Miss Lucy
← All judgments

M/S. Madnani Construction Corporation (P) Ltd. vs Union Of India & Others

Supreme Court7 December 2009Asok Kumar Ganguly · Markandey Katju

Ratio decidendi

The rule this decision rests on

Where an arbitration agreement or contract is silent on the grant of interest, or contains a general clause prohibiting claims for interest only against the employer and not against the arbitrator, an arbitrator retains the power to award interest for all periods—pre-reference, pendente lite, and post-award—unless the contract contains an express and unambiguous prohibition specifically restraining the arbitrator from granting interest; a general prohibition on the employer entertaining claims for interest does not divest the arbitrator of jurisdiction to award interest as compensation for deprivation of money legitimately due.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE
IN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.8385 OF 2004
M/s. Madnani Construction Corporation(P) Ltd. ...Appellant(s)
Vs.
Union of India & Others ...Respondent(s)
J U D G M E N T
GANGULY, J.
1. The subject matter of challenge in this appeal is
the judgment and order dated 29.04.2003 passed by
the High Court of judicature at Allahabad in
F.A.F.O. No. 40 of 1993, in a matter arising from
the order dated 1.12.1992 of the learned Senior
Civil Judge, making the Award a Rule of the Court,
and whereby the High Court had partly allowed the
Appeal filed by the respondent.
1

2. The appellant, a private limited company, is

carrying on, inter alia, various construction

works for both the State and Central Government

and their undertakings. The appellant's case is

that an agreement dated 03.11.1981 was entered

between the appellant and the North Eastern

Railway for the construction of bridge island nos.

13 and 14 over the Kosi river. There were certain

special conditions of the contract (hereinafter,

SCC) and they stipulate that the General

Conditions of Contract (hereinafter, GCC) and

standard specifications of the North Eastern

Railways shall form part of the aforesaid

contract. In terms of the contract, the

construction was to be completed by 15.02.1982.

Certain payments were made to the appellant after

completion of the contract but they were received

by them "under protest". Thus, disputes cropped-up

between the parties. The appellant is said to

have served a notice dated 16.11.1983 for the

appointment of an arbitrator to settle the

2 disputes. The General Manager of the respondent-

Railways by an order dated 24.03.1986 rejected the

appellant's prayer for appointment of an

arbitrator on the ground that the disputes were

not arbitrable, as they fell under `expected

matter' in the contract.

3. On or about 18.08.1987, the appellant filed an

application under Section 20 of the Arbitration

Act, 1940 (hereinafter, the Act) before the Court

of Addl. Civil Judge, Gorakhpur for appointment of

an arbitrator which was transferred on 21st

February, 1990, to the Court of Judge of Small

Causes /Additional Civil Judge (hereinafter, the

Court below). The Court below passed an order on

2.3.1990 that `file received, put up on the date

fixed'. Then by an order dated 31.05.1991 the

learned Civil Judge appointed one Mr. B. N.

Shukla, the Sole Arbitrator, to adjudicate the

disputes arising out of the agreement dated

03.11.1981. Against the order of appointment of

arbitrator the responder approached the High Court

3 by filing F.A.F.O. No. 534 of 1991 (the earlier

F.A.F.O.), but the same was dismissed vide order

dated 27.08.1991.

4. The learned Arbitrator gave his award on 13.4.1992

holding that the Railways should pay an amount of

Rs.4,48,873.22 along with compoundable bank

interest prevalent at that time from 16.11.1983 to

21.3.1992. In passing the award the Arbitrator

relied on the Level book No. I, the Graph Sheets,

the Log Book No. IA and the Log Book No. 4. The

Arbitrator found that there were subsequent

alterations and over writing in the entries made

in the Log Book No.IA and the same were without

any initials by the concerned authority on behalf

of the respondent Railways. From such materials

the Arbitrator held that all the

manipulations/alterations/overwritings had

resulted in reducing the quantities of the work

done by the appellant. It was further observed

that clause 21 (iv) of the special conditions was

not followed by the respondent Railways at all.

