Manoj Kumar vs Ample Infrastructure Pvt. Ltd. & Anr
- CitationCompany Appeal(AT) (Insolvency) No. 645 of 2019
Ratio decidendi
The rule this decision rests on
Where a builder-buyer agreement obliges the developer to deliver possession by a stipulated date and possession has not been delivered, the allottee is a financial creditor entitled to initiate a Section 7 insolvency application, and the existence of contractual options to claim compensation or cancel the allotment does not bar that route, since the Code provides the allottee an independent avenue for relief. For the purposes of Section 7, a default is established where the corporate debtor has failed to deliver possession within the time fixed by the agreement; the absence of a specified date of default in the financial creditor's application format does not defeat the application where the default is apparent on the admitted facts on record.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Manoj Kumar ...Appellant
Vs
Ample Infrastructure Pvt. Ltd. & Anr. ....Respondents Present: For Appellant: Mr. Shambo Nandy, Mr. Arijit Mazumdar and Ms. Akanksha Kaushik, Advocates For Respondents: Mr. Raghavebdra Bajaj and Mr. Sanskar Agarwal, Advocates for Respondent No. 1.
Mr. Saurabh Jain and Mr. Smarth Arora, Mr. Pawan Bhushan, Mr. Tushar Bhushan, Mr. Jitendra Kumar Mr. Anjaneya Singh, Mr. D. Deshpande, Mr. Anil Sutor, Advocates for Intervenors.
Mr. Sameer Rastogi, Advocate for Respondent No. 1.
ORDER
13.11.2019 Heard learned Counsel for Appellant. Ample Infrastructure
Pvt. Ltd. filed an application under Section 7 of Insolvency and Bankruptcy Code,
2016 (in short "IBC") having no. IB-17/ND/2019 before the Adjudicating
Authority (National Company Law Tribunal) New Delhi, Bench - II against M/s
Intellicity Business Park Pvt. Ltd., Respondent- Corporate Debtor. It was
admitted by the Adjudicating Authority on 27.05.2019 and against the
admission of the application, present appeal has been filed by Director of the
Corporate Debtor.
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 1 of 7
2. The Appellant claims that there was a builder-buyer agreement executed
between the Financial Creditor and the Corporate Debtor and if the project was
incomplete or possession had not been handed over in time, the Financial
Creditor had options under builder-buyer agreement.
3. Learned Counsel refers to the agreement dated 03.10.2013 and clause-11
of the same which related to schedule for possession of the unit concerned.
Learned Counsel has stated that as per this clause, no doubt, the Corporate
Debtor was bound to deliver of possession by October, 2017 and if six months'
grace period was to be added, possession was to be given by April, 2018. Learned
Counsel stated that even if the possession had not been given as per this clause,
Clause 11(b) provides for payment of compensation as mentioned in the clause
which reads as under:
...
(b) Delay due to reasons beyond the control of the Builder:
If the possession of the Said Unit is delayed due to Force
Majeure conditions or fire, tempest, flood, violence of any or of
a mob, or other irresistible force or if, then the Builder shall be
entitled to extension of time for delivery of possession of the
Said Unit. The Builder during the continuance of the Force
Majeure reserves the right to alter or vary the terms and
conditions of this agreement or if the circumstance so warrant,
the Builder may also suspend the development for such period
as is considered expedient, the Buyer shall have no right to
raise any claim, compensation of any nature whatsoever for
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 2 of 7 or with regard to such suspension. The Buyer agrees and
understands that if the Force Majeure condition continues for
a long period, then the Building alone in its own judgment and
discretion may terminate this Agreement and in such case only
the liability of the Builder shall be to refund the amount
without any interest or compensation whatsoever. The Buyer
agrees that the Buyer shall have no right claim of any nature
whatsoever and the Builder shall be released and discharged
of all its obligations and liabilities under this agreement. In
case the builder is forced to abandon the said project due to
force majeure circumstances or for reasons beyond its control,
it shall refund the amount paid by the buyer alognwith simple
interest @ 6% p.a. from the happening of such eventuality."
...
4. It is further argued that as per the above clause, allottee was entitled to
compensation and if an allottee did not want to take benefit of this clause, the
allottee had option to cancel the contract for which there is clause-51 in the
agreement which reads as follows:
...
"51. Cancellation/Withdrawal
In the unfortunate event of cancellation/withdrawal of the
allotment, the amount paid by the Buyer shall be refunded
within six months after deducting amount equal to 15% of
basic sale price to partly compensate the Builder for midway
scrapping of contract and resultant delay in time schedule and
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 3 of 7 increase in construction cost of the project due to such
cancellation."
