Miss Lucy
← All judgments

M/S.Indian Oil Corporation Ltd vs M/S.Fabtech Works And Constructions

Madras High Court8 November 2019Senthilkumar Ramamoorthy

Ratio decidendi

The rule this decision rests on

A contractual provision styled as "price adjustment" for delay in completion, notwithstanding its label and any express clause disclaiming application of liquidated damages or penalty provisions, constitutes a stipulation by way of compensation for breach within the meaning of Section 74 of the Indian Contract Act, 1872, and therefore requires proof by the party invoking it that actual loss was incurred as a result of the breach, failure of which renders the claim unenforceable. Where parties have agreed by mutual consent to an extension of the completion date through minutes of meeting signed by both parties, the stipulated compensation clause can only be invoked for delays occurring after that extended date, and not for delays occurring before the extended date was agreed upon. A "no claim certificate" submitted by a contractor in a standard format prescribed by the employer, when accompanied by contemporaneous correspondence notifying a claim for payment of deducted amounts, does not constitute an unequivocal acceptance of full and final settlement so as to bar subsequent arbitration of those claims, particularly where the requirement to submit such certificate is a precondition for processing the final bill. The scope of interference with an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 is limited, and an award reasoned and based on discussion and analysis of evidence and contract terms should not be interfered with merely because another plausible view of the contract could have been taken.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

O.P.No.485 of 2014

IN THE HIGH COURT OF JUDICATURE AT MADRAS

Judgment reserved on 31.10.2019 Judgment pronounced on 08.11.2019

CORAM

THE HONOURABLE Mr. JUSTICE SENTHILKUMAR RAMAMOORTHY

O.P. No.485 of 2014

M/s.Indian Oil Corporation Ltd, Rep. by its Deputy General Manager(LPG) Tamil Nadu State Office, No.139, Nungambakkam High Road, Chennai – 600 034. ... Petitioner

Vs.

1.M/s.Fabtech Works and Constructions Plot Nos.H-44/H-43/H-42, M.I.D.C. Additional Murbad, Village: Kudavali, Murbad – 421 401, Via – Kalyan Dist. Thane(M.S).

2.S.Annamalai, Sole Arbitrator, No.139, Nungambakkam High Road, Chennai – 600 034. ... Respondents

Prayer:- Original Petition is filed under Section 34 of the Arbitration and

Conciliation Act, 1996 to set aside the Award dated 15.05.2014 passed by

the 2nd Respondent herein in the un-numbered Arbitration Case.

http://www.judis.nic.in 1 of 26 O.P.No.485 of 2014

For Petitioner : M/s.Mohammed Fayaz Ali

For Respondents : M/s.Gowtham Kumar for R-1

ORDER

The respondent in the Arbitration is the Petitioner herein. The

dispute between the parties arises out of a contract for the supply of steel

plates, fabrication, erection and commissioning of 3X150 T capacity

mounded type pressure vessels for LPG storage with cathodic protection

at the LPG Bottling plant of the Petitioner at Illayangudi, Tamil Nadu. A

letter of intent dated 27.11.2007 was issued in favour of the first

Respondent in relation to the above mentioned work at the lump sum

price of Rs.4,68,45,000/- inclusive of all taxes and duties. The entire

work was required to be completed within a period of 12 months from the

date of handing over of the site. Pursuant to the letter of intent, a

detailed work order was issued to the first Respondent. The admitted

position is that the site was handed over on 10.12.2007. Thereafter, the

execution of work is stated to have been delayed by various factors such

as delay in approval of designs and drawings by the Third Party Inspection

Agency, namely Projects and Development India Limited(PDIL), changes

in the orientation of the mounds which necessitated revision in the

designs and drawings, heavy rainfall, delay in supply of steel, etc.

According to the first Respondent, the work was completed on http://www.judis.nic.in 2 of 26 O.P.No.485 of 2014

26.12.2009, as certified by PDIL, whereas, according to the Petitioner, the

work was completed on 30.04.2010.

