Miss Lucy
← All judgments

M/S Shri Karshni Alloys Private Limited vs Ramakrishnan Sadasivan

Supreme Court10 December 2025

Ratio decidendi

The rule this decision rests on

1. A sale of assets by a liquidator pursuant to prior permission of the NCLT granted under Regulation 33(2)(d) of the Insolvency and Bankruptcy Board of India (Liquidation Process) Regulations, 2016 is not governed by the Indian Contract Act, 1872, but is subject to the IBC and NCLT supervision; accordingly, a forfeiture condition stipulated by the NCLT as a term of extension of time granted under Rule 15 of the National Company Law Tribunal Rules, 2016 cannot be assailed as a penalty clause under Section 74 of the Indian Contract Act, 1872. 2. Under Rule 15 of the NCLT Rules, which empowers the NCLT to extend time upon such terms as the justice of the case may require, the NCLT is justified in stipulating forfeiture of amounts paid if the purchaser fails to comply with extended timelines for payment, particularly where the purchaser had committed to a temporal obligation in its original offer and later sought extension but thereafter failed to meet even the extended deadlines. 3. A purchaser who accepts and acts upon an NCLT order granting extension of time coupled with a forfeiture condition—by making further payments after the order—cannot subsequently approbate and reprobate by challenging the very forfeiture clause contained in that order which it had accepted and acted upon. 4. The expeditious resolution of liquidation proceedings is a crucial object of the IBC scheme; time stipulations in NCLT orders are material to this purpose and forfeiture conditions reinforcing compliance with such stipulations are within the NCLT's power to impose under Rule 15 of the NCLT Rules. 5. A party that files a statutory appeal before the NCLAT while simultaneously filing a writ petition before the High Court against the same order without disclosing the appeal, and misrepresents to the High Court that the time for appeal has expired, thereby securing interim relief, is disentitled to relief on grounds of abuse of process and lack of bonafides, independently of the merits.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

Non-reportable 2025 INSC 1411 IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOs. 3625-3628 OF 2025

M/s. Shri Karshni Alloys Private Limited … Appellant

versus

Ramakrishnan Sadasivan … Respondent

JUDGMENT

SANJAY KUMAR, J

1. Company Appeal (AT)(CH)(Ins) No. 443 of 2022 was filed by M/s. Shri

Karshni Alloys Private Limited before the National Company Law Appellate

Tribunal, Chennai Bench1, assailing the order dated 29.06.2022 passed by

the National Company Law Tribunal, Chennai Bench 2, in I.A. No. (IBC)/512

(CHE)/2021 in TCP/95/2017. Company Appeal (AT)(CH)(Ins) No. 438 of

2022 was also filed by it before the NCLAT against the order dated

10.08.2022 passed by the NCLT in l.A. No. 952/2022 in TCP/95/2017. Both

the appeals were heard by a bench composed of two Members and they

delivered separate judgments on 20.10.2023. However, the Member Signature Not Verified Digitally signed by Deepak Guglani Date: 2025.12.10 16:39:31 IST Reason:

1 For short, ‘the NCLAT’ 2 For short, ‘the NCLT’ (Judicial) disagreed with the judgment authored by the Member (Technical).

The Member (Technical) had partly allowed the appeals while the Member

(Judicial) was inclined to dismiss them in their entirety. Owing to their

difference in opinion, the Chairperson of the NCLAT referred the matter to

another Member (Technical). By judgment dated 31.05.2024, the third

Member agreed with the view taken by the Member (Judicial) and, in

consequence, the appeals stood dismissed.

2. Aggrieved by the dismissal of its appeals, M/s. Shri Karshni Alloys

Private Limited filed the present appeals under Section 62 of the Insolvency

and Bankruptcy Code, 20163. The respondent in the appeals, viz.,

Ramakrishnan Sadasivan is the liquidator of M/s. Surana Industries Limited.

3. The corporate insolvency resolution process against M/s. Surana

Industries Limited was initiated on 02.01.2018 but its liquidation commenced

pursuant to the order dated 12.10.2018 passed by the Adjudicating Authority.

