M/S. Tommorrowland Limited vs Housing and Urban Development Corporation Ltd.
- SCC(2025) 4 SCC 19
- Neutral2025 INSC 207
- SCR[2025] 2 SCR 998
Ratio decidendi
The rule this decision rests on
When a lease agreement contains reciprocal obligations placed on both parties, a party cannot insist on performance of one obligation by the other party while failing to perform its own corresponding obligations that are conditions precedent to the performance demanded. Where a contract provides that upon failure to secure statutory approvals required under law, the contracting party shall refund amounts paid by the other party without interest, this refund obligation is triggered when the contracting party breaches its duty to execute necessary documents for obtaining those approvals. A party who fails to establish its bona fides before the court by failing to comply with interim orders, engages in forum shopping by withdrawing proceedings without liberty to refile when disadvantaged, and abandons substantive reliefs to evade procedural obligations, comes before the court with unclean hands and is therefore disentitled to discretionary relief of interest under Section 34 of the Code of Civil Procedure, notwithstanding that breach of contract by the other party is established.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
2025 INSC 207 REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No.__________ OF 2025 (Arising out of SLP (C) No. 34338 OF 2016)
M/s. Tomorrowland Limited .…Appellant
versus
Housing and Urban Development Corporation Limited and Another ….Respondents
JUDGMENT
SURYA KANT, J.
Leave granted.
2. The instant appeal preferred by M/s Tomorrowland Technologies
Exports Limited (formerly M S Shoes East Ltd.) is directed against
the judgment dated 03.06.2016 (Impugned Judgment) passed by
the High Court of Delhi (High Court) in RSA No. 362/2014 whereby
the concurrent findings returned by the courts below have been set
aside. Consequently, the Appellant’s suit seeking declaratory relief
has been dismissed for being not maintainable.
3. Signature Not Verified The fulcrum of the dispute herein lies in respect of the forfeiture of Digitally signed by ARJUN BISHT
the Appellant’s payments by Respondent No. 1, namely the Date: 2025.02.13 13:56:41 IST Reason:
Housing and Urban Development Corporation Limited (HUDCO), on account of non-performance of contractual obligations by the
Appellant. Before adverting to the respective contentions of the
parties, we deem it appropriate to briefly narrate the factual
background leading to the present appeal.
A. FACTUAL BACKGROUND
4. The sequence of events in the instant appeal commenced with the
Ministry of Urban Development, Government of India (MUD), i.e.,
Respondent No. 2 herein, having decided in 1990 to develop an area
of 71 acres of land located at Andrew's Ganj, New Delhi, through
Respondent No. 1. Bids were thus invited by Respondent No. 1 for
properties at Andrew’s Ganj inter alia offering:
(i) Land, which was to be leased for 99 years, in order to establish
a 5-star Hotel, along with an already-built Car Park;
(ii) Nine Guest House blocks, nine Restaurants, and 25 Shops
already constructed by Respondent No. 1;
(iii) A Shopping Arcade and;
(iv) A Cultural Centre to be built by the successful bidder(s).
We must underscore that the scope of the present appeal is
restricted only to Item No. (i) specified hereinabove, i.e. ‘land, which
was to be leased for 99 years, in order to establish a 5-star Hotel,
along with an already-built Car Park’ (Subject Property). We
further clarify that the conclusions drawn in the instant appeal will have no bearing on the ongoing disputes in respect to the other
bids.
5. Reverting to the facts, the Appellant seems to have emerged as the
highest bidder for the Subject Property after the conclusion of the
bidding process. As a result, Respondent No. 1 issued the allotment
letter dated 31.10.1994 (Allotment Letter), on such terms and
conditions as specified therein, including the following:
5. “The broad terms and conditions for the allotment are as follows:-
The 5-star hotel building shall be constructed within the parameters of the approved overall Urban Design Form after obtaining required approvals from the concerned local authority and the Delhi Urban Arts Commission. The height coverage in basement and such related development controls shall be as per the operative norms of the statutory authorities.
