Miss Lucy
← All judgments

Raza Ahmad vs State Of Chhattisgarh .

Supreme Court7 March 2022Surya Kant · Dhananjaya Y Chandrachud

Ratio decidendi

The rule this decision rests on

1. A challenge to an Environmental Clearance issued before the commencement of the National Green Tribunal Act 2010, which is sought to be raised for the first time before the NGT after three years from the date of publication of the clearance, is barred by the six-month limitation period prescribed under Section 14(3) of the NGT Act, and does not stand transferred to the NGT under Section 38(5) of the NGT Act where no challenge was pending before the National Environment Appellate Authority at the time of commencement of the NGT Act. 2. A challenge to a state government notification altering land use on the ground that such alteration would violate conditions imposed in an Environmental Clearance issued under the Environment (Protection) Act 1986 may constitute a substantial question relating to the environment arising out of the implementation of the 1986 Act, and may therefore fall within the original jurisdiction of the NGT under Section 14 of the NGT Act, even though the notification itself derives from a state urban planning statute not listed in Schedule I of the NGT Act. 3. The six-month limitation period under Section 14(3) of the NGT Act for original jurisdiction may be extended by condonation of delay up to sixty days for sufficient cause, and where a writ petition is instituted within the limitation period but transferred to the NGT after the expiry of that period, the question of whether the delay should be condoned is a matter within the discretion of the NGT to determine.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

Reportable

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

Civil Appeal No 2804 of 2014

Raza Ahmad .... Appellant(s)

Versus

State of Chhattisgarh & Ors ....Respondent(s)

JUDGMENT

Dr Dhananjaya Y Chandrachud, J

1 This appeal under Section 22 of the National Green Tribunal Act 2010 1 arises

from a judgment dated 2 August 2013 of the National Green Tribunal 2, at its

Central Zone Bench in Bhopal.

2 In April 2007, the seventh respondent, Steel Authority of India 3, and Jayprakash

Associates entered into a Memorandum of Association to establish a cement

grinding unit of 2.2 MTPA capacity at Bhilai, Chhattisgarh. In pursuance of this

goal, they set up the tenth respondent, Bhilai Jaypee Cement Limited. A parcel of

land admeasuring 34.59 acres belonging to SAIL, falling in the villages of Hingna

Signature Not Verified and Maroda at Bhilai in District Durg, was leased out to the tenth respondent for Digitally signed by Sanjay Kumar Date: 2022.03.12 11:33:31 IST thirty years, based on a long-term lease dated 16 June 2007. The land use of this Reason:

1 “NGT Act” 2 “NGT” 3 “SAIL” 2

parcel of land had been designated as “green belt” in the 1991 Development

Plan of Bhilai. On the tenth respondent’s application, an Environmental

Clearance4 was granted to their project of the cement grinding unit on 1 May

20085 by the second respondent, the then Ministry of Environment and Forests.

It was subsequently published in newspapers on 8 May 2008.

3 It is alleged by the appellant that since the EC was incorrectly issued, the tenth

respondent’s constructions on the parcel of land were illegal. In this regard,

several notices were issued to them by the fifth respondent, Director, Town and

Country Planning, Bhilai and the sixth respondent, Commissioner, Municipal

Corporation of Bhilai to revert the land to its original condition or face demolition

of the structure. The tenth respondent then applied for the modification of the

land use of the parcel of land admeasuring 34.59 acres.

4 The first respondent, the State of Chhattisgarh, considered their case under

Section 23-A of Chhattisgarh Nagar Tatha Gram Nivesh Adhiniyam 1973. On 22

May 2010, the State government made a proposal to change the land use from

“green belt” to “industrial purpose” on the basis that the setting up of the

cement grinding unit by the tenth respondent constituted an “urgent public

purpose”. Between 13 July 2010 and 15 July 2010, the State government

published circulars in two evening newspapers highlighting the proposed

modification in land use and inviting objections/suggestions from the general

public. The appellant allegedly raised objections against the proposed

modification. However, relying on the EC granted on 1 May 2008, the State

government issued a notification 6 dated 3 February 2011 modifying the land use

of the parcel of land from “green belt” to “industrial purpose”. The notification

was published in the Chhattisgarh Gazette on 18 February 2011.

