Miss Lucy
← All judgments

M/S. Mitra Guha Builders (India) Company vs Oil And Natural Gas Corporation Limited

Supreme Court8 November 2019Hrishikesh Roy · A.S. Bopanna · R. Banumathi

Ratio decidendi

The rule this decision rests on

1. Where a contract provides for the decision of a designated official (such as a Superintending Engineer) to be "final" in determining the quantum of liquidated damages or compensation for delay, disputes concerning the levy of such damages constitute an "excepted matter" not arbitrable under the contract's arbitration clause, and the arbitrator lacks jurisdiction to adjudicate upon the correctness or legality of such determination. 2. The finality clause in a contract's provision for compensation determination, read together with the arbitration clause which expressly excludes "matters otherwise provided in the contract," excludes from the arbitrator's purview the question of whether compensation for delay has been correctly levied by the authorized official, even though the contractor may dispute the liability. 3. A distinction exists between disputes concerning the quantification of liquidated damages (which may be arbitrable in the absence of a finality clause) and disputes concerning the levy of damages by a designated official acting under contractual authority with an express finality clause: the latter is non-arbitrable because the contract itself provides the complete adjudicatory mechanism and mechanism to determine liability.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO.5511 OF 2012

M/S. MITRA GUHA BUILDERS (INDIA) COMPANY ...Appellant VERSUS OIL AND NATURAL GAS CORPORATION LIMITED …Respondent

WITH

CIVIL APPEAL NO.5512 OF 2012

JUDGMENT

R. BANUMATHI, J.

These two appeals arise out of the judgment dated

16.02.2009 passed by the High Court of Delhi in FAO(OS) No.6 of

2008 and FAO(OS) No.7 of 2008 in and by which the Division

Bench of the High Court has set aside the order of the learned

Single Judge and also of the learned Arbitrator by holding that the

levy of liquidated damages is an “excepted matter” under Clause 2

read with Clause 25 of the contract and the same is not arbitrable. Signature Not Verified Digitally signed by MADHU BALA

2. Brief facts which led to filing of these appeals are as follows:- Date: 2019.11.08 16:49:28 IST Reason: 1

Appellant-M/s. Mitra Guha Builders (India) Company and the

respondent-Oil and Natural Gas Corporation Limited (ONGC)

entered into a contract on 05.01.1996 bearing

No.DHL/Civil/NOIDA/6/94 for construction of Multi-storeyed

Residential flats 28 Nos. ‘C’ type guest house multipurpose hall

service block underground water tank etc. and other work for

ONGC. The appellant-claimant raised certain claims which were

refuted by the respondent and thus, the claimant invoked the

arbitration Clause 25 of the General Conditions of the contract vide

letter dated 07.09.2001. The appellant-claimant had also entered

into a contract dated 05.01.1996 bearing No.DHL/Civil/NOIDA/5/94

for construction of Multi-storeyed Residential flats 20 Nos. ‘B’ type

for ONGC. The appellant-claimant raised certain claims which were

refuted by the respondent and here again, the claimant invoked the

arbitration Clause 25 of the General Conditions of the contract vide

letter dated 07.09.2001.

3. The designated authority vide its order dated 03.01.2002

appointed Justice P.K. Bahri (Retd.) as the sole Arbitrator to

adjudicate upon the claims of the parties. The learned Arbitrator

vide award dated 01.07.2005 allowed the claim of the claimant and

disallowed the liquidated damages/compensation and rejected the

2 counter claim of respondent-ONGC. Various claims made by the

contractor and the amount awarded by the learned Arbitrator in both

the arbitration cases are as under:-

Arbitral Award in Arbitration Case No.297/2002 dated 01.07.2005

Claim Particulars of claim of the Amount Amount No. Petitioner before the Ld. claimed by the awarded by Ld. Arbitral Tribunal Petitioner Arbitrator

1. Balance payment claimed Rs.21,22,249/- Rs.21,18,975/-

by the Petitioner towards Final Bill

2. Amount allegedly withheld Rs.9,00,000/- Rs.9,00,000/-

by ONGC

3. Escalation claimed by the Rs.27,92,189/- Rs.27,92,189/-

Petitioner as per provisions of the contract

4. Losses and damages Rs.21,60,375/- Claim rejected incurred by the Petitioner in by the Ld. the shape of overheads due Arbitrator to prolongation of contract

