,406, N.S. PHADKE MARG,ANDHERI, MUMBAI - 400069.MAHARASHTRA. ...PETITIONER
(BY SRI PRABHULING K. NAVADGI, SENIOR ADV. FORSRI RAJESHWARA P.N., ADV.)
AND :
1. STATE OF KARNATAKATHROUGH ITS DEPUTY SECRETARY,ENERGY DEPARTMENT,VIKASA SOUDHA,BENGALURU-01.
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)REP. THROUGH ITS SECRETARY,AT NO.16, C-1, MILLERS TANK BED AREA,VASANTH NAGAR,BENGALURU - 560052KARNATAKA.
3. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL),A COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,HAVING ITS REGISTERED OFFICE AT:KAVERI BHAWAN, KEMPEGOWDA ROAD,BANGALORE - 560009, KARNATAKA.
4. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,-8-
HAVING ITS REGISTERED OFFICE AT:KR. CIRCLE, BANGALORE-560001,KARNATAKA.
5. MANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (MESCOM)A COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,HAVING ITS REGISTERED OFFICE AT:PARADIGM PLAZA,A B SHETTY CIRCLE,MANGALORE- 575001, KARNATAKA.
6. CHAMUNDESHWARI ELECTRICITY SUPPLYCORPORATION LIMITED (CESC, MYSORE)A COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,HAVING ITS REGISTERED OFFICE AT:NO.29, VIJAYANAGARA 2ND STAGE,HINAKAL, MYSORE-570017
7. GULLBARGA ELECTRICITYSUPPLY COMPANY LIMITEDA COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,HAVING ITS REGISTERED OFFICE AT:STATION ROAD, KALABURAGI - 585102KARNATAKA.
8. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITEDA COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTOR,HAVING ITS REGISTERED OFFICE AT:NAVANAGAR, HUBLI-580025KARNATAKA. ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;-9-
SRI S.S.NAGANAND, SENIOR ADV. FOR SRI S.SRIRANGA,ADV.FOR R-3, R-4 & R-7;SRI MURUGESH V. CHARATI, ADV. FOR R-8;R-5 & R-6 ARE SERVED, BUT UNREPRESENTED.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASHIMPUGNED ORDER DATED 14.05.2018 (ANNEXURE-A) PASSEDBY RESPONDENT NO.2 COMMISSION IN SO FAR AS PETITIONERIS CONCERNED.
IN W.P.Nos.22841 - 22842/2018:
BETWEEN :
1. M/s EMBASSY ENERGY PVT. LTD.,A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 2013,HAVING ITS REGISTERED OFFICEAT 1ST FLOOR, EMBASSY POINT,NO.150, INFANTRY ROAD,BANGALORE-560001REP. BY ITS AUTHORISED SIGNATORYMr. P.R.RAMA KRISHNAN.
2. PRADEEP NENUMAL LALAS/O NENUMAL LALA,AGED ABOUT 55 YEARS,R/AT OCEAN VIEW,ABDUL GAFFAR KHAN ROAD,WORLI, MUMBAI-400018. ...PETITIONERS
(BY SRI N.VENKATARAMAN, SENIOR COUNSEL FORSRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT (ENERGY DEPARTMENT)VIKASA SOUDHA,BANGALORE-560001.- 10 -
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHNAGAR, BANGALORE-560052.(REP. BY ITS CHAIRMAN)
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R.CIRCLE,BENGALURU-560001.(REP BY ITS MANAGING DIRECTOR)
4. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITED (GESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALABURAGI-585101(REP. BY ITS MANAGING DIRECTOR)
5. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMAPNY REGISTRED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN,K.G.ROAD, BENGALURU-560009.(REP. BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR M/s LAWYERS INC. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3;SRI MURUGESH V. CHARATI, ADV. FOR R-4;SMT.M.C.NAGASHREE, ADV. FOR R-5.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14.05.2018 PASSED BYTHE 2ND RESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.- 11 -
IN W.P.Nos.23069 - 23070/2018:
BETWEEN :
1. INR ENERGY VENTURESAS PARTNERSKHIP FIRM REGISTEREDUNDER THE PARTNERSHIP ACT, 1932,HAVING ITS REGISTERED OFFICE AT:"THE FALCON HOUE", NO.1,MAIN GUARD CROSS ROAD,BANGALORE-560001. KARNATAKA,REP. BY ITS AUTHORISED SIGNATORY,Ms. KHIZRA ATIQUE BANDUKWALA
2. Mr. VENKATA NARAYANA KONANKIS/O VENKATAIAH KONANKI,AGED ABOUT 38 YEARS,R/AT 2011, EMBASSY HABITAT,PALACE CROSS ROAD,VASANTH NAGAR,BANGALORE-560052, KARNATAKA ...PETITIONERS
(BY SRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARY TOGOVERNMENT (ENERGY DEPARTMENT)VIKASA SOUDHA, BANGALORE-560001.
2. KARNATAKA ELECTRICITY REGULATORYCOMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHNAGAR,BANGALORE-560052.(REP. BY ITS CHAIRMAN)
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTERED- 12 -
OFFICE AT K.R.CIRCLE,BENGALURU-560001.(REP. BY ITS MANAGING DIRECTOR)
4. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITED (GESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALBURAGI-585101(REP. BY ITS MANAGING DIRECTOR)
5. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITSREGISTERED OFFICE ATKAVERI BHAVAN, K.G. ROAD,BENGALURU-560009,REP. BY ITS MANAGING DIRECTOR. ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-5;SRI NIKHILESH RAO, ADV. FOR R-5.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14.05.2018 PASSED BYTHE 2ND RESPONDENT - KARNATAKA ELECTRICITYREGULATORY COMMISSION, BENGALURU, VIDE ANNEXURE-A.
IN W.P.Nos.23078 & 23119/2018:
BETWEEN :
1. M/s MAMADAPUR SOLAR PRIVATE LTD.,A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 2013,HAVING ITS REGISTERED OFFICE AT:- 13 -
D-43, 2ND FLOOR, JANPATH,SHYAM NAGAR, SODALA,JAIPUR, RAJASTHAN - 302019.REP. BY ITS AUTHORISED SIGNATORYMrs. KHIZRA ATIQUE BANDUKWALA
2. Mr. VENKATA NARAYANA KONANKIS/O VENKATAIAH KONANKI,AGED ABOUT 38 YEARSR/AT 2011, EMBASSY HABITAT,PALACE CROSS ROAD,VASANTH NAGAR,BANGALORE - 560052KARNATAKA. ...PETITIONERS
(BY SRI N.VENKATARAMAN, SENIOR ADV. FORSRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT (ENERGY DEPARTMENT),VIKASA SOUDHA, BANGALORE - 560001.
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHNAGAR, BANGALORE - 560052.(REP. BY ITS CHAIRMAN),
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R. CIRCLE,BENGALURU - 560001(REP. BY ITS MANAGING DIRECTOR)
4. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITED (HESCOM),A COMPANY REGISTERED UNDER THE- 14 -
PROVISIONS OF COMPANIES ACT, 1956,HAVING ITS REGISTERED OFFICE ATP.B. ROAD, NAVANAGAR,HUBBALI - 580025.(REP. BY ITS MANAGING DIRECTOR)
5. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL),A COMPANY REGISTERED UNDER THEPROVISIONS OF COMPANIES ACT, 1956,HAVING ITS REGISTERED OFFICE ATKAVERI BHAVAN, K.G. ROAD,BENGALURU - 560009.(REP. BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3;SMT.M.C.NAGASHREE, ADV. FOR R-5.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14.05.2018 PASSED BYTHE 2ND RESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.
IN W.P.Nos.23080 & 23118/2018:
BETWEEN :
1. M/s BELGAUM SOLAR POWERPRIVATE LTD.,A COMPANY INCORPORATEDUNDER THE COMPANIES ACT, 2013,HAVING ITS REGISTERED OFFICE AT:D-43, 2ND FLOOR, JANPATH,SHYAM NAGAR, SODALA,JAIPUR, RAJASTHAN-302019REP. BY ITS AUTHORIZED SIGNATORY,Mrs. KHIZRA ATIQUE BANDUKWALA
2. Mr. VENKATA NARAYANA KONANKIS/O VENKATAIAH KONANKI,- 15 -
AGED ABOUT 38 YEARS,R/AT NO.2011,EMBASSY HABITAT,PALACE CROSS ROAD,VASANTH NAGAR,BANGALORE-560052KARNATAKA ...PETITIONERS
(BY SRI N.VENKATARAMAN, SENIOR ADV. FORSRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT (ENERGY DEPARTMENT),VIKASA SOUDHA, BANGALORE - 560001.
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHNAGAR, BANGALORE - 560052.(REP. BY ITS CHAIRMAN),
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R. CIRCLE,BENGALURU - 560001(REP. BY ITS MANAGING DIRECTOR)
4. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITED (HESCOM),A COMPANY REGISTERED UNDER THEPROVISIONS OF COMPANIES ACT, 1956,HAVING ITS REGISTERED OFFICE ATP.B. ROAD, NAVANAGAR,HUBBALI - 580025.(REP. BY ITS MANAGING DIRECTOR)- 16 -
5. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL),A COMPANY REGISTERED UNDER THEPROVISIONS OF COMPANIES ACT, 1956,HAVING ITS REGISTERED OFFICE ATKAVERI BHAVAN, K.G. ROAD,BENGALURU - 560009.(REP. BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-5;SRI MURUGESH V. CHARATI, ADV. FOR R-4;SMT.M.C.NAGASHREE, ADV. FOR R-5.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14.05.2018 PASSED BYTHE 2ND RESPONDENT-KARNATAKA ELECTRICITYREGULATORY COMMISSION, BENGALURU, VIDE ANNEXURE-A;
IN W.P.No.23085/2018:
BETWEEN :
BELGAUM RENEWABLE ENERGYPRIVATE LIMITED (BREPL)HAVING ITS CORPORATE OFFICE ATE-5, DEFENCE COLONYNEW DELHI - 110 024(REP. THROUGH ITS AUTHORIZED SIGNATORYMr. ADITYA AGARWAL)HAVING ITS REGISTERED OFFICE ATD-43, JANPATH, SHYAM NAGARJAIPUR, RAJASTHAN - 302019. ...PETITIONER
(BY SRI PRABHULING K. NAVADGI, SENIOR ADV. FORSRI RAJESWARA P.N., ADV.)
AND :
1. STATE OF KARNATAKATHROUGH ITS DEPUTY SECRETARY,ENERGY DEPARTMENT,- 17 -
VIKASA SOUDHABENGALURU-560001.
2. KARNATAKA ELECTRICITY REGULATORYCOMMISSION (KERC)REP THROUGH ITS SECRETARYAT NO.16, C-1, MILLERS TANK BED AREA,VASANTH NAGAR, BENGALURU - 560 052KARNATAKA.
3. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTORHAVING ITS REGISTERED OFFICE ATKAVERI BHAWAN, KEMPEGOWDA ROAD,BANGALORE - 560 009, KARNATAKA.
4. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956,REP. THROUGH ITS MANAGING DIRECTORHAVING ITS REGISTERED OFFICE ATK.R. CIRCLE, BANGALOREKARNATAKA - 560 001.
5. MANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (MESCOM)A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956REP. THROUGH ITS MANAGING DIRECTORHAVING ITS REGISTERED OFFICE ATPARADIGM PLAZA, A B SHETTY CIRCLE,MANGALORE, KARNATAKA - 575 001.
6. CHAMUNDESHWARI ELECTRICITY SUPPLYCORPORATION LIMITED (CESC, MYSORE)A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956REP THROUGH ITS MANAGING DIRECTOR- 18 -
HAVING ITS REGISTERED OFFICE ATNO.29, VIJAYANAGARA 2ND STAGE,HINAKAL, MYSURU-570017, KARNATAKA.
7. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITEDA COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956REP THROUGH ITS MANAGING DIRECTORHAVING ITS REGISTERED OFFICE ATSTATION ROAD, KALABURAGI - 585 102KARNATAKA.
8. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITEDA COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 1956REP THROUGH ITS MANAGING DIRECTORHAVING ITS REGISTERED OFFICE ATNAVANAGAR, HUBBALLIKARNATAKA - 580025. ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-4;SRI S.S.NAGANAND, SENIOR ADV. FOR SRI S.SRIRANGA, ADV.FOR R-5, R-6 & R-8;SRI MURUGESH V. CHARATI, ADV. FOR R-7.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASHIMPUGNED ORDER DATED 14.05.2018 (ANNEXURE-A) PASSEDBY RESPONDENT NO.2 COMMISSION IN SO FAR AS PETITIONERIS CONCERNED.
IN W.P.Nos.23086 & 23116/2018:
BETWEEN :
1. MATRIX POWER (WIND) PRIVATE LIMITEDHAVING ITS REGD. OFFICE AT#8-2-277/12, MCH NO.296, ROAD NO.3,UBI COLONY, BANJARA HILLS- 19 -
HYDERABAD-500 034REP BY ITS AUTHORISEDSIGNATORY Mr. SHARAN B.
2. MATRIX GREEN ENERGY PRIVATE LIMITEDHAVING ITS REGD. OFFICE AT# 8-2-277/12, MCH NO.296,ROAD NO.3, UBI COLONY,BANJARA HILLS,HYDERABAD-500 034,REP BY ITS AUTHORISEDREP. Mr. NAVEEN KUMAR ...PETITIONERS
(BY SRI PRABHULING K. NAVADGI, SENIOR ADV. FORSRI RAJESWARA P.N., ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSION37, M.G. ROAD, YELLAPPA GARDEN,YELLAPPA CHETTY LAYOUT, ULSOOR,BENGALURU, KARNATAKA-560 001REP. BY ITS MANAGING DIRECTOR.
2. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,KAVERI BHAVAN, K.G. ROAD,BENGALURU-560 009REP. BY ITS MANAGING DIRECTOR.
3. BENGALURU ELECTRICITY SUPPLYCOMPANY LTD., K.R. ROAD,BENGALURU-560 001REP. BY ITS MANAGING DIRECTOR.
4. HUBALLI ELECTRICITY SUPPLYCOMPANY LTD.,PB ROAD, DURGAD BAIL,NAVANAGAR, HUBBALLI-580 025KARNATAKAREP. BY ITS MANAGING DIRECTOR.- 20 -
5. GULBARGA ELECTRICITY SUPPLYCOMPANY LTD.,48, SUPER MARKET MAIN ROAD,HALBARGA, BRHAMPURKALABURAGI, KARNATAKA-585 10REP. BY ITS MANAGING DIRECTOR. ...RESPONDENTS
