Miss Lucy
← All judgments

M/S Sorath Builders vs Shreejikrupa Buildcon Limited & Anr

Supreme Court20 February 2009Arijit Pasayat · Mukundakam Sharma

Ratio decidendi

The rule this decision rests on

1. A tenderer who submits pre-qualification documents after the stipulated deadline has failed to comply with the express terms of the tender notice, and rejection of such a tender is justified even if the documents are submitted only a few days late, provided the deadline was clearly notified and sufficient time was given to submit the documents. 2. The court's jurisdiction to interfere with tender awards by a public authority is limited; courts cannot alter, amend or modify the terms and conditions of a tender or direct a tenderer-inviting authority to re-issue tenders on modified terms, as tender terms are contractual in nature and it is the privilege of the authority inviting tenders to frame them. 3. In evaluating a tender award by a public authority, the court must apply the principle that commercial considerations—including price, specifications, financial ability, past experience, and delivery capability—are paramount, but adherence to procedural rules and instructions in the tender notice is equally important to prevent discrimination, arbitrariness and favouritism and to uphold the rule of law. 4. Where a tender inviting authority awards a contract to the lowest tenderer who has complied with all requirements and the award is found to be reasonable and not arbitrary, the court will not set aside such award merely because a rejected tenderer's bid would have resulted in greater public savings, especially where doing so would cause delay in a time-bound project. 5. Strict adherence to the terms, conditions and deadlines specified in a tender notice cannot be disregarded as a pedantic approach; the enforcement of such rules is essential to prevent discrimination and to maintain the integrity of the tender process.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE
IN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
CIVIL APPEAL N. 1127 OF 2009(Arising out of SLP (C) No. 111 of 2009)

M/s. Sorath Builders .....Appellant

Versus

Shreejikrupa Buildcon Limited & Anr. .....Respondents

JUDGMENT

Dr. Mukundakam Sharma, J.

1. Leave Granted.

2. In the present appeal what is under consideration is the

construction of Veterinary College building at Navsari Agricultural

University, Gujarat (hereinafter referred to as "University"). Since

construction of the aforesaid building was required to be done

immediately, University released the grant which was going to lapse on

31.03.2009. The University issued a Tender Notice No. 20/2008-09 on

21.11.2008 inviting tenders for construction of Veterinary College building

at Navsari Agricultural University, Gujarat. The tender notice was widely

advertised through publication in newspaper "Sandesh", being the largest

local daily in the State of Gujarat. The tender notice was also published

on the internet. The notice inviting tenders required the following from

the bidders:

Page 1 of 12

a) Pre qualification documents had to be sent by 27.11.2008,

failing which the tender would be liable for rejection and

will not be opened;

i) "AA" Class certificate with minimum 80% of the project cost

turnover audited in the last financial year 2007-08;

ii) Bidding capacity value should be more than project cost;

iii) II Building category registration and above.

All the above documents have to be readily available with

any builder having continuous work for different

authorities.

b) Last date of "On Line" submitting of "Price bid" was

28.11.2008.

c) Tender fees, Earnest Money Deposit (EMD) and other

documents can be submitted by 04.12.2008.

3. Pursuant to the aforesaid advertisement three bids were received by

the University out of which one was disqualified at the threshold for not

having the requisite experience. Out of the remaining two, the bid of the

appellant - M/s. Sorath Builders was the lowest. One of the terms and

conditions of the bid was that pre-qualification documents were required

to be sent by 27.11.2008. Since the bid of respondent no. 1,

Shreejikrupa Buildcon Limited was sent on 01.12.2008 i.e. three days

after the last date of receiving these documents by the University the bid

of respondent no. 1 could not have been opened as it was received

Page 2 of 12 beyond the time stipulated and accordingly it was not taken into

consideration.

