M/s. Interstate Construction vs National Projects Construction Corporation Ltd.
- SCC(2026) 2 SCC 780
- Neutral2025 INSC 699
- SCR[2025] 5 SCR 2106
Ratio decidendi
The rule this decision rests on
1. Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 empowers an arbitral tribunal to award interest for the whole or any part of the period between the date on which the cause of action arose and the date on which the award is made. This provision permits the tribunal to subdivide this single statutory period into multiple sub-periods (such as pre-reference and pendente lite periods) and to award different rates of interest for those sub-periods, and to exclude parts of the period where the claimant has been remiss in pursuing its claims. 2. The statutory language "for the whole or any part of the period" in Section 31(7)(a) authorizes an arbitral tribunal to award interest on varying rates or at different rates for different sub-divided periods within the overall period from the cause of action to the award, provided that the tribunal's discretion is exercised reasonably. 3. Under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, post-award interest is calculated on the "sum directed to be paid by an arbitral award," which includes both the principal amount and any interest awarded from the date of the cause of action to the date of the award; accordingly, an arbitral tribunal may award post-award interest on the combined sum of principal and pre-award interest without this constituting impermissible compound interest. 4. An arbitral tribunal does not commit an illegality by awarding interest in the manner described above, which was correctly upheld by the Single Judge and should not have been set aside on appeal under Section 37 of the 1996 Act.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 3461 OF 2025
M/S. INTERSTATE CONSTRUCTION APPELLANT(S)
VERSUS
NATIONAL PROJECTS CONSTRUCTION CORPORATION LTD. RESPONDENT(S)
JUDGMENT
UJJAL BHUYAN, J.
This appeal by special leave is directed against the
judgment and order dated 01.08.2023 passed by the Division
Bench of the High Court of Delhi in FAO (OS) (Comm) No.175 of
2021.
Signature Not Verified Digitally signed by ASHISH KONDLE
2. It may be mentioned that by the aforesaid judgment Date: 2025.05.15 13:35:47 IST Reason:
and order dated 01.08.2023 (impugned judgment), Division Bench of the High Court of Delhi (High Court) allowed the
appeal of National Projects Construction Corporation Limited,
(NPCC) or the respondent hereinafter, filed under Section 37 of
the Arbitration and Conciliation Act, 1996 (briefly ‘the 1996 Act’
hereinafter) setting aside that part of the judgment and order
dated 02.08.2021 passed by a learned Single Judge of the High
Court under Section 34 of the 1996 Act upholding the directions
contained in paragraph 58(b) of the award dated 28.10.2020 as
well as setting aside the directions of the arbitral tribunal as
contained in paragraph 58(b) of the said award.
3. Relevant facts may be briefly noted.
4. Respondent had engaged the services of the
appellant for executing a contract relating to Ramagundam
Super Thermal Power Project, Ramagundam, District
Karimnagar in the then composite State of Andhra Pradesh. In
this regard, two separate work orders were issued:
(i) Work order No.917344/838 dated 19.06.1984 in
respect of the work excavation of foundation package
work-II 3 X 500 MW of National Thermal Power
2 Corporation Limited, Ramagundam Super Thermal
Power Project;
(ii) Work Order No. 917344/2382 in respect of the work
foundation package work, stage-II, at Ramagundam
Super Thermal Power Project;
5. Thereafter, contract agreement was entered into
between the parties. As per clause 4 of the conditions of contract
read with clause 15 of the special conditions attached to the
work orders, all the disputes and differences between the
parties were to be settled by way of arbitration.
6. It is stated that appellant had completed the contract
work in the year 1987. Respondent had paid the appellant the
contractual dues after withholding certain sums on account of
recoveries. Appellant disputed such recoveries. Additionally,
appellant also raised certain claims which were not accepted by
the respondent.
7. In view of such disputes and differences, appellant
invoked the arbitration clause by issuing notice dated
17.05.1993.
3
8. Respondent did not take immediate steps for
appointment of an arbitrator. After considerable delay, by
communication dated 07.10.1997, respondent appointed Shri
Shivamoy Ghosh, Additional General Manager, NPCC, Madras
Sector, Chennai as the sole arbitrator to arbitrate on the subject
dispute.
9. Appellant filed statement of claims before the learned
arbitrator on 20.01.1998 claiming an aggregate amount of
Rs.4,46,29,404.00 along with pendente lite and future interest
at the rate of 24 percent per annum till final realization of the
amount.
