Oil and Natural Gas Corporation Ltd. vs Newton Engineering and Chemicals Ltd.
- Neutral2025:BHC-OS:19596
Ratio decidendi
The rule this decision rests on
A court exercising jurisdiction under Section 34 of the Arbitration and Conciliation Act, 1996 cannot re-appreciate evidence or re-interpret contractual terms to arrive at a conclusion contrary to that of the arbitral tribunal, where the tribunal's conclusion rests upon a possible view of the matter grounded in the evidence before it. Where an arbitral tribunal has appreciated evidence in the form of invoices, work orders, and bank statements to establish payments made under the contract, a court under Section 34 cannot interfere with such findings by re-appreciating that evidence. Where an arbitral tribunal, after appreciating evidence on record including witness testimony and documentary materials, has determined the quantity of sludge and the rate applicable to it, a court under Section 34 cannot re-appreciate such evidence-based findings. Where an arbitral tribunal has found that a contract has been wrongfully and illegally terminated, the award of loss of profit at 15% on the balance remaining work—computed as per the established legal principles laid down in A.T. Brij Paul Singh v. State of Gujarat and Mohd. Salamatullah v. Govt. of A.P.—is justified and cannot be set aside merely on the basis that the claimant failed to adduce independent proof of the quantum of damages, if the loss follows as a legal consequence of the wrongful termination. Where an arbitral tribunal has found a contract wrongfully terminated, the award of refund of performance bank guarantees invoked by the terminating party, together with reasonable interest, is justified as a consequence of that finding of wrongful termination.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
J-CARBP 648.2021.doc
Kavita S.J.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION PETITION NO.648 OF 2021
Oil and Natural Gas Corporation Ltd., ...Petitioner Versus Newton Engineering and Chemicals Ltd., ...Respondent ---------- Mr. Vishal Kanade a/w Mr. Virendra Pereira, Mr. Anagh Pradhan, Ms. Aneesha Munshi, Mr. Anand Iyer, M.s Niyati Dasondi and Ms. Palak Jain i/b Divya Shah Associates for the Petitioner. Mr. Mayur Khandeparkar a/w Mr. Bernando Reis i/b Dr. Prem S. Motiramani for the Respondent. ----------
CORAM : R.I. CHAGLA, J.
RESERVED ON : 22nd APRIL, 2025.
PRONOUNCED ON : 17th OCTOBER, 2025.
JUDGMENT :
1. By this Commercial Arbitration Petition, the Petitioner
has impugned the Award dated 26th August, 2021 passed by the
Arbitral Tribunal. By the impugned Award the Arbitral Tribunal has
KAVITA directed the Petitioner to pay an aggregate amount of SUSHIL JADHAV Digitally signed Rs.27,43,69,720/- alongwith interest @ 12% per annum as well as by KAVITA SUSHIL JADHAV Date: 2025.10.17 17:16:35 +0530 costs as mentioned in the impugned Award.
1/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
2. It is pertinent to note that by an Order dated 17 th April
2023, the present commercial Arbitration Petition had been admitted
by this Court and execution of the impugned Award was stayed
subject to deposit of the said amount. The Petitioner has deposited
an amount of Rs.41,12,17,356/- with the learned Prothonotary and
Senior Master of this Court on 25th May 2023, within the time
stipulated by the said order.
3. A brief background of facts is necessary and which are as
under:
(i) A Tender was floated for Modernization of
the Effluent Treatment Plant ("ETP") at Uran Plant of
Petitioner. The scope of work, which the successful
bidder was required to inter-alia carry out included :
i. Process design, basic engineering, detailed
engineering, manufacture, fabrication, supply,
total procurement of all the Items including
construction materials as defined in the special
condition of the bid;
ii. demolition of existing surge pond and other
2/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
units;
iii. revamp of existing units as indicated in the
bid;
iv. construction, erection, and installation, air-
conditioning, ventilation, testing, painting, lining,
insulation, commissioning and guaranteeing the
entire modernization of ETP on turnkey basis to
meet the treated effluent quality;
v. remove debris and sludge from the surge
pond.
(ii) A Pre-Bid Meeting was held on 10th January,
2014. Clarification was issued by the Petitioner that M/s
Mumbai Waste Management Limited ("MWML") Taloja
was the approved party for sludge disposal and bidders
may fix a Contract with them.
(iii) On 6th May 2014, an Agreement and
Memorandum of Understanding ("MoU") was executed
between the Respondent and M/s UEM India Pvt. Ltd.
3/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
("UEM"). As per Technical Collaboration Agreement
between the Respondent and UEM, UEM was primarily
responsible for basic design and engineering, detailed
engineering, technical collaboration assistance / services,
critical equipment supplies and expert supervision.
(iv) The Bid of the Respondent was submitted on
7th July, 2014. The Respondent's bid qualified for
consideration. It is the Petitioner's claim that this was
only because UEM was the Respondent's technical
collaborator for execution of the project. The bid of the
Respondent was accordingly reviewed considering the
fact that UEM was meeting the criteria given in the
tender document.
(v) A Letter of Award ("LOA") was issued by
Petitioner to Respondent. The Petitioner claims that
based on the submission of technical collaboration
agreement with UEM, the Respondent's Bid was
technically accepted and the Respondent was awarded
the Contract.
4/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
(vi) Pursuant to the Respondent having been
awarded the Contract, a letter dated 1 st August, 2015
was addressed by the Respondent to Midland Oil
Corporation Limited ("MOCL") accepting their offer for
disposal of sludge from Surge Pond B @ Rs. 4000 per MT
- Sludge in Surge Pond A which was to be released only
after Pond B equipment's were erected and
commissioned and which may be commissioned after 8
months after Pond B is cleaned and handed over.
(vii) The Respondent for the first time on 29 th
February, 2016 informed the Petitioner about the
Contract with MOCL for recycling and safe disposal of
sludge from surge pond B.
(viii) The Petitioner by letter dated 3rd March
2016, brought to the notice of the Respondent that in
respect of sludge removal it was clarified in the pre-bid
reply that "M/s. MWML, Taloja" was the only agency
through whom the sludge could be disposed of in view of
the MPCB consent granted to the Petitioner.
5/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
(ix) The Petitioner by Letter dated 23 rd March
2016, informed the Respondent that MWML Taloja was
approved by CPCB / MPCB for handling/disposal of
sludge and the bidder was to fix Contract and disposal of
sludge through that agency. It was mentioned that MOCL
was not the authorized agency to dispose of sludge and
that the consent available with MOCL was for waste oil
and not sludge.
