Madhya Pradesh Housing And Infrastructure Development Board & Ors. vs B. S. S. Parihar & Ors.
- SCC(2015) 14 SCC 130
- Neutral2015 INSC 505
- SCR[2015] 6 SCR 841
Ratio decidendi
The rule this decision rests on
Where an allotment of land is made by a housing board under a scheme containing an express clause stating that the advertised cost is provisional and final price will be fixed after project completion, the allotee is bound by that condition and the board retains the power to demand final payment at a determined final price, regardless of delay in that determination. The right to allotment crystallises only upon communication of the allotment letter, not upon draw of lots; therefore the price prevailing on the date of the allotment letter, not the date of draw, applies. A statutory housing authority's determination of final land price must be conducted in accordance with its governing statute, rules, and scheme conditions. The authority may take into account the Collector's market value guidelines issued under the Stamp Act and valuation rules for purposes of determining the cost of land, and such determination is legally valid where the valuation was properly fixed by the competent District Valuation Committee. Although a statutory authority may lawfully exercise power to re-determine final price after registration and may be entitled to demand payment reflecting escalation in both land costs and construction materials, the exercise of such power is subject to the constitutional doctrine of proportionality and principles of reasonableness and fairness. An arbitrary, unreasonable or grossly disproportionate demand—such as fixing price at double previously-established rates with no justification tied to actual cost escalation—violates Article 14 and must be moderated. Where an authority is empowered to fix final price but exercises that power in a manner that fails the test of proportionality, a court may modify the demand by reference to established base rates, measurable escalation factors, and legitimate interest, in order to achieve a just balance between the authority's rights and the allottee's interests.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1801 OF 2015
MADHYA PRADESH HOUSING AND INFRASTRUCTURE DEVLOPMENT BOARD …APPELLANT
Vs. B.S.S. PARIHAR & ORS. …RESPONDENTS AND CIVIL APPEAL NOS.1802-1803 OF 2015
MADHYA PRADESH HOUSING AND INFRASTRUCTURE DEVLOPMENT BOARD …APPELLANT
Vs. DR. SUDHA JAIN & ORS. ETC. …RESPONDENTS
J U D G M E N T
V. GOPALA GOWDA, J.
Civil Appeal No. 1801 of 2015 by special leave
has been filed against the impugned judgment and Signature Not Verified
order dated 31.7.2014 passed in Writ Appeal No. 1565 Digitally signed by Shashi Sareen Date: 2015.10.26 08:17:03 IST Reason: 2
of 2013 by the High Court of Judicature at Madhya
Pradesh at Jabalpur, whereas C.A. Nos. 1802-1803 of
2015 by special leave have been filed against the
impugned judgment and order dated 31.7.2014 passed in
Writ Appeal Nos. 1550 of 2013 and 1563 of 2013 by the
same High Court. In both the matters, the dispute
relates to the fixation of the price of the under
construction 36 Duplex/Triplex HIG Houses, situated
in “Riviera Towne”, Bhopal, by the appellant-Madhya
Pradesh Housing and Infrastructure Development Board
(for short “the appellant-Board”) and the method
adopted by them for fixing the price of the
properties in dispute and linking the cost price of
the land with the Collector’s guidelines on the date
of completion of the project in the case of Self
Financing Scheme. The High Court dismissed the writ
appeals filed by the appellant-Board and quashed the
enhanced/final demand for price fixation of land by
the appellant-Board.
2. The brief facts of the case are stated hereunder
to appreciate the rival legal contentions urged on
behalf of the parties:
An advertisement was published on 9.11.2007 in 3
the local daily newspaper ‘Dainik Bhaskar’ regarding
the Housing Scheme which was floated by the
appellant-Board for the allotment of 36 residential
houses for the employees of the State Government and
the State Public Sector Undertaking under the name of
“Riviera Towne” in Bhopal with the following terms
and conditions :-
1. Application forms for residential houses in Riviera Towne, Bhopal can be purchased at a cost of Rs.250/- from the Punjab National Bank, R.S.S. Market Panch Bus Stop, Bhopal on all working days between 21.11.2007 and 7.12.2007 and Registration Amount/Banker’s Cheque/Demand Drafts can be deposited in the above bank on all working days till 7.12.2007.
2. In case the number of applications are more than the number of premises advertised for sale, the registration will be done through a system of lottery which will be held at 4.00 pm on 14.12.2007 in the office of Estate Officer.
3. Preference in registration will be given to those who pay the total estimated amount in one lump sum.
4. Apart from the sale price, other charges and maintenance fee shall be payable as per the Board rules.
5. Once registration is sanctioned under Self Financing Scheme, the applicants have to pay the balance amount in instalments as per the intimation given by the Board.
6. Costs of the houses shown in this advertisement are totally provisional and the final fixation of the price 4
will be done after completion of the Scheme. Allottees have to pay the difference of tentative cost and final sale price in fixation of final cost on intimation within the time stipulated.
7. Other taxes and lease rent shall be payable as per rules.
8. Applications for registration are invited from the officers and employees of various departments of the Madhya Pradesh Government and undertakings Institutions. Reservation of houses will be in accordance with the rules.
9. Even after publication of two advertisements for registration of the house, if some houses still remain available, then application will be invited from General Category as per rules.
10. Other terms and conditions apply.
Type No. Approx. Approx. Estimated Regn.
of carpet plot area Cost (in Amount House area in in Sq. lakhs) (in Sq. mtrs. mtrs. lakhs)
Nice 18 184.57 150 40.00 4 Duplex sq.mtrs.
Nice 14 228.25 150 45.00 4.50 Triplex sq.mtrs.
Nice 4 223.51 223 53.00 5.50 Duplex sq.mtrs. Corner
XXX XXX
3. The appellant-Board held the draw of lots for the
allotment of the said houses in dispute and the 5
successful applicants were notified by the
appellant-Board vide communication letter dated
20.12.2007 about the allotment of the said houses in
their favour. The appellant-Board also took the
administrative approval on 3.1.2008 for the
construction of 36 houses of the disputed properties.
The appellant-Board also constituted a Price Fixation
Committee in its 199th meeting for the fixation of the
rational price for the said houses. They also issued
two Circulars dated 30.9.2008 and 24.10.2008 relating
to the fixation of cost of the said properties in
dispute.
4. The Price Fixation Committee worked out the
prices of the said 36 residential houses as mentioned
below :-
Total Flats-18 Total Flats-14 Total Flats-4 Plot area -150 sq. Plot area-150 sq. Plot area-223 mts. mts. sq. mts.
Built up area- Built up area Built up area 184.57 sq.mts. -228.25 sq. mts. -223.51 sq. mts.
Cost - Cost-Rs.55,91,000/ Cost-Rs.66,17,00 Rs.49,53,000/- - 0/-
Upon getting the tentative cost of construction
of the houses and on the basis of the revised
calculations and price determination of the said 6
properties in dispute and after the receipt of
tender, the demand letters were issued on 18.6.2009
to the respondent-allottees requesting them to submit
their consent or dissent to the enhanced estimated
cost in writing within 15 days from the date of the
issuance of the letter.
