Mora Tollways Limited vs The State Of Bihar & Ors
- Citation2016 SCC OnLine Pat 6121
Ratio decidendi
The rule this decision rests on
1. A writ petition against the State or its instrumentality arising from a contractual obligation is maintainable in an appropriate case, even where disputed questions of fact arise and even where monetary relief is sought, provided the State's action is arbitrary and unreasonable in violation of Article 14, or other valid and legitimate reasons exist requiring writ jurisdiction; however, if a contract contains an arbitration clause, the writ court should not ordinarily invoke jurisdiction unless the action is arbitrary. 2. Every State action must satisfy the test of reasonableness and not be susceptible to arbitrariness: the petitioner must make a prima facie case of arbitrariness, and the State must then demonstrate that the decision was informed by reason; if the State cannot do so, the action perishes as arbitrary under Article 14. 3. Where the State, through its authorized representatives, has given an assurance to a contracting party that additional costs incurred in reliance on that assurance will be reimbursed, and the contracting party has acted upon that assurance and incurred the costs, the State cannot subsequently retract that assurance without assigning any specific reason or discernible principle for the departure, as such conduct is arbitrary and uninformed by reason, and the doctrine of promissory estoppel operates to prevent the State from denying responsibility. 4. Where the quantum of payment due under a contractual clause is not disputed—the calculation method, the debt amount, and all component figures being admitted and verified—a writ court may grant relief for payment of the contractual sum without referring the matter to arbitration, notwithstanding that the agreement contains an arbitration clause. 5. In determining a matter having a public law domain, even though it involves a contract, a court is entitled to take a broader view and not consider it merely as a private contract question under Article 226 of the Constitution.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE HIGH COURT OF JUDICATURE AT PATNA Letters Patent Appeal No.2158 of 2015 IN Civil Writ Jurisdiction Case No. 7259 of 2015 =========================================================== 1. Mora Tollways Limited, a company incorporated under the provisions of the Companies Act, 1956 and having its registered office at 302, Shree Amba Shanti Chambers, Opposite Hotel Leela, Andheri Kurla Road, Andhri (East), Mumbai-400059, a Special Purpose Vehicle created by Atlanta Limited, 101, Shree Amba Shanti Chambers, Opposite Hotel Leela, Andheri Kurla Road, Andhri (East), Mumbai-400059 through its authorized representative and Project In Charge, Mr. Pillai Ponipass Packiriswami, Son of Late C.K. Packiriswami, permanent resident of flat no. 306, Jalalpur City, Gola Road, Police Station- Rupaspur, District-Patna.
.... .... Appellant Versus 1. The State of Bihar through Principal Secretary, Road Construction Department, Government of Bihar, Patna. 2. The Principal Secretary, Road Construction Department, Government of Bihar, Patna. 3. Bihar State Road Development Corporation Limited through its Managing Director, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 4. The Managing Director, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 5. The Chairman, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 6. The Directors, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 7. The Chief General Manager, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 8. The General Manager, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 9. The Deputy General Manager, Bihar State Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna.
.... .... Respondents WITH
=========================================================== Patna High Court LPA No.2158 of 2015 dt.12-05-2016
2/208
Letters Patent Appeal No. 2084 of 2015 IN Civil Writ Jurisdiction Case No. 7259 of 2015 =========================================================== 1. Bihar State Road Development Corporation Limited through its Managing Director, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 2. The Managing Director, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 3. The Chairman, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 4. The Director, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 5. The Chief General Manager, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 6. The General Manager, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna. 7. The Deputy General Manager, Bihar State Road Development Corporation Limited, office at RCD Central Mechanical Workshop Campus, Sheikhpura, Patna.
.... .... Appellants Versus 1. Mora Tollways Limited, a company incorporated under the provisions of the Companies Act, 1956 and having its registered office at 302, Shree Amba Shanti Chambers, Opposite Hotel Leela, Andheri Kurla Road, Andhri (East), Mumbai-400059, a Special Purpose Vehicle created by Atlanta Limited, 101, Shree Amba Shanti Chambers, Opposite Hotel Leela, Andheri Kurla Road, Andhri (East), Mumbai-400059 through its authorized representative and Project In Charge, Mr. Pillai Ponipass Packiriswami, Son of Late C.K. Packiriswami, permanent resident of flat No.38, Triveni Chaul, Police Station Santa Cruz and presently residing at flat no. 306, Jalalpur City, Gola Road, Police Station- Rupaspur, District-Patna. 2. The State of Bihar through Principal Secretary, Road Construction Department, Government of Bihar, Patna. 3. The Principal Secretary, Road Construction Department, Government of Bihar, Patna.
.... .... Respondents WITH
=========================================================== Patna High Court LPA No.2158 of 2015 dt.12-05-2016
3/208
Letters Patent Appeal No. 2131 of 2015 IN Civil Writ Jurisdiction Case No. 7259 of 2015 =========================================================== 1. The State of Bihar through the Principal Secretary, Road Construction Department, Govt. of Bihar, Patna 2. The Principal Secretary, Road Construction Department, Govt. of Bihar, Patna .... .... Appellants Versus 1. Mora Tollways Ltd. a Company incorporated under the Provision of the Companies Act, 1956 and having its registered office at 302, Shree Amba Shanti Chambers Opposite Hotel Leela, Andheri Kurla Road, Andhari ( East ), Mumbai - 400059, a Special Purpose Vehicle Created by Atlanta Limited, 101 Shree Amba Shanti Chambers, Opposite Hotel Leela, Andhari Kurla Road, Andhari ( East Mumbai - 400059 through its Authorized representative and Project In Charge, Mr. Pillai Ponipass Packiriswami, Son of Late C.K. Packiriswami, Permanent Resident of Flat No. 38, Triveni Chaul, Police Station Santa Cruz and Presently residing at Flat No. 306 Jalalpur City, Gola Road, Police Station Rupaspur, District - Patna 2. Bihar State Road Development Corporation, Ltd., through its Managing Director, office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 3. The Managing Director, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 4. The Chairman, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 5. The Director, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 6. The Chief General Manager, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 7. The General Manager, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna 8. The Deputy General Manager, Bihar State Road Development Corporation, Ltd., office at RCD, Central Mechanical Workshop, Campus, Sheikhpura, Patna .... .... Respondents =========================================================== Appearance : (In LPA No. 2158 of 2015) For the Appellant : Mr. Y. V. Giri, Sr. Adv. Mr. Sanjeev Kumar, Advocate Patna High Court LPA No.2158 of 2015 dt.12-05-2016
4/208
Mr. Dayanand Singh, Advocate For the Respondents : Mr. Harish Kumar, GP 32 For the BSRDC : Mr. Lalit Kishore, PAAG Mr. Vikas Kumar, AC to AG
(In LPA No. 2084 of 2015) For the Appellants : Mr. Lalit Kishore, PAAG Mr. Vikas Kumar, AC to AG For the Respondents : Mr. Y. V. Giri, Sr. Adv. Mr. Sanjeev Kumar, Advocate
(In LPA No. 2131 of 2015) For the Appellants : Mr. Harish Kumar, Advocate Mr. Binod Kumar Sinha, Advocate For the Respondents : Mr. Lalit Kishore, PAAG Mr. Vikas Kumar, AC to AG For the BSRDC : Mr. Lalit Kishore, Sr. Adv. =========================================================== CORAM: HONOURABLE THE ACTING CHIEF JUSTICE AND HONOURABLE MR. JUSTICE CHAKRADHARI SHARAN SINGH
JUDGMENT AND ORDER CAV
(Per: HONOURABLE MR. JUSTICE CHAKRADHARI SHARAN SINGH) Date: 12-05-2016 These appeals arise out of common judgment and
order, dated 22.09.2015, passed by the learned single Judge
of this Court on a writ application filed under Article 226 of the
Constitution of India by Mora Tollways Limited, a company
incorporated under the provisions of the Companies Act, 1956
(hereinafter referred to as the „Companies‟). The said
Company is the appellant of L.P.A. No. 2158 of 2015. The
Bihar State Road Development Corporation Limited and others
(hereinafter referred to as the „Corporation‟) and its
functionaries, who were impleaded as respondent Nos. 3 to 9
in the writ proceedings before learned Single Judge, have also Patna High Court LPA No.2158 of 2015 dt.12-05-2016
5/208
questioned the legality of the same judgment and order passed
by the learned single Judge by filing LPA No. 2084 of 2015.
The State of Bihar has filed another appeal being L.P. A. No.
2131 of 2015, who were respondent Nos. 1 and 2 in the writ
proceedings, being aggrieved by the same judgment and order
of the learned single Judge.
2. This is the reason why all the three appeals have
been heard together, with the consent of the parties, and are
being disposed of by the present common judgment and order.
3. Before I advert to the extensive arguments
advanced on behalf of the Company, the Corporation and the
State of Bihar, it would be apt to take note of the conclusion
arrived at by learned single Judge in the order under appeal,
and legal reasoning assigned for such conclusion since
sustainability of the said order is in question, in the present
batch of appeals. For the said purpose, I have considered it
appropriate to take brief note of the admitted facts mentioned
by learned single Judge, which are foundation for arriving at
the said conclusion.
4. There was a notice/request for qualification,
dated 16.07.2010, by the Corporation for the purpose of
construction, operation and maintenance of National Highway
No.30 in the State of Bihar, including the section from km
0.000 to km 116.760 on Mohania-Ara section of National Patna High Court LPA No.2158 of 2015 dt.12-05-2016
6/208
Highway No.30, by Four Laning on Design, Build, Finance,
Operate and Transfer ("DBFOT") basis. Atlanta Ltd., a
Company incorporating under the Companies Act, 1956 had
submitted bit in pursuance thereof and was short listed.
Cosequent upon its short listing, the Company was created as
special purpose vehicle by parent Company, and registered
under the provisions of the Companies Act, 1956 by its parent
company, viz, Atlanta Ltd. Consequent upon the short listing
of the parent Company, and creation of Mora Tollways
Company Limited, as special purpose vehicle for the said
purpose, a Concession Agreement was entered into between
the Corporation and the company, on 10.09.2011.
5. It is mystery why the Concession Agreement has
been described as between "the Governor of State of Bihar,
represented by its Managing Director, Bihar State Road
Development Corporation Limited through its Managing
Director, Central Mechanical Workshop Campus, Sheikhpura,
Patna", when the agreement appears to be between the
Corporation and the Company. I have not gone into
consequence of such recital in the agreement, in view of the
nature of dispute involved, as is being discussed hereinabove.
6. The Company, before entering into the
agreement had made demands for grant of mining lease for
stone quarries as according to it, the bid had been submitted Patna High Court LPA No.2158 of 2015 dt.12-05-2016
7/208
keeping in mind the facilities that were available of mining of
aggregates from stones quarries in possession of the
Government of Bihar. The bid period was extended from time
to time on four occasions. Finally, the Company entered into a
Concession Agreement on 10.09.2011. It is the case of the
Company that the bids submitted by it was conditional, subject
to making facilities for mining of aggregates from nearby
quarries in possession of the Government of Bihar.
Alternatively, according to them, procuring aggregates from
the neighbouring states would have incurred additional
expenditure and, therefore, necessitated reimbursement of
extra lead of aggregates, entry tax, toll tax etc, which would
need to be reimbursed by the Corporation.
7. The fact remains that there was no such
stipulation in the Concession Agreement entered into on
10.09.2011
. This is also not in dispute that at the time of
entering into agreement, mining of stone quarries in the State
of Bihar was impermissible.
8. The Corporation, through its Managing Director,
made request to the Collector, Rohtas to take necessary action
for relaxation of the rules in special cases in terms of Mines &
Mineral (Development & Regulation) Act, 1957. Since no
decision, to allow mining in the State of Bihar was taken by the
State Government of Bihar, the matter was referred to an Patna High Court LPA No.2158 of 2015 dt.12-05-2016
8/208
independent engineers engaged by the Corporation. The
independent engineers, after obtaining legal opinion
recommended either for allotment of mines or for the
reimbursement of the additional costs of procuring aggregates
from neighbouring State, estimated at Rs. 410.13/- crores, to
the Company.
9. The Corporation, however, rejected the claim of
the Company for reimbursement of the additional cost to be
incurred on procurement of aggregates from neighbouring
States through letter, dated 16.06.2014, there being no
provisions for extra lead of aggregates in the Concession
Agreement. This is evident from the minutes of the meeting
held on 05.08.2014. This made the Company to take recourse
to the provisions of Article 37.2 of the Concession Agreement
with the issuance of a notice, dated 09.08.2014, for curing the
defaults by the respondent authority within a period of 90 days
as contemplated thereunder.
10. Since Article 37.2 of the Concession
Agreement is at the core of the dispute between the parties,
the same is being extracted hereinbelow as the said Article will
be required to be discussed at subsequent stages also:-
"37.2. Termination for Authority Default 37.2.1 In the event that any of the defaults specified below shall have occurred, and the Authority fails to cure Patna High Court LPA No.2158 of 2015 dt.12-05-2016
9/208
such default within a Cure Period of 90 (ninety) days or such longer period as has been expressly provided in this Agreement, the Authority shall be deemed to be in default of this Agreement (the "Authority Default") unless the default has occurred as a result of any breach of this Agreement by the Concessionaire or due to Force Majeure.. the defaults referred to herein shall include:
(a) The Authority commits a material default in complying with any of the provisions of this Agreement and such default has a Material Adverse Effect on the Concessionaire;
(b) the Authority has failed to make any payment to the Concessionaire within the period specified in this Agreement; (c) the Authority repudiates this Agreement or otherwise takes any action
that amounts to or manifests an irrevocable intention not to be bound by this Agreement; or
(d) the State commits a material default in complying with the provisions of the State Support Agreement if such default has a Material Adverse Effect on the Concessionaire and the breach continues for a period of 90 (ninety) days from the date of notice given in this behalf by the Concessionaire to the Authority."
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
10/208
11. It can be noted here that Article 37 of the
Concession Agreement under which Article 37.2 falls deals with
the termination of the agreement. Article 37.1 deals with
termination for Concessionaire (in the present case for
Corporation) default and Article 37.2 deals with termination for
authority (in the present case for Corporation) default. Article
37.3.2 provides the consequence of termination on account of
an authority default, and stipulates that the authority shall pay
to the Concessionaire, by way of termination payment, an
amount equal to:
(a.) Debt Due; and (b.) 150% of the Adjusted Equity.
12. Adjusted equity as defined in Article 48.1 of the
Concession Agreement means "equity funded in Indian rupees
and adjusted on the first day of current month ( the
"Reference Date"), in the manner set forth, to reflect the
change in its value on account of depreciation and variations in
WPI, and for any Reference Date as mentioned therein.
13. A team of independent engineers was
appointed by the Corporation which, after examining the issue
of additional cost of procurement of aggregates held in report,
dated 09.09.2014 that the Corporation may take a decision for
reimbursement of cost of excess lead of aggregates in public
interest and for avoiding delay in the completion of the project, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
11/208
as according to them, the reimbursement would involve less
financial implication to the Government exchequer as
compared with the other two options, namely, the Termination
Cost payable to the petitioner and Re-tendering cost. After
having received the notice under Article 37.2 of the Concession
Agreement, a meeting appears to have taken place, on
06.11.2014, participated by the officials of the Corporation
including Chief General Manager, Chairman-cum-Managing
Director of the Company and Team Leader of the independent
Engineers (M/s ICT). From serial No. (b) of the minutes of the
said meeting, it appears that the representative of the
Company took a stand that notice under Article 37.2 of the
Concession Agreement was not a termination notice, rather, it
was notice to the authority to cure all the issues having
material adverse effect on the project within 90 days. The
Corporation took a plea that the issues raised in the said notice
under Article 37.2 shall be cured.
14. As the issue relating to reimbursement of
additional cost of aggregates could not be resolved, the
Company, considering it to be failure on the part of the
respondents to cure the defaults, issued a notice of intent to
terminate the Concession Agreement in terms of Article 37.2.2
of the agreement. The Corporation, thereafter, vide its letter,
dated 07.02.2015, asked the Company to submit the details of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
12/208
all the materials, stores, plant machinery and equipments
available at site for the purpose of Article 37.4(b) of the
Concession Agreement. Article 37.4 of the Agreement
provides for rights and obligations of the Corporation upon
termination of agreement for any reason whatsoever which
includes the authority to "take possession and controls of all
materials, stores, implements, construction plants and
equipments or about the site" Article 37.4 (a) of the
Concession Agreement describes upon termination or any
reason whatsoever, the Authority shall "be deemed to have
taken possession and control of the project Highway
forthwith".
15. The Company finally invoked the provisions of
Article 37.2.2 by issuing a termination notice by letter, dated
20.02.2015, and thus, terminated the Concession agreement,
dated 10.09.2011. The Company demanded termination
payment of an amount of Rs. 610,52,72,733/- from the
Corporation in terms of Article 37.3.2 of the Concession
Agreement.
16. Before I proceed further, with reference to the
facts which have been taken note of, by learned single Judge,
in the order under appeal, I consider it appropriate to refer to
a communication, dated 16.02.2015, which was issued within
15 days from the date of issuance of notice under Article Patna High Court LPA No.2158 of 2015 dt.12-05-2016
13/208
37.2.2 of the Concession Agreement, in response to the letter,
dated 04.02.2015, issued by the Company of terminating the
concession agreement by invoking Article 37.2.2. There is a
clear provision in Article 37.2.2 for granting 15 days time to
inform the authority (in the present case the Corporation) to
make representation before issuance of final termination
notice, and only after expiry of 15 days, whether or not the
Company is in receipt of such representation, the Company
could issue termination notice. The said representation of the
Corporation is there on record by way of Annexure-16 of the
writ application. I will be referring to the contents of the said
letter, dated 16.02.2016, at subsequent stage, while dealing
with the question as to whether any dispute in fact
exists/existed between the Corporation and the Company or
not OR every fact having been admitted by the Corporation,
this Court exercising writ jurisdiction under Article 226 of the
Constitution of India can/could issue a direction for payment of
money against compensation on Corporation‟s default leading
to termination of Concession Agreement.
17. Thereafter, the Corporation recommended the
case of the Company to Intra Structure Development Authority
for obtaining approval of the Committee presided over by the
Secretary for extra demand of carriage of stone aggregates to
the Company. It was mentioned in the said letter that though Patna High Court LPA No.2158 of 2015 dt.12-05-2016
14/208
the Company had terminated the Concession Agreement, the
said termination was not acceptable to the Corporation and the
Company had been requested to resume the work.
18. The Company thereafter, approached this Court
by filing writ application on 29.04.2015 (registered on
07.05.2015). Thereafter, the Corporation issued a notice on
16.05.2015, invoking Article 37.1.2 of the Concession
Agreement which enables the Corporation to terminate the
agreement upon occurrence of a Concessionaire (Company)
default. The said letter was a notice of intent to terminate the
Concession Agreement giving the Company. In terms of the
said Article of the agreement, the agreement could be
terminated after 15 days. I have noticed the similar provision,
which is there for termination of the agreement by the
concessionaire on the authorities default. Finally, through
letter, dated 10.06.2015, after lapse of 15 days, the
Corporation issued a letter terminating the Concession
Agreement.
19. The two letters, dated 16.5.2015, and
10.06.2015, were put to challenge in the writ proceedings by
seeking amendment through I. A. Nos. 4607 of 2015 and 4702
of 2015 which were allowed and treated to be the part of the
writ petition, by learned single Judge. A preliminary objection
was taken on behalf of the Corporation and the State of Bihar Patna High Court LPA No.2158 of 2015 dt.12-05-2016
15/208
over the maintainability of the writ application on the ground of
availability of alternative remedy of arbitration as
contemplated under Article 44 of the Concession Agreement.
Relevant potion of Article 44 is being extracted hereinbelow
since the same will be required to be referred at subsequent
stages and are apposite for the present also:-
"44.1 Dispute resolution 44.1.1. Any dispute, difference or controversy whatever nature howsoever arising under or out of or in relation to this Agreement (including its interpretation) between the parties, and so notified in writing by either party to the other party (the "Dispute") shall, in the first instance, be attempted to be resolve amicable in accordance with the conciliation procedure set forth in Article 44.2.
44.1.2. The parties agree to use their best efforts for resolving all Disputes arising under or in respect of this Agreement promptly, equitably and in good faith, and further agree to provide each other with reasonable access during normal business hours to all non-privileged records, information and data pertaining to any Dispute.
44.2 Conciliation In the event of any Dispute between the Parties, either party may call upon the Independent Engineer to mediate and assist the Parties in arriving at an amicable Patna High Court LPA No.2158 of 2015 dt.12-05-2016
16/208
settlement thereof. Failing mediation by the Independent Engineer, or without the intervention of the Independent Engineer, either Party may require such Dispute to be referred to the Chairman of the Authority and the Chairman of the Board of Directors of the Concessionaire for amicable settlement, and upon such reference, the said persons shall meet no later than 7 (seven) days from the date of reference to discuss and attempt to amicably resolve the Dispute. If such meeting does not take place within the 7 (seven) day period or the Dispute is not amicably settled within 15 (fifteen) days of the meeting or the Dispute is not resolved as evidenced by the signing of written terms of settlement within 30 (thirty) days of the notice in writing referred to in Article 44.1.1 or such longer period as may be mutually agreed by the parties, either Party may refer the Dispute to arbitration in accordance with the provisions of Article 44.3.
44.3 Arbitration Any dispute which is not resolved amicably by conciliation, as provided in Article 44.2, shall be finally decided by reference to Bihar Arbitral Tribunal in accordance with Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008, Rules framed thereunder or procedure prescribed by the Bihar Arbitral Tribunal. The award of Bihar Arbitral Patna High Court LPA No.2158 of 2015 dt.12-05-2016
17/208
Tribunal shall be final and binding on the parties.
44.4 Adjudication by Regulatory Authority or Commission.
Deleted."
20. The objection was opposed on behalf of the
Company before the writ Court on the ground that foundational
facts were not is dispute. I find from the judgment and order
under appeal that specific stand was taken on behalf of the
Corporation that the Corporation cannot treat the Companies‟
termination notice as illegal and refuse to accept it as this will
amount to sitting in judgment in their own case, they
themselves being a party to the contract. A plea was also
taken on behalf of the Company that action of the Corporation
ignoring termination notice issued by the Company, dated
20.02.2015, and instead issuing termination notice, dated
10.06.2015, much after filing of the writ petition was illegal
and arbitrary.
21. The learned single Judge turned down the
preliminary objection over maintainability of the writ
application and recorded in paragraph 12 as follows:-
"12. On the merits of the present case, this Court finds no error in the action of the petitioner in issuing the Termination Notice, and the Respondent‟s contention that the petitioner ought to have first opted for arbitration cannot be accepted. The Patna High Court LPA No.2158 of 2015 dt.12-05-2016
18/208
request for aggregates or for reimbursement of cost of procurement thereof remained a claim of the petitioner, and it was only after the Termination notice was given to the Respondents that a dispute within the meaning of Article 44 of the Agreement can be said to have arisen.
In other words, the core dispute between the parties relates not to the issue of aggregates, but is concerned with the validity of the Termination Notice, dated 20.02.2015 in accordance with Article 37.2.2 of the Agreement. Moreover, the fact that the petitioner had terminated the Agreement by its Termination Notice cannot be disputed. Once the Agreement had been terminated by the petitioner, the question of the Respondents terminating it over again could not arise as that would amount to termination of an already terminated agreement. The Respondents could only have sought remedy against such termination as may have been available to it. The respondent-Corporation on its part could not negate such notice by unilaterally treating the same as illegal. As held in M/s J. G. Engineer Pvt. Limited Vs. Union of India and Another (AIR 2011 (SC) 2477) as also in para 16 in M/s NCC Limited Vs. The State of Bihar (2013(1) PLJR 952), if the State is a party to the contract, it cannot decide whether there was a breach of contract by the other party. The remedy Patna High Court LPA No.2158 of 2015 dt.12-05-2016
19/208
available to it had to be found within the terms of the agreement itself to which it was a party. If at all, therefore, the respondents might have taken recourse to Article 44 of the agreement for dispute resolution, including arbitration. Failing to do so and instead sitting in judgment to unilaterally dub the petitioner‟s Termination Notice as illegal must be as held to constitute arbitrary action on the part of the respondent-Corporation and it can safely be concluded that the respondent-Corporation has acted de hors the terms of the contract between the parties. It would further appear that the respondents‟ own Termination Notice, dated 10.06.2015 has been issued after filing of the writ petition by the petitioner, possible for the purpose of avoiding the consequences of having to make the Termination payment to the petitioner as a fallout of the Termination Notice issued by the petitioner for authority default.
22. Upon reading of paragraph 12 of the judgment
under appeal, I find that the learned single Judge concluded
that there was no error in the action of the petitioners in
issuing termination notice. Learned single Judge has held that
once the agreement has been terminated by the Company,
question of the respondents terminating it again could not
have arisen and would amount to termination of already Patna High Court LPA No.2158 of 2015 dt.12-05-2016
20/208
terminated agreement. Learned single Judge also concluded
that the Corporation could only have sought remedy against
such termination as it might have available to it but it could
not, on its own part, negate such notice by unilaterally treating
the same as illegal. Such remedy, according to the learned
single Judge, was available within the terms of the agreement
itself to which the Corporation was a party and the Corporation
could have taken recourse to Article 44 of the Agreement of
disputes of resolution, including arbitration.
23. Learned single Judge accordingly, quashed the
termination notice issued by the Corporation, dated
10.06.2015, which according to the learned single Judge was
issued, possibly for the purpose of avoiding the consequence of
termination of agreement for Corporation‟s default by the
Company in terms of Article 37.3.2 (supra), of the Concession
Agreement.
24. Learned Single Judge accordingly, quashed the
Corporation‟s termination notice, dated 10.06.2015, with a
liberty to the Corporation to take recourse to Article 44 of the
Concession Agreement. As regards quantification of
compensation under Article 37.3.1 of the Concession
Agreement, consequent upon termination for the authority
default the learned single Judge held that such exercise would
necessarily require detailed investigation into the facts and Patna High Court LPA No.2158 of 2015 dt.12-05-2016
21/208
adduction of evidence. Learned single Judge also observed
that Article 44 of the Concession Agreement contains adequate
provisions of dispute resolution which the Corporation are at
liberty to advert to, if they were aggrieved by the termination
notice, dated 20.02.2015.
25. The Company in the present appeals is
aggrieved by the decision/conclusion of learned Single Judge
as contained in paragraphs 13 and 14 of the order under
appeal, which reads thus:-
"13. As regards the quantification of consequent Termination Payment liable to be paid by the respondents with regard to the nature and extent of authority default in terms of Article 37.2.2 of the agreement, the same would necessarily require detailed investigation into facts and adduction of evidence, into the details of which this Court need not travel. There is ample provision for Dispute Resolution detailed in Article 44 of the Concession Agreement referred to above, which the respondents are at liberty to advert to if they be aggrieved by the Termination Notice, dated 20.02.2015 issued by the petitioner.
14. In the result, the respondent-
Corporation‟s Termination Notice as contained in letter No. 1382, dated 10.06.2015 (Annexure-23) is hereby set aside with liberty to the respondents to take recourse to Article 44 of the
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
22/208
Concession Agreement dated 10.09.2011, if so advised. Needless to say, the petitioner shall cooperate in all such proceedings for resolution of the issues in dispute in accordance with law. The writ petition stands disposed of."
26. It is evident from paragraphs 13 and 14 that
learned single Judge has allowed the Corporation to take
recourse to the arbitration Article as contained in Article 44 of
the Concession Agreement, if they had any grievance against
the termination notice, dated 20.02.2015, issued by the
Company. Learned single Judge further held that
quantification of amount consequent upon termination of
Concession Agreement for Authority‟s default required
detailed investigation, and therefore, he refused to go into the
questions of fact which would have essentially required
detailed investigation and adduction of evidence.
27. On the other hand, the Corporation and State
of Bihar have filed the appeals aggrieved by the decision of
the learned single Judge setting aside the termination notice,
dated 10.06.2015, and holding the writ application to be
maintainable, there being arbitration Article in the Concession
Agreement for the resolution of the disputes between the
parties to the agreement.
28. From the memo of Appeal and the arguments Patna High Court LPA No.2158 of 2015 dt.12-05-2016
23/208
advanced by Mr. Y.V. Giri, learned Senior Counsel, appearing
on behalf of the Company, it is easily discernible that it is
Company‟s stand that learned single Judge ought not to have
given liberty to the Corporation to raise plea against
termination notice, dated 20.02.2015, by invoking Article 44
of the Concession Agreement, which provides for conciliation,
arbitration and methods for resolution of dispute since,
according Mr. Giri, learned Senior Counsel, default on the part
of the Corporation, leading to issuance of the letter of intent
of termination of agreement and final termination notice were
an admitted facts. According to him, validity of termination
notice, issued by the Company, dated 20.02.2015, could not
be called in question. It is his further case that as regards the
quantification of consequent termination payment, the same
had already been quantified by the team leader of
independent engineers, as contained in Annexure-34 of the
writ application, (being part of second supplementary
affidavit), wherein Intercontinental Consultants and
Technocrats Pvt. Limited‟s., letter, dated 09.09.2014,
addressed to the General Manager (PPP), Bihar State Road
Development Corporation Limited, have made detailed
conclusion regarding financial implication and reimbursement
of cost along with tentative cost implication for re-tendering.
29. It is evident from the grounds taken in the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
24/208
memo of Appeal that judgment and order of learned single
Judge on question of quantification of the amount liable to be
paid consequent upon termination for authorities default, is
being assailed on the following sole ground:-
"(iv) For that the Hon‟ble Single Judge has failed to appreciate that the quantification of the consequent termination payment liable to be paid by the respondents have already been quantified by the team leader of independent engineers as contained in
Annexure 34 of the writ application (being the part of second supplementary affidavit), wherein the Intercontinental Consultants and Technocrats Private Limited vide letter dated 09.09.2014 addressed to the General Manager (PPP), Bihar State Road Development Corporation Limited, wherein they have made detailed conclusion regarding financial implication reimbursement of cost of excess lead along with tentative cost implication for re-
tendering."
30. I will first deal with the pleadings on record
and submissions advanced on behalf of the Company as to
whether direction for payment of Rs. 610,52,72,733/- as
sought for in the writ application could be made in exercise of
writ jurisdiction of this Court, under Article 226 of the
Constitution of India, on the ground that there was no dispute Patna High Court LPA No.2158 of 2015 dt.12-05-2016
25/208
at all between the parties over the said amount and the said
amount was admittedly payable to the Company. As has been
noted, for seeking such direction, heavy reliance has been
placed on Annexure-34 of the second supplementary affidavit
filed on behalf of the Company in the writ proceeding. From
the said Annexure-34, dated 09.09.2014, it appears that
Intercontinental Consultants and Technocrats Pvt. Ltd. has
been engaged as independent engineers for Four Laning of
concerned Mohania-Ara Section of NH-30. Paragraph 7 of the
said report, dated 09.09.2014, contains the
comment/opinion on termination of agreement, concluding as
follows:-
"The tentative amount on account of termination works out to about Rs.
