Miss Lucy
← All judgments

M/S. Ladli Construction Co. (P) Ltd vs Punjab Police Housing Corpn. Ltd. & Ors

Supreme Court23 February 2012H.L. Gokhale · R.M. Lodha

Ratio decidendi

The rule this decision rests on

1. A party to a contract containing an arbitration clause naming a specific arbitrator is bound by that agreement and must proceed to arbitration before the named arbitrator unless good legal grounds exist for his exclusion. 2. The test for removal of an agreed arbitrator on grounds of alleged bias is whether a reasonable and intelligent man, fully apprised of all the circumstances, would feel a serious apprehension of bias; vague, fanciful or general suspicions without cogent materials will not suffice to establish reasonable apprehension of bias. 3. Where a party has not raised any objection to the named arbitrator at the time of his appointment but instead sought his appointment, and then later raises objections of bias without any intervening event justifying the change in position and without placing cogent materials on record, the party cannot escape the arbitration agreement on grounds of alleged bias. 4. An arbitrator who is named in a contract with knowledge of his role and authority relating to the contract, and who proceeds ex parte when the contracting party fails to appear before him despite being called upon to do so and fails to obtain a stay order from the court, does not thereby commit misconduct or demonstrate bias, particularly where the arbitrator gave full opportunity to the party to appear and present its case. 5. The fact that an arbitrator defends allegations of bias against him by filing an affidavit in opposition to an appeal does not itself constitute evidence of bias, as he is merely rebutting allegations made against him.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO(s). 947 OF 2006

M/S. LADLI CONSTRUCTION CO. (P) LTD. Appellant (s)

VERSUS

PUNJAB POLICE HOUSING CORPN. LTD. & ORS. Respondent(s)

J U D M E N T

R.M. LODHA, J. :

This Appeal, by special leave, arises from

the judgment and order dated November 25, 2002 passed by

the Punjab & Haryana High Court.

2. The controversy arises in this way. A

contract was entered into between the appellant - M/s Ladli

Construction Co. (P) Ltd. (hereinafter referred to as 'the

Contractor'), and the respondent Nos. 1 and 2, namely,

Punjab Police Housing Corporation Limited and Executive

Engineer (Civil), Punjab Police Housing Corporation

Limited (hereinafter referred to as 'the Corporation') for

construction of 240 houses Type II-A at Urban Estate,

Ludhiana at an estimated cost of Rs. 273.84 Lakhs. The

contract provided in Clause 2 that time was essence of the

contract and the time allowed for carrying out work as

entered in the tender shall be strictly observed by

2

Contractor. The Contractor could not maintain the time

schedule and the progress of the work was not observed. The

Contractor was directed to push up the progress of work but

that also it failed to do. The Contractor was notified

that if it failed to take any action to show requisite

progress by 30th of April, 1991, action against it under

Clause 3 of the agreement would be taken. Still there was

no requisite progress in execution of the work by the

Contractor. On May 8, 1991, the Corporation resorted to

action under Clause 3 of the contract, rescinded the

contract and adopted further course by giving unexecuted

work to another contractor. The disputes, thus, having

arisen between the parties, the Contractor moved the court

of Sub Judge, First Class, Chandigarh, for appointment of

the arbitrator in terms of Clause 25A of the contract.

3. On the application made by the Contractor for

appointment of the arbitrator, the Sub Judge, on May 13,

1992, ordered that matter in dispute may be referred for

arbitration as per Clause 25A of the agreement and,

accordingly, as per the agreement and the statement of

parties, the Sub Judge ordered the Chief Engineer of the

Corporation to act as an arbitrator as provided under

Clause 25A of the agreement. Both the parties were

permitted to file claim and counter claim before the

arbitrator.

4. In pursuance of the order dated May 13, 1992,

3

the Corporation lodged its claim against the Contractor on

June 15, 1992. The arbitrator - Chief Engineer of the

Corporation - called upon the Contractor to appear before

him on June 25, 1992. Thereafter also the arbitrator called

upon the Contractor to appear before him. The Contractor,

however, did not appear before the arbitrator and instead

sent a letter on June 29, 1992 intimating him that his

appointment as arbitrator was not acceptable to it; it did

not expect any justice and fair play from him and he must

refrain from acting as an arbitrator in the case.

5. Thereafter, on July 24, 1992, the Contractor

made an application before the Sub Judge, Chandigarh under

Sections 5, 11 and 12 of the Arbitration Act, 1940 (for

short, 'the 1940 Act') for removal of the arbitrator. The

Contractor did not appear before the arbitrator.

