Miss Lucy
← All judgments

M/S. Nava Bharat Ferro Alloys Ltd vs Transmission Corpn.Of A.P.Ltd.& Anr

Supreme Court18 November 2010T.S. Thakur · Markandey Katju

Ratio decidendi

The rule this decision rests on

1. An interim order of stay operating during the pendency of a writ petition does not relieve the consumer from the obligation to pay the tariff charges and any stipulated interest or surcharges on delayed payment when the substantive writ petition is finally dismissed. 2. When a Court's decision that struck down or stayed a revision of tariffs is itself reversed on appeal, the liability to pay the revised tariff revives with full force from the date the revision was made effective, not from the date of the appellate judgment. 3. The principle of restitution, once applied by a court reversing an erroneous prior decision, entitles the party who suffered loss by that erroneous decision to claim compensation including interest at stipulated contractual rates, even where the other party did not deliberately default but was protected by the court order during the pendency of proceedings. 4. A distinction exists between a final adjudication striking down an order and an interim order granting stay of operation; while the former has finality in restoring the position as it stood before the order was passed, the latter merely suspends operative effect and carries no implication that the underlying obligation ceases to exist. 5. Where a contract of supply of electricity stipulates payment of interest or surcharge on delayed payment, such stipulation remains enforceable even during periods when the tariff revision itself was unenforceable by court order, provided the writ petition challenging the tariff is ultimately dismissed.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICITION
CIVIL APPEAL NO.1607 OF 2004

M/s Nava Bharat Ferro Alloys Ltd. ...Appellant

Versus

Transmission Corporation of A.P. Ltd. and Anr. ...Respondents

(With CA Nos.1608-1609 of 2004 and CA No.4741 of 2006)

J U D G M E N T

T.S. THAKUR, J.

1. These appeals by special leave arise out of an

order dated 6th June, 2002 passed by the High Court of

Andhra Pradesh whereby Writ Petitions No.9081 of 1999

and 13458 of 1993 filed by the appellant have been

dismissed and the demand for additional

charges/surcharge payable on the delayed payment of

outstanding electricity dues raised under Clause 32.2.1

and 34 of the Terms and Conditions of supply (TCS) 2

upheld. Facts necessary for the disposal of these

appeals may be summarised as under:

2. The appellant is a public limited company engaged

in the manufacture of Ferro Silicon. The industry set

up by the appellant is energy intensive in as much as it

consumes approximately 10,000 units of electricity for

every ton of Ferro Silicon produced. The appellant's

case is that the respondent-Electricity Board had

initially agreed to supply power to the appellant @ 6

paise per unit but revised the said rate to 11 paise per

unit in the year 1975. The revised rate was in the

beginning applicable only to four consumers who were

similarly situate but the number of such power intensive

consumers gradually rose to 84. On 13th December, 1983

the Board revised the general tariff but a separate

order applicable to power intensive consumers like the

appellant was issued on 29th January, 1984. Aggrieved by

the said order which permitted charging of a higher rate

of tariff, the appellant and few others filed writ

petitions before the High Court of Andhra Pradesh, which

were dismissed by a Division Bench of that Court on 3rd

April, 1985. During the pendency of the writ petition,

however, the High Court had granted an interim order of 3

stay against the collection of the disputed amount in

the following terms:

"There shall be stay of operation of the order in so far as writ petition is concerned, subject to the condition if the writ petitioner pays at the rate of 47.89 paise per unit with effect from April 1984 onwards, furnishing Bank guarantee for the balance to the satisfaction of the Superintending Engineer concerned in four weeks from today. In default of any of the conditions, the stay stands vacated. The bank guarantee furnished shall be renewed for every 3 months. If the petitioner has already paid the demand for the month of April, on the basis of the impugned order, this order passed by me shall be effective from the month of May 1984 otherwise it will be operative from April, 1984."

3. The dismissal of the writ petitions filed by the

appellants was assailed by them before this Court by way

of special leave petitions nos.9206-9207/1985 (C.A.

