Miss Lucy
← All judgments

M/S Lanco Hills Technology Park Pvt Ltd. vs Manisha Balkrishna Kulkarni

Supreme Court17 December 2019D.Y. Chandrachud · Hrishikesh Roy

Ratio decidendi

The rule this decision rests on

1. Where an agreement to sell contains a force majeure clause extending the time for possession during the subsistence of a prohibitory court order, and such an order prevents performance of the obligation to deliver possession, the period of delay caused by the force majeure event does not constitute a breach for which contractual compensation is due; the obligation to compensate arises only after the force majeure period ends. 2. The contractual stipulation in an agreement fixing the rate of compensation for delay in possession (here, Rs 5 per sq ft for a maximum of six months) applies only for the period expressly covered by that stipulation; for delays beyond that contractual period, the court may award reasonable compensation at a rate different from the contractual rate where the contract makes no specific provision for such extended delay. 3. The stipulation in a sale deed that possession has been handed over is not conclusive of the actual date of delivery of possession; the court will look to contemporaneous documentary evidence (such as the Keys Hand Over Form) to determine when physical possession was actually delivered to the purchaser, notwithstanding what the sale deed records. 4. Where a purchaser has paid the full consideration for a property and the developer retains possession beyond the contractually stipulated period and any agreed grace period or force majeure extension, the developer is liable to pay reasonable compensation to the purchaser for the period of unlawful retention, and a rate of interest or compensation of 18% per annum may be reduced to a more reasonable rate as a court deems appropriate.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

Civil Appeal No 155 of 2015

M/s Lanco Hills Technology Park Pvt Ltd .... Appellant(s)

Versus

Manisha Balkrishna Kulkarni & Anr ....Respondent(s)

JUDGMENT

Dr Dhananjaya Y Chandrachud, J

1 Admit.

2 This appeal arises from a judgment of the National Consumer

Disputes Redressal Commission1 dated 9 October 2014 in Consumer

Complaint No 112 of 2014.

3 An agreement to sell was executed between the appellant and the

respondents on 21 March 2011 under which the respondents agreed to

purchase an apartment in a complex which was developed by the Signature Not Verified appellant in Hyderabad. The total consideration was Rs 1,55,50,826. Digitally signed by SANJAY KUMAR Date: 2019.12.18

Subsequently, an amount of Rs 6,00,000 was paid towards an additional 20:10:57 IST Reason:

parking space. Under Clause 5.1(iii) of the agreement, possession of the 1 NCDRC 2

apartment was to be handed over to the respondents by 28 March 2011,

with a grace period of three months. Clause 8 of the agreement

contemplated that the period of possession would be extended during the

operation of a force majeure event. The appellant received a no-objection

certificate from the State Disaster Response and Fire Services Department

on 4 July 2011. The final occupancy certificate for the residential tower in

which the apartment was situated was issued by the Andhra Pradesh

Industrial Infrastructure Corporation Limited on 22 August 2011.

4 Though the agreement contemplated that possession would be

handed over on 28 March 2011 with a grace period of three months, it

appears that on 28 March 2011 a restraining order was issued by the State

Waqf Tribunal as a result of a dispute in relation to a part of the land on

which the project was being developed. The order of the Waqf Tribunal

was upheld by the High Court on 3 April 2012. However, on 8 May 2012,

the order of injunction was vacated by this Court. On 15 October 2012, the

appellant informed the respondents that the apartment would be ready for

occupation on 3 November 2012 and followed this up with communications

dated 5 November 2012, 20 December 2012 and 7 February 2013. By the

communication dated 20 December 2012, the appellant recorded that all

the deficiencies which had been noticed by the respondents had been

cleared. Eventually, a sale deed was executed on 11 February 2013 and

the sale transaction was completed and registered. The total

consideration inclusive of the cost of the parking space was Rs

1,61,50,826. The respondents had paid 85% of the total agreed

consideration under the agreement to sell while the balance was paid, 3

together with the execution of the sale deed.

5 The dispute between the parties relates to the claim of the

respondents that despite the execution of the sale deed, possession was

not handed over. The respondents moved a consumer complaint before

the NCDRC seeking a direction for the handing over of physical

possession, together with interest and damages for delayed delivery.

6 During the pendency of the proceedings, possession of the apartment

was handed over to the respondents on 28 August 2014. A document

which is styled as “the Keys Hand Over Form” records that all three sets of

keys were handed over to the representative of the respondents.

7 The NCDRC disposed of the consumer complaint by its judgment and

order dated 8 October 2014. The NCDRC directed the appellant to pay

compensation at the rate of Rs 5 per sq ft for the delay of six months, at

the agreed contractual rate. There is a direction to pay compensation at

the rate of 18% per annum for the delay beyond six months for which no

specific provision was contained in the agreement between the parties.

8 Learned counsel appearing on behalf of the appellant placed reliance

on the provisions contained in the sale deed which was executed on 11

February 2013. Clause 3 of the sale deed contains a stipulation of

possession being handed over in the following terms: 4

“3. Possession

Simultaneously, upon the execution of this Sale Deed and the full receipt of the total consideration, the Vendor has and the Purchasers acknowledge that the Vendor has handed over the physical, vacant, lawful and peaceful possession of the Scheduled Property.”