The respondent was thereupon appointed as the liquidator. The company

under liquidation owned assets/plants at Gummidipoondi in the State of Tamil

Nadu and Raichur in the State of Karnataka. Between 06.01.2019 and

02.02.2021, six auctions were held by the liquidator for the sale of these

assets/plants. However, only the assets/plant at Gummidipoondi were sold.

3 For short, ‘the IBC’

2 As regards the assets/plant at Raichur, altogether thirteen auctions were

conducted unsuccessfully by the liquidator till 30.06.2021. It was then

decided that the said assets/plant should be sold at the scrap value of

approximately ₹50 crores and the same was approved by the Stakeholders

Consultation Committee4 at its meeting held on 31.07.2021.

4. While so, on 09.09.2021, the appellant made an offer of ₹105.21 crores

to the liquidator to purchase the assets/plant at Raichur as a going concern.

This proposal was placed before the SCC at its meeting held on 15.09.2021

and they consented to the sale. The appellant’s proposal envisaged that the

appellant and its associates would invest ₹40 crores by way of equity infusion

and the balance ₹65.21 crores would be brought in through unsecured debts.

The appellant deposited 10% of the sale consideration, i.e., ₹10.5210 crores,

as a commitment advance. Pursuant thereto, on 22.09.2021, the liquidator

filed an application, viz., IA No. 997/CHE/2021 in TCP/95/IB/2017, before the

NCLT seeking its approval for the private sale of the assets/plant at Raichur

to the appellant. The NCLT allowed the application on 22.03.2022 and

directed the appellant to pay the sale consideration within 15 days from the

date of receipt of the said order. The application was filed by the liquidator

on 22.09.2021 but the same was allowed by the NCLT only on 22.03.2022.

4 For short, ‘the SCC’

3

5. The appellant claims that owing to this efflux of time and the changes

in the market scenario, it had difficulty in making the payment within the time

stipulated. On 13.04.2022, a meeting of the SCC was held and it was

decided to extend the timeline till 30.05.2022 to enable the appellant to make

the payment. This extension was stated to be a measure of prudence,

factoring in unforeseen circumstances. The stakeholders were unwilling to

extend the time till 28.06.2022 as sought by the appellant, opining that a

three-month extension may result in cancellation of the proposal.

6. Thereupon, the appellant filed IA No. (IBC)/512(CHE)/2022 in IA No.

997/CHE/2021 in TCP/95/IB/2017 before the NCLT, seeking extension of

time till 31.05.2022 to make the balance payment. By order dated

29.06.2022, the NCLT noted that the appellant had paid ₹36.30 crores till

that date, as was admitted by the liquidator, and granted extension of time.

The appellant was directed to pay 50% of the balance sale consideration,

i.e., ₹34.60 crores, with 12% interest thereon from 15.04.2022 till the date of

payment, on or before 30.06.2022; and the remaining 50%, i.e., ₹34.60

crores, with 12% interest thereon from 15.04.2022 till the date of payment,

on or before 31.07.2022. The NCLT categorically recorded that the appellant

should strictly comply with these timelines and any deviation from the same

would result in forfeiture of the entire amount paid by the appellant.

4

7. Admittedly, the appellant failed to abide by the extended timelines.

It, however, paid a further sum of ₹1.50 crores, thereby bringing the total

amount paid by it to ₹37.80 crores. At the SCC’s meeting held on 01.08.2022,

the stakeholders decided to enforce forfeiture of the entire payment made by

the appellant, as per the NCLT’s order, and that the liquidator should issue a

fresh auction notice to dispose of the assets/plant at Raichur. By letter dated

02.08.2022, the liquidator informed the appellant that, as the payment had

not been made by it as directed by the NCLT, the entire amount of ₹37.80

crores paid by it stood forfeited, in adherence to the order dated 29.06.2022

passed by the NCLT. The appellant, thereupon, filed IA No. 952 of 2022 in

TCP/95/2017 assailing the liquidator’s letter dated 02.08.2022, whereby the

sum of ₹37.80 crores paid by it stood forfeited. It also sought further

extension of time to pay the balance sale consideration with waiver of

interest. However, by order dated 10.08.2022, the NCLT dismissed the

application. The NCLT noted therein that the liquidator had issued the letter

dated 02.08.2022 based on its earlier order dated 29.06.2022 and if the

appellant had been aggrieved thereby, it ought to have challenged the same

but had not done so. The NCLT, therefore, opined that merely challenging

the liquidator’s letter dated 02.08.2022 would not suffice as, once there was

non-payment of the sum as directed by it, the forfeiture became automatic.