4 Moreover in utter violation of the Railway rules

and orders on the subject, the measurements were

hardly entered in the measurement book directly

and mostly entries in the measurement books were

copied down from subsidiary records or note books.

After recording such findings, the Arbitrator gave

the aforesaid award.

5. Thereafter on 08.05.1992 the appellant filed an

application under Section 17 of the Act for

pronouncing judgment and making decree according

to the award.

6. On 20.5.1992 the respondent Railways filed

application under Section 30 read with Section 33

(Section 30/33) of the Act before the Civil Judge

for setting aside the award. Then on 24.08.1992

they also filed their objections against the

application filed by the contractor under Section

17 of the Act. The following facts were recorded

in the judgment of the High Court.

5

"The Railways filed an application before the District Judge for transfer of the application filed by the contractor under Section 20 of the Act and under Section 24 of the Civil Procedure Code. It was dismissed on 13th November, 1992. The Railways filed an application on 23rd November, 1992, before the court below for summoning their application and under Section 30/33 of the Act from the Court where it was filed. This was objected to by the Contractor on the same date. However, the Court below summoned it and not only rejected it but also rejected their objections against the application under Section 17 of the Act. The Court below by its order dated 1.12.1992 also pronounced judgment according to the award and decreed interest at the rate given by the Bank from the date of the award till actual payment".

7. On 1st December 1992, the Senior Civil Judge,

Gorakhpur of the Court of Judge, Small Causes

Gorakhpur made the award a Rule of Court and

directed that a decree be prepared accordingly and

directed that from the date of the award to the

date of payment the rate of interest on the Bank

loan is to be paid.

8. Challenging the aforesaid order of the Civil

Judge, the Railways filed an appeal before the

High Court.

6

9. Before the High Court, 7 issues were framed. The

appeal was partly allowed by the High Court and in

doing so the High Court came to the conclusion

that the court below had the jurisdiction to

entertain the application under Section 17 of the

Act.

10. On the application of the Railways under Section

30/33 of the Act, the High Court held that the

case is not required to be remanded as the court

below decided the case correctly on merits.

11. Referring to the decision of the General Manager

dated 24.03.1986 rejecting request for appointment

of Arbitrator on the ground that dispute fell

under excepted matters, the High Court concluded

that there is difference of opinion between the

parties whether the dispute falls under excepted

matters or not and the decision of the General

Manager regarding excepted matters is not final

between the parties. The General Manager by

7 wrongly deciding this question could not exclude

the jurisdiction of the Court.

12. On the issue as to whether the respondent Railways

are entitled to raise objections regarding the

excepted matters at the stage of Section 20, the

High Court concluded that the trial Court did not

say a word about it and the High Court merely

affirmed the order passed by the trial court. As

such the issue was left to be decided by the

Arbitrator who has held that none of the claims of

the contractor were excepted matters. It was held

that as the question was not decided in the

earlier litigation, it cannot be said that the

Railways are precluded from raising this question

in these proceedings.

13. On the issue of excepted matters the High Court

held that Item Nos. 1 to 3 and 5 to 8 were

excepted matters and were non-arbitrable and the

Arbitrator committed an illegality in allowing

them. For the remaining items viz. item No. 9 (a)&

8

(d) relating to supply of boats, 11 (b) relating

to cost of wastage of labour, it was held that

these were not covered by Clause 22 (5) or 45 (a)

of the GCC, as such they do not fall in the

category of non-arbitrable matters and are

arbitrable.

14. On the award of interest it was contended that

clause 16 (1) read with 16 (2) of GCC prohibits

payment of interest on amounts payable to the

appellant under the contract except the Government

securities mentioned therein. In this regard, the

High Court considered Clause 30 of SCC and Clause

52 of GCC and found them to be similar and these

clauses, according to High Court, bar interest and

damages in respect of withholding or retention

under the lien. Further by placing reliance on the

case of Executive Engineer, D.M.I. Division v. N.