(x) On 29th March 2016, a detailed Contract
Agreement was executed between the Petitioner and the
Respondent.
(xi) A Letter dated 16th April, 2016 was
addressed by the Respondent to the Petitioner pointing
out that they were not bound to send the sludge to
MWML - Taloja and that the pre-bid queries only
suggested that they may approach them. It was pointed
out that since sludge analysis was pending processing
from MPCB Laboratory, the Respondent cannot proceed
further and hence, delay for sludge disposal as recorded
in Weekly Review Meetings (WRMs) was not due to
6/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Respondent.
(xii) A letter dated 21st April, 2016 was addressed
by the Respondent to the Petitioner once again pointing
out that sludge in Surge Pond could be processed by
MPCB Authorized Reprocessor and the remaining sludge
would be disposed off by incineration facility at any
MPCB approved agency and requested for permission for
the same.
(xiii) The Petitioner recorded by Letter dated 11 th
July, 2016 that the Management Review Meeting to be
held on 8th July, 2016 was constrained to be rescheduled
since the Respondent's MD did not attend the meeting.
The meeting was of grave importance since the
important issues of sludge disposal and project progress
were to be discussed.
(xiv) The MPCB on 7th September, 2016 directed
the Petitioner to carry out sludge testing and accordingly,
the Laboratory Report of Sludge Analysis was submitted
by MWML, Taloja. The report established that almost
7/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
30% of the contents of surge pond B consisted of hydro
carbons i.e. crude oil and not waste oil.
(xv) A letter was addressed by the Petitioner on
9th November, 2016 to the Respondent that since the
progress of the Respondent's execution of the subject
Contract project was only 0.71% as against the
scheduled target of 26.20% as on 9 th November 2016, it
was abnormally low.
(xvi) The Petitioner once again by a letter dated
29th December, 2016 recorded that the progress of the
project was only 0.72% against the schedule of 33.99%
as on the date of the letter, which was abnormally low.
(xvii) The Petitioner by a letter dated 13th
February, 2016 recorded that the progress achieved by
the Respondent upto 13th February, 2017 was highly
unsatisfactorily to the extent of only 1.62% as against
the scheduled progress of 59.42%.
(xviii) The Respondent through its letter dated 11 th
March, 2017 stated that there were commercial issues
8/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
between the Respondent and UEM which were
unresolved inspite of meetings held between UEM and
the Respondent.
(xix) The Petitioner by a letter dated 15 th March,
2017 recorded that the project progress was only 1.8%
against the schedule of 68.15%.
(xx) The Petitioner by a letter dated 31st March,
2017 recorded that the progress of the project is 2.01%
against the schedule of 68.70% which was highly
unsatisfactory and the Respondent was called upon to
improve the performance forthwith.
(xxi) The Respondent by its letter dated 13th April,
2017 informed the Petitioner that the Project has slowed
down because of the Sludge disposal issue.
(xxii) The Respondent by a letter dated 8 th May,
2017 informed the Petitioner about its progress with
UEM. The Respondent accepted that there were agreed
terms between them and UEM. The Respondent further
admitted that there was delay in the start of the Project
9/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
as the issue pertaining to sludge was resolved only in
November, 2016.
(xxiii) The Petitioner issued Notice of Termination
dated 9th May, 2017 to the Respondent, notifying the
Respondent to complete the minimum actions on design
and engineering, procurement and construction activities
within period of 30 days of the notice, as particularly set
out therein.
(xxiv) A detailed letter dated 29th May, 2017 was
addressed by the Respondent to the Petitioner pointing
out all the difficulties faced by the Respondent in the
execution of the Contract and the work done by them
together with various documents annexed. The
Respondent reiterated that the delay in execution of
the project was due to the sludge issue. Due to delay in
project the Respondent had invested huge sums in the
project from its own pocket due to which the Respondent
ran out of funds and couldn't pay their technology back
up partners. The Respondent had paid more than 80
lakhs to UEM even though they had not been paid by the
10/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Petitioner. UEM was the technical collaborator but any
Contractual liability would be on the Respondent. It was
further informed to the Petitioner by the said letter that
the commercial dispute with UEM had been resolved.
(xxv) The Respondent addressed a Reply dated 3rd
June, 2017 to the Termination Notice of the Petitioner,
wherein it was claimed that the Respondent has
submitted large number of engineering documents to the
Petitioner. The Respondent also informed the Petitioner
that some documents were simultaneously also pending
for review with UEM.
(xxvi) A Confirmation Letter of Termination dated
15th June, 2017 was addressed by the Petitioner to the
Respondent confirming termination by the Petitioner to
the Respondent, wherein it is inter alia stated that the
Respondent failed to take any steps to complete the
activities that it was called upon to perform in the
Termination Notice.
(xxvii) The Respondent by their letter dated 16th
11/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
June, 2017 replied to the Petitioner's Letter of
Confirmation dated 15th June 2017, which terminated
the Contract.
(xxviii) The Respondent issued a Notice invoking
arbitration under the subject Contract on 27th June,
2017.
(xxix) The Respondent filed Arbitration Petition (L)
No.289 of 2017 under Section 9 of the Arbitration and
Conciliation Act, 1996 ("Arbitration Act") inter alia
seeking injunction on invocation of the Performance
Bank Guarantees. It is pertinent to note that no
injunction was granted by this Court restraining the
Petitioner from invoking the Bank Guarantees.
(xxx) The Petitioner invoked the Bank Guarantees
on 23rd June, 2017.
(xxxi) The Arbitral Tribunal passed the impugned
Award on 26th August, 2021 after hearing the parties.
The Arbitral Tribunal arrived at the conclusion that the
Petitioner had wrongfully terminated the subject
12/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Contract on the reasons mentioned therein.
(xxxii) Being aggrieved by the impugned award, the
Petitioner filed the present Commercial Arbitration
Petition on 23rd November, 2021 inter alia seeking to
quash and set aside the impugned Award. An Interim
Application No.3169 of 2021 was also filed for stay of
execution and implementation of the impugned Award.
(xxxiii) This Court vide its Order dated 17 th April,
2023 admitted the present Commercial Arbitration
Petition and granted stay of the impugned Award upon
the Petitioner depositing the amounts under the Award
with the learned Prothonotary & Senior Master of this
Court.
