Miss Lucy
← All judgments

National Aluminium Co. Ltd. & Anr vs G.C. Kanungo

Supreme Court29 April 2009Asok Kumar Ganguly · Arijit Pasayat

Ratio decidendi

The rule this decision rests on

Where a contractor's claim arises from work completed, the period of limitation under Section 137 of the Limitation Act, 1963 is calculated from the date when the claim is finally determined or when the matter is put in a state of finality, not necessarily from the date of completion of work or payment of a final bill; correspondence and office notings indicating that a matter remains alive and under consideration for decision operate to keep the clock running and prevent a claim from being time-barred even where an initial payment has been made. The interest awarded by an arbitrator in a dispute over claims arising from contractual work may be modified by a court exercising appellate jurisdiction over the award where, in the peculiar circumstances of the case, the rate awarded is found to be excessive, and a lower rate which is reasonable and justified by the facts may be substituted.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL No. 62 OF 2003

NATIONAL ALUMINIUM CO. LTD. & ANR. ... Appellant(s)

Versus

G.C.KANUNGO ... Respondent(s)

JUDGMENT

Dr.ARIJIT PASAYAT,

Heard.

Challenge in this appeal is to the order of a learned Single Judge of the

Orissa High Court dismissing the miscellaneous appeal filed by the present

appellant. In the miscellaneous appeal which was filed under Section 39 of

Arbitration Act, 1940 (in short the 'Act') challenge was to the order passed by

learned Civil Judge, Senior Division, Angul making the award rule of the Court.

The primary stand before the High Court was that the claim made by the

respondent-contractor was barred in terms of Section 137 of the Limitation Act,

1963, (in short 'Limitation Act') The High Court did not accept the stand of the

appellant.

In the present appeal, Mr. A.Sharan, learned ASG appearing for the

appellant submitted that the claim was

-2- barred and for substantiating this stand reference was made to certain dates which

are almost undisputed. The work order in this case was issued on 18.12.1985 and the

work was completed on 15.6.1987. On 20.05.1995, the respondent made a request for

appointment of an Arbitrator and on 29.6.1995 an Arbitrator was appointed. It is

the case of the appellant that sometime in 1989, final bill was paid and there was

nothing remaining to be paid and therefore the further correspondence, if any, are of

no consequence. In any event, the office notings on which reliance has been placed

by the Arbitrator as well as the courts below did not confer any legal right on the

respondent. It was also submitted that the award for the additional work done was

against the terms of the contract. It was, however, fairly accepted that the later

point was never argued before the High Court. It was also submitted that the rate at

which interest has been awarded is high.

In response, Mr. R.K.Rath, learned senior counsel appearing for the

respondent submitted that there are several documents on which the courts below

have placed reliance. This unmistakably show that the matter was alive and more

particularly the letter of the appellant dated 26.8.1992 to the respondent puts the

controversy beyond doubt.

-3-

"Dear Sir, The case file for consideration of your different claims for the above said work is processed.

The decision is awaited.

After the decision is known, the same shall be communicated to you.

In other words, there was no finality in the matter and the matter was

alive for consideration. If this date i.e. 26.5.1992 is taken into account, the claim

made was within the period of three years. That being so, the claim as made was

within the period of limitation and the stand of the appellant that the claim was

barred by limitation is not tenable.

Another point which has been urged with some vehemence is that the rate

at which interest has been granted is 15%. It is stated that rate is quite high. In

response, learned counsel for the respondent stated that presently the applicable rate

is 18% and there is nothing infirm in the award of interest @ 15%.

Considering the peculiar facts of the case we direct that the interest

payable will be 12% p.a. in place of 15% as awarded. The appeal is allowed to the

aforesaid extent.

-4- The documents submitted by way of furnishing security as filed in this

court shall be handed over to learned counsel for the respondent.

...................J. (Dr. ARIJIT PASAYAT) ....................J. ((ASOK KUMAR GANGULY)

New Delhi, April 29, 2009.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free