Consequently, the arbitrator proceeded with the arbitration

ex parte and passed the award on August 18, 1992.

6. After filing of the award, the Contractor

submitted objections under Section 30 of the 1940 Act

alleging misconduct on the part of the arbitrator and also

objected to the award being made rule of the court.

7. The Sub Judge heard the two applications

together - (i) application made by the Contractor for

removal of the arbitrator and objections under Section 30,

and (ii) application for making the award rule of the court

- and by a common order dated May 8, 1995 dismissed the

4

application made by the Contractor for removal of the

arbitrator and made the award dated August 18, 1992 rule of

the court and passed decree in terms thereof.

8. The Contractor challenged the common order dated May

8, 1995 passed by the Sub Judge, Chandigarh in appeal

before the District Judge, Chandigarh. The District Judge

dismissed the appeal on September 19, 1998.

9. Against these two concurrent judgments, the

Contractor filed civil revision before the High Court which

too was dismissed on November 25, 2002. As noted above, it

is from this order that the present Appeal, by special

leave, has arisen.

10. We have heard Mr. Rajeev Sharma, learned counsel for

the Contractor, and Dr. Balram Gupta, learned senior

counsel for the respondent Nos. 1 and 2 - Corporation.

11. Mr. Rajeev Sharma, learned counsel for the

Contractor, strenuously urged that the Contractor had

reasonable apprehension of bias on the part of the

arbitrator as the action of cancellation of contract was

taken by the Executive Engineer at the behest of the

arbitrator as he was the Chief Engineer of the Corporation.

He referred to the inspection made by the Chief Engineer

along with other Engineers of the Corporation on October

26, 1990 and the opinion formed by the Chief Engineer on

the basis of the inspection that the work was not being

carried out by the Contractor in accord with the time

5

schedule. He also referred to conduct of the arbitral

proceedings by the arbitrator, particularly concluding the

arbitration proceedings in a short span of about 49 days

and that too when the Contractor's application for his

removal was pending before the Court. In support of his

submission that the arbitrator was biased against the

Contractor, the learned counsel also referred to post

arbitral conduct of the arbitrator in contesting the Appeal

before this Court and filing counter affidavit in

opposition to the Appeal.

12. Mr. Rajeev Sharma would highlight two aspects,

viz., (i) the arbitration agreement was not placed before

the arbitrator, yet he commenced and concluded the arbitral

proceedings, and (ii) the award relating to unutilised

amount of secured advance which was not claimed by the

Corporation was passed, to indicate that the arbitrator was

biased. In support of his submissions, the learned counsel

relied upon a Constitution Bench judgment of this Court in

Gullapalli Nageswara Rao and Others Vs. Andhra Pradesh

State Road Transport Corporation and Another1 and a judgment

of the House of Lords in Bristol Corporation Vs. John

Aird & Co.2

13. Dr. Balram Gupta, learned senior counsel for the

Corporation, supported the judgment of the High Court. He

submitted that only two submissions were made before the

1 [1959] Supp. (1) SCR 319

2 [1911-13] All E.R. 1076

6

High Court which have been noted and considered and no

other point was urged.

14. The arbitration clause in the agreement, i.e.,

Clause 25A, reads as follows :

"Clause 25A. Arbitration etc. - If any question, difference or objection whatsoever shall arise in any way connected with or arising out of this instrument of the meaning of operation of any part thereof or the rights duties or liabilities of either party, then save in so far as the decision of any such matter is hereinbefore provided for and has been so decided, every such matter including whether its decision has been otherwise provided for and/or whether it has been finally decided accordingly, or whether the contract should be terminated or has been rightly terminated and as regards the rights and obligations of the parties as the results of such termination shall be referred for arbitration to the Chief Engineer of the Punjab Police Housing Corporation, Chandigarh or acting as such at the time of reference within 180 days or in six months from the payment of the final bill to the contractor or from the date registered notice is sent to the contractor to the effect that his final bill is ready for payment and his decision shall be final and binding and where the matter involves a claim for or the payment or recovery or deduction of money, only the amount, if any, awarded in such arbitration shall be recoverable in respect of the matter so referred."