(xxxiv) As per the direction in the Order dated 17 th
April, 2023, the Petitioner deposited a sum of
Rs.41,12,17,356/- in this Court on 25 th May, 2023. By
virtue of this deposit, the impugned Award has been
stayed.
4. Mr. Vishal Kanade, the learned Counsel appearing for the
13/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Petitioner has submitted that the Arbitral Tribunal had framed 34
issues for determination of the claim of the Respondent/Claimant
therein and the Counter Claim of the Petitioner/Respondent therein.
The Arbitral Tribunal awarded the monetary claim of the Claimant on
issue Nos.10, 15, 16 & 17. The monetary claims have been allowed
on the basis that the Petitioner failed to perform his Contractual
obligations arising under the subject Contract 11th May, 2015 singed
on 29th March, 2016 and that the Petitioner had breached the terms
thereof because of which the Petitioner's termination has been held
to be wrongful. This is covered by issue Nos.1, 2, 6, & 9.
5. Mr. Kanade has submitted that the Petitioner had
terminated the said Contract on the grounds mentioned in the
termination notice. The said Contract entered into between the
parties i.e. the Petitioner and the Respondent primarily contemplated
the Respondent to construct, erect and install the modernized
effluent treatment plant and provide facilities in connection
therewith. The Respondent was required to complete the works
within a period of 32 months from the date of issuance of the Letter
of Award (LoA) which was issued on 11th May, 2015 and the
expected date of completion thus was 10th January, 2018.
14/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
6. Mr. Kanade has submitted that the Respondent was
responsible for inordinate delay in the completion of its Contractual
obligations leading to the delay in the project. The Respondent had
appointed one UEM as its technical collaborator and submitted the
MoU with UEM to the Petitioner. As per the technical collaboration
agreement UEM was responsible for basic design and detailed
engineering, technical collaboration assistance, services, critical
equipment supplies and expert supervision.
7. Mr. Kanade has submitted that in view of the delays on
the part of the Respondent, on 9th May 2017 the Petitioner issued
termination notice to complete minimum action on design and
engineering within 30 days. The reason for termination by the
Petitioner was on account of unsatisfactory performance of the
Respondent for which remedy period of 30 days was provided under
Clause 12.4 of the said Contract. During this period the Respondent
was required to complete essentially six items.
8. Mr. Kanade has referred to the correspondence
addressed by the Respondent which was without submitting any
catch-up plan duly endorsed by UEM to arrest the delay.
15/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
9. Mr. Kanade has submitted that the Arbitral Tribunal had
found that the Respondent has no technical expertise for this project
(Paragraph 107 of the impugned Award). Further, the Arbitral
Tribunal held that but for participation of UEM, the Respondent
could not have been awarded this tender (Paragraph 111 of the
impugned Award). The Arbitral Tribunal further found that
although signatures of UEM on the basic plans and engineering
designs were not required but the fact remained that the Respondent
had to satisfy the Petitioner that UEM was involved and had
approved what was submitted (Paragraph 124 of the impugned
Award).
10. Mr. Kanade has submitted that inspite of rendering the
aforesaid findings, the Arbitral Tribunal gave a contradictory finding
that although approval of UEM was not provided, the said Contract
could not be terminated (Paragraph 163, 181 and 192 of the
impugned Award).
11. Mr. Kanade has submitted that the Arbitral Tribunal has
erred in equating the milestone payment for drawings at 5% as the
basis of importance of submission of approved drawings without
which construction could not have proceeded. He has submitted that
16/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
the value of preparation of plans cannot be conflated to the
importance of approved plans, since it is only after plans for ETP
were approved, could further work be carried out under the said
Contract.
12. Mr. Kanade has submitted that once the Tribunal held in
Paragraph 124 of the impugned Award that the Respondent had to
satisfy the Petitioner herein that UEM was involved and had
approved the plans that were submitted, it was for the Respondent to
show that the said plans were approved by UEM. He has submitted
that there is no such evidence on record. Despite rendering this
finding, the Arbitral Tribunal in further portion of the said award has
held that the said Contract does not provide for any involvement of
UEM. He has submitted that the contradictory findings make the
impugned Award perverse.
13. Mr. Kanade has submitted that there was no effective
response to this argument of the Petitioner on the aforementioned
issue. The findings on termination not being valid are ex facie
erroneous necessitating interference under Section 34 of the
Arbitration Act.
17/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
14. Mr. Kanade has submitted that the Arbitral Tribunal has
awarded monetary claims of the Respondent by deciding Issue No.
10, 15, 16 and 17 in its favour. He has submitted that the
Respondent had sought the claim of work done not paid for inter alia
the expenses incurred towards the purchase orders, sludge removal
and shifting from Pond B to the excavated area, amounts paid to
UEM and M/s. RPS (Engineering Consultant) and other work orders.
In support of this claim, the Respondent had produced the Work
Order/Purchase Orders, Invoices and Bank Statements in the
Statement of Claim. The Petitioner had explicitly denied the
contentions of the Respondent in the Statement of Defence and inter
alia denied that the Respondent was entitled to any amounts under
the head of work done not paid.
15. Mr. Kanade has submitted that the documents submitted
by the Respondent having not been admitted by the Petitioner and
denied on the ground that they were photocopies and some
documents were not offered for inspection has not been considered
by the Arbitral Tribunal.
16. Mr. Kanade has submitted that the Petitioner has pleaded
that the Statements of Expenses have not been proved by the
18/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Respondent's witness and this further explicated the discrepancy in
the purchase orders and bank statements produced by the
Respondent. He has referred to the discrepancies in the documents
relied upon by the Respondent. His submission is that the Statement
of Expenses are not certified by the bank and is a mere print out and
there are further discrepancies in the statement. He has submitted
that there are no invoices which backed the Statement of Expenses
and thus, no proof of payment.
17. Mr. Kanade has submitted that the work orders were not
offered for inspection. Further, it does not contain acceptance by the
Vendor. Hence, no evidence was led by Respondent to corroborate
the same.
18. Mr. Kanade has submitted that the Arbitral Tribunal has
awarded the claim of 'work done not paid' only on the basis of the
statement made by the Respondent that it had made payments to
various third parties, and in the absence of any supporting evidence.
The Respondent had merely made bold assertions without any
reasoning to support it, i.e., a bare ipse dixit.