5. The construction of the houses started from
30.6.2009 and almost 90% of the allottees gave their
consent to the revised cost of the properties in
dispute as determined by the appellant-Board on the
report of the Price Fixation Committee.
6. The appellant-Board, vide letter dated 7.7.2009,
sought for consent from the remaining
allottees-respondents, who had not given their
consent with regard to the revised fixation of prices
on the said disputed properties, stating thereby that
if they fail to do so, they will not be allotted the
houses and the registration amount that they had
earlier given towards the allotment of the houses
will be refunded to them with interest as per the
rules of the Madhya Pradesh Co-operative Societies
Act, 1960 (hereinafter called as “the Societies Act”)
and Madhya Pradesh Co-operative Societies Rules, 7
1962(hereinafter called as “the Rules”).
7. On 7.10.2009, the appellant-Board had informed
that all the allotments that were made to the
respondents subsequent to the issuance of the
circulars dated 30.9.2008 and 24.10.2008, will be
final and they will be bound by the said circulars.
The draw of lots was conducted on 22.12.2009 for the
allocation of house numbers to the eligible
applicants. In the meeting held on 2.12.2011, it was
decided by the appellant-Board that all the
allotments made to the respective applicants will be
governed by the notifications/circulars regarding the
cost of fixation of the properties in dispute and
also according to the appellant-Board.
8. The Price Fixation Committee in its meeting held
on 9.12.2011 and in its report dated 15.12.2011,
fixed the cost with regard to the houses to be
allotted under the said “Riviera Towne” Scheme. In
the report, the commencement of the Scheme is to be
considered to be from the date of the Work Order and
not from the date of the advertisement. Thereafter,
taking into consideration the final cost determined
by the Price Fixation Committee, the final demand 8
letters were issued to the successful allottees on
24.12.2011.
9. Being aggrieved by the action of the
appellant-Board, the respondents filed Writ Petition
No.15983 of 2012 before the learned single Judge of
the High Court of Madhya Pradesh, challenging the
decision of the Price Fixation Committee, whereby the
appellant-Board has directed the respondents to
deposit the price for the said houses allotted to
them at a highly enhanced rate which is 300% more
than the original price of the said properties in
dispute. The grievance of the respondents was that
they had applied for the said Scheme and had been
allotted houses in the year 2007 at the price
prevalent at the relevant period of time, subject to
reasonable escalation. But at the time of the
delivery of possession of the said properties in
dispute the appellant-Board has demanded the price of
Rs.30,000/- instead of Rs.9,000/- per sq. mtr. which
is highly unjustified on its part. The respondents
have further contended that the appellant-Board has
wrongly taken into consideration the subsequent
guidelines and notifications issued by the Collector, 9
notifying the price of the land for registration and
the stamp duty which is contrary to the law laid down
by this Court in a catena of cases.
10. The learned single Judge disposed of the said
writ petition on 24.9.2012, and directed the
appellant-Board to consider the representation of the
respondents and the legal opinion obtained by them
and decide the matter in accordance with the
decisions of this Court in a catena of cases, after
giving the respondent-allottees due opportunity of
being heard.
11. Though various representations were filed before
the appellant-Board by the allottees with regard to
the fixation of the cost of the properties in
dispute, the Commissioner of the appellant-Board by
order dated 8.3.2013, after considering the
representations of the respondent-allottees and by
referring to the various circulars regarding the cost
fixation, rejected the representations of the
allottees.
12. The said action of the Commissioner of the
appellant-Board led the respondents to file Writ 10
Petition No.5690 of 2013 and connected writ petitions
before the learned single Judge of the High Court.
During this period 3 applicants did not make the
initial payment of Rs.4 lakhs i.e. 10% of the
advertised tentative cost which resulted in the
cancellation of their registration to the said
properties and their duplex houses were put to
auction.
13. The learned single Judge of the High Court
disposed of the Writ Petition No.5690 of 2013 along
with the other connected writ petitions vide its
common order dated 21.11.2013. The learned single
Judge allowed the writ petitions of the respondents
and directed the appellant-Board to fix the price of
the land as it existed on the date of issuance of the
allotment letter and consequently quashed the land
price determined by the appellant-Board which was
based on the guidelines of the Collector.
14. Being aggrieved by the order dated 21.11.2013,
the appellant-Board filed Writ Appeals before the
Division Bench of the High Court which were dismissed
vide its common order dated 31.7.2014. The Division
Bench upheld the findings of the learned single 11
Judge, thereby quashing the enhanced/final demand
raised by the appellant-Board. Hence, these appeals
have been filed by the appellant-Board, urging
various legal grounds and contentions and prayed to
set aside the impugned order passed by the High
Court.
15. Mr. Sunil Gupta, the learned senior counsel
appearing on behalf of the appellant-Board has relied
upon the judgment of this Court in the case of Delhi
Development Authority v. Pushpendra Kumar Jain1, in
support of his case, wherein this Court has held that
the allottee was bound to make the deposit at the
enhanced rate as per the demand raised by the D.D.A.
if he wanted to secure the flat. It was further held
that an allottee gets an indefeasible right to
allotment only on the date of communication of
allotment and not on the date of draw of lots which
is only a process to identify or select the persons
for allotment and not the allotment itself. It was
further held that when the cost was enhanced prior to
the allotment letter, demand of the enhanced rate was
justified. The learned senior counsel has contended
1 (1994) Supp (3) SCC 494 12
that the impugned order of the High Court was not
right as the same is contrary to the case of Delhi
Development Authority (supra), which is squarely
applicable to the fact situation of the instant case
and the High Court has failed on its part by ignoring
the same and passing the order against the
appellant-Board.
16. It has been further contended by the learned
senior counsel that the High Court has gravely erred
in determining the price of the properties in dispute
at a rate prevalent during the period 2007-2008 or
2008-2009, as the appellant-Board has sold and
executed the sale deeds of 1718 flats and 302 plots
as per the guidelines of the Collector issued from
time to time which would become applicable to the
allottees as well.
17. The learned senior counsel has further contended
that the fixation of the cost of the properties in
dispute has been done in accordance with the Scheme,
the rules and the policy of the appellant-Board and
the so-called allotment made in favour of the
allottees is not an allotment but only a registration
granted to them which the High Court has misconstrued 13
as allotment of the said land.
18. On the contrary, the learned senior counsel
appearing on behalf of the respondents has sought to
justify the impugned judgment and order contending
that the judgment of the High Court is perfect and
justified. He has contended that on the issue of
fixing the price of the land, the High Court has
rightly held that the price or cost of the said land
should be in accordance with the price or the cost of
land which existed on the date of allotment.
19. He has further contended that the High Court has
rightly held that the date of allotment is the date
on which the offer of the respondents was accepted
and their applications were registered and the
allotments to the land were made accordingly, which
is clear from a bare perusal of the letters
indicating the acceptance of registration in
allotment.
20. The learned senior counsel has further contended
that the main dispute is with regard to the
difference of the amount of the cost of the land that
is being demanded by the appellant-Board as per the
Collector’s guidelines prevailing in the year 2011-12 14
and the actual cost that existed on the date of
allotment of the said land. The applicants have
already paid the entire cost as per the demand of the
appellant-Board and have in fact paid 10% extra
towards the cost of the said property and despite the
same, the property has not been handed over to them
which is a grave miscarriage of justice and the
respondents have been suffering for a long time.