Nos.2569-2570/1985). This Court by an order dated 22nd

July, 1985 while granting leave to appeal directed

continuation of interim arrangement made by the High

Court in the following terms:

"As regards stay, after hearing learned counsel for the parties we felt that the order passed by the High Court dated 24.4.1984 which operated during the pendency of the writ petitions will continue to operate during the pendency of the appeals 4

with the modification that the rate of 47.89 paise per unit mentioned in the order is rounded to 48 paise per unit.

We would, however, like to make it clear that because of the High Court's order dated 13.4.1985, for a couple of months, there was no such orders in regard to future payments and the Electricity Board has received the dues at the enhanced rates in lump sum from some of the consumers. There will no question of refunding the amounts back to these consumers.

The bank guarantee already furnished by the petitioners/appellants will be kept alive from time to time and will cover all the differences including the future difference."

4. It is not in dispute that the above order was

modified subsequently in respect of the bills issued from

16th March, 1990 onwards. The appeals, eventually failed

and were dismissed by this Court by an order dated 2 nd

May, 1991. In I.As. filed by the appellant post-

dismissal of the appeals, this Court passed an order on

9th May, 1991 to the effect that the appellants could

after paying outstanding 50% of the amount due under the

subsisting bank guarantee make representation to the

Board for payment of the balance amount in instalments

keeping in view the circumstances and the hardships in

each individual case. Consequently, the appellants made a

representation to the Board praying for grant of

installments for payment of the balance amount. While 5

the said request was under consideration, the appellant

received a communication dated 14th June, 1991 from the

Superintending Engineer pointing out that an amount of

Rs.5,57,66,539.18 was recoverable from the appellant for

the period April 1984 to August 1987. For the recover of

the outstanding amount the Board invoked the bank

guarantee furnished to it for a sum of Rs.2,83,53,120.93

thereby leaving a balance of Rs.2,74,13,218.25 due and

payable which amount the appellant was requested to

arrange. The communication also pointed out that in

addition to the above amount arrears of Rs.4,45,63,903.21

for the period from August 1987 to July 1989 were also

payable besides additional charges for delayed payments

of the said amount which the latter proposed to

communicate separately.

5. The request made by the appellant for payment of the

balance amount of tariff arrears was accepted by the

Board in terms of communication dated 9th July, 1999. It

was in the above background that the appellant filed writ

petitions No.9081 of 1999 and 13458 of 1993 raising

common questions of law relevant to two different periods

in the High Court of Andhra Pradesh, inter alia,

assailing the demand of additional charges and interest 6

on the delayed payment of the amounts determined pursuant

to the judgment of this Court. By the order impugned in

these appeals the said petitions have been dismissed by

the High Court. The High Court held that the Terms and

Conditions of Supply (TCS) were statutory in character

and were not in conflict with any provision of the

Electricity Supply Act or the Constitution of India. It

also held that Clause 32.2.1 and Clause 34 of the said

Terms and Conditions of Supply upon which the Board

placed reliance for its demand did not violate any

constitutional or statutory provision. The stipulated

terms and conditions were, according to the High Court,

intended to achieve the objective mentioned in Clause (b)

of sub-section 2 of Section 49 of the Act, namely, to

discourage delayed payment of electricity dues and to

compensate the Board in cases of delay in the making of

the payment. Both these conditions, according to the High

Court were intended to sustain the economic health of the

Board.

6. The High Court further held that the decisions of

this Court in Kerala State Electricity Board v. MRF

Limited (1996) 1 SCC 597 and Kanoria Chemicals and

Industries Ltd. v. U.P. State Electricity Board (1997) 5 7

SCC 772 were of no assistance to the appellants. The High

Court noted the factual background in which the said

decisions were rendered and found that in cases before it

there was no justification for nullifying the effect of

the Clauses 32.2.1 and 34 of the T.C.S.