10. Appellant sought for a direction from the learned
arbitrator to the respondent to supply various documents
related to the dispute. However, learned arbitrator only
permitted the appellant an opportunity to inspect the
documents and did not issue any direction to the respondent
for supply of copies.
11. Aggrieved thereby, appellant filed a petition under
Section 14 of the 1996 Act before the High Court seeking
4 termination of the mandate of the learned arbitrator and for
appointment of a new arbitrator in his place. This petition was
registered as OMP No. 214/2002. By order dated 11.10.2004,
learned Single Judge terminated the mandate of Shri Shivamoy
Ghosh and appointed Shri A.S. Chandhiok, Sr. Advocate, as the
sole arbitrator.
12. Respondent challenged the said order of the learned
Single Judge dated 11.10.2004 before the Division Bench of the
High Court in FAO (OS) No.241/2004. By order dated
02.02.2005, Division Bench appointed Shri L.R. Gupta, retired
Director General of CPWD as the sole arbitrator.
13. Before Shri L.R. Gupta, the learned arbitrator,
respondent while filing its reply to the statement of claims filed
by the appellant, also challenged the authority of one Shri
Jagdish Raj Yadav to file the claim on behalf of the appellant. In
this regard an application dated 23.02.2007 was filed before the
learned arbitrator. Learned arbitrator dismissed the said
application vide the order dated 03.08.2007.
5
14. The said order dated 03.08.2007 was challenged by
the respondent before the learned Single Judge of the High
Court by filing a petition under Section 34 of the 1996 Act, being
OMP No.537/2007.
15. It may be mentioned that Shri L.R. Gupta resigned
as the sole arbitrator on 23.06.2008.
16. Vide order dated 30.01.2007, learned Single Judge
disposed of the petition filed under Section 34 of the 1996 Act
bearing OMP No.537/2007.
17. Appellant filed a petition under Section 15 of the
1996 Act before the High Court being OMP (T) (Comm) No.
30/2018 seeking appointment of an arbitrator in place of Shri
L.R. Gupta who had resigned. The said petition was disposed of
by the learned Single Judge of the High Court vide order dated
31.05.2018 reconstituting the arbitral tribunal by appointing
Mr. Justice R.C. Jain, a former Judge of the High Court, as the
sole arbitrator to arbitrate on the disputes between the parties.
6
18. New arbitrator held the first hearing on 03.05.2019
and finally pronounced the award on 28.10.2020. While the
arbitral tribunal allowed the claims of the appellant under
several heads, we are concerned with the contentious part of
the award relating to payment of interest (claim No. 7) contained
in paragraph 58 of the award. Relevant portion contained in
paragraph 58 of the award reads as under:
58. *** *** *** *** In a nutshell the claimant is held entitled to interest as under:
a) Pre-reference / past period interest:
@ 18% per annum on a sum of Rs.34,43,490.61 w.e.f. July 1987 up-till 19.01.1998.
b) Pendente lite interest:
i) @ 12% per annum w.e.f. 20.01.1998 uptill 31.12.2008 on the total amount (i.e. principal amount + the amount of interest on the pre-reference/past period).
ii) @ 12% per annum w.e.f. 01.01.2017 till the date of award on the total amount (i.e. principal amount + the amount of interest for the pre-reference period and for the period from 20.01.1998 till 31.12.2008).
c) Future interest:
7
@ 18% per annum from the date of the award till the date of payment on the total amount (i.e. principal amount + amount of interest on the pre-reference/past period+ amount of interest pendente lite).
19. Respondent filed a petition under Section 34 of the
1996 Act before the Single Bench of the High Court for setting
aside the award dated 28.10.2020. The same was registered as
OMP (Comm) No. 78/2021. By the judgment and order dated
02.08.2021, learned Single Judge partly allowed the petition by
setting aside the award with regard to future interest at the rate
exceeding 9 percent per annum from the date of the award till
the date of payment.
20. Aggrieved by the judgment and order dated
02.08.2021 passed by the learned Single Judge, respondent
preferred an appeal under Section 37 of the 1996 Act before the
Division Bench of the High Court which was registered as FAO
(OS) (Comm) No. 175/2021. In the appeal, learned senior
counsel for the respondent (which was the appellant before the
Division Bench) clarified that the challenge would be restricted
to the directions issued by the arbitral tribunal insofar the issue
8 of interest was concerned. This was further clarified by
submitting that the challenge was not with respect to the rate
of interest or award of interest for the pre-reference/past period.