C. Budhraj, AIR 2001 SC 628 High Court held that

interest could not be awarded since there was

specific prohibition in the contract regarding

awarding of interest.

9

15. On the award of interest High Court's specific

conclusions are:

"(f) The contract prohibited payment of interest. Item 10 is award for interest;

it could not be awarded. Similarly no interest could be awarded under clause 3 of the Award.

(g) There is no illegality in awarding interest payable at the bank rate, but it could only be awarded from the date of decree and not from the date of award."

16. Appellant also filed a review petition before the

High Court but the same was dismissed vide order

dated 15.05.2003.

17. This Court finds that the High Court's conclusion

that Item Nos. 1 to 3 and 5 to 8 of the award are

`excepted matters' and non-arbitrable is not

correct for the reasons discussed below.

18. In coming to the aforesaid finding, the High Court

relied on Clause 45 (a) of GCC. Clause 45(a) of

the GCC is set out below:

10

"45(a): It shall be open to the Contractor to take specific objection to any recorded measurement or classification on any ground within seven days of the date of such measurements. Any re-measurements taken by the Engineer or the Engineer's Representative in the presence of the Contractor or in his absence after due notice has been given to him in consequence of objection made by the Contractor shall be final and binding on the Contractor and no claim whatsoever shall thereafter be entertained regarding the accuracy and classification of the measurements."

19. A plain reading of Clause 45(a) of the GCC makes

it clear that re-measurement are to be made by the

Engineer or the Engineer's representative in the

presence of the Contractor. It may be done in the

absence of the contractor but that has to be done

only after due notice. On a proper construction

of Clause 45(a) it appears that it gives the

contractor, (a) an opportunity to take a specific

objection to any recorded measurement within seven

days of such measurements; (b) Then any re-

measurements is to be taken by the Engineer or the

Engineer's representative in the presence of the

contractor or in his absence after due notice; if

11 the steps under (a) and (b) are strictly followed,

(c) no claim whatsoever by the contractor shall be

entertained about the classification or the

accuracy of the measurement.

20. Under Clause 62 of the GCC it is provided that

matters for which provisions have been made in

Clause 45(a) shall be excepted matters.

21. The arbitrator in his award after perusal of the

level Book No.1, Graph-Sheets, Logbook No. 1A and

Logbook No.4 came to a clear finding that there

were manipulations/alterations/over writings by

the railways and as a result of which the volume

of work done by the contactor has been reduced.

22. It is well settled that the arbitrator is the

master of facts. When the arbitrator on the basis

of record and materials which are placed before

him by the railways came to such specific findings

and which have not been stigmatized as perverse by

the High Court, the High Court in reaching its

conclusions cannot ignore those findings.

12

23. But it appears that in the instant case, the High

Court has come to the aforesaid finding that the

items mentioned above are excepted matters and

non-arbitrable by completely ignoring the factual

finding by the arbitrator and without holding that

those findings are perverse.

24. It goes without saying that in order to deny the

claims of the contractor as covered under excepted

matters, the procedure prescribed for bringing

those claims under excepted matters must be

scrupulously followed. The clear finding of the

arbitrator is that it has not been followed and

the High Court has not expressed any dis-agreement

on that. Therefore, the finding of the High Court

that those items are non-arbitrable cannot be

sustained.

25. On the question of grant of interest by the

arbitrator, the High Court held that Clause 16(2)

13 of the GCC contains a provision against grant of

interest. Clause 16(2)of the GCC is set out below:

"16(2): No interest will be payable upon the earnest money or the security deposit or amounts payable to the contractor under the contract but government securities deposited in terms of such clause (1) of this clause will be repayable with interest accrued thereto."

26. The High Court has also relied on Clause 30 of the

SCC and Clause 52 of the GCC to hold that payment

of interest has been barred. The relevant portion

of Clause 30 of the SCC relating to interest is

set out below:

"...That the contractor will have no claim for interest and damage whatsoever on any account in respect of such with-holding or retention under the lien referred to supra and duly notified as such to the Contractor."