You shall make the payment of premium, i.e., consideration of Rs. 64.10 Cores (Rs. Sixty Four Crores and ten lacs only) for the allotment of the Hotel site and Rs. 14.00 crores for the allotment of car parking space. The payment shall be made in the following manner/stages:
(A) Hotel Site (Rs. 64.10 Crores)
(i) Within 4 weeks of the date of this allotment letter (i.e. before 28.11.94) - 40% (Rs. 25,64,00,000)
(ii) Before the end of one year of the date of this allotment letter (i.e. before 31.10.95) - 30% (Rs 19,23, 00,000)
(iii) Before the end of two years of the date of this allotment letter (i.e. before 31.10.96) - 30% (Rs. 19, 23,00,000)
------------------------
Rs. 64,10,00,000
------------------------
(B) Car Parking Space (Rs. 14.00 Crores)
(i) Within four weeks of the date of issue of allotment letter (i.e. before 28.11.94) - 10% (Rs.1,40,00,000)
(ii) Before the end of one year of the date of issue of the allotment letter (i.e. before 31.10.95) - 40% (Rs. 5,60,00,000)
(iii) Within four weeks of issue of letter by HUDCO intimating that the services were ready for being handing over - 50% (Rs.7,00,00,000)
------------------------
Rs. 14,00,00,000
------------------------
The above payments shall be made through demand drafts drawn in favour of HUDCO payable at New Delhi.
(iii) No interest will be charged on payments made before the due dates stated above. In case of default, interest shall be charged @ 16% p.a. for three months if the payment is made after the due date. Additional penal interest @ 3% p.a. shall also be charged on the interest for three months. Any delay beyond three months would entail cancellation of allotment and/or forfeiture of the total amount deposited to date.
(iv) You will be required to complete the construction of the Hotel Site within three years of the date of handing over possession of the Hotel Site on licence basis for construction of the Hotel building as per terms and conditions contained in the proforma of Agreement to Sub- lease, two copies of which are enclosed with this allotment letter. In the event of non- completion of construction within the stipulated time, HUDCO may consider granting extension if exceptional and unavoidable circumstances have prevented you to complete construction within the stipulated time. The decision of HUDCO regarding the existence of the exceptional and unavoidable circumstances will be final and binding upon you. In case the construction is not completed within the prescribed period or the extended period as decided by HUDCO, HUDCO will have the right to take over the land along with the unfinished building with materials, fixtures, if any, on the site without payment of any compensation to you. Since the underground car parking space will be made available to you in the adjacent building, you may provide underground linkage from the hotel with the parking space. However, cost of such linkages shall be borne by you.
(v) You shall not have any right to sell, transfer, assign or otherwise parting with the possession without the prior permission of Lessor/ HUDCO. You may also at the discretion of HUDCO, be permitted to raise loan only for construction of the building and equipment, to mortgage the premises subject to such terms and conditions including recovery of 50% unearned increase in the value of this land as will be laid down in the lease documents and subject to the first charge of HUDCO for the unpaid cost of land for the hotel as well as other dues payable hereunder.
(vi) Hudco will execute all required documents for obtaining approval of the competent authority under the Urban Land (Ceiling and Regulation) Act, 1976 and also of the Appropriate Authority in terms of Chapter XX C of the Income Tax Act. If these approvals are not accorded Hudco will refund the amount paid without any interest and you shall not be entitled to claim any compensation for damages.
(vii) You shall pay annual ground rent at the rate of 2-1/2% of the premium for land for the Hotel site land the proportionate cost of land underneath the car parking space from the date of handing over of possession of the Hotel site and the car parking space to you. The ground rent shall be revised periodically in accordance with the terms and conditions of the sub lease deed.
(viii) Initially, the Hotel site will be on a licence under an Agreement to Sub-lease and upon fulfilment of the terms of the said agreement including payment of all dues, perpetual sub- lease will be executed. The terms and conditions of the perpetual sub-lease shall be as per the proforma duly approved by the Govt. of India, a copy of which will be sent to you in due course.
(ix) Upon the receipt of the first instalment of the premium both for the Hotel site as well as the car parking space as indicated in para 5(ii) and also after receipt of approvals as indicated in para 5(vi), the Agreement to Sub-lease will be made available to you for execution for the Hotel site and upon its execution, the possession of Hotel Site will be handed over to you for raising construction.
(x) All costs for the preparation of required documents, stamp duty, registration charges and other levies of any kind whatsoever will have to be borne by you. Property taxes and other municipal levies shall borne by you from the date of possession of the site(s)”.
[Emphasis supplied]
6. The Appellant duly deposited the first instalment of Rs. 27.04
Crores along with interest at the rate of 16.48% for three months,
amounting to Rs. 1,04,81,939, as per Clause 5(A) of the Allotment
Letter. In addition, the Appellant also deposited a sum of Rs. 2.5
Lakhs towards the maintenance corpus. As such, the total amount
paid by the Appellant was admittedly Rs. 28,11,31,939.
7. Subsequently, a dispute arose between the parties; purportedly on
account of the Appellant’s assertion: that in terms of the Allotment
Letter, Respondent No. 1 was obligated to execute certain
documents after obtaining clearances under the Income Tax Act,
1961 (IT Act) and the Urban Land (Ceiling and Regulation) Act,
1976 (ULCR Act). Respondent No. 1 was further obligated to
execute an ‘agreement to sub-lease’ in favour of the Appellant.