21. We have heard both the parties. On the basis of
the aforesaid rival legal contentions urged on behalf
of the parties and on perusal of the findings
recorded by the High Court in its impugned judgment
and order, we have to answer the points of dispute on
the basis of the evidence produced on record. We
record our reasons hereunder:-
The contentions urged on behalf of the
respondents that once the appellant-Board has made
the allotment of the said plot of land, it is
debarred from raising the cost of construction or
claiming enhanced prices for the said land, is wholly
untenable in law in view of the clauses contained in
the advertisement published in the newspaper Dainik
Bhaskar dated 09.11.2007, which read that the cost of 15
the houses shown in this advertisement are totally
provisional and the final fixation of the price will
be done after the completion of the Scheme.
Therefore, the allottees will have to pay the
difference between the tentative cost and the final
sale price of the land which is based on the fixation
of the final cost of the land, within the stipulated
time.
Therefore, in view of the aforesaid clause, the
allotment of the said plot of land in favour of the
respondent-allottees is only provisional in nature
and the same would be subject to the final fixation
of the price of the land that will be done after the
completion of the Scheme as the said clause is
binding upon the respondent- allottees.
22. Further, the said clause is also traceable to
Section 50 of the Madhya Pradesh Griha Nirman Mandal
Adhiniyam, 1972 (in short ‘the Act, 1972’), wherein
the appellant-Board is empowered to retain, lease,
sell, exchange or otherwise dispose of any land,
building or other property vesting with it, situated
in the area comprised in any housing Scheme or in any
adjoining area. The Madhya Pradesh Housing Board 16
Accounts Rules, 1991, ( in short “the Rules, 1991”)
were framed in this regard, the relevant provisions
of which are necessary to be extracted hereunder:
“5.4.SALE PRICE Sale price of sites and buildings shall be separately determined in accordance with the guidelines issued by the Board. But where yield a sale price for any reason different from cost price determined under Rule 5.3.2 and 5.3.3 (e.g. due to adoption of different rates of overheads for different income groups, charging premium from higher income groups for appreciation in land value, grant of concessions to Board’s employees adoption of average expenditure on project instead of year wise expenditure for calculating overheads on interest, adoption of uniform rate of interest of the entire construction period instead of varying rates of interest for separate years), sales may be brought to account in the revenue section of project accounts without prejudice to the operation of Rules 5.3.2 and 5.3.3 (These rules deal with account adjustment in the expenditure section of project account upto the state of recording under the account head “cost of Sales”). Accordingly account adjustment regarding capitalization of overheads, transfer of assets from Divisions to Estate Management and incorporation of costs in the account “Cost of Sales” in the ledgers of Estate Management shall be carried out immediately on completion of project and not held up till sale price approved by the Competent Authority.
5.7 LAND 5.7.1 Land acquired shall be brought to account on accrual basis, land made over to the Board free of cost shall be brought to account at nominal price.
XXX XXX XXX 17
5.7.4 For the purpose of assessing the cost of a project, i.e., debiting “Cost of Sales” as well for the purpose of valuation of closing stock in Final Accounts, appreciation in land value shall be ignored. The Board may, however, take it into account for the purpose of determination of sale price.”
23. The final sale price which is fixed and
intimated to the allottees is in accordance with the
provisions of the Act 1972, the Rules, 1991 and the
clause of the advertisement which is binding on the
respondent allottees. Therefore, the High Court has
committed an error in law by quashing the demand
notice of the appellant-Board for the payment of the
final sale price and allowing the writ petitions of
the respondent-allottees without considering the
terms and conditions of the advertisement and the
statutory provisions of the Act and the Rules towards
the fixation of the cost of the land. On this
ground, the impugned judgments of both the learned
single Judge and the Division Bench of the High Court
are liable to be quashed and set aside.
24. The learned senior counsel on behalf of the
appellant-Board has rightly pointed out the
concurrent findings recorded in the impugned judgment
of the Division Bench, which has referred to the 18
judgment of the learned Single Judge, wherein he has
held that once the allotment of the said plot of land
is made, the appellant-Board is denuded of its power
to seek enhanced cost of land based on the
Collector’s guidelines, as erroneous in law. He has
also relied on the principles that have been laid
down in various cases of this Court including the
cases of Tamil Nadu Housing Board v. Service Society
& Anr2 and Delhi Development Authority (supra). He
has rightly pointed out that the said conclusions of
both the learned single Judge and the Division Bench
of the High Court are erroneous in law and the same
is a perverse finding of fact for the reason that
they have misconstrued the registration of the
applications and the allotments made with respect to
the land in dispute which is in accordance with the
clause published in the advertisement. Reliance has
been placed in the case of Delhi Development
Authority (supra) which reads thus:
“8……..No provision of law also could be brought to our notice in support of the proposition that mere draw of lots vests an indefeasible right in the allottee for allotment at the price obtaining on the date of draw of lots. In our opinion, since the 2 (2011) 11 SCC 13 19
right to flat arises only on the communication of the letter of allotment, the price or rates prevailing on the date of such communication is applicable unless otherwise provided in the Scheme. If in case the respondent is not willing to take or accept the allotment at such rate, it is always open to him to decline the allotment. We see no unfairness in the above procedure.”
25. The conditions stipulated in the advertisement
inviting applications from the applicants and the
provision provided under Section 50 Rule (5)(iv) of
the Act of 1972 and Rules 5.7.1 and 5.7.4 of the
Rules, 1991 would make it clear that the law laid
down in the Delhi Development Authority (supra) case
is aptly applicable to the fact situation of the
instant case. The same has not been considered by
the High Court while passing its impugned order. On
this ground also, the impugned judgment is liable to
be set aside.
26. The learned senior counsel on behalf of the
appellant-Board has rightly pointed out that the
determination of the sale price of the flats
allotted in favour of the respondent-allottees is
based on the cost price fixed as per the guidelines
provided by the Collector from time to time for the
relevant year for the final allotment. He has 20
further pointed out that the total number of
allottees who have applied to the advertisement
through the procedure of drawing the lottery for the
allotment of flats in their favour are 2531. The
allottees who have accepted the final cost are 1472.
The allottees who have not accepted the final cost
and filed a petition against the same are 84. There
are 975 applicants who have vacant houses and are
awaiting the decision of the courts in other cases
but they have neither accepted nor refused the final
cost fixation. Apart from the said factual position,
about 700 HIG & MIG and 1500 LIG and EWS housing
units would be further affected by the impugned
judgment of the High Court. The legal issue that is
present for our determination is, whether the demand
of the final sale price which has been fixed by the
appellant-Board in terms of the conditions
stipulated in the advertisement with regard to the
land in dispute for the year 2010-2011 which has
been done on the basis of the “Market Price Guiding
Principles, District, Bhopal” by the Collector under
Section 47(a) of the Indian Stamp Act, 1899 (Act NO.