19. Mr. Kanade has submitted that the Arbitral Tribunal has
19/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
rejected the Counter Claim of the Petitioner without furnishing
reasons. On the contrary, the Arbitral Tribunal has erroneously
observed that in the absence of any Counter-claim, the Respondent
must be paid for work done / payments made, whether the Contract
was terminated or not.
20. Mr. Kanade has submitted that the Respondent has
claimed profit of 15% on the amount of work withdrawn on account
of the alleged wrongful and illegal termination. However, the
Respondent failed to substantiate with proof that such a loss or
damage has actually been incurred. The Respondent was never
prevented from performing its part of the Contract. The figure of
15% is arbitrary and unsubstantiated.
21. Mr. Kanade has submitted that the Arbitral Tribunal has
erroneously awarded the claim for loss of profit on the basis that the
termination of the said Contract was allegedly wrongful. He has
submitted that in the event the Court interferes with the findings on
termination, this issue of loss of profit would have to be answered in
the negative.
22. Mr. Kanade has submitted that the Arbitral Tribunal has
20/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
erroneously awarded Rs.14,93,79,332/- for loss of profit only on the
basis of the contentions made by the Respondent without any
evidentiary proof thereof. Thus, such a claim could not have been
awarded in the first place.
23. Mr. Kanade has submitted that the Petitioner has been
directed to refund the performance bank guarantee only on the
premise that the termination was invalid and Issue No. 9 being
decided in favour of the Respondent. He has submitted that if the
findings on Issue No. 9 i.e. the 'Issue on Termination' is found to be
erroneous warranting interference under Section 34 of the
Arbitration Act, the encashment of the performance bank guarantee
cannot be faulted with.
24. Mr. Kanade has submitted that the Arbitral Tribunal has
awarded interest of 12%. He has submitted that this is contrary to
Clause 28.1(6) of the said Contract, wherein the parties have agreed
that any claim for such interest made by any party shall be void. He
has submitted that in view of this Contractual stipulation, the Arbitral
Tribunal could not have awarded pendent lite interest on the claim
granted under this issue.
21/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
25. Mr. Kanade has submitted that the sludge cannot be
equated to scrap. He has referred to the said Contract as well as the
pre bid meeting held on 10th January, 2014. At the meeting the
bidders which included the Respondent also consciously addressed
separate queries on the method of disposal of sludge and scrap. He
has submitted that the bidders including the Respondent were aware
that sludge did not form part of the scrap generated from the
dismantling activities under the said Contract. The Petitioner had
satisfactorily answered the queries raised by different bidders clearly
differentiating sludge from scrap and clarifying the method in which
they had to be independently disposed. He has submitted that the
clarifications provided by the Petitioner during the pre-bid meeting
are to be read with and forms part of the said Contract.
26. Mr. Kanade has submitted that even in the terms of the
Contract, more particularly Clause 1.11 of the Scope of Work it was
postulated for a strict adherence to the statutory requirements and
approvals and specifically connoted the term 'disposal' as the method
of dealing with and removing sludge from the existing facilities
contemplated. He has relied upon Clause 6.8 of General Conditions
of Contract in support of his submission that even assuming that the
22/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Respondent herein was permitted to treat the sludge as its
entitlement and dispose of the same in any manner it chooses, in
view of inconsistency between discretion of the parties, the
instruction of the Petitioner would prevail and the Respondent would
be bound to implement the Contract in the manner as called upon by
the Petitioner.
27. Mr. Kanade has submitted that the Arbitral Tribunal
erred in not appreciating the test reports placed on record. The
Arbitral Tribunal failed to notice that the reason for re-processing of
the sludge content was a result of the 3 rd Test Report, which was
conclusive in relation to presence of hydrocarbons. He has submitted
that it was in that context that the Petitioner re-processed the sludge
from surge pond B.
28. Mr. Kanade has submitted that the Petitioner's re-
processing sludge from surge pond B has been disregarded by the
Arbitral Tribunal.
29. Mr. Kanade has submitted that the Arbitral Tribunal has
failed and erred in awarding the Claim for loss of revenue against
sludge recycling. He has submitted that the basis of granting the
23/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
claim is that scrap and sludge are synonymous and that amount of
Claim (Rs.4000/- per MT) is based on a single document being a
purported letter dated 10th August 2015 from the Respondent to
MOCL.
30. Mr. Kanade has submitted that the Petitioner had denied
the aforementioned document in his Statement of Defence. This
document had been relied upon by the Respondent's witness in his
evidence, however, the contents of the documents have not been
proved in evidence.
31. Mr. Kanade has submitted that the Respondent having
failed to prove its case is evident from reading of Paragraph 234 of
the said Award, inspite of which the Tribunal relied upon the
approximate sludge quantity of 4459 MT, suo moto and without any
basis increased this quantity to 5000 MT. He has submitted that there
was no basis for this supposition and conjecture. He has submitted
that even the rate mentioned of Rs. 4,000/- was not proved in as
much as this is a quotation and not a final Contract. He has
submitted that accordingly, the Arbitral Tribunal has arrived at
findings which are not supported by evidence and / or has not dealt
with objections of the Petitioner to the admissibility and reliance on
24/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
this document while granting the claim.
32. Mr. Kanade has accordingly submitted that the impugned
Award be set aside as the impunged Award has been challenged
within the scope and confines of Section 34 of the Arbitration Act on
the ground that the impugned Award is patently illegal and perverse.
33. Mr. Kanade has in support of his submission that the
impugned Award is vitiated on account of patent illegality and
findings rendered in the impugned Award are merely based on the
Respondent's herein contentions without dealing with the Petitioner's
evidence is against the public policy of India has relied upon the
Judgment of the Supreme Court in Ssangyong Engineering
Construction Ltd. v. NHAI1 at Pargraphs 34 to 36 (Award being
against public policy) and Paragraph 37 onwards (Setting out the
grounds of patent illegality); Delhi Metro Railway Corporation Pvt.
Ltd. v. Delhi Airport Metro Express Pvt. Ltd. 2 at Paragraph 29
onwards & Associate Builders v Delhi Development Authority 3 at
Paragraph 27 onwards.
1 [(2019) 15 SCC 131] 2 [(2024) 6 SCC 357] 3[(2015) 3 SCC 49]
25/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
34. Mr. Kanade has submitted that there is no proof of loss of
profit adduced by the Respondent in support of its claim and the
amount awarded is merely predicated on there being breach on
behalf of the Petitioner. In support of his submission on this issue, he
has relied upon the ratio laid down in the Judgments requiring the
party claiming damages (including by way of loss of profit) to
establish proof of the damages suffered upon established procedure
and principles. These Judgments are as under:
(i) Bharat Coking Coal v LK Ahuja [(2004) 5 SCC
109] at Paragraph 24.