2.It is also the admitted position that the Petitioner made

deductions from the running account bills of the first Respondent. Such

deductions were made from amounts due and payable towards RA Bill

No.3 dated 28.03.2009, RA Bill No.4 dated 02.05.2009, RA Bill No.5 dated

29.10.2009, RA Bill No.6 dated 15.11.2009, RA Bill No.7 dated

04.02.2010, RA Bill No.8 dated 23.06.2010 and RA Bill No.9 dated

28.09.2010. By making the said deductions, an aggregate sum of

Rs.46,84,500/-, which constitutes 10% of the total lump sum contract

price, was deducted. Therefore, a dispute arose between the parties and

the said dispute was referred to arbitration. In the Arbitration

Proceedings, the first Respondent herein claimed the deducted sum of

Rs.46,84,500/- and a further sum of Rs.5,00,000/- towards expenses

incurred for commissioning the work along with interest thereon. Other

claims, such as a sum of Rs.93,69,000/- towards loss of reputation and

goodwill, were also made and, in the aggregate, a sum of

Rs.2,55,33,436/- was claimed. In the said Proceeding, the Petitioner filed

an application under Section 16 of the Arbitration and Conciliation

Act,1996(the Arbitration Act) challenging the jurisdiction of the Arbitral

Tribunal and the said application was rejected by Order dated 04.07.2013.

http://www.judis.nic.in 3 of 26 O.P.No.485 of 2014

Thereafter, the Petitioner filed its reply statement before the Arbitral

Tribunal, wherein it refuted the claims of the first Respondent herein and

prayed that the said claims be rejected. The learned Arbitrator framed

three issues by considering the pleadings of the parties. In substance,

these issues are: 1) Whether the invocation of the price adjustment

clause by the Petitioner herein is justifiable? 2) Whether the first

Respondent herein committed a breach of Contract by delaying the

completion of the project? and 3) Whether the first Respondent herein is

entitled to the relief as claimed? Both parties adduced oral and

documentary evidence: the first Respondent herein exhibited 18

documents as Exs.C-1 to C-18 and the Petitioner herein exhibited 13

documents as Exs.R1 to R-13. Upon consideration of the above, the

learned Arbitrator by Arbitral Award dated 15.05.2014 (the Award)

directed the Petitioner herein to pay a sum of Rs.46,84,500/- to the first

Respondent herein immediately. The said Award is impugned in this

Petition.

3.I heard the learned counsel for the Petitioner and the

learned counsel for the first Respondent.

4.The learned counsel for the Petitioner submitted that the

main question that arises for consideration is with regard to the

http://www.judis.nic.in 4 of 26 O.P.No.485 of 2014

entitlement of the Petitioner to make deductions as per the price

adjustment clause. According to the learned counsel for the Petitioner,

the contract between the parties provides for price adjustment in the

event of delay by the first Respondent/Contractor. He further submitted

that the said clause is neither a liquidated damages clause nor a penalty

clause. In order to substantiate this submission, he referred to the said

price adjustment clause, which reads inter alia as under:

“4.4.0.0 PRICE ADJUSTMENT FOR DELAY IN COMPLETION

4.4.1.0 The contractual price payable shall be subject to adjustment by way of discount hereinafter specified, if the Unit(s) are mechanically completed or the contractual works are finally completed, subsequent to the date of Mechanical Completion/final completion specified in the Progress Schedule.

4.4.2.0 If Mechanical Completion of the Unit(s)/final completion of the works is not achieved by the last date of Mechanical Completion of the Unit(s)/final completion of the works specified in the Progress Schedule (hereinafter referred to as the “starting date for discount calculation”), the OWNER shall be entitled to adjustment by way of discount in time price of the works and services in a sum equivalent to the percent of the total contract value as specified below namely:-

(i)For Mechanical Completion of the Unit(s)/final completion of time works achieved within (one) week of the starting date for discount calculation – ½% of the total contract value.

(ii)For Mechanical Completion of the Unit(s)/final

http://www.judis.nic.in

5 of 26 O.P.No.485 of 2014

completion of time works achieved within 2 (two) weeks of the starting date for discount calculation – 1% of the total contract value.