15. The Contractor consciously agreed for the disputes

between the parties to be referred for arbitration to the

Chief Engineer of the Corporation. The Contractor, at the

time of agreement, was in full knowledge of the fact that

the Chief Engineer is under full control and supervision of

all civil engineering affairs of the Corporation, yet it

7

agreed for resolution of disputes between the parties by

him as an arbitrator. It is a fact that the Chief Engineer

inspected the progress of the work given to the Contractor

along with other engineers of the Corporation on October

26, 1990. In the course of inspection, the slow progress of

the work was brought to the notice of the Contractor on

that date. There was nothing unusual about it and, as a

matter of fact, on the contract being terminated on May 8,

1991, it was the Contractor who made an application for

appointment of arbitrator in terms of Clause 25A of the

agreement as it was well aware that the inspection by the

arbitrator did not disqualify him to be arbitrator. In the

application for appointment of arbitrator, no allegation of

any bias or hostility was made against the named

arbitrator, i.e., Chief Engineer of the Corporation, rather

the Contractor prayed for appointment of arbitrator in

terms of the arbitration Clause 25A. When the application

came up for consideration before the Sub Judge on May 13,

1992, the advocate appearing for the Contractor also

submitted for appointment of the arbitrator as named in the

agreement. Before the Court, no allegation was made that

the contract was terminated at the instance or behest of

the Chief Engineer. These facts clearly show that no case

of bias on the part of the Chief Engineer was pleaded or

pressed by the Contractor before the court in the

proceedings for appointment of the arbitrator. There is

8

nothing to indicate that something happened after May 13,

1992 which prompted the Contractor to write to the

arbitrator on June 29, 1992 that it had lost faith in him.

16. It is pertinent to notice that on May 13, 1992

while referring the disputes between the parties for

arbitration as per Clause 25A of the agreement, the

Contractor as well as the Corporation were permitted to

file claim and counter claim before the arbitrator. The

Corporation filed its claim against the Contractor on June

15, 1992. Upon receipt of the claim by the Corporation, the

arbitrator called upon the Contractor to appear before him

on June 25, 1992. The Contractor did not appear and instead

sent a letter to the arbitrator on June 29, 1992 intimating

him that his appointment as arbitrator was not acceptable.

No steps were taken by the Contractor for removal of the

arbitrator immediately. The application for removal of the

arbitrator was made almost after 26 days. Although the

Contractor prayed before the Sub Judge for stay of the

proceedings before the arbitrator but it was not successful

in getting any such order on July 24, 1992, or on the

subsequent dates, namely, July 30, 1992, August 3, 1992 and

August 6, 1992 from the court. In the absence of any stay

order from the court and non-appearance by the Contractor,

the arbitrator was left with no choice but to proceed ex

parte and conclude the arbitral proceedings. Merely

because the award came to be passed on August 18, 1992,

9

i.e., a day before the next date fixed before the Sub

Judge, it cannot be said that the arbitrator concluded the

proceedings hastily or he was biased.

17. The two aspects highlighted by Mr. Rajeev Sharma,

learned counsel for the Contractor, regarding (i) non-

availability of the agreement before the arbitrator, and

(ii) the award of return of unutilised amount of secured

advance by him, as grounds of bias have no merit at all.

18. The order dated May 13, 1992 passed by the Sub Judge

shows that photocopy of the arbitration agreement was

produced before the court. AW-1, who was examined by the

Corporation, in his deposition before the arbitrator, has

stated that photocopy of the agreement was tendered to the

arbitrator. Merely because copy of the agreement was not

found by the District Judge in the record of the arbitral

proceedings, it cannot be assumed that copy of the

agreement between the parties was not placed for

consideration before the arbitrator.

19. The arbitrator in his award has awarded interest in

the sum of Rs. 1,40,150/- upto December 31, 1991 on the

amount of secured advance paid to the Contractor for the

period the amount remained unutilised although the

Corporation had claimed the interest on that count in the

sum of Rs. 1,69,878/-. With regard to award of unutilised

amount of secured advance, the arbitrator observed in the

award that the exact amount of award will depend upon the

10

actual unutilised amount of secured advance till

realisation. On ascertaining the total amount of

unutilised secured advance, it was found to be Rs.

9,63,635.25/-.

20. The District Judge in the appeal preferred by the

Contractor in challenging the judgment and decree held in

para 21 of the judgment thus :-

"....In it unutilised advance of Public Health items as per statement at page 243 of the arbitrator file is Rs. 5,85,423.75ps. The statement of this witness dated 14.8.1992 with statement of interest and principal of the unutilised secured advance of building component is at pages 283-289 of the arbitration file in which unutilised secured advance of building component is mentioned as Rs. 3,73,211.50ps. So the total unutilised secured advance on both the counts comes to Rs. 9,63,635.25ps. The maxim is,"Certum est quod, certum reddi potest".