5

8. The liquidator published a fresh e-auction sale notice in relation to the

Raichur assets/plant on 12.08.2022. On 13.08.2022, the appellant filed

Company Appeal (AT)(CH)(Ins) No. 443 of 2022 before the NCLAT

challenging the earlier order dated 29.06.2022 passed by the NCLT.

Thereafter, on 31.08.2022, the appellant filed Company Appeal (AT)(CH)

(Ins) No. 438 of 2022 against the later order dated 10.08.2022. Having filed

the said appeals, the appellant chose to file a writ petition before the High

Court of Madras, viz., Writ Petition No. 24262 of 2022. Therein, it sought a

writ of certiorarified mandamus to call for the records of the NCLT’s order

dated 29.06.2022 and to quash the same along with the subsequent actions

taken by the liquidator. It also sought extension of time to enable it to make

the balance payment and conclude the sale or, in the alternative, to direct

the liquidator to refund the entire amount paid by it along with interest.

9. Before the High Court, it was contended by the learned senior counsel

who appeared for the appellant that it could not file an appeal before the

NCLAT in relation to the order dated 29.06.2022, impugned in the Writ

Petition, owing to the limitation prescribed under the IBC. Having noted this

submission in the order, the High Court observed that the appellant had not

exhausted the statutory remedy of preferring an appeal, though it had the

opportunity and time to do so. It was noted that, after the dismissal of its

6 extension application on 10.08.2022, the appellant still had four days’ time to

file an appeal against the order dated 29.06.2022, but without doing so, the

appellant had chosen to file a writ petition on 05.09.2022. Holding that there

were several factual disputes which could not be adjudicated under Article

226 of the Constitution of India, the High Court dismissed the writ petition as

not maintainable, vide order dated 24.11.2022.

10. Significantly, the appellant did file an appeal against the order dated

29.06.2022 before the NCLAT on 13.08.2022 but did not disclose the same

in its writ petition filed on 05.09.2022. This is clear not only from its senior

counsel’s statement but also from para 14 of the order, wherein the High

Court noted that the appellant filed an appeal against the order dated

10.08.2023 passed by the NCLT relating to the same issue and left all

contentions available to the appellant to be raised in the said appeal.

11. As noted earlier, the Member (Judicial) of the NCLAT, by his judgment

dated 20.10.2023, dismissed both the appeals filed by the appellant while,

by her separate judgment of the same date, the Member (Technical) partly

allowed the appeals holding that, out of the forfeited amount of ₹37.80 crores

only 10%, i.e., ₹10.5210 crores, was liable to be forfeited, as per Clause 9 of

the appellant’s offer, and directed the balance amount to be refunded. In the

light of this split verdict, the matter was referred to the third Member, i.e., a

7 Member (Technical), and he agreed with the view taken by the Member

(Judicial), by way of his judgment dated 31.05.2024. In effect, the appeals

filed by the appellant stood dismissed in their entirety, as per the majority

opinion. The appellant is before us challenging the two majority opinions.