Grievance highlighted was against the directions contained in
sub-paragraph (b)(i) of paragraph 58 to the extent of the arbitral
tribunal stipulating that interest for the period mentioned
therein would be leviable not merely on the principal amount as
awarded but upon the said amount inclusive of the amount of
interest relating to the pre-reference/past period. Likewise,
arbitral tribunal awarded interest on identical terms in sub-
paragraph (b)(ii) of paragraph 58 which was objected to.
Division Bench of the High Court vide the judgment and order
dated 01.08.2023 (impugned judgment) allowed the appeal by
setting aside the directions contained in paragraph 58(b).
21. Aggrieved thereby, appellant filed the related SLP (C)
No.23235/2023 before this Court. By order dated 19.10.2023,
this Court issued notice. In the hearing held on 25.02.2025,
leave was granted.
9
22. Though there is no challenge by either parties to the
award on merit, challenge of the respondent being confined only
to the interest part, nonetheless, to have a complete picture, it
would be appropriate to mention the claims of the appellant and
the corresponding amounts awarded by the arbitral tribunal.
The following statement in tabular form will throw light on the
amounts claimed by the appellant and the amounts awarded by
the arbitral tribunal under sixteen heads of claim. The tabular
statement is as under:
Claim Particulars Amount Amount No. Claimed Awarded (a) Escalation at 10% for work Rs.20,71,322.0 Rs.20,71,322 order 48/4 0 .00
(b) Escalation at 10% for work Rs.1,84,418. 77 Rs.1,84,418. order 47/11 77
(c) Refund of panel recovery of steel taking 5% of scrap wastage in place of 3% wastage: - I) Steel difference Rs.1,75, 132.00 II) M.S. Found Steel Rs. 1,806.42 III) 12 Dia M.S. Rs. 68,750.00 IV) Structural Steel Rs. 2,513.28 V) Steel Plates Rs. 2,649.84 VI) Scrap made in labour Rs.12,000.00 rates Total Rs.2,62,850.70 Rs.1,82,463. 70 d) Unreasonable recoveries:- i) Cribes Rs. 3,747.75 ii) Shutter plates Rs. 38,322.65
10 iii) B.F.P. Hire charges for Rs. 15,776.31 shutter plates iv) B.F.P. Hire charges for Rs. 64,521.00 shutter plates v) Refund of 28% Rs. 60,833.00 overhead supply for metal vi) Dozer recovery for work Rs. 10,676.00 order No. 48/4 vii) Cubes failure Rs. 34,701.92 (never given in writing of any cube failure of any member) viii) Chain pulley Rs. 8,000.00 block (not with us) ix) Clamps (already Rs. 14,990.00 returned) x) Pipes (already Rs. 89,353.00 returned) Total Rs.3,40,921.63 Rs.60,833.00 e) Work order by other agencies Rs.84,447.00 Rs.84,447.00 but not in our scope like plastering etc. f) Held amounts:- i) Amount held on account Rs.3,95,000.00 of grouting T.G. ii) Amount held on account Rs.20,000.00 of grouting C.E.P. iii) Staging held amount of Rs.3,09,203.14 T.G. iv) Work order No. 48/4 Rs.43,000.00 withheld amount v) Work Order No. 47/11 Rs.51,803.00 withheld amount vi) Work Order No. 48/4 Rs.23,000.00 shutter plates held vii) Curing held amount Rs.3,000.00 48/4 viii) Work order No.48/4 Rs.10,000.00 E.S.P. rectification held amount ix) Work order No.48/4 Rs.5,000.00 T.G. held amount for final shape. Total Rs.8,60,004.14 Rs.8,60,004. 14
11 g) Balance payable in bills i) Payable in bills 47/11 Rs.64,376.76 ii) S.D. 47/11 total balance Rs.2,02,870.00 iii) Work order No. 48/4 Rs.84,000.00 money payable in bills Total Rs.3,51,246.76 h) Difference in excavation Rs.1,31,464.00 i) Booking of C.E.P. in package- Rs.17,690.00 IV as agreed by E.D.S.R. differences j) Claims of not allotting quarry Rs.2,66,000.00 as agreed by E.D.S.R. k) 1200 M3 of stone aggregate Rs.13,40,000.0 from Karim Nagar for 0 rate differences of Rs. 70/- M3 extra and the claim was agreed by EDSR referred to our letter ISC/ Claims/1 Dt.14.10.89 para III. l) Idle labour charges refer Rs.4,81,000.00 our letter ISC/Claims/1 dt. 14.10.89, para IV m) 2% interest rate difference on Rs.50,000.00 mobilization advance. n) Interest on delayed release of Rs.2,40,000.00 S.D. refer para 9 of our letter ISC/Claims/1 dt. 14.10.89. o) Mental anguishes, torture Rs.60,00,000.0 and loss of social status 0 suffered refer Letter No. ISC/ Claims/1 dt. 14.10.89 para II. p) Addl. 24% interest for 10.5 Rs.3,19,57,039. years w.e.f. July 1987 upto 0 Dec. 1997. Total Rs.4,46,38,404. Rs.34,43,490 00 .61
23. We have already extracted the nature of interest
payment provided in the award dated 28.10.2020. However, for
12 ready reference, interest awarded to the appellant by the
arbitral tribunal may once again be noted which is as under:
(a) Pre-reference/past period interest at the rate of 18% per annum on the sum of Rs. 34,43,490.61 with effect from July 1987 uptill 19.01.1998.
