Miss Lucy
← All judgments

R.S.Sehrawat vs Rajeev Malhotra

Supreme Court5 September 2018Chief Justice · A.M. Khanwilkar · D.Y. Chandrachud

Ratio decidendi

The rule this decision rests on

In contempt proceedings, the court must frame and formally convey specific charges to the alleged contemnor, and the alleged contemnor is entitled to all safeguards afforded in criminal proceedings, including the benefit of doubt and the protection of the standard of proof beyond reasonable doubt. When an alleged contemnor's affidavit is supported by contemporaneous official records such as office submissions, photographs, registers, and documentary evidence, the court must test the authenticity and veracity of that contemporaneous record before finding the affidavit to be false or misleading; a finding of falsehood based solely on a later inspection report, prepared months after the events in question, is manifestly wrong if it does not engage with the supporting contemporaneous evidence. In contempt proceedings for filing a false affidavit, the court cannot rely on evidence obtained after a substantial temporal gap (such as an inspection report prepared six months after the alleged events) to contradict the factual position stated in the affidavit, particularly where the alleged contemnor offers credible explanation that the structures in question could have been reconstructed in the interval, and the court fails to consider such explanation.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

REPORTABLE

IN THE SUPREME COURT OF INDIA CRIMINAL APPELLATE JURISDICTION

CRIMINAL APPEAL NO. 684 OF 2006

R. S. Sehrawat … Appellant(s)

:Versus:

Rajeev Malhotra & Ors. …. Respondent(s)

JUDGMENT

A.M. Khanwilkar, J.

1. The instant appeal under Section 19 (1) (b) of the

Contempt of Courts Act, 1971, assails the judgment and

orders passed by the Division Bench of the High Court of Delhi

at New Delhi in C.M. No.820 of 2001 in C.W.P. No.6734 of

2000 dated 1st June, 2001 and in R.A. No.6600 of 2001 in

C.W.P. No.6734 of 2000 dated 10th May, 2006 whereby the Signature Not Verified Digitally signed by CHETAN KUMAR Date: 2018.09.05 appellant has been found guilty of filing false affidavit and 12:21:45 IST Reason:

attempting to mislead the Court, thus committing contempt of 2

court by his acts which were of such a nature that they tended

to substantially interfere with the due course of justice. The

appellant has been sentenced to undergo simple imprisonment

for a period of 30 (Thirty) days and to pay a fine of Rs.25,000/-

(Twenty Five Thousand Only). Review petition against the said

decision came to be dismissed on 10th May, 2006.

2. Briefly stated, the appellant was working as a Junior

Engineer in Municipal Corporation of Delhi (MCD). The writ

petitioner (respondent No.1 herein) had alleged that the

appellant and other officials, including police officials had, by

their act of commission and omission, first permitted the writ

petitioner to carry on unauthorised construction on the

property bearing Plot No.37-C measuring 834 square yards at

Asoka Avenue, Sainik Farms, New Delhi and later on

unilaterally demolished the said structure. This was the

grievance made in Civil Writ Petition No.6734 of 2000 filed by

respondent No.1. Respondent No.1 had prayed for taking

action against the appellant and other officials including police

officials involved in the alleged incident of demolition of the 3

structure. The Division Bench of the High Court adverting to

the direction issued in Public Interest Litigation bearing

C.W.P. No.7441 of 1993 dated November 3, 1997 restraining

unauthorised constructions in unauthorised colonies, issued

notice on 6th December, 2000 in the present writ petition to

the officers of the MCD and the police personnel who were

posted during the time the construction was raised on the plot

belonging to respondent No.1, to show cause as to why

proceedings for contempt of court should not be initiated

against them.

3. After receipt of notice, the appellant, as well as other

officials, filed their respective affidavits. The appellant filed his

detailed affidavit on 3rd January, 2001 inter alia pointing out

the primary responsibility of the officials who were expected to

comply with the directions issued on November 3, 1997 by the

High Court. As regards his role in the capacity of Junior

Engineer, the appellant asserted that he discharged the task

assigned to him from time to time by his superior officers and

submitted compliance reports to them in that behalf. He 4

further asserted that he had undertaken 14 major demolition

actions in Sainik Farms alone between 7th March, 2000 and

27th September, 2000 and razed these constructions to the

ground. It was asserted that the writ petitioner illegally

constructed the building at the same location inspite of the

demolition action taken on the earlier occasions. In support of

the contention that he had resorted to the demolition of

concerned structure, he placed reliance on the office

submission made by him to his superiors as well as the

photographs of the structures taken before and after the

demolition drive. The stand taken by the appellant was

contested by respondent No.1. To verify the factual position,

the High Court vide order dated 12th January, 2001 appointed

a Committee of advocates to inspect the site and submit a fact

finding report. That report was submitted to the High Court by

the Committee of advocates on 23rd January, 2001.