2 of 1899), read with Section 75 of the Madhya 21
Pradesh Preparation and Revision of Market Value
Guidelines Rules, 2000 (hereinafter called as “the
Rules, 2000”), framed by the State Government for
the determination of the market price of immoveable
property and the tier review under Rule 4(b) of
Rules, 2000, the proposal of rates of market price
for the year 2011-2012, submitted by the
sub-District Valuation Committee before the District
Valuation Committee is legal and valid?
27. The provisos issued by the Central Valuation
Board vide letter No. 713/Ga.La./2011 Bhopal dated
29.03.2011 for the implementation of the rates of
plots of land, buildings and agricultural land in
Rule 3(2) of the Rules, 2000 and the after approval
of the rate of the market price proposed by District
Valuation Committee Guiding Principles (Guidelines)
for the year 2011-2012 for reckoning the market
price of the immovable property (plots of land,
building and agricultural land) situated in District
Bhopal under Rule 4(2)(c) of the Rules, 2000, are
forwarded by the Sub-Registrar of the Districts for
the purpose of issuing directions under Section
47-A, sub-Section (1) of the Indian Stamp Act, 1899. 22
The said valuation fixed by the District Valuation
Committee under the Chairmanship of the District
Collector of Bhopal is not under challenge by either
the allottees or any other person. Therefore, the
guiding principles for the determination of the
final sale price of the plots in favour of the
allottees cannot be termed as either erroneous or
error in law. Further, the learned senior counsel
for the appellant-Board has placed reliance upon the
judgment of this Court in the cases of BSEB v.
Suresh Pd. Sinha3 and State Of U.P. v. Synthetics &
Chemicals Ltd.4 in support of the proposition of law
upon the principal of binding precedents, wherein
this Court has held that any declaration or
conclusion arrived at without application of mind or
preceded without any reason cannot be deemed to be
declaration of law or authority of a general nature
and the same cannot been deemed as a precedent.
The learned senior counsel on behalf of the
appellant-Board has further rightly placed reliance
upon the judgment of this Court in the case of Tamil
Nadu Housing Board (supra) in support of his legal
3 (2009) 8 SCC 483 4 (1991) 4 SCC 139 23
submission wherein, this Court has held thus:
“18. There is no term or provision in the contract that if the Board does not determine the final price within three years from the date of allotment, the Board would lose the right to determine the final price thereafter or that the tentative price would become the final price. If on account of delay in determination of compensation for land acquisition or delay on the part of the contractors in completing the development works or construction, or if there are any encroachments or if there are pending claims of contractors regarding development or construction, the Board would not be able to determine the final cost within three years. But that did not mean that the tentative cost would become the final cost in the absence of such a provision in the letter of allotment or lease-cum-sale agreement.
20. Clause 17 states that except the fixation of price with reference to the compensation finally awarded by the courts, the Board should fix the price of the LIG house after taking into consideration the development charges, cost of amenities and cost of buildings within three years from the date of allotment. If the final price is so fixed, thereafter what could be increased is only the land cost component on account of any increase in compensation that may be awarded by the courts. If the Board had earlier fixed the final price, the Society’s contention might have merited acceptance as the component of price with reference to cost of development and amenities and cost of building would have attained finality on account of such final determination and only the increase on account of award of compensation for land could be demanded after such determination of final price. But where the final price 24
has not been determined at all, for whatsoever reason, and the final cost was being determined for the first time, the allottee cannot contend that only the increase on account of the land, and not the increase on account of development cost and construction cost, could be demanded. Where the final price has not been fixed, the Board could, after ascertainment of various costs, determine the final price even after three years, and the finality in regard to cost of development and amenities and the cost of construction, referred under Clause 17, would not apply.
30. Whenever allotments are made even before the completion of the development of land and construction, necessarily the cost that is shown by the authority or the Board will be tentative. In regard to the land cost, there may be claims for enhancement of compensation before the Reference Court with appeals to the High Court and this Court. Sometimes the entire process may take 10 to 15 years and till that process is concluded the final cost of the land cannot be determined. An allottee cannot therefore say that the authority cannot increase the cost after 12 years.
32. Therefore, an allottee cannot contend that the increase, if any, should be determined within three years and if the increase is not so determined, the tentative cost would itself become the final cost. Such an interpretation of Clause 17 would be illogical and unreasonable. If the Board is able to show that there was sufficient cause for the delay in deciding the final price and that it was beyond its control to determine the final cost earlier (or within three years) it will be entitled to final cost even if the claim is delayed by a few years. The allottee cannot refuse to pay it merely on 25
the ground of delay.
37. We find that the allottees/Society do not dispute that the cost of the land increased considerably on account of enhancement of compensation. The Board showed that the total cost of land inclusive of interest up to 31-3-1987 was Rs. 35,02,727 for 8 acres and 16,422 sq ft. The said figure was broadly accepted by the Society, in its calculation sheet. The Society arrived at the cost of a plot measuring 1040 sq ft as Rs. 3500 (paid as deposits) plus Rs. 8634 which aggregates to Rs. 12,134. But as noticed above, this is the proportionate cost worked out for 1040 sq ft out of the total cost of an extent of 33,64,902 sq ft (8 acres and 16,422 sq ft). It is not possible for the allottee to contend that he will pay only the proportionate actual cost of his plot. If the cost of the plot has to be worked out, the cost relating to proportionate share in the common/service areas (roads, parks, playgrounds, etc.) should be added. That means at least addition of another 40% to the price worked out for the actual extent of the plot. With reference to the cost worked out by the Society, if 40% is added, the increased cost of plot would be around Rs. 16,987.60. According to the Society the original tentative cost for the plot was Rs. 3000. Therefore the increase in cost would be around Rs.
14,000. What is demanded as additional amount is Rs. 16,770. The difference is hardly Rs. 2770 which may be attributable to the increase in the cost of development/construction. It cannot therefore be said that the amount claimed under the demand notice dated 21-5-1988 is excessive or unreasonable. Neither party has given the full data or facts or accounts. The allotment was made 35 years back. No purpose would be served by remitting the matter for re-examination. 26
In the facts and circumstances, we are satisfied that the demand is not open to challenge.”
In view of the aforesaid decisions of this
Court, both the learned single Judge and the
Division Bench of the High Court have misconstrued
the terms and conditions stipulated in the
advertisement and have erroneously applied the same
to the fact situation of the present case and came
to the erroneous conclusion by placing reliance upon
the judgment of this Court in the case of M.P.
Housing Board v. Anil Kumar Khiwani5, wherein this
Court by referring to the observations made by the
Division Bench in its judgment at paras
6,7,8,9,10,11,12, 16 and 17 held that the Board was
not entitled to raise the price of 71 lakhs
particularly, when it was guilty of delaying the
project. The strong reliance placed upon the
aforesaid judgment by both the learned single Judge
and the Division Bench of the High Court in holding
that the appellant-Board is not empowered to
determine the final cost of the properties in
dispute is wholly erroneous in law as the said 5 (2005) 10 SCC 796 27
judgment does not deal with the role and the power
of the appellant-Board to determine the final price
of the allotted plot which power is in conformity
with the provisions of Section 50 of the Act of 1972
and the relevant rules referred to supra and the
terms and conditions of the advertisement.