7. Appearing for the appellants Mr. Sudheer Chandra

Agarwal, learned senior counsel, strenuously agued that

the High Court had fallen in error in declining relief to

the appellant which according to the learned counsel was

due to it on the analogy of the orders of this Court in

Kerala State Electricity Board's case (supra). It was

submitted that in the light of the decision of this Court

in Kerala State Electricity Board's case (supra) the

appellant-consumers could not be said to be in default of

payment of the outstanding amount during the period the

interim order passed by the High Court in its favour had

remained operative. It was further contended that this

Court had in the above case and in Kanoria Chemicals's

case (supra) dealt with a similar fact situation and

granted relief, by awarding interest @ 18% to the Board

to compensate it for the monetary loss that it may have

suffered on account of delay in the making of such

payment and to prevent any prejudice and consequent 8

injustice to the Board on account of the direction issued

by the Court. It was argued that the appellant-company

was ready and willing to pay interest @ 18% p.a. on the

outstanding amount for the relevant period but the demand

raised by the Board being far in excess, deserves to be

suitably reduced.

8. On behalf of the respondent it was, on the other

hand, argued by Mr. C. Kodanda Ram, learned senior

counsel, that the High Court was, in the facts and

circumstances of the case, right in distinguishing the

decisions relied upon by the appellant and declining the

relief prayed for before it. It was submitted that the

facts situation in which the relief was granted in those

cases was different from that of the present case. It

was further argued that the additional charges and

interest were payable in terms of the TCS which was

statutory in character and to which the appellant had

agreed to abide by. The amount which the appellant had

not paid would have been utilized by it in its commercial

ventures to make profits. Non-payment of the dues

recoverable from the appellant would, therefore, expose

the Board to serious financial prejudice and loss. 9

9. The case of the appellant-company rests entirely

upon the decisions of this Court in the case of Kerala

State Electricity Board (supra) and that delivered in the

case of Kanoria Chemicals Ltd. (supra). The argument

advanced on behalf of the appellant in essence is that

the fact situation in the said two cases being similar to

the one at hand grant of interest @ 18% p.a. on the

outstanding amount would meet the ends of justice in the

instant case also.

10. There is, in our opinion, a basic fallacy in the

analogy which the appellant draws between its case and

the cases referred to above. What is overlooked by the

appellant is the fact that the decision of this Court in

the Kerala State Electricity Board's case (supra) has

enforced the terms under which the supply of energy was

made to the consumers in that case. Award of interest @

18% p.a. is not an innovation of this Court. The

consequence of non-payment of the amount within the time

stipulated was on the contrary prescribed in the tariff/

conditions subject to which energy was supplied to MRF

the consumer in that case. It would not, therefore, be

correct to apply the tariff conditions relevant to that

case to the case at hand where such conditions are 1

materially different. It is on the contrary necessary to

cull out the principle of law settled in the said case

for application to the case at hand. This may require

recapitulation of a few facts in the backdrop whereof the

decision in the Kerala State Electricity Board's case

(supra) was delivered.

11. MRF was engaged in manufacturing automobile tubes

and tread rubber in the State of Kerala. The company

entered into an agreement with the Kerala State

Electricity Board for supply of power to the factory set

up by it. The agreement contained a provision for payment

of power and energy supplied to the company by the Board

within 15 days from the date of the receipt of the

invoice by the consumer-company. The agreement further

provided that in the event of a default in the payment of

the amount within the stipulated period, interest @ 18%

p.a. or at such other rate as may be fixed by the Board

from time to time would be chargeable.

12. The Board revised the tariff for the electricity

supplied by it in 1980, 1982 and 1984. These revisions

were challenged by MRF in a writ petition filed before

the High Court of Kerala, which was together with other 1

similar petitions disposed of by a common order by which

the revisions made by the Board were struck down.

Consequently MRF Limited and other consumers became

entitled to the refund of the excess amount paid by them

pursuant to the revised tariffs. The High Court of

Kerala directed the adjustment of such amounts towards

future bills to be issued by the Board.

13. Aggrieved by the order passed by the Kerala High

Court the Board filed special leave petitions before this

Court which were entertained by this Court and an interim

order passed, inter alia, directing that pending disposal

of the appeals before this Court, the refund of charges

already collected shall remain stayed. It was further

directed that the future charges would be collected to

the extent of 50% only and the balance adjusted towards

the past charges.