Hence, it has been submitted that upon handing over of possession, the

appellant was not liable to pay compensation to the respondents.

9 On the other hand, it has been submitted on behalf of the

respondents that despite the above stipulation in the sale deed, the fact of

the matter is that there were numerous deficiencies in the apartment which

was agreed to be sold even at the stage when the sale deed was

executed. Hence, it has been submitted that it was only on 28 August

2014 that possession was handed over, as is evidenced by the document

which was executed between the parties.

10 The agreement to sell contained a stipulation in Clause 5.1(iii) to the

effect that the appellant would hand over the possession of the apartment

by 28 March 2011 and, in any event, within a grace period of three months

thereafter. The grace period expired on 28 June 2011. The agreement

contained a stipulation to the effect that:

“In the event of occurrence of a Force Majeure Event in terms of Clause 8 of this Agreement, the period of possession will be automatically extended for such period that the Force Majeure Event subsists. In the event of any delay beyond the time stated above the Developer shall pay the Purchaser an amount of Rs.5 (Rupees Five Only) per square foot of the Super built up area of the Residential Unit for every month of delay up to a maximum of 6 months”.

5

11 The record indicates that between 28 March 2011, when the

restraining order was passed by the Waqf Tribunal, and 8 May 2012, when

the injunction was vacated by this Court, the appellant was prohibited from

handing over of possession or alienating any part of the property. One of

the force majeure events stipulated in Clause 8 of the agreement is to the

following effect:

“(iv) any notice, order, rules, notification of the Government and/or other public or competent authority, including any prohibitory order of any court against development of property;”

Hence, in terms of the stipulation contained in Clause 5.1(iii), the period for

handing over of the possession stood extended during the prevalence of

the force majeure event. After the injunction was vacated by this Court on

8 May 2012, the appellant had, in terms of the grace period of three

months, time until 8 August 2012. Thereafter, for a period of six months

ending on 8 February 2013, the appellant was subject to the requirement

of paying compensation at Rs 5 per sq ft. The agreement stipulated that

this would be for a delay of up to a maximum of six months. The period of

six months ended on 8 February 2013. The agreement did not make any

specific provision for the period thereafter.

12 The respondents had paid 85% of the agreed consideration, together

with the agreement to sell, and even the balance at the time when the sale

deed was executed on 11 February 2013. Having paid the consideration,

it was evidently not in their interest to delay the receipt of possession. 6

Though the sale deed records that possession was handed over, it is clear

from the contemporaneous record that it was only on 28 August 2014 that

all the sets of keys of the apartment were handed over to the respondents.

Consequently, the appellant would be liable to pay reasonable

compensation to the respondents for the period between 9 February 2013

and 28 August 2014, in addition to the contractual payment due for the

period between 8 August 2012 and 8 February 2013.

13 However, we are of the view that the direction to pay interest at the

rate of 18% per annum is excessive and accordingly has to be scaled

down. Adopting a rate of 6% as a broad guideline, we have computed the

compensation at a lump sum of Rs 10 lakhs to obviate any dispute on

computation.

14 We accordingly issue the following directions:

(i) For the period between 8 February 2012 and 8 February 2013, the

appellant shall pay compensation in terms of Clause 5.1(iii) of the

agreement to sell at the rate of Rs 5 per sq ft;

(ii) For the period between 9 February 2013 and 28 August 2014, the

compensation which is payable by the appellant to the respondents is

computed at a lump sum of Rupees Ten Lakhs.

The aforesaid amount shall be paid within a period of one month from the

receipt of a certified copy of this order.

7

15 The appeal is partly allowed in the above terms. There shall be no

order as to costs.

…………...…...….......………………........J. [Dr Dhananjaya Y Chandrachud]

…..…..…....…........……………….…........J. [Hrishikesh Roy]

New Delhi;

December 17, 2019 8

ITEM NO.23 COURT NO.8 SECTION XVII-A

S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS

Civil Appeal No(s). 155/2015

M/S LANCO HILLS TECHNOLOGY PARK PVT LTD. Appellant(s)

VERSUS

MANISHA BALKRISHNA KULKARNI & ANR. Respondent(s)

(WITH IA No. 2/2015 - STAY APPLICATION)

Date : 17-12-2019 This appeal was called on for hearing today.

CORAM :

HON'BLE DR. JUSTICE D.Y. CHANDRACHUD HON'BLE MR. JUSTICE HRISHIKESH ROY

For Appellant(s) Mr. Deepak Khurana, Adv.

Mr. Tejasv Anand, Adv.

Mr. Umesh Kumar Khaitan, AOR

For Respondent(s) Mrs. D. Bharathi Reddy, AOR Ms. D. Tejaswi Reddy, Adv.

UPON hearing the counsel the Court made the following O R D E R

Admit.

The appeal is partly allowed in terms of the signed

reportable judgment.

There shall be no order as to costs.

Pending application, if any, stands disposed of.

(SANJAY KUMAR-I) (SAROJ KUMARI GAUR) AR-CUM-PS COURT MASTER

(Signed reportable judgment is placed on the file)

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free