602.00 crores, subject to verification of actual expenditure incurred on permanent works by the Concessionaire."
31. I find from the said report that independent
engineers were giving his opinion for the purpose of exploring
possibilities of alternative solutions, in view of the dispute
which had emerged between the Company and the
Corporation in relation to execution and fulfilling the obligation
of the Concession Agreement. The said observation of the ICT
independent engineers as quoted above, can by no stretch of
imagination be treated to be an admitted amount or otherwise Patna High Court LPA No.2158 of 2015 dt.12-05-2016
26/208
an amount so determined, that would have bound the
Corporation to make payment. Evidently, the said conclusion
is subject to verification of actual expenditure incurred on
permanent works by the Concessionaire. This Court in my
considered view cannot hold, on the basis of the materials on
record that the said amount is admittedly payable to the
Company.
32. This Court‟s attention has been drawn to a
legal opinion, dated 31.10.2014, recorded by Mr. Lalit
Kishore, learned Senior Advocate of this Court and Principal
Additional Advocate General, as sought for by the
Corporation. Much emphasis has been laid on the said opinion
of Mr. Lalit Kishore, learned Senior Advocate by Mr. Y. V. Giri,
learned Senior Counsel to contend that the quantification of
consequent termination payment amount of Rs. 602.00 crores
was endorsed by learned Senior Advocate, Mr. Lalit Kishore.
33. Before adverting to the contents of the said
legal opinion, I record my strong displeasure over the conduct
of the appellant in bringing on record legal opinion, which is
essentially a confidentially communication between learned
Senior Counsel and the Corporation. It is not evident from
the pleadings on record as to how the Company procured a
copy of the said legal opinion. The conduct of the Company in
this regard is highly reprehensible. It would be apt to refer to Patna High Court LPA No.2158 of 2015 dt.12-05-2016
27/208
the Supreme Court decision in the case of R. C. Jain v. High
Court of Patna, reported in (1996) 10 SCC 5, in paragraph
11 whereof, the Apex Court has ruled thus:
"11. Along with the SLP, the appellant has filed a copy of the office note submitted by the Registrar (Inspection) dated 4-4-1996 before the learned Chief Justice for consideration of the Chief Justice. In the affidavit of urgency (available at pp. 52 to 55) filed by Shri Rajendra Kumar Jain, son of the appellant, the said office note (available at pp. 54 and 55 of the paper-book), has been reproduced. We questioned counsel for the appellant as to how the appellant was able to produce a copy of the office note dated 4-4-1996. The appellant having produced the said document, a duty is cast on him to explain the source from which he obtained the said copy and in what circumstances he could obtain the same. This is all the more so, since reference has been made in the affidavit of urgency dated 14-6-1996 to the said document. Counsel for the appellant declined to disclose the source from where he obtained a copy of the said document. On the other hand, he vehemently stated that this Court should call upon the Registrar of the Patna High Court to explain and it is no part of his duty to explain as to how he obtained a copy of the document. To say the least, we are surprised at the attitude of the appellant's counsel in totally refusing to disclose the source from which the appellant obtained a copy of the document. In our opinion, the appellant and his counsel owe a duty to this Court to Patna High Court LPA No.2158 of 2015 dt.12-05-2016
28/208
disclose the source or circumstances under which the said document dated 4-4-1996 was obtained. We express our strong displeasure at the attitude of the appellant and his counsel in totally refusing to disclose to the Court the manner in which a document filed in court was obtained. For the present, we do not want to say anything further in this matter, but we want to make it clear that the attitude adopted is totally reprehensible and cannot be countenanced by a court of law."
34. Further, there is nothing in the said legal
opinion of learned Senior Counsel, Mr. Lalit Kishore, to show
that in his opinion that the Company was liable for making
such payment. It contains mere reference of a fact that the
independent engineers have pointed out that in case of
termination of the contract, the concessionaire would be
entitled to payment for 602.00 crores.
35. In my view, the question whether a dispute
exists for payment of amount will arise only after an amount
has been computed explicitly, by either of the parties to an
agreement. The entire case of the Company is based on the
said opinion of the independent engineers. Further, there is
nothing on record to show that there was any agreement
between the parties the amount as might be determined by
the independent engineers shall be liable to be paid by the
parties concerned, without raising any dispute. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
29/208
36. I am, therefore, of the considered view that
this Court, in the present facts and circumstances of the case
cannot issue a direction for payment of amount as claimed by
the Company in his writ application. Learned single Judge has
rightly held that quantification of the amount would require
detailed investigation and adduction of evidence. I do not find
any valid reason to interfere with the said order of the learned
single Judge.
37. Of course, the question of consequent
termination payment, as envisaged under Article 37.1.3 of the
Concession Agreement, would arise only if termination of the
agreement for authority default is held to be justified. Such
termination can be held to be justified, if the other side, i.e.,
the Corporation, in the present case, does not raise any
dispute against such termination and specifically accepts that
there has been default on its part. Can this Court, in a
proceeding under Article 226 of the Constitution of India,
conclusively hold, on the basis of affidavits, that the
termination notice, dated 20.02.2015, issued by the
Company, is beyond the scope of being questioned by the
Corporation or any dispute, arising out of the said notice, is
beyond the scope of arbitration Article on the ground that
default, on the part of the Corporation, is an admitted fact, is
question, which is to be kept in mind while adjudicating the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
30/208
present matter.
38. Provision for reimbursement of additional cost
of procuring aggregates from neighbouring States, in the
absence of grant of mining lease, within the State of Bihar,
was one of the main issues being consistently raised by the
Company. It is to be noted that the issue was raised by the
Company, in view of the ban on crushing of stones in the
State of Bihar. This was never a part of the agreement that
the mining lease shall be granted to the Company for
execution of the work. Article 12.1(d) of the Concession
Agreement provides thus:-
"Prior to commencement of construction works, the Concessionaire shall make its own arrangements for quarrying of materials needed for the Project Highway under and in accordance with the Applicable Laws and Applicable Permits." (Emphasis is mine)
39. The case of the Company is based on its plea
that his bid was conditional and subject to making provision for
extra leads for procuring aggregates from the neighbouring
States. It is their case that in the review meeting, held on
25.09.2013, where this issue had been raised, the General
Manager of the Corporation had given a signal to go ahead
with the installation of crushers and procurement of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
31/208
aggregates from the neighbouring States.
40. There is a letter, dated 26.09.2013, which has
been brought on the record by way of Annexure-2 to the writ
petition, written by the authorized signatory of the Company,
which is said to be containing the minutes of the review
meeting, held on 25.09.2013.
41. I have perused Annexure-2 of the writ petition
carefully, paragraph No.2 of which refers to allotment of
mines, which is being extracted hereinbelow:-
"Allotment of Mines: Shri Vijay Shankar, GM informed that the Government has not taken a decision to allow mining in the State of Bihar and as such, the Concessionaire has to submitted that the allotment of mines at Sasaram is a precondition before signing the Concession Agreement. The procurement of the aggregate from neighbouring States has got material financial impact of more than Rs. 400 Cr. These has been vetted by the independent Engineer vide their letter No. ICT/IE/BSRDC/IND/NH-30/TL/416 dated 31.05.2013. Procuring aggregate from neighbouring States will necessitate reimbursement of extra lead charges, Entry Tax, Toll Tax etc. as brought out in the earlier correspondence. It is imperative to note that no tangible progress can be achieved without mining and crushing, even if Appointed Date is fixed.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
32/208
Shri Vijay Shankar, GM wanted to know the view of Shri A.D. Nariain, Independent Engineer on this issue. Shri A.D. Narain stated that ICT have already obtained legal opinion and have also recommended reimbursement of additional cost vide their letter dated 31.05.2013. He further stated that even otherwise, the Concessionaire is entitled for reimbursement of additional cost on account of subsequent legislation.
In view of above, Shri Vijay Shankar, GM requested the Concessionaire to go ahead with installation of crusher and procurement of aggregates from the neighbouring States. Shri Vijay Shankar, GM requested the DGM (CPIU) Shri R.P. Singh and Shri Mahesh Prasad, DGM (PPP) to initiate a note to the Government appraising financial implication."
42. I have my reservations as to whether the said
communication can be said to be containing minutes of the
meeting held on 25.09.2013.
43. This is to be noted that the case of the Company
that it was given a nod to the General Manager of the
Corporation to go ahead, with the installation of crushers and
procurement of aggregates, is based on the said
communication, dated 26.09.2013. Though, there is denial in
the counter affidavit that there was any such assurance by the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
33/208
General Manager of the Corporation in a meeting held on
25.09.2013, it has been averred in the counter affidavit, filed
on behalf of the Corporation, that proceedings of the meeting,
as represented by the Company, cannot, under any
circumstance, alter specific intent of the Concession
Agreement, which clearly specified that exclusive responsibility
of procuring input material was that of the Company. The
minutes of the said meeting have not been brought on the
record. What has been described in the said letter, dated
26.09.2013, to be the minutes of the meeting, cannot be said
to be so, as it does not bear the signature of the persons, who
had participated in the said meeting. The said document, in
my view, cannot lay the basis for coming to a definite
conclusion that the Corporation had given any assurance of
making provisions for reimbursement of additional cost to be
incurred on account of procurement of aggregates from the
neighbouring States. At the maximum, this could be a dispute,
which could be raised before the forum, prescribed under the
agreement.
44. Upon perusal of the documents, which are
there on the record, I notice that the minutes of different
meetings, held in the office of the Corporation and attended by
the officials and representatives of the Company and
independent engineer, had been duly prepared and signed by Patna High Court LPA No.2158 of 2015 dt.12-05-2016
34/208
the persons present. There is no clue, as to why there is no
formal minute of the meeting, said to have been held on
25.09.2013, in which the Company was asked to go ahead, as
has been noted above.
45. From the minutes of the review meeting, held
on 12.05.2014, the Company again raised an issue of payment
of extra lead of aggregates. The description of the said
meeting, in relation to the concerned item, reads thus:-
"Payment of extra lead of aggregate: The Concessionaire raised the issue of payment of extra lead of aggregate. GM (PPP) reiterated that same is under process and it is a policy matter.
The decision shall be taken as per the rules based on CA."
46. Evidently thus, upon an issue having been
raised by the Company, it was made clear that the decision
shall be taken as per the rules based on CA (Concession
Agreement). It does not contain any assurance that the
decision shall be taken de hors to the terms of Concession
Agreement.
47. The dispute, on the question of termination of
Concession Agreement, is evident from the correspondence
made between the Corporation and the Company. On
04.02.2015, notice of intent to terminate the Concession
Agreement, in terms of Article 37.2.2 of the Concession Patna High Court LPA No.2158 of 2015 dt.12-05-2016
35/208
Agreement, was issued by the Company. Within 15 days of
the said notice, the Corporation, on 16.02.2015, responded to
the said notice, as contemplated under Article 37.2.2 of the
Concession Agreement. In the said communication, dated
16.02.2015, the Corporation dealt with all the points raised by
the Company for issuing the notice of intent of termination of
agreement. On the question of non-payment of additional cost
incurred by the Company for procurement of aggregates, it
was pointed out firstly that it was the responsibility of the
Company, in terms of Article 12.1(d) of the Concession
Agreement. Secondly, it was mentioned as follows:-
"From the above, it is inferred beyond doubt that you shall make all arrangements for procurement of aggregates or any other material needed for the Project Highway. Thus your alleged claim is contrary to the Concession Agreement and denied. Be that as it may, it is informed that the Govt. of Bihar has vide Notification no. 3085/M, Patna dated 11.08.2014 opened the mining lease for procurement of aggregates. The Govt. of Bihar has already allowed the procurement of aggregates in the month of August but you have not made any efforts for procurement of aggregates till now. In such background, your contention to claim additional cost from the BSRDCL is clearly manifests of your intention to wriggle out of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
36/208
the Concession Agreement. Concessionaire is advised to immediately start the execution of works which are virtually suspended/ abandoned by the Concessionaire. This is in fact an admission by the Concessionaire of its inability to comply with specific contractual obligations."
48. It was specifically mentioned in the said letter,
dated 16.02.2015, that the notice of intent of termination of
agreement was illegal and invalid. The Company was asked
to withdraw his notices, dated 09.08.2014 and 04.02.2015.
49. Upon perusal of the notice of intent to
terminate the Concession Agreement, dated 04.02.2015, and
representation, dated 16.02.2015, I find that there are
disputed questions of facts with respect to alleged default by
the Corporation, which could have given the Company a valid
right to invoke Article 44 of the Concession Agreement.
50. An argument has been advanced on behalf of
the Company that after issuance of notice, dated 04.02.2015,
the Corporation, through a letter, dated 07.02.2015, had
asked the Company to submit the details of all material,
stores, plants & machineries and equipments available at the
site of the Authority, pursuant to Article 37.4(b) of the
Concession Agreement and, accordingly, the Company waived
the right of representation, under Article 37.2.2 of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
37/208
Concession Agreement. The said contention is fit to be
rejected. Article 37.4 of the Concession Agreement provides
for the rights and obligations of the Authority upon
termination for any reason whatsoever.
51. Article 37.4 provides that upon termination,
the Corporation will be deemed to have been in possession
and control of the Project Highway forthwith. This is a
deeming Article and operates automatically once the
Concession Agreement stands terminated. Article 37.4(b)
further provides for taking possession and control of all
materials, stores, implements, construction plants and
equipments on or about the site. This provision contemplates
taking actual physical possession and control of the Articles,
as mentioned above. Issuance of letter, dated 07.02.2015,
does not amount to invoking Article 37.4(b) of the Concession
Agreement. Through said letter, the Corporation merely
sought for the information and details of all materials, stores,
construction plants and equipments on or above the site, so
that, if needed, possession of the same can be taken over. It
will, in no circumstance, amount to waiving right of
representation within 15 days of issuance of termination
notice, dated 04.02.2015. This is apparent from the fact that
within 15 days of the said notice, the Corporation filed its
representation, raising the dispute, through letter, dated Patna High Court LPA No.2158 of 2015 dt.12-05-2016
38/208
16.02.2015.
52. In such circumstance, it cannot be held that
there was no dispute between the parties on the question of
default on the part of the Corporation, leading to issuance of
termination notice, invoking Article 37.2.2 of the Concession
Agreement. It cannot be said, in the facts and circumstances
and on the basis of materials available on the record, that
there was no scope for the Corporation to raise any dispute
against termination of Concession Agreement since the facts
are not admitted. In my view, in the given facts and
circumstances of the case, the learned Single Judge rightly
gave the Corporation and the State of Bihar an opportunity to
question the validity of the termination notice, issued by the
Company.
53. Situated thus, in my considered view, it cannot
be held that there is no dispute required to be resolved,
invoking Article 44 of the Concession Agreement. The
definition of dispute is wide, as given in Article 44 of the
Concession Agreement, which can be seen from Article 44.1.1
of the Concession Agreement and it means "any dispute,
difference or controversy of whatever nature howsoever
arising under or out of or in relation to the agreement". For
quick reference, the said Article 44.1.1. of the Concession
Agreement is being extracted hereinbelow:-
"Any dispute, difference or Patna High Court LPA No.2158 of 2015 dt.12-05-2016
39/208
controversy of whatever nature howsoever arising under or out of or in relation to this Agreement (including its interpretation) between the Parties, and so notified in writing by either Party to the other Party (the "Dispute") shall, in the first instance, be attempted to be resolved amicably in accordance with the conciliation procedure set forth in Article 44.2."
54. In the present matter there exists
dispute/difference/controversy between the parties worth
being resolved, in accordance with Article 44 of the
Concession Agreement, through the process of conciliation or
arbitration, as the case may be. The learned Single Judge, in
the judgment and order, under appeal, has set aside the
termination notice, issued by the Corporation, on the ground
that the Company had already terminated the Concession
Agreement and it was not within the jurisdiction of the
Corporation to decide that termination of agreement by the
Company, alleging default of the Authority, was not valid. If
the Corporation had any grievance against the said
termination notice, issued by the Company, the same could
have been raised before the forum, prescribed under the
Agreement, and could not have been unilateral decision to
treat the termination notice of the Company to be not
acceptable. The said view, adopted by learned Single Judge, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
40/208
in my opinion, is appropriate in the present facts and
circumstances of the case.
55. The question of interference by the High Court
in exercise of power, under Article 226 of the Constitution of
India, in contractual matters, has been raised on umpteen
occasions and has been answered. This is settled now that a
settlement of facts, based on the contents of the affidavits, in
a proceeding under Article 226 of the Constitution of India, is
impermissible in dealing with the contractual disputes, though
there is no bar on the High Court. Reference in this regard
made to a recent Supreme Court decision, in case of State of
Kerala and Others vs. M.K. Jose, reported in (2015) 9
SCC 433, paragraph 13 of which reads as thus:-
"13. A writ court should ordinarily not entertain a writ petition, if there is a breach of contract involving disputed questions of fact. The present case clearly indicates that the factual disputes are involved."
56. The said decision, in case of State of Kerala
(supra) has been referred to in almost all Supreme Courts‟
decisions, on the issue, and the Supreme Court finally held in
paragraphs 20 and 21 of the judgment in following terms:-
"20. We have referred to the aforesaid authorities to highlight under what circumstances in respect of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
41/208
contractual claim or challenge to violation of contract can be entertained by a writ court. It depends upon facts of each case.
The issue that had arisen in ABL International was that an instrumentality of a State was placing a different construction on the Articles of the contract of insurance and the insured was interpreting the contract differently. The Court thought it apt merely because something is disputed by the insurer, it should not enter into the realm of disputed questions of fact. In fact, there was no disputed question of fact, but it required interpretation of the terms of the contract of insurance. Similarly, if the materials that come on record from which it is clearly evincible, the writ court may exercise the power of judicial review but, a pregnant one, in the case at hand, the High Court has appointed a Commission to collect the evidence, accepted the same without calling for objections from the respondent and quashed the order of termination of contract.
21. The procedure adopted by the High Court, if we permit ourselves to say so, is quite unknown to exercise of powers under Article 226 in a contractual matter. We can well appreciate a Committee being appointed in a public interest litigation to assist the Court or to find out certain facts. Such an exercise is meant for public good and in public interest. For example, when Patna High Court LPA No.2158 of 2015 dt.12-05-2016
42/208
an issue arises whether in a particular State there are toilets for school children and there is an assertion by the State that there are good toilets, definitely the Court can appoint a Committee to verify the same. It is because the lis is not adversarial in nature. The same principle cannot be taken recourse to in respect of a contractual controversy. It is also surpassing that the respondent, which is nothing but abuse of the process of extraordinary jurisdiction of the High Court. The Appellate Bench should have applied more restraint and proceeded in accordance with law instead of making a roving enquiry. Such a step is impermissible and by no stretch of imagination subserves any public interest."
57. There cannot be any doubt that mandamus is
not a writ of right and is not granted of course but at the
discretion of the Court to which an application seeking
issuance of mandamus is made. It is equally well settled that
a High Court exercising power under Article 226 of the
Constitution of India is to be slow in issuing a writ of
mandamus if the party concerned has an alternative remedy
available. Existence of an alternative remedy, though, is not
a bar for the High Court to exercise jurisdiction under Article
226 of the Constitution of India, the High Court may in its
discretion entertain claim of a party despite availability of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
43/208
alternative remedy, depending on facts and circumstances of
the case. At the same time, existence of an alternative
remedy is a good ground for refusing to exercise discretion
under Article 226 of the Constitution of India.
58. In case of State of Bihar. Vs. Jain Plastics
and Chemicals Limited reported in (2002)1 SCC 216, the
Supreme Court held in paragraph 3 as follows:-
"It is settled law that when an alternative and equally efficacious remedy is open to the litigant, he should be required to pursue that remedy and not invoke the writ jurisdiction of the High Court. Equally, the existence of alternative remedy does not affect the jurisdiction of the Court to issue writ, but ordinarily that would be a good ground in refusing to exercise the discretion under Article 226."
59. The Supreme Court further, held in the said case in
paragraph 7 that non-interference in contractual matter while
exercising jurisdiction under Article 226 of the Constitution of
India is the general rule and held as follows:-
"7..... It is true that many matters could be decided after referring to the contentions raised in the affidavits and counter affidavits, but that would hardly be a ground for exercise of extraordinary jurisdiction under Article Patna High Court LPA No.2158 of 2015 dt.12-05-2016
44/208
226 of the Constitution in case of alleged breach of contract. Whether the alleged non-supply of road permits by the appellants would justify breach of contract by the respondent would depend upon facts and evidence and is not required to be decided or dealt with in a writ petition. Such seriously disputed questions or rival claims of the parties with regard to breach of contract are to be investigated and determined on the basis of evidence which may be led by the parties in a properly instituted civil suit rather then by a court exercising prerogative of issuing writs."
60. In my opinion, therefore, in the facts and
circumstances of the case, it would not be safe to decide the
dispute between the parties on the basis of affidavits and
counter affidavits in the present proceeding of appeal under
the Letters Patent of the High Court more particularly when
learned single Judge by the order under appeal, has refused
to exercise discretion and has relegated the dispute to the
forum of arbitration as contemplated in the contract itself.
61. This is trite that in an intra Court appeal of the
present nature, the Court of appeal should not interfere with
the refusal by learned single Judge to exercise discretion
under Article 226 of the Constitution of India on the ground of
availability of an alternative remedy of arbitration. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
45/208
Entertainment of Letters Patent Appeal is discretionary and
unless there exist cogent reasons, the Division Bench would
not interfere with the reasonings assigned by the learned
single Judge.
62. Reference can be made in this regard to a
Supreme Court decision in case of Asha Devi Vs. Dukhi Sao
reported in ( 1974) 2) SCC 492.
63. I do not find that any cogent reason which
exists for interfering with the decision of the learned single
Judge.
64. A submission was advanced that once learned
single Judge has held the writ application to be maintainable,
he ought not to have relegated the appellant and the parties
to the forum of arbitration. According to Mr. Giri, learned
Senior Counsel appearing on behalf of the appellant, the
learned single Judge ought to have decided the dispute on the
basis of admitted facts and materials on record, after having
held the writ application to be maintainable. I do not find any
force in such submission. Maintainability of an application and
grant of relief sought for in the said application are two
different aspects. The writ petition filed by the Company
could not have been held to be not maintainable in the
absence of any bar against filing of such application. Existence
of an alternative remedy is not a bar in invoking writ Patna High Court LPA No.2158 of 2015 dt.12-05-2016
46/208
jurisdiction of the High Court under Article 226 of the
Constitution of India. Learned single Judge accordingly, held
writ application to be maintainable, despite there being
alternative remedy of arbitration. But while considering the
relief sought for, learned single Judge refused to decide the
question of quantum consequent termination payment as well
as justification of termination notice for authority‟s default
issued by the appellant-Company. Learned single Judge
rightly observed that the dispute as to whether the said notice
issued by the Company was valid or not could not have been
unilaterally decided by the Corporation which was itself a
party to the contract. Learned single Judge, therefore, rightly
held that the termination notice for concessionaire default by
the Corporation treating the termination notice for authorities
default as invalid, was not proper and the Corporation, for
that purpose could have invoked the arbitration Article under
Article 44 of the agreement. It is, however, made clear that
no observation made by learned single Judge in the order
under appeal shall be treated as finding, implied of explicit, on
correctness/validity or justifiability of the termination notices
issued by the Company.
65. In the background of the facts, as discussed
above, and settled legal position, I do not find any reason to
interfere with the judgment and order, under appeal, passed Patna High Court LPA No.2158 of 2015 dt.12-05-2016
47/208
by the learned single Judge. The appeal, preferred by the
Company, being L.P.A. No.2158 of 2015, has no merit and is,
accordingly, dismissed.
66. Since I have come to a conclusion that learned
single Judge has rightly quashed the termination notices,
issued by the Corporation, dated 16.05.2015 and 10.06.2015,
the appeals, preferred by the Corporation and the State of
Bihar, being L.P.A. No. 2084 of 2015 and L.P.A. No.2131 of
2015, have also no merit and are, accordingly, dismissed.
67. Before I part with this judgment, I reiterate my
observation that the conduct of the appellant of bringing on
record legal opinion tendered by a learned senior counsel of
this Court to the Corporation is highly reprehensible.
Considering the said conduct of the appellant, I am inclined to
impose exemplary cost on the appellant, so that it may have a
deterrent effect. Accordingly, I impose a cost of Rs.
5,00,000/- to be paid by the appellant to the Corporation
within a period of one month from today.
68. In terms of the above observations and
directions, these appeals shall stand disposed of.
(Chakradhari Sharan Singh, J.) Patna High Court LPA No.2158 of 2015 dt.12-05-2016
48/208
(Per : HONOURABLE THE ACTING CHIEF JUSTICE)
In Ramana Dayaram Shetty v. International
Airport Authority of India, (1979) 3 SCC 489, the Supreme
Court, while dealing with the diversification of State activities,
over the years, observed that today, with tremendous
expansion of welfare and social service functions, increasing
control of material and economic resources and large scale
assumption of industrial and commercial activities by the State,
the power of the executive Government to affect the lives of the
people is steadily growing. The attainment of socio-economic
justice being a conscious end of State policy, there is a vast and
inevitable increase in the frequency with which ordinary citizens
come into relationship of direct encounter with State power-
holders. This renders it necessary to structure and restrict the
power of the executive Government so as to prevent its
arbitrary application or exercise. Whatever be the concept of
the Rule of Law, whether it be the meaning given by Dicey in
his "The Law of the Constitution" or the definition given by
Hayek in his "Road to Serfdom" and "Constitution of Liberty" or
the exposition set forth by Harry Jones in his "The Rule of Law
and the Welfare State", there is, as pointed out by Mathew, J.,
in his article on "The Welfare State, Rule of Law and Natural
Justice" in "Democracy, Equality and Freedom" "substantial
agreement in juristic thought that the great purpose of the rule Patna High Court LPA No.2158 of 2015 dt.12-05-2016
49/208
of law notion is the protection of the individual against arbitrary
exercise of power, wherever it is found". It is indeed
unthinkable that in a democracy governed by the rule of
law the executive Government or any of its officers
should possess arbitrary power over the interests of the
individual. Every action of the executive Government
must be informed with reason and should be free from
arbitrariness. That is the very essence of the rule of law
and its bare minimal requirement. And to the application
of this principle it makes no difference whether the
exercise of the power involves affectation of some right
or denial of some privilege.
(Emphasis supplied)
70. The present batch of appeals raises issues of great
public importance, wherein the actions of the respondents, the
Instrumentalities of State Government of Bihar, have been
alleged to be arbitrary and unreasonable and, therefore, their
impugned actions are violative of Article 14 of the Constitution
of India.
71. The present appeals have been preferred, under
Clause 10 Appendix-E of the Patna High Court Rules, against
the judgment and order of a learned single Judge of this Court
in CWJC No. 7259 of 2015, whereby and whereunder the
learned single Judge has disposed of the writ petition with Patna High Court LPA No.2158 of 2015 dt.12-05-2016
50/208
certain directions and observations that have been put to
challenge by both the sides to the litigation.
72. Considering the fact that these appeals have been
filed against the same judgment and since common questions
of law arise herein, these appeals have been heard together
and are disposed of by this common judgment and order.
73. Before dealing with the rival submissions, made
on behalf of the parties, on the merits of these appeals, a brief
narration of the facts, leading to the appeals, would be
necessary.
Facts in LPA No. 2158 of 2015: -
74. The appellant, in LPA No. 2158 of 2015, filed, as
petitioner, a writ petition, giving rise to CWJC No. 7259/2015,
invoking Article 226 of Constitution of India praying therein for
certain reliefs, the principal, among them, being to issue a writ,
in the nature of mandamus, commanding the respondent
authorities to pay to the appellant company Termination
Payment amounting to Rs 610,52,72,733 (Rupees Six hundred
ten crores fifty two lacs seventy two thousand even hundred
thirty three only) with interest at contractual rate on the ground
that respondent authorities have acted illegally, arbitrarily and
without jurisdiction.
75. The writ petitioner is, admittedly, a Limited
Company registered under the Companies Act, 1956, having Patna High Court LPA No.2158 of 2015 dt.12-05-2016
51/208
been created as a special purpose vehicle by its parent
company, Atlanta Limited. It is further stated that pursuant to a
notice/request for qualification by the respondents, dated
16.7.2010, for the construction, operation and maintenance of
National Highway No. 30 in the State of Bihar, including the
section from 0.000 to km 116.760 on the Mohania-Ara section
of National Highway No. 30, by four laning on a Design, Build,
Finance, Operate and Transfer (DBFOT) basis, Atlanta Limited
was shortlisted and, in due course, a Concession Agreement
was entered into between the appellant company and the
Managing Director, Bihar State Road Transport Corporation,
Patna, on 10.09.2010.
76. After submission of its bid, the writ petitioner
made demands for a Mining lease for stone quarries to be made
available to it inasmuch as the bid had been submitted keeping
in mind the facilities of mining aggregates from enumerated
quarries in the possession of the Government of Bihar and it
was duly indicated that in the absence of the mining lease, it
would be practically impossible for it to execute the project. It
was only upon the expectation of grant of the Mining lease and
on the insistence of the respondents that the validity of the
original bid was extended by the writ petitioner from time to
time. After extension of the validity of the bid, on four
occasions, a Concession Agreement was finally entered into on Patna High Court LPA No.2158 of 2015 dt.12-05-2016
52/208
10.9.2011. On the other hand, the issue relating to provision of
aggregates, through mining leases, continued to be subject
matter of discussion. The matter was also referred to an
Independent Engineer, chosen and appointed by the
respondents, who recommended, by letter, dated 31.05.2013,
for either allotment of mines in favour of the writ petitioner or
for re-imbursement of additional cost of procuring aggregates
from neighbouring States estimated at Rs 410.13 crores to the
writ petitioner. However, in the meeting, dated 05.08.2014,
between the writ petitioner and the respondent authorities, it
was observed that the writ petitioner‟s claim, with regard to
extra lead aggregates, was not sustainable and this event led
the writ petitioner to serve a notice upon the respondent
authorities, in terms of Clause 37.2 of the Agreement, asking
the respondent authorities to cure the defaults within the
stipulated period of 90 days. Pursuant to the notice so served
under Clause 37.2 by the writ petitioner, the respondents, in a
meeting, dated 06.11.2014, agreed to cure the defaults and the
Chief General Manager of the respondent Corporation sent a
letter, dated 21.11.2014, addressed to the Principal Secretary,
Road Construction Department, Government of Bihar, seeking,
in principle, approval for payment of extra cost of carriage of
stone aggregates amounting to the tune of Rs. 435 crores to
the writ petitioner. Despite correspondences and meetings, the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
53/208
issue, relating to re-imbursement of cost of aggregates, could
not be resolved and considering this failure, on the part of the
respondents, to cure the defaults, the writ petitioner, on
04.02.2015, issued a notice of its intent to terminate the
Concession Agreement in terms of Clause 27.2.2 of the
Agreement. Acting upon such notice, the respondent
Corporation, vide letter, dated 07.02.2015, directed the writ
petitioner to submit details of all materials, etc., for the purpose
of Clause 37.4 (b). The respondents, according to the writ
petitioner, kept dilly dallying the matter in order to avoid their
liability compelling the appellant to issue termination notice,
dated 20.02.2015, thereby terminating the Concession
Agreement, dated 10.09.2011, and demanding termination
payment of an amount of Rs.610,52,72,733 with interest at
contractual rate.