4 “EC” 5 Letter No J-1101111000112007-IA-ll(I) 6 Notification No F/7-24/32/2010 3

5 The appellant then instituted a public interest petition 7 under Article 226 of the

Constitution before the High Court of Chhattisgarh on 8 September 2011. The

reliefs which were sought by the appellant were:

(i) Quashing of the notification dated 3 February 2011 of the State

government modifying the land use of the parcels of land designated in

the 1991 Development Plan of Bhilai as a “green belt” to “industrial

purpose”;

(ii) Quashing of the EC issued on 1 May 2008 to the tenth respondent for its

cement grinding unit (the ground of challenge being that the project had

been erroneously categorized in Category B2 instead of Category A, and

hence the mandatory procedures of conducting an Environmental Impact

Study and public hearing/consultation were not followed); and

(iii) The restoration of 34.59 acres of land designated as a “green belt”, which

was leased out to the tenth respondent, to its original condition prior to

the construction which was carried out on the land.

6 An objection was raised in regard to the maintainability of the petition before the

High Court by the tenth respondent.

7 By an order dated 28 January 2013, the High Court transferred the petition to

the NGT in view of the decision of this Court in Bhopal Gas Peedith Mahila

Udyog Sangathan v Union of India8. The NGT, by its impugned judgment

dated 2 August 2013, dismissed the appeal 9 on the ground that:

(i) The appeal is barred by limitation; and

7 Writ Petition (PIL) No 5467 of 2011 8 (2012) 8 SCC 326 9 Appeal No 1 of 2013 4

(ii) The NGT is constituted by the NGT Act, and does not have jurisdiction to

entertain a challenge to the notification dated 3 February 2011 of the

State government altering the land use.

8 We have heard Dr Surender Singh Hooda, counsel appearing on behalf of the

appellant, Mr Yashraj Singh Deora, counsel appearing on behalf of the seventh

respondent and Mr Sumeer Sodhi, counsel appearing on behalf of the State of

Chhattisgarh.

9 The NGT Act came into force on 18 October 2010, after it was published in the

Gazette of India in pursuance of the provisions of Section 1(2). The NGT has

original jurisdiction, conferred by Section 14 and appellate jurisdiction, which is

conferred by Section 16. Further, Section 15 empowers the NGT to grant relief to

remedy environmental damage, including compensation and restitution.

10 Section 14 empowers the NGT to exercise jurisdiction over all civil cases where a

substantial question relating to the environment (including enforcement of any

legal right relating to the environment) is involved and such a question arises

out of the implementation of the enactments specified in Schedule I. Sub-Section

(3) of Section 14 provides that no application for adjudication of a dispute under

the provision shall be entertained unless it is made within a period of six months

from the date on which the cause of action for such dispute first arose. Under

the proviso, the NGT is empowered to entertain an appeal beyond the prescribed

period for sufficient cause, subject to a limit of sixty days.

11 Section 16, which confers appellate jurisdiction on the NGT, contemplates in

Clause (h) that an appeal can lie against an order made, on or after the

commencement of the NGT Act, granting an EC. Such an appeal has to be filed

within thirty days from the date of the communication of the order, decision,

direction or determination. The NGT is entrusted with the power to condone a 5

delay of a period not exceeding sixty days, for sufficient cause.

12 In the present case, the relevant dates which would have a bearing on the

subject matter of the controversy are as follows:

(i) 1 May 2008 – EC was granted to the tenth respondent’s project

(subsequently published in the newspapers on 8 May 2008);

(ii) 18 February 2011 – publication of the notification dated 3 February 2011

by the State government proposing a modification of land use for 34.59

acres of land from “green belt” to “industrial purpose”;

(iii) 8 September 2011 – institution of the writ petition before the High Court

by the appellant; and

(iv) 28 January 2013 – transfer of the proceedings to the NGT by the High

Court.

13 Section 38(1) of the NGT Act stipulates that the National Environment Tribunal

Act 1995 and the National Environment Appellate Authority Act 1997 10 would

stand repealed. Section 38(2) protects anything done or any action taken under

the repealed enactments. Section 38(3) dissolved the National Environment

Appellate Authority established under the above 1997 Act. Section 38(5),

however, makes a provision for the transfer of all cases pending before the

National Environment Appellate Authority to the NGT.

14 In the present case, the EC was issued on 1 May 2008, prior to the enforcement

of the NGT Act. No steps were taken by the appellant to pursue a challenge to

the EC under the provisions of the 1997 Act. No challenge was pending on the

date of the enforcement of the NGT Act and hence, there was no question of

10 “1997 Act” 6

transfer of any proceedings to the NGT. The challenge before the High Court to

the EC was raised on 8 September 2011, well beyond three years of the date of

the publication of the EC in the newspapers on 8 May 2008. Consequently, the

challenge to the EC was barred by limitation. As a matter of fact, Dr Surender

Singh Hooda has fairly accepted the said position.