(BY SRI SHAHBAAZ HUSSAIN, ADV. FOR R-2 & R-3;R-1 SERVED, BUT UNREPRESENTED.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH IMPUGNED ORDER DATED 14.05.2018 (ANNEXURE-A)PASSED BY RESPONDENT NO.1 COMMISSION IN SO FAR ASPETITIONER IS CONCERNED.
IN W.P.Nos.23108 - 23109/2018:
BETWEEN :
1. M/s ATRIA SOLAR POWER(CHAMARAJANAGAR) PVT. LTD.,A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 2013,HAVING ITS REGISTERED OFFICE ATNO.11, 1ST FLOOR, COMMISSARIAT ROAD,BANGALORE - 560 027(REP. BY ITS AUTHORISED REPRESENTATIVEMr. ANAND LAHOTI)
2. Mr. C.S. SUNDER RAJUS/O LATE CHINNASWAMY RAJUAGED ABOUT 60 YEARS,R/AT 294, UPPER PALACE ORCHARDSSADASHIVANAGARBANGALORE. ...PETITIONERS
(BY SRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARY- 21 -
TO GOVERNMENT (ENERGY DEPARTMENT)VIKASA SOUDHA,BANGALORE - 560 001.
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHANAGAR, BANGALORE - 560 052.(REP. BY ITS CHAIRMAN)
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R.CIRCLEBENGALURU - 560 001(REP BY ITS MANAGING DIRECTOR)
4. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITED (GESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALABURAGI - 585 101(REP. BY ITS MANAGING DIRECTOR)
5. CHAMUNDESHWARI ELECTRICITY SUPPLYCORPORATION LIMITED (CESC)NO. 29, VIJAYANAGARA 2ND STGEHINKAL, MYSORE - 570 017(REP. BY IS MANAGING DIRECTOR)
6. HUBLI ELECTRICITY SUPPLYCORPORATION LIMITED (HESCOM)CORPORATE OFFICEP.B.ROAD, NAVANAGARHUBBALLI - 580 025(REP BY ITS MANAGING DIRECTOR)
7. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMPANY REGISTERED UNDER- 22 -
THE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN, K.G.ROAD,BENGALURU - 560 009(REP. BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI, AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3;SRI MURUGESH V. CHARATI, ADV. FOR R-4 & R-6;SRI S.SRIRANGA, ADV. FOR R-5;SMT.M.C.NAGASHREE, ADV. FOR R-7.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14.05.2018 PASSED BYTHE 2ND RESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.
IN W.P.No.23242/2018:
BETWEEN :
M/s KUSHTAGI SOLARPOWER PRIVATE LTD.,A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 2013,HAVING ITS REGISTERED OFFICEAT No.29, HARE KRISHNA REGENCY,RAMAPURA ROAD SUKHIYA,SANGANER, JAIPUR-302011,RAJASTHAN,REP BY ITS AUTHORISED SIGNATORY,Mr. KESA VIKRAM ...PETITIONER
(BY SRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT,- 23 -
(ENERGY DEPARTMENT),VIKASA SOUDHA,BANGALORE-560001
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.6, C-1, MILLERS TANK BED AREA,VASANTHANAGAR, BANGALORE-560052.REP BY ITS CHAIRMAN
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R. CIRCLE,BENGALURU-560001(REP BY MANAGING DIRECTOR)
4. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITED (HESCOM),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT P.B. ROAD, NAVANAGAR,HUBBALI-580025(REP BY MANAGING DIRECTOR)
5. KARNATAKA POWER TRANSMISSIONSCORPORATION LIMITED ( KPTCL),A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN,KG ROAD, BENGALURU-560009(REP. BY MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-5;SRI MURUGESH V. CHARATI, ADV. FOR R-4..)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE- 24 -
IMPUGNED ORDER DATED 14.05.2018 PASSED BY THE 2NDRESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.
IN W.P.No.23696/2018:
BETWEEN :
M/s EASTMAN INTERNATIONAL(A PARTNERSHIP FIRM REGISTEREDUNDER THE PROVISIONS OF INDIANPARTNERSHIP ACT, 1932)HAVING ITS REGISTERED OFFICE ATB-XXX 2185/C-203/1PHASE VII, FOCAL POINT,LUDHIANA-141010, PUNJAB(REP. BY ITS AUTHORIZED SIGNATORY)Mr. TARAK PRAKASH TRIVEDI. ...PETITIONER
(BY SRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP. BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT (ENERGY DEPARTMENT)VIKASA SOUDHA, BANGALORE-560001
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREA,VASANTHANAGAR, BANGALORE-560052(REP BY ITS CHAIRMAN)
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY REGISTERED UNDERTHE PROVISION OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT K.R.CIRCLEBENGALURU-560001(REP BY ITS MANAGING DIRECTOR )- 25 -
4. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITED (GESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROADKALABURAGI-585101(REP BY ITS MANAGING DIRECTOR)
5. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITED (HESCOM)A COMPANY REGISTERED UNDERTHE PROVISION OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT P.B. ROAD,NAVANAGAR, HUBBALI-580025(REP. BY ITS MANAGING DIRECTOR )
6. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN,K.G. ROAD, BENGALURU-560009(REP. BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI M., AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI S.SRIRANGA, ADV. FOR R-3;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-6;SRI MURUGESH V. CHARATI, ADV. FOR R-4;SMT.M.C.NAGASHREE, ADV. FOR R-5 & R-6.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEIMPUGNED ORDER DATED 14.05.2018 PASSED BY THE 2NDRESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.- 26 -
IN W.P.No.23700/2018:
BETWEEN :
M/s SURYODAY ONE ENERGY PVT. LTD.,A COMPANY INCORPORATED UNDERTHE COMPANIES ACT, 2013HAVING ITS REGISTERED OFFICE ATS.P. CENTRE, 41/44MINOO DESAI MARG,COLABA, MUMBAI-400005REP. BY ITS AUTHORISED SIGNATORYMr. SUNIL VASUDEO KULKARNI ...PETITIONER
(BY SRI SURAJ GOVINDA RAJ, ADV.)
AND :
1. STATE OF KARNATAKAREP BY ADDITIONAL CHIEF SECRETARYTO GOVERNMENT (ENERGY DEPARTMENT)VIKASA SOUDHA, BANGALORE-560 001
2. KARNATAKA ELECTRICITYREGULATORY COMMISSION (KERC)NO.16, C-1, MILLERS TANK BED AREAVASANTHANAGAR, BANGALORE-560 052(REP BY ITS CHAIRMAN)
3. BANGALORE ELECTRICITY SUPPLYCOMPANY LIMITED (BESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R. CIRCLEBENGALURU-560001(REP BY ITS MANAGING DIRECTOR)
4. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITED (HESCOM)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT P.B. ROAD, NAVANAGAR- 27 -
HUBBALI-580 025(REP. BY ITS MANAGING DIRECTOR)
5. GULBARGA ELECTRICITY SUPPLYCOMPANY LIMITED (GESCO)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALABURAGI-585 101(REP BY ITS MANAGING DIRECTOR)
6. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITED (KPTCL)A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN,K.G. ROAD, BENGALURU-560009(REP BY ITS MANAGING DIRECTOR) ...RESPONDENTS
(BY SMT.JYOTHI, AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3 & R-6;SRI ARAVIND KAMATH, ADV. FOR R-5;SRI MURUGESH V. CHARATI, ADV. FOR R-5 & R-6.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEIMPUGNED ORDER DATED 14.05.2018 PASSED BY THE 2NDRESPONDENT-KARNATAKA ELECTRICITY REGULATORYCOMMISSION, BENGALURU, VIDE ANNEXURE-A.
IN W.P.No.23851/2018:
BETWEEN :
M/s MARVEL SOLREN PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE T.MAHINDRA TOWERS,Dr. G.BHOSALE MARG,- 28 -
P.K. KURNE CHOD, WORLIMUMBAI-400018REP. BY ITS GENERAL MANAGERMr. RAKESH KHAITAN ... PETITIONER
(BY SRI SHODHAN BABU A.M., ADV.)
AND :
1. BANGALORE ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT K.R.CIRCLE,BENGALURU-5600001(REP BY ITS MANAGING DIRECTOR)
2. CHAMUNDESHARI ELECTRICITYSUPPLY CORPORATION LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT NO.29KAVERI GRAMEENA BANK ROADHINKAL, VIJAYANAGAR 2ND STAGEMYSURU-570019(REP BY ITS MANAGING DIRECTOR)
3. MANGALORE ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT MESCOM BHAVANA,KAVOOR CROSS ROADBEJAI, MANGALURU-570004(REP. BY ITS MANAGING DIRECTOR)
4. HUBLI ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTERED- 29 -
OFFICE AT P.B. ROADNAVANAGAR, HUBBALLI-580025(REP BY ITS MANAGING DIRECTOR)
5. GULBARGA ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT STATION ROADKALABURGI-585101(REP BY ITS MANAGING DIRECTOR)
6. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956 HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN, K G ROADBENGALURU-560009(REP. BY ITS MANAGING DIRECTOR)
7. KARNATAKA ELECTRICITYREGULATORY COMMISSIONNO.16, C-1MILLERS TANK BED AREAVASANTH NAGARBENGALURU-560052 ...RESPONDENTS
(BY SRI S.S.NAGANANDA, SENIOR ADV. FOR SRI S.SRIRANGA,ADV. FOR R-2, R-4 & R-5;SMT.M.C.NAGASHREE, ADV. FOR R-3;SRI ARVIND KAMATH K., ADV. FOR R-5;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-6;SRI H.V.DEVARAJU, ADV. FOR R-6;SRI B.N.PRAKASH, ADV. FOR R-7;R-1 IS SERVED, BUT UNREPRESENTED.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEIMPUGNED ORDER, DATED 14.05.2018, PASSED BY THERESPONDENT NO.7 (PRODUCED HEREIN AS ANNEXURE R).- 30 -
IN W.P.Nos.23990 - 23995/2018:
BETWEEN :
1. FORTUNE FIVE HYDELPROJECTS PRIVATE LIMITEDHAVING ITS ADMN. OFFICE ATNO.701-702, PRESTIGE MERIDIAN-II,NO.30, M.G. ROAD,BENGALURU-560 001,REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L.
2. VYSHALI ENERGY PRIVATE LIMITEDHAVING ITS ADMN. OFFICE ATNO.701, PRESTIGE MERIDIAN-II,NO.30, M.G. ROAD,BENGALURU-560 001,REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L.
3. MANGALORE ENERGIES PRIVATE LIMITEDHAVING ITS REGISTERED OFFICE ATNO.173, 3RD MAIN, 11TH CROSS,DOLLARS COLONY, RMV 2ND STAGE,BENGALURU-560 094,REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L.
4. GREENKO BAGEWADI WINDENERGIES PRIVATE LIMITEDHAVING ITS ADMN. OFFICE ATNO.701-702, PRESTIGE MERIDIAN-II,NO.30, M.G. ROAD,BENGALURU-560 001,REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L.
5. AMR POWER PRIVATE LIMITEDHAVING ITS REGISTERED OFFICE ATNO.701-702, PRESTIGE MERIDIAN-II,NO.30, M.G. ROAD,BENGALURU-560 001,- 31 -
REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L.
6. PERLA HYDRO POWER PRIVATE LIMITEDHAVING ITS ADMN. OFFICE ATNO.701-702, PRESTIGE MERIDIAN-II,NO.30, M.G. ROAD,BENGALURU-560 001,REP BY ITS AUTHORIZED SIGNATORYMr. NAVEEN KUMAR L. ...PETITIONERS
(BY SRI RAJESWARA P.N., ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSION,#16C-1, MILLER TANK BED AREA,VASANTHANAGAR, BENGALURU-560 052REP. BY MANAGING DIRECTOR.
2. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,KAVERI BHAVAN, K.G. ROAD,BENGALURU-560 009,REP. BY ITS MANAGING DIRECTOR.
3. BENGALURU ELECTRICITYSUPPLY COMPANY LTD.,K.R. ROAD, BENGALURU-560 001,REP BY ITS MANAGING DIRECTOR,
4. HUBALLI ELECTRICITYSUPPLY COMPANY LTD.,P.B. ROAD, DURGAD BAIL,NAVANAGAR, HUBBALLI,KARNATAKA-580 025,REP. BY ITS MANAGING DIRECTOR.
5. MANGALORE ELECTRICITYSUPPLY COMPANY LIMITEDCORPORATE OFFICE,MESCOM BHAVANA,KAVOOR CROSS ROAD,- 32 -
BEJAI, MANGALORE-575 004,REP BY ITS MANAGING DIRECTOR. ...RESPONDENTS
(BY SRI B.N.PRAKASH, ADV. FOR R-1;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-2;SRI S.SRIRANGA, ADV. FOR R-5; R-3 SERVED.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER OF RESPONDENT NO.1COMMISSION DATED 14.05.2018 VIDE ANNEXURE-A, IN SOFAR AS THE PETITIONERS ARE CONCERNED.
IN W.P.Nos.24248 - 24259/2018:
BETWEEN :
1. BHADRA PACKAIDS PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS HEAD OFFICEAT No.23/14, II FLOOR,JALASAMBHAVI COMPLEX,1ST MAIN ROAD, GANDHINAGAR,BANGALORE - 560009REP. BY ITS AUTHORIZED SIGNATORYMr. MADESH LAKSHMAN
2. CHARISHMA HOTELS PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS REGISTERDOFFICE AT RADISSON BLU BENGALURU,OUTER RING ROAD, SY.NO.90/4,MUNNEKOLLALU VILLAGE,MARATHAHALLI OUTER RING ROAD,BANGALORE -560037RER. BY ITS AUTHORIZED SIGNATORYMr. ANDREW HINES
3. KEMWELL BIOPHARMA PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIES- 33 -
ACT, 1956, HAVING ITS OFFICEAT 34TH KM, TUMKUR ROAD,T.BEGUR, NELAMANGALA TALUK,BANGALORE - 562123REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