Therefore, the said judgment does not have the
binding precedent for the proposition of law that
the appellant-Board does not have the power to
re-determine the final price of the allotted
properties after the applications of the allottees
were registered. In this regard, the learned senior
counsel for the appellant-Board has rightly placed
reliance upon the judgment of this Court in the case
of State of U.P. v. Synthetics and Chemicals Ltd.
(supra), the relevant paras of which read thus:
“41. Does this principle extend and apply to a conclusion of law, which was neither raised nor preceded by any consideration. In other words can such conclusions be considered as declaration of law? Here again the English courts and jurists have carved out an exception to the rule of precedents. It has been explained as rule of sub-silentio. “A decision passes sub-silentio, in the technical sense that has come to be attached to that phrase, when the particular point of law involved in the decision is not perceived by the court or present to its mind.”. In 28 Lancaster Motor Company (London) Ltd. v. Bremith Ltd. the Court did not feel bound by earlier decision as it was rendered ‘without any argument, without reference to the crucial words of the rule and without any citation of the authority’. It was approved by this Court in Municipal Corporation of Delhi v. Gurnam Kaur. The bench held that, ‘precedents sub-silentio and without argument are of no moment’. The courts thus have taken recourse to this principle for relieving from injustice perpetrated by unjust precedents. A decision which is not express and is not founded on reasons nor it proceeds on consideration of issue cannot be deemed to be a law declared to have a binding effect as is contemplated by Article 141. Uniformity and consistency are core of judicial discipline. But that which escapes in the judgment without any occasion is not ratio decidendi. In B. Shama Rao v. Union Territory of Pondicherry it was observed, ‘it is trite to say that a decision is binding not because of its conclusions but in regard to its ratio and the principles, laid down therein’. Any declaration or conclusion arrived without application of mind or preceded without any reason cannot be deemed to be declaration of law or authority of a general nature binding as a precedent. Restraint in dissenting or overruling is for sake of stability and uniformity but rigidity beyond reasonable limits is inimical to the growth of law.
42. Effort was made to support the conclusion, indirectly, by urging that the State having raised same objections by way of review petition and the same having been rejected it amounted impliedly as providing reason for conclusion. Law declared is not that can be culled out but that which is stated as law to be accepted and applied. A conclusion without reference to relevant provision of law is weaker than even casual observation. In the order of Brother Thommen, the extracts from the judgment of the 29
Constitution Bench quoted in extenso demonstrate that the question of validity of levy of sales and purchase tax was neither in issue nor was it raised nor is there any discussion in the judgment except of course the stray argument advanced by the learned Attorney General to the following effect:
“But alcohol not fit for human consumption are not luxuries and as such the State legislatures, according to Attorney General, will have no power to levy tax on such alcohol.” Sales tax or purchase tax under Entry 54 is levied on sale or purchase of goods. It does not contemplate any distinction between luxury and necessity. Luxuries are separately taxable under Entry 62. But that has nothing to do with Entry 54. What prompted this submission is not clear. Neither there was any occasion nor there is any constitutional inhibition or statutory restriction under the legislative entry nor does the taxing statute make any distinction between luxuries and necessities for levying tax. In any case the bench did not examine it nor did it base its conclusions on it. In absence of any discussion or any argument the order was founded on a mistake of fact and, therefore, it could not be held to be law declared. The bench further was not apprised of earlier Constitution Bench decisions in Hoechst Chemicals v. State of Bihar and Ganga Sugar Mill v. State of U.P. which specifically dealt with the legislative competence of levying sales tax in respect of any industry which had been declared to be of public importance. Therefore, the conclusion of law by the Constitution Bench that no sales or purchase tax could be levied on industrial alcohol with utmost respect fell in both the exceptions, namely, rule of sub-silentio and being in per incuriam, to the binding authority of the precedents.” 30
Further reliance has been placed upon the
decision of this Court in the case of Bihar
School Examination Board v. Suresh Prasad Sinha,
(supra), the relevant paras of which read thus:
“18. The courts should guard against the danger of mechanical application of an observation without ascertaining the context in which it was made. In CIT v. Sun Engg. Works (P) Ltd.
“39. … It is neither desirable nor permissible to pick out a word or a sentence from the judgment of this Court, divorced from the context of the question under consideration and treat it to be the complete ‘law’ declared by this Court. The judgment must be read as a whole and the observations from the judgment have to be considered in the light of the questions which were before this Court. A decision of this Court takes its colour from the questions involved in the case in which it is rendered and while applying the decision to a later case, the courts must carefully try to ascertain the true principle laid down by the decision of this Court and not to pick out words or sentences from the judgment, divorced from the context of the questions under consideration by this Court, to support their reasonings.”
19. It is also necessary to keep in mind the following principles laid down in Govt. of Karnataka v. Gowramma with reference to precedential value of decisions:
“10. ‘12. … Reliance on the decision without looking into the factual background of the case before it, is 31
clearly impermissible. A decision is a precedent on its own facts. Each case presents its own features. It is not everything said by a Judge while giving [a] judgment that constitutes a precedent. The only thing in a Judge’s decision binding a party is the principle upon which the case is decided and for this reason it is important to analyse a decision and isolate from it the ratio decidendi. According to the well-settled theory of precedents, every decision contains three basic postulates: (i) findings of material facts, direct and inferential. An inferential finding of facts is the inference which the Judge draws from the direct, or perceptible facts; (ii) statements of the principles of law applicable to the legal problems disclosed by the facts; and (iii) judgment based on the combined effect of the above. A decision is an authority for what it actually decides. What is of the essence in a decision is its ratio and not every observation found therein nor what logically flows from the various observations made in the judgment. The enunciation of the reason or principle on which a question before a court has been decided is alone binding as a precedent. (See State of Orissa v. Sudhansu Sekhar Misra and Union of India v. Dhanwanti Devi.) A case is a precedent and binding for what it explicitly decides and no more. The words used by Judges in their judgments are not to be read as if they are words in an Act of Parliament. In Quinn v. Leathem the Earl of Halsbury, L.C. observed that every judgment must be read as applicable to the particular facts proved or assumed to be proved, since the generality of the expressions which are found there are not intended to be the exposition of the whole law but governed and qualified by the particular 32
facts of the case in which such expressions are found and a case is only an authority for what it actually decides.’
11. ‘15. … Courts should not place reliance on decisions without discussing as to how the factual situation fits in with the fact situation of the decision on which reliance is placed. Observations of courts are neither to be read as Euclid’s theorems nor as provisions of the statute and that too taken out of their context. These observations must be read in the context in which they appear to have been stated. Judgments of courts are not to be construed as statutes. To interpret words, phrases and provisions of a statute, it may become necessary for Judges to embark into lengthy discussions but the discussion is meant to explain and not to define. Judges interpret statutes, they do not interpret judgments. They interpret words of statutes; their words are not to be interpreted as statutes.
* * *
18. The following words of Lord Denning in the matter of applying precedents have become locus classicus:
“Each case depends on its own facts and a close similarity between one case and another is not enough because even a single significant detail may alter the entire aspect. In deciding such cases, one should avoid the temptation to decide cases (as said by Cardozo) by matching the colour of one case against the colour of another. To decide therefore, on which side of the line a case falls, the broad resemblance to another case is not at all decisive.