The Appellant thus claimed that as per the terms and conditions of
allotment, the second and third instalments would have become
due in favour of Respondent No. 1, only in the event that the
abovementioned documents were duly executed by the latter.
8. Thereafter, the Appellant sent letters to Respondent No. 1
requesting compliance with the reciprocal contractual obligations
enshrined in the Allotment Letter. That being said, it is imperative
to caveat at this juncture that Respondent No. 1 was bereft of a
perpetual lease to be executed in its favour by MUD, and as such,
was not in a position to execute the ‘agreement to sub-lease’ in
favour of the Appellant. Regardless thereto, Respondent No. 1
insisted on payment of the second and third instalments, and
further sought to threaten the Appellant that non-compliance with
the payment schedule would result in cancellation of the allotment
in its favour.
9. At this point, it is also relevant to bring on record that Ansal
Properties & Industries Limited (Ansals), who being the successful
bidders for the establishment of a Shopping Arcade (as enumerated
in Item No. (iii) of Paragraph 4), were allotted land in this regard as
well as access to utilise certain portion of the aforementioned Car
Parking, which indubitably would have to be shared with the
Appellant. Pertinently, the Ansals also delayed the payment of
further instalments on the similar ground that the Car Park was
allegedly illegal/unauthorised. Pursuant thereto, the Ansals
appear to have been granted an interest-free extension of
instalment payments by Respondent No. 1.
10. In these circumstances, the Appellant filed Suit No. 275/1996
before the High Court (First Suit), seeking mandatory injunction
against Respondent No. 1 to extend the dates for payment of the
second and third instalments until Respondent No. 1 fulfilled its
reciprocal obligations. The Appellant further sought a permanent
injunction to restrain Respondent No. 1 from cancelling its
allotment.
11. The High Court passed a conditional status quo order on
31.01.1996 in the First Suit, in terms whereof, the Appellant was
directed to deposit Rs. 15 Crores by 08.04.1996, failing which such
an order would stand automatically vacated. It is not in dispute
that the Appellant failed to deposit the aforesaid amount even
within the extended period. As a result, the status quo order stood
vacated.
12. This followed an order by Respondent No. 1 issued on 02.05.1996,
whereby the allotment was cancelled and the entire amount of Rs.
28,11,31,939 was forfeited.
13. Respondent No. 1 thereafter invited fresh bids in November, 1996
for the development of the Subject Property, this time disclosing in
the bid that a lease in its favour for the said land was yet to be
executed. Additionally, Respondent No. 1 also filed an application
in the pending First Suit seeking its dismissal on the ground that the proceedings had become infructuous, owing to the cancellation
of the allotment.
14. The Appellant being aggrieved by the cancellation of their allotment
filed a fresh suit bearing Suit No. 1/1997 (Second Suit), changing
the forum from the High Court to Tis Hazari Courts, Delhi (Civil
Court). In the Second Suit, the Appellant sought a declaration that
the cancellation of allotment by Respondent No. 1 was illegal, null
and void. They also consequently sought possession of the Subject
Property.
15. Interestingly, the Appellant moved an application before the High
Court for the withdrawal of their First Suit, on the plea that the
Second Suit had been filed before the Civil Court on the basis of a
fresh cause of action. The High Court rejected the aforesaid
application on 22.04.1997, citing that there were several factual
aversions made by the Appellant. Eventually, the First Suit was
dismissed as withdrawn unconditionally, upon the statement made
by the Appellant’s counsel before the High Court.
16. In the meantime, Leela Hotels Limited (Leela) emerged as the
highest bidder in the fresh bid invited for the Subject Property,
followed by allotment. Leela’s allotment, however, was contingent
on the outcome of the pending suit filed by the Appellant. It is also relevant to note that the Respondent No. 2/MUD executed the
perpetual lease deed in favour of Respondent No. 1 on 04.07.1997.
17. The Appellant, meanwhile, impleaded Respondent No. 2 as one of
the defendants in the Second Suit. The Respondent No. 2, in turn,
filed an application under Order VII Rule 11 of the Code of Civil
Procedure, 1908 (CPC), seeking rejection of the plaint based on the
assertion that the Appellant had allegedly not paid the requisite
court fee. Though the Civil Court rejected that application, the High
Court thereafter, on revision, allowed the objection raised by
Respondent No. 2, holding that the Appellant was liable to pay
court fees based on the market value of the Subject Property.
18. The Appellant, mirroring the characteristics of a chronic defaulter,
this time decided to evade the liability of paying the court fee by
abandoning the relief of delivery of possession. Resultantly, the
Appellant restricted the relief in the Second Suit only to a
declaration that the cancellation of the allotment by Respondent
No. 1 was null and void.