4. MLS ESTATE LLPA LIMITED LIABILITY PARTNERSHIPHAVING ITS OFFICE AT'THE MILLENIA' TOWER A14TH FLOOR, 1 & 2 MURPHY ROADULSOOR, BANGALORE- 560008REP. BY ITS AUTHORISED SIGNATORYMr. SANJIV SHANMUGAM
5. SHREE M.T.K. TEXTILES PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS REGISTEREDADMINISTRATIVE OFFICE AT NEW No.57,DPF STREET, RAMASWAMY LAYOUT,PAPPANICKENPALAYAMCOIMBATORE - 641037REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
6. AVON CYCLES LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, G.T. ROAD, LUDHIANA- 141003REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
7. AVON ISPAT AND POWER LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFIE AT G.T. ROAD, LUDHIANA- 141003REP BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
8. LOZEN PHARMA PVT. LTD.,A COMPANY REGISTERED UNDER- 34 -
THE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS FACTORY ATRAGHAV ESTATE,KSSIDC INSUTRIAL ESTATESHIGGAON ROADREP BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
9. RENNAISSANCE ADVISORYSERVICES PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT 19/3, SUJATA BUILDING,RANISATI MARG, MALAD EAST,MUMBAI - 400097REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
10. SHREE ANANTNATH REALESTATE PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT STEELYARD HOUSE,St. ROAD, IRON MARKETMASJID BUNDER,MUMBAI - 400009REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES
11. ABHISHTA SOLAR PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013, HAVING ITS REGISTEREDOFFICE 4E AND 5E, INDUSTRIAL ESTATE,VAISHNAVI SAROVAROPP. GUJARATHI SAMAJAPT No.402 & 403,D BLOCK, YADAVGIRIMYSORE - 570020REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES- 35 -
12. UMIYA HOLDINGS PVT. LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF THE COMPANIESACT, 2013, HAVING ITS REGISTEREDOFFICE # 29/3, H.M.STRAFFORD,2ND FLOOR, 7TH CROSS ROAD,VASANTHNAGARBANGALORE - 560052JAIPUR, RAJASTHAN - 302019REP. BY ITS AUTHORISED SIGNATORYMr. ANDREW HINES ...PETITIONERS
(BY SRI C.MURALIDHARA, ADV.)
AND :
1. BANGALORE ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT K.R.CIRCLE,BENGALURU - 560001REP BY ITS MANAGING DIRECTOR
2. GULBARGA ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT STATION ROAD,KALABURAGI - 585101REP BY ITS MANAGING DIRECTOR
3. KARNATAKA ELECTRICITYREGULATORY COMMISSIONNo.16, C-1 MILLERS TANK BED AREA,VASANTH NAGAR,BENGALURU - 560052REP. BY ITS CHAIRMAN
4. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,A COMPANY REGISTERED UNDER- 36 -
THE PROVISIONS OF COMPANIESACT, 1956, HAVING ITS REGISTEREDOFFICE AT KAVERI BHAVAN, K.G.ROAD,BENGALURU - 560009REP. BY ITS MANAGING DIRECTOR ...RESPONDENTS
(BY SRI SHAHABAAZ HUSSAIN, ADV. FOR R-1 & R-4;SRI PRASHANT T. PANDIT, ADV. FOR R-2;SRI B.N.PRAKASH, ADV. FOR R-3.)
THESE WRIT PETITIONS ARE FILED UNDER ARTICLES226 AND 227 OF THE CONSTITUTION OF INDIA PRAYING TOQUASH THE IMPUGNED ORDER DATED 14TH MAY, 2018PASSED BY THE RESPONDENT NO.3 (PRODUCED HEREIN ASANNEXURE-A).
IN W.P.No.25090/2018:
BETWEEN :
MATRIX WIND ENERGY PRIVATE LIMITEDHAVING ITS REGD. OFFICE AT8-2-277/12, NO.296, ROAD NO.3,UBI COLONY, BANJARA HILLS,HYDERABAD-500 034REP BY ITS AUTORIZEDSIGNATORY Mr. SHARAN B. ...PETITIONER
(BY SRI DHYAN CHINNAPPA, SENIOR ADV. FORSRI P.N.RAJESWARA, ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSION#16C-1, MILLER TANK BED AREA,VASANTHANAGAR,BENGALURU-560 052MANAGING DIRECTOR
2. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,KAVERI BHAVAN, K.G. ROAD,- 37 -
BENGALURU-560 009REP BY ITS MANAGING DIRECTOR
3. BENGALURU ELECTRICITY SUPPLYCOMPANY LTD.,K.R. ROAD, BENGALURU-560 001REP BY ITS MANAGING DIRECTOR
4. HUBALLI ELECTRICITYSUPPLY COMPANY LTD.,P.B. ROAD, DURGAD BAIL,NAVANAGAR, HUBBALLI-580 025KARNATAKAREP BY ITS MANAGING DIRECTOR ...RESPONDENTS
(BY SRI B.N.PRAKASH, ADV. FOR R-1;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-2 & R-3.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEIMPUGNED ORDER OF RESPONDENT NO.1 COMMISSIONDATED 14.05.2018 VIDE ANNEXURE-A IN SO FAR AS THEPETITIONER IS CONCERNED.
IN W.P.No.26480/2018:
BETWEEN :
JINDAL ALUMINUM LTD.,REGISTERED OFFICE ATJINDAL NAGAR, TUMKUR ROAD,BENGALURU-560 073REP BY AUTHORIZED SIGNATORYSHRI H.S.HAYATH KHAN ...PETITIONER
(BY SRI RAJESWARA P.N., ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSION,# 16C-1, MILLER TANK BED AREA,VASANTHANAGAR,- 38 -
BENGALURU-560052
2. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,KAVERI BHAVAN, K.G. ROAD,BENGALURU-560 009REP BY ITS MANAGING DIRECTOR
3. BENGALURU ELECTRICITYSUPPLY COMPANY LTD.,K.R. CIRCLE, BENGALURU-560 001REP BY ITS MANAGING DIRECTOR
4. GULBARGA ELECTRICITYSUPPLY COMPANY LIMITEDCORPORATE OFFICE,# 48, SUPER MARKET MAIN ROAD,HALBARGA, BRHAMPURKALABURGI-585 101REP BY ITS MANAGING DIRECTOR
5. CHAMUNDESHWARI ELECTRICITYSUPPLY CORPORATION LTD.,CORPORATE OFFICE, #927,L.J. AVENUE COMMERCIAL COMPLEX,NEW KANTHARAJA URS ROAD,SARASWATHIPURAM,MYSURU-570 009REP BY ITS MANAGING DIRECTOR ...RESPONDENTS
(BY SRI B.N.PRAKASH, ADV. FOR R-1;SRI H.V.DEVARAJU, ADV. FOR R-2;SRI SHAHABAAZ HUSSAIN, ADV. FOR R-2;SRI SHANMUKA G.C. ADV. FOR R-3;SRI S.SRIRANGA, ADV. FOR R-3;SRI PRASHANTH T. PANDIT, ADV. FOR R-4;SRI HARIKRISHNA S. HOLLA, ADV. FOR R-5.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH ANDSETTING ASIDE THE IMPUGNED ORDER OF R-1 COMMISSIONDATED 14.05.2018 VIDE ANNEXURE-A IN SO FAR AS THEPETITIONER IS CONCERNED.- 39 -
IN W.P.No.28622/2018:
BETWEEN :
M/s P.BALASUBBA SETTY POWER & STEEL2ND FLOOR, D.NO.2078, P.B.NO.03,22ND WARD, J.P.NAGARBALLARY ROAD, BALLARI, HOSPETBELLARY DISTRICT-583101REP BY ITS AUTHORIZED REPRESENTATIVESHRI P.PRABHAKAR SETTY ...PETITIONER
(BY SRI SHIVAPRASAD SHANTANAGOUDAR, ADV.)
AND :
1. THE STATE OF KARNATAKAREP BY ITS PRINCIPAL SECRETARYDEPARTMENT OF ENERGYVIKASA SOUDHABANGALORE-560 001
2. THE KARNATAKA ELECTRICITYREGULATORY COMMISSIONNO.16, C-I,MILLERS TANK BED AREAVASANTH NAGARBENGALURU-560 001REP BY ITS SECRETARY
3. THE KARNATAKA POWERTRANSMISSION CORPROATION LIMITEDREGISTERED OFFICE AT CAUVERY BHAVANAKEMPEGOWDA ROAD,BENGALURU-560009REP BY ITS MANAGING DIRECTOR
4. HUBLI ELECTRICITY SUPPLYCOMPANY LIMITEDNAVANAGAR, P.B. ROAD,HUBBALLI-580025REP BY ITS MANAGING DIRECTOR- 40 -
5. MANGALURU ELECTRICITY SUPPLYCOMPANY LIMITEDREGISTERED OFFICE ATPARADISE PLAZAA.B. SHETTY CIRCLEMANGALURU -575001REP. BY ITS MANAGING DIRECTOR
6. CHAMUNDESHWARI ELECTRICITYSUPPLY COMPANY LIMITEDHAVING ITS OFFICE ATNAVANAGAR, HUBBALLI-580025REP BY ITS MANAGING DIRECTOR
7. GULBARGA ELECTRICITY SUPPLYCOMAPANY LIMTIEDSTATION ROAD, GULBARGA -585 102REP BY ITS MANAGING DIRECTOR
8. BENGALURU ELECTRICITY SUPPLYCOMPANY LIMITEDREGISTERED OFFICE ATK.R. CIRCLE, BENGALURU-560001
9. MYSURU ELECTRICITY SUPPLYCOMPANYREGISTRED OFFICE ATNO.29, VIJAYANAGAR II STAGE,HINAKAL, MYSURU-570017 ...RESPONDENTS
(BY SMT.JYOTHI, AGA FOR R-1;SRI B.N.PRAKASH, ADV. FOR R-2;SRI S.SRIRANGA, ADV. FOR R-3;SRI PRASHANT T. PANDIT, ADV.FOR R-4;SRI DEVARAJU H.V., ADV. FOR R-5;SRI G.C.SHANMUKHA, ADV. FOR R-6 & R-9;SRI RAVINDRA REDDY, ADV. FOR R-7;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-8.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEORDER DATED 14.05.2018 PASSED BY THE KARNATAKAELECTRICITY REGULATORY COMMISSION, BENGALURUPASSED IN NO.S/03/2017, IN THE MATTER OF REVISION OF- 41 -
"WHEELING AND BANKING CHARGES FOR RENEWABLE POWERPROJECTS", VIDE ANNEXURE-D, IN SO FAR AS IT RELATES TOPETITINER'S COMPANY.
IN W.P.No.53531/2018:
BETWEEN :
M/s LAKSHMI JALAVIDYUTH(KRISHNA) LIMITEDNO.156, GOLF LINK ROAD,AMARAJYOTHI LAYOUT,DOMLUR, BENGALURU-560071REP BY ITS DIRECTORMr. B.SAILESH REDDY,S/O B.SUDHAKAR REDDY,AGED ABOUT 45 YEARS ...PETITIONER
(BY SRI REUBEN JACOB, ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSIONNO.16, C-1,MILLER TANK BED AREAVASANTH NAGAR,BENGALURU-560052REP BY ITS SECRETARY
2. KARNATAKA POWER TRANSMISSIONCORPORATION LTD.,KAVERI BHAVAN,BENGALURU-560 009REP BY ITS MANAGING DIRECTOR
3. BANGALORE ELECTRICITYSUPPLY COMPANY LTD.,K.R.CIRCLE,BENGALURU-560 001REP BY ITS MANAGING DIRECTOR- 42 -
4. GULBARGA ELECTRICITYSUPPLY COMPANY LTD.,STATION ROAD, KALABURGI-585102REP BY ITS MANAGING DIRECTOR ...RESPONDENTS
(BY SRI B.N.PRAKASH, ADV. FOR R-1;SRI S.SRIRANGA, ADV. FOR R-2;SRI SHAHBAAZ HUSSAIN, ADV. FOR R-3;SRI PRASHANT T. PANDIT, ADV. FOR R-4.)
THIS WRIT PETITION IS FILED UNDER ARTICLES 226 AND227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THEORDER DATED 14.05.2018 BEARING NO.S/03/2017 ATANNEXURE-A PASSED BY R-1 IN SO FAR AS PETITIONER ISCONCERNED.
IN W.P.No.39329/2018:
BETWEEN :
NARAYANAPUR POWERCOMPANY PRIVATE LIMITED,A COMPANY INCORPORATED ANDGOVERNED BY THE PROVISIONS OFTHE COMPANIES ACT, 1956HAVING ITS REGISTERED OFFICEAT NO.A-12, MANYATA RESIDENCYARABIC COLLEGE POST,BENGALURU-560045REP. BY ITS MANAGING DIRECTOR,Mr. Y.S.V.K.VASUDEV RAO ...PETITIONER
(BY SRI SHRIDHAR PRABHU, ADV.)
AND :
1. KARNATAKA ELECTRICITYREGULATORY COMMISSION,NO.16, C-1, MILLERS BED AREA,VASANTH NAGAR,BENGALURU-560052(REP BY ITS CHAIRPERSON)- 43 -
2. BANGALORE ELECTRICITYSUPPLY COMPANY LIMITEDA COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT 1956, HAVING ITS REGISTEREDOFFICE AT K.R.ROAD,BENGALURU-560001(REP BY ITS MANAGING DIRECTOR)
3. GULBARGA ELECTRICITYSUPPLY COMPANY LTD.,A COMPANY REGISTERED UNDERTHE PROVISIONS OF COMPANIESACT 1956, HAVING ITS REGISTEREDOFFICE AT STATION ROAD,GULBARGA-585102(REP BY ITS MANAGING DIRECTOR)
4. KARNATAKA POWER TRANSMISSIONCORPORATION LIMITEDKAVERI BHAVAN, K.G.ROAD,BENGALURU-560009(REP BY ITS MANAGING DIRECTOR)
5. STATE OF KARNATAKADEPARTMENT OF ENERGY,VIKASA SOUDHA,Dr. AMBEDKAR VEEDHI,BENGALURU-560001, (REP BY ITSADDITIONAL CHIEF SECRETARY) ...RESPONDENTS
(BY SMT.JYOTHI, AGA FOR R-5.)
THIS WRIT PETITION IS FILED UNDER ARTICLE 226 OFTHE CONSTITUTION OF INDIA PRAYING TO QUASH THEIMPUGNED ORDER DATED 14.05.2018 PASSED BY THE R-1KARNATAKA ELECTRICITY REGULATORY COMMISSION,BENGALURU VIDE ANNEXURE-A, AS FAR AS THE PETITIONERIS CONCERNED.
THESE PETITIONS HAVING BEEN HEARD ANDRESERVED ON 05.02.2019, COMING ON FORPRONOUNCEMENT OF ORDER THIS DAY, S.SUJATHA J.,PASSED THE FOLLOWING:- 44 -
ORDER
These petitions involving similar and akin issues,
have been considered together and are taken up for
final disposal at this stage with the consent of the
learned counsel appearing for the parties.
2. Facts of the case:
The petitioners have challenged the order dated
14.5.2018 (impugned order) passed by the Karnataka
Electricity Regulatory Commission (KERC), Bengaluru
under the provisions of the Electricity Act, 2003 ['Act'
for short] and the KERC (Terms and Conditions for
Open Access) Regulations, 2004, which deals with open
access charges including wheeling and banking charges,
transmission losses and cross subsidy surcharge of
Renewable Energy [RE] projects commissioned between
01.04.2013 and 31.3.2018. The open access charges for
RE projects commissioned between 01.04.2013 and
31.3.2018 were governed by two separate orders of the
- 45 -
KERC. The order dated 4.7.2014 dealt with wind based
as well as Mini hydel power plants and the order dated
18.8.2014 dealt with solar power plants. The wind/Mini
hydel power plants under order dated 4.7.2014 were
required to pay 5% wheeling charges of the injected
energy. The banking charges were specified at 2% of the
injected energy. The solar power generators as per the
order dated 18.8.2014 were exempt from paying
wheeling and banking charges and gross subsidy
surcharge for a period of 10 years from the date of