(b) Pendente lite interest at the rate of 12% per annum with effect from 20.01.1998 uptill 31.12.2008 on the total amount (that is, principal amount plus the amount of interest for the pre-
reference/past period).
(c) Pendente lite interest at the rate of 12% per annum with effect from 01.01.2017 till the date of the award on the total amount (that is, principal amount plus the amount of interest on the pre- reference period and for the period from 20.01.1998 till 31.12.2008).
(d) Future interest at the rate of 18% per annum from the date of the award till the date of payment on the total amount (that is, principal amount added to the amount of interest for the pre-
reference/past period and interest pendente lite).
23.1. While holding that appellant was entitled to award of
interest for the pre-reference period i.e. from the date on which
the cause of action arose till filing of the claim before the arbitral
13 tribunal as well as for the pendente lite period and also for the
future period, arbitral tribunal agreed with the respondent that
no interest should be awarded to the appellant for the period
when there was absolute laches on the part of the appellant.
Arbitral tribunal held that for the period from 01.01.2009 till
31.12.2016, that is for a period of about eight years, there was
complete laches on the part of the appellant. Therefore, the
arbitral tribunal declared that appellant would not be entitled
to any interest for the aforesaid period.
24. Respondent filed a petition under Section 34 of the
1996 Act before the High Court impugning the arbitral award
dated 28.10.2020. Vide the judgment and order dated
02.08.2021, learned Single Judge upheld the claims awarded
by the arbitral tribunal. On the question of interest, learned
Single Judge framed the question as to whether interest
awarded by the arbitral tribunal was exorbitant and
unsustainable. Learned Single Judge held that arbitral
tribunal’s decision to award pre-reference interest at the rate of
18 percent per annum did not warrant any interference. As
14 regards pendente lite interest, learned Single Judge while noting
that arbitral tribunal had awarded 12 percent interest per
annum for the period from 20.01.1998 till 31.12.2008 and
again from 01.01.2017 till 28.10.2020, justified the decision of
the arbitral tribunal not to award interest for the period from
01.01.2009 to 31.12.2016 as during this period the appellant
was remiss and did not pursue its claim before the arbitral
tribunal diligently. On the rate of interest, learned Single Judge
held that interest at the rate of 12 percent per annum could not
by any stretch be considered to be exorbitant or unreasonable
but held that 18 percent future interest from the date of the
award till the date of payment granted by the arbitral tribunal
was ex facie erroneous as according to learned Single Judge the
interest rate should have been 2 percent higher than the
current rate of interest prevalent on the date of the award.
Therefore, this portion of the award was set aside by the learned
Single Judge; instead learned Single Judge awarded future
interest holding that it could not have been in excess of 9
percent per annum. Therefore, learned Single Judge partly
15 allowed the petition under Section 34 of the 1996 Act to the
extent of setting aside the award of future interest at a rate
exceeding 9 percent per annum from the date of the award till
the date of payment.