5. Loss of turnover suffered by Rs.55,58,428/- Claim rejected the Petitioner due to by the Ld. prolongation of contract Arbitrator

6. Declaration sought by the Rs.30,18,975/- Amount of Petitioner that the penalty [amount that Rs.30,18,975/-

under Clause 2 imposed by was withheld by withheld by ONGC was illegal and ONGC towards ONGC as unwarranted and the liquidated liquidated amount withheld by ONGC damages] damages was to was payable to the be refunded and Petitioner with interest @ adjusted 24% towards payment of Claim No.1 and 2 7. Interest payable on final bill - -

8. Interest payable on withheld - - amount 9. Interest payable on - - escalation amount 10. Interest payable on looses - - and damages 11. Interest pre-suit pendente - 10% interest lite and future interest @ 24% 12. Cost of Arbitration Rs.1,00,000/- Rs.2,00,000/-

Total amount awarded by Ld. Arbitrator Rs.58,11,164/- (Claim 1 + 2 + 3)

3

Arbitral Award in Arbitration Case No.297A/2002 dated 01.07.2005

Claim Particulars of claim of the Amount Amount No. Petitioner before the Ld. claimed by the awarded by Ld. Arbitral Tribunal Petitioner Arbitrator

1. Balance payment claimed Rs.25,91,225/- Rs.24,80,142/-

by the Petitioner towards Final Bill

2. Amount allegedly withheld Rs.12,00,000/- Rs.12,00,000/-

by ONGC

3. Escalation claimed by the Rs.29,56,110/- Rs.29,56,110/-

Petitioner as per provisions of the contract

4. Losses and damages Rs.18,23,613/- Claim rejected incurred by the Petitioner in by the Ld. the shape of overheads due Arbitrator to prolongation of contract

5. Loss of turnover suffered by Rs.46,91,973/- Claim rejected the Petitioner due to by the Ld. prolongation of contract Arbitrator

6. Declaration sought by the Rs.36,80,142/- Amount of Petitioner that the penalty [amount that Rs.36,80,142/-

under Clause 2 imposed by was withheld by withheld by ONGC was illegal and ONGC towards ONGC as unwarranted and the liquidated liquidated amount withheld by ONGC damages] damages was to was payable to the be refunded and Petitioner with interest @ adjusted 24% towards payment of Claim No.1 and 2 7. Interest payable on final bill Rs.9,84,680/- -

8. Interest payable on withheld Rs.6,36,000/- - amount 9. Interest payable on Rs.18,91,910/- - escalation amount 10. Interest payable on looses Rs.40,39,666/- - and damages 11. Interest pre-suit pendente - 10% interest lite and future interest @ 24% 12. Cost of Arbitration Rs.1,00,000/- Rs.2,00,000/-

Total amount awarded by Ld. Arbitrator Rs.66,36,252/- (Claim 1 + 2 + 3)

4

The learned Arbitrator allowed the claim of the claimant and

disallowed the liquidated damages/compensation of Rs.32,79,828/-

in Arbitration Case No.297A of 2002 and Rs.42,08,940/- in

Arbitration Case No.297 of 2002 presuming the same to be a

penalty.

4. Challenging the award, the respondent filed petitions bearing

OMP Nos.358 and 359 of 2005 under Section 34 of the Arbitration

and Conciliation Act, 1996 before the High Court of Delhi and the

same were dismissed by the Single Judge vide order dated

02.11.2007. The learned Single Judge held that the Arbitrator has

found that under the garb of liquidated damages, what was sought

to be imposed was penalty. The learned Single Judge found that

almost 60% of the delay was attributable to the respondent-ONGC

while 273 days - 40% delay was attributable to the appellant. The

learned Single Judge held that when the respondent-ONGC

themselves are responsible for substantive part of the delay, it can

hardly be said that respondent is entitled to recovery of liquidated

damages or penalty. While upholding the award passed by the

Arbitrator, the learned Single Judge in Arbitration Case No.297A of

2002 corrected the award amount as Rs.66,36,252/- from

Rs.69,36,252/- which was on account of clerical mistake.