commissioning provided that their power plants were
commissioned between 1.4.2013 and 31.3.2018. It
appears that the petitioners have complied with the
conditions in the orders dated 4.7.2014 and 18.8.2014
and commissioned their respective projects prior to
31.3.2018. However, KERC by the order impugned
herein continued the exemption on the wheeling and
banking charges to the solar projects commissioned on
or earlier to 31.3.2017 and all the RE Projects [other
- 46 -
than the captive generators] availing of the benefit of the
Renewable Energy Certificate [REC], which have not yet
completed ten years from the date of commercial
operation as on 31.03.2018 are made liable to pay 25%
of the normal transmission charges and/or wheeling
charges and banking charges of two percent in kind. In
case of wind/Mini hydel power projects commissioned
during the period between 10.10.2013 and 3.9.2017,
25% of the normal transmission charges and/or
wheeling charges have been levied. The line losses were
to be exempted in kind. The banking charges were
retained at 2% for projects commissioned between
10.10.2013 and 3.9.2017. The other applicable charges
are liable to be levied in respect of wind projects as well.
Being aggrieved by the order impugned, these petitions
are filed.
3. Submissions on behalf of M/s. Renew
Power Limited & others:-
- 47 -
The impugned order suffers from jurisdictional
error being contrary to sections 42(2), 61 and 62 of the
Act, Rule 11 of the Open Access Regulations 2004 ['OA
Regulations' for short] as well as the judgment of the
Hon'ble Apex Court in PTC India limited Vs Central
Electricity Regulatory Commission1. It was contended
that the respondent KERC has no jurisdiction to
interfere with the settled contract under the provisions
of the Act, Regulations 2004 and in terms of the
contract entered into between the parties. The KERC
has not traced the power to re-determine the tariff to
any provision under the Act. Settled contract cannot be
unsettled except by way of fresh regulation in exercise of
the legislative function of the state commission.
The statutory contracts have to be read with the
Act and the regulations governing the statutory
contract. Any amendments to statutory contract have to
be in conformity with the parent statute and the specific1 (2010)4 SCC 603
- 48 -
regulations that govern the statutory contract in
question. A generic order made applicable to multiple
projects may only be revised by resorting to a regulation
under section 181 of the Act and not under the quasi
judicial functions of the KERC.
It was submitted that the amendment can only be
carried out at the instance of one of the parties to the
contract which is admittedly not the case herein.
Neither the KERC nor the public notice and the
discussion paper issued prior to the impugned order do
trace the power of the commission to the amendment
clause of the contract and the same is an after thought.
The KERC cannot revisit the open access charges
determined in a settled contract by belatedly resorting
to amendment clause in the contract. KERC has
reaffirmed the exemption granted in its order dated
18.8.2014 repeatedly in the orders dated 30.7.2015 and
12.4.2017 which were applicable to various control
- 49 -
periods from 1.4.2013 to 31.3.2018. Achieving the
desired objective and the solar as well as wind power
generation in the State of Karnataka has been increased
cannot be treated as a ground for change in the
circumstances to revisit the exemptions granted to solar
and wind generators in the orders dated 10.10.2013,
4.7.2014, 18.8.2014, 30.7.2015 and 12.4.2017.
The OA regulations framed in the present case
under Sections 42 and 62 of the Act are in exercise of
delegated legislative powers under Sections 42, 61, 62
and 181 of the Act. The KERC cannot re-open the tariff
determination made under the order dated 18.8.2014
without there being corresponding change in the
regulations through legislative amendments or by way
of introduction of a fresh regulation under Section 181
of the Act. It was argued that the tariff order in question
traces its source to section 86(1)(e) of the Act which
mandates promotion of cogeneration and generation of
- 50 -
power from renewable sources of energy and therefore,
the order granting exemption from payment of OA
charges was essential for the development of renewable
energy generation and therefore is not a concession that
can be withdrawn unilaterally.
The exemption granted is not in the nature of
state largesse. The exemption granted by the order
dated 10.10.2013 has been extended for a specific
period of ten years by the order dated 18.08.2014, after
taking into account a) the debt repayment period of ten
years. b) High cost of solar power generation and c) the
requirement for transparency and clarity in revenue for
the next ten years. The KERC after applying its mind to
the issues and passing OA regulations read with
sections 61, 62, 64 and 86(1)(e) of the Act cannot now
revisit the issues by citing subsequent changes in
circumstances such change in circumstances can only
be applied to projects which are set up after 31.03.2018
- 51 -
and not for projects commissioned prior to 31.03.2018
which were commissioned based on the
assurance/promise made by the State Government in
as much as the exemption granted relating to tariff and
banking charges in terms of the orders as well as the
order of the KERC dated 18.08.2014.
As regards the alternative remedy of appeal
available under the Act, it was contended that the KERC
has no jurisdiction to interfere with the settled contracts
under the provisions of the Act which are statutory
contracts. OA Regulations and/or the terms of the
contracts entered into between the parties, the settled
contract between the parties which are wheeling and
banking agreement in this case, do not permit either a
re-determination, revision or review of the generic OA
charges determined in accordance with applicable tariff
orders and the OA Regulations, 2004. The order
impugned passed without jurisdiction is amenable to
- 52 -
writ jurisdiction. Reliance was placed on the judgment
of the Hon'ble Apex Court in PTC India Private
Limited supra, to substantiate their arguments.
4. Submission on behalf of M/s Embassy
Energy Private Limited:-
The Respondent No.1 convened a Global Investors
Meet (Invest Karnataka 2016) and issued public policy
document on 05.02.2016. This global investors meet
was exclusive and focus was on the energy development
through alternative source, which contains the foreword
of the then Hon'ble Minister of the Energy providing the
aim of achieving the maximum solar/wind/mini hydel
energy. Under foreword of Additional Chief Secretary,
Government of Karnataka inviting additional active
investment on solar energy providing with the key high
lights revising the minimum target as 2000MW in solar
power, planning to achieve 6000 MW by 2021 with no
limits or caps for projects under REC mechanism.
- 53 -
Industry friendly policy regulation therein assured no
cross subsidy surcharge for third party, no
transmission and wheeling charges, 100% banking for
open access projects. Applications were made by the
petitioner for submitting proposals for solar power
plants of 100 MW. Government by order dated
28.03.2016 permitted the setting up of the solar power
plant.
Petitioner submitted performance of security with
Government of Karnataka on 16.09.2017. Tentative
evacuation scheme and regular evacuation scheme were
made on 24.10.2016 and 28.03.2017 respectively.
Wheeling and banking agreement was entered into by
the petitioner with KPTCL on 19.12.2017
commissioning of 40MW out of 100MW of solar power
plant started on 23.01.2018. Commission certificate for
the balance 60MW was given on 28.02.2018.
- 54 -
Referring to these events and the list of dates, it
was argued that the KERC had granted ten years tariff
holiday on banking, wheeling and cross subsidy
surcharge for all solar plant commissioned between
01.04.2013 and 31.03.2018. The State Government
has issued a public policy document of energy Invest
Karnataka 2016, GIM, declaring and re-iterating the
availability of these benefits to those invest in solar
power plant industry in Karnataka. It is based on the
promises and assurances of the KERC and the
Government of Karnataka, the petitioner initiated the
process of filing the applications for setting up of solar
plants and after carrying out series of steps, carried out
commissioning of the plants on 23.01.2018, thus
coming within the time period mandated by the KERC
and the Government of Karnataka. The discussion
paper initiated by the KERC on 10.01.2018 on wheeling
and banking charges re-iterates its earlier order dated
04.07.2014 granting the benefit for the period of ten
- 55 -
years for such projects commissioned on or before
31.03.2018. The reasons stated for revisiting the earlier
decisions that the solar power project capacity has
increased to 1698 MW as on the November 2017 and by
the end of the financial year 2019, it anticipated
commissioning of 6000 MW would call for revisiting the
concession granted post 31.03.2017 is without
jurisdiction, arbitrary and discriminatory.
Nextly, it was argued that, a] State action
withdrawing the promise midway without there being a
supervening public interest necessitating such
withdrawal calls for interference in the judicial review by
this court. b] Agreement or contract in question is not a
private contract between the private parties but a
statutory contract. Arbitrary classification made by the
impugned order continuing the benefit for the solar
plants commissioned between 01.04.2013 and
31.03.2017 and withdrawing the benefits for such
- 56 -
plants commissioned post 01.04.2017 is unreasonable,
arbitrary and hit by Article 14 of Constitution of India.
The reasons assigned by the KERC that the
petitioners are making super profit and therefore, the
concession requires to be withdrawn is legally
unsustainable. On the contrary, the records show a
down word decline of an unimaginable 98% down fall as
regards the solar power projects are concerned.
Regarding alternative remedy it was argued that
the order impugned being violative of Article 14 of the
Constitution and is passed without jurisdiction is
amenable to the writ jurisdiction under Articles 226 and
227 of the Constitution of India.
5. Submissions on behalf of M/s. Matrix
Wind Energy Private Limited:
It was argued that the commission lacks
jurisdiction to amend / modify the wheeling and
- 57 -
banking charges once determined in respect of
renewable energy projects. The transmission and
wheeling charges are amenable to section 61(b) of the
Act and the said power is exercised by the commission
as a regulator and not as an adjudicator, exercising the
statutory power wheeling and banking charges were
fixed/determined payable by renewable power plant
established up to a particular period of ten years.
Commission cannot suo-moto exercise the powers to
revise / amend the wheeling and banking charges fixed
in terms of the statutory contract on the assurance/
promise made to provide an exemption to the petitioner,
no such suo-moto power is vested with the commission.
Reference was made to Doctrine of promissory
estoppel, legitimate expectation and the discussion
paper in as much as revising the order dated
18.08.2014 to contend that the order impugned is
- 58 -