25. This brings us to the impugned judgment and order
dated 01.08.2023. We have already noted about the limited
nature of challenge made by the respondent during the hearing
of the appeal filed under Section 37 of the 1996 Act. Learned
senior counsel appearing for the respondent clarified that the
challenge to the award stood restricted to the directions issued
by the arbitral tribunal insofar the issue of interest was
concerned. He clarified that the challenge was not with respect
to either the rate at which interest was awarded or the grant of
interest for the pre-reference/past period. The grievance was
confined to the directions contained in paragraph 58(b)(i) of the
award and the similar nature of interest in paragraph 58(b)(ii)
inasmuch as the arbitral tribunal proceeded to award interest
on identical terms: on the principal amount plus the amount of
interest for the pre-reference/past period. Division Bench
16 referred to Section 31(7)(a) and (b) of the 1996 Act as well as
placed reliance on the decision of this Court in Sayeed Ahmed
and Company Vs. State of Uttar Pradesh 1 and came to the
following two conclusions:
i) Section 31(7) recognizes only two periods for which interest may be awarded. The two periods are, firstly from the date on which the cause of action arose till passing of the award and secondly from the date of the award till actual payment. Therefore, the distinction between pre-
reference/past period and pendente lite period no longer existed. The period from the date of cause of action i.e. July, 1987 till the date of the award dated 28.10.2020 would constitute the period contemplated under Section 31(7)(a) of the 1996 Act. The period commencing from the date of award till payment would be the second period within the meaning of Section 31(7)(b) of the 1996 Act. Therefore, the arbitral tribunal committed an illegality in awarding interest for three periods: pre-reference/past periods, pendente lite and for the future period.
ii) Arbitral tribunal committed further illegality in forging the principal amount with interest as would be evident from paragraph 58(b) of the award. Interest awarded for the pre-reference period as well as for the pendente lite period have been subjected to further levy
1 (2009) 12 SCC 26
17 of interest for the said periods by adding the interest amount with the principal amount awarded. This amounted to levying compound interest which is impermissible. Accordingly, the directions contained in paragraph 58(b) were set aside by the Division Bench.
26. In our considered view, the reasonings given by the
Division Bench are fallacious. We say so for the reasons
mentioned hereunder.
27. Section 31 of the 1996 Act is the relevant provision.
It deals with the form and contents of arbitral award. Section
31 has eight sub-sections. Sub-section (7) is central to the
debate and after the amendment with retrospective effect from
23.10.2015 read as under:
31. Form and contents of arbitral award -
* * * * * (7)(a) Unless otherwise agreed by the parties, where and in so far as an arbitral award is for the payment of money, the arbitral tribunal may include in the sum for which the award is made interest, at such rate as it deems reasonable, on the whole or any part of the money, for the whole or any part of the period between the date on
18 which the cause of action arose and the date on which the award is made.
(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of two per cent higher than the current rate of interest prevalent on the date of award, from the date of award to the date of payment.
27.1. Before substitution and prior to 23.10.2015, clause
(b) of sub-section (7) of Section 31 stood thus:
(b) A sum directed to be paid by an arbitral award shall, unless the award otherwise directs, carry interest at the rate of eighteen per centum per annum from the date of the award to the date of payment.
28. We now come to the analysis of Section 31(7), both
clauses (a) and (b). For the time being we concentrate on clause
(a) insofar it deals with the period for which interest may be
awarded. A reading of clause (a) reveals that interest may be for
the whole or any part of the period between the date on which
the cause of action arose and the date on which the award is
made. In real terms it means the period from the date on which
the cause of action arose till filing of the claim petition by the
19 claimant and from the date of filing of the claim petition till the
date of the award. Division Bench of the High Court relied upon
Sayeed Ahmed and Company (supra) wherein this Court
analyzed Section 31(7) of the 1996 Act and opined that the
difference between pre-reference period and pendente lite period
has disappeared insofar award of interest by the arbitrator is
concerned. The said section now recognizes only two periods
and makes the following provision:
i) In regard to the period between the date on which the cause of action arose and the date on which the award is made (pre-reference period + pendente lite), the arbitral tribunal may award interest at such rate as it deems reasonable for the whole or any part of the period unless otherwise agreed by the party;
ii) For the period from the date of award to the date of payment, interest at the rate of 18 percent per annum (this is in reference to the pre 23.10.2015 position) if no specific order is made in regard to interest; however, the arbitrator may award interest at a different rate for the period between the date of award and the date of payment.
29. Based on the aforesaid decision, the Division Bench
held that it was not open for the arbitral tribunal to have carved
out three periods for payment of interest: pre-reference,
20 pendente lite and future when the statute provides for only two
periods: first period being the period between the date on which
the cause of action arose and the date on which the award is
made and the second period is from the date of the award till
the date of payment.