* * * Precedent should be followed only so far as it marks the path of justice, but you must cut the dead wood and trim off the 33
side branches else you will find yourself lost in thickets and branches. My plea is to keep the path to justice clear of obstructions which could impede it.”
20. In Sarva Shramik Sanghatana (KV) v. State of Maharashtra this Court cited the following passage from Quinn v. Leathem with approval:
“… Now, before discussing Allen v. Flood and what was decided therein, there are two observations of a general character which I wish to make, and one is to repeat what I have very often said before, that every judgment must be read as applicable to the particular facts proved, or assumed to be proved, since the generality of the expressions which may be found there are not intended to be expositions of the whole law, but [are] governed and qualified by the particular facts of the case in which such expressions are to be found. The other is that a case is only an authority for what it actually decides. I entirely deny that it can be quoted for a proposition that may seem to follow logically from it. Such a mode of reasoning assumes that the law is necessarily a logical code, whereas every lawyer must acknowledge that the law is not always logical at all.”
28. Applying the guideline rates in relation to
the valuation of the land in accordance with Circular
No. 21 of 2008 dated 24.10.2008, for the
determination of the cost of the L.I.G./E.W.S.
buildings, the Board has passed the following
resolution:-
34 “Following decision has been taken by the competent authority in connection with the buildings of all the categories of E.W.S./L.I.G. in all the districts of Madhya Pradesh whose registration has been carried out before 19th of December, 2011 and whose final determination of the value is effected the Circular No.21/2008 dated 24.10.2008:-
(i) From the date of coming into force of the Circular of the Board vide No. 21/08 dated 24.10.2008 and in between the period of coming into force of the Circular No.15/11 dated 19.12.2011 the cost of the land in the final valuation of the buildings of E.W.S/L.I.G. duly advertised, the value taken in the initial determination of the value, be determined.
(ii) In the final determination of the value of the aforesaid
E.W.S./L.I.G. buildings, following shall be the criteria/ingredients:-
(a) The cost of the land which was determined at the time of the registration.
(b) Actual development expenditure incurred on the plot since after the registration.
(c) Total construction cost.
(d) Supervision fees (At the rate prevalent at the time of the registration).
(e) Penal interest against the remaining instalments as per the rules of the Board (at the rate prevalent from time to time).
(f) Other charges as per the rules of the Board……”
The said guidelines have been laid down by the 35
Development Board during the pendency of this
proceeding. The submission made by the learned senior
counsel on behalf of the allottees is that the said
benefit may be extended to these allottees involved
in these proceedings. The rates with regard to the
cost of flats as on the date of the publication of
the advertisement in November, 2007, the cost of the
flats fixed in the year June, 2009 and the total
final demand for the cost of the flats in December,
2011 are furnished in the table which are extracted
herein below for our perusal:-
Type of Advt. Cost Cost as Total Final House (In Lakhs) told in Demand in In November, June, Dece., 2011 2007 2009 (In (In Lakhs) Lakhs)
Nice 40.00 49.53 81.73 Duplex Nice 45.00 55.91 88.97 Triplex Nice Duplex 53.00 66.17 120.44 Corner
29. Dr. Rajeev Dhawan, the learned senior counsel
for the respondent-allottees in C.A. Nos. 1802-1803
of 2015, has placed strong reliance upon Article 14
of the Constitution of India and upon the judgment of
this Court in the case of Coimbatore District 36
Central Coop. Bank v. Employees Association6, in
support of the proposition of law that the
appellant-Board while exercising its power to fix the
final rates of the allotted plots by invoking the
clause contained in the notification issued by it for
inviting applications, wherein it has retained its
right to determine the final price of the allotted
plot, must pass the test of the doctrine of
proportionality in determining the final price of the
plot. He has placed strong reliance in support of his
case upon the following decisions of this Court in
the cases of Coimbatore District Central Coop. Bank
(supra), Teri Oat Estates (P) Ltd. v. U.T.
Chandigarh7, Om Kumar v. Union of India8 and State of
U.P. v. Sheo Shanker Lal Srivastava9 and has
contended that the same have to be applied to the
fact situation of the present case with regard to the
legal principle of doctrine of proportionality. The
relevant paras of the above mentioned judgments are
stated hereunder:
In Coimbatore District Central Coop. Bank (supra),
6 (2007) 4 SCC 669 7 (2004) 2 SCC 130 8 (2001) 2 SCC 386 9 (2006) 3 SCC 276 37
this Court has held thus:
“17. So far as the doctrine of proportionality is concerned, there is no gainsaying that the said doctrine has not only arrived in our legal system but has come to stay. With the rapid growth of administrative law and the need and necessity to control possible abuse of discretionary powers by various administrative authorities, certain principles have been evolved by courts. If an action taken by any authority is contrary to law, improper, irrational or otherwise unreasonable, a court of law can interfere with such action by exercising power of judicial review. One of such modes of exercising power, known to law is the “doctrine of proportionality”.
18. “Proportionality” is a principle where the court is concerned with the process, method or manner in which the decision-maker has ordered his priorities, reached a conclusion or arrived at a decision. The very essence of decision-making consists in the attribution of relative importance to the factors and considerations in the case. The doctrine of proportionality thus steps in focus true nature of exercise—the elaboration of a rule of permissible priorities.
19. de Smith states that “proportionality” involves “balancing test” and “necessity test”. Whereas the former (balancing test) permits scrutiny of excessive onerous penalties or infringement of rights or interests and a manifest imbalance of relevant considerations, the latter (necessity test) requires infringement of human rights to the least restrictive alternative. [Judicial Review of Administrative Action (1995), pp. 601-05, para 13.085; see also Wade & Forsyth:
Administrative Law (2005), p. 366.]
20. In Halsbury’s Laws of England (4th Edn.), Reissue, Vol. 1(1), pp. 144-45, para 78, it is stated:
“The court will quash exercise of 38
discretionary powers in which there is no reasonable relationship between the objective which is sought to be achieved and the means used to that end, or where punishments imposed by administrative bodies or inferior courts are wholly out of proportion to the relevant misconduct. The principle of proportionality is well established in European law, and will be applied by English courts where European law is enforceable in the domestic courts. The principle of proportionality is still at a stage of development in English law; lack of proportionality is not usually treated as a separate ground for review in English law, but is regarded as one indication of manifest unreasonableness.””
In Teri Oat Estates (P) Ltd. (supra), it was held as
under:
“46. By proportionality, it is meant that the question whether while regulating exercise of fundamental rights, the appropriate or least restrictive choice of measures has been made by the legislature or the administrator so as to achieve the object of the legislation or the purpose of the administrative order, as the case may be. Under the principle, the court will see that the legislature and the administrative authority “maintain a proper balance between the adverse effects which the legislation or the administrative order may have on the rights, liberties or interests of persons keeping in mind the purpose which they were intended to serve”.