arbitrary and capricious and passed without

jurisdiction.

It was argued that surprisingly, a sub

categorization was made to discriminate between the RE

Generators commissioned before 31.03.2017 and post

31.03.2017. Order 47 Rule 1 of CPC was also referred to

submit that no review of the order dated 18.08.2014 is

permissible.

As regards alternative remedy, it was argued that

there being breach of fundamental rights and the

promise/assurance made, order impugned lacks

jurisdiction, as such there is no bar to exercise the writ

jurisdiction under Articles 226 and 227 of the

Constitution.

Inherent powers of the commission are saved to

make orders which are necessary to secure the ends of

justice and to prevent the abuse of the process of the

- 59 -

commissions. Reference was made to the judgment of

the Hon'ble Apex Court in the case of Gujarat Urja

Vikas Nigam Limited Vs. Solar Semi Conductor

Power company (India Private Limited) and

another2.

6. Submissions on behalf of M/s. Narayanpur

power Company Private Limited:

It was argued that existence of the judicial

member is sine quo non for the Tribunal passing quasi

judicial orders. Placing reliance on the judgment of the

Hon'ble Apex Court in the case of State of Gujarat and

others Vs. Utility Users Welfare Association and

others3, it was submitted that if the Tribunals are to be

given judicial power, they must possess judicial

independency and capacity associated with the courts,

Members of judiciary should be the presiding

officer/member of such Tribunal. Further, referring to

2 (2017) 16 SCC 498 3 (2018)6 SCC 21

- 60 -

the clarificatory orders of the Hon'ble Apex Court dated

10.09.2018, it was submitted that the clarificatory

order has to be understood in the light of the series of

judgments of the Hon'ble Apex Court. The clarificatory

order reads as under:

"Application[s] for impleadment /intervention is/are dismissed

We are of the view that there is no ambiguity in the Judgment and till such time a reconstitution of the Tribunal does not take place arising from a retirement of a Member from the legal field, the existing Tribunal will decide all the cases.

The application/s for clarification/direction is/are disposed of.

In view of the above, the misc. petition is disposed of."

The said clarificatory order applies to the transfer

case MA No.2217/2018 in TC (C No.137/2015) and not

to the entire batch of cases. In any event, the ratio laid

down by the Hon'ble Apex Court in the State of

Gujarat supra, is not disturbed or in other words, the

- 61 -

clarificatory order of the Hon'ble Apex Court would not

be of any avail to the respondents. The contract would

not confer the jurisdiction on the commission or

delegate to issue a revising / modification order in

respect of the wheeling and banking charges fixed with

retrospective effect. No such power is vested with the

commission.

7. The submissions made on behalf of M/s.

Awada Sustainable Energy Private Limited:

Order impugned has been passed by the

commission against the principles of natural justice

without issuing any individual notice, the general and

blanket order has been passed in violation of the

principles of natural justice. Order impugned seeks to

undo the settled contract between the parties. The

concessional charges/exemption extended in the order

dated 18.08.2014, issued cannot be withdrawn or

modified much against the principles of legitimate

- 62 -

expectation and promissory estoppel. The order

impugned is in utter defiance and disregard to the

doctrine of promissory estoppel. To promote solar power

generation providing a level playing field for such

generation vis-à-vis the solar power being sold by

ESCOM of the State to such private parties, it was

envisaged to achieve the same by affording the

exemption/concession from payment of wheeling and

banking charges etc., However, in utter disregard, the

impugned order has been passed which is violative of

Article 14 of the Constitution of India. In view of the

order impugned being illegal, without jurisdiction,

violative of the principles of natural justice and also hit

by Article 14 of the Constitution of India, invoking the

extraordinary writ jurisdiction of this Court is not

unjustifiable and writ petitions requires to be

adjudicated on merits, not withstanding the alternative

remedy of appeal available under the Act.

- 63 -

The other petitioners have adopted the arguments

as aforesaid.

8. Submissions on behalf of the Commission

- KERC and Electricity Supply Companies

[ESCOMS].

Primarily, it was argued that the writ petitions are

not maintainable in view of the alternative remedy of the

appeal available under the Act. Placing reliance on the

judgment of the Hon'ble Apex Court in Civil Appeal

No.879/2019 disposed of on 21.01.2019 in the matter

of Reliance Infrastructure Limited Vs. State of

Maharashtra4, it was argued that in exercise of power

of judicial review under Article 226 of the Constitution

arising out of orders passed by the specialized Tribunal

like Electricity Regulatory Commission, the Hon'ble

court would have to be circumspect in examining the

merits of the decision particularly relating to fixation of

tariff and ought not to interfere unless the matter is 4 Civil Appeal No.879/2019 (D.D. Jan 21, 2019)

- 64 -

manifestly unreasonable, arbitrary and based on

extraneous consideration. The petitioners have not

pleaded/demonstrated such infirmity in the order of the

commission and therefore, the petitions are liable to be

dismissed in limine.

It was argued that the wheeling and banking

agreement itself provides the alteration/modification of

the terms of the contract under Article 12.6. Article 5 of

the Wheeling and Banking agreement clearly states that

the petitioners are liable to pay the charges as

determined by the commission in its orders passed from

time to time. Standard format of the wheeling and

banking agreement being accepted by the petitioner and

respondents, the petitioners are therefore precluded

from contending that the contracts could not have been

modified. The provisions of the Act, Regulation, 2004

and Wheeling and Banking agreements empowers the

commission to determine and revise the wheeling

- 65 -

charges, banking charges and cross subsidy charges.

Hence, passing a regulation under Section 181 of the

Act is not necessary as the Commission is empowered

under the parent Act and the regulation to determine

the tariff and the period, the principles of legitimate

expectation and promissory estoppel are not applicable

in the present context when parties are governed by the

contract. It is always open to the regulator to take into

consideration the changed circumstances which

necessitates change in the regulatory frame work.

Concessions that were granted earlier were required at

that time however the commission has noted that in

view of the change in the circumstances warranting the

imposition of wheeling charges of 25% and banking

charges passed the orders impugned.

Reference was made to section 21 of the General

Clauses Act, 1897 to argue that the power to issue an

order includes the power to alter, amend, vary or

- 66 -

rescind the order. The orders dated 04.07.2014 and

18.07.2014 as well as the order impugned have been

issued in furtherance of such powers. The impugned

order is prospective in nature and has not taken away

the concession / promotional measures granted in the

orders dated 04.07.2014 and 18.08.2014 respectively.

The commission has granted promotional measure and

concessional charges in orders dated 04.07.2014 and

18.08.2014 in view of the short fall in energy in the

State and the country. However, now in view of the

changed circumstances, energy generation is surplus in

the State. Therefore, the commission came to the

opinion that change in the demand and supply position

and the significant reduction in cost of generation has

necessitated reconsideration of whether concession for

wheeling and banking ought to be given. After thorough

analysis, the commission has come to the conclusion

that the concessions granted earlier are now no longer

required to be granted. RE Generators are making super

- 67 -

profits availing the concession granted in the orders

dated 04.07.2014 and 18.08.2014, which additional

cost is ultimately being borne by the consumers of the

State.

Drawing the attention of the Court to the

clarificatory order passed on 10.09.2018 in the case of

State of Gujarat supra, argued that the Hon'ble Apex

Court has observed that till such time a reconstitution

of the Tribunal does not takes place arising from a

retirement of a member from the legal field, the existing

Tribunal will decide all the cases, the said decision is

applicable to the commission as the question before the

Hon'ble Apex court was whether requirement of non-

judicial member was legal. Hence, the orders passed by

the commission are in accordance with law and have

been passed in exercise of the jurisdiction vested in it.

The order impugned cannot be construed as being

passed in exercise of the power of review.

- 68 -

It was argued that in terms of the order dated

30.07.2015 and the order dated 12.04.2017 passed by

the Commission, the capital cost was considered at

Rs.440 lakhs for MW for the purpose of determination of

tariff per mega watts solar PV power plants. The

commission in its order dated 23.03.2016 has

determined the bench mark capital cost norms for solar

photo volaptic projects for 2016-17 at Rs.530.02 lakhs

per MW as against the Rs.605.85 lakhs per MW

determined for 2015-16, considering these bench mark

norms, the commission in its discussion paper dated

09.02.2017 had proposed to adopt Rs.463.76 lakhs per

MW, a capital cost for 2017-18. The capital cost has

reduced from year to year.

9. Submissions on behalf the State:

The order impugned being appealable, the writ

petition is not maintainable. The Government of

Karnataka has allotted the projects to the petitioners

- 69 -

vide Government order dated 28.03.2016 and

08.09.2017. The government orders make it clear that

the petitioners are governed by the solar policy 2014 to

2021. Clause 13 of Solar Policy makes it clear that the

wheeling, banking and cross subsidy charges shall be

applicable as determined by the KERC from time to

time. Brochures furnished by the petitioners Karnataka

2016 Global Investors Meet 3 to 5, 2016 is not a solar

policy, the said booklet/brochures have been issued by

the Department of the Industries and Commerce which

contains the information regarding solar policy. Solar

policy 2014-21 issued on 22.05.2014 is still in

operation. By the impugned order dated 14.05.2018

commission has withdrawn the exemption on wheeling

and banking charges based on the public interest and is

not arbitrary. The doctrine of promissory estoppel is not

attracted in the sphere of legislative power since the

fixing of tariff of wheeling and banking charges is a

consequence of the legislative measure.

- 70 -

10. It is apt to refer to relevant provisions of

the Act:-

Section 2(76): 'Wheeling' means the operation whereby the distribution system and associated facilitates of a transmission licensee, as the case may be, are used by another person for the conveyance of electricity on payment of charges to be determined under Section 62.

Section 61 "Tariff regulations - The Appropriate Commission shall, subject to the provisions of this Act, specify the terms and conditions for the determination of the tariff, and in doing so, shall be guided by the following, namely:-

(a) the principles and methodologies specified by the Central Commission for determination of the tariff applicable to generating companies and transmission licensees;

(b) the generation, transmission, distribution and supply of electricity are conducted on commercial principles;

- 71 -

(c) the factors which would encourage competition, efficiency, economical use of the resources, good performance and optimum investments; (d) safeguarding of consumers' interest

and at the same time, recovery of the cost of electricity in a reasonable manner;

(e) the principles rewarding efficiency in performance;

(f) multi-year tariff principles;

(g) that the tariff progressively reflects the cost of supply of electricity and also reduces cross-subsidies in the manner specified by the Appropriate Commission;]

(h) the promotion of co-generation and generation of electricity from renewable sources of energy;

(i) the National Electricity Policy and tariff policy:

Provided that the terms and conditions for determination of tariff under the Electricity

- 72 -

(Supply) Act, 1948 (54 of 1948), the Electricity Regulatory Commissions Act, 1998 (14 of 1998) and the enactments specified in the Schedule as they stood immediately before the appointed date, shall continue to apply for a period of one year or until the terms and conditions for tariff are specified under this section, whichever is earlier."

"Section 62. (Determination of tariff): --

(1) The Appropriate Commission shall determine the tariff in accordance with the provisions of this Act for - (a) supply of electricity by a generating company to a distribution licensee:

Provided that the Appropriate Commission may, in case of shortage of supply of electricity, fix the minimum and maximum ceiling of tariff for sale or purchase of electricity in pursuance of an agreement, entered into between a generating company and a licensee or between licensees, for a period not exceeding one year to ensure reasonable prices of electricity;

- 73 -

(b) transmission of electricity ;

(c) wheeling of electricity;

(d) retail sale of electricity:

Provided that in case of distribution of electricity in the same area by two or more distribution licensees, the Appropriate Commission may, for promoting competition among distribution licensees, fix only maximum ceiling of tariff for retail sale of electricity.

(2) The Appropriate Commission may require a licensee or a generating company to furnish separate details, as may be specified in respect of generation, transmission and distribution for determination of tariff.

(3) The Appropriate Commission shall not, while determining the tariff under this Act, show undue preference to any consumer of electricity but may differentiate according to the consumer's load factor, power factor, voltage, total consumption of electricity during

- 74 -

any specified period or the time at which the supply is required or the geographical position of any area, the nature of supply and the purpose for which the supply is required.

(4) No tariff or part of any tariff may ordinarily be amended, more frequently than once in any financial year, exception respect of any changes expressly permitted under the terms of any fuel surcharge formula as may be specified.

(5) The Commission may require a licensee or a generating company to comply with such procedures as may be specified for calculating the expected revenues from the tariff and charges which he or it is permitted to recover.

(6) If any licensee or a generating company recovers a price or charge exceeding the tariff determined under this section, the excess amount shall be recoverable by the person who has paid such price or charge along with interest equivalent to the bank rate without

- 75 -

prejudice to any other liability incurred by the licensee.

"64. Procedure for tariff order: ---

(1) An application for determination of tariff under section 62 shall be made by a generating company or licensee in such manner and accompanied by such fee, as may be determined by regulations.

(2) Every applicant shall publish the application, in such abridged form and manner, as may be specified by the Appropriate Commission.

(3) The Appropriate Commission shall, within one hundred and twenty days from receipt of an application under sub-section (1) and after considering all suggestions and objections received from the public,-

(a) issue a tariff order accepting the application with such modifications or such conditions as may be specified in that order;

(b) reject the application for reasons to be recorded in writing if such application is not in accordance with the provisions of this Act and the rules and regulations made thereunder or the provisions of any other law for the time being in force:

Provided that an applicant shall be given a reasonable opportunity of being heard before rejecting his application.

- 76 -

(4) The Appropriate Commission shall, within seven days of making the order, send a copy of the order to the Appropriate Government, the Authority, and the concerned licensees and to the person concerned.

(5) Notwithstanding anything contained in Part X, the tariff for any inter-State supply, transmission or wheeling of electricity, as the case may be, involving the territories of two States may, upon application made to it by the parties intending to undertake such supply, transmission or wheeling, be determined under this section by the State Commission having jurisdiction in respect of the licensee who intends to distribute electricity and make payment therefor.

(6) A tariff order shall, unless amended or revoked, continue to be in force for such period as may be specified in the tariff order."