4. The High Court vide order dated 24th January, 2001 after

recording its prima facie opinion issued show cause notice to

the concerned officials including the appellant as to why they 5

should not be convicted and punished for contempt of court.

After the said order, the appellant filed a further affidavit

dated 8th February, 2001 and reiterated the stand taken in the

earlier affidavit as also explained the position of possibility of

reconstruction on the same location after the demolition was

done on 7th June, 2000 and 14th/15th September, 2000. The

appellant also relied on contemporaneous evidence such as

the report and photographs of the demolition. The High Court,

however, was not impressed by the explanation offered by the

appellant and proceeded to record finding of guilt against the

appellant for filing false affidavit on January 3, 2001. The

appellant preferred a review petition which was dismissed on

10th May, 2006. As a result, the appellant has challenged both

the orders by way of the present appeal.

5. The principal grievance of the appellant is that no proper

charge was framed and conveyed to the appellant. The first

show cause notice issued to the appellant in terms of order

dated 6th December, 2000 was presumably for non-compliance

of the direction given on November 3, 1997 in C.W.P. No.7441 6

of 1993; whereas the second show cause notice issued to the

appellant pursuant to order dated 24th January, 2001 was for

filing an incorrect and misleading affidavit dated 3rd January,

2001. The appellant had revealed the factual position in his

affidavit dated 3rd January, 2001 and further affidavit dated

8th February, 2001. The factual position stated in the said

affidavits has not been analysed by the High Court at all,

much less in its proper perspective. On the contrary, the High

Court, proceeded to record a finding of guilt, being swayed

away by the factual position recorded in the report submitted

by the Committee of advocates, completely overlooking the

plausible explanation offered by the appellant that the

unauthorised structure in question was demolished on 7th

June, 2000 and again on 14th/15th September, 2000. The

contemporaneous record regarding the extent of demolition in

the form of office submission, press reports and photographs

was also brought to the notice of the High Court. However,

that has been overlooked. The grievance of the appellant is

that in the affidavit dated 8th February, 2001 a specific

disclosure was made about the video recording done by news 7

channels and liberty to play the video clippings was sought

but the High Court did not deal with this request of the

appellant at all. The time period between the demolition and

the inspection by the Committee of advocates being quite

substantial, the possibility of reconstruction of the structures

in question could not be ruled out. However, the High Court

has not dealt with this aspect.

6. The respondent No.1 and the Amicus Curiae espousing

the cause of the respondent No.1, would, however, contend

that there is no error in the approach or the conclusion

recorded by the High Court.

7. We have heard Mr. Ashok Mathur advocate for the

appellant, Mr. K. Radhakrishnan, learned senior counsel

appearing as amicus curiae and Mr. Ashok Kumar Panda,

learned senior counsel for the respondent.

8. As noted earlier, action against the appellant and other

officials was initiated by the High Court in terms of order 8

dated 6th December, 2000. The relevant portion of the said

order reads thus:

“............

In the instant petition, unauthorized construction was carried out in Sainik Farm which happens to be an unauthorized colony. It is not disputed that the petitioner started construction on Plot No.37C measuring 834 Sq. Yds. At Ashoka Avenue, Sainki Farm, New Delhi, in July 2000. The building was allowed to come up and when it was nearing completion the same was demolished on 30.10.2000. We fail to understand as to how the building activity could be permitted/allowed from July 2000 till October 2000 when order of this court dated November 3, 1997 was in force. It prima facie appears to us that the building in question could not have come up unless the concerned officers of the MCD and the Police connived with the petitioner. The allegation of the petitioner is that he paid bribes to various offices for raising the construction. He has named those officers.