4. The University considered the following stipulation in the tender:

"Late date of "On Line" submission of price bid is dated 28/11/2008 upto 18.00 hrs. All documents, tender fees, registration, bank solvency, bank guarantee and EMD etc. duly scan along with the tender documents should be submitted "On Line". Last date for submission of pre- qualification documents by R.P.A.D./Speed Post is 27/11/2008. Any violation in the above instructions, the tender will be liable for rejection and will not be opened".

In terms of and in accordance with the mandate of the tender notice

the tender of respondent no. 1 - Shreejikrupa Buildcon Limited was not

opened. Being so situated, the respondent no. 1 filed a writ petition

before the High Court of Gujarat praying for quashing the decision of

respondent no. 2 - University dated 8.12.2008 considering the

respondent no. 1 as disqualified from participating in the tender selection

process for the construction of Veterinary College building at Navsari

Agricultural University, Gujarat.

5. The said writ petition was placed before the Division Bench and

after looking into the records and after hearing the parties the Division

Bench held that the University acted arbitrarily in requiring the pre

qualification documents to be sent physically so as to reach the University

by R.P.A.D./Speed Post by 27.11.2008, inasmuch as it meant that the

contractor had to send pre qualification documents by the aforesaid mode

Page 3 of 12 by dispatching the same latest by 25.11.2008. Consequently, the writ

petition was allowed and the decision of the respondent no. 2 - University

dated 10.12.2008 accepting the bid of the appellant was quashed and set

aside with a further direction that the University shall issue a fresh tender

notice with the same terms and conditions but it would also provide seven

days time for submitting the pre qualification documents after the end

date for downloading the bid documents.

6. Being aggrieved by the aforesaid Judgment and Order the present

appeal was filed in which several contentions were raised on behalf of the

parties.

7. It is the case of the appellant before us that the High Court has

wrongly set aside a settled contract pursuant to the tender issued by

respondent no. 2 - University on the ground that the terms of the tender

were arbitrary. It was also argued that the High Court has not only

interfered with the terms and conditions of the tender but has written the

terms of the tender itself by directing the University to issue a fresh

tender on the terms and conditions suggested in the said order. It was

also submitted that jurisdiction of the writ court to interfere in the terms

of a contract is very limited and that even if two views are possible and

the authorities granting tender takes a particular view, the courts should

not interfere. It was also submitted by the counsel appearing for the

appellant that the time period which was granted by the University cannot

Page 4 of 12 be said to be too short for it was possible for the respondent no. 1 to

submit the bid after satisfying all the requirements. It was also pointed

out that the respondent came to know about the tenders only on

27.11.2008 as he was undertaking various construction works, and

therefore could not submit the required pre qualification documents in

time within the stipulated date. It was also submitted that so placed and

situated, the respondent no. 1 was not entitled to and competent to take

up a plea that he did not receive sufficient time to submit the pre

qualification documents.

8. The case of respondent no. 1 on the other hand was that by

providing arbitrary time limit to submit pre qualification documents the

University tried to shut out competition and permitted only two eligible

parties to enter the fray. It was also submitted that the price bid offered

by respondent no. 1 was much lower than the appellant, being only

6.38% above the estimated contract value while bid offer of appellant

was 21.21% above the estimated contract value, which would mean that

the University would be unnecessarily spending public money to the tune

of more than Rs. 1 crore.

9. We have carefully considered the aforesaid submissions of the

counsel appearing for the parties. So far as the issue with regard to

stipulation that pre qualification documents to be sent latest by

27.11.2008 for the estimated contract value of Rs. 8.40 crores, is

Page 5 of 12 concerned, three parties applied and submitted their tenders and on

scrutiny it was found that one out of the three did not satisfy the

requirements, and therefore, his tender was rightly rejected by the

parties. So far as the tenders of the appellant and respondent no. 1 are

concerned, on going through the record we find that the respondent no. 1

never specifically raised the issue regarding paucity and shortage of time

as one of the grounds for challenging the decision of the University. The

only stand that was taken by respondent no. 1 for late submission of his

pre qualification documents is that he came to know about the tenders

only on 27.11.2008 as he was undertaking various construction works,

and therefore, could not submit all the required pre qualification

documents in time stipulated in the notice inviting tenders. The aforesaid

stand makes it crystal clear that respondent no. 1 was prevented in

submitting the required documents in time due to his personal difficulty

and not for the time schedule attached to the notice inviting tenders.