77. Some further developments took place after the
termination notice was issued by the writ petitioner. The
respondent No.2, in his letter, dated 23.03.2015, recommended
the case of the writ petitioner to the Infrastructure
Development Authority for obtaining the approval of the
Committee presided over by the Secretary, Road Construction
Corporation, Government of Bihar, for payment of extra cost of
carriage of stone aggregates to the writ petitioner. It was also
observed therein that the writ petitioner had already terminated Patna High Court LPA No.2158 of 2015 dt.12-05-2016
54/208
the Concession Agreement, on 20.02.2015, in terms of Clause
37.2.2 of the Concession Agreement, which, however, had been
termed illegal and not accepted by the respondent Corporation
and, accordingly, the writ petitioner was requested to resume
the work. The writ petitioner, then, approached this Court by
filing the writ petition.
78. During the pendency of the writ petition, the
respondent Corporation issued a notice, on 16.05.2015,
purportedly in terms of Clause 37.1.2, for termination of the
agreement, which, later on, culminated into purported
termination of the Concession Agreement by the respondent
Corporation in terms of its letter No. 1382, dated 10.06.2015.
79. After the termination notice was issued by the
respondents, the writ petitioner filed I. A. No. 4702 of 2018 for
amendment of the prayer portion in the writ petition and
seeking quashment of the letter No. 1180, dated 16.05.2015,
as well as the letter No. 1382, dated 10.06.2015. Upon hearing
both sides, I. A. 4702 of 2018 was allowed.
80. The respondents contested the writ petition on the
ground of maintainability. It was argued that the subject-matter
of the writ petition was based on contractual obligations and,
hence, a writ would not lie.
81. Upon hearing the rival submissions, the learned
single Judge held, in the judgment, dated 22.09.2015, the writ Patna High Court LPA No.2158 of 2015 dt.12-05-2016
55/208
petition to be maintainable and this finding forms the subject of
LPA No. 2084 of 2015, filed by the respondent Corporation,
which is being dealt with hereinafter.
82. The writ petition was disposed of by judgment,
dated 22.09.2015, whereby the learned single Judge gave
liberty to the respondents to advert to provisions of Dispute
Resolution Agreement contained in Article 44 of the agreement
if the respondents were aggrieved by the termination notice
issued by the writ petitioner. The learned single Judge also set
aside the termination notice, dated 10.06.2015, issued by the
respondents, but granted liberty to them (respondents) to take
recourse to Article 44 of the Agreement.
83. The appellant (i.e., the writ petitioner) has also
challenged, in its appeal, some observations of the learned
single Judge, particularly, those contained in paragraph 13 and
paragraph 14 of the judgment, whereby the dispute has been
allowed to be referred to arbitration even though it was
specifically held by the learned single Judge that the
termination notice, issued by the appellant, was valid. It may
also be pointed out here that the learned single Judge has also
set aside the Termination Notice, dated 10.06.2015, issued by
the respondents holding the same to have been issued only for
the purpose of avoiding the consequences of having to make
termination payment to the writ petitioner herein. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
56/208
Facts in LPA No.2084 of 2015: -
84. LPA No. 2084 of 2015 has been preferred by the
respondent Bihar State Road Construction Corporation, who are
aggrieved by the decision of the learned single Judge negating
the plea, raised by them, that the subject matter of the dispute
is covered by Arbitration Clause as contained in Article 44 of the
Concession Agreement and, hence, no relief can be granted in
exercise of writ jurisdiction. The respondent Corporation has
also challenged the decision of learned single Judge in setting
aside their termination notice, dated 10.06.2015, as illegal and
holding that the termination notice, dated 10.06.2015, was
issued only with the intent to avoid the termination payment to
the writ petitioner.
Facts in LPA No. 2131 of 2015
85. LPA No. 2131 of 2015 has been preferred by the
respondent-State of Bihar, who, too, are aggrieved by the
judgment and order, under appeal, of the learned single Judge
and have sought to challenge the same on identical grounds as
has been sought to be raised by the respondent-Corporation.
86. I have heard the submissions advanced by Mr.
Y.V. Giri, learned Senior Counsel, appearing for the appellants
in LPA No. 2158 of 2015, and Mr. Lalit Kishore, learned Principal
Additional. Advocate General, appearing for the appellants in
LPA No. 2084 of 2015 and LPA No. 2131 of 2015.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
57/208
87. Before I proceed further, I may point out that in
order to maintain clarity, the parties to the three appeals are
being described hereinafter in the same manner as they stood
in the writ petition, which has given rise to the present set of
appeals. Consequently, „the writ petitioner‟ is being referred to
as „the writ petitioner‟, „the respondent Corporation‟ is being
referred to as „the respondent Corporation‟ and „the State
respondents‟ are being referred to as „the State respondents‟.
WHETHER THE WRIT PETITION WAS HEARD ONLY ON A
PRELIMINARY POINT: -
88. It has been argued by the learned Principal
Additional. Advocate General that in view of the Arbitration
Clause, the writ petition was heard only on the point of
maintainability of the writ petition. However, on perusal of the
judgment of the learned single Judge, I do not find any force in
the submissions of the learned Principal Additional Advocate
General as the learned single Judge has taken into account all
factors, including facts and documents, before arriving at the
conclusions, which were reached. Hence, the argument, on this
count needs to be rejected and is accordingly rejected.
MEANING OF THE EXPRESSION "DISPUTE" VIS-À-VIS
ARBITRATION CLAUSE: -
89. The learned Principal Additional Advocate General
invited the attention of this Court to Article 44 of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
58/208
Concession Agreement and argued that in view of the specific
clause in the Concession Agreement that all „disputes' will be
referred to arbitration, the exercise of writ jurisdiction was not
tenable.
90. In order to appreciate the above submissions,
Article 44 is being reproduced hereinbelow for reference:
"44.1 Dispute Resolution 44.1.1 Any dispute difference or controversy of whatsoever nature howsoever arising under or out of or in relation to this Agreement (including its interpretation) between the parties and so notified in writing by either Party to the other party shall in the first instances be attempted to be resolved amicably in accordance with the conciliation procedure set forth in Clause 44. 2.
44.1.2 The Parties agree to use their best efforts for resolving all Disputes arising under or in 'respect of this Agreement promptly, equitably and in good faith, and further agree to provide each other with reasonable access during normal business hours to all non-privileged records, information and data pertaining to any dispute.
44.2 Conciliation In the event of any Dispute between the Parties either party may call upon the Independent Engineer to mediate and assist the Parties in arriving at an amicable settlement thereof. Failing mediation by the Independent Engineer to without the intervention of the Independent Engineer either party may require such dispute to be referred to the Chairman of the Authority and the Chairman of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
59/208
Board of Directors of the Concessionaire for amicable settlement and upon such reference the said persons shall meet no later than 7 days from the date of reference to discuss and attempt to amicably resolve the dispute. If such meeting does not take place within the 7 days period or the Dispute is not amicably settled within 15 days of the meeting or the Dispute is not resolved as evidenced by the signing of written terms of the settlement within 30 days of the notice in writing referred to in Clause 44.1.1 or such longer period as maybe mutually agreed by the parties either party may refer the Dispute to arbitration in accordance with the provisions of Clause 44.3 44.3 Arbitration Any dispute which is not resolved amicably by conciliation as provided in Clause 44.2 shall be finally decided by reference to Bihar Arbitral Tribunal in accordance with Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008 Rules framed thereunder or procedure prescribed by the Bihar Arbitral Tribunal. The award of Bihar Arbitral tribunal shall be final and binding on the parties.
44.4. Adjudication by Regulatory Authority or Commission.
Deleted."
91. It is the submission of the learned Principal
Additional Advocate General that in view of Article 44 of the
Agreement, the only remedy available to the writ petitioner, for
redressal of its grievances, is to approach the Tribunal
constituted under the Bihar Public Works Contracts Disputes Patna High Court LPA No.2158 of 2015 dt.12-05-2016
60/208
Arbitration Tribunal Act, 2008.
92. In order to appreciate the submissions of the
learned Principal Additional Advocate General, it would be
necessary to advert to the relevant provisions of the Bihar
Public Works Contracts Disputes Arbitration Tribunal Act, 2008.
93. Section 2 of the Bihar Public Works Contracts
Disputes Arbitration Tribunal Act, 2008, deals with definitions
and Section 2(b) defines "Arbitration Clause" to mean a clause
in the works contract to submit present or future differences to
arbitration. Again, Section 2 (e) defines "Dispute" to mean any
difference relating to any claim arising out of the execution or
non-execution of the whole or part of a contract for works or
services or both including the act of rescinding the contract.
94. It would be seen from a reading of Section 2 (b)
and 2 (e) of the Bihar Public Works Contracts Disputes
Arbitration Tribunal Act, 2008, that the condition precedent, for
assumption of jurisdiction by the Arbitral Tribunal, is existence
of differences. Even though the expression "dispute" has been
defined in the Bihar Public Works Contracts Disputes Arbitration
Tribunal Act, 2008, yet the meaning of the "dispute" is
differences relating to any claim arising out of the execution or
non-execution of the whole or part of a contract for works or
services or both including the rescinding thereof.
95. In other words, no occasion would arise for the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
61/208
Arbitral Tribunal to adjudicate if no difference exists on an
issue. Hence, in the facts of this case, the matter could have
been decided by the Bihar Public Works Contracts Disputes
Arbitration Tribunal Act, 2008, only and only if the writ petition,
when read in its entirety, revealed that a difference existed
between the writ petitioner and the respondents over any claim
arising out of the execution or non-execution of the whole or
part of a contract for works or services or both including the act
of rescission thereof. Conversely, if the averments in the writ
petition, when read in its entirety, and the circumstances,
preceding the writ petition, show that there existed no
difference with respect to any issue or claim made by any party,
the condition precedent, for referring the matter to the Bihar
Public Works Contracts Disputes Arbitration Tribunal Act, 2008,
would not be treated to have been satisfied and, in such a case,
question of resorting to arbitration by the Bihar Public Works
Contracts Disputes Arbitration Tribunal Act, 2008, would
naturally not arise.
96. In the case of P.K. Ramaiah & Co. v. NTPC,
Supp (3)SCC 126, the Supreme Court had pointed out and
held that if there is an arbitrable dispute, it shall be referred to
the named arbitrator; but there must exist a subsisting dispute.
97. Similarly, therefore, if it has to be held that the
writ petition, in the present case, is amenable to arbitration, it Patna High Court LPA No.2158 of 2015 dt.12-05-2016
62/208
would not be possible to do so unless I am able to hold that
there was a dispute, which was real and subsisting and that the
plea of dispute has not been raised by the respondents merely
as a clog to resist the writ petition by camouflaging the issue.
98. In P.K. Ramaiah (supra), the Supreme Court
considered the ambit of accord and satisfaction by the parties,
voluntarily entered into and disputation raised thereunder. The
Supreme Court held as follows;
"8. Admittedly the full and final satisfaction was acknowledged by a receipt in writing and the amount was received unconditionally. Thus, there is accord and satisfaction by final settlement of the claims. The subsequent allegation of coercion is an afterthought and a device to get over the settlement of the dispute, acceptance of the payment and receipt voluntarily given.... Having acknowledged the settlement and also accepted measurements and having received the amount in full and final settlement of the claim, there is accord and satisfaction. There is no existing arbitrable dispute for reference to the arbitration."
99. A similar view was expressed in the case of
Nathani Steels Ltd. v. Associated Constructions, 1995
Supp (3) SCC 324, wherein the Supreme Court held that once
the parties have arrived at a settlement in respect of any
dispute or difference arising under a contract and that the
dispute or the difference is amicably settled by way of a final Patna High Court LPA No.2158 of 2015 dt.12-05-2016
63/208
settlement by and between the parties, then, unless that
settlement is set aside in proper proceedings, it cannot lie in the
mouth of one of the parties to the settlement to spurn it on the
ground that it was a mistake and proceed to invoke the
Arbitration clause. If this is permitted, the sanctity of contract
would be wholly lost and it would be open to one party to take
the benefit under the settlement and, then, question the same
on the ground of mistake without having the settlement set
aside.
100. The relevant paragraph of Nathani Steels
(supra), wherein the aforesaid observations were made, is
being reproduced as follows;
"3. ... Even otherwise we feel that once the parties have arrived at a settlement in respect of any dispute or difference arising under a contract and that dispute or the difference is amicably settled by way of a final settlement by and between the parties, unless that settlement is set aside in proper proceedings, it cannot lie in the mouth of one of the parties to the settlement to spurn it on the ground that it was a mistake and proceed to invoke the Arbitration clause. If this is permitted the sanctity of contract, the settlement also being a contract, would be wholly lost and it would be open to one party to take the benefit under the settlement and then to question the same on the ground of mistake without having the settlement set aside...."
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
64/208
101. Again, in the case of Ramesh Kumar v. Furze
Ram, reported in (2011) 8 SCC 613, the Supreme Court held
that there can be a reference to arbitration only if there is a
dispute and there is an agreement to settle the dispute by
arbitration. If the parties had already settled the disputes, there
was no dispute between the parties that could be referred to
arbitration. Is this the position in the present case too? This is
the question of paramount importance.
102. The analysis of the cases, referred to above,
clearly show that condition precedent for referring a dispute to
arbitration is the existence of differences on any claim. A
settlement of claim would mean that the difference has ceased
to exist and, hence, no question would arise for referral of the
difference to arbitration. In other words, arbitration, being an
adjudicatory process, must be preceded by an existing dispute,
which requires adjudication. In the absence of an issue, which
needs adjudication, question of arbitration would never arise.
103. Mustill and Boyd's The Law and Practice of
Commercial Arbitration in England, (1989 Ed), observes that a
"dispute" must be construed by reference to the subject matter
of the contract in which they are included. Thus, only by a
reference to facts of the case, it can be said whether dispute
exists or not.
104. It would be apposite to reflect herein on one of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
65/208
the arguments made by the learned Counsel for the writ
petitioner. It has been argued that the respondents have been
deliberately confusing the expression "default" with the
expression "dispute". According to the learned Counsel for the
writ petitioner, the expression "default" has been specifically
dealt with in Article 37 of the Concession Agreement and some
of the defaults, pointed out by the writ petitioner, to the
respondents, were never denied by the respondents and,
hence, those defaults never attained the shape of a dispute
within the meaning of Article 44 of the Agreement.
105. "Dispute", as has been discussed hereinbefore,
would mean, in simple expression, difference over an issue.
"Default, on the other hand, is something, which means
omission of that which a man ought to do. (Per Dhan Singh
Ramkrishna Chaudhari v. Laxminarayan Ramkishan,
reported in (1974) 2 SCC 293.
106. In order to appreciate the rival submission as to
whether a dispute existed between the writ petitioner and the
respondents, it would be necessary to traverse some aspects of
the Concession Agreement and the written correspondences.
107. Article 37 of the Concession Agreement deals
with the topic of Termination. It would appear that termination
of the Concession Agreement is possible from either ends, one
from the side of the Concessionaire and the other from the side Patna High Court LPA No.2158 of 2015 dt.12-05-2016
66/208
of the Authority.
108. Clause 37.1 deals with Concessionaire default
and provides that save as otherwise provided in the Agreement,
in the event that any of the defaults, as mentioned therein,
shall have occurred and the Concessionaire fails to cure the
default within the cure period set forth or where no cure period
is specified, then, within a cure period of 60 days, the
Concessionaire shall be deemed to be in default of the
Agreement and this is known as Concessionaire default. Clause
37.1.1 also provides a list of instances, which may be termed as
Concessionaire default.
109. Clause 37.2, on the other hand, deals with
Termination for Authority default. It provides that in the event
of any of the default, specified therein, if the Authority fails to
cure such default within a period of 90 days or such longer
period as has been expressly provided in the Agreement, it shall
be termed as Authority default.
110. It may be mentioned that Clause 37.1.1, which
deals with Concessionaire default, lists as many as 23
circumstances, whereunder the Authority can terminate the
agreement; whereas Clause 37.2, which deals with Authority
default, provides a list of only four instances, when the
Concessionaire can terminate the agreement.
111. It is apparent from the language of Article 37 Patna High Court LPA No.2158 of 2015 dt.12-05-2016
67/208
that the agreement may be terminated even if one of the
defaults is not cured.
112. The Agreement also provides a procedure for
termination as contained in 37.1.2 and 37.2.2 for
Concessionaire default and for Authority default respectively.
The procedure is same for both the parties and the procedure is
as follows:
"Upon occurrence of Concessionaire/ Authority default the Concessionaire/Authority shall be entitled to terminate the Agreement by issuing a Termination Notice to the Concessionaire/Authority, as the case may be, provided that before issuing the Termination Notice, the Concessionaire/Authority shall by a notice inform the Concessionaire/Authority of its intention to issue such Termination Notice and grant 15 days to the Concessionaire/Authority to make representation and may after the expiry of such 15 days whether or not it is in receipt of such representation, issue the Termination Notice."
113. It may be pointed out here that so far as
Concessionaire default is concerned, there is an additional
procedure, which is not found in Authority default. The
Authority can terminate the Agreement only on compliance of
Clause 37.1.2, which provides issuance of a copy of termination
notice to the Senior Lenders of the Concessionaire. However, in
the case of Authority default, there is no such requirement.
114. Thus, the process of termination may be Patna High Court LPA No.2158 of 2015 dt.12-05-2016
68/208
summarized as follows;
a) Issuance of Notice to cure defaults ;
b) Time period for curing defaults elapses;
c) Notice of Intention to terminate;
d) Consideration of representation, if any, and
e) Termination of Agreement
115. Along with the process of termination of
agreement, it is equally necessary to understand the
consequences, which ensue, when Agreement is terminated.
116. Clause 37.3 deals with the Termination
Payment. Clause 37.3.1 provides that upon termination on
account of Concessionaire default, during the operation period,
the Authority shall pay to the Concessionaire, by way of
Termination Payment, an amount equal to 90 per cent of the
Debt Due less Insurance Cover provided that if any insurance
claims, forming part of the Insurance Cover, are not admitted
and paid, then, 80 per cent of such unpaid claims shall be
included in the computation of Debt due.
117. Clause 37.3.2 provides that for termination on
account of Authority Default, the Authority shall pay to the
Concessionaire, by way of termination payment, an amount
equal to;
a. Debt due; and
b. 150 % of the Adjusted Equity Patna High Court LPA No.2158 of 2015 dt.12-05-2016
69/208
118. Clause 37.4 of the Agreement deals with other
rights and obligations of the Authority and it provides, inter alia,
that upon termination for any reasons whatsoever, the
Authority shall be deemed to have taken possession and control
of the project Highway forthwith, take possession and control of
all materials stores, all implements, construction plants and
equipment on or about the site.
119. It would appear from the reading of various
clauses, referred to hereinabove, that when there is default on
the part of any of the parties, the party, suffering from the
default, must issue a notice to cure the defaults. When the
notice to cure default is issued by a party, the party, called
upon to answer the notice, may have three probable options,
namely;
a. The party, called upon to answer the notice to cure default, may admit the default and cure it. In such an event, no dispute arises;
b. The party, called upon to answer the notice, takes a prevaricating stand. In such an event, no dispute arises, because there is no specific denial of the default and, hence, the party, issuing the notice to cure defect, may proceed to the next stage, that is, issuance of notice of intent to terminate the agreement;
c. The party, called upon to answer the notice to cure, may deny the existence of default. In such an instance, dispute arises.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
70/208
120. Thus, in the present set of facts, the question
of referring the matter to the Bihar Public Works Contracts
Disputes Arbitration Tribunal Act, 2008, would arise only in the
third circumstance, because in the first two circumstances,
there exist no difference or dispute within the meaning of the
Bihar Public Works Contracts Disputes Arbitration Tribunal Act,
2008, for referral of the matter to the Tribunal.
121. It, now, needs to be determined the
circumstances, whereunder the case, set up by the writ
petitioner, falls.
122. In order to ascertain whether the disputes
arose or not, for the purpose of arbitration, it would be
necessary to consider all the circumstances preceding the writ
petition.
123. The undisputed circumstances, leading to the
writ petition, started with a news item, dated 06.06.2011,
appearing in Hindustan Times, under the caption "Mining
Operations to gradually stop in State". As the news,
regarding ban on mining operations, had a bearing on the
proposed Concession Agreement between the writ petitioner
and the respondents, the writ petitioner wrote a letter, dated
16.06.2011, Annexure 29 to the writ petition, addressed to the
respondent No. 7, namely, Chief General Manager, Bihar State
Development Corporation Limited, stating therein that while Patna High Court LPA No.2158 of 2015 dt.12-05-2016
71/208
submitting the bid for construction of four lane highway
between Mohania to Ara, they had envisaged mining of
aggregates from the stone quarries in the possession of
Government of Bihar. The stone quarries mentioned were as
follows:
a. Plot No. 924 (P)-Rohtas-Aggregates for concrete
works
b. Plot No. 3(P)-Rohtas-Aggregates for WMM and
Bituminous Works
c. Plot No. 4084- Kaimur-Aggregates for GSB
materials
124. In the letter (Annexure 29), the writ petitioner
mentioned that a mega project of this kind cannot be executed
without raw materials like aggregates and it will be practically
impossible to execute the project without the mining leases.
The writ petitioner also mentioned, in its letter, that importing
aggregates from neighbouring States will not only tremendously
escalate the project cost, but will also have uncertainty of
supplies and inconsistent quality. The writ petitioner
categorically stated, in its letter (Annexure 29), that the bid
validity would be extended beyond 15th June, 2011, provided
the respondent No 3, Bihar State Road Development
Corporation Limited, grants mining leases for the three plots
mentioned above for a period of 48 months failing which, it Patna High Court LPA No.2158 of 2015 dt.12-05-2016
72/208
would not be possible to extend the bid validity beyond the
period 15.07.2011 in view of spiraling commodity prices like
bitumen, steel, cement, etc.
125. After the letter, dated 16.06.2011 (Annexure
29), the writ petitioner issued another letter, dated 17.06.2011
(Annexure 30), addressed to the respondent No. 7, namely,
Chief General Manager, Bihar State Development Corporation
Limited, raising its concern regarding the availability of mining
leases for stone quarrying set out in the letter, dated
16.06.2011 (Annexure 29), and impressed upon the respondent
No. 7, namely, Chief General Manager, Bihar State
Development Corporation Limited, to resolve the issue before
entering into the Concession Agreement. It is, now, of immense
importance to note that the respondents, thereafter, without
adverting to the conditional bid by the writ petitioner, accepted
the conditional bid with the approval of the Cabinet.
126. Pursuant to the requests made, through
Annexure 29 and 30 the respondent No. 4, Managing Director,
Bihar State Road Development Corporation Limited, wrote a
letter, dated 03.11.2011 (Annexure 32), to the Collector,
Rohtas, Sasaram, whereby the respondent No. 4 brought to the
notice of the Collector that the writ petitioner had been issued
letter of award for four laning of Mohania-Ara section of NH 30
on Design, Build, Finance, Operate and Transfer (DBFOT) basis Patna High Court LPA No.2158 of 2015 dt.12-05-2016
73/208
and that the writ petitioner would require approximately 4
million tonnes of aggregate for completion of the project for
which a request had been submitted. The respondent No. 4,
accordingly, requested the Collector to take necessary action as
per the provisions of Mines & Minerals (Development &
Regulation) Act, 1957, Rule 36 "Relaxation of rules in special
cases".
127. The letter of the respondent No. 4 (Annexure
32), goes to show that acting on the request of the writ
petitioner, steps had, indeed, been taken by none other than
respondent No.4, who is the Managing Director of the
respondent-Corporation, to grant mining leases to the
appellant; but as would be seen, later, the mining lease was not
granted.
128. Though the days passed by, there was no
headway with respect to the request of the writ petitioner for
granting mining leases. The respondents, thereafter, sought for
the assistance of the Independent Engineers to suggest the
course of action to be adopted vis-a-vis the grievances of the
appellant. It may be pertinent to mention here that an
Independent Engineer was appointed by the respondents in
terms of the Concession Agreement to make necessary
comments on issues as and when sought for by the
respondents.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
74/208
129. In the present case, Intercontinental Consultants
and Technocrat Pvt. Ltd was appointed as Independent
Engineer. There was a meeting among the writ petitioner,
respondents and the Independent Engineer, on 05.04.2013, to
discuss the issues raised by the Concessionaire, the writ
petitioner, and accordingly, the respondents directed the
Independent Engineer to review the issues raised by the writ
petitioner and furnish comments.
130. The Independent Engineer, vide its letter, dated
31.05.2013 (Annexure 3), addressed to the respondent No. 8,
namely, General Manager of the respondent-Corporation, laid
its comments on the issues raised. The letter (Annexure 3),
among others, mentioned that if the writ petitioner is required
to bring the aggregates from the identified sources in the
districts of Mirzapur, Sonbhadra and Gaya, then, the additional
cost, bearing in mind the relevant technical factors, would come
to Rs. 410.13 crores. The Independent Engineer impressed
upon the respondents to take immediate steps to resolve the
issues in the interest of the project.
131. Thereafter, on 25.09.2013 (vide Annexure 2), a
review meeting was held in the Conference room of BSRDC in
the presence of respondent No. 8, namely, General Manager of
the respondent-Corporation, the Independent Engineer, and the
representative of the writ petitioner.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
75/208
132. Among the various issues discussed in the
meeting, dated 25.09.2013, the important agenda, having a
bearing in the present case, was item No. 2 relating to
allotment of mines. It has been recorded in the minutes that
the respondent No. 8, namely, General Manager of the
respondent-Corporation, had informed in the meeting that the
Government had taken a decision not to allow mining in the
State of Bihar and, as such, the Concessionaire has to arrange,
in the interest of the work, mines outside the State of Bihar. As
the minutes reveal, the cost factor, for procurement of
aggregates from outside the State of Bihar, was discussed that
such a step had got material financial impact of more than Rs
400 cr.
133. The aforementioned minutes further reveal that
the respondent No. 8, namely, General Manager of the
respondent-Corporation, having discussed the matter with the
Independent Engineer, gave a 'go ahead to the writ petitioner
with the installation of crusher and procurement of aggregates
from the neighboring States'.
134. The minutes No. 2 (in Annexure 2), being
extremely relevant, is reproduced herein;
"Allotment of Mines: Shri Vijay Shankar, GM informed that the Government has not taken a decision to allow mining in the State of Bihar and as such the Concessionaire has to arrange mines outside the State of Bihar, in the interest of work. Mr. Rajhoo Patna High Court LPA No.2158 of 2015 dt.12-05-2016
76/208
Bharot, CMD, submitted that the allotment of mines at Sasaram is a precondition before signing the Concession Agreement. The procurement of the aggregate from the neighbouring States has got material financial impact of more than Rs400 cr. This has been vetted by the Independent Engineer vide their letter no. ICT/ IE/ BSRDC/ IND/ NH-30/ TL/ 416 dated 31.5.2.2013. Procuring aggregate from the neighbouring State will necessitate re-imbursement of extra lead charges, Entry tax, toll tax etc as brought out in the earlier correspondence. It is imperative to note that no tangible progress can be achieved without mining and crushing, even if appointed date is fixed.
Shri Vijay Shankar, GM wanted to know the view of Shri A.D. Narain, Independent Engineer on this issue. Shri A.D. Narain stated that ICT have already obtained legal opinion and have also recommended re-imbursement of additional cost vide their letter dared 31.5.2013. He further stated that even otherwise the Concessionaire is entitled for re- imbursement of additional cost on account of subsequent legislation.
In view of above, Shri Vijay Shankar, GM requested the Concessionaire to go ahead with the installation of crusher and procurement ofaggregates from the neighboring States. Shri Vijay Shankar, GM requested the DGM (CPIU) Shri R.P. Singh and Shri Mahesh Prasad, DGM (PPP) to initiate a note to the Government appraising financial implication."
(Emphasis is added) Patna High Court LPA No.2158 of 2015 dt.12-05-2016
77/208
135. The writ petitioner, thereafter, went ahead with
the procurement of aggregates from neighbouring States in
view of the go-ahead given to him by the respondent No. 8. It
may be pointed out here that at the time of making
representation, the respondent No. 8 was fully aware of the fact
that such a step would burden the respondent Corporation with
an extra cost of more than Rs. 400 crores than the amount
contracted by the parties for the project; yet the representation
was made, which shows that respondent No. 8, namely,
General Manager, Bihar State Development Corporation
Limited, was seized of all the relevant factors before taking a
decision on the procurement of aggregates from outside the
State of Bihar.
136. On 05.08.2014, vide Annexure 33, another
meeting was held among the respondent No. 8, namely,
General Manager, Bihar State Development Corporation
Limited, the Independent Engineer, and the representative of
the writ petitioner and the proceeding of the meeting was
recorded. As against Serial No. 3, the discussion held and
decision arrived at with respect to payment of extra lead of
aggregates were recorded.
137. It was recorded in the minutes that since there
was no provision of extra lead aggregate in the CA (Concession
Agreement) and, hence, the claim for extra lead of aggregate Patna High Court LPA No.2158 of 2015 dt.12-05-2016
78/208
has already been rejected vide letter No. BSRDCL-
772/2011/Part-II/2013-1428, dated 16.06.2014. It is further
mentioned therein that on the request of the concessionaire,
BSRDCL shall take legal opinion on this issue.
138. The minutes in Serial No. 3, in Annexure 33, is
reproduced herein as follows;
"It has been informed that there is no provision of extra lead aggregate in the CA and the claim for extra lead of aggregate has already been rejected vide their letter no.BSRDCL-772/2011/Part- II/2013-1428, dated 16.6.2014.On the request of the concessionaire, BSRDCL shall think over to take legal opinion on this issue."