(ii) State of Rajasthan and Another Versus Ferro
Concrete Construction Private Limited [(2009) 12 SCC
1] at Paragraph 24 read with Paragraphs 52 to 55.
(iii) Essar Procurement Services Ltd. v. Paramount
constructions (2016 SCC OnLine Bom 9697) at
Paragraphs 101 to 113.
35. Mr. Kanade has submitted that the Arbitral Tribunal has
erred in awarding the claim for pendent lite interest, particularly in
view of the Contractual bar contained in the said Contract between
26/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
the parties. He has in support of this submission relied upon Union
of India v Manraj Enterprises4 at Paragraphs 23 to 36 & IOCL v.
Shree Ganesh Petroleum Ltd.5 at Paragraphs 15 and 44.
36. Mr. Kanade has distinguished the Judgments cited on
behalf of the Respondent as being inapplicable to the present case.
He has submitted that the impugned Award be set aside as it has
been challenged within the scope and confines of Section 34 of the
Arbitration Act as being patently illegal and perverse.
37. Mr. Mayur Khandeparker, the learned Counsel appearing
for the Respondent has submitted that the Arbitral Tribunal has
arrived at findings with regard to the rival issues as to Performance of
the Work and which are in Paragraphs 195 to 226 of the impugned
Award.
38. He has submitted that disposal of the sludge was the
prime activity without which the work could not be progressed. It is
an expressed finding of the Arbitral Tribunal that the Petitioners
wrongly insisted on the Respondent for disposing the sludge through
incineration right from start of work. This is despite 3 Test Reports
4 (2021 SCC OnLine SC 1081) 5(2022 SCC OnLine SC 131)
27/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
on the record which clearly established that the sludge was to be
recycled. He has referred to the three Reports which have been
relied upon by the Arbitral Tribunal viz. Geo Chem Report dated 31st
December, 2015; MPCB Report dated 17 th May, 2016 & MWML
Report dated 07th September, 2016.
39. Mr. Khandeparkar has submitted that there were further
activities as per the Planning Package which could not be achieved as
the prime activity of disposal of sludge was still not completed due to
the Petitioner's insistence in not allowing the Respondent to dispose
sludge through recycling. Hence, the delay in progress though
negligible, was purely on the Petitioner's Account.
40. Mr. Khandeparkar has submitted that finally after 18
Months on 29th November, 2016 the Petitioner gave permission and
allowed the Respondent to shift the sludge inside the Plant in nearby
area of Pond-B. Due to the bulk quantity of sludge of 7500 MT the
Respondent consumed a period of 3.5 Months to shift the Sludge.
The shifting was completed by March, 2017. It was only then that the
Respondent could place orders for Equipment and submitted 143
Nos. of Drawings against Requirement of 129 Drawings as per
Planning Package.
28/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
41. Mr. Khandeparkar has submitted that the Petitioners by
their Show Cause Notice dated 9th May, 2017 called upon the
Respondent to show progress as per the Original Planning Package
without considering the delay of 18 Months committed by the
Petitioner in giving their decisions for disposal of the sludge.
42. Mr. Khandeparkar has submitted that the Respondent has
in its correspondence shown its bonafides by placing orders of
Equipment's, submitting Drawings with respect to progress of the
work and requested the Petitioner not to compare the progress
achievable as per the Planning Package. This due to the sludge
having to be removed 18 months back but it was on the Petitioner's
wrong insistence and wrong decision that the entire said period of 18
Months was wasted. He has submitted that the progress has to be
calculated by giving effect of sludge removal from November, 2016
instead of May, 2015.
43. Mr. Khandeparkar has submitted that the Petitioner
terminated the Contract on 15 th June, 2017 without dealing with any
of the issues raised by the Respondent and without considering the
aforementioned correspondence of the Respondent.
29/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
44. Mr. Khandeparkar has referred to the findings of the
Arbitral Tribunal at Paragraphs 223 & 224 of the impugned Award
wherein there is a categorical finding that the Respondent had
achieved a progress of 2.01% which as per the statistics in Planning
Package only 1.62% could have been achieved without removal of
sludge. Hence, the Respondent had achieved more than what was
required.
45. Mr. Khandeparkar has submitted that the Arbitral
Tribunal has awarded an amount of Rs. 1.06 Crores only for which
the Respondent had submitted the Invoices & Work Orders of UEM,
the Engineering Consultant and Vendors. The Respondent had also
submitted the Bank Statements in support thereof. He has submitted
that it is not the case of the Petitioner that the payments made to
Vendors were pertaining to another Contract. The Bank Statements
clearly establish that the payment of Rs. 1,06,91,238.00 was made by
the Respondent to UEM, the Engineering Consultant and Vendors
under the said Contract. The evidence of Respondent Witness was left
uncontroverted as no questions were asked by the Petitioner in that
regard. Accordingly, the awarded sum of Rs.1,06,91,238.00 was
justified.
30/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
46. Mr. Khandeparkar has submitted that reliance has been
placed by the Petitioner on the Pre-Bid Meeting on the queries of the
Bidders wherein the Petitioner had recorded that "MWML, Taloja an
approved Party from CPCB / MPCB for handling / disposal. Bidder
may fix Contract and dispose sludge". He has submitted that this was
not an explicit condition but merely a suggestion on the part of the
Petitioner.
47. Mr. Khandeparkar has submitted that it was the case of
the Respondent that the Respondent had shifted 7500 MT of sludge
in the area nearby to Pond-B inside the Plant allotted by the
Petitioner. However, the said quantity was not awarded by the
Tribunal against which the Tribunal awarded 5000 MT of sludge
revenue to the Respondent. He has submitted that the impugned
Award for quantity of 5000 MT was based on various documents on
the record. The dimension of the Pond- B where sludge was lying
was answered in pre-bid query by the Petitioners. Further, during
cross-examination of RW-1, in Q.138, the witness has answered that
the dimensions of the Pond were l00 meters x 35 meters; hence, the
Quantity of Sludge can be worked out as 100 x 35 x 2.00 Depth =
7000 cum which translates to 7000 MT; the Petitioner's Suggestion to
31/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
the Respondent Witness CW-1 during cross examination was that the
maximum capacity of the surge pond B is 7500 MT. CW-1 had
confirmed that the Sludge of 7500 MT was shifted from one Pond to
the other; it was the case of Petitioner that the sludge lying in the
Pond was 7500 MT; Respondent's CW- 1 Evidence at Paragraph 31
has pleaded his case for Quantity of 7500 MT.