(iii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 3 (three) weeks of the starting date for discount calculation – 1½% of the total contract value.

(iv)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 4(four) weeks of the starting date for discount calculation – 2% of the total contract value.

(v)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 5(five) weeks of the starting date for discount calculation – 2½% of the total contract value.

(vi)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 6(six) weeks of the starting date for discount calculation – 3% of the total contract value.

(vii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 7(seven) weeks of the starting date for discount calculation – 3½% of the total contract value.

(viii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 8(eight) weeks of the starting date for discount calculation – 4% of the total contract value.

(ix)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 9(nine) weeks of

http://www.judis.nic.in 6 of 26 O.P.No.485 of 2014

the starting date for discount calculation – 4½% of the total contract value.

(x)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 10(ten) weeks of the starting date for discount calculation – 5% of the total contract value.

(xi)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 11(eleven) weeks of the starting date for discount calculation – 5½% of the total contract value.

(xii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 12(twelve) weeks of the starting date for discount calculation – 6% of the total contract value.

(xiii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 13(thirteen) weeks of the starting date for discount calculation – 6½% of the total contract value.

(xiv)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 14(fourteen) weeks of the starting date for discount calculation – 7% of the total contract value.

(xv)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 15(fifteen) weeks of the starting date for discount calculation – 7½% of the total contract value.

(xvi)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 16(sixteen)

http://www.judis.nic.in 7 of 26 O.P.No.485 of 2014

weeks of the starting date for discount calculation – 8% of the total contract value.

(xvii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 17(seventeen) weeks of the starting date for discount calculation – 8½% of the total contract value.

(xviii)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 18(eighteen) weeks of the starting date for discount calculation – 9% of the total contract value.

(xix)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 19(nineteen) weeks of the starting date for discount calculation – 9½% of the total contract value.

(xx)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 20(twenty) weeks of the starting date for discount calculation – 10% of the total contract value.

(xxi)For Mechanical Completion of the Unit(s)/final completion of time works achieved within 21(twenty one) weeks of the starting date for discount calculation – 10½% of the total contract value.

4.4.2.1 Time starting date for discount calculation shall be subject to variation upon extension of time date for Mechanical Completion of the Unit(s)/final completion of the works with a view that upon any such extension there shall be an equivalent extension in the starting date for discount calculation under Clause 4.4.2.0 thereof.

http://www.judis.nic.in 8 of 26 O.P.No.485 of 2014

4.4.2.2 It is specifically acknowledged that the provisions of Clause 4.4.2.0 constitute purely a provision for price adjustment and/or fixation and are not be understood or construed as a provision for liquidated damages or penalty under Section 74 of the Indian Contract Act or otherwise.”

5. With reference to the delay, he submitted that the contract

provides that final completion should be done within 12 months from the

date when the site was handed over. In this case, the site was admittedly

handed over on 10.12.2007 and, therefore, the work should have been

completed on or before 09.12.2008. Instead, he submitted that the first

Respondent herein, by letter dated 28.02.2009(Ex.C-10), requested for

an extension of time up to 09.06.2009 by citing several reasons as set out

in the said letter. He further submitted that in response to the request for

extension of time, at the minutes of meeting(Ex.R-8) held on 31.07.2009,

it was recorded that the first Respondent confirmed that the entire work

would be completed by 30.09.2009. Thereafter, he pointed out that no

further extensions were agreed to by the parties. Although the first

Respondent had confirmed that it would complete work on or before

30.09.2009, he submitted that admittedly work was not completed by

30.09.2009 and was, in fact, completed only on 30.04.2010. In this

regard, he further pointed out that the certificate that was issued by the

PDIL on 26.12.2009 (Ex.C-12) is not a completion certificate under the

contract. Instead, it is merely a certificate issued by PDIL after inspecting http://www.judis.nic.in 9 of 26 O.P.No.485 of 2014

the 3x150 MT mounded LPG storage bullets. Therefore, he pointed out

that there is a delay of 7 months from the last extended date for

completion up to the date of actual completion. Consequently, he

submitted that the Petitioner was entitled to resort to price adjustment as

per the contract.