14. The appeals filed by the Board were finally allowed

by this Court by its judgment dated 26th August, 1986

upholding the validity of the revision of the tariffs by

the Board. The inevitable conclusion flowing from that

decision was that the consumer-company and other

consumers became liable to pay the amounts due on the 1

basis of the revision of tariffs including those that had

since been adjusted by them pursuant to the interim

directions of this Court. Consequently, the Board raised

a demand for the payment of the amount inclusive of

interest @ 18% p.a. While the company did not challenge

the liability to pay the excess amount pursuant to the

revision that had been upheld by this Court it refused to

pay the interest and challenged the demand to that extent

before the High Court of Kerala in a writ petition filed

before it. The Single Judge as also the Division Bench

of the High Court in appeal held that the consumer-

company could not be said to be in default for non-

payment of liability which did not factually exist at the

relevant time and struck down the demand for payment of

interest.

15. The Electricity Board appealed to this Court against

the said judgment of the High Court. Allowing the appeals

preferred by the Board this Court took the view that

while the consumers had no obligation to take notice of

the revised tariffs and to make any payment on the basis

thereof after the judgment of the High Court of Kerala

till the said decision was reversed by this Court, yet no

sooner the decision of this Court upheld the upward 1

revision of the tariffs, the Board's entitlement to draw

bills on the basis of the revisions and consequently

enforce payment of such bills by the consumers revived

with full force. This Court repelled the contention that

the liability to pay the revised tariffs accrued only

after the pronouncement of the judgment of this Court

upholding the upward revision and not from any date prior

to that. This Court held that once the upward revision

was found to be valid and enforceable such revision would

be effective from the date the revision was made, no

matter such revision had remained unenforceable for some

period on account of the decision of the High Court. The

following passage from the decision of this Court is in

this regard apposite:

"But after the decision of this Court upholding upward revisions of tariffs, the Board's entitlement to draw bills on the basis of upward revisions and consequential enforceability of payment of such bills by the consumers revived with full force. Hence, it would not be correct to contend that although the Company or for that matter other consumers were required to pay on the basis of revisions of tariffs from the dates when such revisions became effective, liability for such payment would accrue only from the date of pronouncement of the judgment by this Court upholding upward revisions and not from any date prior to that. If the upward revisions are held as valid, enforceability of such upward revisions being consequential to such revisions, though it had remained unenforceable for some period on account of 1

the decision of the High Court, cannot but revive from the dates of upward revisions."

16. This Court then applied the principle of restitution

as enunciated by the Privy Council in Rodger v. Comptoir

D'Escompte de Paris 1871 (3) PC 465 and held that it will

be the endeavour of the Court to ensure that a party who

had suffered on account of a decision that is finally

reversed should be put back in the same position as far

as the same is practicable, in which he would have been

if the decision of the Court adversely affecting him had

not been passed. This Court observed:

"In giving full and complete relief in an action for restitution, the court has not only power but also a duty to order for mesne profits, damages, costs, interest etc. as may deem expedient and fair conforming to justice to be done in the facts of the case. But in giving such relief, the court should not be oblivious of any unmerited hardship to be suffered by the party against whom action by way of restitution is taken. In deciding appropriate action by way of restitution, the court should take a pragmatic view and frame relief in such a manner as may be reasonable, fair and practicable and does not bring about unmerited hardship to either of the parties."

17. Applying the above principle to the case before it

this Court held that the consumer-company was an on-going

business concern who must have gainfully utilized the 1

money saved on account of the decision of the High Court,

in its commercial activities. The Court further held that

the Board had to suffer financial loss because of the

erroneous decision delivered by the High Court and that

conforming to equity as well as well-established

principle of restitution the Board could claim interest @

18% p.a. on the unpaid portion of the bill drawn on the

basis of the revised tariffs to which the consumer-

company had agreed. The Court observed:

"The Company is an ongoing business concern and must have utilised the money, saved on account of the decision of the High Court, gainfully in its commercial activities. Similarly, other consumers have gainfully utilised the amount saved for being not required to pay on the basis of revised tariffs. The Board had to suffer financial loss because of the said erroneous decision of the High Court. In the aforesaid circumstances, it will be lawful, conforming to equity and well-established principle of restitution for the Board to claim interest at 18% on the unpaid portion of the Bill drawn on the basis of revised tariffs. The Company had agreed to pay interest at 18% on the bills if not paid when it became due and payable."