5

5. The respondent-ONGC filed appeals under Section 37 of the

Arbitration Act, 1996 before the High Court of Delhi. The

respondent contended that the pre-estimated liquidated damages of

Rs.32,79,828/- in Arbitration Case No.297A of 2002 and

Rs.42,08,940/- in Arbitration Case No.297 of 2002 claimed by the

respondent-ONGC in terms of Clause 2 of the contract between the

parties was wrongly disallowed by the Arbitrator presuming the

same to be a penalty.

6. The issue involved before the Division Bench of the High

Court was interpretation of Clause 2 of the contract regarding

liquidated damages/compensation levied by the Superintending

Engineer and the finality attached to it. Before the Division Bench, it

was contended by the respondent-ONGC that the decision of the

Superintending Engineer to levy liquidated damages under Clause

2 being final, the same was an “excepted matter” and not arbitrable.

7. The Division Bench set aside the findings of the award

passed by the learned Arbitrator and the order of the learned Single

Judge by holding that Clause 2 of the agreement provided that the

decision of the Superintending Engineer on the question of levy of

liquidated damages is final and that the same could not have been

agitated in the arbitration proceeding. The Division Bench held that

6 when the parties have consciously provided that the decision of the

Superintending Engineer shall be final only to exclude the issue of

“excepted matter” from the scope of the arbitration, the Arbitrator

ought not to have dealt with the same and passed the award. The

Division Bench has also pointed out that when the respondent-

ONGC first gave notices to the appellant-contractor to rectify the

defects and thereafter, gave a notice to levy liquidated damages on

15.05.2001 followed by the letter dated 25.05.2001 to the appellant-

contractor that the final bill was ready and that the appellant was

required to reconcile the final bill to ensure the settlement of the

account, it cannot in such circumstances be said that the liquidated

damages were imposed as a counter blast to the appellant’s claim.

With those findings, the Division Bench reversed the findings of the

learned Single Judge and set aside the award.

8. Assailing the above judgment of the Division Bench, Mr. Bipin

Prabhat, learned counsel for the appellant contended that the High

Court failed to appreciate that Clause 25 of the contract which

authorises the quantum of reduction as well as the reduction of

rates for substantive works cannot be construed to empower the

Superintending Engineer to determine the issue of levy of liquidated

damages. It was submitted that the High Court failed to appreciate

7 that the dispute relating to levy of compensation for delay provided

under Clause 2 read with Clause 25 of the contract is not an

“excepted matter” and the same has been rightly adjudicated upon

by the learned Arbitrator. The learned counsel further contended

that the Division Bench, in exercising its power under appellate

jurisdiction under Section 37 of the Act, erred in reappreciating the

evidence and in upsetting the findings of the learned Arbitrator and

the learned Single Judge.

9. Per contra, Mr. K.M. Natraj, learned Additional Solicitor

General (ASG) assisted by Mr. Akshay Amritanshu, learned counsel

submitted that the learned Arbitrator wrongly disallowed the

estimated liquidated damages and reasonable compensation of

Rs.32,79,828/- in Arbitration Case No.297A of 2002 and

Rs.42,08,940/- in Arbitration Case No.297 of 2002 presuming the

same to be a penalty. The learned ASG further contended that the

learned Arbitrator travelled beyond the terms of the contract and

disallowed the liquidated damages to the respondent even though it

was an “excepted matter”, not falling within his jurisdiction. It was

submitted that the Division Bench of the High Court has rightly held

that the imposition of liquidated damages by the respondent was

8 not a counter-blast or an afterthought and prayed for dismissal of

the appeals.

10. We have carefully considered the contentions of both sides

and perused the impugned judgment and materials on record. The

following points arise for consideration in these appeals:-

(i) Whether the levy of pre-estimated liquidated damages and reasonable compensation by the Superintending Engineer in terms of Clause 2 of the contract between the parties is “arbitrable”?

(ii) Whether the respondent-ONGC is right in contending that the levy of liquidated damages in terms of Clause 2 of the contract is final and an “excepted matter” not falling within the jurisdiction of the Arbitrator and whether the learned Arbitrator has travelled beyond the terms of the contract?

11. ONGC’s claim of liquidated damages in terms of Clause 2

of the agreement:- The salient features of the contract in

Arbitration Case No.297A/2002 are that the work was to commence

on 22.02.1996 and was stipulated to be completed by 21.08.1997.