That was also not one of his grounds taken specifically in the writ petition

at any stage. But only during the course of hearing such a contention

seems to have been raised which found favour with the High Court. No

other intending bidder came to the court on any such plea that they were

deprived of an opportunity of submitting their tender due to paucity of

time and that any prejudice is caused to anyone due to time schedule

provided by the University. It appears that only during the hearing stage

a plea was raised which found favour with the High Court but as stated

above the aforesaid plea is without any merit for the advertisement was

Page 6 of 12 issued on 21.11.2008 requiring the parties to submit their pre

qualification documents only by 27.11.2008. Therefore, sufficient time

was provided to submit tender papers. The University also permitted pre

qualification documents to be submitted "On Line". Therefore, the

contention that the time was too short for submission of pre qualification

documents by 27.11.2008 is without any merit.

10. We also find on record that the tender submitted by the appellant

was the lowest and the same was accepted as the same was found to be

reasonable, tenable, plausible and valid. The High Court went beyond its

jurisdiction in setting aside the decision of the University in accepting the

bid of the appellant. We are of the opinion that there is no fault or

arbitrariness in the decision making process of the University. The said

decision cannot be said to be in any manner arbitrary or unreasonable.

The respondent no. 1 submitted his pre qualification documents late for

which he is only to be blamed. The University has taken a specific stand

before us that the price settled for the tender is neither unreasonable nor

excessive in comparison with the project. It was also stated before us

that the main interest of the University is to get a good quality Veterinary

College within the stipulated time because the grant out of which the

payment of construction of the college is to be made would lapse on 31st

March, 2009 and that the University has already started the process of

admission to the batch of students for the coming academic year.

Page 7 of 12 Consequently we feel that a time bound completion of a good quality

Veterinary College has become a necessity.

11. We are of the considered opinion that there is definitely urgency in

the aforesaid project, and therefore, the process of awarding the contract

of construction should be expedited and the same should not be stalled in

between. The process which is suggested by the High Court in its

Judgment and Order if allowed to be gone through the same would mean

prolonged delay in the completion of the project. The project is time

bound and money must be utilized by 31st March, 2009. The process of

re-tendering and allotment of fresh tender would mean delay and would

also be time consuming.

12. The Supreme Court in number of decisions has held that there is a

vital distinction between administrative and contractual law. In

Puravankara Projects Ltd. vs. Hotel Venus International and

Others, reported in (2007) 10 SCC 33, in which one of us, namely,

Justice Arijit Pasayat was a party, it was held as follows:

"tender terms are contractual and it is the privilege of the Government which invites its tenders and courts do not have jurisdiction to judge as to how the tender terms should be framed. By observing that there was an implied term which was not there in the tender, and postponing the time by which the bank guarantee had to be furnished, in essence the High Court directed modification of a vital term of the contract".

It further held that

Page 8 of 12 "the statutory parameters have to be kept in view and the High Court can never alter or amend a contract entered into between the parties".

In Raunaq International Ltd. vs. I.V.R. Construction Ltd. and

Others, reported in (1999) 1 SCC 492, this Court had occasion to dispose

of a case of paramount importance of Government contract. In the said

decision this Court has observed as follows:

"where rational non-discriminatory norms have been laid down for granting of tenders, a departure from such norms can only be made on valid principles. The award of contract cannot be by stopping the performance of the contract so awarded, there is a major detriment to the public because the construction of two thermal power units is held up on account of the dispute".