18. It is quite evident that this Court had upheld the

claim for payment of interest @ 18% p.a. primarily

because of the stipulation contained in the

tariffs/agreement executed between the Board and the

consumer providing for payment of interest at that rate 1

in the event of delay in the payment/discharge of the

bills raised against the consumer. It is not as though

this Court had refused to enforce the stipulation

contained in the tariffs providing for recovery of

interest from the consumer if the latter failed to pay

the amounts within the time stipulated. It is also

manifest that this Court had in no uncertain terms held

that even after the upward revisions of the tariffs had

remained unenforceable for a certain period on account of

erroneous judgment of the High Court, the moment the said

judgment was set aside in appeal, the liability to pay

revived with full force from the date the revisions were

made effective. The very fact there was during the

intervening period an erroneous decision of the High

Court obliterating the revision in full or in part would

make little difference in so far as the liability to pay

the amount under the revised tariffs was concerned. So

also the fact that the consumers were not deliberately in

default on account of the judgment of the High Court did

not affect the enforceability of the demand arising from

the revised tariffs or the stipulation regarding payment

of interest demanded on the same on account of the non-

payment or delayed payment of the amount recoverable by

the Board.

1

19. Suffice it so say that the decision of this Court in

the case of Kerala State Electricity Board (supra) does

not grant any relief to a defaulting consumer once the

demand is upheld nor does it interfere with the principle

of restitution which would entitle the successful party

to be relegated back to the position it would hold had

there been no judgment adverse to it.

20. Super added to all this is the fact that this Court

was dealing with a case where the High Court had finally

struck down the revised tariff, but the said decision was

reversed in appeal. In the present case the appellant

had obtained only an ad interim order of stay against the

enforcement of the tariffs. There is a qualitative

difference in the two situations. Even if one were to

take a charitable view of the legal effect of any

direction of the High Court, pending adjudication by the

Court, cases in which the High Court finally held the

tariffs to be bad would in our opinion stand on a

different footing than cases where the party obtains an

order granting interim protection to it. While there is

an element of finality in the case of a final

adjudication by a competent Court in so far as that Court

is concerned, an interim order can be vacated at any 1

stage. The interim order may not even prevent a prudent

party from paying the charges according to the revised

tariffs if it does not propose to take any chance and

suffer recovery of an additional amount on account of the

non-payment of the dues by the date stipulated for the

purpose. We may in this regard refer to the following

observations of this Court in Shree Chamundi Mopeds Ltd.

v. Church of South India Trust Association CSI Cinod

Secretariat, Madras 1992 (3) SCC 1:

"While considering the effect of an interim order staying the operation of the order under challenge, a distinction has to be made between quashing of an order and stay of operation of an order. Quashing of an order results in the restoration of the position as it stood on the date of the passing of the order which has been quashed. The stay of operation of an order does not, however, lead to such a result. It only means that the order which has been stayed would not be operative from the date of the passing of the stay order and it does not mean that the said order has been wiped out from existence."

21. Suffice it to say that the decision of this Court in

Kerala State Electricity Board's case (supra) does not

lend any support to the appellant-company in its

endeavour to avoid payment of the amount which became

recoverable from it no sooner the judgment of the High 1

Court was reversed in the earlier round of litigation

upholding the revision of the tariffs.

22. That brings us to the decision of this Court in

Kanoria Chemicals and Industries Ltd. and Ors. v. U.P.

State Electricity Board and Ors. (1997) 5 SCC 772. That

was also a case where the validity of a notification

issued by the U.P. State Electricity Board revising the

electricity rates/tariffs under Section 49 of the

Electricity (Supply) Act, 1948 was challenged by the

consumers. Interlocutory applications filed in the writ

petitions for stay of the operation of the impugned

notification were eventually dismissed by the High Court

whereupon the consumers deposited the differential amount

between the pre-revised and the revised electricity

rates. Consumers did not, however, deposit the late

payment surcharge "recoverable" in terms of Clause 7(b)