19. The Civil Court eventually decreed the Second Suit vide judgment
dated 03.07.2010, inter alia, holding that: (i) Respondent No. 1 was
guilty of committing a breach of the terms of allotment; (ii) the
Appellant was discriminated against and was denied parity with the Ansals; and (iii) a declaration under Section 34 of the Specific Relief
Act, 1963 (SR Act) to the effect that the cancellation letter was null,
void, and inoperative is warranted on account of the concealment
and gross misrepresentation of facts by Respondent No. 1.
20. Respondent No. 1 unsuccessfully laid challenge to the judgment
and decree dated 03.07.2010, as the First Appellate Court
dismissed the Regular First Appeal vide judgment dated
18.07.2014, reiterating the same grounds.
21. Still aggrieved, Respondent No. 1 preferred a Regular Second
Appeal before the High Court, which was allowed vide the
Impugned Judgment dated 03.06.2016. Notably, the High Court
overturned the concurrent findings of the courts below, and has
inter alia observed that the Appellant admittedly did not have
sufficient funds and, thus, wanted to prolong the litigation. The
High Court further held that:
“39. … the suit filed by the Appellant suffered from a fatal defect of not claiming possession as a further relief in terms of proviso to Section 34 of the Specific Relief Act, and therefore the decree seeking only declaration to the effect that the cancellation letter dated 02.05.1996 was bad in law could not have been passed by the courts below”.
Additionally, the High Court went on to observe that the grant of
declaration under Section 34 of the SR Act, being a discretionary relief, cannot be bestowed upon a party who indulges in ‘sharp’
practices. Hence, this appeal.
B. CONTENTIONS ON BEHALF OF THE APPELLANT
22. Shri Tejinder Singh Dhindsa, learned Senior Counsel, representing
the Appellant has painstakingly taken us through the voluminous
material placed on record. He contended that the High Court has
committed grave error in upsetting the concurrent finding of fact
arrived at by the courts below.
23. Shri Dhindsa advanced the following submissions on behalf of the
Appellant to challenge the Impugned Judgment:
a) At the time of allotment of the Subject Property, Respondent
No. 1 failed to disclose that it had no subsisting lease in its
favour to execute the sub-lease in favour of the Appellant. As
such, it is a clear case of misrepresentation on the part of
Respondent No. 1.
b) After payment of the first instalment by the Appellant,
Respondent No. 1 was obligated to execute the ‘agreement to
sub-lease’ in favour of the Appellant and further execute
documents for obtaining statutory approvals under the ULCR
Act and IT Act. However, Respondent No. 1 failed to execute
these documents in the absence of a perpetual lease in its favour. There was, thus, no contractual obligation on the
Appellant to pay further instalments.
c) The High Court erroneously held that the Second Suit filed by
the Appellant suffered from a fatal defect of not claiming
possession as a further relief in terms of the proviso to Section
34 of the SR Act. The High Court in this regard overlooked the
fact that possession could be sought from Respondent No. 1
only after the execution of the sub-lease agreement, which was
admittedly not done at the time of filing of the Second Suit. For
this reason, the Appellant gave up the consequential relief of
possession in the Second Suit, and it would be unfair to non-
suit the Appellant on this ground.
d) After the Subject Property was allotted to Leela under the
subsequent bidding process, a dispute arose between
Respondent No. 1 and Leela on account of failure of the former
to disclose that the revised layout plan was yet to be approved
by the Competent Authority. The said dispute was adjudicated
by an Arbitrator directing refund of the entire sum paid by
Leela, along with 20% interest. That Award attained finality,
except that the rate of interest was reduced to 18% by this
Court. The Appellant being similarly placed, therefore,
deserved to be treated at par with Leela.
e) The treatment meted out to the Appellant was discriminatory
when juxtaposed with the Ansals, who were granted repeated
interest-free extensions for paying the second and third
instalments, in regards to the shared Car Parking. Conversely,
the Appellant was compelled to pay instalments as per the
payment schedule and was threatened with cancellation of the
allotment in the event of default.
f) The forfeiture of the amount paid by the Appellant towards the
first instalment was done on account of misconstruction and
selective reading of the mutual obligations emanating from the
Allotment Letter and not on account of any actual loss suffered
by Respondent No. 1.
24. Alternatively, Shri Dhindsa submitted that since considerable time
has passed following the allotment and its cancellation, it would be
in the interests of justice and equity to entertain the Appellant’s
limited relief for return of Rs. 28,11,31,929 along with the
applicable rate of interest.