139. The fallout of the minutes, vide Serial No. 3, in
Annexure 33, was issuance of Notice, dated 09.08.2014,
Annexure 6, under Clause 37.2 of the Concession Agreement,
whereby the writ petitioner invoked the Authority default clause
notifying the respondents to cure the defaults and issues within
a period of 90 days of the notice.
140. Among the various defaults and issues raised by
the appellant, the default and issue against serial No. 1 was
with respect to non-payment of additional cost incurred for the
procurement of aggregates from longer leads amounting to
Rs. 5.63 crores till date.
141. Within one month from the date of issuance of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
79/208
Annexure 6, a meeting was held, on 04.09.2014, Annexure 7,
among the respondent No. 8, the Independent Engineer, and
the representative of writ petitioner and the proceedings of the
meeting were recorded. The first item of the meeting was
regarding the Notice, under Clause 37.2, served by the writ
petitioner upon the respondents. As against this item of
discussion, the following minutes were recorded;
"The Authority advised IE to examine and submit the proposal for additional cost for procurement of aggregates involving longer leads, by 8th September, 2014 for further consideration and submission to the State Government for approval considering the following aspects:
Cost implication for extra lead to be calculated considering carriage from road 86 rail both.
Carriage cost to be calculated from latest SOR Quarry considered in PPR to be reflected in the proposal State support agreement clause to be considered It is also directed to include the financial implication to the Authority taking into account termination of contract pursuant to the notice of the Concessionaire. The Final decision in this regard will be taken by the Govt. of Bihar ........
........
The Damages claimed by the Concessionaire for failure to procure satisfaction Patna High Court LPA No.2158 of 2015 dt.12-05-2016
80/208
of condition precedent is, now, rejected by the Authority. The Concessionaire may take recourse of Arbitration in this regard."
(Emphasis is supplied)
142. The meeting, dated 04.09.2014, Annexure 7,
reveals two important aspects, which have great bearing on this
appeal.
143. Firstly, the respondents, again, changed their
stance, contrary to the one taken vide Annexure 33, and the
respondents agreed to consider the grievance of the writ
petitioner with respect to payment of additional cost and
directed the Independent Engineer to submit fresh proposal
bearing in view the cost implication for extra lead to be
calculated considering carriage from road and rail both, carriage
cost to be calculated from latest SOR, quarry considered in PPR
to be reflected in the proposal, and State support agreement
clause to be considered. It was also recorded in the said minute
that final decision, with respect to payment of additional cost,
would be taken by the Government of Bihar.
144. Secondly, there was another issue discussed in
item No. 1 under the title "Failure to procure satisfaction of
condition precedent". In the minutes, the relevant decision
taken against this issue was that the damages, claimed by the
Concessionaire for failure to procure satisfaction of condition
precedent, is, now, rejected by the Authority; hence, the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
81/208
Concessionaire may take recourse to Arbitration in this regard.
145. Thus, when the claim, with respect to the issue
of failure of the respondents to procure satisfaction of condition
precedent, was rejected, it gave rise to a disputed claim and
accordingly, the writ petitioner was advised to take recourse to
Arbitration; but this was not so with respect to the issue of non-
payment of additional cost for procurement of aggregates from
longer leads, because there was no denial of such a claim and,
hence, no question arose for referral of the matter to
Arbitration.
146. The other important aspect of the meeting,
dated 04.09.2014 (Annexure 7), was the last recorded minute,
which stated as follows;
"Authority advised the Concessionaire to withdraw the termination notice issued by them in the light of discussion/decision held in the meeting. The concessionaire agreed for the same depending upon the recommendation of the proposal of the extra lead by the Authority to the Govt. of Bihar."
(Emphasis is added)
147. Thus, the respondents desired that the notice of
cure, issued by the writ petitioner, be withdrawn.
148. Following the minutes, recorded in the meeting,
dated 04.09.2014, against the item in serial No. 1, the
Independent Engineer submitted a fresh report to the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
82/208
respondent No. 8, vide letter, dated 09.09.2014 (Annexure 34).
It is important to note herein the subject reference of the letter,
dated 09.09.2014, which contains a reference to the Notice,
issued by the writ petitioner under Clause 37.2 of the
Agreement. Among the other technical contents of Annexure
34, the important aspect of the letter having a bearing in the
present context, is the observation contained in serial No. 1 by
which the assessment of the procurement of aggregates from
outside the State of Bihar has been reflected. The observations
are as follows;
"Cost implication for carriage of aggregate from Dalla and Dagmagpur mines in UP through Road Transport is Rs 435.28 crores Cost implication for carriage of aggregate from Dalla and Dagmagpur mines in U.P through Road and rail transport is Rs 277.288 crores."
149. The Independent Engineer also offered his
comments on the termination agreement in serial No. 7, which
may be reproduced here for the sake of understanding of the
issues.
"Article 37.3.2 of the Concession Agreement provides for quantum of payment to the Concessionaire in case of the occurrence of Default on the part of the Authority covered under clause 37.2.1 which is a sum equal to sum total of Debts due on the date of termination/ transfer date: And Patna High Court LPA No.2158 of 2015 dt.12-05-2016
83/208
150% of the Adjusted Equity • The following are the components of Debt Due payable to the Concessionaire upon occurrence of Default by the Authority:
The Principal Amount Outstanding to Senior Lenders under the Financing Agreements for financing the Total Project Cost (the principal) i.e the present outstanding amount from the Lenders is Rs 248.49 crores.
All accrued interest, financing fees and charges payable under the Financing Agreements on or in respect of the debt referred to in Sub clause (1) above until the transfer Date;
Any sub-ordinate debt under clause (c), in respect of Debts other than the borrowings from Lenders plus interest accruing @ maximum above the bank rate 5% thereon."
150. While concluding the comments in serial No. 7,
the Independent Engineer opined that the tentative amount on
account works out to about Rs 602.00 crores. The Independent
Engineers further commented that approximate estimated cost
for re-tendering of this project worked out to Rs 1472.50 crores
if the project is finally terminated.
151. Among the various opinions, given in the letter,
dated 09.09.2014 (Annexure 34), one of the important
observations was that BSRDC could consider paying the
additional cost due to extra lead as it will, in the overall
position, involve less financial implication to the Government Patna High Court LPA No.2158 of 2015 dt.12-05-2016
84/208
Exchequer as compared to other two options, viz., termination
cost payable to the Concessionaire and re-tendering cost.
152. On 06.11.2014, vide Annexure 8, another
tripartite review meeting was held at the Office of BSRDCL,
Patna, in the presence of the respondents, the writ petitioner
and the Independent Engineer. In the said meeting, vide item
(b), the issue of withdrawal of termination notice was
discussed. Against this item, the following minutes were
recorded :
"It has been informed by the Concessionaire that their notice under Clause 37.2 of CA is not a termination notice since it is the notice to the Authority to cure all the issues having material adverse effect on the project within 90 days.
The Authority stated the issues raised in the Termination Notice are promised to be cured by the Authority.
Hence the Concessionaire assured that they will not issue Termination notice as per clause 37.2.2 of the Concession Agreement"
(Emphasis is supplied)
153. It is seen that by an explicit language, used in
the minutes, the respondents promised to cure the issue raised
in the Termination Notice.
154. A reading of issue, mentioned in item no. (1)
(Annexure 8), further reveals that aggregate for longer leads Patna High Court LPA No.2158 of 2015 dt.12-05-2016
85/208
was also discussed. A verbal representation was made by the
writ petitioner to the respondents stating that Rail cum Road
route is not feasible to complete the work within the stipulated
construction period. Hence, it requested to consider only road
route for the proposal of payment of excess cost for
procurement of aggregates form longer leads. The respondents,
as is learnt from the minutes, informed that they would write to
the concerned Railway Authority at, Allahabad, to confirm the
availability of rakes/wagons and that the decision will be taken
accordingly.
155. Situated thus, it is clear that the proposal, for
procurement of aggregates from outside the State of Bihar, was
accepted by the respondents and that is why, they had
considered writing a letter to the Railways.
156. In the meanwhile, on 28.10.2014, opinion from
Principal Additional Advocate General was also obtained and he,
too, opined that payment of extra lead for stone aggregates can
be allowed subject to approval by the Cabinet.
157. On 21.11.2014. the respondent No. 7 addressed
a letter to the respondent no. 2 (vide Annexure 35), on the
subject, seeking, in principle, approval of Rs 435 crores with
regard to extra cost carriage of stone aggregate for N.H. 30
Mohania-Ara section.
158. In the meanwhile, a joint meeting was Patna High Court LPA No.2158 of 2015 dt.12-05-2016
86/208
convened, wherein the lenders of the writ petitioner, namely,
Union Bank of India, Bank of Baroda, Oriental Bank of
Commerce and Punjab and Sindh Bank, were present along with
the respondent No. 8 and the writ petitioner to discuss the
progress of the project and the issues raised by the writ
petitioner. It has been recorded in the minutes that the
respondent No. 8 advised the Bank authorities that the writ
petitioner should arrange extra funds, required for procurement
of aggregates from longer leads for the project, from the
lenders, or internally, by the Company, as the State
government has not granted approval to the Authority to bear
the extra cost. However, the Authority will consider extending
concession period for the extra cost incurred by the company
based on revised cash flow.
159. It is seen that even in the joint meeting with
Bank officials, the respondents did not deny entitlement of
extra cost by the writ petitioner.
160. By now, neither the respondents paid the
additional cost to the writ petitioner nor did they deny, in
principle, that the claim of the writ petitioner is illegitimate. In
these circumstances, as is understood from the letter, dated
04.02.2015 (Annexure 11), the writ petitioner invoked Clause
37.2.2 of the Concession Agreement and issued a notice of
intent to terminate the Agreement asking the respondents to Patna High Court LPA No.2158 of 2015 dt.12-05-2016
87/208
make representation within the stipulated period of 15 days.
161. 1t may be mentioned that Notice to cure defaults
required that defaults be cured within 90 days and even
though it has been noticed hereinbefore that on record, the
respondents promised to cure the defaults, yet the defaults
were not cured since the date of 09.08.2014, when the notice
to cure default was, first, issued by the writ petitioner.
162. Among the list of defaults , mentioned along
with Annexure 11, item No. 1 referred to Non-payment of
additional cost incurred for the procurement of aggregates from
longer leads amounting to Rs 9,15,20,314/- till 31.12.2014 and
non-granting of permission to procure aggregates from longer
leads for road works as had been decided in the meeting, dated
25.09.2013.
163. Not barely three days had passed after the
issuance of the letter, dated 04.02.2015. Annexure 11, that the
respondents, through respondent no. 9, issued a letter, dated
07.02.2015 (Annexure 12). The contents of the letter, dated
07.02.2015, being relevant, are being reproduced ad verbatim.
"Dear Sir,
The Concessionaire given NOTICE and invoke the provisions of clause 37.2.2 of the Concession Agreement with intension of the Concessionaire to issue Termination Notice and calls upon the Authority to make representation within 15 days from the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
88/208
receipt of this Termination Notice.
In this connection, the Authority is directed to the concessionaire to submit the details all the materials stores, plant and machineries and equipment available at site to the Authority pursuant to clause 37.4 (b) of C.A for taking further action by the Authority"
(Emphasis is added)
164. It is evident from the contents of Annexure 12
that pursuant to the invocation of Clause 37.2.2 of the
Concession Agreement by the writ petitioner, and the issuance
of notice of intent to terminate the Agreement, the respondents
did not even submit a representation in terms of the rights,
conferred by the said clause; rather, they straightaway
proceeded to Clause 37.4 (b), the occasion for which would
have had arisen only when the agreement had been terminated
after exhausting the process. Therefore, a right to
representation, which existed, had been waived by the
respondents. Thus, on principle, the respondents agreed to the
termination of the agreement.
165. Ordinarily, after the issuance of the letter, dated
07.02.2015, Annexure 12, no issue, with respect to the
payment of additional cost for procurement of aggregates from
longer leads, remains alive; nonetheless; it transpires from the
letter, dated 16.02.2015, that in para 3.1, under the heading Patna High Court LPA No.2158 of 2015 dt.12-05-2016
89/208
Non-payment of additional cost incurred by the Concessionaire
for procurement of aggregates, the respondents referred to
Clause 12.1(d) of the Agreement, which provides as follows;
"Prior to commencement of Construction works, the Concessionaire shall make its own arrangement for quarrying the materials needed for the project highway under and in accordance with applicable laws and applicable permits".
166. By referring to Clause 12.1(d), the respondents
stated that it is the responsibility of the writ petitioner to
procure aggregates or any other materials needed for the
project highway.
167. Apparently, it seems that contents of Clause
12.1(d) have not been construed in proper perspective. It
mentions that the Concessionaire, the writ petitioner, shall
make its own arrangement for quarrying the materials needed
for the project highway under, and in accordance with,
applicable laws and applicable permits. Quarrying is an act of
removal of aggregates from the quarry, which the writ
petitioner had been demanding all along; but despite repeated
applications from the writ petitioner, the respondents had done
nothing to allow quarrying in the State of Bihar by granting
mining lease; rather, they permitted the writ petitioner to bring
aggregates from outside the State of Bihar, which the writ
petitioner, admittedly, did. Hence, quarrying, in the present Patna High Court LPA No.2158 of 2015 dt.12-05-2016
90/208
context, does not mean quarrying even though, when the
quarrying is prohibited law.
168. A further reading of paragraph 3.1 of Annexure
16 would show that respondents contended that by then, the
Govt. of Bihar had, vide Notification No. 3085/M, Patna, dated
11.08.2014, opened the mining lease for procurement of
aggregates and even then, the writ petitioner had not made any
efforts for procurement of aggregates.
169. However, it is not understood as to how
removal of prohibition on mining would automatically lead to an
inference that the writ petitioner would have been granted
mining lease, had he made such efforts. In fact, it would not be
proper to even suggest that writ petitioner had not put up
efforts to get a mining lease within the State of Bihar. The
letters, vide Annexure 29 and 30, indicate that writ petitioner
was pressing hard for a mining lease in the State of Bihar,
pursuant to which the letter, vide Annexure 32, was written by
respondent No. 4 to the Collector, Rohtas, Sasaram, for
considering the request of the writ petitioner in view of Rule 36
of the Rules under the Mines 86 Minerals (Development 86
Regulation) Act, 1957, as a special case.
170. It, thus, clearly emerges that the plea of lifting
of prohibition on mining and alleging the writ petitioner of not
putting up efforts to get an allotment of mining lease was taken Patna High Court LPA No.2158 of 2015 dt.12-05-2016
91/208
only with a view to subverting the Notice of Intent to Terminate
issued by the writ petitioner. In any view of the matter, such a
reply, as contained in Annexure 16, was issued only after the
issuance of Notice of Intent to terminate in view of Authority
default.
171. Having induced the writ petitioner, by various
representations to procure aggregates from outside the State of
Bihar, a representation, as have been noticed, on which the writ
petitioner had acted upon, it was not open to the respondents
to turn around and say that it is the responsibility of the writ
petitioner to procure aggregates.
172. Nonetheless, the writ petitioner issued a
termination notice by invoking the provisions of Clause 37.2 of
the Agreement.
173. It is noteworthy that more than a month after
the issuance of Termination Notice, dated 20.02.2015, the
respondent No. 2, namely, Principal Secretary, Road
Construction Department, in his letter, dated 23.03.2015,
Annexure 26, informed the respondent No. 4, namely,
Managing Director, Bihar State Development Corporation
Limited, that the matter, as regards payment of extra cost of
carriage of stone aggregate, is being submitted for review by
Assembled Authorized Committee under the Chairmanship of
the Chief Secretary. It may be further pointed out that this Patna High Court LPA No.2158 of 2015 dt.12-05-2016
92/208
letter, Annexure 26, was in response to the request made by
the respondent No. 7, namely, Chief General Manager, Bihar
State Development Corporation Limited, on 21.11.2014, by a
letter to the respondent No. 2, namely, Principal Secretary,
Road Construction Department, vide Annexure 35, for granting,
in principle, approval for payment of Rs. 435 crores With regard
to extra cost carriage of stone aggregate for N.H. 30 Mohania-
Ara section.
174. The writ petitioner, then, approached the Court
by filing a writ petition, on 29.04.2015, subsequent to which
the respondents issued notices, dated 26.05.2015 and
10.06.2015, vide Annexure 22 and 23 respectively, purporting
to terminate the agreement.
175. In view of the above sequence of events, the
first question, which needs an answer is whether, till the filing
of the writ petition, a dispute existed on the point that the writ
petitioner is not entitled to payment of additional cost for
procurement of aggregates from longer leads. If the answer to
this question is in the affirmative, the writ petition would not be
maintainable in view of Article 44 containing a clause of
Arbitration. On the other hand, if the answer to the question, so
posed, is in the negative, the writ petition would be
maintainable to the extent that no dispute existed for referral to
arbitral Tribunal.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
93/208
176. Recalling, at this stage, the process for
termination of agreement, as discussed hereinbefore, the party
called upon to cure the defects has two options; namely, he
may admit the defaults, or he may deny that defaults exist. A
dispute would arise only when there is a specific denial of
defaults as mentioned in the Notice to Cure defaults.
177. In the sequence of events, pointed out above,
it would be noticed that the writ petitioner had been urging the
respondents cure the defect with respect to procurement of
aggregates from longer leads. The respondents prevaricated on
this issue and, on one occasion, made an explicit promise to
cure the default.
178. Thus, the claim, as to additional cost, was
admitted, and, hence, the writ petitioner was asked to procure
aggregates from longer leads. A promise, on which the writ
petitioner acted and incurred financial expenditure under the
impression additional cost issue would be cured, has to be held
against the respondents. However, as no solution could be
arrived at nor was the claim denied, it amounted to a default on
the part of the respondents having a material adverse effect on
the project implementation. Once the notice to cure the defaults
was issued by the writ petitioner, on the ground of, amongst
others, additional cost, and the default was not denied by the
respondent, the stage for disputing the claim was over. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
94/208
Thereafter, the only recourse, which the writ petitioner could
have taken, was to issue Notice of Intent to Terminate, which
the writ petitioner did issue. As the facts reveal, even after the
Notice of Intent to Terminate, the respondents did not deny the
contents of notice; rather, they took the follow up steps for
termination of agreement for taking possession and control of
the project in terms of Clause 37.4. Thus, a dispute was not
raised even after the Notice of Intent to terminate was issued.
Logically extended, it would mean that the stage for raising
dispute was already over.
179. Indeed, the respondent, vide letter, dated
16.02.2015 (Annexure 16), served a representation against the
Notice of Intent to Terminate issued by the writ petitioner; but
by then, the scope for raising dispute was over. If the
representation, vide Annexure 16, is construed as creating a
dispute on the claims made by the writ petitioner, then, on the
face of Annexure 12, it would amount to allowing the
respondents to approbate and reprobate. It is not permissible
for the respondents to once admit the default and take follow
up action in termination of the contract and, then, to turn
around and say that the Notice of Intent to Terminate, issued
by the writ petitioner, is illegal. It would be evident from the
conduct of the respondents that even though settlement of
financial claims was not arrived, yet so far as the termination of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
95/208
agreement is concerned, the letter, dated 04.02.2015
(Annexure 11), amounted to accord and satisfaction so far as
the issue of termination of agreement is concerned.
180. It is, thus, found that so far as the issue raised
by the writ petitioner, regarding payment of additional cost, for
procurement of aggregates from longer leads, is concerned, the
respondents not only admitted the default by promising to cure
it, but they also omitted to cure the default and this act of the
respondents amounts to default and not a dispute. The writ
petitioner had the liberty to initiate the process of termination
of agreement in the event of any one of the default occurring
within the meaning and scope of Clause 37.2.1.
181. Thus, it would be seen that there remains no
issue for adjudication by the Arbitration Tribunal as regard the
issues relating to payment of additional cost for procurement of
aggregates from longer leads and consequential termination of
agreement. In any view of the matter, if the respondents were
aggrieved by the act of the writ petitioner in issuing Notice of
intent to Terminate, and term it as 'dispute' within the meaning
of Article 44, then, even they were at liberty to approach the
Arbitration Tribunal; but, as the records would show, the
respondents, too, never approached the Tribunal.
182. Having not approached the Arbitration Tribunal
and having admitted the default by promising to cure the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
96/208
default, it does not lie in the mouth of the respondents to say
that disputes are arbitrable. It is accordingly held, on the facts
of this case, that no occasion arose for invocation of Article 44
of the Concession Agreement.
183. Moreover, as held by the Supreme Court, in
the case of Union of India v. Tantia Construction (P) Ltd.,
(2011) 5 SCC 697, while making an observation on arbitration
clause, that it is, now, well established that an alternative
remedy is not an absolute bar to the invocation of the writ
jurisdiction of the High Court or the Supreme Court and that
without exhausting such alternative remedy, a writ petition
would be maintainable. It was further held, in Tantia
Constructions (supra), that injustice, whenever and wherever
it takes place, has to be struck down as an anathema to the
rule of law and the provisions of the Constitution. The relevant
observations, appearing in Tantia Constructions (supra),
read:
"33. Apart from the above, even on the question of maintainability of the writ petition on account of the arbitration clause included in the agreement between the parties, it is now well established that an alternative remedy is not an absolute bar to the invocation of the writ jurisdiction of the High Court or the Supreme Court and that without exhausting such alternative remedy, a writ petition would not be maintainable. The Patna High Court LPA No.2158 of 2015 dt.12-05-2016
97/208
various decisions cited by Mr Chakraborty would clearly indicate that the constitutional powers vested in the High Court or the Supreme Court cannot be fettered by any alternative remedy available to the authorities. Injustice, whenever and wherever it takes place, has to be struck down as an anathema to the rule of law and the provisions of the Constitution."
SCOPE OF JURISDICTION UNDER ARTICLE 226 OF THE CONSTITUTION OF INDIA WITH RESPECT TO CONTRACTS BY OR ON BEHALF OF STATE: -
184. The learned Principal Additional Advocate
General strenuously argued that the claims, made in the writ
petition, fall within the realm of contract and in view of the
several pronouncements of Supreme Court, it is, now, well
settled that contractual obligations cannot be enforced by
resorting to extraordinary jurisdiction of the High Court under
Article 226 of the Constitution. Learned Principal Additional
Advocate General placed reliance on the case of Radhakrishna
Agarwal v. State of Bihar, reported in (1977) 3 SCC 457, to
buttress his argument that a writ petition, under Article 226 of
the Constitution of India, cannot, in the present case, be
maintained for enforcing contractual obligations.
185. The basic question, which needs to be
addressed, in the present appeal, is: whether the remedy Patna High Court LPA No.2158 of 2015 dt.12-05-2016
98/208
available, under Article 226 of the Constitution of India, can
legitimately be resorted to in order to obtaining a direction from
the High Court for payment of amounts due and payable by the
State Government in contractual matters and if so, in what
circumstances, such a remedy can be made available?
186. While considering the question, posed above,
what needs to be noted is that a government contract, even if
commercial in nature, involves, broadly speaking, four stages.
The first stage relates to the floating of tenders by publishing
notice inviting tenders. At this stage, the authorities concerned
are required to formulate the terms and conditions subject to
which the tenders would be invited and also the terms and
conditions of the contract, which, if entered into, would govern
the parties. These terms and conditions would obviously include
all the eligibility criteria for a person to participate in the tender
process. After the notice inviting tender is published and the
tenders are received, the second stage of such a contract
commences. This stage involves the process of taking of the
decision to allot or not to allot the contract at all and cancel the
entire process. This stage would include selection of the person
or the party to whom the contract shall be allotted. This stage
ends with the allotment of the contract or with the decision not
to allot the contract at all and cancel the entire tender process.
The third stage of the contract essentially covers the stage of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
99/208
performance of the contract. This stage would include
commencement of the performance of the allotted contract and
would, normally, end with the completion of the allotted
contract. During this stage, there may arise the question of
breach of the contract, because of non-fulfilment of the terms
and conditions of the contract by either party to the contract.
The fourth stage of such a contract arises, when, on completion
of his part of the contract, the contractor or supplier raises his
demand for making payment of his bills. This fourth stage can,
however, be divided into two categories. There may be a case,
where the amount demanded is not disputed and yet the dues
of the contractor are not paid compelling thereby the contractor
to seek avenues for obtaining payment of his dues. In this
fourth stage, there may, however, be a case, where the
correctness of the demand for payment raised by the contractor
is disputed, denied or challenged by the authority, who had
allotted the contract. In such a case, too, the contractor may be
driven to take recourse to such avenues as may be open to
him, in law, for the purpose of enabling him to obtain his dues
in terms of the demand that he may have made.
187. It may, now, be pointed out that at the first
stage of a contract, which requires the authorities concerned to
formulate the terms and conditions subject to which the tenders
would be invited or the contract would be allotted, many factors Patna High Court LPA No.2158 of 2015 dt.12-05-2016
100/208
are taken into account. The decision as to what terms shall be
included in the tender is really a policy decision, for, it is the
authority, issuing the notice inviting tender, which is the best
judge to determine as to what terms and conditions would be
required for successful completion of the work or the project
concerned. Thus, it is, primarily, for the authority issuing the
NIT to decide what particular terms and conditions should be
incorporated in the NIT. However, when the invitation to tender
is floated, the second stage, which consists of the process of
selection of the person for awarding the contract, commences
and this process comes to an end, when a decision either
awarding the contract or cancelling the entire tender process is
taken. The decision to award the contract to a person, who
participates in a tender process, is not open to judicial review,
but the decision making process, which leads to the ultimate
decision, is, according to the law laid down in Tata Cellular v.
Union of India, reported in, (1994) 6 SCC 651, open to
judicial review. In Raunaq International Ltd. v. I.V.R.
Construction Ltd. and Ors., (AIR 1999 SC 393), the Apex
Court has made it clear that though the decision to award a
contract is not open to judicial review, the decision making
process, which leads to the ultimate decision, is, indeed, open
to judicial review provided that there is an element of public
interest involved in the case requiring a review by the court of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
101/208
the administrative decision to allot the contract.
188. What may be further noted is that at the first
and the second stage of the contracts, when the government or
any of its instrumentalities sets up the terms and conditions of
the contract or takes a decision to allot the contract, it acts
purely in its executive capacity and its action is, therefore, open
to judicial review, though in a limited way, as indicated
hereinabove. However, when the third stage is reached and a
contract is entered into by the government or its
instrumentality, on the one hand, and the contractor, on the
other, the parties are no longer governed by constitutional
provisions, but by the terms of the contract. Hence, when a
State, purporting to act within the field allotted to it under the
terms and conditions of a contract, performs an act, the rights
and obligations of the parties would be, ordinarily, governed by
the law that governs the terms and conditions of the contract.
189. What logically follows from the above
discussion is that in the third stage, which consists of the
performance of the contract, the remedy of the parties to the
contract for breach of any of the terms and conditions of the
contract would, ordinarily, lie in the civil court of competent
jurisdiction unless the parties have, under the terms of the
contract, agreed to refer such a dispute to arbitration. Thus,
ordinarily, no writ would be issued, under Article 226 of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
102/208
Constitution of India, for a mere breach of the terms and
conditions of the contract, particularly, when, for settlement of
such a dispute, there is a provision for arbitration.
190. In the fourth stage of a contract, which arises
on completion of the contract, a demand for payment of bills or
Clues, raised by the contractor, may not be amenable to
arbitration proceedings, for, the authorities concerned, who had
allotted the contract, may dispute entitlement of the contractor
to receive the dues, which the contractor has demanded, or
there may be a case, wherein although no dispute is raised by
the authorities concerned that the bills are due and payable to
the contractor, the payment is not made.
191. In a case, wherein demands are not disputed,
but payment is not made, the demand for payment may or may
not be amenable to arbitration proceeding, for, it would
essentially depend upon the terms and conditions of the
contract inasmuch as the terms and conditions of the contract
would determine if, even for realization of an admitted amount
or even when there is no dispute as regards the dues claimed,
an arbitration proceeding can or must be resorted to. If no
provision for arbitration of such a claim has been made in the
contract agreement, the remedy of the person, who demands
payment, lies, ordinarily, in instituting suit in civil courts and
not in filing petition under Article 226 of the Constitution of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
103/208
India, seeking enforcement of the State's obligation to pay its
dues.
192. What is, now, of immense importance to note
is that there may be a case, where the demand for payment
made by a contractor is disputed or there may be a cross-claim
raised by the State against the contractor. There may, however,
be cases, wherein the claim made by the contractor is admitted
and there is no cross-claim between the parties to be
determined. In such cases, there is really no dispute as regards
the facts. Would it, in such a case, be necessary for the writ
court to revert the party to the remedies available through the
civil court?
193. The answer to the crucial question, posed
above, hinges on the principle that if an alternative efficacious
remedy is available, writ jurisdiction shall not be exercised.
What is, of course, necessary to point out is that existence of
an alternative remedy is not an absolute bar to the jurisdiction
of the court under Article 226 of the Constitution of India, but is
always a matter of exercise of discretion and remains,
therefore, in the realm of prudence. What is, however, of great
relevance to note is that though a disputed question of fact is
not, normally, entertained by a High Court in its writ
jurisdiction, it will not, as a corollary, follow that if there is no
disputed question of fact, remedy under Article 226 of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
104/208
Constitution of India would be available. The mere fact,
therefore, that in a writ petition, the bills, raised by a
contractor, are admitted to be due and payable by the State
cannot, in itself, be a ground for issuing a writ of mandamus to
the State respondents commanding them to make payment of
the dues of such a contractor. Conversely put, a State cannot
refuse to pay its dues without any good and sufficient cause or
else, its refusal would amount to its act being arbitrary and a
remedy under Article 226 of the Constitution of India, in such a
case, may not remain as an absolute bar. Necessarily,
therefore, it is the facts of a given case, which would decide
whether a writ of mandamus can be issued or not.
194. It may be further noted that a writ of
mandamus is a public remedy and this remedy lies, when a
public authority fails to perform the duty entrusted to it by law.
In other words, a writ of mandamus is issued against a person,
who has a legal duty to perform, but has failed or neglected to
do so. Distinguishing a case, wherein a public duty of a State is
sought to be enforced, and a case, wherein a contractual
obligation of a State is sought to be enforced, Professor Wade,
in his well-known treatise, 'Administrative Law', makes it clear
that while a public duty is enforceable by the public law remedy
of a writ of mandamus, a contractual duty is enforceable, as a
matter of private law, through the avenues of civil courts. The Patna High Court LPA No.2158 of 2015 dt.12-05-2016
105/208
observations made, in this regard, by Professor Wade read
thus:
"...A distinction which needs to be clarified is that between public duties enforceable by mandamus, which are usually statutory and duties arising merely from contract. Contractual duties are enforceable as matters of private laws by the ordinary contractual remedies, such as damages, injunction, specific performance and declaration. They are not enforceable by mandamus, which in the first place is confined to public duties and secondly is not granted where there are other adequate remedies."