30. We are unable to agree with the view expressed by
the Division Bench. Even in Sayeed Ahmed and Company
(supra) relied upon by the Division Bench, the Bench held that
Section 31(7) had carved out two periods, the first period being
from the date on which the cause of action arose till the date on
which the award is made and the second period being from the
date of award till the date of payment. As regards the first period,
the Bench clarified that it includes the pre-reference period plus
pendente lite period. Though the arbitral tribunal had granted
interest for three periods: pre-reference period, pendente lite
and post award period, the first two period basically comprises
of the period contemplated under clause (a) of sub-section (7) of
Section 31. It is another matter that the arbitral tribunal
awarded varying degrees of interest for the two sub-periods: 18
21 percent per annum for the pre-reference period and 12 percent
as pendente lite, excluding from the said period, the period of
eight years when the appellant was found to be remiss in
pursuing its claims before the arbitral tribunal. This is also
permissible as we shall explain.
31. Therefore, Sayeed Ahmed and Company (supra) does
not exclude or does not say that interest should not be granted
for the pre-reference period. All that it explains is that Section
31(7)(a) has joined the two periods of interest: pre-reference and
pendente lite.
32. This position has been clarified by a recent decision
of this Court in Pam Developments Private Limited Vs. State of
West Bengal2. After extracting Section 31(7) of the 1996 Act, this
Court held that power of the arbitrator to grant pre-reference
interest, pendente lite interest and post award interest under
Section 31(7) of the 1996 is now fairly well settled. The Bench,
thereafter, culled out the following legal propositions in this
2 (2024) 10 SCC 715
22 regard highlighting the difference in the position of law qua the
Arbitration Act, 1940 vis-à-vis the 1996 Act:
23. The power of the arbitrator to grant pre-
reference interest, pendente lite interest, and post- award interest under Section 31(7) of the Act is fairly well-settled. The judicial determinations also highlight the difference in the position of law under the Arbitration Act, 1940. The following propositions can be summarised from a survey of these cases:
23.1. Under the Arbitration Act, 1940, there was no specific provision that empowered an arbitrator to grant interest. However, through judicial pronouncements, this Court has affirmed the power of the arbitrator to grant pre-reference, pendente lite, and post-award interest on the rationale that a person who has been deprived of the use of money to which he is legitimately entitled has a right to be compensated for the same.
When the agreement does not prohibit the grant of interest and a party claims interest, it is presumed that interest is an implied term of the agreement, and, therefore, the arbitrator has the power to decide the same.
23.2. Under the 1940 Act, this Court has adopted a strict construction of contractual clauses that prohibit the grant of interest and has held that the
23 arbitrator has the power to award interest unless there is an express, specific provision that excludes the jurisdiction of the arbitrator from awarding interest for the dispute in question.
23.3. Under the 1996 Act, the power of the arbitrator to grant interest is governed by the statutory provision in Section 31(7). This provision has two parts. Under clause (a), the arbitrator can award interest for the period between the date of cause of action to the date of the award, unless otherwise agreed by the parties. Clause (b) provides that unless the award directs otherwise, the sum directed to be paid by an arbitral award shall carry interest @ 2% higher than the current rate of interest, from the date of the award to the date of payment (referring to the post 23.10.2015 position).
23.4. The wording of Section 31(7)(a) marks a departure from the Arbitration Act, 1940 in two ways : first, it does not make an explicit distinction between pre-reference and pendente lite interest as both of them are provided for under this sub- section; second, it sanctifies party autonomy and restricts the power to grant pre-reference and pendente lite interest the moment the agreement bars payment of interest, even if it is not a specific bar against the arbitrator.
24 23.5. The power of the arbitrator to award pre-
reference and pendente lite interest is not restricted when the agreement is silent on whether interest can be awarded or does not contain a specific term that prohibits the same.
23.6. While pendente lite interest is a matter of procedural law, pre-reference interest is governed by substantive law. Therefore, the grant of pre- reference interest cannot be sourced solely in Section 31(7)(a) (which is a procedural law), but must be based on an agreement between the parties (express or implied), statutory provision (such as Section 3 of the Interest Act, 1978), or proof of mercantile usage.
24. In view of the above, the High Court had no reason to interfere with the arbitral award with respect to grant of pre-reference interest, since the contract between the parties does not prohibit the same.