49. Ever since 1952, the principle of proportionality has been applied vigorously to legislative and administrative action in India. While dealing with the validity of 39
legislation infringing fundamental freedoms enumerated in Article 19(1) of the Constitution of India, this Court had occasion to consider whether the restrictions imposed by legislation were disproportionate to the situation and were not the least restrictive of the choices. In cases where such legislation is made and the restrictions are reasonable; yet, if the statute concerned permitted administrative authorities to exercise power or discretion while imposing restrictions in individual situations, question frequently arises whether a wrong choice is made by the administrator for imposing the restriction or whether the administrator has not properly balanced the fundamental right and the need for the restriction or whether he has imposed the least of the restrictions or the reasonable quantum of restrictions etc. In such cases, the administrative action in our country has to be tested on the principle of proportionality, just as it is done in the case of main legislation. This, in fact, is being done by the courts. Administrative action in India affecting the fundamental freedom has always been tested on the anvil of the proportionality in the last 50 years even though it has not been expressly stated that the principle that is applied is the proportionality principle.
50. In Om Kumar, however, this Court evolved the principle of primary and secondary review. The doctrine of primary review was held to be applicable in relation to the statutes or statutory rules or any order which has the force of statute. The secondary review was held to be applicable inter alia in relation to the action in a case where the executive is guilty of acting patently arbitrarily. This Court in E.P. Royappa v.
State of T.N. noticed and observed that in such a case Article 14 of the Constitution of India would be attracted. In relation to other administrative actions as for example, 40
punishment in a departmental proceeding, the doctrine of proportionality was equated with Wednesbury unreasonableness.
52. In Edore v. Secy. of State for the Home Deptt. the appellant was a citizen of Nigeria who had entered the United Kingdom and remained back after her visa had expired. She had two children, born to a British citizen. The children were emotionally dependent on him and he was a stabling influence on their lives. If the appellant and her children were returned to Nigeria, their relationship with their father would end. The Court trying to resolve the conflict at hand opined:
Where the essential facts were not in doubt or dispute, the adjudicator’s task was to determine whether the decision under appeal was properly one within the decision-maker’s discretion, namely, that it was a decision which could reasonably be regarded as striking a fair balance between the competing interests in play. If it were, then the adjudicator could not characterize it as a decision “not in accordance with the law” and so, even if he personally would have preferred the balance to have been struck differently, he could not substitute his preference for the decision in fact taken. However, there would be occasions where it could properly be said that the decision reached was outside the range of permissible responses open to him, in that the balance struck was simply wrong.”
In Om Kumar v. Union of India (supra), this Court has
held thus:
“28. By “proportionality”, we mean the question whether, while regulating exercise of fundamental rights, the appropriate or 41
least-restrictive choice of measures has been made by the legislature or the administrator so as to achieve the object of the legislation or the purpose of the administrative order, as the case may be. Under the principle, the court will see that the legislature and the administrative authority “maintain a proper balance between the adverse effects which the legislation or the administrative order may have on the rights, liberties or interests of persons keeping in mind the purpose which they were intended to serve”. The legislature and the adminis-trative authority are, however, given an area of discretion or a range of choices but as to whether the choice made infringes the rights excessively or not is for the court. That is what is meant by proportionality.
67. But where an administrative action is challenged as “arbitrary” under Article 14 on the basis of Royappa (as in cases where punishments in disciplinary cases are challenged), the question will be whether the administrative order is “rational” or “reasonable” and the test then is the Wednesbury test. The courts would then be confined only to a secondary role and will only have to see whether the administrator has done well in his primary role, whether he has acted illegally or has omitted relevant factors from consideration or has taken irrelevant factors into consideration or whether his view is one which no reasonable person could have taken. If his action does not satisfy these rules, it is to be treated as arbitrary. In G.B. Mahajan v. Jalgaon Municipal Council, Venkatachaliah, J. (as he then was) pointed out that “reasonableness” of the administrator under Article 14 in the context of administrative law has to be judged from the stand point of Wednesbury rules. In Tata Cellular v. Union of India (SCC at pp. 679-80), Indian Express Newspapers Bombay (P) Ltd. v. Union of India 42
(SCC at p. 691), Supreme Court Employees’ Welfare Assn. v. Union of India (SCC at p.
241) and U.P. Financial Corpn. v. Gem Cap (India) (P). Ltd. (SCC at p. 307) while judging whether the administrative action is “arbitrary” under Article 14 (i.e. otherwise then being discriminatory), this Court has confined itself to a Wednesbury review always.
68. Thus, when administrative action is attacked as discriminatory under Article 14, the principle of primary review is for the courts by applying proportionality. However, where administrative action is questioned as “arbitrary” under Article 14, the principle of secondary review based on Wednesbury principles applies.
71. Thus, from the above principles and decided cases, it must be held that where an administrative decision relating to punishment in disciplinary cases is questioned as “arbitrary” under Article 14, the court is confined to Wednesbury principles as a secondary reviewing authority. The court will not apply proportionality as a primary reviewing court because no issue of fundamental freedoms nor of discrimination under Article 14 applies in such a context. The court while reviewing punishment and if it is satisfied that Wednesbury principles are violated, it has normally to remit the matter to the administrator for a fresh decision as to the quantum of punishment. Only in rare cases where there has been long delay in the time taken by the disciplinary proceedings and in the time taken in the courts, and such extreme or rare cases can the court substitute its own view as to the quantum of punishment.”
In the case of State of U.P. v. Sheo Shanker Lal
Srivastava (supra), this Court has held thus: 43
“23. In V. Ramana v. A.P. SRTC this Court upon referring to a large number of decisions held: (SCC p. 348, para 11) “11. The common thread running through in all these decisions is that the court should not interfere with the administrator’s decision unless it was illogical or suffers from procedural impropriety or was shocking to the conscience of the court, in the sense that it was in defiance of logic or moral standards. In view of what has been stated in Wednesbury case the court would not go into the correctness of the choice made by the administrator open to him and the court should not substitute its decision for that of the administrator. The scope of judicial review is limited to the deficiency in decision-making process and not the decision.”
24. While saying so, we are not oblivious of the fact that the doctrine of unreasonableness is giving way to the doctrine of proportionality.
25. It is interesting to note that the Wednesbury principles may not now be held to be applicable in view of the development in constitutional law in this behalf. See, for example, Huang v. Secy. of State for the Home Deptt. wherein referring to R. v. Secy. of State of the Home Deptt., ex p Daly it was held that in certain cases, the adjudicator may require to conduct a judicial exercise which is not merely more intrusive than Wednesbury, but involves a full-blown merit judgment, which is yet more than ex p. Daly requires on a judicial review where the court has to decide a proportionality issue.”
30. The respondent-allottees have concurred with
the fact that the appellant-Board has the right to 44
re-determine the final cost price of the plots
allotted on the basis of the escalation of rates with
regard to both the land as well as the building
materials used for the construction of the buildings
of the allotted plots in favour of the
respondent-allottees. However, while exercising that
power their decision in determining the final price
of the property must pass the test of reasonableness
and fairness which are the cardinal principles of law
as enunciated by this Court in the catena of cases
referred to supra upon which the learned senior
counsel for the respondents has placed strong
reliance in support of his contention that the
determination of the final price of the allotted plot
which has been done on the basis of the Collector’s
guidelines, for the financial year 2011-12, was fixed
at Rs.30,000/- per sq. mtr. as per the Circular
No.1842, dated 30.9.2008 which is arbitrary,
unreasonable and unfair.