But the work was completed only on 24.05.1999. Insofar as

Arbitration Case No.297/2002, the work was to commence on

21.02.1996 and was stipulated to be completed by 21.08.1997. But

the work was completed only on 24.05.1999. In its statement of

9 defence, the respondent-ONGC asserted that there has not been

any significant delay caused by the respondent-ONGC which could

delay the work of the claimant. In its statement of defence, the

respondent-ONGC mentioned that total delay which has occurred

was 640 days out of which claimant is responsible for the delay of

39 weeks (39 × 7 = 273 days) and on this account, the claimant is

liable to pay compensation in terms of Clause 2 of the contract

which stipulate compensation payable @ ½% per week subject to

maximum 10% of the cost of the executed work and the decision of

the Superintending Engineer in this regard is final. The respondent-

ONGC has thus claimed Rs.32,79,828/- in Arbitration Case No.297A

of 2002 and Rs.42,08,940/- in Arbitration Case No.297 of 2002

recoverable from the claimant as compensation for the delay

caused by the claimant in completing the work.

12. After reference to various correspondences between the

respondent-ONGC and the appellant and after a detailed

discussion, the learned Arbitrator recorded a finding of fact that the

respondent-ONGC was responsible to an extent for the prolongation

of the contract and the claimant was also to some extent

responsible which resulted in slow progress of the work.

Considering the delay alleged by the respondent-ONGC, the

10 learned Arbitrator has observed that there was delay of 640 days

and both the respondent-ONGC and the appellant were responsible

for the delay and observed as under:-

“….The date of commencement of the work stipulated in the contract was the 22nd February 1996 and the work was to be completed on the 22nd August 1997. According to the respondent, the actual date of commencement of the work was the 13 th March 1996 and the work was completed on the 24th May 1999. Thus, there took place delay of 640 days. The respondent was responsible for only 160 days of delay whereas the claimant was responsible for delay of 371 days. It is not understood how the respondent has quantified the delay imputed to either of the parties.”

13. By upholding the award of the learned Arbitrator, the learned

Single Judge held that the delay in completion of the work was on

account of both parties and by applying the equitable principles, the

learned Single Judge held that the damages were payable by either

of the parties.

14. The learned Single Judge, in our view, failed to note the

implication of Clause 2 of the contract and also various

correspondences between the parties, while affirming the award

passed by the learned Arbitrator. In terms of Clause 2 of the

agreement dated 05.02.1996 between the parties, the contractor is

to proceed with the work with due diligence throughout the contract

period. In case of delay or failure to ensure good progress during

11 execution of the work, Clause 2 of the agreement provides for

determination/quantification of compensation for delay or certain

inactions, on the part of the contractor. In terms of Clause 2 of the

agreement, the Superintending Engineer shall assess and quantify

the compensation. By the terms of the agreement, the parties have

consciously agreed that in case the contractor fails to comply with

the conditions and complete the work with due diligence, the

Superintending Engineer may decide the compensation in terms of

Clause 2 of the agreement.

15. In order to appreciate the claim of ONGC in levying the

damages in terms of Clause 2, it is necessary to refer to Clause 2 of

the agreement which reads as under:-

“Clause 2: Compensation for Delay

The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be deemed to be the essence of the contract on the part of the contractor and shall be reckoned from the 15th day after the date on which the order to commence the work is issued to the contractor. The work shall throughout the stipulated period of the contract be proceeded with all due diligence and the contractor shall pay compensation on amount equal to ½ % per week as the Superintending Engineer (whose decision in writing shall be final) may decide on the amount of the contract, value of the whole work as shown in the agreement, for every week that the work remains uncommenced, or unfinished, after the proper dates. After further to ensure good progress during the execution of the work, the contractor shall be bound in all cases in which the time allowed for any

12 work exceeds, one month (save the special jobs) to complete one-eighth of the work, before one-fourth of the whole time allowed under the contract has elapsed and three-eights of the work, before one-half of such time has elapsed, and three-fourth of such time has elapsed. However, for special jobs if a time schedule has been submitted by the contractor and the same has been accepted by the Engineer-in-Charge, the Contractor shall comply with the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay as compensation an amount equal to ½ % per week as the Superintending Engineer (whose decision in writing shall be final) may decide on the said contract value if the whole work for every week that the due quantity of works remains incomplete provided always that the entire amount of compensation to be paid under the provisions of the clause shall not exceed ten per cent (10%) of the tendered cost of the work as shown in the tender.” [Emphasis added]

A reading of Clause 2 makes it clear that the Superintending

Engineer has been conferred with not only a right to levy

compensation; but it also provides a mechanism for determination

of the liability/quantum of compensation. The very Clause 2 itself

would show that such a decision taken by the Superintending

Engineer shall be final. The finality clause in the contract in terms of

Clause 2 makes the intention of the parties very clear that there

cannot be any further dispute on the said issue between the parties;

much less before the arbitrator.

