Manisha Satish Mahale and others vs The State of Maharashtra through its Secretary and another
- Neutral2025:BHC-AUG:36145
Ratio decidendi
The rule this decision rests on
Where a reference application under Section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 is filed with a delay of a short duration (such as 11 days), and the applicant furnishes a reasonable explanation for the delay arising from procedural matters inherent in acquisition proceedings, the Collector is bound by the proviso to Section 64(2) to adopt a liberal, pragmatic and justice-oriented approach in exercising discretion to condone the delay, rather than applying a hyper-technical construction that would mechanically reject the application on limitation grounds and deprive the landowner of their statutory right to seek determination of fair compensation.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Manisha Satish Mahale and others VERSUS The State of Maharashtra through its Secretary and another
Mr. A. B. Kale, Advocate for petitioners Mr. R. S. Wani, AGP for respondent-State
CORAM : Smt. Vibha Kankanwadi & Hiten S. Venegavkar, JJ. DATE : 10th December, 2025
ORDER (Per: Hiten S. Venegavkar) :
-
1. The present proceedings instituted under Article 226 of the
Constitution of India, assails the order dated 22.04.2025, passed by the
Collector, whereby the petitioner's reference application under Section 64
of the Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2023, (hereinafter referred to as
"the 2013 Act") has been rejected solely on the ground of delay. The
petitioners further seek a direction to the Collector to restore and
adjudicate the reference on its own merits.
2. The material facts are not in dispute. The petitioner's land
came to be acquired for the construction of the Surat-Dhule Bypass
Road. In the acquisition proceedings, the competent authority issued
notices under Section 21 of the Act on 18.01.2023 and thereafter, a final
award was passed on 03.05.2023. By the said award, compensation of
WP-13634-2025.odt 1 of 6 Rs. 6,94,00,000/- only was granted. The petitioner received part
compensation on 24.05.2023 and the balance on 24.07.2023. Being
satisfied with the quantum of compensation, the petitioners submitted a
Reference Application bearing No. 710 of 2024, on 14.09.2023, seeking
enhancement under Section 64 of the 2013 Act. It is the petitioners' case
that due to the involvement of several contesting parties and the
consequential delay in completion of stamp duty formalities, certain
procedural delays occurred in filing the reference, which ultimately
resulted in a delay of only 1 week and 4 days beyond the prescribed
limit.
3. The record indicates that notices came to be issued by the
Collector on 31.12.2024 calling upon the petitioner to submit their
response in the matter. A detailed reply was accordingly filed on
09.01.2025, explaining the factual circumstances surrounding the minor
delay and setting out the grounds for seeking reference.
However, by the impugned order dated 22.04.2025, the Collector
rejected the reference holding that it was barred by limitation and that
no sufficient cause for condonation has been established. It is also
evident that the collector proceeded to pass the impugned order without
affording the petitioners any opportunity of personal hearing.
4. The learned advocate for the petitioners contended that the
WP-13634-2025.odt 2 of 6 short delay of merely 11 days ought to have been condoned in view of
the proviso to section 64(2) of the 2013 Act, which empowers the
Collector to entertain a delayed reference upon being satisfied that the
applicant had sufficient cause. It was urged that the statutory scheme
itself contemplates a liberal construction, as the proviso authorizes
condonation for a further period of one year beyond the primary
limitation. Reliance was placed upon the well-settled principles
enunciated by the Hon'ble Supreme Court in Collector, Land
Acquisition, Anantnag Vs. Mst. Katiji, reported in (1987) 2 SCC 107,
wherein the Court held that a justice oriented approach must be adopted
while considering application for condonation of delay and that
substantial justice must prevail over technicalities. In the said judgment,
the Hon'ble Supreme Court observed that refusal to condone delay may
result in meritorious matters being thrown out at the threshold and
therefore, a pragmatic and liberal interpretation should inform the
exercise of discretion. The Court emphasized that litigants do not stand
to benefit by filing delayed appeals and that Court should not take a
pedantic approach that defeats substantive rights.
5. The petitioners further relied upon the Hon'ble Supreme
Court's judgment in N. Balakrishnan Vs. M. Krishnamurthy (1998) 7
SCC 123 wherein it was held that the length of delay is immaterial so
long as sufficient cause is shown and that a short delay particularly
WP-13634-2025.odt 3 of 6 deserves liberal condonation unless malafides or dilatory tactics are
evident. The Court clarified that the primary function of limitation law is
not to destroy rights but to ensure timely prosecution. Hence, a
reasonable and justice-oriented assessment must govern condonation of
application. In land acquisition matters, courts have adopted the
principles that minor delays in filing reference under Section 18 of the
Land Acquisition Act, 1894, which is pari materia with Section 64 of the
2013 Act, should ordinarily be condoned when no negligence or malafide
can be attributed and when refusal to condone would result in grave
prejudice to the landowners whose lands have been compulsorily taken.
6. The learned AGP appearing for the State supported the
impugned order and submitted that although the delay was short, the
petitioners had failed to expressly and satisfactorily explain every day's
delay and had even denied the existence of delay. It was contended that
the Collector is bound by the statutory limitation and cannot exercise
discretion in absence of a clear explanation.
7. Having heard both the sides and upon perusal of the material
on record, this Court is of the considered view that the approach adopted
by the Collector is unsustainable. The delay involved is only of one week
and four days. The Hon'ble Supreme Court through a consistent line of
authorities, beginning with Katiji (supra), has laid down that Court
WP-13634-2025.odt 4 of 6 should adopt a liberal, pragmatic and justice oriented approach in
matters of condonation, particularly where the delay is short and the
litigant stands to suffer severe prejudices if technicalities are allowed to
prevail. The Collector, being a statutory authority exercising quasi-
judicial powers, is equally bound to apply these principles. The proviso to
section 64 of the 2013 Act vests the Collector with ample power to
condone delay up to a further period of one year. Conditional only upon
satisfaction regarding the cost shown. Thus, the legislature itself has
mandated a flexible and equitable approach.
8. In the present case, the explanation of procedural delays
arising out of the nature of acquisition proceedings, involvement of
multiple parties, and time consumed in completion of stamp duty
formalities cannot be said to be fanciful or insufficient, especially when
the delay is merely of 11 days. The Collector was duty bound to examine
the reasons in liberal spirit and to ascertain whether substantial justice
required condonation. Instead, the Collector has adopted a hyper
technical view by mechanically computing the delay and rejecting the
reference without considering the over arching objective of the statute,
which is to ensure fair compensation to landowners whose properties
have been compulsorily acquired. Furthermore, the denial of a personal
hearing, despite the quasi-judicial character of the decision, reinforces
the infirmity in the impugned order.
WP-13634-2025.odt 5 of 6
9. In light of these circumstances, and in view of the law
decided by declared by the Hon'ble Supreme Court and consistently
followed by this Court, the impugned order dated 22.04.2025 cannot be
sustained. The delay of one week and four days in filing the reference
application deserves to be condoned. Failure to do so would unjustly
deprive the petitioners of their statutory right to seek determination of
fair compensation.
10. Accordingly the order dated 22.04.2025 passed by the
Collector is quashed and set aside. The delay caused in filing the
petitioners' reference under section 64 of the 2013 act is hereby
condoned. The collector shall restore Reference Application No. 710 of
2024 to file and shall adjudicate the same on its own merits and in
accordance with law, after granting due opportunity of hearing to all
parties concerned. The petition is allowed in the above terms.
11. There shall be no orders as to costs.
(Hiten S. Venegavkar, J.) (Smt. Vibha Kankanwadi, J.)
B. S. Joshi
WP-13634-2025.odt 6 of 6
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free