15 However, the submission which has been urged on behalf of the appellant is that

besides challenging the EC, the appellant had also placed in issue the validity of

the notification of the State government dated 3 February 2011 (published on 18

February 2011), by which the use of the land was sought to be altered to

“industrial purpose”. The NGT came to the conclusion that this part of the

notification was beyond its jurisdiction since the Town and Country Planning Act

1973 of the State of Chhattisgarh is not one of the notified statutes in relation to

which it has jurisdiction. To challenge this finding, it has been urged on behalf of

the appellant that the appellant, for the purpose of the said relief, does not

challenge the EC, but asserts that the conditions of the EC would stand violated

by the change of land use. In this context, reliance has been placed on the

following conditions of the EC:

“ix. As proposed, green belt shall be developed in 4.62 ha (33 %) out of total 14 ha area to reduce impact of fugitive emissions. Central Pollution Control Board guidelines shall be followed in planning and developing green belt and selection of species etc.

x. Other necessary statutory clearances from the concerned Departments including 'No Objection Certificate’ from the Chhattisgarh Environment Conservation Board (CECB) shall be obtained prior to commencement of construction and/or operation.”

16 The submission is that the EC has been issued in pursuance of the EIA

notification, which in turn traces its source of power to the Environment 7

(Protection) Act 198611. The 1986 Act is a statute which is listed at Entry 5 of

Schedule I of the NGT Act. Thus, it has been submitted that any breach of the EC

by a proposed change of land use can be made the foundation for invoking the

remedy before the NGT. Moreover, it has been urged that it was open to the

appellant to invoke the jurisdiction under Section 14 of the NGT Act for

contending that the change of land use notification dated 18 February 2011

would result in a violation of the EC conditions noted above and this could be

remedied before the NGT in the exercise of its original jurisdiction under Section

14. It has been urged that Parliament has given overriding force to the NGT Act

by Section 33.

17 The notification in question by which the change of land use was proposed was

published on 18 February 2011. The writ petition before the High Court was

instituted on 8 September 2011. In terms of Section 14 of the NGT Act, any

recourse to the original jurisdiction of the NGT has to be taken within a period of

six months from the date on which the cause of action of such dispute first

arose. The NGT has the power to condone a delay of a further period not

exceeding sixty days. Between 8 September 2011, when the writ petition was

instituted, and 28 January 2013, when the High Court transferred the

proceedings, the appellant was agitating the issue before the High Court. In the

event that the NGT considers that the appellant has shown sufficient cause

within the meaning of the proviso to sub-Section (3) of Section 14, the institution

of the proceedings on 8 September 2011 would fall within the period of

limitation as specified in sub-Section (3) of Section 14 read with its proviso.

18 Mr Sumeer Sodhi, counsel appearing on behalf of the State of Chhattisgarh,

submitted that, in the present case, the appellant had invoked the appellate

jurisdiction of the NGT under Section 16, which is why the proceedings were not

11 “1986 Act” 8

numbered as an OA, but as an appeal.

19 What seems to have transpired is that the appellant had instituted a writ petition

in the High Court under Article 226 of the Constitution, which was transferred to

the NGT and upon transfer, the proceedings were numbered as an appeal. The

reliefs which were claimed, as already noted earlier, involved a challenge to the

EC as well as a challenge to the notification dated 3 February 2011, by which the

use of the land was proposed to be changed to “industrial purpose”. The

challenge to the EC, as we have already noted above, is barred by limitation.

However, the challenge to the change of land use, on the ground that such a

change would violate a condition of the EC, is something which in the submission

of the appellant would fall within the jurisdiction of the NGT provided the NGT

decides to exercise its discretion to condone the delay within the meaning of

Section 14(3) read with its proviso. Whether the delay should be condoned is

entirely a matter for the NGT to decide.

20 We accordingly issue the following directions:

(i) The challenge to the EC dated 1 May 2008 is barred by limitation;

(ii) The proceedings are remitted back to the NGT for determining as to

whether the challenge to the proposed modification of the land use to

“industrial purpose” through the notification dated 3 February 2011 can be

entertained within the extended period as prescribed by the proviso to

Section 14(3) of the NGT Act;

(iii) The NGT, in considering the aspect which is referred to in (ii) above, shall

be at liberty to determine whether sufficient cause has been shown by the

appellant for condoning the delay; and 9

(iv) We clarify that we have not expressed any opinion on the merits of the

rival contentions. Should the delay be condoned, the NGT would be at

liberty to take a decision on all the issues and contentions raised by the

rival parties.

21 The appeal shall stand partly allowed in the above terms with no orders as to

costs.

22 Pending application(s), if any, stand disposed of.

…..…..…....…........……………….…........J. [Dr Dhananjaya Y Chandrachud]

…..…..…....…........……………….…........J. [Surya Kant]

New Delhi;

March 07, 2022

-S-

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free