16. Clause 25 of the agreement – Settlement of disputes by

Arbitration, reads as under:-

13

“Clause 25 – Settlement of disputes by Arbitration If any dispute, difference, question or disagreement shall, at any time, hereafter arises between the parties hereto or the respective representatives or assigns in connection with or arising out of the contract, or in respect of meaning of specifications, design, drawings, estimates, scheduled, annexures, orders, instructions, the construction, interpretation of this agreement, application of provisions thereof or anything hereunder containing or arising hereunder or as to rights, liabilities or duties of the said parties hereunder or arising hereunder any matter whatsoever incidental to this contract or otherwise concerning the works of execution or failure to execute the same whether during the progress of work or stipulated/extended period or before or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by a Director of ONGC Ltd. at the time of dispute. There will be no objection to any such appointment that the arbitrator so appointed is an employee of ONGC Ltd. or that he had to deal with the matters to which the contract relates and that in the course of this duties as ONGC Ltd. employees, lie had expressed views on all or any of the matters in dispute or difference. If the arbitrator to whom the matter is originally referred dies or refuses to act or resigns for any reason from the position of arbitrator, it shall be lawful for the Director of ONGC Ltd. to appoint another person to act as arbitrator in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor if both the parties consent to this effect, failing which the arbitrator will be entitled to proceed de-novo.

………..

It is also a term of the contract that if the contractor(s) do/does not make any demand for arbitration in respect of any claim(s) in writing within 90 days of receiving the intimation from the corporation that the bill is ready for payment, the claim of the contractor(s) will be deemed to have been waived and absolutely barred and the Corporation shall be discharged and released of all liabilities under the contract in respect of these claims.

14 The decision of the Superintending Engineer regarding the quantum of reduction as well as his justification in respect of reduced rates for sub-standard work, which may be decided to be accepted, will be final and would not be open to arbitration.

………..”. [Emphasis added]

The intention of the parties to exclude some of the decisions of the

Superintending Engineer from the purview of arbitration is clearly

seen from the abovesaid clause. Claim No.6 made by the appellant

is to declare that the penalty imposed by ONGC under Clause 2

was illegal and unwarranted and the amount withheld by ONGC

was payable to the appellant. The very prayer to declare the

amount levied by the Superintending Engineer as illegal is against

the tenor of the terms of the contract (Clause 2) between the

parties. By virtue of the finality clause in the contract, any decision

taken by the Superintending Engineer in levying compensation

cannot be referred to an arbitrator. The parties have consciously

agreed to have finality to the decision of the Superintending

Engineer and the same cannot be frustrated by challenging the

same as illegal. Any other meaning to the finality clause in the

contract and allowing further adjudication by another authority would

make the agreed Clause 2 and Clause 25 of the agreement

meaningless and redundant.

15 17. As held by the Division Bench of the High Court, whether

there was delay in completion of work and the levy of liquated

damages, could not have been determined by the arbitrator. Vide

letters dated 08.12.1999, 09.12.1999, 17.12.1999, 11.02.2000 and

17.04.2000, ONGC called upon the respondent/contractor to

remove the defects failing which it would get the defects remedied

at his cost. According to ONGC, the completion time was extended

without prejudice to the right of ONGC to recover compensation in

accordance with Clause 2 of the agreement. The contention of

ONGC is that by the letter dated 15.05.2001, the contractor was put

on notice that in exercise of the power conferred on the

Superintending Engineer under Clause 2, the contractor is liable to

pay 10% of the contract value by way of compensation. The

contractor was informed by the said letter dated 15.05.2001 that the

compensation is levied on him for the period of 39 weeks at half per

cent per week subject to maximum of 10% of the contract value and

that the actual amount of compensation shall be worked out on

checking the final bill and the same shall be recovered by ONGC

from the final bill. By the subsequent letter dated 25.05.2001, the

claimant was informed that the final bill is ready and the claimant

was required to reconcile the final bill after adjusting the

compensation.