6.In response to a question as to when deductions were made

towards price adjustment, he submitted that the deductions were made

from RA Bills 3 to 9 which were submitted between 28.03.2009 and

28.09.2010. He further confirmed that the said details are contained in

the statement of claim at page No.276 for Volume – I. In effect, he

submitted that the period of delay is about 28 weeks, whereas deductions

were made of the stipulated maximum of 10% of the contract price, which

is liable to be deducted for a cumulative delay of 20 weeks.

7.In these facts and circumstances, he submitted that the

Arbitral Tribunal completely disregarded the contract and, in particular, the

price adjustment clause, by allowing the claim to the extent of

Rs.46,84,500/-. In support of this submission, he referred to the Award.

In specific, he referred to Page No.333 of Volume – I, wherein the Arbitral

Tribunal referred to 3 letters from the first Respondent seeking extension

of time. In this connection, he pointed out that the letters dated

http://www.judis.nic.in 10 of 26 O.P.No.485 of 2014

19.07.2010 and 20.09.2010 were issued after the completion of work on

30.04.2010 and, therefore, the said letters cannot be treated as letters

seeking extension of time. However, the learned Arbitrator relied on such

irrelevant evidence and held that the resort to the price adjustment clause

by the Petitioner herein is not justifiable. He further pointed out that the

Arbitral Tribunal also concluded that the first Respondent committed

breach of contract by delaying the completion of the project beyond the

stipulated time. By referring to the said finding on issue No.2, he

submitted that the Arbitral Tribunal committed a patent illegality by,

nonetheless, directing the Petitioner to pay a sum of Rs.46,85,500/-.

8.In order to substantiate the above submissions, he referred

to and relied upon the judgments which are set out below along with

context and principle:

(i)Cauvery Coffee Traders, Mangalore vs. Hornor Resources

(International) Company Ltd, (2011) 10 SCC 420, wherein, at

Paragraphs 31 to 35, the Hon'ble Supreme Court held that a party that

received a particular sum as full and final settlement cannot do a

complete somersault thereafter. It was further held therein that a person

cannot be permitted to approbate and reprobate and that the doctrine of

election is based on the rule of estoppel.

http://www.judis.nic.in 11 of 26 O.P.No.485 of 2014

(ii) Indian Oil Corporation Ltd. vs. Man Industries(India) Ltd.

(the IOCL case) 2017 SCC Online Del 6452, wherein the Delhi High

Court set aside the Arbitral Award because the contractual clause with

regard to price adjustment was overlooked by the Arbitral Tribunal.

(iii)Chennai Petroleum Corporation Limited vs. HES Infro

Private Ltd (the CPCL case) (2018) 3 CTC 764, wherein this Court

held that the no claim certificate is binding in the absence of averments or

findings that it was obtained by force or coercion. It was further held in

the said judgment that the Award passed in spite of the no claim

certificate and contractual clauses prohibiting the claims is against public

policy and suffers from patent illegality.

(iv)Oil & Natural Gas Corporation Ltd vs. SAW Pipes Ltd,

(2003) 5 SCC 705 (the ONGC case), wherein the Hon'ble Supreme

Court held that an award, which is contrary to substantive provisions of

law or the provisions of the Arbitration and Conciliation Act or against the

terms of the contract, would be patently illegal and could be interfered

with under Section 34 of the Arbitration and Conciliation Act.

9.In response and to the contrary, the learned counsel for the

first Respondent made submissions. He opened by pointing out that the

primary obligation of the Petitioner, namely, to hand over the site was not

fulfilled within time and the site was handed over only on 20.12.2007. He,

http://www.judis.nic.in 12 of 26 O.P.No.485 of 2014

thereafter, referred to the fact that the designs and drawings were not

approved in time, the mounds were re-oriented thereby entailing

modification of the designs and drawings, which were eventually

approved by PDIL only on 23.06.2008. In light of the delay in handing

over the site and the delayed approval of designs and drawings, he

submitted that it was just and necessary to re-fix the time for completion

of work and that the first Respondent was entitled to such extension.