In the circumstances, we consider it appropriate to issue notices to the following officers of the MCD and the Police, who were posted during the time the construction was raised on the plot in question, to show cause why proceedings for contempt of court be not initiated against them:

1. Mr. R.S. Sherawat (JE) MCD

2. Mr. U.S. Chowhan (JE) MCD

3. Mr. S.R. Bhardwaj, A.E. South zone Building Department MCD.

4. Mr. Puran Singh Rawat, Baildar, MCD

5. Mr. Rakesh Baildar, MCD

6. Mr. Man Mohan, S.I. Chowki Incharge, Sainik Farms

7. Mr. V.K. Malhotra, Ex. Engineer MCD

8. Mr. Vir Singh, SHO.

The aforesaid officers are present and they accept notice. They are granted two weeks time to file affidavits in reply to the show cause notice. Pleadings in the writ petition be completed before the next date.” 9

9. On a bare perusal of this order, it is evident that the High

Court took suo motu action as it was prima facie convinced

that unauthorised construction was carried out in Sainik

Farms despite the direction contained in order dated

November 3, 1997 in C.W.P. No.7441 of 1993. The order also

records that the show cause notice was accepted by the

officers present in Court. The appellant, like other officers,

filed his affidavit revealing the relevant facts concerning him

vide affidavit dated 3rd January, 2001. The appellant had

explained the factual position as to the action of demolition of

unauthorised structures in Sainik Farms during the relevant

period as per the task assigned to him by his superior officers

and reporting of that fact to his superiors by way of

contemporaneous office submission. The correctness of the

said contemporaneous office reports could not be and has not

been questioned or doubted as such. The reply affidavit makes

it amply clear that the Commissioner of the Corporation was

personally supervising the demolition work of unauthorised

constructions and, therefore, there was no reason to doubt the 10

contemporaneous record in the form of office submissions and

photographs reinforcing the fact of demolition. The report of

the Committee of advocates, however, was based on the site

visit made in January, 2001 after a gap of more than 6

months from 7th June, 2000 and 3 months from 14th

September, 2000 when the demolition was actually carried

out. The factual position stated in the said report, therefore,

may not be the actual position as obtained on the date of

demolition i.e. 7th June, 2000 and 14th September, 2000. It is

not unknown that such unauthorised structures could be and

were reconstructed overnight after the demolition work is

undertaken by the officials. That was done by unscrupulous

persons clandestinely and without notice. The factual position

stated in the reply affidavit filed by the appellant also reveals

that continuous follow-up action was being taken in respect of

unauthorised structures including those which were

demolished. Furthermore, the appellant was transferred from

the concerned ward w.e.f. 27th September, 2000 and any

development or illegal activity unfolding after that date cannot 11

be attributed to the appellant. All these aspects have not been

considered by the High Court.

10. During the pendency of this appeal the appellant has

also brought on record a fact that he had faced departmental

action on the basis of same set of facts regarding his acts of

commission and omission for the following three charges:

“Shri R.S. Sehrawat while functioning as JE (B) in Building Department, South Zone and remained incharge of the area of Sainik Farm w.e.f. 07.03.2000 to 27.09.2000, committed gross misconduct on the following counts:

1. He is connivance with the owner/builders allowed them to carry out and complete the unauthorized construction in P.Nos 37-C, 49, H-541, Sainik Farms unabatedly and did not take effective action to stop/demolish the same at its initial/ongoing stage.

2. He also did not book the said unauthorized construction in Sainik Farm just to avoid demolition action u/s 343/344 of the DMC Act.

3. He also submitted wrong affidavit in the High Court mentioning therein that unauthorized construction in P.No.49 and H-541, Sainik Farms were demolished but the same were found still existing at site. Thus, he mislead the Hon‟ble High Court.

He, thereby contravened Rule 3 (I) (i) (ii) & (iii) of the CCS (Conduct) Rules, 1964 as made applicable to the employees of the MCD.” 12

Notably, the appellant has been exonerated in the said enquiry

by a detailed report analysing all the official records

supporting the stand of the appellant.

11. Be that as it may, the law relating to contempt

proceedings has been restated in the case of Sahdeo Alias

Sahdeo Singh Versus State of Uttar Pradesh and Others1

in paragraph 27 as follows:

“27. In view of the above, the law can be summarised that the High Court has a power to initiate the contempt proceedings suo motu for ensuring the compliance with the orders passed by the Court. However, contempt proceedings being quasi-criminal in nature, the same standard of proof is required in the same manner as in other criminal cases. The alleged contemnor is entitled to the protection of all safeguards/rights which are provided in the criminal jurisprudence, including the benefit of doubt. There must be a clear-cut case of obstruction of administration of justice by a party intentionally to bring the matter within the ambit of the said provision. The alleged contemnor is to be informed as to what is the charge, he has to meet. Thus, specific charge has to be framed in precision. The alleged contemnor may ask the Court to permit him to cross-examine the witnesses i.e. the deponents of affidavits, who have deposed against him. In spite of the fact that contempt proceedings are quasi-criminal in nature, provisions of the Code of Criminal Procedure, 1973 (hereinafter called “CrPC”) and the Evidence Act are not attracted for the reason that proceedings have to be concluded expeditiously. Thus, the trial has to be concluded as early as possible. The case should not rest only on surmises and conjectures. There must be clear and reliable evidence to substantiate the allegations against the alleged contemnor. The proceedings

1 (2010) 3 SCC 705 13

must be concluded giving strict adherence to the statutory rules framed for the purpose.”