The court further held:

"the award of a contract, whether it by a private party or by a public body or the State, is essentially a commercial transaction. In arriving at a commercial decision, considerations which are of paramount importance are commercial considerations, and the same would be:

(1) The price at which the other side is willing to do the work;

(2) Whether the goods or services offered are of the requisite specifications;

(3) Whether the person tendering has the ability to deliver the goods or services as per specifications. When large works contracts involving engagement of substantial manpower or requiring specific skills are to be offered, the financial ability of the tenderer to fulfil the requirements of the job is also important;

(4) The ability of the tenderer to deliver goods or services or to do the work of the requisite standard and quality;

Page 9 of 12 (5) Past experience of the tenderer and whether he has successfully completed similar work earlier;

(6) Time which will be taken to deliver the goods or services; and often

(7) The ability of the tenderer to take follow-up action, rectify defects or to give post-contract services".

It was also held in the said decision:

"the public would also be interested in the quality of the work undertaken or goods supplied by the tenderer for poor quality of goods can lead to tremendous public hardship and substantial financial outlay either in correcting mistakes or in rectifying defects or even at times in re-doing the entire work

- thus involving larger outlays of public money and delaying the availability of services, facilities or goods".

13. The prime consideration on which the High Court set aside the

award of contract in favour of the appellant is that if the bid of respondent

no. 1 was considered in the tender process there would have been saving

of public money. However, that would not in any manner justify in going

through once again the same tender process, which is always time

consuming. Any delay in awarding the contract would only mean increase

in the cost of expenditure for cost of construction would go up with the

passage of time.

14. In W.B. State Electricity Board vs. Patel Engineering Co. Ltd.

and Others, reported in (2001) 2 SCC 451, this Court while considering

the issue with regard to the process of tender held:

"where bidders who fulfil prequalification alone are invited to bid, adherence to the instructions cannot be given a go-by by

Page 10 of 12 branding it as a pedantic approach, otherwise it will encourage and provide scope for discrimination, arbitrariness and favouritism which are totally opposed to the rule of law and constitutional values".

It was also held:

"the very purpose of issuing rules/instructions is to ensure their enforcement lest the rule of law should be a casualty".

It was further held:

"the contract is awarded, normally, to the lowest tenderer which is in public interest and that it is equally in public interest to adhere to the rules and conditions subject to which bids are invited".

15. Following the aforesaid legal principles laid down by this Court, we

are of the considered opinion that the respondent no. 1 was negligent and

was not sincere in submitting his pre qualification documents within the

time schedule laid down despite the fact that he had information that

there is a time schedule attached to the notice inviting tenders. Despite

being aware of the said stipulation he did not submit the required

documents within the stipulated date. Pre-qualification documents were

received by the respondent no. 2 - University only after time schedule

was over. The terms and conditions of the tender as held by the Supreme

Court are required to be adhered to strictly, and therefore, the

respondent no. 2 - University was justified in not opening the tender

submitted by respondent no. 1 on 01.12.2008, which was late by three

days. According to us no grievance could also be made by the respondent

no. 1 as lapse was due to his own fault. The High Court proceeded to

interfere with the entire process as if acting as an appellate authority over

Page 11 of 12 the decision of the University which was beyond the jurisdiction of the

Court. The High Court was not justified in accepting the contentions of

respondent no. 1 and thereby upsetting the entire process of inviting

tenders by interfering with the terms and conditions of inviting the

tenders and by rescheduling and directing the process of re-tendering,

which would only cause further delay and would increase the burden on

the exchequer of the University.

16. In that view of the matter, we set aside the Judgment and Order of

the High Court and upheld the decision of the University in awarding the

contract in favour of appellant. Accordingly, the appeal stands allowed.

.............................................J. [Dr. Arijit Pasayat]

..............................................J. [Dr. Mukundakam Sharma]

New Delhi, February 20, 2009

Page 12 of 12

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free