33. This position has been further explained by a recent
decision of this Bench in North Delhi Municipal Corporation Vs.
S.A. Builders Ltd.3. After adverting to Section 31(7) of the 1996
Act, this Court explained as under:
3
(2024) SCC Online SC 3768
25 36.1. From a minute reading of sub-section (7), it is seen that it has got two parts: the first part i.e. clause (a) deals with passing of award which would include interest up to the date on which the award is made. The second part i.e. clause (b) deals with grant of interest on the ‘sum’ awarded by the arbitral tribunal.
33.1. Thereafter the Bench observed that under Section
31(7) of the 1996 Act, an arbitral tribunal has the power to grant
– (i) pre-award (ii) pendente lite (iii) post-award interest. The
Bench explained the reason for award of such interest in the
following manner:
39. Generally, going by the provisions contained in Section 31(7) of the 1996 Act, it is evident that an arbitral tribunal has the power to grant (i) pre-award (ii) pendente lite (iii) post-award interest. Intention behind awarding pre-award interest is primarily to compensate the claimant for the pecuniary loss suffered from the time the cause of action arose till passing of the arbitral award.
Further, this is also to ensure that the arbitral proceeding is concluded within a reasonable period to minimise the impact of the pre-award interest as well as interest pendente lite; thereby promoting efficiency in the arbitration process. Similarly, grant of post-award interest also serves a salutary purpose. It primarily acts
26 as a disincentive to the award debtor not to delay payment of the arbitral amount to the award holder.
34. Thus, what Section 31(7)(a) has done is that there is
now a statutory recognition of the power of the arbitral tribunal
to grant pre-reference interest from the date on which the cause
of action arose till the date on which the award is made. There
was a vacuum in the Arbitration Act, 1940 as there was no such
provision for granting pre-reference interest. It was through
judicial pronouncements that such power of the arbitrator to
grant pre-reference interest was conferred. Now under Section
31(7)(a) of the 1996 Act, such power is statutorily recognized.
35. Let us revert back to clause (a) of sub-section (7) of
Section 31 of the 1996 Act. A careful and minute reading of this
provision will make it clear that the arbitral tribunal has the
discretion to include in the sum awarded interest at such rate
as it deems reasonable on the whole or any part of the money
awarded for the whole or any part of the period from the date
on which the cause of action arose till the date on which the
award is made. We may exclude that part of the sentence ‘on
27 the whole or any part of the money’ from our analysis since this
is not relevant to the controversy. If we exclude this portion,
what then becomes discernible is that the arbitral tribunal has
the discretion to include in the sum awarded : firstly, interest at
such rate as it deems reasonable; and secondly, for the whole or
any part of the period between the date on which the cause of
action arose and the date on which the award is made. This
would mean that the arbitral tribunal can exclude a period from
the date on which the cause of action arose till the date on
which the award is made for the purpose of grant of interest, as
has been done in the present case. It would also mean that the
arbitral tribunal can grant interest for the whole or any part of
the period between the date on which the cause of action arose
and the date on which the award is made. It can be a composite
period or the said period can be further sub-divided, as done in
the present case i.e. from the date of cause of action to filing of
the claim and from the date of filing of the claim till the date of
the award excluding the period when the appellant was found
to be remiss. It would also mean that there can be one rate of
28 interest for the whole period or one or more rates of interest for
the sub-divided periods as has been done in the instant case.
In our opinion, this would be the correct approach to interpret
Section 31(7)(a), given the scheme of the 1996 Act.
36. That being the position, we are of the view that the
Division Bench had fallen in error by holding that the arbitral
tribunal had no jurisdiction to award interest for two periods i.e.
pre-reference and pendente lite when the statute provides for
only one period viz. from the date when the cause of action arose
till the date of the award. The view expressed by the High Court
is not the correct interpretation of Section 37(1)(a) of the 1996
Act as explained by us supra as well as in Pam Developments
Private Limited (supra) and S.A. Builders Ltd. (supra).
37. This brings us to the second issue on which the High
Court set aside the directions of the arbitral tribunal contained
in paragraph 58(b) of the award. According to the Division
Bench, the arbitral tribunal had committed an illegality in
forging the principal amount with interest while computing the
awarded amount on which future interest is to be paid. Interest
29 awarded for the past period could not have been subjected to
further levy of interest during the pendente lite or post award
period on merger with the principal amount as this would
amount to levy of compound interest.