C. CONTENTIONS ON BEHALF OF RESPONDENT NO. 1
25. Ms. Meenakshi Arora, learned Senior Counsel appearing on behalf
of Respondent No. 1, contrarily opposed the Appellant’s prayer inter
alia and vehemently contended that not only did they fail to comply
with the terms and conditions of the Allotment Letter but that the Appellant had disqualified itself from any relief on account of its
deceitful, unfair and unethical conduct.
26. Ms. Arora canvassed the following grounds in support of her
submissions:
a) The Appellant defaulted on the payment schedule stipulated in
the Allotment Letter, resulting in a breach of contractual
obligations. As a result, Respondent No. 1 exercised its
contractual right by cancelling the allotment in favour of the
Appellant and forfeited the deposited amount, as envisaged in
Clause 5(iii) of the Allotment Letter. The operation of the
aforementioned Clause is not interlinked or contingent on any
other clause of the Allotment Letter and therefore, non
payment of the instalment is bound to entail cancellation of
the allotment and forfeiture of the deposited amount.
b) The Second Suit filed by the Appellant was barred under Order
II Rule 2 of the CPC, considering the cause of action of both
the suits was one and the same, and also because the
Appellant relinquished a portion of the claim which they could
have sought in the First Suit itself.
c) The Second Suit was also barred in view of Clause (3) of Rule
1 of Order XXIII of the CPC, since in the First Suit which was unconditionally withdrawn by the Appellant, the High Court
did not grant any liberty therein to institute a fresh suit.
d) The Appellant in the Second Suit, while seeking declaratory
relief of the cancellation of allotment being null and void,
abandoned the consequential relief of possession in order to
avoid paying court fees. Such a recourse defies the proviso to
Section 34 of the SR Act, which mandates that consequential
relief be sought along with a declaratory decree. Hence, the
High Court has rightly held that the Second Suit was non-
maintainable.
e) The Appellant brazenly attempted to overreach the judicial
process; indulge in forum shopping and finagle the judicial
process. This is writ large from: (i) the Appellant dishonouring
the High Court’s direction to deposit Rs. 15 Crores for
continuation of the order of status quo; (ii) the First Suit being
withdrawn due to forum non conveniens; (iii) the Second Suit
being crafted with a view to change the forum from the High
Court to the Civil Court; (iv) the relief of possession being
abandoned to avoid payment of court fees as the entire lis was
speculative for the Appellant; and (v) non-payment of further
instalments and failure to perform reciprocal obligations such
as securing statutory approvals.
f) Unlike the Appellant, the Ansals had secured approval from
the Income Tax authorities, whereas the Appellant did not take
any steps to do so, despite categorical assertions in the
Allotment Letter. Hence, no parity with the Ansals can be
claimed when the Appellant never demonstrated any
willingness to honour their obligations.
27. In essence, Ms Arora contended that the conduct of the Appellant
throughout has been to prolong the litigation and entangle
Respondent No. 1 in vexatious litigation. She thus maintained that
the High Court has rightly reversed the findings of the courts below
or that the Appellant is not entitled to any discretionary relief under
Section 34 of the SR Act.
28. Ms. Aishwarya Bhati, learned Additional Solicitor General of India,
on behalf of Respondent No. 2 reiterated the contentions put forth
by Ms. Arora. She further fairly submitted that if this Court fixes
any liability on Respondent No. 1 to refund the forfeited amount, it
is inter-se the Respondents to comply with such direction. Ms Bhati
maintained that Respondent No. 1 has sufficient assets to meet any
liability imposed by this Court.
D. ISSUES FOR CONSIDERATION
29. In our considered view, the salient issues that arise for our
consideration can be summed up as follows:
(a) Whether Respondent No. 1/HUDCO was in breach of its
reciprocal contractual obligations qua the Appellant?
(b) If so, whether the Appellant is entitled to a refund of the
forfeited amount under Clause 5(vi) of the Allotment Letter?
(c) If Issue (b) above is answered in the affirmative, whether the
Appellant is entitled to interest on refund of the forfeited
amount?
E. ANALYSIS
E. 1 Whether Respondent No. 1/HUDCO was in breach of its
reciprocal contractual obligations qua the Appellant?
30. We have carefully perused the terms and conditions of the
Allotment Letter and find that there are several reciprocal
obligations placed upon the Appellant and Respondent No. 1.
31. First, a bare reading of the relevant recitals in the Allotment Letter
extracted at Paragraph 5 above, leaves no room to doubt that
Clause 5(vi) obligates Respondent No. 1 to ‘execute all required
documents for obtaining approval of the competent authority under
the Urban Land (Ceiling and Regulation) Act, 1976 and also of the
Appropriate Authority in terms of Chapter XX C of the Income Tax
Act’. In fact, in the event of failure to do so this very Clause also
necessitates that Respondent No. 1 ‘will refund the amount paid without any interest and you shall not be entitled to claim any
compensation for damages’.