Therefore, he submitted that extension of time was requested for by the

first Respondent both at meetings between the Petitioner and the first

Respondent and also by issuing letters requesting for extension of time.

By way of illustration, he submitted that extension of time was requested

for at the meeting held on 23.07.2008(Ex.R-3) and also by letter dated

28.07.2009(Ex.C-10). He further submitted that, in the meeting held on

29.04.2009(Ex.R-5), it was agreed that final completion would be done by

30.09.2009. He also referred to the minutes of the subsequent meeting

held on 31.07.2009 at Page 105 of Volume – II(Ex.R-8) in this connection.

He next referred to the letter dated 30.11.2009(Ex.C-11), wherein the

first Respondent informed the Petitioner that mechanical works were

totally completed for the three bullets and that the total site would be

wound up within 10 to 15 days. In order to substantiate the fact that

mechanical completion took place on 26.12.2009, he referred to the

certificate of PDIL at Page 35 of Volume – II(Ex.C-12). He, thereafter,

http://www.judis.nic.in 13 of 26 O.P.No.485 of 2014

referred to the letter dated 19.07.2010 (Ex.C-13), wherein the first

Respondent stated that the job had been completed on 26.12.2009 and

had provided reasons for delay and requested the Petitioner to refrain

from levying liquidated damages. He, thereafter, referred to the letter

dated 28.09.2010 (Ex. C-14) enclosing the final bill and pointed out as to

how the first Respondent did not have any choice or option with regard to

the submission of the “no claim certificate” on 26.10.2010 in as much as

it was a pre-condition for the processing of the final bill. In this regard,

he referred to the said “no claim certificate” at Page 286 of Volume – I

and contended that the said “no claim certificate” is not an unequivocal

acknowledgment of full and final payment so as to constitute accord and

satisfaction. He submitted that payment of the final bill was made on

19.11.2010 after deducting the aggregate sum of Rs.46,84,500/- as per

details set out in the statement of claim at Page No.276 of Volume No.1.

10.With regard to the deductions made by the Petitioner, he

submitted that both parties understood such deductions to be by way of

liquidated damages. In order to substantiate this submission, he referred

to the e-mail of 29.07.2010 at page 112 of Volume – II, wherein it is

expressly stated that “LD as applicable may please be deducted from the

RA Bill.” He also referred to the e-mail of 08.10.2010 in respect of the

final bill wherein it is stated that “we are going ahead with processing of

http://www.judis.nic.in 14 of 26 O.P.No.485 of 2014

your final bill and applicable LD would be deducted”. In order to

substantiate that the “no claim certificate” was not unequivocal, he

referred to the reply to the Section 16 application and the order thereon

dated 04.07.2013, wherein the contention of the first Respondent, in this

regard, was accepted.

11.With specific reference to price adjustment, he pointed out

that Clause 4.4.2.1 provides that if extension of time is granted, time

should run from the last date of extension and not from the original

completion date. He, thereafter, referred to the Award and pointed out as

to how the learned Arbitrator entered the definitive factual finding that the

delay of 197 days is attributable to the Petitioner. By referring to the said

finding of the Arbitral Tribunal, he pointed out that the Petitioner has

failed to make out a case for interference under Section 34 of the

Arbitration and Conciliation Act. In order to substantiate this submission,

he referred to the judgments which are set out below along with context

and principle:

(i)Indian Oil Corporation vs. Lloyds Steel Industries Ltd,

2007 SCC Online Del 1169, wherein, at Paragraph 44, the Delhi High

Court held that time would not be of the essence of the contract when

there is no specific provision to that effect. In Paragraph 51 of the same

http://www.judis.nic.in 15 of 26 O.P.No.485 of 2014

judgment, it was further held that it is necessary to prove that loss was

incurred before claiming liquidated damages.