12. Perusal of the two opinions under appeal reflects that the majority were

of the view that the sale in favour of the appellant was under Regulation

33(2)(d) of the Insolvency and Bankruptcy Board of India (Liquidation

Process) Regulations, 2016 5. The contention of the appellant that the sale

was under Regulation 33(2)(c) of the Liquidation Regulations, which

provides for private sale of the assets of the corporate debtor by the liquidator

when the asset is sold at a price higher than the reserve price of a failed

auction, was rejected. The consequential argument of the appellant that its

sale transaction was, in effect, a contract governed by the provisions of the

Indian Contract Act, 1872, was also rejected. Reference was made to Rule

15 of the National Company Law Tribunal Rules, 20166, which empowers

the NCLT to extend time upon such terms, if any, as the justice of the case

may require, and it was opined that as the forfeiture clause in the order dated

29.06.2022 was to come into effect only if the appellant failed to make the

5 For short, ‘the Liquidation Regulations’ 6 For short, ‘the NCLT Rules’

8 payment by 31.07.2022, the condition was rational as the intent was to

resolve the liquidation process expeditiously. It was held that this stipulation

was well within the power of the NCLT under Rule 15 of the NCLT Rules.

13. We must also note that the liquidation value of the assets/plant at

Raichur was assessed thrice. In December, 2018, it was assessed at

₹338.01 crores; in August, 2019, it fell to ₹227.31 crores; and in August,

2020, it fell further to ₹117.23 crores. However, pursuant to the liquidator’s

efforts to sell the assets/plant, after the appellant’s failure to make the

payment, the same was sold to M/s. Texcon Steels Limited for ₹145.38

crores on 30.08.2022. In that context, the appellant contended before the

NCLAT that, as the resale value was far higher than the amount offered by

it, i.e., ₹105.21 crores, there was no actual loss suffered by the stakeholders.

Dealing with this argument, the majority observed that the outstanding dues

of the financial creditors were never fully recovered and they had to suffer a

major haircut even if the assets/plant at Raichur were eventually sold at a

value higher than that offered by the appellant. The majority also took note

of the crucial fact that the appellant had accepted and acted upon the order

dated 29.06.2022 by making two more payments, amounting to ₹1.50 crores

on 13.07.2022 (₹0.50 crore) and on 25.07.2022 (₹1.00 crore). Given the

aforestated facts, the majority opined that the appellant could not approbate

9 and reprobate in relation to the order dated 29.06.2022, that is, by acting

upon it, on the one hand, and assailing it, on the other. They, therefore, held

against the appellant and dismissed its appeals against the NCLT’s orders

dated 29.06.2022 and 10.08.2022.

14. The learned senior counsel appearing for the appellant would contend

that, as the stakeholders did not suffer any loss in the long run as the

assets/plant at Raichur were sold for a much higher price than that offered

by the appellant, forfeiture of the amounts paid by the appellant was not just

and lawful. Reliance was sought to be placed on case law pertaining to

Section 74 of the Indian Contract Act, 1872, apropos compensation payable

for breach of contract. On the other hand, the learned counsel appearing for

the liquidator would argue that extension of time was granted by the NCLT

in exercise of power under Rule 15 of the NCLT Rules, which was duly acted

upon by the appellant by making a further payment of ₹1.50 crores, and

having done so, the appellant could not seek to assail the condition included

therein as regards forfeiture. The learned counsel would, therefore, contend

that this is not a case of penalty or unjust enrichment falling under Section

74 of the Indian Contract Act, 1872, and that the judgments relied upon by

the other side have no relevance. He would point out that the appellant filed

its appeal against the order dated 29.06.2022 before the NCLAT on

10 13.08.2022, but deliberately kept the same defective till 28.12.2022, and

having done so, the appellant chose to file the writ petition on 05.09.2022

and it was stated before the High Court by the learned senior counsel

appearing for the appellant that the time for filing an appeal against the

NCLT’s order dated 29.06.2022 had already expired. He also pointed out that

the appellant, by resorting to this subterfuge, secured an interim order on

29.09.2022, which continued to operate till the dismissal of the writ petition

and even by the said date, the appellant did not inform the High Court that it

had filed an appeal against the NCLT’s order dated 29.06.2022. The learned

counsel stated that after dismissal of the writ petition, the liquidator

distributed the forfeited amount amongst the stakeholders as per law and

there is, therefore, no cause to turn back the clock at this stage when the

appellant was wholly disentitled from claiming any relief.