48. Mr. Khandeparkar has submitted that the impugned
Award for quantity of 5000 MT is substantiated based on the
documents produced. He has referred to the MPCB Letter dated 23 rd
January 2013 which gave Consent to the Petitioner to operate for
5000 MT of oil sludge from the storage tank in Ponds under Sr. No.
3.3 of Schedule I of the HW Rules 2008 which provides for disposal
through CHWTSDF for incineration / bioremediation / MPCB
authorized reprocessor. Further, the Petitioner's Witness RW-1 in
answer to Question 67 admitted that the 2014 consent to operate
does not apply to the 5000MT of sludge which was lying in the surge
ponds since the same was covered only by the earlier 2013 Consent
to Operate. Hence RW-1 had admitted the quantity of 5000 MT lying
in Surge Pond. Finally, Petitioner floated the Tender on 14 th March,
2017 for recycling of the said sludge and mentioned Estimate
32/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Quantity as 4459 MT of sludge. He has submitted that there was
sufficient evidence to support at least minimum quantity of 5000 MT
of sludge lying.
49. Mr. Khandeparkar has submitted that the Arbitral
Tribunal had considered and allowed the quantity of 5000 MT of
sludge revenue to the Respondent. The Petitioner has not dealt with
the aforementioned documents in Rejoinder.
50. Mr. Khandeparkar has submitted that the objection to the
rate of sludge of Rs.4000 Per MT is misplaced. There is sufficient
material to justify the said rate considered by the Arbitral Tribunal.
He has referred to the Order dated 01st August, 2015 placed on
MOCL @ Rs.4000/ Per MT by the Respondent for disposal of sludge.
The MOCL had attended and participated in the process of Sample
Testing of the Sludge inside the Uran Plant. Further, MOCL was an
Approved Agency for recycling, approved by MPCB & CPCB. He has
also relied upon the DAR and Final Audit Report wherein it was
recognised by the Petitioner's Audit Team that for recycling of sludge,
the rate prevailing prior to the year 2000 was Rs.1600/-
51. Mr. Khandeparkar has submitted that the Respondent's
33/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
CW-1 Evidence at Paragraph 31 has pleaded its case and claimed the
Rate of Rs.4000/- Per MT for the said quantity of sludge. This
evidence was left uncontroverted as no questions were asked by the
Petitioner in that regard. He has submitted that after a period of 17
years, it cannot be said that the rate of Rs.4,000/- is inflated and / or
exaggerated. He has submitted that the Tribunal based on the
aforementioned documents granted Award for the quantity of 5000
MT to be paid @ Rs.4000/- MT amounting to Rs.2.00 Crores to the
Respondent and hence, the impugned Award insofar as this claim is
concerned is justified.
52. Mr. Khandeparkar has then referred to the findings of the
Arbitral Tribunal on the claim of loss of profit, in particular
Paragraphs 195 to 226 of the impugned Award. The Arbitral
Tribunal has rendered detailed justification with elaborate findings
that termination of the Contract was declared as illegal and
wrongful. Hence, the claim for Loss of Profit was justified.
53. Mr. Khandeparkar has submitted that the Petitioner's
contentions that the Respondent was never prevented from
performing its part of Contract is a mere Statement without any
supportive document.
34/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
54. Mr. Khandeparkar has submitted that the Respondent
never lacked in achieving the progress and that the termination of
the Contract was wrongful & unjustified. He has reiterated his
submissions with regard to the sludge being recyclable and within
the Respondent's Scope. The Respondent has relied on various
documents to substantiate that the Respondent was very well
prevented from progressing the work and the Petitioners action of
terminating the Contract for short progress was highly erroneous
since the Petitioner itself had delayed the work and hence could not
have expected / sought the progress from the Respondent achievable
as per planning package more specifically by giving decision of
sludge on 29th November, 2016 which otherwise was to be given in
May, 2016.
55. Mr. Khandeparkar has placed reliace upon A. T. Brij Paul
Singh v. State of Gujarat,6 and Mohd. Salamatullah V. Govt.of A.P. 7
wherein the Supreme Court has laid down directives that the proof of
expected profit cannot be given but on the grounds of wrongful
termination and upon which the Loss of Profit claim will follow @
15% towards the amount of balance remaining work. He has
6 (1984) 4 SCC 59) 7(1977) 3 SCC 590)
35/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
submtited that it is the Respondent's case that in the said Contract
the Respondent Profit Margin was 15% on the entire Contract sum
i.e. Rs.111,04,76,499/-.
56. Mr. Khandeparkar has submitted that the balance work
remained to be executed was Rs.99,58,62,217/- after deducting the
total work claimed to be done i.e. Rs. 11,46,14,282/- Hence, 15% on
said balance remaining work of Rs.99,58,62,217/- comes to Rs.
14,93,79,332/-.
57. Mr. Khandeparkar has submitted that the Respondents
through CW-1 Affidavit of Evidence has claimed 15% on the
aforementioned balance remaining work which comes to
Rs.14,93,79,332/-.
58. Mr. Khandeparkar has submitted that the evidence of
Respondent's witness was left uncontroverted as no questions were
asked by the Petitioner in this regard. He has submitted that the
Arbitral Tribunal in Paragraphs 248 to 252 of the impugned Award
has with sufficient justification awarded amount of
Rs.14,93,79,332/- towards Loss of Profit.
59. Mr. Khandeparkar has submitted that the Petitioners'
36/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
contention that out of entire Contract sum of Rs.111,04,76,499/-, the
Cost of Rs.16,74,85,000/- was towards the operation & maintenance
work and hence the Loss of Profit ought not to have been granted by
the Arbitral Tribunal for the said operation & maintenance work is
misplaced. He has submitted that whereas the Respondent had a
Profit Margin of 15% on entire Contract value including for the work
of operation & maintenance of Rs.16,74,85,000/- since the said work
was to maintain the ETP Plant i.e., the subject work itself. Hence, the
Respondent had correctly claimed the Loss of Profit on the balance
remaining entire subject Contract work. He has accordingly
submitted that the finding of the Arbitral Tribunal of
Rs.14,93,79,332/- which was the claim for Loss of Profits was
justified and there is no error or discrepancy in such finding.