of the notification. Notices of demand were, therefore,

issued to the consumers which were challenged in a fresh

batch of writ petitions filed by them. The main

contention urged by the consumers before the High Court

was that since the operation of the notification revising

the tariffs had been stayed between 25th July, 1990 and

1st March, 1993, no late payment surcharge could be levied 2

on the amount withheld by the petitioners under the

orders of the Court, no matter the writ petitions were

finally dismissed. That contention was rejected by a

Division Bench of the High Court of Allahabad. The

matter was then brought up to this Court in appeal by the

consumers, inter alia, contending that the stay of the

operation of the impugned notification relieved the

consumers of the obligation to pay the revised

tariffs/rates and consequently additional charges for

late payment, if any. Reliance in support of that

submission was placed by the consumers upon the decision

of this Court in Adoni Ginning Factory v. Secy. A.P.

Electricity Board (1979) 4 SCC 560. Speaking for the

Court, Hon'ble B.P. Jeevan Reddy, J. held that the

decision of this Court in Adoni Ginning Factory's case

(supra) had no application to the case at hand nor could

it be understood to mean that during the period covered

by the stay no demand could be made against the consumers

as no such issue has been raised before this Court in

Adoni Ginning Factory's case (supra). This Court

observed:

"..............We, therefore, agree with the High Court that Adoni Ginning1 cannot be read as laying down the proposition that the grant 2

of stay of a notification revising the electricity charges has the effect of relieving the consumers/petitioners of their obligation to pay late payment surcharge/interest on the amount withheld by them even when their writ petitions are dismissed ultimately. Holding otherwise would mean that even though the Electricity Board, who was the respondent in the writ petitions succeeded therein, is yet deprived of the late payment surcharge which is due to it under the tariff rules/regulations. It would be a case where the Board suffers prejudice on account of the orders of the court and for no fault of its. It succeeds in the writ petition and yet loses. The consumer files the writ petition, obtains stay of operation of the notification revising the rates and fails in his attack upon the validity of the notification and yet he is relieved of the obligation to pay the late payment surcharge for the period of stay, which he is liable to pay according to the statutory terms and conditions of supply

-- which terms and conditions indeed form part of the contract of supply entered into by him with the Board. We do not think that any such unfair and inequitable proposition can be sustained in law..........."

23. This Court further clarified that the terms in which

the prayer in the stay application was made by the

consumers did not determine the effect of the order

issued by the Court in the writ petitions raising similar

questions of law. The phraseology used in the prayer for

interim orders could be materially different though in

essence the relief may be similar. On a question of

principle this Court held that the impugned order coming 2

to an end upon dismissal of the substantive proceedings,

it is the duty of the Court to put the parties in the

same position as they would have occupied but for the

interim orders of the Court for otherwise it would give

rise to unjust results. This Court said:

"..............It is equally well settled that an order of stay granted pending disposal of a writ petition/suit or other proceeding, comes to an end with the dismissal of the substantive proceeding and that it is the duty of the court in such a case to put the parties in the same position they would have been but for the interim orders of the court. Any other view would result in the act or order of the court prejudicing a party (Board in this case) for no fault of its and would also mean rewarding a writ petitioner in spite of his failure. We do not think that any such unjust consequence can be countenanced by the courts. As a matter of fact, the contention of the consumers herein, extended logically should mean that even the enhanced rates are also not payable for the period covered by the order of stay because the operation of the very notification revising/enhancing the tariff rates was stayed. Mercifully, no such argument was urged by the appellants. It is ununderstandable how the enhanced rates can be said to be payable but not the late payment surcharge thereon, when both the enhancement and the late payment surcharge are provided by the same notification - the operation of which was stayed..............."

2 24. It is manifest from the above that both on the

question of restitution of the benefit drawn by a party

during legal proceedings that eventually fail as also on

the general principle that a party who fails in the main

proceedings cannot benefit from the interim order issued

during the pendency of such proceedings, this Court

found against the consumers and upheld the demand for

payment of additional charges recoverable on account of

the delay in the payment of the outstanding dues. Far

from lending any assistance to the appellant-company the

decision squarely goes against it and has been correctly

appreciated and applied by the High Court.

25. In the result these appeals fail and are hereby

dismissed but without any orders as to costs.

.................................J. (MARKANDEY KATJU)

.................................J. (T.S. THAKUR) New Delhi November 18, 2010

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free