M/S. M.B. Patel & Co vs Oil & Natural Gas Commission
- SCC(2008) 8 SCC 251
- Neutral2008 INSC 618
- SCR[2008] 8 SCR 35
Ratio decidendi
The rule this decision rests on
An arbitrator's award is unintelligible and liable to be set aside where it consists of a lump sum figure that does not indicate how the arbitrator has dealt with, evaluated, or rejected the separate and distinct claims placed before him. An arbitrator commits an error on the face of the record and acts in breach of the arbitration agreement where he awards interest in contravention of an express contractual clause prohibiting such interest, and where he fails altogether to consider the material terms of the agreement governing the parties' rights and obligations, such as a clause limiting compensation claims to extensions of time only and expressly excluding claims for compensation.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
REPORTABLE IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.7340 OF 2002
M/S. M.B. PATEL & CO. ... APPELLANT
VERSUS
OIL & NATURAL GAS COMMISSION ... RESPONDENT
ORDER
This appeal is filed against the judgment and order dated 11.07.2000 of
the High Court of Gujarat at Ahmedabad in First Appeal No.418 of 1986 whereby
the High Court set aside the award dated 03.05.1985 passed by the Arbitrator. The
High Court set aside the aforesaid award on the following reasonings :
(a) that an arbitrator or umpire has misconducted himself in the
proceedings;
(b) that there appears to be an error on the face of the record
inasmuch as the Umpire has overlooked clauses 14 & 18 of the Arbitration
Agreement;
(c) that the Umpire has traveled beyond the scope of the contract
between the parties on certain items and claims and
(d) that he has rendered lump sum award making it totally
unintelligible.
2
On the aforesaid premises the award was set aside.
In the present case the contractor claimed Rs.30,425/- for abandonment
of contract. This was the first claim. The second claim was for Rs.30,213/- for illegal
deductions made by ONGC. The third claim was for Rs.2,00,000/- for not supplying
the material in time by the ONGC. The fourth claim was loss occasioned by the
contractor for keeping his establishment alive and on this head the claim was for
Rs.3,50,000/-. The fifth claim was loss of profit at the rate of 20 percent amounting
Rs.1,80,000/-. Last claim was interest at the rate of 18% p.a.
As already pointed out that the Arbitrator awarded Rs.5,98,438/- as
lump sum, we agree with the reasoning of the High Court that the award is
unintelligible.
Clause 14 of the Arbitration Agreement reads as under :
"DELAY IN CONSTRUCTION (COMMISSION'S DEFAULTS);
The Commission will make every reasonable affect to furnish the materials under the contract and the right of user including the permits required to be furnished by the Commission under the contract in due time so as not to delay the construction related work of reconditioning. In case of any hold up to site work of the CONTRACTOR on account of non-availability of any one of these terms, no compensation by way of claims is admissible but only corresponding extension of time limit would be granted."
Under the aforesaid clause no claim for compensation is admissible
even that foul of the Commission. Clause 18 of the Arbitration Agreement reads : 3
"INTEREST ON AMOUNTS
No interest will be payable on the security deposit or any other amount payable to the CONTRACTOR under the contract."
The Arbitrator has awarded the interest at the rate of 12% on the
amount with effect from 09.02.1984 to 03.05.1985 (pendente lite). He has also
awarded interest from the date at the rate of 12% on the amount as shown in 1 & 3
above till the date of decree or actual date of payment, whichever is earlier.
In view of the aforesaid premises, the Arbitrator has not at all
considered clause 14 of the Arbitration Agreement. The interest has been awarded
in violation of clause 14 of the Agreement. Apart from others these two legal aspects
have not been considered by the Arbitrator. We are, therefore, in full agreement with
the reasoning given by the High Court. The Arbitrator may now proceed with the
arbitration but in the light of the judgment of the High Court. We direct the
Arbitrator to consider the matter afresh in the light of the reasoning of the High
Court.
Subject to the aforesaid, the appeal is dismissed.
............................J. ( H.K. SEMA )
............................J. ( MARKANDEY KATJU ) NEW DELHI, MAY 08, 2008.
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free