"Section 86. (Functions of State Commission): ---

(1) The State Commission shall discharge the following functions, namely: -

(a) determine the tariff for generation, supply, transmission and wheeling of electricity, wholesale, bulk or retail, as the case may be, within the State:

Provided that where open access has been permitted to a category of consumers under section 42, the State Commission shall

- 77 -

determine only the wheeling charges and surcharge thereon, if any, for the said category of consumers;

(b) regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State;

(c) facilitate intra-State transmission and wheeling of electricity;

(d) issue licences to persons seeking to act as transmission licensees, distribution licensees and electricity traders with respect to their operations within the State;

(e) promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee;

(f) adjudicate upon the disputes between the licensees, and generating companies and to refer any dispute for arbitration;

(g) levy fee for the purposes of this Act;

- 78 -

(h) specify State Grid Code consistent with the Grid Code specified under clause (h) of sub- section (1) of section 79;

(i) specify or enforce standards with respect to quality, continuity and reliability of service by licensees;

(j) fix the trading margin in the intra-State trading of electricity, if considered, necessary; and

(k) discharge such other functions as may be assigned to it under this Act.

(2) The State Commission shall advise the State Government on all or any of the following matters, namely :-.

(i) promotion of competition, efficiency and economy in activities of the electricity industry;

(ii) promotion of investment in electricity industry;

(iii) reorganization and restructuring of electricity industry in the State;

(iv) matters concerning generation, transmission , distribution and trading of electricity or any other matter referred to the State Commission by that Government.

(3) The State Commission shall ensure transparency while exercising its powers and discharging its functions.

- 79 -

(4) In discharge of its functions, the State Commission shall be guided by the National Electricity Policy, National Electricity Plan and tariff policy published under section 3."

181. Powers of State Commissions to make regulations: ---

(1) The State Commissions may, by notification, make regulations consistent with this Act and the rules generally to carryout the provisions of this Act.

(2) In particular and without prejudice to the generality of the power contained in sub- section (1), such regulations may provide for all or any of the following matters, namely: -

xxxxxx

(3) All regulations made by the State Commission under this Act shall be subject to the condition of previous publication.

11. Regulation No.11 of KERC (TQC for open Access) Regulations, 2004.

"11. Saving of inherent power of the Commission:

(1) Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent power of the Commission to make such orders as may be necessary for meeting

- 80 -

the ends of justice or to prevent the abuse of the process of the Commission.

(2) Nothing in these Regulations shall bar the Commission from adopting a procedure which is at variance with any of the provisions of these Regulations, if the Commission, in view of the special circumstances of a matter or class of matters and for reasons to be recorded in writing, deems it necessary or expedient for dealing with such a matter or class of matters.

(3) Nothing in these Regulations shall, expressly or impliedly, bar the Commission from dealing with any matter or exercising any power under the Act for which no Regulations have been framed, and the Commission may deal with such matters, powers and functions in a manner it thinks fit.

(4) In the exercise of its powers under the Act and in the discharge of its functions, the Commission shall as circumstances may permit, be guided by the principles of natural justice".

12. Order dated 18.08.2014 (Solar) :

On analyzing the discussion paper, suggestions/

comments of Stakeholders on the discussion paper,

promotion of solar power, High Cost of solar power

- 81 -

projects, competitive rates of solar power, Commission

KERC has arrived at a decision and the relevant portion

of the order reads thus:

"In exercise of the powers conferred under clause 11 of the KERC [Terms and Conditions of open access] Regulations, 2004 as amended from time to time and all other powers enabling in this behalf, the Commission hereby orders as follows:

1. All solar power generators in the State achieving commercial operation date [CoD] between 1st April 2013 and 31st March 2018 and selling power to consumers within the State on open access or wheeling shall be exempted form payment of wheeling and banking charges and cross subsidy surcharge for a period of ten years from the date of commissioning. This is also applicable for captive solar power plants for self-consumption within the State.

2. Captive solar power plants opting for Renewable Energy Certificates shall pay the normal wheeling, banking and other charges as specified in the Commission's Order dated 9th October 2013."

- 82 -

13. Order dated 04.07.2014 (Wind and Mini-

hydel):

(1) The Wheeling charges shall be 5% of the injected energy for wind, mini-hydel, Bagasse based co-generation plants and Biomass based projects;

(2) The banking charges shall be 2% of the injected energy and shall be applicable for wind and mini-hydel projects only;

14. Brochure of the Global Investors Meet:

The Brochure of the Global Investors Meet

February 3-5/2016 held at Bengaluru Palace,

Bengaluru provides the key highlights for the Karnataka

Solar Policy 2014-2021 which is quoted under:

• "Government of Karnataka [GoK] on 22nd May 2014 revised its existing State Solar Power Policy with minimum target of 2,000 MW.

• MNRE has revised this target to 6,000 MW to achieve national target of 175 GW. • Planning to achieve 6,000 MW [in phased manner] by 2021 • Grid connected projects - 3,600 MW

- 83 -

• Projects under REC mechanism, captive/group captive, IPPs - No limit • Projects under bundled power • Projects selected by competitive bidding [capacity > 3MW] • Grid connected rooftop projects - 2,400 MW by 2020."

Regarding renewable energy, solar power, it is

assured that industry friendly policies and regulations.

- No cross subsidy surcharge

- No transmission and wheeling charges

- 100% banking for open access projects.

Shelf of projects regarding renewable energy is

stated as under:

"Solar Power: [as per Solar Policy 2014-21] • Ultra Mega Solar Parks having capacity of 500 MW or above are planned as per MNRE guidelines • Solar projects can be installed under IPP model. There are no wheeling and banking charges & cross subsidy for the projects commissioned before 2018 • Government of Karnataka encourages solar parks with area not less than 100 acres through a viable model in backwards districts of Karnataka • Karnataka offers the best policy and tariff in net metering in the country; promotional measures will be taken for increasing

- 84 -

awareness about the advantages of net metering within residential, community, institutional, industrial, and commercial establishments • A new policy for promoting gross metering for commercial and industrial establishments will be published to tap solar power potential.

Wind power:

• Investors are encouraged to set up wind power plants as per the prevailing policies of Karnataka.

• Re-powering of old wind mills having capacity less than 500 KW will be taken up in the State in a pro-active manner for enhancing the existing capacity. In this regard, discussions with investors will be made to frame a new policy document for enhancing wind power potential in the State."

Similar for Mini-hydel project also.

15. Amendment Clause in PPA:

Clause 12.6 of the Wheeling and Banking

agreement reads thus:

"12.6 Amendments:

This Agreement shall not be amended, changed, altered, or modified except by a written instrument duly executed by the authorized representatives of both the Parties and approved by the Commission. However,

- 85 -

the Commission shall be entitled to modify/alter the conditions of this contract [agreement] at the instance of either of the parties, or Suomotu, after giving an opportunity of hearing to all the parties."

16. Clause 5.1 of PPA:

"The Company shall pay all the charges to the Corporation/GESCOM/BESCOM for using their network as per the applicable KERC Regulations/Orders issued from time to time............."

17. Discussion paper - Relevant portion:

In the discussion paper on wheeling and banking

charges for renewable power projects, relevant para 11

reads thus:

"11. Considering that the Orders dated 04.07.2014 and 08.07.2014 relating to wheeling and banking charges are valid upto 31.03.2018, there is a need to take a decision on the wheeling and banking charges that would be applicable for both solar and non- solar power projects under non-REC route from 01.04.2018, onwards. Therefore, the Commission is issuing this Discussion Paper with the proposal for revising the wheeling

- 86 -

and banking charges, as discussed in the subsequent paragraphs."

18. Order Dated 14.05.2018:

Wheeling and Banking Charges for Renewable

Power Projects has been revised in terms of the order of

the KERC dated 14.05.2018 [impugned order]. The

relevant paragraphs of the said order is quoted herein

for ready reference:

"[1] Subject to the terms stated in Paragraph-2 below of this Order, all Renewable Energy Projects [other than the Captive Generators availing of the benefit of the Renewable Energy Certificate (REC)], which have not yet completed 10 [ten] years from the date of commercial operation, as on 31.03.2018, shall be:

[a] liable to pay 25% [twenty five percent] of the normal Transmission Charges and/or Wheeling Charges, payable in cash, as determined by the Commission in its Tariff Orders, issued from time-to-time, transmitting/wheeling electricity using the network of the Transmission Licensee/Distribution Licensee, as the case may be; and,

- 87 -

[b] xxxxx

[c] xxxxx

[2] [a] The Solar Power Projects

commissioned on or earlier to 31.03.2017 shall be continued with the existing concessional Charges.

[b] For the Wind Power Projects commissioned during the period between 10.10.2013 and 03.09.2017, 25% [twenty-five percent] of the normal Transmission Charges and/or Wheeling Charges, in cash, alone shall be levied, exempting the levy of the line loss, in kind;"

(c) The Solar Power Projects commissioned on or earlier to 31.03.2017 shall be continued with the existing concessional charges:

For the Wind Power Projects commissioned during the period between 10.10.2013 and 03.09.2017, 25% (twenty five percent) of the normal Transmission Charges and/or Wheeling charges, in cash, alone shall be levied, exempting the levy of the line loss, in kind.

19. In the background as aforesaid, the points

that arise for consideration before this Court are:

1. Whether the writ petitions are maintainable circumventing the alternative remedy of

- 88 -

appeal provided under Section 111 of the Act?

2. Whether the KERC is estopped from withdrawing the exemption granted on the wheeling and banking charges before the completion of term period by virtue of doctrine of promissory estoppel?

3. Whether the order impugned suffers from discrimination and thus hit by Article 14 of the Constitution of India?

4. Whether existence of judicial member is sine qua non for the Tribunal to pass the orders?

5. Whether in the absence of the Regulation framed under Section 181 of the Act, the KERC is empowered to interfere or revise the wheeling and banking charges with the existing contractual relationship between the regulated entities?

- 89 -

Re: Point No.1

20. In Karnataka Power Transmission

Corporation Ltd. Vs. R.K. Powergen Pvt. Ltd.5 the

Hon'ble Apex Court at paras 14 and 15 has observed

thus:

"14. The next question which requires consideration is assuming that this Court can entertain the Writ Petition notwithstanding there being an alternate and efficacious remedy by way of an appeal before the Tribunal, the Courts are empowered or for that matter have enough machinery to deal with a situation like this. The Apex Court in the case of W.B. Electricity Regulatory Commission v. Cesc Ltd., (Supra) has observed as follows:

"The Commission constituted under Section 17 of the 1998 Act is an expert body and the determination of tariff which has to be made by the Commission involves a very highly technical procedure, requiring working knowledge of law, engineering, finance, commerce, economics and management, It would be more appropriate and effective if a statutory appeal is provided to a similar expert body, so that the various questions which are factual and technical that arise in such an appeal, get appropriate consideration in the first 5 ILR 2005 KAR 5468

- 90 -

appellate stage also. The Central Electricity Regulatory Commission which has a judicial member as also a number of other members having varied qualifications, is better equipped to appreciate the technical and factual questions involved in the appeals arising from the orders of the Commission. Neither the High Court nor the Supreme Court would in reality be appropriate appellate forums in dealings with this type of factual and technical matters. Therefore, it is recommended that the appellate power against an order of the State Commission under the 1998 Act should be conferred either on the Central Electricity Regulatory Commission or on a similar body."

It is brought to my notice that a Appellate Tribunal as contemplated under Section 111 of the Act has already been formed and is functioning. A notification to that effect is also produced. It is also brought to my notice that all three members of the Appellate Tribunal have already been appointed and assumed the office on 13.5.2005. In the circumstances the question of entertaining this petition when there is an alternate and efficacious remedy for redressal of the petitioner's grievance is available there is no reason as to why this Court should exercise its powers under Articles 226 and 227 of the Constitution and deal with the technical matter. In my considered view the grievance of the petitioner should be

- 91 -

decided by the Appellate Tribunal consisting of experts.

15. Another reason as to why this Writ Petition cannot be entertained is because, as stated in the body of the Writ Petition itself, since there is no appellate Tribunal as yet formed, the present Writ Petition is filed. But however during this interregnum, the Appellate Tribunal has already come into effect and is functioning."

The said judgment was rendered in the context of

the company filing the writ petition aggrieved by the

termination of the power purchase agreement wherein

the content of the writ petition disclosed that no

appellate Tribunal was constituted, however during the

pendency of the writ petition, the appellate Tribunal

having been formed and started functioning this court

relegated the generator company to the appellate

jurisdiction.

- 92 -

21. In Whirlpool Corporation vs. Registrar of

Trade Marks Mumbai and others6, the Hon'ble Apex

Court at paras.15 and 20 has held thus:

"15. Under Article 226 of the Constitution, the High Court, having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. But the High Court has imposed upon itself certain restrictions one of which is that if an effective and efficacious remedy is available, the High Court would not normally exercise its jurisdiction. But the alternative remedy has been consistently held by this Court not to operate as a bar in at least three contingencies, namely, where the writ petition has been filed for the enforcement of any of the Fundamental Rights or where there has been a violation of the principle of natural justice or where the order or proceedings are wholly without jurisdiction or the vires of an Act is challenged. There is a plethora of case- law on this point but to cut down this circle of forensic whirlpool, we would rely on some old decisions of the evolutionary era of the constitutional law as they still hold the field.

20. Much water has since flown beneath the bridge, but there has been no corrosive effect on these decisions which though old, continue to hold the field with the result that law as to the jurisdiction of the High Court in entertaining a Writ Petition under Article 226 of the Constitution, in spite 6 Civil Appeal No.5201/1998 (D.D.26.10.98)

- 93 -

of the alternative statutory remedies, is not affected, specially in a case where the authority against whom the Writ is filed is shown to have had no jurisdiction or had purported to usurp jurisdiction without any legal foundation."

