Miss Lucy
← All judgments

Pattipati Venkateswarlu Naidu vs The Special Deputy Collector (L.A.)

Supreme Court27 September 2018Sanjay Kishan Kaul · Kurian Joseph

Ratio decidendi

The rule this decision rests on

1. In proceedings for enhancement of compensation under land acquisition law, where an unexplained delay has occurred in approaching the court, that delay may be condoned if the claimant is denied statutory benefits for the period of delay; this ensures that the claimant suffers a consequence for the delay while allowing the substantive claim to be considered on merits. 2. Where the Supreme Court has previously fixed compensation for acquired property at a particular rate in a case involving the same project and similar circumstances, that rate constitutes the appropriate measure of compensation for other claimants whose acquisitions relate to the same project, even if their acquisitions were notified at different dates. 3. Statutory benefits accrued during the period of delay in approaching the court are properly denied to a claimant as a consequence of that delay, notwithstanding that the claimant is granted the substantive relief sought.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

NON-REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO(S). 10044 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 8343 OF 2018]

PATTIPATI VENKATESWARLY NAIDU Appellant(s)

VERSUS

THE SPECIAL DEPUTY COLLECTOR (L.A.) Respondent(s)

CIVIL APPEAL NO(S). 10036 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 315 OF 2018]

WITH

CIVIL APPEAL NO(S). 10039 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 4590 OF 2018]

WITH

CIVIL APPEAL NO(S). 10042 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 6016 OF 2018]

WITH

CIVIL APPEAL NO(S). 10047 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 6017 OF 2018]

WITH

CIVIL APPEAL NO(S). 10041 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 6013 OF 2018]

WITH

CIVIL APPEAL NO(S). 10040 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 6012 OF 2018]

WITH Signature Not Verified CIVIL APPEAL NO(S). 10038 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 4593 OF 2018] Digitally signed by JAYANT KUMAR ARORA Date: 2018.10.06 12:37:28 IST Reason:

WITH

CIVIL APPEAL NO(S). 10037 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 4588 OF 2018] 2

WITH

CIVIL APPEAL NO(S). 10045 OF 2018 [@ SPECIAL LEAVE PETITION (C) NO. 10827 OF 2018]

J U D G M E N T

KURIAN, J.

SLP (C) No. 8343 OF 2018

1. Leave granted.

2. The High Court, as per the impugned order,

declined to consider the claim made by the

appellant(s) for enhancement of compensation on the

ground of unexplained delay in approaching the High

Court. In cases where the claim is made for

enhancement, this Court has taken a consistent view

that in case the claimants are denied the statutory

benefits for the period covered by delay, a lenient

view should be taken while condoning the delay.

3. Having regard to the facts and circumstances of

the case, we condone the delay on the part of the

appellant(s) in approaching the High Court on the

condition that for the period of delay, they shall

not be entitled to any statutory benefits in case any

enhancement is granted by the High Court on merits.

4. Since we are bereft of other particulars on

merits, we remit the matter to the High Court for

consideration of the claims made by the appellant(s)

on merits. The parties will appear before the High 3

Court on 01.11.2018. We request the High Court to

consider the matter expeditiously since the claim

pertains to the acquisition in the year 1990.

In view of the above, the appeal is disposed of.

Pending interlocutory application(s), if any,

is/are disposed of.

SLP (C) No. 315 OF 2018, SLP (C) No. 4590 OF 2018,

SLP (C) No. 6016 OF 2018, SLP (C) No. 6017 OF 2018,

SLP (C) No. 6013 OF 2018, SLP (C) No. 6012 OF 2018,

SLP (C) No. 4593 OF 2018, SLP (C) No. 4588 OF 2018

and SLP (C) No. 10827 OF 2018

1. Leave granted.

2. The issue raised in these appeals pertains to the

claim made by the appellants for enhancement of

compensation for pomegranate trees, which stood in

the land acquired for the purpose of

Somashila/Telugu Ganga Project. The notifications in

these cases have been issued on different dates

between 1990 to 1994. The appellants have been

granted compensation at the rate of Rs.2000/- per

Pomegranate Tree. We find from Civil Appeal Nos.

11404-11405 of 2016 that this Court has fixed

compensation at the rate of Rs. 3,000/- per

pomegranate tree, as against Rs. 2000/- fixed by the

High Court, in respect of the acquisition for the

same project, for which notification was issued in 4

the year 1994. Having regard to the entire facts and

circumstances of the case, we are of the view that it

would be just, reasonable and proper to fix the

compensation at the rate of Rs. 3000/- per

Pomegranate Tree. Therefore, these appeals are

disposed of with the following directions :-

(i) The appellants shall be entitled to compensation

at the rate of Rs. 3000/- (Rupees Three Thousand) per

Pomegranate Tree along with all statutory benefits.

(ii) However, they shall not be entitled for

statutory benefits for the period of delay in

approaching this Court or the High Court.

.......................J. [ KURIAN JOSEPH ]

.......................J. [ SANJAY KISHAN KAUL ]

New Delhi;

September 27, 2018.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free