We may usefully refer to two other decisions dealing with

the issue under consideration. In Muthu Karuppan,

Commissioner of Police, Chennai Vs. Parithi Ilamvazhuthi

and Anr., 2 this Court observed thus:

“15. Giving false evidence by filing false affidavit is an evil which must be effectively curbed with a strong hand. Prosecution should be ordered when it is considered expedient in the interest of justice to punish the delinquent, but there must be a prima facie case of „deliberate falsehood‟ on a matter of substance and the court should be satisfied that there is a reasonable foundation for the charge.”

“17. The contempt proceedings being quasi-criminal in nature, burden and standard of proof is the same as required in criminal cases. The charges have to be framed as per the statutory rules framed for the purpose and proved beyond reasonable doubt keeping in mind that the alleged contemnor is entitled to the benefit of doubt. Law does not permit imposing any punishment in contempt proceedings on mere probabilities, equally, the court cannot punish the alleged contemnor without any foundation merely on conjectures and surmises. As observed above, the contempt proceeding being quasi-criminal in nature require strict adherence to the procedure prescribed under the rules applicable in such proceedings.”

2 (2011) 5 SCC 496 14

In Mrityunjoy Das and Anr. Vs. Syed Hasibur Rahaman

and Ors.,3 this Court observed thus:

“14. The other aspect of the matter ought also to be noticed at this juncture, viz., the burden of standard of proof. The common English phrase „he who asserts must prove‟ has its due application in the matter of proof of the allegations said to be constituting the act of contempt. As regards the „standard of proof‟, be it noted that a proceeding under the extraordinary jurisdiction of the court in terms of the provisions of the Contempt of Courts Act is quasi-criminal, and as such, the standard of proof required is that of a criminal proceeding and the breach shall have to be established beyond reasonable doubt....”

12. In the present case, going by the material on record it is

not possible to conclude beyond reasonable doubt that the

appellant had contributed to the reconstruction of the

unauthorised structure before or after 27th September, 2000.

Furthermore, the appellant was not served with any charges

muchless specific charge which he was expected to meet. Yet,

the final conclusion in the impugned judgment is that the acts

of the appellant tended to substantially interfere with the due

course of justice and amounted to committing criminal

3 (2001) 3 SCC 739 15

contempt of court for having filed incorrect affidavit. The High

Court made no attempt to verify or examine the

contemporaneous record relied upon by the appellant in

support of his plea that the factual position stated in the

affidavit filed by him was borne out and reinforced from the

said record. The affidavit so filed cannot be termed as

incorrect or misleading by relying on the report of the

advocates‟ committee, which was prepared after a gap of 6

months from the date of first demolition (7th June, 2000) and 3

months from the second demolition (14th September, 2000).

13. The finding recorded by the High Court that the property

was not razed to the ground based on the report prepared in

January, 2001, therefore, is not the correct approach and is

manifestly wrong. The High Court ought to have tested the

authenticity and veracity of the contemporaneous record in

the form of office submissions, Misel Band register, office files,

notices, photograph and press reports etc. relied upon by the

appellant. It would be a different matter if the

contemporaneous record did not support the stand taken by 16

the appellant in the affidavits filed by him dated 3rd January,

2001 and 8th February, 2001 respectively. As a matter of fact,

the appellant has already faced departmental enquiry in which

the matter in issue has been exhaustively dealt with and the

plea taken by the appellant has been found to be correct.

14. Be that as it may, the appellant has been found guilty in

reference to the notice issued in terms of order dated 24 th

January, 2001, the relevant portion whereof reads thus:

“Learned counsel for the petitioner also pointed out in the affidavit of Mr. R.S. Sehrawat, it is mentioned that property Nos.49 and H-541 were demolished on 7th June, 2000 and 14th September, 2000 respectively. Mr. Awasthy has shown photographs of these properties. From the photographs, it appears that the properties are intact and were not demolished, therefore we are prima facie of the opinion that even Mr. Sehrawat has taken liberties with truth. Issue notices to Mr. U.S. Chauhan and Mr. R.S. Sehrawat, Junior Engineers, MCD, to show cause why they should not be convicted and punished for contempt of Court. Let the affidavits in response be filed by 6th February, 2001.”