60. Mr. Khandeparkar has submitted that the Arbitral
Tribunal in Paragraphs 195 to 226 of the impugned Award has
rendered detail justification with elaborate findings that Termination
of the Contract was declared as illegal and wrongful. Hence, the
claim for refund of Bank Guarantee was justified. He has submitted
that the Arbitral Tribunal in Paragraph 264 of the impugned Award
allowed refund of Performance Bank Guarantee amount of
37/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Rs.9,42,99,150/- alongwith interest @ 12% from the date the
Petitioner received the said amount from the Bank. This is totally
justified.
61. Mr. Khandeparkar has submitted that the Supreme Court
has laid down directives that in the Award if the reasons appear to be
insufficient or inadequate but on a careful reading of the Entire
Award, coupled with Documents recited / relied therein, the
underline the reason, factual or legal, that forms the basis of the
Award is in discernible / intelligible and the same Exhibits no
perversity then the Court need not set aside the Award while
exercising the powers under Section 34 and 37 of the Act. The Court
may explain the existence of that underline the reason while dealing
with a challenge laid to the Award and in doing so, the Court does
not supplant the reasons of the Arbitral Tribunal but only explains it
for a better and a clearer understanding of the Award. He has placed
reliance upon the Judgment of the Supreme Court in OPG Power
Generation Pvt. Ltd. V/s. Enexio Power Cooling Solutions India Pvt.
Ltd. & Anr.,8 at Paragraph 148 in this context.
62. Mr. Khandeparkar has submitted that the jurisdiction of
8 2024 SCC Online SC 2600
38/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
the Courts under Section 34 is fairly narrow and the Court may
interfere on merits on limited grounds under Section 34 of the
Arbitration Act. He has in this context placed reliace upon the
Judgment of the Supreme Court in UHL Power Co. Ltd. Vs. State of
Himachal Pradesh9.
63. Mr. Khandeparkar has further relied upon the Judgment
of the Supreme Court in Delhi Airport Metro Express Private Limited
Vs. Delhi Metro Rail Corporation Limited10 in support of his
submission that the Courts cannot re-appreciate evidence to conclude
that the impugned Award suffers from patent illegality.
64. Mr. Khandeparkar has submitted that if the conclusion of
the Arbitrator is based on a possible view of the matter, the Court
should not interfere. In this connection he has placed reliance upon
the Judgment of the Supreme Court in OPG Power Generation Pvt.
Ltd. (supra).
65. Having considered the submissions, the Arbitral Tribunal
has in the impugned Award held that the Petitioner / Respondent
therein had failed to perform its Contractual obligations under the
9 (2022) 4 SCC 116
10 (2022) 1 SCC 131
39/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
said Contract dated 11th May, 2015 signed on 29th March, 2016.
There is a finding that the Petitioner has breached the terms of the
said Contract and because of which the Petitioner's termination has
been held to be wrongful. This is a finding in relation to Issue Nos.1,
2, 6, & 9. It is by virtue of this finding that the Arbitral Tribunal has
awarded the monetary claim of the Respondent / Claimant therein
under Issue Nos.10, 15, 16 & 17.
66. The Petitioner has contended that the Arbitral Tribunal
has erroneously held that the Petitioner has wrongfully terminated
the Contract. It is their contention that the delay in performance of
the said Contract i.e. delay in issuance of the basic plans and
engineering design / drawings had resulted in the Termination Notice
to complete minimal action on design and engineering within 30
days thereof. There is reliance upon the period within which the
Respondent was to complete the works under the said Contract i.e. to
construct, erect, install the modernized Effluent Treatment Plant and
provide facilities for air-conditioning, ventilation, testing, painting,
lining, insulation, commissioning and guaranteeing the entire
modernization of ETP. These contentions are in my view misplaced
and are contrary to the plain reading of the said Contract as well as
40/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
the documents on record / evidence which was before the Arbitral
Tribunal and appreciated by them.
67. The Petitioner has called upon this Court exercising
jurisdiction under Section 34 of the Arbitration Act to re-appreciate
the evidence as well as arrived at an interpretation of the terms of
the Contract contrary to that arrived at by the Arbitral Tribunal and
particularly when the conclusion of the Arbitral Tribunal is a possible
view. It has been held by the Supreme Court in Delhi Airport Metro
Express Pvt. Ltd. (Supra) that Courts exercising jurisdiction under
Section 34 of the Arbitration Act cannot re-appreciate evidence to
conclude that the Award suffers from patent illegality. Further, the
Supreme Court in OPG Power Generation Pvt. Ltd. (Supra) has held
that if the conclusion of the Arbitrator is based on a possible view of
the matter, the Court under Section 34 of the Arbitration Act should
not interfere. The grounds raised by the Petitioner are directly hit by
the aforementioned Judgments of the Supreme Court as these are
considered to be not valid grounds to be raised under Section 34 of
the Arbitration Act.
68. The contention of the Petitioner that the Arbitral
Tribunal erred in equating the mile stone payment for drawings at
41/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
5% as the basis of importance of submission of the approved
drawings without which construction could not have proceeded is
misconceived. The Arbitral Tribunal has in construing the Contract
held that the disposal of the sludge was a prime activity without
which the work of construction / engineering under the said Contract
could not proceed. The Petitioner had wrongly insisted on the
Respondent disposing the sludge through incineration right from the
start of the work. The Arbitral Tribunal has placed reliance upon the
three Test Reports viz. Geo Chem Report dated 31st December, 2015;
MPCB Report dated 17th May, 2016 & MWML Report dated 07 th
September, 2016 which clearly establish that sludge was to be
recycled, inspite of which, the Petitioner insisted on the Respondents
to dispose of the sludge through incineration.
69. The Petitioner's reliance on the work to be completed
within a period of 32 months from the date of issuance of the LoA
and there being delay in issuance of basic plans and engineering
design / drawings is entirely misplaced. The issuance of the basic
plans and engineering designs / drawings by the Petitioner cannot be
read in isolation as the prime activity was the disposal of sludge,
without which the construction work could not commence.
42/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
70. It is to be seen that the Petitioner after a period of 18
months of execution of the said Contract, i.e. on 29th November,
2016 gave permission and allowed the Respondent to shift the sludge
inside the Plant in nearby area of Pond-B. It is only after the period
of 3.5 months consumed by the Respondent for shifting the bulk
quantity of sludge of 7500 MT and which was completed by March,
2017, could the Respondent placed orders for equipment and submit
143 numbers of drawings against requirement of 129 drawings as per
the planning package.