(certain is that which can be made certain). Now, from the perusal of the record of the total unutilised secured advance can be ascertained as Rs. 9,63,635.25ps. Similarly, from the record, the principal amount of the secured advance can also be calculated and on it, interest on the amount of the secured advance paid to the appellant for the period the amount remain unutilised could be calculated. The appellant has not been able to point out that the calculation of this amount as Rs. 1,40,150/- upto 31.12.1991 was wrong or incorrect. Therefore, it would be naove to contend that the award was vague, evasive or non-committal."

21. The above finding of the District Judge, Chandigarh,

was not challenged by the Contractor before the High Court

as is apparent from the impugned order. Thus, there is no

merit, at all, in the submission of the learned counsel for

the Contractor that the arbitrator awarded unutilised

11

secured advance for which there was no claim. In any case,

this hardly leads to any inference of bias of the

arbitrator.

22. In Gullapalli Nageswara Rao and Others (supra) this

Court restated the principle of natural justice that the

authority empowered to decide the dispute must be one

without bias towards one side or the other in the dispute.

There can hardly be any doubt about this fundamental

principle of natural justice. The question is - Whether on

facts, the Contractor has been able to establish that the

arbitrator was biased against it ? None of the

circumstances pointed out by the Contractor leads to any

inference that the arbitrator had any bias, personal or

otherwise. No doubt, bias may be found in variety of

situations and each case, where bias of adjudicator is

alleged, has to be seen in the context of its own facts but

a fanciful apprehension of bias is not enough.

23. The observations of the Lord Atkinson in Bristol

Corporation (supra), relied upon by the learned counsel for

the Contractor, instead of supporting his argument, go

fully against the Contractor. In Bristol Corporation

(supra) Lord Atkinson stated thus :

"...If a contractor chooses to enter into a contract binding him to submit any disputes which arise between him and the engineer of the persons with whom he contracts to that engineer to arbitrate on, then he must be held to his

12

contract; whether it be wise or unwise, prudent or the contrary, he stipulated that a person who is the servant of the persons with whom he contracted shall be the judge to decide upon matters upon which, necessarily, that engineer or arbitrator has himself formed an opinion. But though the contractor is bound by that contract, still he has a right to demand that, notwithstanding those pre-formed views of the engineer, that gentleman should listen to argument, and should determine the matters submitted to him as fairly as he can, as an honest man; and if it be shown in fact that there is any reasonable prospect that he will be so biased as not to decide fairly upon those matters, then the contractor is allowed to escape from his bargain, and to have the matters in dispute tried by one of the ordinary tribunals of the land. But he has more than that right. If, without any fault of his own, the engineer has put himself in such a position that it is not fitting, or decorous, or proper that he should act as arbitrator in any one or more of those disputes, the contractor has the right of appealing to a court of law to exercise the discretion which s. 4 of the Arbitration Act vests in them...."

24. The above observations exposit the legal position

that a contractor is bound by the contract if he has agreed

to submit the disputes to the engineer for arbitration

although he has to deal with such engineer under the

contract. It needs no emphasis that once the dispute is

referred to such arbitrator, the arbitrator has to act

fairly and objectively and the proceedings must meet the

requirements of principles of natural justice.

25. Insofar as the facts of the present case are

concerned, the Contractor moved the court for appointment

of the Chief Engineer as arbitrator and then chose not to

appear before him. What was the intervening event after

13

the arbitrator was appointed at his instance that prompted

him to ask the arbitrator to recuse is not stated by the

Contractor. The Contractor was not successful in getting

any final or interim order in the proceedings initiated by

it for removal of the arbitrator. The award passed by the

arbitrator also does not show that he misconducted in any

manner in the proceedings. He gave full opportunity to the

Contractor to appear and put forth its case but the

Contractor failed to avail of that opportunity.

26. There is no justifiable circumstance on record that

enables the Contractor to escape from the bargain that it

made under the contract and have the disputes resolved

through the process other than agreed.