16

18. A reading of the other terms of the contract would further

indicate that under Clauses 13 and 14 of the agreement, the parties

have agreed for payment of compensation and non-payment of

compensation in certain situations. Significantly, Clauses 13 and 14

of the agreement do not have any finality clause which indicates

that any dispute arising out of such clauses may be a dispute

referable to arbitration. However, in respect of levy of compensation

for the delay, Clause 2 of the agreement specifically makes the

decision of the Superintending Engineer, final. The entire contract

between the parties and the terms thereon have to be read as a

whole to decide the rights and liabilities of the parties arising out of

the contract. In claim No.6, the contractor has sought for declaration

“that the penalty under Clause 2 imposed by ONGC was illegal and

unwarranted and the amount withheld by ONGC was payable to the

contractor with interest @ 24%”. Claim No.6 sought for by the

contractor is clearly in violation of Clause 2 of the agreement

between the parties, in and by which, the parties have agreed that

the decision taken by the Superintending Engineer levying

compensation shall be final. The finality clause in the contract

cannot therefore be frustrated by calling upon the arbitrator to

decide on the correctness of levy of compensation by the

Superintending Engineer.

17

19. While considering similar contractual provisions viz. Clause 2

of the agreement as in the present case, in Vishwanath Sood v.

Union of India and Another (1989) 1 SCC 657, the Supreme Court

held as under:-

“8. ……… As we see it, clause 2 contains a complete machinery for determination of the compensation which can be claimed by the Government on the ground of delay on the part of the contractor in completing the contract as per the time schedule agreed to between the parties. The decision of the Superintending Engineer, it seems to us, is in the nature of a considered decision which he has to arrive at after considering the various mitigating circumstances that may be pleaded by the contractor or his plea that he is not liable to pay compensation at all under this clause. In our opinion the question regarding the amount of compensation leviable under clause 2 has to be decided only by the Superintending Engineer and no one else.

9. ……..After referring to certain judicial decisions regarding the meaning of the word “final” in various statutes, the Division Bench concluded that the finality cannot be construed as excluding the jurisdiction of the arbitrator under Clause 25. We are unable to accept this view. Clause 25 which is the arbitration clause starts with an opening phrase excluding certain matters and disputes from arbitration and these are matters or disputes in respect of which provision has been made elsewhere or otherwise in the contract. These words in our opinion can have reference only to provisions such as the one in parenthesis in clause 2 by which certain types of determinations are left to the administrative authorities concerned. If that be not so, the words “except where otherwise provided in the contract” would become meaningless. We are therefore inclined to hold that the opening part of clause 25 clearly excludes matters like those mentioned in clause 2 in respect of which any dispute is left to be decided by a higher official of the Department. Our conclusion, therefore, is that the question of awarding compensation under clause 2 is outside

18 the purview of the arbitrator and that the compensation, determined under clause 2 either by the Engineer-in-charge or on further reference by the Superintending Engineer will not be capable of being called in question before the arbitrator.

10. ……. But we should like to make it clear that our decision regarding non-arbitrability is only on the question of any compensation which the Government might claim in terms of Clause 2 of the contract. We have already pointed out that this is a penalty clause introduced under the contract to ensure that the time schedule is strictly adhered to. It is something which the Engineer-in-charge enforces from time to time when he finds that the contractor is being recalcitrant, in order to ensure speedy and proper observance of the terms of the contract. This is not an undefined power. The amount of compensation is strictly limited to a maximum of 10 per cent and with a wide margin of discretion to the Superintending Engineer, who might not only reduce the percentage but who, we think, can even reduce it to nil, if the circumstances so warrant.

It is this power that is kept outside the scope of arbitration. We would like to clarify that this decision of ours will not have any application to the claims, if any, for loss or damage which it may be open to the Government to lay against the contractor, not in terms of clause 2 but under the general law or under the Contract Act. As we have pointed out at the very outset so far as this case is concerned the claim of the Government has obviously proceeded in terms of clause 2 and that is the way in which both the learned Single Judge as well as the Division Bench have also approached the question. Reading clauses 2 and 25 together we think that the conclusion is irresistible that the amount of compensation chargeable under clause 2 is a matter which has to be adjudicated in accordance with that clause and which cannot be referred to arbitration under clause 25”. [Underlining added]

The ratio of the above decision squarely applies to the present

case. Once the parties have decided that certain matters are to be

19 decided by the Superintending Engineer and his decision would be

final, the same cannot be the subject matter of arbitration.