(ii)The State of Jharkhand and Others vs. M/s.HSS Integrated

SDN and another in Special Leave To Appeal(C) No.13117 of

2019, wherein, at paragraph 6.4, the Hon'ble Supreme Court held that a

plausible view by the Arbitral Tribunal should not be interfered with under

Section 34 of the Arbitration Act.

(iii)Wishwa Mittar Bajaj and Sons vs. Shipra Estate Lted and

Jaikishan Estate Developers Private Limited, 2018 SCC Online Del

12918, wherein, at Paragraphs 32 and 34, the Hon'ble Supreme Court

held that the scope of interference with an arbitral award is limited and

that such an award should not be interfered with if it is reasoned and

based on a discussion and analysis of the evidence.

(iv)Bharat Coking Coal Ltd. vs. Annapurna Construction(the

Bharat Coking Coal case), (2003) 8 SCC 154, wherein, at Paragraph

9, the Hon'ble Supreme Court held that unless a party states

unequivocally that it would not raise any further claim such a party cannot

be held to be precluded from raising further claims.

(v) Chairman and MD, NTPC Ltd. vs. Reshmi Constructions,

Builders & Contractors (the NTPC case), (2004) 2 SCC 663,

wherein, at Paragraph 26 and 27, the Hon'ble Supreme Court took judicial

notice of the fact that the final bill is not ordinarily processed to release

http://www.judis.nic.in 16 of 26 O.P.No.485 of 2014

the money unless a no demand certificate is signed and that necessity

knows no law.

(vi)National Highway Authority of India vs. Gammon India

Limited, 2014 SCC Online Cal 17407, wherein, at Paragraph 11 to 22,

the limited scope of interference with an arbitral award was discussed

especially in the context of a plausible view by the Arbitral Tribunal.

(vii)M/s.L.G. Electronics India(p) Ltd. vs. Dinesh Kalra, 2018

SCC Online Del 8367, wherein, at Paragraph 15 to 22, once again, the

limited scope of interference with an arbitral award was discussed.

12.By way of rejoinder, the learned counsel for the Petitioner

pointed out that all the reasons for delay and for seeking extension of

time were mentioned in the letter dated 28.02.2009 wherein extension

was requested until 30.06.2009. In fact, he pointed out that no additional

reason was cited in the letter dated 19.10.2010. Accordingly, he

submitted that there is no justification at all for not completing the work

within the extended completion date of 30.09.2009 and, therefore, the

first Respondent is completely responsible for the delay of 7 months

beyond 30.09.2009 up to 30.04.2010. In these facts and circumstances,

the learned counsel for the Petitioner concluded by reiterating that the

Arbitral Tribunal disregarded the critical clauses of the contract such as

the price adjustment clause and relied upon irrelevant evidence such as

http://www.judis.nic.in 17 of 26 O.P.No.485 of 2014

letters written after completion of work to conclude that the Petitioner was

not justified in resorting to price adjustment. He also circulated written

submissions and annexed the judgment in Bank of India vs. K.

Mohandas (2009) 5 SCC 313 for the proposition that contractual

interpretation should be based on the text of the contract and not on what

parties say, in that regard, subsequently. He also relied on the order in

Vedanta Limited vs. SGS India Private Limited, O.P. No.1115 of

2018, for the principle that an arbitrator cannot decide on the basis of

equity and good conscience unless expressly authorised to do so under

the contract.

13.The records were examined and the oral and written

submissions of the learned counsel for both sides were considered

carefully. The preliminary question to be considered is whether the claims

made by the first Respondent are liable to be rejected on account of the

“no claim certificate” dated 26.10.2010. In order to answer this question,

the said certificate should be examined. On perusal thereof, it is clear that

the said certificate is in a standard format, which appears to have been

prescribed by the Petitioner. Therefore, the question arises as to whether

this “no claim certificate” is liable to be reckoned as an unequivocal

acceptance of the payment against the final bill as full and final

settlement. The answer is obvious upon examining the letter dated

http://www.judis.nic.in 18 of 26 O.P.No.485 of 2014

28.09.2010 (Ex.C-14) enclosing the final bill. By this letter, the first

Respondent called upon the Petitioner to release the provisional liquidated

damages aggregating to Rs.42,02,829/-. This request would qualify as a

notified claim for purposes of Clause 6.2.2.0 of the contract. When viewed

in this factual context, the “no claim certificate” certainly does not qualify

as an unequivocal acceptance of full and final settlement as per the law

laid down both in the Bharat Coking case and the NTPC case and in

contrast to the CPCL case.