15. Having given our earnest consideration to the matter, we must stress

upon certain critical facts. The last auction in relation to the assets/plant at

Raichur was held on 28.07.2021 with a reserve price of ₹105 crores.

However, no bids were forthcoming on that date. Thereupon, the SCC held

a meeting on 31.07.2021 and decided to sell the said assets/plant at the

scrap value of approximately ₹50 crores. The auction process, therefore,

stood concluded in its entirety, having culminated in failure, and the later

11 decision of the stakeholders to resort to a scrap sale was in place on the date

the appellant made its offer on 09.09.2021, proposing to buy the assets/plant

at Raichur as a going concern. Perusal of the said proposal demonstrates

that the appellant made a commitment that, after deducting its initial deposit

of ₹10.5210 crores made along with its offer as a commitment advance, the

balance payable out of the offered ₹105.21 crores would be deposited within

15 days from the date of receipt of the approval of the sale by the competent

authority, i.e., the NCLT. This offer was considered by the stakeholders in

their 9th meeting held on 15.09.2021. All 15 secured financial creditors/

stakeholders were present online and upon being informed of the proposal

made by the appellant, including its commitment to pay the balance amount

after deduction of the commitment advance of ₹10.5210 crores within 15

days from the date of approval of the sale by the NCLT, the stakeholders

asked the liquidator to take the process forward in keeping with the IBC.

16. Pursuant thereto, the liquidator filed IA No. 997/CHE/2021 in

TCP/95/IB/2017 seeking approval of the NCLT for the sale in favour of the

appellant. It is, therefore, clear that this sale did not fall within the ambit of

Regulation 33(2)(c) of the Liquidation Regulations but was squarely covered

by Regulation 33(2)(d) thereof. Regulation 33(2), to the extent relevant,

reads as follows:

12

‘(2) The liquidator may sell the assets of the corporate debtor by means of private sale in the manner specified in Schedule I when-

(a) the asset is perishable;

(b) the asset is likely to deteriorate in value significantly if not sold immediately;

(c) the asset is sold at a price higher than the reserve price of a failed auction; or

(d) the prior permission of the Adjudicating Authority has been obtained for such sale:’ Once the stakeholders directed the liquidator to take the process

forward in accordance with the IBC and the liquidator filed an IA seeking

approval of the NCLT for the sale, there is no possibility of the appellant trying

to bring the sale within the ambit of Regulation 33(2)(c). Be it noted that the

auction process failed in July, 2021, itself and was thereafter followed by the

decision of the stakeholders to resort to a scrap sale and the question of the

assets/plant being sold at a price higher than the reserve price of the failed

auction was not available thereafter. It was thus a private sale that required

prior permission of the NCLT and the liquidator, accordingly, resorted to that

procedure. By order dated 22.03.2022, the NCLT accepted the proposal put

forth by the appellant and directed it to pay the sale consideration within 15

days from the date of receipt of its order, as proposed by the appellant itself.

Contrary to its own commitment in the offer made on 09.09.2021, the

appellant then sought extension of time beyond the stipulated 15 days.

17. The stakeholders showed lenience in that regard in their 10th meeting

held on 13.04.2022 and agreed to extend the time till 30.05.2022, subject to 13 the condition that the appellant would pay interest at 12% per annum on the

payments made post 15.04.2022. The appellant was asked to submit an

application before the NCLT seeking approval of the proposed revision in the

timeline for making the payment. Pursuant thereto, the appellant filed IA No.

(IBC)/512/CHE/2022 before the NCLT seeking extension of time till

31.05.2022. This application was filed on 25.04.2022. It is on this application

that order dated 29.06.2022 was passed by the NCLT, stating as follows:

‘(i) The Applicant is directed to pay on or before 30.06.2022 the balance 50% of the sale consideration i.e., 34.60 Crore with 12% interest from 15.04.2022 till the date of payment.

(ii) The remaining sum of Rs. 34.60 Crore shall be paid on or before 31.07.2022 with 12% interest from 15.04.2022 till the date of payment.

(iii) The Applicant is directed to strictly comply with the said timelines. Any deviation from the same would amount to forfeiture of the entire amount paid by the Applicant.’