195. What, now, needs to be noted is that howsoever
thin and subtle may be, there is, indeed, a real and definite line
demarcation not only between a public wrong and a private
wrong, but also between a public law remedy and private law
remedy. Article 226 of the Constitution of India is pre-eminently
a public law remedy and is not, generally, available as a remedy
against private wrongs. Resort to Article 226 of the Constitution
of India can be had to enforce various rights of the public or to
compel the public or statutory authorities to discharge their
public duties and/or to act, in the realm of their public function,
within the bounds of law. The remedy under Article 226 of the
Constitution of India can, no doubt, be availed of even against a
private body or person; but the scope of the writ of mandamus Patna High Court LPA No.2158 of 2015 dt.12-05-2016
106/208
is limited to, enforcement of public duty. In minimum possible
words, but with extreme exactitude, clarified the Supreme
Court, in Binny Limited and Anr. v. V. Sadasivan and Ors.,
reported in MANU/SC/0470/2005, the position of law, in this
regard, in the following words:
"29. Thus, it can be seen that a writ of mandamus or the remedy under Article 226 is pre-eminently a public law remedy and is not generally available as a remedy against private wrongs. It is used for enforcement of various rights of the public or to compel public/ statutory authorities to discharge their duties and to act within their bounds. It may be used to do justice when there is wrongful exercise of power or a refusal to perform duties. This writ is admirably equipped to serve as a judicial control over administrative actions. This writ could also be issued against any private body or person, specially in view of the words used in Article 226 of the Constitution. However, the scope of mandamus is limited to enforcement of public duty. The scope of mandamus is determined by the nature of the duty to be enforced, rather than the identity of the authority against whom it is sought. If the private body is discharging a public function and the denial of any right is in connection with the public duty imposed on such body, the public law remedy can be enforced. The duty cast on the public body may be either statutory or Patna High Court LPA No.2158 of 2015 dt.12-05-2016
107/208
otherwise and the source of such power is immaterial, but, nevertheless, there must be the public law element in such action."
196. Thus, in the face of succinctly laid down position
of law with regard to the issuance of a writ of mandamus under
Article 226 of the Constitution of India, what one has to bear in
mind is that in order to invoke the writ jurisdiction under Article
226 of the Constitution of India, two conditions, in a case of
private wrong, must be satisfied, namely;
(i) the identity of the person, against whom the writ is sought, as a person or body, which is amenable to writ jurisdiction, and
(ii) the nature of duty, which is sought to be enforced, is a public duty or has an element of public interest.
197. In a given case, one may, perhaps, ignore the
first pre-requisite, namely, the identity of the person or body as
a person or body amenable to writ jurisdiction, but the second
prerequisite, as indicated hereinbefore, cannot be ignored, for,
in the absence of public interest or in the absence of breach of
public duty or in the absence of any public wrong having been
committed, no recourse to Article 226 of the Constitution of
India is possible.
198. What also needs to be cautiously noted is that
constitutional or statutory duty is a public duty and enforceable Patna High Court LPA No.2158 of 2015 dt.12-05-2016
108/208
by a writ of mandamus. To put it differently, the rights and
duties go hand-in-hand. When a right is given to a person by a
State, the State casts upon itself a duty to enforce such a right.
Logically, therefore, when a person is given fundamental right
by the Constitution, a duty rests on the State to ensure that the
person realizes his fundamental rights.
199. In a given case, therefore, if a person, aggrieved
by a breach of contract, shows that though the breach is in the
realm of a contract, the duty, sought to be enforced, is a
constitutional or statutory duty, the remedy of a writ of
mandamus may not be refused, for, it is the constitutional
obligation of the High Court, under Article 226 of the
Constitution of India, to enforce the constitutional and statutory
duties of the State and its instrumentalities.
200. The question, therefore, is as to whether every
breach of governmental obligation to pay its dues, under a
contract, falls outside the purview of Article 226 of the
Constitution of India. This brings us to a more important
question and the question is: Will the constitutional remedy of
Article 226 of the Constitution of India never be available
against a State even if the State refuses to carry out its
contractual obligations with ulterior motives, irrationally,
arbitrarily, unreasonably, unfairly, whimsically or when its
denial suffers from mala fide, or when the State, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
109/208
demonstratively discriminates, while making payment of its
dues? Shall the writ court withdraw its hand resignedly and
helplessly by saying that a writ of mandamus is a public law
remedy and no writ of mandamus would be issued to any State
directing it not to discriminate or act irrationally, arbitrarily,
unreasonably, unfairly, whimsically, or with ulterior motives,
while refusing or omitting to make payment of its dues arising
out of contracts or when the State‟s denial is mala fide?
Imperative, therefore, for us to ask: Can a breach of contract
ever give rise to any constitutional obligation of the State to
make payment of its dues?
201. Coming, now, to the case of Radhakrishna
(supra), as referred to by the learned Principal Additional
Advocate General, it becomes necessary to discuss, herein, the
circumstances whereunder the decision, in Radhakrishna
(supra), was rendered.
202. This was an appeal from the judgment of Patna
High Court. In Radhakrishna (supra), the petitions were
directed against orders of the State Government, passed in
1974, revising the rate of royalty payable by the petitioners-
appellants under a lease of 1970, and, thereafter, cancelling the
lease by a letter of March 15, 1975. The petitioners' case was
that the revision of the rate of royalty payable by the
petitioners for the lease to collect and exploit Sal seeds from Patna High Court LPA No.2158 of 2015 dt.12-05-2016
110/208
the forest area was illegal during the subsistence of the lease
and, thereafter, cancellation of the lease itself was illegal for
various reasons.
203. The relevant clause, relating to revision of
royalty in the written contract, read as follows:
"The rate of royalty will be revised every three years cycle in consultation with the lessee and the decision will be binding on the lessee."
204. The Supreme Court found that there was no
restriction, under the terms of the contract, upon the amount
by which the royalty could be increased by a revision after a
three years' cycle under the relevant clause. The lessee was
only entitled, under the contract, to be consulted before a
revision. But the decision of the Governmental authorities to
enhance royalty was binding. It was in these circumstances
that the Supreme Court, held, in Radhakrishna (supra), that
the questions, which apparently arose, appertained to action,
alleged by the State, that fall within the terms of the
agreement between the parties, regulated by the duly signed
contract, which was presumably executed in compliance with
the provisions of Article 299 of the Constitution of India and,
accordingly, the petitioners could only get their remedies, if
they can obtain any at all, through ordinary suits for damages
or for injunctions to restrain breaches of contract provided they
could show how the contracts were broken or were going to be Patna High Court LPA No.2158 of 2015 dt.12-05-2016
111/208
broken.
205. While considering the scope of Article 226 of the
Constitution of India with respect to contractual matters, the
Supreme Court approved, in principle, the three circumstances,
laid down by the Patna High Court, in Radhakrishna (supra),
which are likely to arise vis-a-vis a contract.
206. The circumstances were stated as follows:
b. Where a petitioner makes a grievance of breach of promise on the part of the State in cases where on assurance or promise made by the State he has acted to his prejudice and predicament, but the agreement is short of a contract within the meaning of Article 299 of the Constitution;
c. Where the contract entered into between the person aggrieved and the State is in exercise of a statutory power under certain Act or Rules framed thereunder and the petitioner alleges a breach on the part of the State; and d. Where the contract entered into between the State and the person aggrieved is non-statutory and purely contractual and the rights and liabilities of the parties are governed by the terms of the contract, and the petitioner complains about breach of such contract by the State.
207. The Patna High Court had held, in
Radhakrishna (supra), that so far as the first category of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
112/208
cases are concerned, it could be held that public bodies or the
State are as much bound as private individuals and are to carry
out obligations incurred by them, because parties, seeking to
bind the authorities, have altered their position to their
disadvantage or have acted to their detriment on the strength
of the representations made by these authorities.
208. According to the Patna High Court, in
Radhakrishna (supra), the obligation could, sometimes, in
such cases, be appropriately enforced by filing of a writ petition
even though the obligation was equitable only.
209. As against the proposition, laid down by the
Patna High Court, with respect to the first category of cases, in
Radhakrishna (supra), the Supreme Court held that they do
not propose to express any opinion on the question whether
such an obligation could be enforced in a proceeding under
Article 226 of the Constitution. However, the Supreme Court did
hold that dispute, raised in Radhakrishna (supra), does not
fall within the first category of cases. The relevant extract of the
observations made by the Supreme Court, in Radhakrishna
(supra), in this regard, are reproduced herein as follows;
"13. The High Court thought that in such cases the obligation could sometimes be appropriately enforced on a writ petition even though the obligation was equitable only. We do not propose to express an opinion here on the question whether such an obligation could be enforced in proceedings under Patna High Court LPA No.2158 of 2015 dt.12-05-2016
113/208 Article 226 of the Constitution now. It is enough to observe that the cases before us do not belong to this category."
210. On an analysis of the Radhakrisha (supra), it is
found that even though Supreme Court gave its stamp of
approval on the categorization of cases with respect to
contractual rights, yet chose not to express any opinion on the
question whether, for contractual obligations, falling under the
first category, a writ under Article 226 of the Constitution of
India would lie or never lie?
211. Thus, the ratio of Radhakrishan (supra) cannot
be held to be a law of universal principle that under no
circumstances, a writ, under Article 226 of the Constitution of
India, would lie for enforcement of contractual obligation of the
State or its instrumentalities.
212. In order to ascertain the judicial trend, it would
be proper to examine some of the relevant judicial
pronouncements, wherein the issues of contractual obligations
vis-a-vis role of the State action were involved.
213. One of the principle cases, which dealt with the
issue of enforcement of contractual obligations was the case of
Divl. Forest Officer v. Bishwanath Tea Co. Ltd., reported in
(1981) 3 SCC 238, the facts of which may be taken note of
214. The facts of the case of Bishwanath Tea Co.
Ltd. (supra) was that the respondent had filed a writ petition Patna High Court LPA No.2158 of 2015 dt.12-05-2016
114/208
questioning the action of the appellant, the Divisional Forest
Officer, Darrang Division, for recovering Rs 7069.37 as royalty
for cutting and felling trees from Tezalpatty Grant 1 held under
lease, dated September 27, 1932, and for a mandamus
directing the appellant to issue permits without insisting upon
payment of royalty for the trees cut and felled from the area
under lease. As against the writ petition, a preliminary objection
was raised by the appellant that the right, claimed by the
respondent, flowed from the contract of lease and such
contractual rights and obligations can only be enforced in civil
court. It was contended that apart from the fact that
interpretation of the contract of lease is, generally, not
undertaken by the High Court in exercise of its extraordinary
jurisdiction under Article 226 of the Constitution of India, it was
further contended that even if interpretation of the relevant
clause of the lease, as alleged on behalf of the respondent,
finds favour with the court, yet facts will have to be
investigated before any refund could be ordered or a blanket
injunction could be granted for all times to come against the
appellant from performing his duty, namely, of granting permit
and recovering royalty.
215. The preliminary objection was overruled and the
writ petition was allowed by Gauhati High Court.
216. In appeal, the Supreme Court, at the outset, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
115/208
held, in Bishwanath Tea Co. Ltd. (supra), that the
respondent, being a juristic person, was not entitled to any
relief for enforcement of rights guaranteed under Article 19 of
the Constitution of India and, on this count, alone, the writ
petition would fail.
217. In order to further appreciate the ruling of the
Supreme Court, in Bishwanath Tea Estate (supra), it would
be necessary to set out the some of the other facts involved.
218. Bishwanath Co. Ltd. had taken on lease land
measuring 1107.26 acres from the Government. The lease was
to be exploited for cultivation and raising tea-garden. The
manager of the company approached the appellant seeking
permission to cut 7000 cubic feet of timber from grant N.C.
Tezalpatty 1 of Nagshankar Mouza for utilising the same for
building of staff and labourer's houses. By a reply, the appellant
noted that the timber was to be cut for constructing houses in
Partabghur and Dekorai Tea Estates and that it was necessary
to ascertain whether any of the aforementioned two tea estates
was situated within the grant evidenced by lease of N.C.
Tezalpatty 1. It was made clear that if it was not so, full royalty
will be payable by the company for cutting, felling and removing
timber. The manager, by his letter, informed the appellant that
as the lessee is Bishwanath Tea Co. Ltd., it can cut and fell
timber from any of its leased area to 'be utilised for its purposes Patna High Court LPA No.2158 of 2015 dt.12-05-2016
116/208
in any other division. Therefore, the manager suggested that
the permit must be issued without insisting on payment of
royalty. The appellant, by his letter, informed the manager that
as the timber was required for use in Partabghur and Dekorai
Tea Estates, which were not within N.C. Tezalpatty Grant 1 of
Nagshankar Mouza from which timber was to be felled and cut,
full royalty will be payable on timber so cut and removed,
because it was to be utilised for the purpose unconnected with
the grant. For this assertion, the appellant relied upon a portion
of clause 2 of Part IV of the lease deed, dated September 27,
1932. Correspondence further ensued between the parties and,
ultimately, the respondent Company paid an amount of Rs
7069.37 as and by way of royalty under protest and, then, filed
a petition under Article 226 of the Constitution in the High Court
alleging that upon a true construction of the relevant clause of
the grant as also the proviso to Rule 37 of the Settlement
Rules, since the timber was required for the purpose connected
with the exploitation of the grant, the company, as lessee, was
entitled to cut and remove timber without payment of royalty
and, therefore, the recovery of royalty being not supported by
law, the appellant was liable to refund the same. The company
also prayed for a mandamus directing the appellant, who was
respondent in the High Court, to issue permits without insisting
on payment of royalty, whenever timber was to be cut from the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
117/208
leased area for the purposes connected with the exploitation of
the grant.
219. The Supreme Court, on appreciation of facts,
found, in Bishwanath Tea Estate (supra), that the relief,
claimed by the respondent, was referable to nothing else but
the term of the lease viz. clause 2, Part IV and that a bare
perusal of clause 2 of Part IV of the indenture of lease and the
proviso to Rule 37 would, at a glance, show that the proviso
enables a grantee to take benefit of it by fulfilling certain
conditions, namely, by paying a reduced valuation representing
only the profit, which it is likely to derive from the use of timber
for purposes connected with the exploitation of the grant. It is,
thus, an enabling provision and the grantor of the lease may
permit this option to be enjoyed by the grantee. But whether
that has been done or not is always a question of fact. If the
pre-condition is satisfied, the benefit can be taken. That again is
a matter to be worked out by the parties to the indenture of
lease.
220. The Supreme Court held, on facts, in
Bishwanath Tea Estate (supra), that it can be demonstrably
established that the respondent was trying to enforce, through
the writ petition, the right to remove timber without the liability
to pay royalty not under the proviso to Rule 37, which was
merely an enabling provision, but on the basis of the specific Patna High Court LPA No.2158 of 2015 dt.12-05-2016
118/208
term of lease agreed to between the parties.
221. The Supreme Court, in Bishwanath Tea Estate
(supra), held that ordinarily, where a breach of contract is
complained of, a party, complaining of such breach, may sue
for specific performance of the contract, if contract is capable of
being specifically performed, or the party may sue for damages.
Such a suit would, ordinarily, be cognizable by the civil court.
The High Court, in its extraordinary jurisdiction, would not
entertain a petition either for specific performance of contract
or for recovering damages. A right to relief, flowing from a
contract, has to be claimed in a civil court, where a suit for
specific performance of contract or for damages could be filed.
In this regard, the Supreme Court, in Bishwanth Tea Estate
(supra), relied upon the case of Har Shankar v. Deputy
Excise & Taxation Commissioner, reported in (1975) 1 SCC
737, wherein the petitioners had offered their bids in the
auctions held for granting licences for the sale of liquor.
Subsequently, the petitioners moved to invalidate the auctions
challenging the power of the Financial Commissioner to grant
liquor licences. Rejecting this contention, the Constitution
Bench, at page 263 observed as under:
"16. Those who contract with open eyes must accept the burdens of the contract along with its benefits. The powers of the Financial' Commissioner to grant liquor licences by auction and to collect licence fees through the medium of auctions cannot by writ Patna High Court LPA No.2158 of 2015 dt.12-05-2016
119/208
petitions be questioned by those who, had their venture succeeded, would have relied upon those very powers to found a legal claim. Reciprocal rights and obligations arising out of contract do not depend for their enforceability upon whether a contracting party finds it prudent to abide by the terms of the contract. By such a test no contract could ever have a binding force."
222. The Supreme Court, in Bishwanth Tea Estate
(supra), already found that the subject matter, involved in the
writ petition, required evidence of facts, which could not have
been decided in writ petition. The relevant observations are
reproduced as follows;
"12....To be more specific, following facts will have to be proved for obtaining relief:
The area covered by the grant.
Felling of the trees from the area covered by the grant.
Use to which the felled timber was to be put to.
Such use will have to be one connected with the exploitation of the grant.
What is meant by the exploitation of the grant?
Could these facts be assumed without evidence? Was the High Court justified in observing that it was not Patna High Court LPA No.2158 of 2015 dt.12-05-2016
120/208
called upon to decide complicated questions of facts? Some averments in the petition were disputed. The appellant contended that clause 2 of the indenture of lease only means that if there is some use of timber which is being felled and removed from the area covered by the grant for the purpose connected with the exploitation of that very grant, then and only then the relief can be claimed under clause 2."
223. It will, thus, be seen from an analysis of
Bishwanath Tea Estate (supra) that since the facts involved
required assumption of evidence, the performance of contract
could not have been enforced without recording evidence.
Hence, the ratio laid down, in Bishwanath Tea Co. Ltd.
(supra), was that breach of contract, which requires detailed
inquiry of facts, cannot be enforced by resorting to extra
ordinary jurisdiction under Article 226.
224. I may, now, refer to the case of Life Insurance
Corporation of India v. Escorts Ltd., reported in,
MANU/SC/0015/1985, wherein a Constitution Bench held
that though the field of constitutional law, administrative law
and public law has forged ahead of the law in England,
uninhibited by the technical rules, which have hampered the
development of the English Law, and though every action of the
State or an instrumentality of the State must be informed by
reason and that, in appropriate cases, actions, uninformed by
reason, may be questioned as arbitrary in proceedings under Patna High Court LPA No.2158 of 2015 dt.12-05-2016
121/208 Article 226 or Article 32 of the Constitution, Article 14 cannot be
construed as a charter for judicial review of all State actions
and to call upon the State to account for its actions in its
manifold activities by stating reasons for such actions. The
Constitution Bench made it clear, in Escorts Ltd. (supra), that
if the action of the State is political or sovereign in character,
the court will keep away from it. The court will not debate
academic matters or concern itself with the intricacies of trade
and commerce. If the action of the State is related to
contractual obligations or obligations arising out of tort, the
court may, not, ordinarily, examine it unless the action has
some public law character attached to it. The Constitution
Bench further made it clear, in Escorts Ltd. (supra), that
broadly speaking, the court will examine actions of the State if
they pertain to the public law domain and refrain from
examining them if they pertain to the private law field, though
the difficulty will lie in demarcating the frontiers between the
public law domain and the private law field. Made it, however,
explicit the Supreme Court, in Escorts Ltd. (supra), that it is
impossible to draw the line, with precision, between the
frontiers of the public law domain and the private law field and
that the question must be decided, in each case, with reference
to the particular action, activity which the State or the
instrumentality of the State is engaged, when performing the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
122/208
action, the public law or private law character of the action and
a host of other relevant circumstances. Cautioned, however, the
Constitution Bench, in Escorts Ltd. (supra), that Article 14
cannot be used as a charter for judicial review of all actions of
the State. The relevant observations made, in this regard, in
Escorts Ltd. (supra), read as follows:
"101. It was, however, urged by the learned Counsel for the company that the Life Insurance Corporation was an instrumentality of the State and was, therefore, debarred by Article 14 from acting arbitrarily. It was, therefore, under an obligation to state to the court its reasons for the resolution once a rule nisi was issued to it. If it failed to disclose its reasons to the court, the court would presume that it had no valid reasons to give and its action was, therefore, arbitrary. The learned Counsel relied on the decisions of this Court in Sukhdev Singh; Maneka Gandhi; International Airport Authority; and Ajay Hasia. The learned Attorney General, on the other hand, contended that actions of the State or an instrumentality of the State which do not properly belong to the field of public law but belong to the field of private law are not liable to be subjected to judicial review. He relied on O'Reilly v. Mackman (1982) 3 All ER 1124; Davy v. Spelthonne (1983) 3 All ER 278; I Congress del Partido (1981) 2 All ER 1064; R. v. East Berkshire Health Authority (1984) 3 All ER 425; and Radhakrishna Agarwal and Ors. v. State of Bihar MANU/SC/0053/1977 : [1977] 3 SCR 249. While we do find considerable force in the contention of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
123/208
learned Attorney General it may not be necessary for us to enter into any lengthy discussion of the topic, as we shall presently see. We also desire to warn ourselves against readily referring to English cases on questions of constitutional law, administrative law and public law as the law in India in these branches has forged ahead of the law in England, guided as we are by our Constitution and uninhibited as we are by the technical rules which have hampered the development of the English Law. While we do not, for a moment, doubt that every action of the State or an instrumentality of the State must be informed by reason and that, in appropriate cases, actions uninformed by reason may be questioned as arbitrary in proceedings under Article 226 or Article 32 of the Constitution, we do not construe Article 14 as a charter for judicial review of State actions and to call upon the State to account for its actions in its manifold activities by stating reasons for such actions.
102. For example, if the action of the State is political or sovereign in character, the court will keep away from it. The court will not debate academic matters or concern itself with the intricacies of trade and commerce. If the action of the State is related to contractual obligations or obligations arising out of the tort, the court may not ordinarily examine it unless the action has some public law character attached to it. Broadly speaking, the court will examine actions of State if they pertain to the public law domain and refrain from examining them if they pertain to the private law field. The difficulty will lie in demarcating the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
124/208
frontier between the public law domain and the private law field. It is impossible to draw the line with precision and we do not want to attempt it. The question must be decided in each case with reference to the particular action, the activity in which the State or the instrumentality of the State is engaged when performing the action, the public law or private law character of the action and a host of other relevant circumstances. When the State or an instrumentality of the State ventures into the corporate world and purchases the shares of a company, it assumes to itself the ordinary role of a shareholder, and dons the robes of a shareholder, with all the rights available to such a shareholder. There is no reason why the State as a shareholder should be expected to state its reasons when it seeks to change the management, by a resolution of the company like any other shareholder."
225. From the above observations made in Escorts
Ltd. (supra), it becomes clear that though Article 14 cannot be
used as a charter for judicial review of all actions of the State
and that every action of the State in contractual field may not,
ordinarily, be examined by a writ court, the fact remains that
there is no absolute bar to the exercise of writ jurisdiction under
Article 226 of the Constitution of India. Whether a High Court
will exercise such a jurisdiction or not is a question, which must
be decided in each case on the basis of its own facts, though, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
125/208
generally, the High Court will not entertain if the action of the
State does not have any element of public interest involved. The question as to whether a High Court would interfere or not
would depend, in the light of the decision of the Apex Court, in
Escorts Ltd. (supra), on the nature of the action, which is
impugned in the writ petition; but the exercise of writ
jurisdiction is not possible without determining the distinction
between public law and private law character of the duty,
sought to be enforced, and a host of other relevant
circumstances.
226. Closely following the decision of the Constitution
Bench, in Escorts Ltd. (supra), is the case of Dwarkadas
Marfatia and Sons a Board of Trustees of the Port of
Bombay, reported in, [1989] 2 SCR 751. In this case, the
appellant, M/s. Dwarkadas & Sons, had been a tenant on a
portion of a land of the respondent corporation, namely,
Bombay Port Trust, for over 40 years, Bombay Port Trust
having been constituted as a statutory corporation under the
Major Ports Act. The structures, standing on the said land, were
used as a part of a rice mill. Pursuant to a Town Planning
Scheme of 1957, the plots were reconstituted and the port trust
framed a policy to let out the reconstituted plot to the person,
who was in occupation of the major portion of the plot. In terms
of this policy, the trust initiated eviction proceeding against the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
126/208
appellant by giving them one month's notice sometime in
October 1977. As the appellant had not vacated the said
structures, the trust instituted a suit in December 1977, in the
small causes court. The appellant pleaded mala fide and
favouritism and also that the one month notice was bad in law.
The trial court dismissed the suit on the ground of improper
notice and did not enter into the question of mala fide. When
the appellate court reversed the decision upholding the validity
of the notice and also held that the question of mala fide or
arbitrariness was not relevant for the eviction proceeding, a writ
petition under Article 227 was filed in the High Court. As the
High Court concurred with the decision of the appellate court,
the matter was carried to the Supreme Court.
227. In its decision, in Dwarkadas Marfatia (supra),
a Three Judge Bench of the Supreme Court, having taken note
of Rampratap Jaydayal v. Dominion of India, reported in,
MANU/MH/0096/1953: AIR 1953 Bona 170 and Escorts
Ltd. (supra) , held that though the field of letting and eviction
of tenants is, normally, governed by the Rent Act and port trust
is statutorily exempted from the operation of the Rent Act on
the basis of its public/ government character, legislative
assumption or expectation, as noted in the observations of
Chagla, C.J in Rampratap Jaydayal (supra), cannot make
such conduct a matter of contract pure and simple and that Patna High Court LPA No.2158 of 2015 dt.12-05-2016
127/208
these corporations must act in accordance with certain
constitutional conscience and whether they have so acted, must
be discernible from the conduct of such corporations. The Apex
Court clarified, in Dwarkadas Marfatia (supra), that it is not
correct to suggest that in the light of the decision in
Radhakrishna (supra), a State's contractual dealings do not
ever fall under public law domain and is not subject to judicial
review. The court, in Dwarkadas Marfatia (supra), also
clarified that even the Constitution Bench decision, in Escorts
Ltd. (supra), does not wholly exclude State's all actions, in
contractual matters, from the court's power of judicial review.
228. The Apex Court further made it clear, in
Dwarkadas Marfatia (supra), that every action/activity of the
trust, which is a State within the meaning of Article 12, must be
subject to Article 14 and must be reasonable and taken only
upon lawful and relevant grounds of public interest and
whenever there is arbitrariness in the State's action, Article 14
springs in and judicial review strikes such an action down.
Making its views emphatic, the Supreme Court further made it
clear, in Dwarkadas Marfatia (supra), that whatever be the
activity of the public authority, it should meet the test of Article
14 and that the decision in Escorts Ltd. (supra), if read
properly, does not detract from the aforesaid principles.
229. The Apex Court further made it clear, in Patna High Court LPA No.2158 of 2015 dt.12-05-2016
128/208
Dwarkadas Marfatia (supra), that every action/activity of the
trust, which is a State within the meaning of Article 12, must
be subject to Article 14 and must be reasonable and taken only
upon lawful and relevant grounds of public interest and
whenever there is arbitrariness in the State's action, Article 14
springs in and judicial review strikes such an action down.
Making its views emphatic, the Supreme Court further made it
clear, in Dwarkadas Marfatia (supra), that whatever be the
activity of the public authority, it should meet the test of Article
14 and that the decision in Escorts Ltd. (supra), if read
properly, does not detract from the aforesaid principles.
230. The observations made, in this regard, by the
Apex Court, in Dwarkadas Marfatia (supra), read as under:
"22. Our attention was drawn to the observations of this Court in Radhakrishna Agarwal and Ors. v. State of Bihar and Ors.[1977] 3 SCR
249. Reliance was also placed on the observations of this Court in Life Insurance Corporation of India v. Escorts Ltd. and Ors. 1985 Suppl. (3) SCR 909 in support of the contention that the public corporations' dealing with tenants is a contractual dealing and it is not a matter for public law domain and is not subject to judicial review. However, it is not the correct position. The Escorts' decision reiterated that every action of the State or an instrumentality of the State, must be informed by reason. Indubitably, the respondent is an organ of the State under Article 12 of the Constitution. In Patna High Court LPA No.2158 of 2015 dt.12-05-2016
129/208
appropriate cases, as was observed in the last mentioned decision, actions uninformed by reason may be questioned as arbitrary in proceedings under Article 226 or Article 32 of the Constitution. But it has to be remembered that Article 14 cannot be construed as a charter for judicial review of State action, to call upon the State to account for its actions in its manifold activities by stating reasons for such actions.
23. The contractual privileges are made immune from the protection of the Rent Act for the respondent because of the public position occupied by the respondent authority. Hence, its actions are amenable to judicial review only to the extent that the State must act validly for a discernible reason, not whimsically for any ulterior purpose. Where any special right privilege is granted to any public or statutory body on the presumption that it must act in certain manner, such bodies must make good such presumption while acting by virtue of such privileges. Judicial review to oversee if such bodies are so acting is permissible.
24. The field of letting and eviction of tenants is normally governed by the Rent Act. The port trust is statutorily exempted from the operation of Rent Act on the basis of its public/ government character. The legislative assumption or expectation as noted in the observations of Chagla, CJ in Rampratap Jaidayal's case cannot make such conduct a matter of contract pure and simple'. These corporations must act in accordance with certain constitutional conscience and whether they have so acted, must be discernible from the conduct Patna High Court LPA No.2158 of 2015 dt.12-05-2016
130/208
of such corporations. In this connection, reference may be made to the observations of this Court in S.P. Rekhi v. Union of India, reiterated in M.C. Mehta and Anr. v. Union of India and Ors. 1VIA.NU/ SC/ 0092/ 1986: [1987] 1 SCR 819, wherein at p. 148, this Court observed:
It is dangerous to exonerate corporations from the need to have constitutional conscience; and so, that interpretation, language permitting, which
makes governmental agencies, whatever their mien, amenable to constitutional limitations must be adopted by the court as against the alternative of permitting them to flourish as an imperium in imperio.
25. Therefore, Mr. Chinai was right in contending that every action/activity of the Bombay Port Trust which constituted "State" within Article 12 of the Constitution in respect of any right conferred or privilege granted by any statute is subject to Article 14 and must be reasonable and taken only upon lawful and relevant grounds of public interest. Reliance may be placed on the observations of this Court in E.P. Royappa v. State of Tamil Nadu MANU/ SC/ 0380/ 1973: (1974) ILLJ 172 SC; Maneka Gandhi v. Union of India MANU/ SC/ 0133/ 1978: /1978 12 SCR 621 Ramana Dayaram Shetty v. International Airport Authority of India and Ors.