22. Thus, it is clear that the self imposed

restrictions of alternative remedy as a bar for

entertaining writ petition is not applicable where the

orders or proceedings are without jurisdiction or where

there has been a violation of the principle of natural

justice or the vires of the Act is challenged or for

enforcement of fundamental rights. Moreover, it is the

discretion of the court to entertain or not. Considering

the issue of wider magnitude involved coming within the

exception clause of entertaining the writ petitions

despite the availability of the alternative remedy, this

Court finds it appropriate to entertain the writ petition

and to adjudicate the matter on merits.

- 94 -

Re: Point No.2

23. The order dated 18.08.2014 of the KERC

Broachers of the Invest Karnataka 2016 as well as the

subsequent orders dated 30.07.2015 and 12.04.2017 of

the KERC indicates the promise/assurance made by the

KERC and the Government of Karnataka inviting the

entrepreneurs/investors across the globe specifying the

exemption/concession on the wheeling and banking

charges with reference to solar projects/wind

projects/mini hydel projects.

Much reliance is placed by the KERC on the

agreement clause at 12.6 which deals with the

amendment. The agreements/ contract in question is

not a mere private contract between private parties. The

State through its instrumentality viz., the KERC has

entered into a contract in exercise of its statutory

powers under the Act which partakes the power of

statutory contract. The contract with

- 95 -

promises/assurances stands on a different footing from

the statutory contract without such

assurances/promises. The statutory agreement

incorporates the earlier orders granting exemption and

concession for a period of ten years from the

commissioning date through all those projects

commissioned before 31.3.2018. The statutory contract

is ameanable to doctrine of promissory estoppel. The

Hon'ble Apex Court in the case of Pawan Alloys &

Casting Private Limited Vs. U.P. State Electricity

Board and others7 held that even though the

companies/appellants have succeeded in convincing

the Court that the earlier notifications contained a clear

promise and representation by the Board to the

prospective new industrialists that once they

established their industries in the region within the

territorial limits of the operation of the Board, they

would be assured 10% rebate on the total bills

7 ((1997)7 SCC page 251)

- 96 -

regarding consumption of electricity by their industries

for a period of three years from the initial supply of

electric power to their concerns, the appellants will not

be enable to enforce the equity by way of promissory

estoppel against the expiry of three years as available to

the appellants concerned. It is also held that even if

such withdrawal of development rebate prior to three

years is not based on any overriding public interest, if it

is shown that by such premature withdrawal the

appellant promises would be restored to status quo ante

and would be placed in the same position in which they

were prior to the grant of such rebate by earlier

notifications the appellants would not be entitled to

succeed. The relevant passages of Pawan Alloys is

extracted hereunder:

" 31. In the light of this settled legal position we, therefore, hold that even though the appellants have succeeded in convincing us that the earlier three notifications dated 29th October 1982, 13th July 1984 and 28th

- 97 -

January 1986, did contain a clear promise and representation by the Board to the prospective new industrialists that once they established their industries in the region within the territorial limits of the operation of the Board, they would be assured 10% rebate on the total bills regarding consumption of electricity by their industries for a period of three years from the initial supply of electric power to their concerns, the appellants will not be able to enforce the equity by way of promissory estoppel against the Board if it is shown by the Board that public interest required it to withdraw this rebate even prior to the expiry of three years as available to the appellants concerned. It has also to be held that even if such withdrawal of development rebate prior to three years is not based on any overriding public interest, if it is shown that by such premature withdrawal the appellant-promisees would be restored to status quo ante and would be placed in the same position in which they were prior to the grant of such rebate by earlier notifications the appellants would not be entitled to

- 98 -

succeed. We, therefore, now proceed to examine these twin aspects of the controversy.

35. Under these circumstances when no public interest was sought to be pressed in service by the Board for withdrawal of this incentive rebate, as seen earlier, the equity which had arisen in favour of the appellants remained untouched and undisturbed by any overwhelming and superior equity in favour of the Board entitling it to withdraw this development rebate in a premature manner leaving these promisees high and dry before the requisite period of three years earlier guaranteed to them by way of development rebate had got exhausted. This takes us to the consideration of the second aspect of the matter.

43. In the view of the High Court despite the equity by way of promissory estoppel being available to the appellants against the Board, as the appellants themselves had agreed by entering into written agreements and contracts with the Board when they took electric connections for

- 99 -

their industries, that the Board had power to change the rate schedules from time to time and to revise them, the appellants were barred from challenging the impugned notification. Now it must be kept in view that as per the incentives offered to the new industries the Board had promised these new industrialists that for three years from the date on which they took electric supply for the first time for their industries they would be given 10% rebate on the total bill of electricity consumption charges for their industries. It is not in dispute that before electric supply could be made available to these new industries who would be new consumers to be enrolled by the Board these consumers had to enter into standard agreements. Such agreements had to be signed and entered into by all the prospective consumers whether they were covered by any incentive scheme or not. It is also an admitted position that all the appellants while taking electric connections for the first time for their new industries established by them in the region relying upon the incentives offered by the Board,

- 100 -

entered into such written agreements in standard forms. The relevant clauses of these agreements on which strong reliance was placed by the High Court of non-suiting the appellants, deserve to be extracted in extenso at this stage :

"7. (a). The consumer shall pay for the supply of electric energy at the rates enforced by the supplier from time to time as may be applicable to the consumer.

(b) The Rate Schedule applicable to the consumer at the time of execution of this agreement is annexed hereto as Annexure-2.

(c) The Rate Schedule above mentioned, may, at the discretion of the supplier, be revised by the supplier from time to time and in the case of revision, the Rate Schedule so revised shall be applicable to the consumer."

According to the High Court once the consumers agreed to the authority of the Board to revise earlier rate schedule which was existing at the time of the agreement and as item 8 was a part and parcel of the said rate schedule implicit in Clause 7(c) was the

- 101 -

agreement by the appellant-consumers that the Board will be able to tinker with or even wholly withdraw the development rebate earlier made available as per the said item 8 of the rate schedule.

51. It is difficult to appreciate how the High Court could persuade itself to hold in the light of Clause 7(c) that the appellants while signing such agreements for taking electricity supply for the first time for their new industries as if by sidewind agreed of give up their right to claim development rebate by handing over on a platter an absolute right to the Board to totally withdraw such development rebate at any time it liked before the three years' period, for which incentive was meant to be guaranteed, would have expired. On the express language of Clause 7(a), (b) and (c) such a conclusion is impossible to be arrived at.

54. It would be totally absurd and incongruous to suggest on behalf of the Board that on the one hand it guaranteed to the new industrial units for a period of three years from the date of commencement of supply

- 102 -

10% development rebate of the total amount of the bill and on the other hand moment such supply started pursuant to the written agreement the very incentive could be withdrawn by it from its inception as new industrial unit had to sign a written agreement containing Clause 7 (a), (b) and (c). If that submission on behalf of the Board which appealed to the High Court is accepted a most incongruous, unreasonable and absurd result would follow. It can then be said that the Board on the one hand had given incentive to new industries by guaranteeing development rebate of 10% on the total bill of consumption of electricity for a period of three years from the date of commencement of supply but from the very inception of that period the Board on the other hand as per the very agreement with the promisee was enabled to immediately withdraw the very same development rebate in exercise of its contractual powers as per clause 7(c) of that very agreement. If that happens the Board would be giving on the one hand incentive to new industries by way

- 103 -

of development rebate of 10% and by another hand would immediately and almost simultaneously be withdrawing the said incentive by pinning down the consumer to the terms of the agreement as found at clause 7(a), (b) and (c). This would result in a total exercise in futility. The incentive development rebate scheme would in such an eventuality be still-born. It is also easy to visualize that a new industrial unit which spends large amounts for establishing its infrastructure and gets lured in the light of the representation held out by the Board and establishes its plant and machinery in the new unit, would not simultaneously and voluntarily agree by signing such an agreement with the Board to give up the very same benefit of incentive by permitting the latter to withdraw it at any time it likes. That would be doing violence to common sense and business approach of an ordinarily prudent businessman. No businessman in his senses would ever voluntarily to such an absurd, incongruous and inconsistent predicament.

- 104 -

62. As a result of the aforesaid discussion on these points the conclusion becomes inevitable that the appellants are entitled to succeed. It must be held that the impugned notification of 31st July 1986 will have no adverse effect on the right of the appellant-new industries to get the development rebate of 10% for the unexpired period of three years from the respective dates of commencement of electricity supply at their units from the Board with effect from 1st August 1986 onwards till the entire three years period for each of them got exhausted. This result logically follows for the appellants who have admittedly entered into supply agreements with the Board as new industries prior to 1st August 1986. However those appellants who entered into such agreement after 1st August 1986 cannot get benefit of development rebate any longer after 1st August 1986. This conclusion of ours pertains to the question which is no longer res integra. It is already so held by this Court in S.L.P. (C) No. 11906 of 1994 and others decided by a Bench of this Court consisting of A.M.

- 105 -

Ahmadi, CJ. (as His Lordship then was) and S.P. Bharucha, J., in the case of Hotz Hotel Pvt. Ltd. Etc. Etc./Vaidya Ply Board & Anr. v. U.P.S.E.B. & Anr. Etc. Etc. on 3rd October 1994. We find that the appellant in Civil Appeal No. 1713 of 1991 executed agreement with the Board for the first time on 5th May 1987. Similarly appellant in Civil Appeal No. 3534 of 1991 executed agreement with the Board for the first time after 1.8.1986. These appellants, therefore, will not be entitled to get out of the sweep of the impugned notification. These appeals will, therefore, have to be dismissed."

24. In the present set of facts, it is not in dispute

that as per the exemption offered to the RE plants the

KERC had promised the petitioners that for 10 years

from the date on which they commissioned the solar

projects, they would be exempted from wheeling and

banking charges. Concession of tariff was granted with

respect to wind/Mini hydel projects.

- 106 -

25. The statutory contract has been signed and

entered with the State through its instrumentality, the

KERC. It would not be justifiable on behalf of the

Commission that on guarantying the

exemption/concession of wheeling and banking charges

to the new RE projects who have commissioned the said

projects on or before 31.3.18 and on the other hand, to

withdraw the said exemption based on the agreement

clause. A new solar/wind/mini hydel project unit which

spends huge amounts for establishing its infrastructure

in view of the promise/assurance made by the

Commission and after certain period to withdraw the

said exemption subcategorizing the projects who

invested and commissioned before 31.3.2017 and after

31.3.2017 would be incongruous and hit by Article 14 of

the Constitution and the principles of promissory

estoppel. In this context, the objections filed by the

KERC do not establish any supervening public interest

that prevailed to withdraw the exemption even prior to

- 107 -

the 10 years period as available to petitioners

concerned. Neither in the impugned order nor in the

statement of objections filed by the KERC no

satisfactory reasons of public interest warranting such

withdrawal is cited. In the absence of supervening

public interest established by the KERC, withdrawing of

the exemption/concession in a premature manner

giving the assurances/promises a go-by before the

requisite period of 10 years guaranteed by the orders

dated 14.07.2014 and 18.8.2014 of the KERC as well as

the global investment brochure issued by the Energy

Department, Government of Karnataka to attract the

investors cannot be left in lurch in the mid stream. It is

also not possible for the promisee now to restore back to

the original status after acting up on the

promises/assurances made. Once the new

solar/wind/mini hydel plants have been invited by

projecting exemption/concession on wheeling and

banking charges in the State of Karnataka and being

- 108 -

assured with 10 years guarantee on such

exemption/concession and acting on the same and the

promisee established their projects and spend lot of

amount for constructing the infrastructure and the

related employment expenses, it would be difficult for

them to restore the status quo ante and walk out mid

stream relating to the unexpired period out of the ten

years guaranteed. Thus the twin tests propounded by

the Hon'ble Apex Court in Pawan Alloys, supra is not

satisfied by the KERC to disown the Doctrine of

promissory estoppel.

26. The arguments advanced by the learned

AGA, that the Global Investors Meet brochures is not a

state policy and any promise or assurance made in such

investors meet would not be binding on the State,

requires to be negated. All such assurances/promises

were made in the brochures in invest Karnataka 2016

GIM declaring and reiterating the availability of the

- 109 -

benefits of wheeling, banking and cross subsidy

surcharge for all RE plants commissioned between

1.4.2013 and 31.3.2018. Even in the solar policy of the

Government 2014 to2021, the tariff shall be applicable

as fixed by the KERC.

27. The contention of the respondent-state as

well as the KERC that the principles of promissory

estoppel enunciated in the case of Motilal Padmat

Sugar Mills Vs. State of U.P. reported in (1979)2

SCC 409 has been diluted in Jit Ram and others Vs.

State of Haryana - AIR 1988 SC 1285 is

unsustainable. The principles laid down in Motilal

Padmat Sugar Mills still holds the field as held by the

Hon'ble Apex Court in Nestle India Limited.

In the case of State of Punjab V/s. Nestle India

Ltd.,8 the Hon'ble Apex Court has held thus:

"34. The discordant note struck by Jit Ram case [[1981] 1 SCC 11 : [1980] 3 SCR 8 [2004] 6 SCC 465

- 110 -

689] was firmly disapproved by a bench of three Judges in Union of India & Ors. v. Godfrey Philips India Ltd. (1985) 4 SCC 369. It was affirmed that: [SCC p.387, para 12] "12. There can therefore be no doubt that the doctrine of promissory estoppel is applicable against the Government in the exercise of its governmental, public or executive functions and the doctrine of executive necessity or freedom of future executive action cannot be invoked to defeat the applicability of the doctrine of promissory estoppel".