71. The Petitioner has relied upon findings of the Arbitral
Tribunal that but for the participation of UEM who had technical
expertise, the Respondent would not have been awarded the tender
and that although the signatures of UEM on basic plans and
engineering designs were not required but the fact remains that the
Respondent had to satisfy the Petitioner that UEM was involved and
had approved what was submitted. This Petitioner has by placing
reliance on these findings contended that the Arbitral Tribunal gave
contradictory finding that though the approval of UEM to the basic
plans and engineering designs was not provided, the said Contract
could not be terminated. This contention in my view is misconceived.
43/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
J-CARBP 648.2021.doc
This overlooks the conclusion arrived at by the Arbitral Tribunal that
under the said Contract, the approval of UEM to such basic plans and
engineering designs was not required.
72. The Termination of the Contract on 15th June, 2017 by
the Petitioner was without considering the issues raised by the
Respondent and the multiple correspondence addressed by them. The
Arbitral Tribunal has in Paragraphs 223 and 224 given a categorical
finding that the Respondent had achieved progress of 2.01% which as
per the statistics and planning package only 1.62% could have been
achieved, without removal of sludge. Hence, the Respondent had
achieved more than what was required.
73. The Arbitral Tribunal after appreciating the evidence on
record as well as terms of the said Contract has awarded the amount
of Rs.1.06 Crores for work done but not paid and this after finding
that the termination of the said Contract by the Petitioner was
wrongful. This Court under Section 34 of the Arbitration Act, cannot
re-appreciate the evidence which is in the form of invoices and work
orders of UEM, the Engineering Consultants and Vendors as well as
the bank statements which were produced by the Respondent and
upon an appreciation of which the Arbitral Tribunal has held that
44/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
they establish payment of Rs.1,06,91,238/- made by the Respondent
to UEM, the engineering consultants and vendors under the said
Contract. Thus, I find no infirmity in the findings in the Award on the
material forming part of the evidence and which has been
appreciated by the learned Arbitrator.
74. In so far as the issue of loss of revenue against sludge
recycling, the findings of the Arbitral Tribunal in the impugned
Award for quantity of 5000 MT is based on the evidence on record as
well as various documents produced by the Respondent. The
evidence of the Respondent through its witness CW-1 has been
referred to whilst recording the submissions on behalf of the
Respondent. The Arbitral Tribunal having found that there was
sufficient evidence to support at least minimum quantity of 5000 MT
of sludge lying, this finding on evidence cannot be faulted with
particularly by this Court exercising jurisdiction under Section 34 of
the Arbitration Act. Further, it is well settled that re-appreciation of
evidence is impermissible.
75. With regard to the rate of Rs.4000 per MT, the Arbitral
Tribunal has held that there was sufficient material to justify the said
rate and based upon which the Arbitral Tribunal has held that the
45/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
loss of revenue against sludge recycling is Rs.2 Crores. This finding of
the learned Arbitral Tribunal is also on an appreciation of evidence,
and cannot be re-appreciated as held above.
76. The claim for loss of profits of Rs.14,93,79,332/-
awarded by the Arbitral Tribunal is pursuant to elaborate findings
that the termination of the Contract by the Petitioner was illegal and
wrongful. It has been held by the Supreme Court M/s. AT Brij Paul
Singh (Supra) and Mohd. Salamatullah & Ors. (Supra) that proof of
expected loss of profit cannot be given but on the grounds of
wrongful termination. The loss of profit claim will follow at the rate
of 15% towards the amount of balance remaining work. The attempt
made by the Petitioner to distinguish these Judgments is entirely
misconceived. The Arbitral Tribunal has awarded the sum of
Rs.14,93,79,332/- on the basis of 15% on the balance remaining
entire subject Contract work. This after taking into consideration the
work done of Rs.11,46,14,282/- which has been deducted from the
entire Contract sum of Rs.111,04,76,499/- leaving balance work as
Rs.99,58,62,217/- from which 15% has been computed as the loss of
profit. I am of the considered view that there is no infirmity in the
Arbitral Tribunal awarding the claim of loss of profits of
46/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
Rs.14,93,79,332/- which is as per the terms of the said Contract and
the settled law.
77. In so far as the claim of release / refund of Performance
Bank Guarantee which has been awarded i.e. in a sum of
Rs.9,42,99,150/-, this follows from the finding that the termination
of the said Contract was illegal and wrongful. Hence, in view of this
finding of the Arbitral Tribunal which has been upheld by this Court
under Section 34 of the Arbitration Act, the Respondent is entitled to
refund of Performance Bank Guarantee which has been invoked by
the Petitioner on the grounds of termination of the said Contract. The
interest awarded also cannot be faulted with as reasonable rate of
interest has been awarded by the Arbitral Tribunal and this awarded
claim is totally justified.
78. The reliance placed by the Petitioner on Ssangyong
Engineering Construction Ltd. (Supra); Delhi Metro Railway
Corporation Pvt. Ltd. (Supra) and Associate Builders (Supra) in
contending that the impugned award is against the public policy of
India and requires to be set aside is misplaced. These Judgments do
not apply in the present case as the Arbitral Tribunal has appreciated
the evidence on record and arrived at its findings based on such
47/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 ::: J-CARBP 648.2021.doc
appreciation of which cannot be re-appreciated under Section 34 of
the Arbitration Act as per settled law.
79. I further do not find merit in the reliance placed by the
Petitioner in Bharat Coking Coal (Supra); State of Rajasthan (Supra)
and Essar Procurement Services Ltd. (Supra) in support of their
contention that the party claiming damages (including by way of loss
of profits) is required to establish proof of damages suffered upon
established procedure and principles. These Judgments are
inapplicable in the present case as they are distinguishable on facts.
80. The Arbitration Petition having raised grounds of
challenge to the impugned Award which are not valid under Section
34 of the Arbitration Act is dismissed. There shall be no orders as to
costs.
81. The Prothonotary and Senior Master of this Court is
directed to release the sum of Rs.41,12,17,356/- deposited by the
Petitioner for stay of the impugned Award together with the accrued
interest to the Respondent within a period of six weeks from
uploading of this Judgment.
[R.I. CHAGLA, J.]
48/48 ::: Uploaded on - 17/10/2025 ::: Downloaded on - 18/10/2025 01:02:14 :::
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free