27. The High Court has held that Clause 30 of the SCC

is similar to Clause 52 of the GCC.

28. Before discussing the implication of these

clauses, it may be noted that the Arbitration Act,

14 1940 does not contain any provision enabling the

arbitrator to give interest.

29. Section 29 of the Arbitration Act enables the

Court to award interest from the date of the

decree and at such rate as the Court deems

reasonable.

30. The present Act of 1996 (the Arbitration and

Conciliation Act, 1996), however, empowers the

Arbitrator under Section 31(7)(a) and (b) to grant

interest. Admittedly, in this case the 1996 Act is

not attracted. Therefore, the provisions of 1940

Act will govern. The arbitrator's power to grant

interest is governed by the various judicial

pronouncements and the provisions of Interest Act

of 1978.

31. It goes without saying that in the instant case,

the provision of the Interest Act, 1978 is

attracted. Under the Interest Act, 1978, Section

15 2(a) defines "Court" to include both a tribunal

and an arbitrator.

32. Under the Interest Act, Section 3 empowers the

Court to allow interest. But sub-Section (3) of

Section 3 contains a proviso, namely, Section 3,

sub-Section (3), Clause (a) (ii), to the following

effect:-

"3. (3) Nothing in this section, -

(a) shall apply in relation to -

(i) xxx xxx

(ii) any debt or damages upon which payment of interest is barred, by virtue of an express agreement'"

33. In the context of the aforesaid provision in the

Interest Act, the Clauses in the agreement quoted

hereinabove assume importance.

34. Normally there are three periods for which

interests are awarded - (a) pre-reference period

i.e. from the date of the cause of action for

going to arbitration and to the date of reference; 16

(b) the pendente lite period i.e. from the date of

reference to the date of award; and (c) the post-

reference period i.e. from the date of the award

to the date of realization.

35. Initially there was a judgment of this Court in

the case of Executive Engineer (Irrigation),

Balimela and Others Vs. Abhaduta Jena and Others

[1988 (1) SCC 418] which held, the arbitrator has

no power to award interests in the absence of

contract or any substantive law.

36. Construing the provision of the 1940 Act, the

Court held:-

"..in cases arising after the commencement of Interest Act of 1978 an arbitrator has the same power as the court to award interest up to the date of institution of the proceedings, in cases which arose prior to the commencement of the 1978 Act the arbitrator has no such power under the Interest Act of 1839." (Para 4)

37. The decision in Abhaduta Jena (supra), however,

was overruled by the Constitution Bench of this

Court in Secretary, Irrigation Department,

17 Government of Orissa and Others Vs. G.C. Roy,

[1992 (1) SCC 508].

38. The Constitution Bench in G.C. Roy (supra)

discussed several aspects of the Act of 1940 and

also the provisions of Section 34 of the Civil

Procedure Code and also those of the Interest Act.

After discussing those provisions, the

Constitution Bench formulated the question which

arose in that case as follows:-

"......In the context of these provisions the question arises whether an arbitrator to whom reference is made by the parties has jurisdiction or authority to award interest pendente lite. If the arbitration agreement or the contract itself provides for award of interest on the amount found due from one party to the other, no question regarding the absence of arbitrator's jurisdiction to award the interest could arise as in that case the arbitrator has power to award interest pendente lite as well. Similarly, where the agreement expressly provides that no interest pendente lite shall be payable on the amount due, the arbitrator has no power to award pendente lite interest. But where the agreement does not provide either for grant or denial of interest on the amount found due, the question arises whether in such an event the arbitrator has power and authority to grant pendente lite interest.

18 39. After formulating the above question and

discussing various decisions and legal issues, the

Constitution Bench in paragraph 43 at page 532

further held:

"The question still remains whether arbitrator has the power to award interest pendente lite, and if so on what principle. We must reiterate that we are dealing with the situation where the agreement does not provide for grant of such interest nor does it prohibit such grant. In other words, we are dealing with a case where the agreement is silent as to award of interest...."