18. We may note that the appellant itself had asked for extension of time

till 31.05.2022 in its prayer in the aforestated IA and as the order was being

passed on 29.06.2022, the NCLT seems to have acted upon the appellant’s

own suggested time frame and directed it to pay ₹34.60 crores with 12%

interest from 15.04.2022 by 30.06.2022, i.e., the very next day. As the

appellant had approached the NCLT for extension of time two months earlier,

stipulating that it required time till 31.05.2022, the NCLT would have

obviously expected that the appellant would have arranged for the funds to

be paid in terms of the extended timeline prayed for by the appellant itself.

14 Therefore, when the NCLT granted just one day’s time to the appellant to pay

50% of the balance amount due, it was justified in doing so and the appellant

cannot make much of the fact that it was required to pay that amount by the

very next day. Further, as the appellant had already backtracked on the

commitment in its offer made on 09.09.2021 with regard to paying the entire

amount within 15 days from the date of approval by the NCLT, i.e., from

22.03.2022, and the appellant was being given an extended timeline to make

the payment at least by 31.07.2022, i.e., nearly 4 months later, the NCLT was

fully justified in adding the forfeiture clause that if the appellant deviated from

the timelines as set out in the order dated 29.06.2022, the entire amount paid

by it was liable to be forfeited. As rightly noted in the clinching judgment dated

31.05.2024, the NCLT was exercising power under Rule 15 of the NCLT

Rules and was, therefore, at liberty to stipulate such terms as the justice of

the case required. As pointed out by this Court in Kridhan Infrastructure

Private Limited vs. Venkatesan Sankaranarayan and others 7, time is a

crucial facet of the scheme under the IBC and to allow such proceedings to

lapse into indefinite delay would plainly defeat the very object of the statute.

19. Further, the conduct of the appellant during the course of the

proceedings also disentitled it from seeking relief. The clandestine act of

7 (2021) 6 SCC 94

15 filing a writ petition before the High Court, suppressing the fact that it had

already filed an appeal before the NCLAT against the order dated

29.06.2022, and attempting to challenge the very same order under Article

226 of the Constitution, clearly reflected on its lack of bonafides. Such abuse

of process warranted non-suiting of the appellant on that ground itself. Even

on merits, we find that the appellant had no justifiable claim to seek refund

of the amounts paid by it, which stood forfeited in keeping with the order

passed by the NCLT. This was not a case of a contract between the appellant

and the liquidator/stakeholders, whereby the appellant could seek to fall back

on Section 74 of the Indian Contract Act,1872. The sale in question was

purely under the supervision of the Adjudicating Authority, i.e., the NCLT, and

the forfeiture condition stipulated by the NCLT while granting extension of

time cannot be equated with a forfeiture clause in a contract. Having made

an offer, coupled with a temporal commitment, which was duly accepted by

the NCLT, vide its order dated 22.03.2022, the appellant went before the

NCLT and sought extension of time. That extension was granted, saddled

with the condition of forfeiture in the event of failure, and was duly accepted

and acted upon by the appellant, as already noted supra. The appellant

actually made payments to the tune of ₹1.50 crores after the passing of the

extension order dated 29.06.2022 but failed to make the full payment by

16 31.07.2022. The appellant cannot, therefore, seek to approbate and

reprobate at this stage by assailing the forfeiture clause in the said order,

having accepted and acted upon the extension granted thereunder.

20. On the above analysis, be it viewed from any angle, we find no merit

in the contentions advanced on behalf of the appellant. The appeals are,

therefore, bereft of merit, be it on facts or in law. No grounds are made out

to interfere with the majority opinions of the Member (Judicial) and the

Member (Technical) of the National Company Law Appellate Tribunal,

Chennai Bench, holding against the appellant and dismissing its appeals.

The appeals are, accordingly, dismissed.

Parties shall bear their respective costs.

……………………...J [SANJAY KUMAR]

……………..………J [ALOK ARADHE]

December 10, 2025 New Delhi.

17

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free