20. In this regard, reliance was also placed upon Food

Corporation of India v. Sreekanth Transport (1999) 4 SCC 491

wherein, the Supreme Court interpreted Clause 12 of the agreement

thereon. Clause 12 of the agreement in Food Corporation of India

reads as under:-

“The decisions of the Senior Regional Manager regarding such failure of the contractors and their liability for the losses etc. suffered by the Corporation shall be final and binding on the contractors….”.

21. While interpreting the clause on ‘excepted matters’, in Food

Corporation of India, the Supreme Court held as under:-

“3. “Excepted matters” obviously, as the parties agreed, do not require any further adjudication since the agreement itself provides a named adjudicator — concurrence to the same obviously is presumed by reason of the unequivocal acceptance of the terms of the contract by the parties and this is where the courts have been found out lacking in their jurisdiction to entertain an application for reference to arbitration as regards the disputes arising therefrom and it has been the consistent view that in the event of the claims arising within the ambit of excepted matters, the question of assumption of jurisdiction of any arbitrator either with or without the intervention of the court would not arise. The parties themselves have decided to have the same adjudicated by a particular officer in regard to these matters; what these exceptions are however are questions of fact and usually mentioned in the contract documents and form part of the agreement and as such there is no ambiguity in the

20 matter of adjudication of these specialised matters and being termed in the agreement as the excepted matters.

……..

9. ……... The Food Corporation, therefore, as a matter of fact desired an adjudication of their claim to the extent of Rs 1,89,775 together with interest at the rate of 18 per cent per annum from the civil court rather than relying on the adjudicatory process available in the contract itself through their own Senior Regional Manager. The agreement as noticed above expressly provides that the adjudication shall be effected by the Senior Regional Manager and by no other authority and the decision, it has been recorded in the agreement, of the Senior Regional Manager would be final and binding on the parties…..”.

In the present case, the parties themselves have agreed that the

decision of the Superintending Engineer in levying compensation is

final and the same is an “excepted matter” and the determination

shall be only by the Superintending Engineer and the correctness of

his decision cannot be called in question in the arbitration

proceedings and the remedy if any, will arise in the ordinary course

of law.

22. The learned counsel for the appellant has relied upon Bharat

Sanchar Nigam Limited and another v. Motorola India (P) Ltd.

(2009) 2 SCC 337 and by referring to Clause 16(2) in the concerned

agreement submitted that for quantification of liquidated damages,

first of all, there has to be a delay and for ascertaining as to who

was responsible for the delay, such an issue will be within the

21 jurisdiction of the arbitrator. The learned ASG however, submitted

that in the present case, Clause 2 of the agreement is not only a

mechanism for quantification of liquidated damages, but Clause 2

also makes the contractor liable for payment of the same and in

terms of Clause 2 of the agreement, the decision of the

Superintending Engineer is final and the present case is therefore,

distinguishable from BSNL’s case.

23. As rightly contended by the learned ASG, in BSNL’s case,

Clause 16(2) of the agreement does not create any kind of liability

to pay liquidated damages; but only provides for entitlement of

BSNL to collect the damages in case of any delay in supply on the

part of the supplier under Clause 16(2). While interpreting Clause

16(2) and Clause 21 of the contract which was under consideration

in BSNL’s case, in paras (23) and (26), the Supreme Court held as

under:-

“23. The question to be decided in this case is whether the liability of the respondent to pay liquidated damages and the entitlement of the appellants, to collect the same from the respondent is an excepted matter for the purpose of Clause 20.1 of the general conditions of contract. The High Court has pointed out correctly that the authority of the purchaser (BSNL) to quantify the liquidated damages payable by the supplier Motorola arises once it is found that the supplier is liable to pay the damages claimed. The decision contemplated under Clause 16.2 of the agreement is the decision regarding the quantification of the liquidated damages and not any decision regarding the fixing of the

22 liability of the supplier. It is necessary as a condition precedent to find that there has been a delay on the part of the supplier in discharging his obligation for delivery under the agreement.