40. After posing the question as above, the

Constitution Bench laid down the following

principles in paragraph 43 at page 532 to 533:

"(i) A person deprived of the use of money to which he is legitimately entitled has a right to be compensated for the deprivation, call it by any name. It may be called interest, compensation or damages. This basic consideration is as valid for the period the dispute is pending before the arbitrator as it is for the period prior to the arbitrator entering upon the reference. This is the principle of Section 34, Civil Procedure Code and there is no reason or principle to hold otherwise in the case of arbitrator.

(ii) An arbitrator is an alternative form (sic forum) for resolution of disputes arising between the parties. If so, he 19 must have the power to decide all the disputes or differences arising between the parties. If the arbitrator has no power to award interest pendente lite, the party claiming it would have to approach the court for that purpose, even though he may have obtained satisfaction in respect of other claims from the arbitrator. This would lead to multiplicity of proceedings.

(iii) An arbitrator is the creature of an agreement. It is open to the parties to confer upon him such powers and prescribe such procedure for him to follow, as they think fit, so long as they are not opposed to law. (The proviso to Section 41 and Section 3 of Arbitration Act illustrate this point). All the same, the agreement must be in conformity with law. The arbitrator must also act and make his award in accordance with the general law of the land and the agreement.

(iv) Over the years, the English and Indian courts have acted on the assumption that where the agreement does not prohibit and a party to the reference makes a claim for interest, the arbitrator must have the power to award interest pendente lite.

Thawardas has not been followed in the later decisions of this Court. It has been explained and distinguished on the basis that in that case there was no claim for interest but only a claim for unliquidated damages. It has been said repeatedly that observations in the said judgment were not intended to lay down any such absolute or universal rule as they appear to, on first impression. Until Jena case almost all the courts in the country had upheld the power of the arbitrator to award interest pendente lite. Continuity and certainty is a highly desirable feature of law.

(v) Interest pendente lite is not a matter of substantive law, like interest for the period anterior to reference (pre- reference period). For doing complete

20 justice between the parties, such power has always been inferred."

41. Ultimately in paragraphs 44 and 45 at page 533 to

534 of the report the Constitution Bench held as

follows:

"Where the agreement between the parties does not prohibit grant of interest and where a party claims interest and that dispute (along with the claim for principal amount or independently) is referred to the arbitrator, he shall have the power to award interest pendente lite. This is for the reason that in such a case it must be presumed that interest was an implied term of the agreement between the parties and therefore when the parties refer all their disputes -- or refer the dispute as to interest as such -- to the arbitrator, he shall have the power to award interest. This does not mean that in every case the arbitrator should necessarily award interest pendente lite. It is a matter within his discretion to be exercised in the light of all the facts and circumstances of the case, keeping the ends of justice in view.

45. For the reasons aforesaid we must hold that the decision in Jena, insofar as it runs counter to the above proposition, did not lay down correct law."

42. Following the Constitution Bench ratio in G.C. Roy

(supra), another three-Judge Bench in the case of

Hindustan Construction Company Limited vs. State

21 of Jammu and Kashmir - (1992) 4 SCC 217, while

referring to the ratio in G.C. Roy (supra), held

in paragraph 5 at page 220:

"......Though the said decision deals with the power of the arbitrator to award interest pendente lite, the principle of the decision makes it clear that the arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or date of realisation, whichever is earlier. This is also quite logical for, while award of interest for the period prior to an arbitrator entering upon the reference is a matter of substantive law, the grant of interest for the post-award period is a matter of procedure. Section 34 of Code of Civil Procedure provides both for awarding of interest pendente lite as well as for the post-decree period and the principle of Section 34 has been held applicable to proceedings before the arbitrator, though the section as such may not apply......."