MANU/ SC/ 0048/ 1979 Kasturi Lai Lakshmi Reddy v. State of J&K and another, MANU/ SC/ 0079/ 1980 :
[1980] 3 SCR 1338; and Ajay Hasiay. Khalid Mujib Patna High Court LPA No.2158 of 2015 dt.12-05-2016
131/208
Sehravardi and Ors.etc. MANU/ SC/ 0498/ 1980. Where there is arbitrariness in State action, Article 14 springs in and judicial review strikes such an action down. Every action of the Executive Authority must be subject to rule of law and must be informed by reason. So, whatever be the activity of the public authority, it should meet the test of Article 14. The observations in paras 101 and 102 of the Escorts' case, read properly, do not detract from the aforesaid principles.
27. We are inclined to accept the submission that every activity of a public authority, especially in the background of the assumption on which such authority enjoys immunity from the rigours of the Rent Act, must be informed by reason and guided by the public interest. All exercise of discretion or power by public authorities as the respondent, in respect of dealing with tenants in respect of which they have been treated separately and distinctly from other landlords on the assumption that they would not act as private landlords, must be judged by that standard. If a governmental policy or action even in contractual matters fails to satisfy the test of reasonableness, it would be unconstitutional.
See, the observations of this Court in Kasturi Lai Lakshmi Reddy and RamanaDayaram Shetty v. International Airport Authority of India and Ors. MANU/SC/0048/1979."
(Emphasis is supplied) Patna High Court LPA No.2158 of 2015 dt.12-05-2016
132/208
231. If the decision, in Dwarkadas Marfatia (supra),
is carefully read, it becomes more than abundantly clear that
though at the first blush, the decision, in Radhakrishna
(supra), appears to have laid down that the remedy of every
breach of contract lies in civil suits and writ jurisdiction would
never be applicable to enforce even constitutional obligations of
the State in contractual matters, the later decision of the Apex
Court, in Dwarkadas Marfatia (supra), clearly shows that
having considered the decision, in Radhakrishna (supra), and
also the Constitution Bench decision, in Escorts Ltd. (supra), it
has clearly held that there is no absolute bar to the exercise of
jurisdiction under Article 226 in a contractual matter,
particularly, when the act or conduct of the State or its
instrumentality is challenged on the anvil of Article 14. It is
also clear from Dwarkadas Marfatia (supra) that a writ court
will enforce even a contractual obligation of the State if the
breach of obligation by the State fails to satisfy the test of
reasonableness under Article 14, for, in such a case, what the
writ court would be enforcing is the constitutional duty of the
State, though such a duty might have arisen in the realm of
contractual obligation. It has been further made clear, in
Dwarkadas Marfatia (supra), that even in contractual
matters, the State's action must be reasonable, lawful and on
relevant ground of public interest.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
133/208
232. What emerges from the above discussion is
that when a writ petition is filed alleging breach of contractual
obligation by the State or its instrumentality, the High Court
shall determine whether the writ petitioner is merely
demanding to enforce his contractual rights or he has raised
some important questions of law and/or constitutional issues. If
he aims at merely enforcing his contractual rights and raises no
important question of law or constitutional issue, writ
jurisdiction will not be invoked; but if the writ petitioner raises
a constitutional issue, there is no absolute bar to the exercise
of jurisdiction under Article 226 even in a contractual matter.
This position of law was made clear in Life Insurance
Corporation of India v. Asha Goel, reported in, (2001) 2
SCC 160, wherein the court observed as under:
"10. Article 226 of the Constitution confers extraordinary jurisdiction on the High Court to issue high prerogative writs for enforcement of the fundamental rights or for any other purpose. It is wide and expansive. The Constitution does not place any fetter on exercise of the extraordinary jurisdiction. It is left to the discretion of the High Court. Therefore, it cannot be laid down as a general proposition of law that in no case the High Court can entertain a writ petition under Article 226 of the Constitution to enforce a claim under a life insurance policy. It is neither possible nor proper to enumerate exhaustively the circumstances in which such a claim can or cannot be enforced by filing a Patna High Court LPA No.2158 of 2015 dt.12-05-2016
134/208
writ petition. The determination of the question depends on consideration of several factors like, whether a writ petitioner is merely attempting to enforce his/her contractual rights or the case raises important questions of law and constitutional issues, the nature of the dispute raised; the nature of inquiry necessary for determination of the dispute, etc. The matter is to be considered in the facts and circumstances of each case. While the jurisdiction of the High Court to entertain a writ petition under Article 226 of the Constitution cannot be denied altogether, courts must bear in mind the self-imposed restriction consistently followed by High Courts all these years after the constitutional power came into existence in not entertaining writ petitions filed for enforcement of purely contractual rights and obligations which involve disputed questions of facts. The courts have consistently taken the view that in a case where for determination of the dispute raised, it is necessary to inquire into the facts for determination of which it may become necessary to record oral' evidence, a proceeding under Article 226 of the Constitution is not the appropriate forum. The position is also well settled that if the contract entered between the parties provides an alternate forum for resolution of disputes arising from the contract, then the parties should approach the forum agreed by them and the High Court in writ jurisdiction should not permit them to bypass the agreed forum of dispute resolution. At the cost of repetition it may be stated that in the above discussions we have only indicated some of the circumstances in which the High Courts Patna High Court LPA No.2158 of 2015 dt.12-05-2016
135/208
have declined to entertain petitions filed under Article 226 of the Constitution for enforcement of contractual rights and obligations; the discussions are not intended to be exhaustive. This Court from time to time disapproved of a High Court entertaining a petition under Article 226 of the Constitution in matters of enforcement of contractual rights and obligations particularly where the claim by one party is contested by the other and adjudication of the dispute requires inquiry into facts. We may notice a few such cases--Mohd. Hanif U. State of Assam MANU/ SC/ 0370/1969 : [1970] 2 SCR 197 ; Banchhanidhi Rath v. State of Orissa MANU/ SC/ 0652 / 1971 : AIR 1972 SC 843 ; Rukmanibai Gupta v. Collector, Jabalpur MANU/ SC/ 0002/ 1980 : AIR 1981 SC 479 ; Food Corporation of India v. Jagannath Dutta 1993 Suppl. (3) SCC 635; and State of H.P. v. Raja Mahendra Pal MANU/ SC/ 0227/ 1999 : [1999] 2 SCR 323."
233. The position that emerges from the
discussions in the decided cases is that, ordinarily, the High
Court should not entertain a writ petition, filed under Article
226 of the Constitution, for mere enforcement of a claim under
a contract of insurance. Where an insurer has repudiated the
claim, in case such a writ petition is filed, the High Court has to
consider the facts and circumstances of the case, the nature of
the dispute raised and the nature of the inquiry necessary to be
made for determination of the questions raised and other
relevant factors before taking a decision whether it should Patna High Court LPA No.2158 of 2015 dt.12-05-2016
136/208
entertain the writ petition or reject it as not maintainable. It
has also to be kept in mind that in case an insured or nominee
of the deceased insured is refused relief merely on the ground
that the claim relates to contractual rights and obligations and
he/she is driven to a long drawn litigation in the civil court it
will cause serious prejudice to the claimant/ other beneficiaries
of the policy. The pros and cons of the matter in the context of
the fact situation of the case should be carefully weighed and
appropriate decision should be taken. In a case where claim by
an insured or a nominee is repudiated raising a serious dispute
and the court finds the dispute to be a bona fide one which
requires oral and documentary evidence for its determination
then the appropriate remedy is a civil suit and not a writ
petition under Article 226 of the Constitution. Similarly, where
a plea of fraud is pleaded by the insurer and on examination is
found prima facie to have merit and oral and documentary
evidence may become necessary for determination of the issue
raised, then a writ petition is not an appropriate remedy.
234. Moreover, when a writ court finds that the
refusal to extend constitutional remedy of Article 226 of the
Constitution of India to enforce a contractual right or obligation
would drive a person, knocking at the doors of a writ court, to
a long drawn litigation in the civil court causing serious
prejudice to the person seeking relief against the State, the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
137/208
writ court may not, according to Asha Goel decline to interfere
in such a matter and hence, reminds the Apex Court, in Asha
Goel (supra), thus:
"The pros and cons of the matter in the context of the fact situation of the case should be carefully weighed and appropriate decision should be taken."
235. From the law, as laid down, in Asha Goel,
(supra), it becomes transparent that when non-interference by
a writ court would drive a person to a long drawn civil litigation
causing serious prejudice to him, the writ court‟s interference is
not only desirable, but even necessary. As a corollary to this
proposition of law, one can safely say that when a contractor's
dues are admitted by a State and the fact situation of a given
case satisfies the writ court that asking the contractor to take
recourse to the civil court would cause serious prejudice to the
contractor, the writ court should step in.
236. From the decision, in Asha Goel (supra),
what emerges is that ordinarily, a High Court should not
entertain a writ petition, under Article 226 of the Constitution
of India, for mere enforcement of claims under a contract of
insurance; however, the Constitution having not placed any
fetters on the exercise of extraordinary jurisdiction by the High
Court under Article 226 of the Constitution of India, it is in the
discretion of the High Court to interfere or not to interfere in a Patna High Court LPA No.2158 of 2015 dt.12-05-2016
138/208
contractual matter. No exercise of discretionary power can be
unfettered, unguided, unsettled or arbitrary, and, hence, the
position of law, on a given subject, should not be completely
unforeseen and legal decisions must have some standards or
parameters in order to enable the people at large to know as to
what the position of law, on a given subject, is. Considered
thus, exercise of jurisdiction under Article 226 of the
Constitution of India cannot be unfettered or arbitrary.
However, it is not possible to enumerate exhaustively the
circumstances in which a writ application even in contractual
matter would lie, for exercise of jurisdiction would depend upon
a considerable number of factors, such as, the question as to
whether the writ petitioner is merely attempting to enforce his
or her contractual rights or has raised important questions of
law or constitutional issues, the nature of the dispute raised
and the nature of enquiry necessary for determination of the
dispute, etc. In short, exercise of jurisdiction would depend on
the facts and circumstances of each given case. While
jurisdiction of the High Court to entertain a writ petition, under
Article 226 of the Constitution of India, cannot be denied
altogether, the courts must bear in mind the self-imposed
restrictions constitutionally followed by the High Courts not to,
ordinarily, entertain writ petitions for enforcement of purely
contractual rights and obligations, particularly, when Patna High Court LPA No.2158 of 2015 dt.12-05-2016
139/208
determination of such questions necessitates taking of oral
evidence or when the parties had agreed to resolve their
disputes arising out of the contract, in the alternative forum
selected by them.
237. I, now, turn to the case of Shrilekha
Vidyarthi (Kumari) v. State of U.P., (1991) 1 SCC 212. While considering the case of Kumari Shrilekha Vidyarthi
(supra) what may be borne in mind is that it was a case in
which the Government of Uttar Pradesh terminated, with the
help of a general order, appointments of all the government
counsel in all the districts of the State of Uttar Pradesh with
effect from 28.02.1990 and directed preparation of fresh panel
to make appointments in place of existing incumbents
irrespective of the fact whether the term of the incumbent had
expired or was subsisting. Validity of this action of the State
was challenged by way of a number of writ petitions. In the
backdrop of these facts, a Two Judge Bench of the Supreme
Court, speaking through J.S. Verma, J. (as His Lordship then
was), posed the question as to whether guarantee of non-
arbitrariness, which is basic to the rule of law under Article 14,
stands excluded from the State's action in contractual field.
238. In answer to the momentous question, posed
above, the Court made it clear, in Kumari Shrilekha
Vidyarthi (supra), that the Constitution does not envisage or Patna High Court LPA No.2158 of 2015 dt.12-05-2016
140/208
permit unfairness in State actions in any sphere of its activity. Leaving no room open for doubt, the Apex Court held, in
Kumari Shrilekha Vidyarthi (supra), that it would be alien to
the constitutional scheme to accept the argument of exclusion
of Article 14 in contractual matters. The Court, however,
hastened to add that the scope and grounds on which judicial
review would be permissible in contractual matters may be a
different matter, but contractual matters cannot be wholly
excluded from the purview of judicial review.
239. Drawing distinction between the contracts to
which the State is a party, and the contracts to which the
private parties are involved, the Court, in Kumari Shrilekha
Vidyarthi (supra), pointed out that while private parties are
concerned with their personal interest, the State, while
exercising its powers and discharging its functions, acts
indubitably for public good and in public interest, for, the
impact of every State action is also on the public interest and
this factor alone is sufficient to import, at least, the minimal
requirements of public law obligations even in the actions of
the State in contractual matters.
240. The Court also pointed out, in Kumari
Shrilekha Vidyarthi (supra), that though the scope of judicial
review in respect of disputes, falling within the domain of
contractual obligations, may be limited, the fact remains that Patna High Court LPA No.2158 of 2015 dt.12-05-2016
141/208
to the extent that a challenge is posed on the ground of
violation of Article 14 by alleging that the impugned action is
arbitrary, unfair or unreasonable, the mere fact that the
dispute also falls within the domain of contractual obligations
would not relieve the State of its obligation to comply with the
basic requirements of Article 14. To this extent, reiterated the
Court, in Kumari Shrilekha Vidyarthi (supra), the obligation
of a State is of a public character and that contractual
obligation cannot divest the person aggrieved of the guarantee
under Article 14 of non-arbitrariness at the hands of the State
in all its actions.
241. Symbolizing the nature of character of the
State, when it enters into contractual relationships, the Apex
Court made it clear, in Kumari Shrilekha Vidyarthi (supra),
that the State cannot be attributed the split personality of Dr.
Jekyll and Mr. Hyde in the contractual field so as to impress on
it all the characteristics of the State at the threshold, while
entering into a contract, and, thereafter, casting off its garb of
a State and adorn the new robe of a private body during the
subsistence of the contract enabling it thereby to act arbitrarily
subject only to the contractual obligations and the remedies
flowing from it. The requirement of Article 14 being the duty to
act fairly, justly and reasonably, there is nothing, observed the
Court, in Kumari Shrilekha Vidyarthi (supra), which militates Patna High Court LPA No.2158 of 2015 dt.12-05-2016
142/208
against the concept of requiring the State always so to act,
even in contractual matters.
242. Drawing strength for the conclusion, reached
above, from the decision in Dwarkadas Marfatia (supra), the
Court, in Kumari Shrilekha Vidyarthi (supra), further held
that if the State is unable to produce materials to justify its
action as fair and reasonable, burden on the person, alleging
arbitrariness, must be held to have been discharged and the
scope of judicial review, howsoever limited in contractual
matters, must remain open to ensure that State action is not
vitiated by the vice of arbitrariness.
243. In Kumari Shrilekha Vidyarthi (supra), the
Court also took the view that even assuming that it is
necessary to import the concept of presence of some public
element in a State action, in the realm of contractual
obligations, to attract Article 14, the fact remains that the
ultimate impact of all actions of the State or a public body
being on public interest, requisite public element is also present
in contractual matters. Held, therefore, the Court, in Kumari
Shrilekha Vidyarthi (supra), that it finds it difficult and
unrealistic to exclude from the purview of judicial review the
State actions in contractual matters after the contract has been
made, in order to test the validity of the actions of the State on
the anvil of Article 14. The relevant observations, made at Patna High Court LPA No.2158 of 2015 dt.12-05-2016
143/208
paras 21, 22, 23, 24, 28, 29, 30 and 33, in Kumari Shrilekha
Vidyarthi (supra), are reproduced hereinbelow:
"21. The Preamble of the Constitution of India resolves to secure, to all its citizens, justice, social, economic and political and equality of status and opportunity. Every State action must be aimed at achieving this goal. Part IV of the Constitution contains 'Directive Principles of State Policy' which are fundamental in the governance of the country and are aimed at securing social and economic freedoms by appropriate State action which is complementary to individual fundamental rights guaranteed in Part III for protection against excesses of State action, to realise the vision in the Preamble. This being the philosophy of the Constitution, can it be said that it contemplates exclusion of Article 14non-arbitrariness which is basic to rule of law from State actions in contractual field when all actions of the State are meant for public good and expected to be fair and just? We have no doubt that the Constitution does not envisage or permit unfairness or unreasonableness in State actions in any sphere of its activity contrary to the professed ideals in the Preamble. In our opinion, it would be alien to the constitutional scheme to accept the argument of exclusion of Article 14 in contractual matters. The scope and permissible grounds of judicial review in such matters and the relief which may be available are different matters but that does not justify the view of its total exclusion. This is more so when the modern trend is also to examine the unreasonableness of a term in such contracts where the bargaining power is unequal so that these are not negotiated contracts but Patna High Court LPA No.2158 of 2015 dt.12-05-2016
144/208
standard form contracts between unequals.
22. There is an obvious difference in the contracts between private parties and contracts to which the State is a party. Private parties are concerned only with their personal interest whereas the State while exercising its powers and discharging its functions acts indubitably, as is expected of it, for public good and in public interest. The impact of every State action is also on public interest. This factor alone is sufficient to import at least the minimal requirements of public law obligations and impress with this character the contracts made by the State or its instrumentality. It is a different matter that the scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes. However, to the extent, challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also falls within the domain of contractual obligations would not relieve the State of its obligation to comply with the basic requirements of Article 14. To this extent, the obligation is of a public character invariably in every case irrespective of there being any other right or obligation in addition thereto. An additional contractual obligation cannot divest the claimant of the guarantee under Article 14 of non- arbitrariness at the hands of the State in any of its actions.
23. Thus, in a case like the present, if it is shown that Patna High Court LPA No.2158 of 2015 dt.12-05-2016
145/208
the impugned State action is arbitrary and, therefore, violative of Article 14 of the Constitution, there can be no impediment in striking down the impugned act irrespective of the question whether an additional right, contractual or statutory, if any, is also available to the aggrieved persons.
24. The State cannot be attributed the split personality of Dr. Jekyll and Mr. Hyde in the contractual field so as to impress on it all the characteristics of the State at the threshold while making a contract requiring it to fulfil the obligation of Article 14 of the Constitution and thereafter permitting it to cast off its garb of State to adorn the new robe of a private body during the subsistence of the contract enabling it to act arbitrarily subject only to the contractual obligations and remedies flowing from it. It is really the nature of its personality as State which is significant and must characterize all its actions, in whatever field, and not the nature of function, contractual or otherwise, which is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters. There is a basic difference between the acts of the State which must invariably be in public interest and those of a private individual, engaged in similar activities, being primarily for personal gain, which may or may not promote public interest. Viewed in this manner, in which we find no conceptual difficulty or anachronism, we find no reason why the requirement of Article 14 should not extend Patna High Court LPA No.2158 of 2015 dt.12-05-2016
146/208
even in the sphere of contractual matters for regulating the conduct of the State activity.
28. Even assuming that it is necessary to import the concept of presence of some public element in a State action to attract Article 14 and permit judicial review, we have no hesitation in saying that the ultimate impact of all actions of the State or a public body being undoubtedly on public interest, the requisite public element for this purpose is present also in contractual matters. We, therefore, find it difficult and unrealistic to exclude the State actions in contractual matters, after the contract has been made, from the purview of judicial review to test its validity on the anvil of Article 14.
29. It can no longer be doubted at this point of time that Article 14 of the Constitution of India applies also to matters of governmental policy and if the policy or any action of the government, even in contractual matters, fails to satisfy the test of reasonableness, it would be unconstitutional. See Ramana Dayaram Shetty v. International Airport Authority of India MANU/SC/0048/1979 : (1979) II LLJ 217 SC and Kasturi Lal Lakshmi Reddy v. State of Jammu and Kashmir MANU/SC/0079/1980 : [1980] 3 SCR 1338 . In Col. A.S. Sangwan v. Union of India 1980 Suppl. SCC 559 : 1981 SCC (L&S) 378 while the discretion to change the policy in exercise of the executive power, when not trammelled by the statute or rule, was held to be wide, it was emphasized as imperative and implicit in Article 14 of the Constitution that a change in policy must be made fairly and should not give the impression that it was so done arbitrarily or by any Patna High Court LPA No.2158 of 2015 dt.12-05-2016
147/208
ulterior criteria. The wide sweep of Article 14 and the requirement of every State action qualifying for its validity on this touchstone, irrespective of the field of activity of the State, has long been settled. Later decisions of this Court have reinforced the foundation of this tenet and it would be sufficient to refer only to two recent decisions of this Court for this purpose.
30. In Divarkadas Marfatia and Sons v. Board of Trustees of the Port of Bombay MANU/SC/0330/1989 : [1989] 2 SCR 751 , the matter was re-examined in relation to an instrumentality of the State for applicability of Article 14 to all its actions. Referring to the earlier decisions of this Court and examining the argument for applicability of Article 14, even in contractual matters, Sabyasachi Mukharji, J. (as the learned Chief Justice then was), speaking for himself and Kania, J. reiterated that: (SCC p. 304, para
22) "every action of the State or an instrumentality of the State, must be informed by reason...actions uninformed by reasons may be questioned as arbitrary in proceedings under Article 226 or Article 32 of the Constitution". Ranganathan, J. did not express any opinion on this point but agreed with the conclusion of the other learned judges on the facts of the case. It is obvious that the conclusion on the facts of the case could not be reached by Ranganathan, J. without examining them and this could be done only on the basis that it was permissible to make the judicial review. Thus, Ranganathan, J. also applied that principle without saying so. In view of the wide ranging and, in essence, all pervading sphere of State activity in discharge of its welfare functions, the question Patna High Court LPA No.2158 of 2015 dt.12-05-2016
148/208
assumes considerable importance and cannot be shelved. The basic requirement of Article 14 is fairness in action by the State and we find it difficult to accept that the State can be permitted to act otherwise in any field of its activity, irrespective of the nature of its functions when it has the uppermost duty to be governed by the rule of law. Non-arbitrariness, in substance, is only fair play in action. We have no doubt that this obvious requirement must be satisfied by every action of the State or its instrumentality in order to satisfy the test of validity.
33. No doubt, it is true, as indicated by us earlier, that there is a presumption of validity of the State action and the burden is on the person who alleges violation of Article 14 to prove the assertion. However, where no plausible reason or principle is indicated nor is it discernible and the impugned State action, therefore, appears to be ex facie arbitrary, the initial burden to prove the arbitrariness is discharged shifting onus on the State to justify its action as fair and reasonable. If the State is unable to produce material to justify its action as fair and reasonable, the burden on the person alleging arbitrariness must be held to be discharged. The scope of judicial review is limited as indicated in Dwarkadas Marfatia case to oversee the State action for the purpose of satisfying that it is not vitiated by the vice of arbitrariness and no more. The wisdom of the policy or the lack of it or the desirability of a better alternative is not within the permissible scope of judicial review in such cases. It is not for the courts to recast the policy or to substitute it with another which is considered to be more appropriate, once the attack Patna High Court LPA No.2158 of 2015 dt.12-05-2016
149/208
on the ground of arbitrariness is successfully repelled by showing that the act which was done, was fair and reasonable in the facts and circumstances of the case. As indicated by Diplock, LJ in Council for Civil Services Union v. Minister of Civil Service (1984) 3 All ER 935 the power of judicial review is limited to the grounds of illegality, irrationality and procedural impropriety. In the case of arbitrariness, the defect of irrationality is obvious."
244. What emerges from the observations made, in
Kumari Shrilekha Vidyarthi (supra), is that even after having
entered into a contract, the State cannot act arbitrarily,
unreasonably or unfairly merely because of the fact that its
actions are in the realm of a contract.
245. In the case of Biman Krishna Bose v. United
India Insurance Co. Ltd., (2001) 6 SCC 477, the appellant
and his wife had taken a mediclaim policy from the United India
Insurance Company. During the subsistence of insurance policy,
the wife of the appellant fell ill and, on the advice of doctor, she
was admitted to hospital and, for her treatment, a certain
amount was spent. When the appellant staked a claim with the
Insurance Company,' it refused to honour the bill leading a
series of litigations before the Consumer Forum. Eventually,
when the matter went to the Supreme Court, a direction was
given to the Insurance Company to pay Rs 20,000.00 to the
appellant. In the meantime, the Insurance policy fell due for Patna High Court LPA No.2158 of 2015 dt.12-05-2016
150/208
renewal. Under such circumstances, the appellant sent a letter
along with a cheque of Rs 1,796.00 to the Insurance Company
requesting for renewal of his existing mediclaim policy.
However, the Insurance Company declined to renew the
mediclaim policy as per the advice of the competent authority
of the Company.
246. Under the aforesaid circumstances, the appellant
filed a writ petition, under Article 226 of the Constitution before
the Calcutta High Court, challenging the order passed by the
respondent Insurance Company refusing to renew the
mediclaim policy. The said writ petition was allowed and the
order, refusing to renew the policy, was set aside and a
direction was issued to the Insurance Company to renew the
mediclaim policy earlier taken out by the appellant. Aggrieved,
the Insurance Company filed an appeal against the judgment of
learned Single Judge. The Division Bench of the Calcutta High
Court while agreeing with the view taken by the learned Single
Judge, substantially, dismissed the appeal; yet, the High Court
directed the appellant to take a fresh mediclaim policy on the
ground that the renewal of mediclaim policy cannot be granted
with retrospective effect, as the period, for which renewal, was
required has already expired. It is against this part of that the
order the appellant preferred an appeal to the Supreme Court.
247. The Supreme Court held, in Biman Krishna Patna High Court LPA No.2158 of 2015 dt.12-05-2016
151/208 Bose (supra), that where an insurance company under the
provisions of the General Insurance Business (Nationalisation)
Act, 1972, has assumed monopoly in the business of general
insurance in the country and, thus, acquired the trappings of
the "State" being other authorities under Article 12 of the
Constitution. It must satisfy the requirement of reasonableness
and fairness, while dealing with its customers. Even in an area
of contractual relations, observed the Supreme Court, in Biman
Krishna Bose (supra), that the State and its instrumentalities
are enjoined with the obligations to act with fairness and, in
doing so, can take into consideration only the relevant materials
and that they must not take any irrelevant and extraneous
consideration, while arriving at a decision. Further observed the
Supreme Court, in Biman Krishna Bose (supra), that
arbitrariness should not appear in their actions or decisions of
the State or its instrumentalities.
248. Biman Krishna Bose (supra) can be considered
as an authority on the point that State, in its contractual
obligations, cannot take an arbitrary decision; rather, the
decision must be taken considering only relevant materials
devoid of any arbitrariness.
249. In the case of ABL International Ltd. v.
Export Credit Guarantee Corpn. of India Ltd., (2004) 3
SCC 553, the facts were that there was an export contract Patna High Court LPA No.2158 of 2015 dt.12-05-2016
152/208
between two companies wherein Kazakhstan Government was
also involved. In this regard the appellants had approached the
respondent, Export Credit Guarantee Corporation of India Ltd,
(EGCIL, in short) for a risk cover, which was granted. Later on,
upon the failure of Kazakhstan Government to fulfil its
guarantee, the appellants made a claim before the first
respondent, which had covered the said risk of compensating
the loss. EGCIL, however, repudiated the claim on the ground
that the appellants had changed the terms of the contract of
payment without first consulting it and, therefore, it had no
obligation to compensate the appellants for the loss suffered by
it.
250. The appellant, then, filed a writ petition before
the Calcutta High Court, inter alia, praying for quashing of the
letters of repudiation issued by the EGCIL with consequential
direction to the first respondent to make payment of the dues
to it under the contract of insurance. The learned Single Judge
came to the conclusion that though the dispute between the
parties arose out of a contract, EGCIL, being a State for the
purpose of Article 12, was bound by the terms of the contract
and, therefore, a writ was maintainable for such non-
performance, and, upon considering the arguments of the
parties, with regard to the liability under the contract of
insurance, allowed the writ petition and issued the writ and Patna High Court LPA No.2158 of 2015 dt.12-05-2016
153/208
directions as prayed for by the appellants in the writ petition.
251. In an appeal filed by the EGCIL before the
Appellate Bench of the Calcutta High Court, the Bench reversed
the findings of the learned single Judge and held that the claim
of the appellant, involving disputed questions of fact, cannot be
adjudicated in a writ proceeding under Article 226 of the
Constitution; hence, the judgment of the learned single Judge
was set aside.
252. In the Supreme Court, EGCIL carried the same
arguments on which the Division Bench of the Calcutta High
Court had ruled. It was argued that the subject-matter is a
dispute arising out of a contract and is not a matter falling
under the purview of administrative law. It was also argued that
the doctrine of fairness and reasonableness applies only in the
exercise of statutory or administrative actions of a State and
not in the exercise of a contractual obligation and issues, arising
out of contractual matters, will have to be decided on the basis
of the law of contract and not on the basis of the administrative
law. It was further argued that at the most, in matters,
involving statutory contracts, where action of the State involves
a public duty, a writ may lie; but in the instant case, the
contract was neither a statutory contract nor did the duty of the
EGCIL, under the contract, have any public law element
involved in it.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
154/208
253. In view of the submissions made by the EGCIL,
the same question, once again, stared at the Supreme Court as
to whether a writ petition, under Article 226 of the Constitution
of India, is maintainable to enforce a contractual obligation of
the State or its instrumentality by an aggrieved party.
254. Placing reliance on K.N. Guruswamy v. State
of Mysore, (AIR 1954 SC 592), the Supreme Court held that
it is clear from its observations, in K.N. Guruswamy (supra),
that on a given set of facts, if a State is found to have acted in
an arbitrary manner even in a matter of contract, an aggrieved
party can approach by way of writ under Article 226 of the
Constitution of India and the Court, depending on facts of the
case, is empowered to grant relief.
255. Having taken note of the case of Ram Sanehi
Singh (supra), which followed K.N. Guruswamy (supra) and
also Gujarat State Financial Corporation v. Lotus Hotels
Pvt. Ltd. reported in MANU/SC/0036/1983 : AIR 1983 SC 848 ,
which followed Ramana Dayaram Shetty v. International
Airport Authority of India, reported in MANU/SC/0048/1979
: (1979) II LLJ 217 SC and, then, having referred to the case of
Escorts Ltd. (supra), the court, in ABL International Ltd.
(supra), has pointed out that the decision in Escorts Ltd.
(supra) does not lay down, as a rule, that in matters of
contract, the courts' jurisdiction under Article 226 stands wholly Patna High Court LPA No.2158 of 2015 dt.12-05-2016
155/208
ousted. On the contrary, points out the Supreme Court, in ABL
International Ltd. (supra), the Constitution Bench's use, in
Escorts Ltd. (supra), of the words 'court may not ordinarily
examine it unless the action has some public law character
attached to it' indicates that in a given case, on the existence of
the required factual matrix, a remedy under Article 226 will be
available.
256. Having analysed several other pronouncements
governing the field, the Supreme Court, in ABL International
Ltd. (supra), laid down the following legal principles:
(a) In an appropriate case, a writ petition as against a State or an instrumentality of a State, arising out of a contractual obligation, is maintainable.
(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable.