...
Submission of the learned Counsel is that the allottee had options to resort
to as per agreement and thus could not have filed application under Section 7 of
IBC. It is stated that there was no financial default and even in the copy of the
format, which has been filed with the rejoinder, Financial Creditor did not state
exact default. It is further stated that Clause -8 of the Agreement (page -40)
shows that time was essence. Clause -8 reads as follows:
...
8. Time is the essence
The Buyer agrees that time is of essence with respect of
payment of Total Sale Price and other charges, deposits and
amounts payable by the Buyer as per this agreement and/or
as demanded by the Builder from time to time and also to
perform/observe all other obligations of the Buyer under this
Agreement. The Builder is under no obligation to send any
reminders for the payments to be made by the Buyer as per
the schedule of payments and for the payments to be made as
per demand by the Builder or other obligations to be performed
by the Allottee. If payment is not received within the stipulated
period or in the event of breach of any of the terms and
conditions this agreement by the Buyer, the allotment will be
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 4 of 7 cancelled and amount received will be refunded without any
interest, after deduction of 15% the total cost of the unit."
...
5. It is the submission of the learned Counsel that when there was no
financial default, application under Section 7 of IBC should not have been
admitted. Learned Counsel for the Appellant prays for setting aside the
admission order.
6. Learned Counsel for the Appellant relied on the judgment in the matter of
"Pravinbhai Raninga Vs. The Kotal Resources and Anr." in Company Appeal
(AT)(Insolvency) No. 140 of 2018 dated 29th August, 2018 and referred to
paragraph-9. It is stated that it is open for the Corporate Debtor or its Directors
to point out that the debt is not payable by the Corporate Debtor in law and also
and/or in fact.
7. Learned Counsel for the Financial Creditor is heard. He has submitted
that admittedly possession was not delivered as per time schedule and there was
default and the impugned order itself shows that the Financial Creditor had paid
all the necessary instalments which is evident from paragraph-4 of the impugned
order. It is stated that the Financial Creditor has not defaulted in payments and
still if the Financial Creditor, because of delay, was to cancel the contract, the
Financial Creditor would be put to loss being made liable to the deduction of
15% of basic sale price for no fault of the Financial Creditor.
8. Learned Counsel for the Intervenors are present and it is stated that apart
from present application of the Financial Creditor, there were various other
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 5 of 7 allottees who had already filed applications under Section 7 which were pending
and as the present application got admitted, those allottees were required to file
their claims before Interim Resolution Professional/Resolution Professional,
which they have done. It is also pointed out that the revival plan pointed out by
the Appellant vide diary No. 15894 (page-14) shows the status of the project.
Learned Counsel referred to paragraph -2(b) (i) & (ii) which is as follows:
...
b. Proposal for Revised Project Plan
i. All allotments will be shifted to Ascot within 90 days
from the zero date.
ii. Spine A and Spine B are twin towers with identical
characteristics. Currently, Spine A is approximately 15%
constructed (Refer picture 1) and Spine B tower
construction is yet to be commenced. Under the revised
scheme, Spine A tower shall be constructed fully in
Phase 1 and Spine B tower shall be constructed in
Phase 2."
...
9. It is stated by the learned Counsel for the Respondents that there has been
construction of only 15% in one Tower and other has not even started, the project
was quite incomplete. There are 1881 allottees out of which 861 allottees have
filed the claims it is submitted.
10. Having heard learned Counsel for both the sides and having gone through
the material pointed out to us and going through the clauses from the agreement
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 6 of 7 referred to, we find that these fine print clauses are quite loaded in favour of the
Corporate Debtor/builder. We do not find substance in the argument that the
allottees were required to adopt options as available in the agreement as we find
that IBC has given option to the allottees to move before the Adjudicating
Authority for relief under IBC and they have been treated as Financial Creditors.
When timely possession as per the agreement has not been delivered, although
it should have been delivered somewhere in April, 2018, Financial Creditor is
entitled to claim that there is default. Merely because in the format, the Financial
Creditor did not mention the date of default, considering the admitted facts, the
default is apparent on record. There is no dispute that till today, possession has
not been handed over and even the affidavit filed by the Corporate Debtor,
referred to above, shows poor progress in the infrastructure which has been put
up.
For the above reasons, we do not find any merit in the appeal. Appeal filed
is rejected.
[Justice A.I.S. Cheema] Member (Judicial)
(Kanthi Narahari) Member(Technical)
(V P Singh) Member(Technical) Akc/Md
Company Appeal (AT)(Insolvency) No. 645 of 2019 Page 7 of 7
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free