46. In any event judicial discipline requires us to follow the decision of the larger Bench. The facts in the present case are similar to those of prevailing in Godfrey Philips (supra). There too, as we have noted earlier, the statutory provisions require exemption to be granted by notification. Nevertheless, the Court having found that the essential pre-requisites for the operation of promissory estoppel had been established, directed the issuance of the exemption notification.

47. The appellants have been unable to establish any overriding public interest which would make it inequitable to enforce the estoppel against the State Government. The representation was made by the highest authorities including the Finance Minister in his Budget Speech after considering the financial implications of the grant of the

- 111 -

exemption to milk. It was found that the overall benefit to the state's economy and the public would be greater if the exemption were allowed. The respondents have passed on the benefit of that exemption by providing various facilities and concessions for the upliftment of the milk producers. This has not been denied. It would, in the circumstances, be inequitable to allow the State Government now to resile from its decision to exempt milk and demand the purchase tax with retrospective effect from 1-4-1996 so that the respondents cannot in any event re-adjust the expenditure already made. The High Court was also right when it held that the operation of the estoppel would come to an end with the 1997 decision of the Cabinet."

It is thus held that the speech made by the

Finance Minister after considering financial implications

of the grant of the exemption to milk is binding on the

State and it would be inequitable to allow the State

Government to resile from its decision applying the

principles of promissory estoppel.

28. The orders dated 30.7.2015 and 12.4.2017

of the KERC confirms, reiterates the benefits of

exemption allowed in wheeling, banking and cross

- 112 -

subsidy surcharge and confirms the continuity of the

same in terms of clause 'd' of the order dated 30.7.2015

and 12.4.2017 which reads thus:

Order dated 30.7.2015:

" (d) Applicability of wheeling and banking charges and cross subsidy surcharge:

The Wheeling, Banking and Cross Subsidy surcharge shall be applicable as per Commission's Order dated 18th August 2014."

Order dated 12.4.2017:

" (d) Applicability of wheeling and banking charges and cross subsidy surcharge:

A stakeholder has sought clarification as to, whether the exemption allowed in Wheeling,

Banking and Cross Subsidy surcharge would continue with the new tariff order.

The Commission hereby clarifies that the tariff Order is to determine the applicable tariff for Solar PV plants coming in the State during FY 18 and

- 113 -

the Wheeling, Banking and Cross Subsidy surcharge shall remain

applicable as per Commission's Order dated 18th August 2014."

29. In such circumstances, the change of

circumstances pleaded by the KERC to contend that the

doctrine of promissory estoppel is not applicable to the

petitioners inasmuch as the installation capacity of

solar power which was 41 MW as on 18.8.2014 has

increased to 1698 MW as on November 2017 and it is

anticipated to touch 6000 MW by the end of financial

year 2019 would not be countenanced as the increase in

the capacity has happened with the consent of the

Government of Karnataka, KERC and the ESCOMS and

they having permitted such an increase in the capacity,

having achieved their objective of increasing RE power,

the benefits granted to the power projects cannot be

withdrawn against the interest of the petitioners more

particularly in view of the clarification issued by the

- 114 -

orders dated 30.07.2015 and 12.04.2017. Such

withdrawal of exemption would be against the public

interest also, inasmuch as, if such exemptions are

withdrawn, not only it would affect the financial viability

of the petitioners but also would make the petitioners

suffer monetary loss of huge amount thereby affecting

the economy as such as the loans which could run into

thousands of crores of rupees given to the various power

generators could not be recovered and the very

financial equilibrium of economy would be in peril. The

action of the banks refraining from altering the existing

guidelines for commissioned projects pursuant to the

impugned order if considered, indeed public interest

would suffer owing to the incapacity of the power

projects repaying the loans borrowed by the banks.

These power plants have a long gestation period

spanning across 25 years. The concessions are only for

10 years. A cooling period or tariff holiday cannot be

- 115 -

withdrawn and trap the investors after securing the

investments.

In the aforesaid circumstances, placing reliance on

clauses 5 and 12.6 of the PPA, the statutory contract

cannot be revised by the KERC much against the

promises/assurances made. The doctrine of promissory

estoppel is squarely applicable in the present fact

situation.

Re: Point No.3

30. The RE generators obviously constitute a

homogeneous single class. The orders dated

14.07.2014 and 18.8.2014 recognized all the wind/mini

hydel/solar power generation commissions from

1.4.2013 to 31.3.2018 as one single class without any

sub-classification. The sub-classification now sought

to be made upto 31.3.2017 and withdrawing the

classification after 1.4.2017 is nothing but an artificial

classification without any basis and is perverse. No

- 116 -

doubt the learned Senior counsel appearing for the

KERC made an endeavour to argue that the capital cost

of the projects has drastically come down and the

petitioners are making super profits, the same cannot

be a ground for sub-classification.

31. In order to examine the sub-classification

whether is hit by Article 14 of the Constitution, it is apt

to refer to the relevant passage in the case of Dharam

Dutt and Others V/s. Union of India and Others

reported in [2004] 1 SCC 712, the same is quoted

hereunder:

"56. Article 14 of the Constitution prohibits class legislation and not reasonable classification for the purpose of legislation. The requirements of the validity of legislation by reference to Article 14 of the Constitution are: that the subject matter of legislation should be a well-defined class founded on an intelligible differentia which distinguishes that subject-matter from the others left out, and such differentia must have a rational

- 117 -

relation with the object sought to be achieved by the legislation. The laying down of intelligible differentia does not, however, mean that the legislative classification should be scientifically perfect or logically complete."

32. It is thus clear that two factors have to be

fulfilled to uphold the validity of sub-classification by

reference to Article 14 of the Constitution viz., the

subject matter classification should be founded on an

intelligible differentia which distinguishes that subject

matter from the others left out and secondly, such

differentia must have a rational nexus with the object

sought to be achieved. That a RE power plant has a

long gestation period across about 25 years. Before

concessional period, the proposal was in order of 3 MW

and after the withdrawal it is around 30 MW, but during

the concessional period it attracted an investment of

2000 MW. It is thus self evident that the investments

had come into the State only because of the exemption

or tariff holiday. Inviting the investors with incentive of

- 118 -

exemption on wheeling and banking charges and then

turning round making sub categorization between the

projects commissioned between 1.4.2013 to 31.3.2017

and the projects commissioned between 1.4.2017 to

31.3.2018 is not a reasonable classification. The same

fails to withstand the test of intelligible differentia.

There is no rational nexus to the objective to be

achieved in sub-classifying a homogenous class. As

could be seen from the details furnished by the

petitioners, to commission the project between

1.4.2017 to 31.3.2018, the process had begun during

2015-16 and finally the commissioning certificates were

issued between 1.4.2017 and 31.3.2018. If a uniform

scheme had been applied for all the projects

commissioned between 1.4.2013 and 31.3.2018 that

would have been different aspect but discriminating the

RE plants commissioned between 1.4.2017 to 31.3.2018

would be discriminatory and cannot be approved.

- 119 -

33. Several judgments referred to, by the

learned Senior counsel for the ESCOMS to contend that

a cut off date prescribed by the Commission, will not

invalidate the order impugned, would relate to the

service matters. Fixing a cut off date in the service

matters stands on a different footing with respect to the

investment made by the entrepreneurs based on the

promise/assurance given by the State.

Re: Point No.4

34. This issue is no more res integra in view of

the dictum enunciated by the Hon'ble Apex Court in the

case of Utility Users Welfare Association and others,

supra, and the clarificatory order thereto. Moreover, it is

not in dispute that the Tribunal is now functioning with

the judicial members.

Re: Point No.5

35. In the case of the Gujarat Urja Vikas

Nigam Limited V/s. Tarini Infrastructure Limited

- 120 -

and others9, the Hon'ble Apex Court conceding the

contention of the appellant Tharini Infrastructure

Limited, that under Clause 5[2] of the PPA wherein the

appellant therein, was required to pay tariff as

determined by the State Commission which would liable

to escalation at 3% per annum and accordingly sought

for the novation of the PPA to the extent of modification

of tariff observed thus:

18. All the above would suggest that in view of Section 86(1)(b) the Court must lean in favour of flexibility and not read inviolability in terms of the PPA insofar as the tariff stipulated therein as approved by the Commission is concerned. It would be a sound principle of interpretation to confer such a power if public interest dictated by the surrounding events and circumstances require a review of the tariff. The facts of the present case, as elaborately noted at the threshold of the present opinion, would suggest that the Court must lean in favour of such a view also having due regard to the provisions of Sections

9 [2016] 8 SCC 743

- 121 -

14 and 21 of the General Clauses Act, 1897. In this context, the views of this Court on the purport and effect of Sections 14 and 21 of the General Clauses Act may be re-noticed by extracting paras 47, 48 and 49 of the decision of this Court in D.K. Trivedi & Sons Vs. State of Gujarat.

As discussed in the preceding paragraphs there is no request made by either of the parties to the revision of the tariff on wheeling and banking charges but it is the suo motu action unilaterally initiated by the KERC to withdraw the exemption of tariff granted on wheeling and banking charges.

36. In PTC India Limited, supra, the Hon'ble

Apex Court has held thus:

58. One must understand the reason why a regulation has been made in the matter of capping the trading margin under Section 178 of the Act. Instead of fixing a trading margin (including capping) on a case-

to-case basis, the Central Commission thought it fit to make a regulation which has a

- 122 -

general application to the entire trading activity which has been recognized, for the first time, under the 2003 Act. Further, it is important to bear in mind that making of a regulation under Section 178 became necessary because a regulation made under Section 178 has the effect of interfering and overriding the existing contractual relationship between the regulated entities. A regulation under Section 178 is in the nature of a subordinate Legislation. Such subordinate Legislation can even override the existing contracts including Power Purchase Agreements which have got to be aligned with the regulations under Section 178 and which could not have been done across the board by an Order of the Central Commission under Section 79(1)(j).

66. While deciding the nature of an Order (decision) vis-a-vis a Regulation under the Act, one needs to apply the test of general application. On the making of the impugned Regulations 2006, even the existing Power Purchase Agreements ("PPA") had to be

- 123 -

modified and aligned with the said Regulations. In other words, the impugned Regulation makes an inroad into even the existing contracts. This itself indicates the width of the power conferred on CERC under Section 178 of the 2003 Act. All contracts coming into existence after making of the impugned 2006 Regulations have also to factor in the capping of the trading margin. This itself indicates that the impugned Regulations are in the nature of subordinate legislation. Such regulatory intervention into the existing contracts across-the-board could have been done only by making Regulations under Section 178 and not by passing an Order under Section 79(1)(j) of the 2003 Act. Therefore, in our view, if we keep the above discussion in mind, it becomes clear that the word "order" in Section 111 of the 2003 Act cannot include the impugned 2006 Regulations made under Section 178 of the 2003 Act.

92. (i) In the hierarchy of regulatory powers and functions under the 2003 Act,

- 124 -

Section 178, which deals with making of regulations by the Central Commission, under the authority of subordinate legislation, is wider than Section 79(1) of the 2003 Act, which enumerates the regulatory functions of the Central Commission, in specified areas, to be discharged by Orders (decisions)".

37. The Hon'ble Apex Court in Gujarath Urja

Vikas Nigam Limited, supra has held that under

regulations 80 to 82, the inherent powers of the State

Commission which is akin to Section 151 of CPC, the

power of the State Commission to regulate the conduct

of the Commission i.e. to regulate its own procedure,

the power cannot travel so as to alter the terms and

conditions of the agreement entered into between the

parties to grant substantive relief to the company by

extending the control period of tariff order. In terms of

Regulation 80, the inherent powers of the State

Commission are saved to make such orders as may be

- 125 -

necessary:- (i) to secure the ends of justice; and (ii) to

prevent abuse of process of the Commission. The

inherent powers under Section 151 CPC are procedural

in nature and cannot affect the substantive right of the

parties. Hence inherent powers preserved under

regulation 80 cannot affect a substantive right of the

parties. This dictum with all force applies to the

proceedings at hand.

It is the contention of the Commission and the

State that the Commission has been conferred with the

power to determine the tariff from time to time and it

cannot be said that the Commission is functus officio

once it has determined the price. The phrase 'time to

time' emphasized would only mean that the KERC can

determine wheeling and banking charges prospectively.

Sections 62 and 64 conferred the power on the

Commission to determine the tariff and once settled

contracts have been entered into, based on the tariff

- 126 -

orders, sans any request made by the either of the

parties to the PPA, the KERC has not been conferred

with the power to determine tariff from time to time.

38. Thus, the power of KERC to revisit the tariff

at the request of the regulated entities though is

traceable to Section 21 of the General Clauses Act, 1897

in terms of the judgment of the Hon'ble Apex Court in

the case of Shree Sidhabali Steel Vs. State of Uttar

Pradesh 10 as well as Tarini Infrastructure Limited

and Others, supra, considering the wider impact of

withdrawing the exemption/concession by the KERC

suo moto as observed by the Hon'ble Apex Court in PTC

India Limited, supra and Gujarat Urja Vikas Nigam

Limited, supra, inasmuch as exercising the inherent

powers in terms of Regulation No.11 of OA Regulations,

Regulation under Section 181 would have been

appropriate which has a general application to the

entire trading activity.

10 (2011)3 SCC 193

- 127 -

Writ Petition Nos.23086/2018, 23116/2018,

23990 to 23993/2018, 23995/2018, 25090/2018,

26480/2018 and 28622/2018 pertain to the wind

project.

Writ Petition Nos.53531/2018 and 23994/2018

pertain to Mini-hydel project.

All other writ petitions relate to the solar projects.

Conclusion:

For the aforegoing reasons, all the writ petitions

are allowed.

The impugned order dated 14.05.2018 issued by

the KERC, Bengaluru is quashed.

No order as to costs.

Sd/-

JUDGE

Dvr/NC:

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free