………..

26. Quantification of liquidated damages may be an excepted matter as argued by the appellants, under Clause 16.2, but for the levy of liquidated damages, there has to be a delay in the first place. In the present case, there is a clear dispute as to the fact that whether there was any delay on the part of the respondent. For this reason, it cannot be accepted that the appointment of the arbitrator by the High Court was unwarranted in this case. Even if the quantification was excepted as argued by the appellants under Clause 16.2, this will only have effect when the dispute as to the delay is ascertained. Clause 16.2 cannot be treated as an excepted matter because of the fact that it does not provide for any adjudicatory process for decision on a question, dispute or difference, which is the condition precedent to lead to the stage of quantification of damages.”

24. In BSNL’s case, Clause 16 provided for entitlement of the

party to recover liquidated damages. In Clause 16(2), the phrases

used “value of delayed quantity” and “for each week of delay”

clearly show that it is necessary to find out whether there has been

delay on the part of the supplier in discharging his obligation. Thus,

in BSNL’s case, in determining whether there is delay or not, a

process of adjudication is envisaged. Per contra, in the present

case, Clause 2 of the agreement is a complete mechanism for

determination of liability. The right to levy damages for delay is

exclusively conferred upon the Superintending Engineer and Clause

23 2 of the present agreement is a complete mechanism for

determination of liability and when such compensation is levied by

the Superintending Engineer, the same is final and binding. The

parties have also consciously agreed that for the delay caused, the

Superintending Engineer shall levy the compensation of the amount

equal to half per cent and the said amount shall not exceed from

10% of the cost of the work and the determination by the

Superintending Engineer is final and cannot be the subject matter of

arbitration. In claim No.6, the prayer sought for by the contractor to

declare the compensation levied by the Superintending Engineer as

illegal is contradictory to the agreed terms between the parties. So

far as the liquidated damages determined and levied, by virtue of

Clause 2, is out of the purview of the arbitration especially in view of

the fact that under the very same clause, the parties have agreed

that the decision of the Superintending Engineer shall be final.

25. Learned Single Judge erred in proceeding under the

presumptive footing that the compensation levied by the

Superintending Engineer was in the nature of penalty. It was

actually levy of liquidated damages/compensation in terms of

Clause 2 of the agreement. Levy of compensation of

Rs.32,79,828/- in Arbitration Case No.297A of 2002 and

24 Rs.42,08,940/- in Arbitration Case No.297 of 2002 in terms of

Clause 2 of the agreement is final and the same could not have

been the subject matter of arbitration. Applying the ratio of

Vishwanath Sood, the Division Bench of the High Court rightly set

aside the order of the learned Arbitrator with regard to claim No.6 by

holding that levy of liquidated damages/compensation is adjustable

against the final bill payable to the appellant. The impugned

judgment does not therefore, suffer from any infirmity warranting

interference.

26. As per the chart filed by the respondent-ONGC, total amount

awarded by learned Arbitrator in favour of the appellant is

Rs.1,24,47,416/- (Rs.66,36,252/- + Rs.58,11,164/-). Total amount

of compensation/liquidated damages withheld by ONGC is

Rs.66,99,117/- (Rs.36,80,142/- + Rs.30,18,975/-). Towards

satisfaction of the arbitral award, ONGC has deposited an amount

of Rs.2,10,41,965/-. As per the order of the Division Bench of the

Delhi High Court, the appellant was directed to refund an amount of

Rs.74,88,768/- (amount withheld by ONGC + accrued interest). In

compliance of the order of the Supreme Court dated 09.04.2009,

the appellant has deposited Rs.75,00,000/- before the Supreme

Court and the same has been invested in a nationalised bank. The

25 amount of Rs.74,88,768/- along with accrued interest is ordered to

be paid to the respondent-ONGC. The balance of Rs.11,232/-

(Rs.75,00,000 – Rs.74,88,768/-) along with accrued interest be

refunded to the appellant.

27. In the result, the appeals are dismissed. No order as to cost.

………………………..J. [R. BANUMATHI]

………………………..J. [A.S. BOPANNA]

….………………………..J. [HRISHIKESH ROY]

New Delhi;

November 08, 2019

26

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free