Patsons Constructions vs Ram Ratan Kanoongo Resolution ...
- CitationCompany Appeal (AT) (Ins.) No. 1269 of 2022
Ratio decidendi
The rule this decision rests on
A direction for payment of usage charges for a corporate debtor's asset cannot be sustained where there is no rental agreement or other contractual basis for such charges, and the adjudicating authority has not stated how the amount claimed was arrived at.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE MATTER OF: Patsons Construction (Operational Creditor) ....Appellant
Vs.
Shri Ram Ratan Kanoongo ....Respondent Resolution Professional of D Thakkar Constructions Pvt. Ltd.
Present: For Appellant: C.S. Sachin Sinha (PCS), Mr. Shravan Shukla, Ms. Tejaswi Kumar, Advocates. For Respondent: Mr. Rajendra Beniwal, Mr. Rajat Kashyap, Mr. Saksham Solanki, Ms. Shivangi Ghosh, Ms. Richa Singh, Advocates.
ORDER
07.11.2023: Heard Practicing Company Secretary for the appellant and
Learned Counsel appearing for the respondent.
2. This appeal has been filed against the order dated 25.03.2022 by which
order Adjudicating authority has issued following directions in paragraph (v).
(a) Consider and allow the instant IA No... of 2022 under the provisions
of Section 14, r.w.s. 18 (1)(f) of the code;
(b) Direct the Respondent to handover the asset of the Corporate Debtor
namely Komatsu Motor Grader GD-511 (having Registration number
MH 40 P 961) which is under the possession of Respondent since
last 2 years;
Company Appeal (AT) (Ins.) No. 1269 of 2022 -2-
(c) Direct the Respondent to deposit the usage charges for the above
mentioned asset of Rs. 2 lakhs per month for 24 months totaling to
Rs. 48 lakhs in the account of Corporate Debtor;
(d) Pass such other order(s) and/or direction(s) in the interest of justice
which this Hon'ble Tribunal deems fit."
3. In this appeal when the appeal was heard this Tribunal passed an order
on 19.10.2022 directing the appellant to hand over the machine within 15
days. In pursuance of our order, it is submitted on behalf of the appellant that
machine has already been handed over to the Corporate Debtor.
4. The order impugned was passed in I.A. 515/2022 filed by the Resolution
Professional where prayers were made with regard to handing over the machine
and direction for usage charges.
5. It appears that Resolution Professional has issued a letter dated
03.06.2021 asking the appellant to hand over the machine and also pay usage
charges. The appellant by letter dated 08.06.2021 sent following reply:
" Dated 08.06.2021 To, D. Thakkar Constructions Pvt. Ltd.
Sub: Regarding your letter dated June 3, 2021 Sir, With respect to your letter we would like to bring to your notice that we had been in contract with D.Thakkar Construction Pvt. Ltd. Work order Ref.no.
WO/SECR/CHHINDWARA-32/2015-16(copy attached herewith) and in the audited year 2017-18 we had to take
Company Appeal (AT) (Ins.) No. 1269 of 2022 -3-
Rs.3981955.00 and Rs.611908.00 in total 4593863.00 against work done (The account ledger attached herewith) which reflects in audit financial books. On 31/08/2018 we had last sent a mail of the outstanding amount with interest and loss (copy enclosed herewith). After that in face to face meeting Vishalbhai Thakkar had agreed to give Grader against our outstanding money and will soon clear the books and handover the transfer documents of Grader (as mentioned in Letter attached dated 07/02/2019 herewith) at the earliest."
6. After the aforesaid reply the application has been filed.
7. The resolution plan of the Corporate Debtor has been approved on
09.08.2021 by CoC and 14.03.2022 by the NCLT. The appellant could filed its
claim after the approval of plan with the Committee of Creditors, hence, the
same has not been considered.
8. The present appeal is concerned with the two directions issued in
paragraph (v) as quoted above. In so far as the first direction the machine has
already been handed over to the Corporate Debtor, hence, that order has been
complied with.
9. In so far as the direction to pay usage charges it is clear that there has
been no rental agreement between the parties for any usage charges and
machine was given to the operational creditor by the director of the Corporate
Debtor in lieu of the certain dues which Corporate Debtor owe to the appellant
which is reflected in letter dated 08.06.2021.
Company Appeal (AT) (Ins.) No. 1269 of 2022 -4-
10. As noted above, the appellant could not filed its claim in the corporate
insolvency resolution process of the Corporate Debtor, hence, his dues do not
find any reflection.
11. In the application which was filed by the Resolution Professional there
was no basis for claiming Rs. 2 lakhs per month of usage charges. Adjudicating
Authority by the impugned order has also not adverted as to how the amount
of Rs. 2 lakhs per month can be allowed for payment of usage charges.
12. We, thus, are of the view that second direction issued by Adjudicating
Authority for payment of Rs. 48 lakhs is unsustainable and is set aside. The
appeal is partly allowed to the above extent.
[Justice Ashok Bhushan] Chairperson
[Mr. Barun Mitra] Member (Technical)
[Mr. Arun Baroka] Member (Technical)
sa/nn
Company Appeal (AT) (Ins.) No. 1269 of 2022
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free