43. Subsequently, in the case of State of Orissa v.

B.N. Agarwalla - (1997) 2 SCC 469, before another

three-Judge Bench a similar question came up for

consideration and this Bench following the ratio

in G.C. Roy (supra) and Hindustan Construction

(supra) considered the question of payment of

interest. After discussing the ratio in Abhaduta

Jena (supra) and G.C. Roy (supra) and various

other cases, the learned Judges in paragraph 18 at 22 page 477 of the report came to the conclusion

that; (a) it is well settled that the arbitrator

has a jurisdiction to award pre-reference interest

in cases which arose after the Interest Act, 1978

had become applicable. It is no doubt that in this

case arbitration proceedings were initiated after

the 1978 Act became applicable; (b) for the period

in which the arbitration proceedings are pending

the arbitrator has the power to award interest;

(c) the Court also held that the power of the

arbitrator to award interest for the post-award

period also exists.

44. In G.C. Roy (supra) this Court made it clear that

the arbitration clause was silent on the payment

of interest but in B.N. Agarwalla (supra) the

Court considered Clause (4) which had the

following stipulation on interest:

"......No interest is payable on amounts withheld under the item of the agreement....... "

23 45. Considering the said Clause (4), the learned

Judges held that the claim which was made before

the arbitrator was for non-payment of the full

amount as per the final bill submitted by the

claimant and the arbitrator awarded interest on

that. The interest so awarded, according to the

learned Judges, is not prohibited under Clause (4)

of the Contract. Therefore, the three Judge Bench

clearly held that just a stipulation in the

contract purporting to indicate non-payment of

interest cannot denude the arbitrator of his right

to pay interest.

46. In a subsequent decision of three-Judge Bench in

the case of State of U.P. v. Harish Chandra and

Company - (1999) 1 SCC 63, there was stipulation

in the arbitration agreement against grant of

interest. The relevant clause namely Clause 1.9

to the aforesaid effect is set out below:

"1.9 No claim for delayed payment due to dispute etc.--No claim for interest or damages will be entertained by the Government with respect to any moneys or balances which may be lying with the Government owing to any dispute, 24 difference; or misunderstanding between the Engineer-in-Charge in marking periodical or final payments or in any other respect whatsoever."

47. Considering the said clause, the Court held that

the prohibition in the said clause does not

prevent the contractor from raising the claim of

interest by way of damages before the arbitrator

on the relevant items placed for adjudication.

(see paragraph 10 page 67). In saying so, the

learned Judges relied on the ratio in the case of

B.N. Agarwalla (supra) and G.C. Roy (supra).

48. In Board of Trustees for the Port of Calcutta v.

Engineers-De-Space-Age, (1996) 1 SCC 516, a two-

judge Bench of this Court considered the same

question. That was a case under the 1940 Act. In

Engineers (supra), the so-called prohibition in

the contract relating to payment of interest was

in Clause 13(g), which is set out below:-

"13(g) No claim for interest will be entertained by the Commissioners with respect to any money or balance which may be in their hands owing to any dispute between themselves and the Contractor or with respect to any delay

25 on the part of the Commissioners in making interim or final payment or otherwise."

49. Relying on the said clause, the appellant in

Engineers (supra) argued that there was absolute

prohibition against payment of interest. The

learned Judges however, relying on the ratio in

G.C. Roy (supra) held that Clause 13(g) merely

prohibits the Commissioner from entertaining any

claim for interest but it does not prohibit the

arbitrator from awarding interest. The learned

Judges held that such clauses must be strictly

construed in view of the ratio of the Constitution

Bench in G.C. Roy (supra). The reasoning given by

the learned Judges in favour of strict

construction runs as follows:-

"...Clause has to be strictly construed for the simple reason that as pointed out by the Constitution Bench, ordinarily, a person who has a legitimate claim is entitled to payment within a reasonable time and if the payment has been delayed beyond reasonable time he can legitimately claim to be compensated for that delay whatever nomenclature one may give to his claim in that behalf. If that be so, we would be justified in placing a strict construction on the term of the contract on which reliance has been placed. Strictly construed the term of the contract merely prohibits the Commissioner from paying interest to the contractor for delayed payment but once the matter goes to 26 arbitration the discretion of the arbitrator is not, in any manner, stifled by this term of the contract and the arbitrator would be entitled to consider the question of grant of interest pendente lite and award interest if he finds the claim to be justified." (Para 4, page 520)

50. It was argued before us by the learned counsel

for the respondent that a subsequent Division

Bench of this Court in the case of Union of India

v. Saraswat Trading Agency & others, JT 2009 (9)

SC 648, has taken a view different from the ratio

in Engineers (supra). We do not think so.