31. We have in the earlier paragraphs held that
the appellant-Board is entitled to fix the final cost
of the land and the same is legal and valid. We 45
however, agree with the learned senior counsel for
the respondent-allottees that the same has been done
arbitrarily, unreasonably, unfairly and without
applying the principle of the doctrine of
proportionality. The determination for the final
price of the plots allotted to the allottees must be
on the basis of the appellant-Board Rules read with
the relevant aspects namely, the Collector’s
Guidelines, the Act, 1972 and the Rules, 1991, for
the purpose of determination of the market value of
the land. A statutory duty is cast upon the
appellant-Board which is governed by the provisions
of the Act and Rules and the appellant-Board being
the statutory Board is amenable to Article 14 of the
Constitution of India. The determination of the final
cost of the land in dispute must be in consonance
with the doctrine of proportionality but not on the
basis of the market price, i.e. fixed by the
Committee for the determination of guidance value of
the immovable property in the District which would be
arbitrary, unreasonable and unfair.
32. As could be seen from the letter dated 46
18.6.2009, by the officers of the appellant-Board
addressed to Mr. B.S.S. Parihar and Mrs. Raina Singh
that as per the advertisement published by the
appellant-Board, the estimated cost of the House of
HIG was Rs.40 lakhs and in view of the approved
minimum bid rates, the costs of the aforesaid type of
houses were likely to increase by Rs.9.53 lakhs and
therefore, the consent or dissent of the allottees
for the enhanced estimated cost for the land was
sought for, as the same was necessary before the
allotment of land. The said value is for the final
determination of the revised estimated cost of house
which is taken into consideration by applying the
Collector’s guidelines, the same will be arbitrary
and unreasonable. Therefore, the doctrine of
proportionality must come into play for the
determination of the final price of the allotted
plot, keeping in view the relevant factors namely,
the escalation of the cost of the building materials
and the cost of land which are re-determined as the
land is acquired by the State Government in favour of
the appellant-Board and the State Government will
have to pay the enhanced compensation of the land to 47
the land owners. The relevant factor to be borne in
mind for the purpose of re-determination of the cost
of the land is that the relevant period from the date
of advertisement in the year 2007 to 2010 should be
taken into consideration.
33. The demand made by the appellant-Board from the
allottees after the cost of the land was determined
at Rs.30,000/- per sq. mtr. is near about double the
cost of the developed plots for the Duplex and
Triplex houses which were earlier fixed at
Rs.16,500/- as per the Rules of the Board. There is
no justification on the part of the appellant-Board
to fix the price of the land at Rs.30,000/- per sq.
mtr. and placing the said demand on the constructed
HIG houses, from the respondent-allottees would be
most unreasonable and unfair. Therefore, this Court
has tried to maintain the balance between the figure
Rs.16,500/- per sq. mtr. fixed in relation to the
cost of the developed plot by the appellant-Board, as
per the Board Rules and Rs.30,000/- per sq. mtr.
fixed on the basis of the Collector’s guidelines for
the financial year 2011-12. It would be just and 48
proper to take into consideration the cost of the
developed plots at Rs.16,500/- per sq. mtr. and take
the escalation at the rate of 10% for every year from
2007 to 2011 and ask the respondent-allottees to pay
simple interest on the said sum which would do
complete justice to both the parties. The same would
be in conformity with the doctrine of proportionality
and it will pass the test of reasonableness and
fairness.
34. For the aforesaid reasons, we partly accept
the submissions made on behalf of the appellant-Board
as well as the submission made on behalf of the
respondent-allottees, particularly, the submission
made by Dr. Rajeev Dhawan on the principle of
doctrine of proportionality, and applying the
constitutional principles of reasonableness and
fairness in fixing the cost of the developed plots
allotted in favour of the respondent-allottees.
Therefore, to that extent his submission is well
founded and the same must be accepted as it is in
conformity with the law enunciated by this Court in
the catena of cases upon which he has rightly placed 49
reliance. Therefore, to that extent, we have to
modify the impugned judgment of the Division Bench of
the High Court. We accordingly pass the following
order :-
I. The appeals are partly allowed and the
impugned judgment and order of the Division
Bench of the High Court is set aside.
II. We modify the demand notice served upon the
respondent-allottees and fix the cost of the
developed plots for the year 2009 at
Rs.16,500/-. The same may be revised by adding
10% to the provisional cost every year upto
the date of the demand made upon the said
amount which is payable by the
respondent-allottees. The interest at the rate
of 9% per annum may be added on such enhanced
revised value amount from the date of demand
till the date of payment in modification of
the demands to the aforesaid extent from the
respondent-allottees.
III. The orders dated 24.11.2014 granting stay in
C.A. No. 1801 of 2015 and the order dated
16.1.2015 granting stay in C.A. Nos. 1802-1803 50
of 2015 shall stand vacated. The applications
for direction in C.A. Nos. 1802-1803 of 2015
are disposed of.
……………………………………………………………………J. [V.GOPALA GOWDA]
……………………………………………………………………J. [R. BANUMATHI] New Delhi, July 21, 2015 51
ITEM No. 1A Court No. 2 SECTION (For Judgment)
S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS
Civil Appeal No(s). 1801 of 2015
M P. HOUSING INFRASTRUCTURE DEV. BOARD Appellant(s)
VERSUS
B S S PARIHAR AND ORS. Respondent(s)
WITH CIVIL Appeal No. 1802-1803 of 2015
Date : 21.07.2015 These appeals were called on for judgment today.
For Appellant(s) Mr. Pramod Dayal, Adv.
For Respondent(s) Mr. M.L.Lahoty, Adv.
Mr. Paban K.Sharma, Adv.
Mr. Himanshu Shekhar, Adv.
Mr. Akshat Shrivastava, Adv.
Hon'ble Mr. Justice V.Gopala Gowda pronounced
Judgment of the Bench comprising Hon'ble Mr. Justice
V.Gopala Gowda and Hon'ble Mrs. Justice R.Banumathi.
The appeals are partly allowed and the
impugned judgment and order of the Division Bench of
the High Court is set aside in terms of the signed
reportable judgment.
We modify the demand notice served upon the
respondent-allottees and fix the cost of the 52
developed plots for the year 2009 at Rs.16,500/-. The
same may be revised by adding 10% to the provisional
cost every year upto the date of the demand made upon
the said amount which is payable by the
respondent-allottees. The interest at the rate of 9%
per annum may be added on such enhanced revised value
amount from the date of demand till the date of
payment in modification of the demands to the
aforesaid extent from the respondent-allottees.
The orders dated 24.11.2014 granting stay in C.A.
No. 1801 of 2015 and the order dated 16.1.2015
granting stay in C.A. Nos. 1802-1803 of 2015 shall
stand vacated. The applications for direction in C.A.
Nos. 1802-1803 of 2015 are disposed.
(Shashi Sareen) (Renu Diwan) Court Master Court Master
(Signed reportable judgment is placed on the file)
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free