15. In response to the second notice given to the appellant,

he filed a further affidavit dated 8th February, 2001 to urge as

under:

17

“3. That the deponent submits that the deponent had not filed any false affidavit, nor did the deponent take liberties with truth while filing the affidavit on 3.1.2001 before this Hon‟ble Court. I state that in the order dated 24.1.2001, qua the deponent it has been recorded that properties No.49 and H-541, which were demolished by the deponent on 7.6.2000 and on 14.9.2000/15.9.2000 were not demolished as per the report of the committee appointed by this Hon‟ble Court and the photographs of these properties.

4. That the deponent submits that property No.49 was demolished on 7.6.2000 and the photo copies of the photographs of the existing building before demolition and after demolition have already been filed by the deponent along with the deponent‟s affidavit filed on 3.1.2001. The deponent is filing photocopies of further photographs of the demolished property. I further state that the press had prior information for the demolition to be carried out at Sainik Farms on 7.6.2000 and the press photographers and reporters were at Sainik Farms. The photograph of the demolished building at 49, Sainik Farm was taken by the photographers of some news papers. The times of India, edition dated 8.6.2000 showed the demolished structure.

This is independent evidence which corroborates the stand of the deponent. I further state that the video team of the Doordarshan video taped the demolition of 49 Sainik Farms and the clippings were shown in the programme “Aaj Tak” on 7.6.2000 itself at 10 P.M. I crave indulgence of this Hon‟ble Court to summon the video film from the Doordarshan Authorities prepared for the programme Aaj Tak telecasted on 7.6.2000. I state that the owner of the property has reconstructed the same after its earlier demolition. I state that as stated by me in the earlier affidavit filed by the deponent, I was no longer assigned the work of Junior engineer for Sainik Farms after 27.9.2000 and the structure has been re-erected, only thereafter. I state that during my tenure as Junior Engineer incharge of Sainik Farms only one property was bearing No.49 Sainik Farms, which was demolished by me.

5. That as regards property No. H-541, Sainik Farms, I state that the committee report has not referred to the same. However, 29.1.2001, I visited the site of the said property and state that the said property has also been reconstructed after the earlier demolition carried out by me. I state that the reconstructed property is still in the process of finishing and 18

painting work is still going on in the property. I state that the committee members should be requested by this Hon‟ble Court to immediately report whether the buildings are in the process of being painted or has been recently completed and painted as the same would show and prove its reconstruction. I have already filed the photographs showing the demolished property by me along with my earlier affidavit.

6. That I state that as already stated by me in my affidavit filed before this Hon‟ble Court on 3.1.2001, the Commissioner of the Corporation was weekly reviewing the activities at Sainik Farms and the Zonal Engineer and the Executive Engineer of the Zone were also personally supervising the demolition operations carried out by me. The reports of the said Zonal Engineer and Executive Engineers should also be called.

7. That I state that I should be given an opportunity to lead evidence of the press photographers, Doordarshan team which video taped the demolitions on 7.6.2000 as also the evidence of the Zonal Engineer and Executive Engineer to prove that I had carried out the demolitions and have not filed any affidavit nor have taken liberties with truth.”

16. This specific stand taken by the appellant has not been

considered by the High Court at all. The appellant made this

grievance in the review petition, but of no avail. In our opinion,

it is not possible to hold that the demolition work undertaken

on 7th June, 2000 and 14th September 2000 was not in

conformity with the position reflected in the contemporaneous

office submissions/record and photographs submitted by the

appellant to his superior authority.

19

17. As a matter of fact, the appellant ought to succeed on the

singular ground that the High Court unjustly proceeded

against him without framing formal charges or furnishing

such charges to him; and moreso because filing of affidavit by

the appellant was supported by contemporaneous official

record, which cannot be termed as an attempt to obstruct the

due course of administration of justice. Accordingly, this

appeal ought to succeed.

18. In view of the above, the impugned judgment and orders

passed by the Division Bench of High Court of Delhi at New

Delhi in C.M. No.820 of 2001 in C.W.P. No.6734 of 2000 dated

1st June, 2001 and in R.A. No.6600 of 2001 in C.W.P. No.6734

of 2000 dated 10th May, 2006 are quashed and set aside and

the show cause notices issued to the appellant pursuant to the

order of the Division Bench of the High Court dated 6th 20

December, 2000 and dated 24th January, 2001 are hereby

dropped. Appeal is allowed in the aforementioned terms.

…………………………….CJI.

(Dipak Misra)

…………………………..….J. (A.M. Khanwilkar) New Delhi;

September 05, 2018.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free