32. Though Respondent No. 1 has, in this regard, attempted to wriggle
out of its obligations on the premise that it could only assist the
Appellant in executing the necessary documents, we do not find
any merit in such submission. We say so for the reason that had it
not been obligatory on Respondent No. 1 to execute the necessary
documents under the first part of Clause 5(vi), the second part
thereof would not have mandated refund of the amount paid by the
successful bidder. It seems to us that since the failure to secure
approval of the Statutory Authorities and resultant execution of
requisite documents has necessary consequences of refund of the
amount paid, the first part of Clause 5(vi) is mandatory in nature.
Respondent No. 1 therefore cannot be allowed to shirk its
responsibility and leave the Appellant at the mercy of the Statutory
Authorities for such approvals.
33. That being the clear intent of the relevant terms and conditions of
the Allotment Letter as well as the supporting material placed on
record, we are of the considered opinion that Respondent No. 1 was
in breach of its contractual duty under Clause 5(vi) of the Allotment
Letter.
34. Second, a conjoint reading of Clauses 5(viii) and (ix) of the Allotment
Letter postulates an unambiguous promise on the part of
Respondent No. 1: that upon receipt of the first instalment and on
grant of approvals by the Statutory Authorities, an ‘agreement to
sub-lease’ will be executed by Respondent No. 1, followed by
handing over of possession of the Subject Property to the Appellant.
35. As held earlier, Respondent No. 1, even after the receipt of the first
instalment, did not take any tangible steps to secure the necessary
statutory approvals. It is obvious that the said failure led to breach
of Clause 5(viii) and (ix) also, as admittedly, no ‘agreement to sub-
lease’ was executed in favour of the Appellant, owing to the non-
execution of a perpetual lease by Respondent No. 2 in favour of
Respondent No. 1. Nonetheless, we proceed to examine the
contention of the Appellant that Respondent No. 1 also concealed
the fact that it did not have the title and authority to execute the
‘agreement to sub-lease’ in favour of the Appellant.
36. The Appellant’s plea to this effect is fortified by the contents of long
drawn correspondence, including letters dated 03.01.1995,
24.01.1995, 03.03.1995, and 29.03.1995, whereby Respondent
No. 1 had been requesting Respondent No. 2 to execute the
perpetual lease deed in its favour, in absence whereof, no sub-lease
could be executed in favour of the Appellant.
37. The other cascading effect of non-execution of perpetual lease in
favour of Respondent No. 1, or sub-lease in favour of the Appellant,
was that the possession of the Subject Property could not have been
handed over to the Appellant. Admittedly, the perpetual lease deed
in favour of Respondent No. 1 was executed only after the
cancellation of allotment in favour of the Appellant, belatedly on
04.07.1997.
38. Our attention was also drawn towards several legal opinions and
internal documents of Respondent No. 2 and the Ministry of Law &
Justice in the context of the underlying bid dispute. While we do
not intend to delve into these documents, we cannot be ignorant of
the fact that these records tend to support the claim of the
Appellant that Respondent No. 1 could not furnish the sub-leasing
arrangements until the perpetual lease was executed in its favour.
39. As such, Respondent No. 1 being incapable of fulfilling its
reciprocal promises, was not entitled to demand payment for the
second instalment until the perpetual lease deed was executed in
its favour. We therefore hold that Respondent No. 1’s failure to
execute the sub-lease in favour of the Appellant, owing to the lack
of its authority and title, also amounts to a breach of their
contractual obligations.
40. We may hasten to add that besides the breach of aforementioned
contractual obligations, it seems that Respondent No. 1 did not
have the necessary sanctions permitting construction of the 5-star
Hotel at the site. This fact came to light only after Leela succeeded
in getting an Arbitration Award in its favour, on account of alleged
failure of Respondent No. 1 to disclose that the revised layout plan
of the Subject Property was yet to be approved.
41. Furthermore, there is some merit in the Appellant’s grievance of
differential treatment when compared to the Ansals. As noted
earlier, the Ansals were granted an interest-free extension for the
pending instalments under similar circumstances, but the request
of the Appellant was declined. It is difficult to comprehend as to
how granting the same relief to the Appellant would have been
detrimental to the interest of Respondent No. 1, when such a relief
was granted to another similarly placed party.
42. As an upshot of the foregoing, we have no doubt in our mind that
Respondent No. 1 was in breach of several obligations as
contemplated in the Allotment Letter, viz. failure to execute
documents for securing approval under the ULCR Act and the IT
Act; failure to execute the sub lease agreement in favour of the
Appellant and; failure to secure the approval of the revised layout
plan for the construction of the hotel.