(Emphasis is added)
257. Striking, however, a word of caution, the
Supreme Court, in ABL International Ltd. (supra), held that
while entertaining an objection as to the maintainability of a
writ petition, under Article 226 of the Constitution of India, the
court should bear in mind the fact that the power to issue Patna High Court LPA No.2158 of 2015 dt.12-05-2016
156/208
prerogative writs, under Article 226 of the Constitution, is
plenary in nature and is not limited by any other provisions of
the Constitution. The High Court, having regard to the facts of
the case, has a discretion to entertain or not to entertain a writ
petition. The Court has imposed upon itself certain restrictions
in the exercise of this power and this plenary power of the High
Court to issue a prerogative writ will not, normally, be exercised
by the Court to the exclusion of other available remedies unless
such action of the State or its instrumentality is arbitrary and
unreasonable so as to violate the constitutional mandate of
Article 14 or for other valid and legitimate reasons for which the
Court thinks it necessary to exercise the said jurisdiction.
258. It will be seen that the decision, in ABL
International Ltd. (supra), follows the line of reasoning as
propounded in Shrilekha Vidyarthi (supra).
259. The relevant observations, appearing in ABL
International Ltd (supra), are being reproduced hereinbelow:
"27. From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:
In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable. Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
157/208
A writ petition involving a consequential relief of monetary claim is also maintainable.
28. However, while entertaining an objection as to the maintainability of a writ petition under Article 226 of the Constitution of India, the court should bear in mind the fact that the power to issue prerogative writs under Article 226 of the Constitution is plenary in nature and is not limited by any other provisions of the Constitution. The High Court having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. The Court has imposed upon itself certain restrictions in the exercise of this power. (See Whirlpool Corpn. V. Registrar of Trade Marks.) And this plenary right of the High Court to issue a prerogative writ will not normally be exercised by the Court to the exclusion of other available remedies unless such action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the Court thinks it necessary to exercise the said jurisdiction."
(Emphasis is supplied)
260. In the case of Gujarat State Financial
Corpn. v. Lotus Hotels (P) Ltd., (1983) 3 SCC 379, the
question before the Supreme Court was whether a writ of
mandamus can be issued for enforcement of contractual
obligations. The facts of this case were that respondent had
applied before the appellant for financial assistance to set up a
5 star hotel. The terms and conditions were settled and the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
158/208
respondent wrote a letter accepting the terms and conditions
on which the Corporation had agreed to advance the loan. As a
part of the deal, the Company had to create an equitable
mortgage in favour of the Corporation for securing the loan. All
the documentations had taken place for the purpose of loan
and, in order to materialize the project, the respondent
invested huge sum of money for the project. Later, due to
complaints against the promoter of the company, the appellant
refused to advance the loan on the ground that loan was
dependent on refinance, by the Industrial Development Bank of
India and since the said Bank has refused to refinance it would
not be possible to advance the loan to the respondent.
261. Ultimately, the respondent moved a petition
under Article 226 of the Constitution in the High Court of
Gujarat. A learned Single Judge issued a mandamus directing
the appellant to disburse the promised loan to the Company,
forthwith, in accordance with its letter of offer followed by the
agreement. The appellant Corporation preferred a Letters
Patent Appeal. The Division Bench, hearing the Letters Patent
Appeal, agreed with the conclusion reached by the learned
Single Judge and dismissed the appeal.
262. In the Supreme Court, one of the contentions
raised by the appellant, Gujarat State Financial Corpn. v.
Lotus Hotels (P) Ltd. (supra), was that the dispute, raised in Patna High Court LPA No.2158 of 2015 dt.12-05-2016
159/208
the writ, falls within the realm of contract and at best, the
Corporation can be charged with breach of contract for which
the remedy was by way of damages or any other remedy
available to the respondent for breach of contract; but, in no
case, a writ of mandamus can be issued compelling the
Corporation to perform its part of the contract.
263. Repelling the arguments, the Supreme Court
held, Gujarat State Financial Corpn. v. Lotus Hotels (P)
Ltd. (supra), that it is too late in the day to contend that the
instrumentality of the State, which would be "other authority"
under Article 12 of the Constitution, can commit breach of a
solemn undertaking on which other side has acted and, then,
contend that the party, suffering by the breach of contract,
may sue for damages, but cannot compel specific performance
of the contract.
264. It further held that in the back drop of
incontrovertible fact situation, the principle of promissory
estoppel would also come into play and, subsequently, placed
reliance on the case of Motilal Padampat Sugar Mills Co.
(P) Ltd. v. State of U.P, (1979) 2 SCC 409. The
observations, in Motilal (supra), were reproduced as follows;
8. "The true principle of promissory estoppel, therefore, seems to be that where one party has by his words of conduct made to the other a clear and unequivocal promise which is intended to create legal relations or affect a legal relationship Patna High Court LPA No.2158 of 2015 dt.12-05-2016
160/208
to arise in the future, knowing or intending that it would be acted upon by the other party to whom the promise is made and it is in fact so acted upon by the other party, the promise would be binding on the party making it and he would not be entitled to go back upon it, if it would be inequitable to allow him to do so having regard to the dealings which have taken place between the parties, and this would be so irrespective of whether there is any pre-existing relationship between the parties or not."
265. The concluding remarks, in Lotus Hotels
(supra), are very important, wherein the Supreme Court held
that if appellant entered into a solemn contract in discharge
and performance of its statutory duty and the respondent acted
upon it, the statutory corporation cannot be allowed to act
arbitrarily so as to cause harm and injury, flowing from its
unreasonable conduct, to the respondent. In such a situation,
the court is not powerless from holding the appellant to its
promise and it can be enforced by a writ of mandamus
directing it to perform its statutory duty. A petition, under
Article 226 of the Constitution, would certainly lie to direct
performance of a statutory duty by "other authority" as
envisaged by Article 12 and accordingly, the High Court was
fully justified in issuing a writ of mandamus to disburse the
loan.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
161/208
266. The relevant observations, appearing in
Gujarat State Financial Corpn. v. Lotus Hotels (P) Ltd.,
(supra), are quoted as follows;
"13. Now if appellant entered into a solemn contract in discharge and performance of its statutory duty and the respondent acted upon it, the statutory corporation cannot be allowed to act arbitrarily so as to cause harm and injury, flowing from its unreasonable conduct, to the respondent. In such a situation, the court is not powerless from holding the appellant to its promise and it can be enforced by a writ of mandamus directing it to perform its statutory duty. A petition under Article 226 of the Constitution would certainly lie to direct performance of a statutory duty by "other authority"
as envisaged by Article 12.
14. The High Court accordingly was fully justified in issuing a writ of mandamus to disburse the loanand therefore the appeal fails."
267. In the case of United India Insurance Co.
Ltd. v. Manubhai Dharmasinhbhai Gajera, (2008) 10 SCC
404, the Supreme Court had the occasion to deal with various
grievances of the public with respect to their Insurance claims.
268. The Supreme Court, while dwelling on the role of
State and its instrumentalities, held, in Manubhai
Dharmasinhbhai Gajera (supra), that one important facet of
the matter, which must be taken note of, is the duty, on the
part of a State, to act fairly. Such a fair dealing is expected at Patna High Court LPA No.2158 of 2015 dt.12-05-2016
162/208
the hands of State within the meaning of Article 12 of the
Constitution of India. It further held that there cannot be any
doubt whatsoever that Article 14 of the Constitution of India,
which encompasses, within its fold, obligations on the part of
the State to act fairly, operates also in the contractual field.
269. The other important aspect of the case of
Manubhai Dharmasinhbhai Gajera (supra) was that the
Supreme Court analysed several previous cases of Supreme
Court, which dealt with the issue of contractual obligations of
State.
270. Among the various cases analyzing, in
Manubhai Dharmasinhbhai Gajera (supra), one was the
case of Excise Commissioner vs. lssac Peter, (1994) 4 SCC
450. It was pointed out that a bare perusal of the decision
would show that the same was rendered in the context of
contracts entered into between the State and its citizens
pursuant to public auction of tenders or by negotiation. The
respondents therein sought to get new term incorporated in the
contract on the specious plea of fairness. The said plea was
rightly rejected. The fact, however, remains that the ratio, in
Issac (supra), is not applicable to the facts of the present case
not because the duty to act fairly on the part of a State has no
application in the field of a contract, but the same would not
apply for the purpose of alterations or modifications of a term of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
163/208
contract.
271. Elaborating further, on the contention that the
writ court would, ordinarily, not grant specific performance of a
contract even if it is found that there exists a renewal clause or
there has been a breach of contract on the part of the appellant
the Supreme Court observed, in Manubhai Dharmasinhbhai
Gajera (supra), that, ordinarily, it is so. A writ of mandamus
shall not issue in case of a breach of contract. The court shall
also not, ordinarily, issue a writ of mandamus directing a party
to perform a specific performance of the contract in exercise of
its writ jurisdiction, however, as would be noticed that this is
the ordinary law as has been held in Hardesh Ores (P) Ltd. v.
Hede & Co. (2007) 5 SCC 614, and Divl. Forest Officer v.
Bishwanath Tea Co. Ltd. (1981) 3 SCC 238. In
Bishwanath Tea Co. (supra), the Supreme Court had used the
word "ordinarily" whereas Hardesh (supra), was a case arising
out of a civil suit. The question, which arose therein was as to
whether exercise of option for renewal by company was itself
sufficient where the execution of a fresh document is necessary.
272. The Supreme Court, thereafter, in Manubhai
Dharmasinhbhai Gajera (supra), went on to observe that
while determining a lis having public law domain, the courts
would be entitled to take a broader view. It would not consider
it to be a case involving contract-qua-contract question only. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
164/208
Even cases, involving contracts, may be determined by the High
Court in exercise of its jurisdiction tinder Article 226 of the
Constitution of India.
273. Coming, now, to the case of Central Bank of
India v. Devi Ispat Ltd., (2010) 11 SCC 186, I may point
out that it related to a dispute between an individual with
respect to non-furnishing of "No objection certificate" by the
Bank. As the facts reveal, in terms of the advice of the
appellant Bank, the respondent had shifted its account to
another Bank and all pending dues with the appellant Bank
were cleared. The respondent, thereafter, applied for a return of
the security documents and, for issuance of "no-objection
certificate" and "no-dues certificate". Thereafter, the
respondent filed a writ petition before the Calcutta High Court.
A learned Single Judge of the High Court allowed the writ
petition and directed the appellant Bank to release the security
documents. Challenging the said decision, the appellant Bank
filed an appeal before the Division Bench of the High Court but
the appeal was dismissed.
274. The argument, before the Supreme Court, in
Devi Ispat Ltd, (supra), was that the direction of the learned
Single Judge, affirmed by the Division Bench, for return of the
title deeds deposited by the respondent Company, as a
security, cannot be a subject-matter of Article 226 of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
165/208
Constitution of India and that the right to retain a mortgage
deed is a civil dispute and proper forum is the Debts Recovery
Tribunal or civil court.
275. Appreciating the submissions of the appellant in
the light of previous pronouncements of the Supreme Court, it
was held, in Devi Ispat (supra), that it is settled law that the
disputes, relating to interpretation of terms and conditions of a
contract, could not be examined/challenged or agitated in a
petition filed under Article 226 of the Constitution. It is a matter
for adjudication by a civil court or in arbitration, if provided for
in the contract or before DRT or under the Securitisation Act.
However, when the relief, sought for, does not relate to
interpretation of any terms of contract, the Bank being a
nationalised bank, a writ court can issue appropriate direction.
276. What follows from the judgment of Devi Ispat
(supra) is that when a contractual dispute against the State is
raised in a writ, then, the writ Court would have jurisdiction to
pass necessary direction provided that the relief sought for does
not relate to interpretation of any terms of contract.
277. Eventually, the Supreme Court, in Devi Ispat
(supra), having discussed several cases, most of which have
been discussed hereinbefore, laid down the following principles:
(a) in the contract, if there is a clause for arbitration,
normally, a writ court should not invoke its Patna High Court LPA No.2158 of 2015 dt.12-05-2016
166/208
jurisdiction;
(b) the existence of effective alternative remedy,
provided in the contract itself, is a good ground to
decline to exercise its extraordinary jurisdiction
under Article 226; and
(c) if the instrumentality of the State acts contrary to
the public good, public interest, unfairly, unjustly,
unreasonably discriminatory and violative of Article
14 of the Constitution of India in its contractual or
statutory obligation, writ petition would be
maintainable. However, a legal right must exist and
corresponding legal duty on the part of the State and
if any action on the part of the State is wholly unfair
or arbitrary, writ courts can exercise their power. In
the light of the legal position, writ petition is
maintainable even in contractual matters, in the
circumstances mentioned in the earlier paragraphs.
278. The relevant paragraph of Devi Ispat (supra),
containing the directions, is reproduced as follows;
"28. It is clear that (a) in the contract if there is a clause for arbitration, normally, a writ court should not invoke its jurisdiction; (b) the existence of effective alternative remedy provided in the contract itself is a good ground to decline to exercise its extraordinary jurisdiction under Article 226; and (c) if the instrumentality of the State acts contrary to the public Patna High Court LPA No.2158 of 2015 dt.12-05-2016
167/208
good, public interest, unfairly, unjustly, unreasonably discriminatory and violative of Article 14 of the Constitution of India in its contractual or statutory obligation, writ Petition would be maintainable. However, a legal right must exist and corresponding legal duty on the part of the State and if any action on the part of the State is wholly unfair or arbitrary, writ courts can exercise their power. In the light of the legal position, writ petition is maintainable even in contractual matters, in the circumstances mentioned in the earlier paragraphs."
279. In a recent decision rendered by the Supreme
Court in the case of State of Kerala v. M.K. Jose, (2015) 9
SCC 433, the Supreme Court has taken into consideration all
the cases, discussed hereinbefore, and has held that it depends
upon facts of each case, under what circumstances contractual
claim or challenge to violation of contract can be sustained in a
writ court.
280. Having discussed the trend of authorities
discussed hereinbefore, the following principles may be suitably
culled out;
(a) Where a petitioner makes a grievance of breach of promise on the part of the State in cases, where, on assurance or promise made by the State, he has acted to his prejudice and predicament, but the agreement is short of a contract within the meaning of Article 299 of the Constitution, a writ petition would not be maintainable. Radhakrishna (supra).
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
168/208
(b) Where for granting relief, disputed questions of fact would be required to be gone into a writ cannot be maintained Biswanath T. E. (supra).
(c) If the right to relief arose out of an alleged breach of contract, because of any breach of duty imposed upon a statutory power, a writ petition, under Article 226, would be maintainable Ram Sanehi Singh, (supra)
(d) If appellant entered into a solemn contract in discharge and performance of its statutory duty and the respondent acted upon it, the statutory corporation cannot be allowed to act arbitrarily so as to cause harm and injury, flowing from its unreasonable conduct, to the respondent. In such a situation, the court is not powerless from holding the appellant to its promise and it can be enforced by a writ of mandamus directing it to perform its statutory duty. A petition under Article 226 of the Constitution would certainly lie to direct performance of a statutory duty by "other authority"
as envisaged by Article 12 Lotus Hotel (supra)
(e) If challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also falls within the domain of contractual obligations would not relieve the State of its obligation to comply with the basic requirements of Article 14. Shrilekha Vidyarthi (supra)
(f) The ultimate impact of all actions of the State or a Patna High Court LPA No.2158 of 2015 dt.12-05-2016
169/208
public body being undoubtedly on public interest, the requisite public element for this purpose is present also in contractual matters and, hence, it is difficult and unrealistic to exclude the State actions in contractual matters, after the contract has been made, from the purview of judicial review to test its validity on the anvil of Article 14. Shrilekha Vidyarthi (supra)
(g) The State, in its contractual obligations, cannot take an arbitrary decision; rather, the decision must be taken considering only relevant materials devoid of any arbitrariness Biman Krishna Bose (supra)
(h) In an appropriate case, a writ petition, as against a State or an instrumentality of a State arising out of a contractual obligation, is maintainable. ABL International (supra)
(i) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule. ABL International (supra)
(j) A writ petition involving a consequential relief of monetary claim is also maintainable. ABL International (supra)
(k) If in a contract, there is a clause for arbitration, a writ court should not invoke, normally, its jurisdiction;
Devi Ispat (supra)
(l) The existence of effective alternative remedy provided Patna High Court LPA No.2158 of 2015 dt.12-05-2016
170/208
in the contract itself is a good ground to decline to exercise its extraordinary jurisdiction under Article
226. Devi Ispat, (supra)
(m) If the instrumentality of the State acts contrary to the public good, public interest, unfairly, unjustly, unreasonably discriminatory and violative of Article 14 of the Constitution of India in its contractual or statutory obligation, writ petition would be maintainable. However, a legal right must exist and corresponding legal duty on the part of the State and if any action on the part of the State is wholly unfair or arbitrary, writ courts can exercise their power. In the light of the legal position, writ petition is maintainable even in contractual matters. Devi Ispat, (supra)
281. Having laid down the general principles, which
governs a writ involving contractual matters, it would, now, be
necessary to adjudge the appeals in the light of attending facts.
ACTION OF THE RESPONDENTS: WHETHER ARBITRARY?
ROLE OF RESPONDENT CORPORATION
282. It has been alleged by the writ petitioner that
action of the respondents, all throughout, have been arbitrary,
unfair and prejudicial to the writ petitioner. It, therefore, needs
to be examined whether the action of the respondents, in the
course of contract with the writ petitioner, has been arbitrary so
as to attract a violation of Article 14 of the Constitution. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
171/208
283. In the case of Shrilekha Vidyarthi (supra), the
Supreme Court, while dealing with the aspects of arbitrariness,
held that every State action, in order to survive, must not be
susceptible to the vice of arbitrariness, which is the crux of
Article 14 of the Constitution and basic to the rule of law, the
system, which governs us. Arbitrariness is the very negation of
the rule of law. Satisfaction of this basic test, in every State
action, is sine qua non to its validity and, in this respect, the
State cannot claim comparison with a private individual even in
the field of contract. This distinction between the State and a
private individual, in the field of contract, has to be borne in
mind.
284. Adding further, the Supreme Court, in Shrilekha
Vidyarthi (supra), held that the meaning and true import of
arbitrariness is more easily visualized than precisely stated or
defined. The question, whether an impugned act is arbitrary or
not, is ultimately to be answered on the facts and in the
circumstances of a given case. An obvious test to apply is to
see whether there is any discernible principle emerging from
the impugned act and if so, does it satisfy the test of
reasonableness. Where a mode is prescribed for doing an act
and there is no impediment in following that procedure,
performance of the act otherwise and in a manner, which does
not disclose any discernible principle, which is reasonable, may Patna High Court LPA No.2158 of 2015 dt.12-05-2016
172/208
itself attract the vice of arbitrariness. Every State action must
be informed by reason and it follows that an act, uninformed by
reason, is arbitrary. Rule of law contemplates governance by
laws and not by humour, whims or caprices of the men to
whom the governance is entrusted for the time being. It is trite
that 'be you ever so high, the laws are above you'. This is what
men in power must remember always.
285. It would be proper to reproduce the relevant
paragraphs, in Shrilekha Vidyarthi (supra), which read as
follows;
"35. It is now too well settled that every State action, in order to survive, must not be susceptible to the vice of arbitrariness which is the crux of Article 14 of the Constitution and basic to the rule of law, the system which governs us. Arbitrariness is the very negation of the rule of law. Satisfaction of this basic test in every State action is sine qua non to its validity and in this respect, the State cannot claim comparison with a private individual even, in the field of contract. This distinction between the State and a private individual in the field of contract has to be borne in the mind.
36. The meaning and true import of arbitrariness is more easily visualized than precisely stated or defined. The question, whether an impugned act is arbitrary or not, is ultimately to be answered on the facts and in the circumstances of a given case. An obvious test to apply is to see whether there is any discernible principle emerging from the impugned act Patna High Court LPA No.2158 of 2015 dt.12-05-2016
173/208
and if so, does it satisfy the test of reasonableness. Where a mode is prescribed for doing an act and there is no impediment in following that procedure, performance of the act otherwise and in a manner which does not disclose any discernible principle which is reasonable, may itself attract the vice of arbitrariness. Every State action must be informed by reason and it follows that an act uninformed by reason, is arbitrary. Rule of law contemplates governance by laws and not by humour, whims or caprices of the men to whom the governance is entrusted for the time being. It is trite that 'be you ever so high, the laws are above you'. This is what men in power must remember, always."
(Emphasis supplied)
286. On the mode of proving arbitrariness, the
Supreme Court, in Shrilekha Vidyarthi (Kumari) (supra),
held that it is for the person alleging arbitrariness, who has to
prove his allegation. This can be done by showing, in the first
instance, that the impugned State action is uninformed by
reason inasmuch as there is no discernible principle on which it
is based or it is contrary to the prescribed mode of exercise of
the power or is unreasonable. If this is shown, then, the burden
is shifted to the State to repel the attack by disclosing the
materials and reasons, which led to the action being taken in
order to show that it was an informed decision, which was
reasonable. If after a prima facie case of arbitrariness is made Patna High Court LPA No.2158 of 2015 dt.12-05-2016
174/208
out, the State is unable to show that the decision is an informed
action, which is reasonable, the State action must perish as
arbitrary.
287. In the light of the law, laid down on
arbitrariness, let us traverse the facts, none of which are
disputed.
288. The chronology of events, which led to the filing
of the present writ petition, have already been set forth
hereinbefore and, hence, those facts are not being repeated
except the basic facts, which have a bearing on the discussion
in question.
289. It is clearly discernible, from the admitted facts
of the present case, that when the writ petitioner raised
concerns about the prohibition on mining in Bihar, which would
have had material financial impact on the project, the
respondent No.4 wrote a letter to the Collector, Sasaram, to
consider the request of the writ petitioner as a special case by
relaxing the provisions under Rule 36 of the Rules under the
Mines & Minerals (Dеvеlорmеnt & Regulation) Act, 1957. This
letter, by the respondent No. 4, is, in fact, an acknowledgment
of the concerns of the writ petitioner. However, as things rolled
out later, the letter (Annexure 32), was never pursued seriously
by the respondents as a result of which a situation arose, when
the writ petitioner had to, in the interest of project, fetch Patna High Court LPA No.2158 of 2015 dt.12-05-2016
175/208
aggregates from outside the State of Bihar. The writ petitioner
needed an assurance from the respondents that the additional
cost of more than Rs 400 crores would be re-imbursed by the
respondents. It may be pointed out that quantification of
additional cost was not done by the writ petitioner himself;
rather, such quantification was done by Independent Engineer,
Intercontinental Consultants and Technocrat Pvt. Ltd, appointed
by the respondents. It may also be pointed out that at no point
of time, the figure of Rs 435 crores, as additional cost, was ever
disputed by the respondents.
290. In the review meeting, dated 25.9.2013, held in
the Conference room of BSRDC, in the presence of respondent
No. 8, the Independent Engineer, and the representative of writ
petitioner, the minutes No. 2, in Annexure 2, of the said
meeting go to show that consent was given by the respondent
No. 8 to the writ petitioner to go ahead with the installation of
crusher and procurement of aggregates from the neighboring
States being fully aware of the additional cost involved and it
was, thereafter, acting on these representations made by the
respondent No. 8, the writ petitioner went ahead with the
procurement of aggregates from neighbouring States.
291. About a year after the meeting was held on
25.9.2013, another review meeting was held on 05.08.2014
vide Annexure 33. As against Serial No. 3, the discussion/ Patna High Court LPA No.2158 of 2015 dt.12-05-2016
176/208
decision reached, with respect to payment of extra lead of
aggregates, was recorded and it would be seen from the
minutes that contrary to the commitment, made before,
respondent stated that that there was no provision of extra lead
aggregate in the Concessional Agreement and the claim for
extra lead of aggregate had already been rejected. The
respondents, therefore, as is apparent, changed their stance so
far as the re-imbursement for additional cost for extra lead of
aggregates is concerned. It may be pointed out at this juncture
that no specific reason was assigned in the meeting, dated
5.8.2014, to explain the departure from the earlier stand.
292. In view of the stance of the respondents, the
writ petitioner invoked the rights conferred by the Concession
Agreement, particular1y, Article 37.2.2, bringing to the notice
of the respondents to cure the defaults and issues within a
period of 90 days. Among the various defaults and issues
raised, by the writ petitioner, the default and issue, with respect
to serial No. 1, was concern as to non-payment of additional
cost incurred for the procurement of aggregates from longer
leads amounting to Rs 5.63 crores till date. In the review
meeting, dated 4.9.2014, which followed the Notice to cure
issued by the writ petitioner, the first item of the meeting was
regarding the Notice, under Clause 37.2, served by the writ
petitioner upon the respondents. As against this item of the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
177/208
discussion, the respondents advised the Independent Engineer
to examine and submit the proposal for additional cost, for
procurement of aggregates involving longer leads, by 8th
September, 2014, for further consideration and submission to
the State Government for approval. The minutes also reveal
that respondents advised the writ petitioner to withdraw the
notice, which the writ petitioner agreed subject to the
recommendation of the proposal of extra lead by the Authority
to the Govt. of B1har.
293. In the meeting, dated 06.11.2014, vide
Annexure 8, the respondents made an explicit promise to the
writ petitioner to cure all the issues (i.e., defects) raised by the
writ petitioner and further requested the writ petitioner not to
terminate the contract.
294. However, as the time passed by and no headway
was being made on the request of the writ petitioner for
payment of additional cost, even though the writ petitioner had
been incurring additional cost for procurement of aggregates
from neighbouring States, on the promise made by the
respondents, the lenders of the writ petitioner held a meeting
with the writ petitioner in the presence of the respondent No. 8.
In this meeting the respondent No. 8, as Annexure 36 explains,
revealed that it is the responsibility of the Company (i.e., the
writ petitioner) to arrange the aggregates. This, again, was a Patna High Court LPA No.2158 of 2015 dt.12-05-2016
178/208
change of stance without any remotely justifiable reasons.
295. Thereafter, the writ petitioner issued the Notice
of Intent to Terminate Agreement in view of the provisions
contained in Article 37.2.2 of the Concession Agreement.
Among several of defaults brought out, the principal one was
non-payment of cost incurred for the procurement of
aggregates and non-granting of permission to procure
aggregates form longer leads for the road works as decided in
the meeting, dated 25.9.2013, i.e, Annexure 2.
296. The options, available to the respondents, on the
receipt of the Notice of Intent to Terminate the Agreement, was
either to cure the defaults or to dispute the notice. However,
rather than curing the defaults or disputing the Notice of Intent
to Terminate, the respondents, as is apparent from Annexure-
12, admitted the default and chose to take the following-up
action under Article 37.4 of the Concession Agreement. The
opening lines of Article 37.4 reads as follows;
"Upon Termination for any reason whatsoever, the Authority shall"
297. It is, thus, clear that the respondents, too,
agreed to terminate the agreement instead of choosing to
contest the claims made by the writ petitioner and that is
precisely the reason that they opted for the follow-up action
needed to be taken by the Authority, when the agreement Patna High Court LPA No.2158 of 2015 dt.12-05-2016
179/208
stands terminated.
298. However, as the events further unfolded, the
respondents became the judge of their own cause and declared
the Notice of Intent to Terminate, issued by the writ petitioner,
as illegal even though, by Annexure 12, the respondents had
started taking follow-up action upon termination of the
agreement.
299. It appears from the letter, dated 16.2.2015,
Annexure 16, that in para 3.1, under the heading Non-payment
of additional cost, incurred by the Concessionaire for
procurement of aggregates, the respondent referred to Clause
12.1(d) of the Agreement, which provides as follows:
"Prior to commencement of Construction works, the Concessionaire shall make its own arrangement for quarrying the materials needed for the project highway under and in accordance with applicable laws and applicable permits".
300. By referring to clause 12.1(d), the respondents
stated that it is the responsibility of the writ petitioner to
procure aggregates or any other materials needed for the
project highway.
301. It seems that contents of clause 12.1(d) has not
been construed in proper perspective. It mentions that the
Concessionaire, the writ petitioner herein, shall make its own Patna High Court LPA No.2158 of 2015 dt.12-05-2016
180/208
arrangement for quarrying the materials needed for the project
highway under, and in accordance with, applicable laws and
applicable permits. Quarrying is the act of removal of
aggregates from the quarry; but despite repeated applications
from the writ petitioner, the respondents had done nothing to
allow quarrying, in the State of Bihar, by granting mining lease;
rather, they directed the writ petitioner to bring aggregates
from outside the State of Bihar, which the writ petitioner did.
The respondents, thus, as an afterthought, sought to create a
confusion over the meaning of quarrying leaving the writ
petitioner to burden the issue of procuring aggregates.
302. A further reading of paragraph 3.1 of Annexure
16 would show that respondents contended that by then, the
Government of Bihar, had, vide Notification no. 3085/M, Patna,
dated 11.08.2014, opened the mining lease for procurement of
aggregates, but even then, the writ petitioner had not made
any efforts for procurement of aggregates.
303. However, it is not understood as to how removal
of prohibition on mining would have automatically led to an
inference that the writ petitioner would have been granted
mining lease, had he taken up the matter. In fact, it would not
be proper to even suggest that writ petitioner had not put up
efforts to get a mining lease within the State of Bihar. The
letters, vide Annexure 29 and 30, indicate that writ petitioner Patna High Court LPA No.2158 of 2015 dt.12-05-2016
181/208
had been pressing hard for a mining lease, in the State of Bihar,
pursuant to which the letter, vide Annexure 32, was written by
respondent No. 4 to the Collector, Rohtas, Sasaram, for
considering the request of the writ petitioner in the light of Rule
36 of the Rules under the Mines & Minerals (Development &
Regulation) Act, 1957, as a special case.
304. It, thus, emerges that the plea of lifting of
prohibition on mining and alleging the writ petitioner of not
putting up efforts to get an allotment of mining lease was taken
only with a view to subvert the Notice of Intent to Terminate
issued by the writ petitioner by misrepresenting the facts. In any
view of the matter, such a reply, as contained in Annexure 16,
was issued only after the issuance of Notice of Intent to
terminate in view of Authority default. Having induced the writ
petitioner by various representations to procure aggregates from
outside the State of Bihar, a representation, as have been
noticed, affirmed on several occasions, and also acted upon by
the writ petitioner, it was not open to the respondents, on the
principles of promissory estoppel, to turn around and say that it
is the responsibility of the writ petitioner to procure aggregates.
It is apparent that respondents initiated the termination process
only to protect itself from the payment of termination amount to
the writ petitioner; hence, the representation, dated 16.02.2015,
smacks of arbitrariness and actuated with ulterior motive. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
182/208
305. It may be pointed out here that Article 37.2.1
mentions the circumstances, whereunder the Agreement can be
terminated by the writ petitioner for default of the Authority. The
principal circumstances are as follows;
The Authority commits a material default in complying with any of the provisions of the Agreement and such default has a material adverse effect on the Concessionaire;
(a) The Authority has failed to make any payment to the Concessionaire within the period specified in the Agreement;
(b) The Authority repudiates the Agreement or otherwise taken any action that amounts to or manifests, an irrevocable intention not to be bound by the Agreement;
(c) The State commits a material default in complying with the provisions of the State Support Agreement if such a default has a material adverse effect on the Concessionaire and the breach continues for a period of 90 days from the date of notice given in this behalf by the Concessionaire to the Authority.