38. This aspect of the matter is no longer res integra.
39. In State of Haryana Vs. S.L. Arora 4 , a two-Judge
Bench of this Court observed that as regards pre-award period,
interest has to be awarded as specified in the contract and in
the absence of any contract, as per the discretion of the arbitral
tribunal. However, with regard to the post-award period, the
interest is payable as per the discretion of the arbitral tribunal
and in the absence of exercise of such discretion, at the
mandatory statutory rate of 18 percent per annum. Award of
interest like award of cost are ancillary matters. Therefore, the
expressions sum for which the award is made and the sum
directed to be paid by an arbitral award contextually refers to
the award on the substantive claims and not ancillary or
4 (2010) 3 SCC 690
30 consequential directions relating to interest or cost. It was held
that arbitral tribunals did not have the power to award interest
upon interest or compound interest either for the pre-award
period or for the post-award period.
40. A three-Judge Bench of this Court in Hyder
Consulting (UK) Ltd. Vs. Governor, State of Orissa5, opined that
it was not possible to agree with the conclusion in S.L.
Arora (supra) that Section 31(7) of the 1996 Act does not require
that interest which accrues till the date of the award be included
in the sum from the date of the award for calculating the post-
award interest. Justice Bobde (as His Lordship then was)
authoring the majority opinion was of the view that the
conclusion reached in S.L. Arora (supra) did not seem to be in
consonance with the clear language of Section 31(7) of the 1996
Act. Hyder Consulting (UK) Ltd. (supra) declared that S.L.
Arora (supra) was wrongly decided in that it held that a sum
directed to be paid by an arbitral tribunal and the reference to
the award on the substantive claim did not refer to
5 (2015) 2 SCC 189
31 interest pendente lite awarded on the sum directed to be paid
upon award and that in the absence of any provision of interest
upon interest in the contract, the arbitral tribunal did not have
the power to award interest upon interest or compound interest
either for the pre-award period or for the post-award period. It
has been clarified that the ‘sum’ includes the principal as
adjudged together with the interest granted.
41. A three-Judge Bench of this Court in UHL Power
Company Ltd. Vs. State of Himachal Pradesh6 declared that the
judgment in S.L. Arora (supra) has since been overruled by a
three-Judge Bench of this Court in Hyder Consulting (UK) Ltd.
(supra). The majority view in Hyder Consulting (UK) Ltd. (supra)
is that post-award interest can be granted by an arbitrator on
the interest amount awarded.
42. This view was reiterated by this Court in subsequent
decisions (please see Delhi Airport Metro Express Private Ltd. Vs.
6 (2022) 4 SCC 116
32 Delhi Metro Rail Corporation7 and Morgan Securities and Credits
Private Ltd. Vs. Videocon Industries Limited8).
43. Finally, in S.A. Builders (supra), this Bench after a
thorough analysis of Section 31(7)(a) and Section 31(7)(b) of the
1996 Act came to the following conclusion:
38. Natural corollary to the above analysis would be that the ‘sum’ so awarded by the arbitral tribunal which may include interest from the date when the cause of action arose to the date of the award, would carry further interest of 18 percent from the date of the award to the date of payment unless the arbitral award otherwise directs (referring to the pre 23.10.2015 position). Thus, the legislative intent is that the awarded sum whether inclusive of interest or not, in case included, then from the date of cause of action to the date of award, would carry further interest from the date of the award to the date of payment.
44. It has been held that the sum awarded would mean
the principal amount plus the interest awarded from the date of
cause of action upto the date of the award. The sum awarded in
Section 31(7)(a) would mean principal amount plus the interest
7 (2022) 9 SCC 286 8 (2023) 1 SCC 602
33 awarded. Thereafter, as per Section 31(7)(b) of the 1996 Act, the
sum (principal amount + interest) would carry further interest
at the rate of 2 per cent higher than the current rate of interest
prevalent on the date of the award to the date of payment.
45. Therefore, in view of the clear legal position
delineated as above, impugned judgment of the Division Bench
dated 01.08.2023 cannot be sustained.
46. Thus, having regard to the discussions made above,
impugned judgment and order dated 01.08.2023 passed by the
Division Bench of the High Court is hereby set aside. Civil
appeal is accordingly allowed. However, there shall be no order
as to cost.
………………………………J. [ABHAY S. OKA]
.……………………………J. [UJJAL BHUYAN] NEW DELHI;
MAY 15, 2025.
34
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free