51. In Saraswat Trading (supra) the Clause which was

construed by the Court as clamping a prohibition

on the grant of interest was Clause 31 and which

is quoted in paragraph 15 of the judgment at page

656 of the report and runs as follows:-

"31. No interest or damage for delay in payment

- No interest or damage shall be paid to the Contractor for delay in payment of the bill or any other amount due to the contractor for any reason whatsoever. The Railway Administration will, however, make every endeavour for payment of the bills or other amount due to the contractor within a reasonable time."

27 52. The learned Judges in Saraswat Trading (supra) in

paragraph 16 held that Clause 31 is different from

Clause 13(g) which was considered in Engineers

(supra). The ratio in Engineers (supra) was not

questioned.

53. In the instant case also the relevant clauses,

which have been quoted above, namely, Clause 16(2)

of GCC and Clause 30 of the SCC do not contain any

prohibition on the arbitrator to grant interest.

Therefore, the High Court was not right in

interfering with the arbitrator's award on the

matter of interest on the basis of the aforesaid

clauses. We therefore, on a strict construction

of those clauses and relying on the ratio in

Engineers (supra), find that the said clauses do

not impose any bar on the arbitrator in granting

interest.

54. Reference in this connection may be made to

another Constitution Bench judgment of this Court

in the case of Executive Engineer, Dhenkanal Minor

28 Irrigation Division, Orissa and others v. N.C.

Budharaj (deceased) by Lrs. and others, (2001) 2

SCC 721.

55. In N.C. Budharaj (supra), Justice Raju, speaking

for the majority, considered the question of the

arbitrator's jurisdiction and authority to grant

interest in great detail and also considered both

Indian and English cases and the ratio of the

Constitution Bench of this Court in G.C. Roy

(supra).

56. In paragraph 25 of the judgment the learned Judge

summed up the position as follows:-

"...By agreeing to settle all the disputes and claims arising out of or relating to the contract between the parties through arbitration instead of having recourse to civil court to vindicate their rights the party concerned cannot be considered to have frittered away and given up any claim which otherwise it could have successfully asserted before courts and obtained relief. By agreeing to have settlement of disputes through arbitration, the party concerned must be understood to have only opted for a different forum of adjudication with less cumbersome procedure, delay and expense and not to abandon all or any of its substantive rights under the various laws in force, according to which only even the arbitrator is obliged to adjudicate the claims referred to him. As long as there is

29 nothing in the arbitration agreement to exclude the jurisdiction of the arbitrator to entertain a claim for interest on the amounts due under the contract, or any prohibition to claim interest on the amounts due and become payable under the contract, the jurisdiction of the arbitrator to consider and award interest in respect of all periods subject only to Section 29 of the Arbitration Act, 1940 and that too the powers of the court thereunder, has to be upheld."

(Emphasis supplied)

57. We are constrained to note that Hon'ble High Court

unfortunately erred in appreciating the ratio of

N.C. Budharaj (supra) in passing the impugned

judgment and order.

58. In view of such consistent views taken by both the

Constitution Bench judgments, in G.C. Roy (supra)

and N.C. Budharaj (supra), we are of the view that

in the facts of this case, no interference is

called for with the award passed by the

arbitrator. The judgment of the High Court is,

therefore, set aside and the award is upheld. The

appeal is allowed.

59. There will be no order as to costs.

30 .......................J. (MARKANDEY KATJU)

.......................J. New Delhi (ASOK KUMAR GANGULY) December 07, 2009

31

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free