306. The facts, noted hereinabove, would reveal that
acting on the assurances given by the respondents, the writ
petitioner started procuring aggregates from outside the State of
Bihar Incurring certain additional cost(s), which was not part of
the contract. The entire cost would not have been a small Patna High Court LPA No.2158 of 2015 dt.12-05-2016
183/208
amount; rather, would have amounted to Rs 435 crores as per
the assessment made by the Independent Engineer. The conduct
of the respondents show that at no point of time, having
promised to bear the additional cost, they actually paid the cost;
rather, as the events turned out to be, the respondents,
suddenly, termed the claim of the writ petitioner as illegal, which
was arbitrary, unreasonable and unfair as a measure of
subsequent or after thought. I, therefore, find no infirmity in the
findings of learned Single Judge that the termination notice,
issued by the respondents on 10.6.2015, is illegal being served
only to avoid termination payment to the writ petitioner. In any
view of the matter, there could not have been any further
termination of the agreement, from the end of respondents, in
view of Annexure 12, whereby they accepted the notice of intent
to terminate issued by the writ petitioner.
307. Subjecting the aforementioned facts to the test of
arbitrariness as laid down in the case of Shrilekha Vidyarthi
(Kumari) (supra), it is found that despite the recommendation
of the Independent Engineer to provide mining lease to the writ
petitioner or to make additional cost, in the alternative to the
writ petitioner, the respondents, having made explicit promise to
the writ petitioner to make additional payments, kept
dillydallying the issue of additional cost leading the writ
petitioner to issue notice of intent to terminate. Thereafter, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
184/208
accepting the notice and taking follow up action upon
termination, the respondents, again, took a somersault and
termed the notice of intent to terminate as illegal.
308. Thus, the conduct of the respondents is
uninformed by reason inasmuch as there is no discernible
principle on which decisions were taken. The initial onus to show
arbitrariness and unreasonable on the part of the respondents
having been discharged by the writ petitioner, no material
and/or sustainable reason have been shown by the respondents,
in this appeal, which led to the action being taken in order to
show that it was an informed decision, which was reasonable.
The State respondents, being unable to show that their decision,
to first, assure the writ petitioner to bear the additional cost,
inducing the writ petitioner to bring aggregates from outside the
State of Bihar, and, eventually, retracting from their assurances
and promise, is not found to be an informed action, which is
reasonable and, hence, the respondents' action must perish as
arbitrary and, consequently, violative of Article 14 of the
Constitution of India.
ROLE OF STATE GOVT OF BIHAR
309. It is also necessary to mention at this juncture
that the project was not only ventured by the respondents, but
the Govt. of Bihar equally had a stake in it. The approval for the
project, along with the request of the writ petitioner, to provide Patna High Court LPA No.2158 of 2015 dt.12-05-2016
185/208
mining leases, was approved by the State Cabinet. It would
appear from the letter, dated 21.11.2014, vide Annexure 35,
that according to RFP (Request for Proposal), the Bid was not
sanctioned within 120 days by the State Cabinet; hence, the writ
petitioner was requested to extend its bid validity beyond
02.03.2011. The writ petitioner extended the validity of the Bid
for one month. In the meantime, the file for projects State VGF
(Viability Gap Funding) share, for theoretical consent was with
the Finance Department, and, therefore, BSRDC, the
respondents herein, requested the writ petitioner to extend the
validity of the Bid for next two months. Based on the request,
the writ petitioner extended its validity of the Bid by one more
month. The writ petitioner was, again, requested to extend the
Bid validity for the third time, which the writ petitioner complied
by extending the Bid by one more month. On the fourth
occasion, when the writ petitioner extended its Bid, its
extension, on 16.06.2011 was subject, admittedly, to the
granting of the mining lease. It is further revealed from the
Annexure 35 that, as the proceedings for approval of the project
were at the final stage before the Govt of Bihar, the respondents
further requested the writ petitioner to extend the Bid, which
writ petitioner did. Eventually, the conditional bid was approved
by the State Cabinet.
310. It is, thus, apparent that at the time, when the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
186/208
State Cabinet approved the project, the conditions, set out by
the writ petitioner, that mining leases shall be granted to the
writ petitioner, were already brought to the notice of State
Cabinet. The opinion of the Principal Additional Advocate
General, in his letter, dated 28.10.2014, also contains a
reference to the approval by the State Cabinet. In this regard,
Clause (d) to Article 37.2.1 provided that if the State commits a
material default in complying with the provisions of the State
Support Agreement and if such default has a Material adverse
effect on the Concessionaire and the breach continues for a
period of 90 days from the date of notice given, in this behalf, by
the Concessionaire to the Authority, the Concessionaire shall be
entitled to terminate the agreement.
311. Mining plots were exclusively under the
possession of State and mining was essential for the
construction of the project. If mining was prohibited, then, the
State Government should have either allowed mining within the
State of Bihar, in the interest of the project, or could have
granted permission for additional cost likely to be incurred by
the writ petitioner. However, despite seeking several extensions
of bid from the writ petitioner, and, eventually, approving the
project with the knowledge of the conditions of mining set out by
the writ petitioner, the State Government continued to sit idle
over the matter, that too, with respect to a project involving Patna High Court LPA No.2158 of 2015 dt.12-05-2016
187/208
huge amount of money. In Annexure 19, the Termination Notice,
issued by the writ petitioner, it has been categorically mentioned
that in view of the delay in the decision as to payment of
additional cost, it would be impossible to complete the project
and commence toll collection from 15.3.2016, the agreed date,
on the basis of which entire financial viability of the project was
worked out.
312. Thus, the Govt. of Bihar, by not taking decision
on the payment of additional cost, not only materially and
adversely affected the project, but also put the writ petitioner to
risk of committing a default in not completing the project in
time. Seen from the perspective of Clause 37.1.1 (e) of the
Concession agreement, such a delay could have been a ground
for the Authority to terminate the agreement, that too, for no
fault of the writ petitioner. It may be pointed out here, as
submitted by the learned Senior Counsel for the writ petitioner,
that if the writ petitioner would not have agitated the issue of
additional cost of aggregates, from the longer leads, the project
would have gone in indeterminate state since the financial close
of Rs 1200 crores did not include the additional cost of Rs 435
crores for procurement of aggregates from longer leads. Hence,
it is evident that, apart from the actions of respondent
Corporation, even the action of State Government is
undoubtedly unfair, unreasonable, arbitrary and, therefore, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
188/208
violative of Article 14 of the Constitution of India.
WHETHER THE WRIT PETITION DISCLOSES DISPUTED QUESTIONS OF FACT?
313. One of the prohibitions, which regulates the grant
of relief in exercise of the extraordinary writ jurisdiction, under
Article 226 of the Constitution of India, is whether the pleadings,
when taken in its entirety, raise disputed questions of fact.
314. In the present case, the pleadings and materials
on record, when read as a whole, reveal no disputed fact. The
contents of the documents, relied upon, by the writ petitioners,
are also admitted. The only issue, which may require
adjudication, even though not specifically disputed, is the
quantum of the money claimed in the writ petition.
315. Clause 37.3.2 of the Concession Agreement deals
with Termination Payment on account of default by the
Authority. It provides that upon termination of agreement on
account of Authority default, the Authority shall pay to the
Concessionaire an amount equal to
a. Debt due; and
b. 150% of the Adjusted Equity.
316. Termination payment shall become due and
payable to the Concessionaire within 15 days of a demand being
made by the Concessionaire to the Authority with the necessary
particulars and, in the event of delay, Authority shall pay interest Patna High Court LPA No.2158 of 2015 dt.12-05-2016
189/208
at the rate equal to 3% above the Bank rate on the amount of
termination payment remaining unpaid.
317. In the present case, the quantum of termination
payment has been worked out by the Independent Engineer
appointed by the respondents themselves. This was done in
terms of the review meeting, dated 04.09.2014. In the report of
Independent Engineer, dated 09.09.2014, Annexure 34, it has
been specifically stated that the amount, on account of
termination, works out to Rs 602 crores by applying the
standards mentioned in Clause 37.3.2, though it may be pointed
that the figure of Rs 602 crores were till the date of report, i.e.,
09.09.2014, which, by stipulated calculation method, has gone
up, on account of interest, as the writ was filed in the month of
May, 2015, which is more or less eight months after the report,
Annexure 34, was submitted. The writ petitioner, along with
Termination Notice, dated 20.02.2015, Annexure 19, had
annexed the calculation for termination payment, supported by
the certificate from the Lead Bank of the Consortium of Banks,
for debt disbursed till that date, which is not disputed on record.
318. Apart from the report of Independent Engineer,
the respondents have themselves got the figures of equity and
debt verified through the Concurrent Auditor, appointed by the
respondents, as can be seen from the minutes of the meetings,
dated 04.09.2014 and 06.11.2014, Annexure 7 and 8, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
190/208
respectively. It would be seen that vide a letter, dated
16.2.2015, respondent No. 7, addressed a letter to the
Department of Economic Affairs, Ministry of Finance, Govt. of
India, vide letter no. BSRDCL-1548/2014-39, dated 16.02.2015,
wherein they have certified that the Concessionaire, the present
writ petitioner, has subscribed Rs 202.00 crores against Equity
support.
319. Again, the lenders of the writ petitioner also
addressed a letter, vide letter No. ADV:KO:2069/14-15, to the
respondent No.8, namely, General Manager of the respondent-
Corporation, on the subject of disbursement made to the writ
petitioner, wherein they have stated that till 16.02.2015, the
lenders have disbursed Rs 3,08,28,389 to the writ petitioner.
The amounts of equity and debt are, thus, not disputed at any
point. Hence, the claim cannot, but be held to be true and
legitimate, which I do.
320. With regard to the findings of the learned single
Judge, in paragraph 13 of the judgment, that "As regards the
quantification of the consequent Termination Payment liable to
be paid by the respondents with regard to the nature and extent
of authority default in terms of Clause 37.2.2 of the of the
agreement, the same would necessarily require a detailed
investigation into facts and adduction of evidence, into the
details of which this Court need not travel" is found to be not in Patna High Court LPA No.2158 of 2015 dt.12-05-2016
191/208
consonance with the admitted position of the case. As already
pointed out, the calculation method of termination payment and
the quantum of payment have never been disputed by the
respondents; hence, no detailed investigation of facts is required
in the present case.
321. Now, the law as provided in Section 70 of the
Contract Act is that even if the contract is illegal, but, in
execution of such a contract, a party has derived benefit, the
party, who derives and accepts the benefit, has to compensate
the person from whom such benefit is derived and accepted.
Hence, though a contract is illegal, the fact remains that if, in
terms of the contract, the State has derived benefit, or received
delivery of property, the State has to compensate the person,
who delivers the property, or from whom benefit is derived by
the State. Though, in the present case there is no question of
illegality of contract as the contract was lawfully entered into but
the fact remains that the respondents have received the benefits
of the work done by the appellant, i.e. construction of road by
procuring aggregates from outside the State of Bihar. In these
circumstances, when the appellant was allowed to execute the
contract, in question, it will be highly iniquitous not to let the
respondents compensate the appellant for the benefits, which
the respondents have derived, because of the execution of the
contract by the appellant. The compensation, in the present Patna High Court LPA No.2158 of 2015 dt.12-05-2016
192/208
case, would be one which has been worked out by the
Independent Engineers in terms of Clause 37.3.2.
322. It would be proper to refer, in this context, to one
of the observations made by the Supreme Court in the case of
Gunwant Kaur v. Municipal Committee, Bhatinda, (1969) 3
SCC 769, wherein it has been held that the High Court is not
deprived of its jurisdiction to entertain a petition under Article
226 of the Constitution of India merely because in considering
the petitioner‟s right to relief, questions of fact may fall to be
determined. In a petition under Article 226 of the Constitution of
India, the High Court has jurisdiction to try issues both of fact
and law.
323. Even though no disputed questions of fact have
been found in this case; yet, it may be proper to quote one of
the observations made in the case of Century Spg. And Mfg.
Co. Ltd. V. Ulhasnagar Municipal Council, (1970) 1 SCC
582, with respect to a submission made therein that the
appellant had raised questions of fact and, hence, remedy under
writ jurisdiction is not appropriate. To this submission the Apex
Court responded as follows;
"13. Mr. Gokhale appearing on behalf of the Municipality urged that the petition filed by the Company apparently raised questions of fact which in the view of the High Court could not appropriately be tried in the exercise of the extraordinary jurisdiction under Article 226. But the High Court has not said so, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
193/208
and on a review of the averments made in the petition this argument cannot be sustained. Merely because a question of fact is raised, the High Court will not be justified in requiring the party to seek relief by the somewhat lengthy, dilatory and expensive process by a civil suit against a public body. The questions of fact raised by the petition in this case are elementary."
(Emphasis is added)
324. In view of the fact that the quantum of
compensation has never been disputed by the respondents, the
findings of the learned single Judge, in paragraph 13, referring
the matter to arbitration and direction to the writ petitioner to
co-operate in the arbitration, are not justified in the context of
this case and, accordingly, needs to be interfered with.
325. The facts of this case are similar to that of Lotus
Hotels (P) Ltd. (supra). In the present case, too, same as
Lotus Hotels (supra), the respondents assured the writ
petitioner that they will bear the additional cost of procurement
of aggregates from outside the State of Bihar. The writ petitioner
had acted on the assurances and promise and invested huge
sums of money to procure aggregates from outside the State of
Bihar; but, later on, not only the respondents resiled from their
promise, but also termed the writ petitioner‟s claim as illegal.
326. I have had the pleasure of reading the judgment
of my learned brother, Justice Chakradhari Sharan Singh, and Patna High Court LPA No.2158 of 2015 dt.12-05-2016
194/208
even though I appreciate the efforts put in by my learned
brother, yet I am unable to persuade myself to agree to the
conclusions reached by my learned brother on some of the vital
aspects of the case.
327. The learned single Judge, in paragraph 12 of his
judgment, has held that "on merits of the present case, this
Court finds no error in the action of the petitioner in
issuing the termination notice and the Respondent's
contention that the petitioner ought to have first opted for
arbitration cannot be accepted".
(Emphasis is added)
328. Thus, the learned single Judge has held that not
only the termination notice of the petitioner is proper, but the
contention of the respondents that petitioner ought to have
taken recourse to arbitration, too, did not find favour with the
learned single Judge. In this regard, while going through the
findings of my learned brother, I notice that this finding of the
learned single Judge has not been disturbed in any manner.
329. The learned single Judge, having held that
termination of the notice by the appellant is proper, has,
however, held that so far as quantification of termination
amount is concerned, the same would require adducing of
evidence and investigation of facts. Such an observation seems
to have been upheld by my learned brother, though the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
195/208
materials on record make it, to my mind, amply clear that even
the amount is not in dispute, or to be more precise, the
termination amount has been admitted.
330. Now, it is an admitted position that at the time of
entering into agreement, mining operations were prohibited in
the State of Bihar and that is why, the bid of the appellant was
conditional that mining would be permitted. The conditional bid
was approved on 2.8.2011 by the State Cabinet. A
reference to the Cabinet approval is found in Annexure 35 and
Annexure 26, the contents whereof have not been in dispute.
The Concession Agreement signed by the parties contains all the
correspondences regarding the conditional bid and allotment of
mines.
331. I, therefore, find myself in disagreement with the
observation made by my learned brother that there was no
stipulation in the Concession Agreement that mining lease would
be granted to the appellant for execution of work. My learned
brother has incorporated the provisions of Article 12 of the
Agreement, which specifically provides that prior to the
commencement of works, the Concessionaire shall make its own
arrangements for quarrying the materials needed for the project
highway.
332. Article 12.1 (d) provided that the appellant shall
quarry the materials needed for the project highway in Patna High Court LPA No.2158 of 2015 dt.12-05-2016
196/208
accordance with applicable laws and applicable permits. The act
of quarrying, as agreed, was the sole responsibility of the
appellant; but such an act of quarrying was subject to applicable
laws and permits. Since, admittedly, mining operations stood
prohibited at the relevant point of time, the question arose as
regards procuring materials from outside the State of Bihar
requiring additional cost. It is not the case of the Corporation
that even for mining operation in Bihar, the appellant was asking
for additional cost. In this regard, when the matter was referred
to Independent Engineers, appointed by the Corporation, they,
too, gave an opinion, vide Annexure 6, that BSRDC, the
respondents herein, may take a decision either to impress upon
the State Government to allow mining or re-imburse the
additional cost of Rs 410.13 crores based on SOR-8th edition of
Road Construction Department, Bihar. The mining operations in
Bihar was, admittedly, never allowed to the appellant.
333. My learned brother has, while referring to
Annexure 2, held that Annexure 2 does not contain any
admission on the part of the respondents permitting the
appellant to procure aggregates from outside the State of Bihar
in view of the mining prohibitions in the State of Bihar and has
further held that since Annexure 2 does not contain the
signatures of the respondents, it cannot form basis of any
assurance. While considering Annexure 2, it needs to be Patna High Court LPA No.2158 of 2015 dt.12-05-2016
197/208
carefully noted that the contents and contentions embodied in
Annexure-2 have never been in dispute between the parties
concerned and, therefore, I am unable to fall in agreement with
my learned brother that Annexure 2 does not contain an
admission. It is apparent from Annexure 6, the notice issued by
the appellant to the respondents for curing the defects/defaults,
that till 31.7.2014, the appellant had already incurred an
expenditure of Rs 5.63 cores for procuring aggregates from
outside the State of Bihar. This amount went upto Rs
9,15,20,314/- as can be seen from Annexure 11. In my
considered view, therefore, the conduct of the respondents in
not prohibiting the appellant from incurring expenditures goes to
show that the respondents wanted the appellant to go ahead
with the assurance. Hence, Annexure 2 has to be treated as
clear admission on the part of the respondents that in view of
the requirement to complete the project in time and also in view
of the mining prohibitions, they had allowed the appellant to
procure aggregates from longer leads. The absence of signatures
of respondents in Annexure 2 is of little importance since the
respondents have not disputed the document, Annexure 2,
and/or the conditions therefor. This apart even Annexure 33,
which is also a minute relied upon by the appellant, bears only
the signature of respondents.
334. It has been held in Nagubai Ammal v. B. Patna High Court LPA No.2158 of 2015 dt.12-05-2016
198/208
Shama Rao, (AIR 1956 SC 593) that an admission is not
conclusive as to the truth of the matters stated therein. It is only
a piece of evidence, the weight to be attached to which must
depend on the circumstances under which it is made. It can be
shown to be erroneous or untrue, so long as the person to
whom it was made has not acted upon it to his detriment,
when it might become conclusive by way of estoppel.
335. It may be stated here that the case of the
respondents is that they are denying the entitlement of the
appellant to the money claimed and not the computation. The
entitlement has been upheld by the learned Single Judge, while
holding that termination of agreement was correct on the facts
of this case.
336. It may be pointed out that in para 7 of Annexure
34, the Independent Engineers have mentioned the expression
tentative, but the method of computation of the amount is,
admittedly, in terms of the Concession Agreement, as reflected
in Article 37.3.2. Article 37.3.2 of the Concession Agreement
deals with Termination Payment on account of default by the
Authority. It provides that upon termination of agreement on
account of Authority default, the Authority shall pay to the
Concessionaire an amount equal to;
a. Debt due; and
b. 150% of the Adjusted Equity.
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
199/208
337. The Independent Engineers had prepared the
report on 9.4.2014 and they had taken into account the
components as available and admitted on the day of preparation
of report. On that day, the principal amount outstanding to
Senior lenders of the appellant was Rs 248.49 crores, which, at
the time of filing of writ petition, was Rs 3,08,28,18,389/- vide,
Annexure I.
338. It is also pertinent to point out that the
Independent Engineers were directed by the respondents
themselves to visit the appellant‟s headquarter along with the
Concurrent Auditor, appointed by the respondents, for the
scrutiny of papers related to VGF grants and to submit a
scrutinized report by 15.9.2014. The VGF grant is based on
equity and debt by the banks. The Independent Engineers and
the Concurrent Auditors scrutinized the accounts of the appellant
at the appellant‟s headquarters as can be seen from the
minutes, dated 6.11.2014, and after all these compliances, the
respondents decided to process the release of grant by the State
and the Central government. This would mean that the debt
amount and equity amount has been verified and were found to
be true as can be seen from the minutes of the meetings, dated
04.09.2014 and 06.11.2014, Annexure 7 and 8, respectively.
339. It would be seen that respondent No. 7,
addressed the Department of Economic Affairs, Ministry of Patna High Court LPA No.2158 of 2015 dt.12-05-2016
200/208
Finance, Govt. of India, letter No. BSRDCL-1548/2014-39, dated
16.02.2015, (Annexure a, page 123), wherein they have
certified that the Concessionaire, the present appellant, has
subscribed Rs 202.00 crores against Equity support. If the
equity amount is Rs 202 crore, then, 150% of 202 crore comes
to Rs 303 crore. Thus, the figure of Rs 602 crores is sum total of
figures of Rs 303 crores and 248.49 crore along with interest.
340. The case of the appellant is, thus, not based on
the report of Independent Engineer alone, but also on the
scrutiny of the Independent Engineer and the Concurrent
Auditor as per minutes, dated 4.9.2014 and 6.11.2014, and the
unequivocal admissions of the respondents about the equity and
debt, while recommending release of grant to the Government
of India read with confirmation letter of the lenders.
341. Thus, if the finding of the learned single Judge
that appellants had rightly terminated the agreement has been
upheld, the denial of relief on the grounds that termination
payment would require adducing evidence and investigation of
facts is not borne out of records. Such quantification is simple
arithmetic based on agreed formula. In any view the matter, the
respondents have never disputed the computation method as
projected by the appellant. No question of any agreement on the
binding force of Independent Engineers‟ report arises for the
reason that it is nobody‟s case. However, what is binding is Patna High Court LPA No.2158 of 2015 dt.12-05-2016
201/208
Article 37.3.2, which deals with the method of computation of
termination payment in the event of Authority default. That
there has been an authority default has already been affirmed in
the findings of learned Single Judge in para 12 of the judgment,
while holding that "on merits of the present case, this Court
finds no error in the action of the petitioner in issuing the
termination notice".
342. Now, so far as quantification of amount,
mentioned in the writ petition, is concerned, the computation
method as stated in Article 37.3.2 is admitted. The components
required for computations are also admitted. The debt due is
admitted to be Rs 3,08,28,18,389/- vide Annexure I. The equity
amount is also admitted to be Rs 202 Crore. The computation of
150 % of adjusted equity done by the appellant have never
been disputed by the respondents ─ be it in the original hearing
or in the appellate hearing. Thus, 150% of 202 crore comes to
Rs 303 crore. The sum total of admitted amounts of Rs
3,08,28,18,389/- and Rs 303 crores comes to Rs
6,11,28,18,389. It is seen that appellant has claimed amount
lesser than the figures arrived at by applying the formula and
this is so, because the debt due figure is required to be
computed with reference to Wholesale Price Index. According to
the appellant, 150% of 202 Crores with reference to Wholesale
Price Index, comes to Rs 3,02,24,54,344 and the total of Rs Patna High Court LPA No.2158 of 2015 dt.12-05-2016
202/208
3,08,28,18,389 and 3,02,24,54,344 comes to Rs 6,105,272,733.
Such a method of computation does not adducing of evidence
nor does it call for any investigation of facts. The figure of the
amount claimed has also neither been disputed in the pleadings
nor in the entire proceedings before the Court.
343. With great respect to the findings of my
learned brother, the observation that question of termination
payment would arise only if termination agreement for authority
default is held to be justified, I am clearly of the view that such
an issue does not remain alive for discussions since my learned
brother has upheld the findings of learned single Judge and the
learned single Judge has categorically held that on merits of the
present case, no error has been found in the action of the
petitioner in issuing the termination notice.
344. In any view of the matter, these issues do not
arise for three specific reasons;
a. Firstly, because the termination of
agreement for authority default has been held
to be correct by the learned Single Judge in
para 12 of the judgment. The respondents
have, in the appeal, put limited challenge to the
finding of the learned single Judge with respect
to maintainability in view of Article 44 and the Patna High Court LPA No.2158 of 2015 dt.12-05-2016
203/208
setting aside of their notice of termination. The
correctness of termination of agreement by the
appellant has not been challenged either in the
writ petition or in this appeal. Hence, the
finding that appellant has correctly terminated
the contract remains intact and cannot be gone
into.
b. Secondly, the question of respondents
approaching the Arbitral Tribunal does not
arise, because the respondents themselves
have never approached the tribunal. If the
respondents' plea of non-maintainability of
writ, due to Article 44, has been over-ruled,
then, the question of referring the matter to
arbitration does not arise, for, if the writ is
maintainable, the only ground on which relief
may be denied is that the writ petition involves
disputed questions of fact, which, in the
present case, has, admittedly, none.
c. Thirdly, an issue can become a disputed
question of fact only when dispute existed
prior to litigation. A mere plea, on facts, in the
pleadings cannot conform to the status of a
disputed fact if the documents, otherwise, Patna High Court LPA No.2158 of 2015 dt.12-05-2016
204/208
make it sufficiently clear that facts are not in
dispute. The representation, dated 16.2.2015,
filed by the respondents, challenging the
validity of the termination notice issued by the
corporation, cannot be taken on its face value,
when on the previous occasion, vide Annexure
8, in the review meeting, the respondents
promised to cure the issues raised by the
appellant in his notice to cure issues. Thus,
when the issue, relating to additional cost of
aggregates, was promised to be cured, such a
promise becomes a binding promise. Hence, by
subsequent denial, a dispute cannot be raised
on previously admitted position. In any view of
the matter, a representation once submitted
may or may not be acted upon by the
appellant. The respondents had the
opportunity to dispute the claims of the
appellant, when it had issued notice of intent
to terminate the contract, but they did not do
so.
d. Fourthly, the respondents have, in para
12 of the counter affidavit, categorically stated
as follows;
Patna High Court LPA No.2158 of 2015 dt.12-05-2016
205/208
"That the termination on account of the petitioner‟s default will absolve the respondent from any termination payment as provided in clause 37.3.1."
e. As against this averment, the learned
single Judge rightly held, in para 12 of the
judgment, that termination notice by the
respondent has been issued after filing of the
writ petition possibly for the purpose of
avoiding the consequences of having to make
the termination payment to the petitioner as a
fallout of the termination notice issued by the
petitioner for the authority default.
345. After the termination notice was issued by the
appellant, the respondents issued the letter dated 7.2.2015,
Annexure 12, which specifically mentions Article 37.4(b). The
opening lines of Article 37.4 reads "Upon Termination for any
reason whatsoever, the Authority shall". This notice was issued
by an officer of the rank of Deputy General Manager and he is
definitely expected to know the contents of Article 37.4(b) and,
hence, he would not have mentioned the Article unless the
respondents intended to act upon it.
346. In the above view of the matter, the respondents
have, nowhere, submitted that the intent of issuing Annexure Patna High Court LPA No.2158 of 2015 dt.12-05-2016
206/208
12 was to seek information and details of all materials, etc, so
that, if needed, possession of the same can be taken over.
347. That apart, Annexure 12 refers to the
termination notice issued by appellant. Hence, the respondents
were fully aware of the nature and content of the letter, which
by no means carried a meaning other than the follow up action
pursuant to the termination of agreement.
348. On the issue of legal opinion, relied upon by the
appellant and on which my learned brother has taken serious
exception of what is of importance to note, while considering
the question of privileges, is that a privilege has to be expressly
or impliedly claimed, by the authority, which enjoys the
privilege, for an authority may choose to waive its privilege in
the greater interest of the general public or for the welfare of
the nation unless a legal or constitutional bar exists restraining
the authority concerned from waiving or restricting its privilege.
For example, Article 74(2) provides that the question, if any,
and, if so, what advice was tendered by the Ministers to the
President shall not be inquired into in any court. Thus,
Article 74(2) contains an express bar restricting Parliament
from waiving its privilege. So long as this Constitutional
provision remains, Parliament cannot enact a law authorising
courts to inquire into as to what advice the Council of Ministers
had tendered to the President, for, such a statutory provision Patna High Court LPA No.2158 of 2015 dt.12-05-2016
207/208
will not be permissible in the face of the embargo imposed by
Article 74(2). However, in respect of those privileges, which the
Constitution do not specifically bar, the Legislature has the
discretion of waiving or not claiming. The Legislature, therefore,
may, by enacting law, give up its privilege. This fundamental
aspect of the scope of "privilege" has to be kept in mind in
deciding the question, which the Court is concerned with.
349. In the present case, too, no privilege has been
claimed by the learned Principal Additional Advocate General,
who gave the opinion and who himself argued the case. This
apart, the legal opinion has been referred to in several other
correspondences precisely in para 14 of Annexure 26 and
Annexure 35. In these circumstances, the legal opinion,
tendered by the learned Principal Additional Advocate General,
loses the touch of any confidentiality or privilege.
350. In the words of Justice Bhagawati, in the case of
Hindustan Sugar Mills vs State of Rajasthan (AIR 1981 SC
1681), in a democratic society governed by the rule of law, it is
the duty of the State to do what is fair and just to the citizen and
the State should not seek to defeat the legitimate claim of its
citizen by adopting a legalistic attitude, but should do what
fairness and justice demand.
351. The question of imposing cost on the
Concessionaire to pay a fine of Rs. 5,00,000/- does not arise and Patna High Court LPA No.2158 of 2015 dt.12-05-2016
208/208
the cost of Rs. 5,00,000/-, contrary to what my esteemed
brother has held, is not and cannot be directed to be paid.
352. In the result and for the reasons discussed
above, I uphold the conclusion of the learned single Judge that
the termination of the Concession Agreement by the
respondent Corporation was invalid, but I set aside the
directions given by the learned single Judge that the parties
shall take recourse to arbitration. I further direct that the
amount, as has been determined above, shall be paid in terms
of the directions, within a period of three months from the
date of pronouncement of this judgment and order with
interest, as provided under Clause 37.3.2, at the rate equal to
3 per cent above the Bank Rate on the amount of termination
payment remaining unpaid from the date of termination, i.e.,
20.02.2015 till the date of payment.
353. However, there shall be no order as to costs.
(I. A. Ansari, ACJ.)
Pawan/-
AFR/NAFR AFR CAV DATE 22.01.2016 Uploading Date 12.05.2016 Transmission N.A. Date
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free