14.This leads to the principal question that is required to be

decided, namely, whether the Petitioner is entitled to make deductions

from the running account bills of the first Respondent. The price

adjustment clause, which is extracted supra, is linked to the completion

of works specified in the progress schedule. The progress schedule is a

defined term under the contract and is required to be submitted by the

contractor or if the contractor fails to submit the same, it is required to be

prepared by the Engineer-in-charge. In this case, the original completion

date was 12 months from the date of hand over of the site. However,

there was admitted delay both in handing over the site and in approval of

designs and drawings. Accordingly, requests were made for extension of

time and it is clear from the minutes of meeting held on 31.07.2009 that

the parties agreed to an extension of time up to 30.09.2009. In fact, it is

http://www.judis.nic.in 19 of 26 O.P.No.485 of 2014

evident from the said minutes of meeting that the decisions taken at the

said meeting have been agreed to by both parties by signing the minutes

of meeting. It is also evident that a completion schedule chart was

annexed to the minutes of meeting and this completion schedule chart

was also signed by both parties. The entitlement to make deductions

should be viewed against this factual backdrop. The completion schedule

chart annexed to the minutes of the meeting held on 31.07.2009 would

qualify as the progress schedule as per clause 4.4 of the GCC. In effect,

the last date specified therein, namely, 30.09.2009, would be the starting

date for discount calculation as per clause 4.4.2.0. This becomes clear on

examining clause 4.4.2.1. However, in this case, deductions were made

not from 01.10.2009 but from 28.03.2009 onwards, as evidenced by the

table in the statement of claim at Page 276 Volume – I, which is not

refuted by the learned counsel for the Petitioner. Therefore, it is clear

that deductions were not made in accordance with the price adjustment

clause. In addition, it is the admitted position that the first Respondent

was not notified about resorting to price adjustment. Although the price

adjustment clause does not specifically provide for the issuance of a

notice, the requirement of notification is implicit for the reason that price

adjustment cannot be resorted to unless the delay in completion of work,

as per the progress schedule, is attributable to the contractor/first

Respondent. In this case, as stated above, the parties agreed to an

http://www.judis.nic.in 20 of 26 O.P.No.485 of 2014

extension of time up to 30.09.2009. The Arbitral Tribunal referred to the

price adjustment clause and the fact that the price adjustment clause

could be operated only with reference to the progress schedule. After

adverting to the said clause, the Arbitral Tribunal also recorded that the

price adjustment clause was resorted to without reference to the minutes

of meeting and the progress schedule agreed to therein. On that basis,

the Arbitral Tribunal held that the resort to the price adjustment clause is

not justifiable. In view of the above analysis and the fact that the price

adjustment clause should have been resorted to only after 30.09.2009, I

find that the conclusions of the Arbitral Tribunal are in accordance with the

contract and, therefore, interference is not warranted.

15.In addition, the larger legal question as to whether the

price adjustment clause is a stipulated compensation or liquidated

damages clause should be examined because it would have a material

bearing on this case de hors the factual findings on the manner of resort

to the price adjustment clause being unjustified. In this regard, it is

pertinent to refer to Section 74 of the Contract Act, 1872, which reads, in

relevant part, as under:

"74. Compensation for breach of contract where penalty stipulated for –

When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any http://www.judis.nic.in 21 of 26 O.P.No.485 of 2014

other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for...."