E. 2 Whether the Appellant is entitled to a refund of the forfeited
amount?
43. Having held that Respondent No. 1 has breached its contractual
obligations, we now proceed to determine the Appellant's
entitlement to refund of the forfeited amount. We may clarify here
that during the course of oral arguments, the Appellant sought a
refund of the forfeited amount along with reasonable interest.
However, in the written submissions, the Appellant, while
reiterating their stance, has sought a refund of Rs. 28,11,31,929
along with interest from the date of payment at the rate of 16.48%,
i.e., the contractual rate of interest charged by Respondent No. 1.
44. Clause 5 (vi) of the Allotment Letter, which deals with the monies
paid by the Appellant, provides that Respondent No. 1 will execute
all required documents to obtain approval from the Competent
Authority under the ULCR Act and also from the Appropriate
Authority as envisaged in Chapter XX C of the IT Act, failing which,
Respondent No. 1 will refund the amount paid without any interest.
45. The contents of the above clause unequivocally enumerate that the
parties had ample knowledge of the obligation cast upon
Respondent No. 1 to refund the amounts paid by the Appellant, in
case statutory approvals were not accorded. Significantly, the said clause also provides that such a refund will be without any interest
or claim of compensation for damages.
46. We have already held in Issue No. E. 1 of this judgment that
Respondent No. 1 was in breach of several obligations as
contemplated in the Allotment Letter.
47. That being the case, it is imperative to maintain the sanctity of the
terms of the agreement between the parties. It is a settled position
of law that a commercial document ought not to be interpreted in
a manner that arrives at a complete variance with what may
originally have been the intention of the parties. As a result, we
hold that Respondent No. 1 is liable to refund the amount of Rs.
28,11,31,939 (First instalment of Rs. 27.04 Crores along with
interest for three months amounting to Rs. 1,04,81,939/- and Rs. 2.5
Lakhs towards maintenance corpus) deposited by the Appellant
pursuant to the Allotment Letter.
E. 3 Whether the Appellant is entitled to interest on refund of the
forfeited amount?
48. Having held that Respondent No. 1 is liable to refund the principal
sum, we may now proceed to determine the Appellant's claim for
interest on the amount directed to be refunded. Evidently, the Appellant is not entitled to any interest on the amount to be
refunded in terms of the Allotment Letter. The Appellant, of course,
can seek award of interest under Section 34 of the CPC, which inter
alia provides that “the court may, in the decree, order interest at such
rate as the Court deems reasonable to be paid on the principal sum
adjudged from the date of the suit to the date of the decree.”
49. It is trite law that under Section 34 of the CPC, the award of interest
is a discretionary exercise steeped in equitable considerations. The
law in this regard has been succinctly discussed in the Constitution
Bench judgment of this Court in Central Bank of India v.
Ravindra & Ors.; (2002) 1 SCC 367, which states:
“Award of interest pendente lite or post-decree is discretionary with the Court as it is essentially governed by Section 34 of the CPC de hors the contract between the parties. In a given case if the Court finds that in the principal sum adjudged on the date of the suit, the component of interest is disproportionate with the component of the principal sum actually advanced, the Court may exercise its discretion in awarding interest pendente lite and post-decree interest at a lower rate or may even decline to award such interest. The discretion shall be exercised fairly, judiciously, and for not arbitrary or fanciful reasons.”
[Emphasis supplied]
50. There is no gainsaying that the power to award interest ought to be
exercised judiciously, aligning with equitable considerations and
also ensuring neither undue enrichment nor unfair deprivation. Courts are duty-bound to assess the facts and circumstances of
each case, applying the principles of fairness and justice. This
discretion must reflect a balanced approach, grounded in reason,
and guided by the overarching objective of equity.
51. It is against this backdrop that the contentions of Respondent No.
1 concerning the conduct of the Appellant become material.
Respondent No. 1 has contended that the Appellant’s actions
demonstrate unscrupulous and evasive conduct, apart from their
financial incapability to honour the contractual obligations,
undermining the essence of the contract.
52. It is not in dispute that in the First Suit, the High Court on
31.01.1996, passed a status quo order against Respondent No. 1
conditionally, obligating the Appellant to deposit Rs. 15 Crores by
08.04.1996. It was contemplated in the order that if the Appellant
fails to make the stipulated deposit, the status quo order would
stand vacated. Admittedly, despite seeking an extension of 10 days,
the Appellant failed to deposit Rs. 15 Crores and establish their
bona fides.