27. In The Secretary to the Government, Transport

Deptt., Madras Vs. Munuswamy Mudaliar and Others3, this

Court stated :-

"11... When the parties entered into the contract, the parties knew the terms of the contract including arbitration clause. The parties knew the scheme and the fact that the Chief Engineer is superior and the Superintending Engineer is subordinate to the Chief Engineer of the particular circle. In spite of that the parties agreed and entered into arbitration and indeed submitted to the jurisdiction of the Superintending Engineer at that time to begin with, who, however, could not complete the arbitration because he was transferred and succeeded by a successor. In those circumstances on the facts stated no bias can reasonably be apprehended and made a ground for removal of a named arbitrator. In our opinion this cannot be, at all, a good or valid legal ground. Unless

3 AIR 1988 SC 2232

14

there is allegation against the named arbitrator either against his honesty or capacity or malafide or interest in the subject-matter or reasonable apprehension of the bias, a named and agreed arbitrator cannot and should not be removed in exercise of a discretion vested in the Courts under S. 5 of the Act.

12. Reasonable apprehension of bias in the mind of a reasonable man can be a ground for removal of the arbitrator. A predisposition to decide for or against one party, without proper regard to the true merits of the disputes is bias. There must be reasonable apprehension of that predisposition. The reasonable apprehension must be based on cogent materials. See the observations of Mustill and Boyd, Commercial Arbitration, 1982 Edition, page 214. Halsbury's Laws of England, Fourth Edition, Volume 2, para 551, page 282 describe that the test for bias is whether a reasonable intelligent man, fully apprised of all the circumstances, would feel a serious apprehension of bias.

13. This Court in International Airport Authority of India v. K.D.Bali, (1988) 2 JT 1 :

(AIR 1988 SC 1099) held that there must be reasonable evidence to satisfy that there was a real likelihood of bias. Vague suspicions of whimsical, capricious and unreasonable people should not be made the standard to regulate normal human conduct. In this country in numerous contracts with the Government, clauses requiring the Superintending Engineer or some official of the Govt. to be the arbitrator are there. It cannot be said that the Superintending Engineer, as such, cannot be entrusted with the work of arbitration and that an apprehension, simpliciter in the mind of the contractor without any tangible ground, would be a justification for removal. No other ground for the alleged apprehension was indicated in the pleadings before the learned Judge or the decision of the learned Judge. There was, in our opinion, no ground for removal of the arbitrator. Mere imagination of a ground cannot be an excuse for apprehending bias in the mind of the chosen arbitrator."

15 28. In S. Rajan Vs. State of Kerala and another4, this

Court stated :-

"12....Thus, this is a case where the agreement itself specifies and names the arbitrator. It is the Superintending Engineer, Buildings and Roads Circle, Trivandrum. In such a situation, it was obligatory upon the learned Subordinate Judge, in case he was satisfied that the dispute ought to be referred to the arbitrator, to refer the dispute to the arbitrator specified in the agreement. It was not open to him to ignore the said clause of the agreement and to appoint another person as an arbitrator. Only if the arbitrator specified and named in the agreement refuses or fails to act the Court does get the jurisdiction to appoint another person or persons as the arbitrator. This is the clear purport of Sub-section (4). It says that the reference shall be to the arbitrator appointed by the parties..."

29. Where parties enter into a contract knowing the

role, authority or power of the Chief Engineer in the

affairs relating to the contract but nevertheless agree for

him to be arbitrator and name him in the agreement to

adjudicate the dispute/s between the parties, then they

stand bound by it unless a good or valid legal ground is

made out for his exclusion.

30. Except raising the vague and general objections that

the arbitrator was biased and had predisposition to decide

against the Contractor, no materials, much less cogent

materials, have been placed by the Contractor to show bias

of the arbitrator. No sufficient reason appears on record

as to why the arbitrator should not have proceeded with the

4 AIR 1992 SC 1918

16

arbitral proceedings. The test of reasonable apprehension

of bias in the mind of a reasonable man is not satisfied in

the factual situation.

31. We may now deal with the submission of the learned

counsel for the Contractor that bias on the part of the

arbitrator is also reflected from the fact that he has

contested the present Appeal and filed the affidavit in

opposition. What would have the arbitrator done when he has

been personally impleaded as respondent in the Appeal and

the allegations of bias have been made against him. He was

left with no choice but to rebut the allegations by filing

his affidavit. The arbitrator did what any other person in

his place would have done in the circumstances.

32. The view taken by the High Court does not suffer

from any infirmity justifying interference by us in our

jurisdiction in appeal under Article 136 of the

Constitution of India.

33. Civil Appeal is dismissed with no order as to costs.

..........................J. (R.M. LODHA)

NEW DELHI ..........................J. FEBRUARY 23, 2012 (H.L. GOKHALE)

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free