Miss Lucy
← All judgments

M/S Sweta Estate Pvt. Ltd. Gurgaon vs Haryana State Pollution Control Board

Supreme Court10 November 2023Sanjay Karol · Abhay S. Oka

Ratio decidendi

The rule this decision rests on

An appellate tribunal seized of an appeal challenging only the legality and validity of a specific order must confine itself to those issues and cannot go into collateral matters beyond the scope of the appeal, such as whether an earlier environmental clearance had expired or whether intervening construction was illegal. Where an applicant accepts the grant of a statutory permission (here, ex-post facto Consent to Establish) subject to a specific condition (here, that prosecution would be initiated), and acts upon that permission without challenging the condition through available statutory remedies within the prescribed time, the applicant cannot subsequently challenge that condition by invoking principles of estoppel and approbation and reprobation; such a challenge will be barred.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2023 INSC 999 Non-Reportable IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NO.2212 OF 2020

M/s Sweta Estate Pvt.Ltd. Gurgaon … Appellant

versus

Haryana State Pollution Control Board & Anr. … Respondents

JUDGMENT

ABHAY S. OKA, J.

FACTUAL ASPECTS

1. By this appeal, the appellant has taken an exception to the

judgment and order dated 24th February 2020 passed by the

National Green Tribunal, Principal Bench at Delhi. The appellant

undertook a project of developing a housing colony at Gurgaon-

Sohna Road, Sector 48, Gurgaon, Haryana. The housing project

comprised several buildings containing apartments, service

apartments, etc. Initially, in August 2006, the appellant applied

to the Haryana State Pollution Control Board (for short ‘the Board’) Signature Not Verified Digitally signed by Anita Malhotra

for a grant of Consent to Establish (CTE) under Section 21 of the Date: 2023.11.10 19:19:04 IST Reason:

Air (Prevention and Control of Pollution) Act, 1981 (the ‘Air Act’)

1 and Sections 25 and 26 of the Water (Prevention and Control of

Pollution) Act, 1974 (the ‘Water Act’) to the Board. Based on

another application made by the appellant, on 10th April 2007, the

Ministry of Environment, Forest and Climate Change of the

Government of India granted environmental clearance (EC) to the

appellant to develop the housing complex. On 18th April 2007, the

Board granted CTE under the Air and Water Act. In 2013 and

2015, the appellant applied for renewal of the CTE. The

applications were rejected. On 29th December 2015, the Board

issued a show cause notice of closure under Section 33-A of the

Water Act and Section 31-A of the Air Act. The notice also called

upon the appellant to show cause why the appellant should not be

penalised under the relevant provisions of the Air Act and the

Water Act. The appellant replied to the said notice.

2. On 4th March 2017, the appellant applied for EC for the

expansion of the housing project to the Government of India. On

21st June 2017, the Chairman of the Board passed an order

granting approval for prosecuting the appellant and its responsible

Directors for the offences punishable under Sections 43 and 44 of

the Water Act and Sections 37 and 38 of the Air Act. On 28th

February 2012, the Board issued an office order providing that the

2 industry which comes into operation without obtaining CTE can

be granted CTE ex-post facto, provided the unit is compliant in all

respects.

3. On 29th August 2017, the Government of India granted EC to

the appellant for the housing complex. On 18th October 2017, the

Board granted ex-post facto CTE to the appellant, which contained

a condition that prosecution would be initiated against the

appellant as per the approval granted under the order dated 21st

June 2017. In January 2018, the appellant preferred an appeal

before the Appellate Authority established under the Air and Water

Acts by invoking Section 31 of the Air Act and Section 28 of the

Water Act for setting aside the order dated 21st June 2017 passed

by the Chairman of the Board granting approval to prosecute the

appellant. The Appellate Authority, by judgment and order dated

15th March 2018, quashed the order of approval on the ground

that, subsequently, ex-post facto CTE has been granted to the

appellant. Being aggrieved by the said order of the Appellate

Authority, the Board preferred an appeal under Section 16 of the

National Green Tribunal Act, 2010, before the National Green

Tribunal (NGT). By the impugned judgment, the appeal was

allowed, and the order dated 15th March 2018 of the Appellate

3 Authority was quashed and set aside. While doing so, in

paragraph 12, observations were made by the NGT that EC granted

on 29th August 2017 cannot condone the illegal construction

raised from 9th April 2012 to 29th August 2017. NGT held that the

environment clearance granted on 10th April 2007 expired on 9th

April 2012.

SUBMISSIONS

4. The learned senior counsel appearing for the appellant urged

that out of a total of 28 towers, 26 towers have been constructed.

He pointed out that in 2010 and 2014, occupation certificates were

granted for nine and ten towers, respectively. On 24th May 2016,

an occupancy certificate was granted with respect to seven towers.

He submitted that even assuming without admitting that the EC

expired on 9th April 2012, renewal or grant of a fresh EC was not

required as the superstructure of the building was complete before

9th April 2012, and for completing the further construction, EC was

not required. In any event, EC was granted on 29th August 2017.

The learned senior counsel urged that in any event, NGT had no

reason to deal with the controversy regarding the effect of the

absence of EC as the appeal was limited to the legality and validity

4 of the order dated 15th March 2018 passed by the Appellate

Authority.

5. The learned senior counsel appearing for the appellant

further submitted that once ex-post facto CTE was granted, even

if the appellant conducted certain activities before the grant of ex-

post facto CTE which required CTE, the appellant cannot be

prosecuted as in this case, there is not a mere grant of CTE but

the same will have retrospective effect. He would, therefore,

submit that the impugned judgment and order is completely

illegal.