53. Shortly after the vacation of the status quo order and cancellation
of the allotment, the Appellant sought to withdraw the First Suit which was pending before the High Court under its original
jurisdiction, instead of seeking amendment of the plaint and the
consequential relief(s) on the basis of subsequent events. This was
done with an oblique motive, as the Appellant did not want to take
a chance before the High Court whose order they had failed to
comply with. The Appellant thus withdrew the First Suit
unconditionally even without the liberty to file a fresh one,
ostensibly with a calculated mindset.
54. We have no hesitation in holding that such conduct was nothing
short of a brazen attempt at forum shopping, as the Appellant
wanted to avoid the jurisdiction of the High Court before whom they
had failed to prove their bona fides by not depositing the stipulated
sum. Such demeanour not only raises grave suspicions on the
Appellant’s propriety, but also amounts to sheer abuse of the
process of law and a waste of precious judicial time.
55. Even in the Second Suit, upon an objection raised by the Union of
India when the High Court directed the Appellant to deposit
requisite court fees, the Appellant abandoned the relief of
possession of the suit land to avoid payment of ad-valorem court
fees. This again casts serious aspersions on the bona fides and
financial capabilities of the Appellant.
56. The material on record sufficiently indicates that the Appellant did
not approach the Court with clean hands and instead attempted to
hoodwink the judicial process by creating a facade to subterfuge
their inability to meet their contractual obligations. We are
constrained to observe that the intent of the Appellant throughout
appears to be that of prolonging the litigation to cloak its
impecuniousness.
57. It needs no emphasis that whosoever comes to the court claiming
equity, must come with clean hands. The expression ‘clean hands’
connotes that the suitor or the defendant have not concealed
material facts from the court and there is no attempt by them to
secure illegitimate gains. Any contrary conduct must warrant
turning down relief to such a party, owing to it not acting in good
faith and beguiling the court with a view to secure undue gain. A
court of law cannot be the abettor of inequity by siding with the
party approaching it with unclean hands. This also brings to mind
the oft-quoted legal maxim—he who seeks equity must do equity.
58. We are conscious of the fact that as a general principle, in
commercial disputes, the award of interest pendente lite or post-
decree is typically granted as a matter of course. This is because
such interest serves to compensate the aggrieved party for the time
value of money that was due but withheld during the legal process. It reflects an established norm aimed at ensuring fairness and
equity in commercial transactions.
59. Having said so, we find the instant case to be fit to justify a
deviation from the established standards. In the facts and
circumstances, though we have held Respondent No. 1 to be in
breach of several contractual obligations, the conduct of the
Appellant is rife with instances where it has also sought to
undermine the authority and integrity of the judicial process, by
treating the Court with disregard, and attempting to exploit
procedural mechanisms for personal gain. We, thus, hold that in
view of the above reasons, the Appellant is not entitled to any
discretionary relief of interest under Section 34 of CPC.
F. CONCLUSION
60. Striking a balance between these considerations, we deem it
appropriate to allow this appeal in part, and dispose of the same in
the following terms:
(i) Respondent No. 1/HUDCO, was in breach of its reciprocal
contractual obligations, thereby disentitling them from
forfeiting the monies already paid by the Appellant towards the
first instalment as enshrined in Clause 5 (iii) of the Allotment
Letter dated 31.10.1994.
(ii) Given that the Appellant has blatantly engaged in forum
shopping, and considering that their overall conduct does not
in any manner reflect an approach aligning with the clean
hands doctrine, they are not entitled to grant of any
discretionary relief of interest in their favour.
(iii) The Impugned Judgement dated 03.06.2016 passed by the
High Court is set aside to the extent above.
(iv) The Second Suit filed by the Appellant is decreed in part, and
the Appellant is held entitled to a refund of the principal
amount, without any interest.
(v) As a sequel to the above, we direct Respondent No. 1/HUDCO,
to refund the amount of Rs. 28,11,31,939 to the Appellant
within three (3) months from the date of this order.
(vi) In the event Respondent No. 1 fails to refund the amount
within the stipulated time, the Appellant shall be entitled to
interest at the rate of 6% per annum till the date of realisation.
61. We find it necessary to clarify that the above-mentioned directions
pertain only to the Subject Property, i.e., land for the establishment
of a 5-star Hotel and the already built Car Park. We have not
expressed any opinion on the pending matters between the parties
insofar as the other properties are concerned. The other pending cases shall be decided by the concerned Court on their own merit
and in accordance with law.
62. The appeal is disposed of in the above terms.
63. Pending interlocutory applications are also disposed of in the above
terms. Ordered accordingly.
………..………………… J.
[SURYA KANT]
………..………………… J.
[UJJAL BHUYAN] NEW DELHI DATED: 13.02.2025
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free