6. The learned counsel appearing for the Board submitted that

there was a specific condition imposed in the ex-post facto CTE

that as per the prosecution the approval order dated 21st June

2017 will be filed. He submitted that the appellant never

challenged the said condition, and therefore, the appellant had no

right to challenge the order dated 21st June 2017 approving the

prosecution. He submitted that prior to the grant of the ex-post

facto CTE, on three occasions, the applications made by the

appellant for the grant of CTE were rejected. He submitted that

work of development cannot be carried out unless there is a valid

and subsisting EC, and for a period between 9th April 2012 and

5 29th August 2017, admittedly, no EC was granted to the appellant.

He would, therefore, submit that no interference was called for

with the impugned judgment.

CONSIDERATION OF SUBMISSIONS

7. Firstly, we deal with the scope of the appeal before the NGT.

The appeal was specifically for challenging the order dated 15th

March 2018 by which the Appellate Authority set aside approval

granted by the Chairman of the Board on 21st June 2017 to

prosecute the appellant for the offences punishable under the Air

and Water Acts. Therefore, the only issue in the appeal preferred

before the NGT was regarding the legality and validity of the order

of the Appellate Authority and the approval granted on 21st June

2017 to prosecute the appellant. While dealing with the appeal,

NGT ought not to have gone into the issue of whether the EC

granted earlier expired on 9th April 2012. Considering the limited

scope of appeal, NGT ought not to have gone into the question of

whether the construction carried out by the appellant between 9th

April 2012 to 29th August 2017 was illegal. Therefore, what is held

in paragraph 12 of the impugned judgment will have to be set

aside.

6

8. Now, we come to the main issue regarding CTE. There is no

dispute that the appellant required CTE under Section 21 of the

Air Act and Section 25 read with Section 26 of the Water Act. In

this appeal, we need not go into the question whether there exists

a power in the Board to grant ex-post facto CTE as the issue

whether ex-post facto CTE could be granted did not arise before

the Appellate Authority.

9. The Chairman of the Board issued the office order dated 28th

February 2012 based on a resolution dated 8th February 2012

passed by the Board in its meeting. The relevant part of the said

office order reads thus:

“The agenda regarding Ex-post facto Consent to Establish was placed before the Board in its 181st meeting held on 08.02.12 vide agenda item No. 161.18. It has been decided that the industry which comes into operation without obtaining consent to establish, be granted Ex-post facto Consent to establish in case unit is presently compliant in all respects. But simultaneously prosecution action will be taken against the unit which violated the provisions of the Water/Air Acts by not obtaining prior consent to establish from the Board, as a past violation.” (emphasis added)

10. It cannot be disputed that ex-post facto CTE was granted to

the appellant on 18th October 2017 on the basis of the said decision

7 dated 8th February 2012 taken by the Board. Moreover, condition

no. 4 in ‘other conditions’ in the ex-post facto CTE reads thus:

"4. Prosecution case will be filed against the unit as per approval for prosecution received from Head office vide orders No-

HSPCB/2017 /926-27 dt.21.06.2017".

11. As noted earlier, even before the ex-post facto CTE was

granted, the order dated 21st June 2017 was made by the

Chairman granting approval to prosecute the appellant and its

responsible Directors/persons for offences punishable under the

Air and Water Acts. The appellant neither challenged the

resolution of the Board dated 8th February 2012 nor the said

condition no.4 by filing any proceedings. The appellant did not

apply to modify condition no.4 by taking recourse to clause (a) of

sub-section (2) of Section 27 of the Water Act. Moreover, an appeal

could have been preferred by the appellant for challenging

condition no.4 by taking recourse to Section 28 of the Water Act

and Section 31 of the Air Act. The appellant did not challenge the

Board’s decision dated 8th February 2012, authorising the Board

to grant ex-post facto CTE, which clearly provided that

simultaneously with the grant of ex-post facto CTE, action would

be taken against the unit which violated the provisions of the

8 Air/Water Acts by not obtaining prior CTE, as a past violation. It

is pertinent to note that the appellant not only failed to make any

grievance about condition no.4 in the ex-post facto CTE dated 18th

October 2017 but acted upon the es-post facto CTE. After the

expiry of two months from the grant of the ex-post facto CTE, the

appellant challenged the order dated 21st June 2017, granting the

approval for prosecuting the appellant. The said challenge at the

instance of the appellant ought not to have been entertained by

the Appellate Authority as the appellant was bound by condition

no.4 in the ex-post facto CTE granted on 18th October 2017. In

fact, the judgment of the Appellate Authority shows that the

attention of the Appellate Authority was invited to the aforesaid

condition no.4. After having acted upon the ex-post facto CTE

dated 18th October 2017, the appellant cannot be allowed to

approbate and reprobate. Therefore, interference by the Appellate

Authority by its judgment dated 15th March 2018 was illegal and

uncalled for. To that extent, the impugned judgment of the NGT

cannot be interfered with.

9

12. Hence, the appeal must succeed in part, and we pass the

following order:

a. The findings recorded in paragraph 12 of the impugned

judgment are set aside on the ground that the issues

decided thereunder were beyond the scope of appeal

preferred before NGT. The issues which are dealt with in

paragraph 12 are kept open. These issues can always be

decided in appropriate proceedings in accordance with the

law. All contentions on that behalf are left open;

b. The impugned judgment and order, insofar as it interferes

with the judgment and order dated 15th March 2018

passed by the Appellate Authority, is hereby confirmed;

c. There will be no order as to costs and

d. The appeal is partly allowed on the above terms.

….…………………….J. (Abhay S. Oka)

…..…………………...J. (Sanjay Karol) New Delhi;

November 10, 2023.

10

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free