16.A plain reading of Section 74 evidences that the Contract

Act provides for two categories of stipulations that could operate in case

of breach. The first category is a sum named in the contract as the

amount to be paid in case of breach, which could be described as

stipulated compensation, and the second category is any other stipulation

by way of penalty. Thus, Section 74 does not use the term "liquidated

damages". It is the admitted position, in this case, that there is no clause

in respect of compensation for delay except the price adjustment clause.

Moreover, paragraph 11 of reply statement before the Arbitral Tribunal,

the Petitioner stated as follows:

“The deduction of Rs.46,84,500/- from the final bill as stated above is not by way of liquidated damages but by way of price adjustment for delay in completion under Clause 4.4.0.0. The purpose behind price adjustment is to safe guard the OWNER from the loss of business due to delay in completion of the work and since the CONTRACTOR under commercial agreement has agreed for such a condition and http://www.judis.nic.in 22 of 26 O.P.No.485 of 2014

having performed the contract and acted upon it, the OWNER is entitled to invoke Clause 4.4.0.0 for price adjustment due to delay.”

17.From the above, it is clear that the price adjustment clause

is intended to provide compensation for loss of business due to delay in

completion of work. In effect, it is stipulated compensation for delay that

is attributable to the contractor. In this connection, it may be further

noted that this is not an incentive-based clause whereby the contractor

could receive additional payment for accelerated completion and, in the

converse situation, should provide a discount in the event of delay. On the

other hand, it is clearly a breach-based compensation clause. Once there

is a contractual stipulation by way of compensation for delay,

notwithstanding the terminology or label used to describe it and the

stipulation in clause 4.4.2.2. of the contract that it is not by way of

liquidated damages or penalty, it amounts to a stipulation by way of

compensation as per Section 74 of the Contract Act. In this regard, in

Dunlop Pneumatic Tyre Company Limited v. New Garage and

Motor Company Limited [1915] A.C. 79 (HL)(the Dunlop

Pneumatic case), the House of Lords held, in the speech of Lord

Dunedin, at page 86 of the Report, that "though the parties to a contract

who use the words "penalty" or "liquidated damages" may prima facie be

supposed to mean what they say, yet the expression used is not

http://www.judis.nic.in 23 of 26 O.P.No.485 of 2014

conclusive. The Court must find out whether the payment stipulated is in

truth a penalty or liquidated damages." The law, in India, is the same on

this subject. As stated earlier, Section 74 of the Contract Act does not

refer specifically to liquidated damages. On the other hand, it refers to a

stipulation by way of compensation. Therefore, Clause 4.4 of the GCC

would qualify as a stipulation by way of compensation. Once it qualifies

as a stipulation by way of compensation, it became necessary for the

Petitioner to prove that loss was incurred as a result of breach, although it

may not be necessary to prove the exact quantum of loss, if it is difficult

or impossible to prove the same. These are the settled principles as per

the decisions of the Hon'ble Supreme Court in Fateh Chand vs.

Balkishan Dass, (1964) 1 SCR 515, Maula Bux vs. Union of India,

(1969) 2 SCC 554, Oil & Natural Gas Corporation Ltd vs. Saw

Pipes Ltd,(2003) 5 SCC 705 and Kailash Nath vs. DDA(the Kailash

Nath case)(2015) 4 SCC 136. It is sufficient to refer to the Kailash

Nath case, in specific, wherein, at paragraph 43.3, it was held “since

Section 74 awards reasonable compensation for damage or loss caused by

a breach of contract, damage or loss is a sine qua non for the applicability

of the section.” The Petitioner cannot circumvent the legal regime

governing the imposition of liquidated damages merely by using the label,

price adjustment. Therefore, in the admitted absence of proof of the

factum of loss, it would be an injuria sine damnum scenario and the

http://www.judis.nic.in 24 of 26 O.P.No.485 of 2014

Petitioner is not entitled to compensation by way of price adjustment.

Therefore, I do not find any reason to interfere with the Arbitral Award.

18.In the result, the Petition to set aside the Arbitral Award is

dismissed.

08.11.2019 Speaking/non speaking order Index: Yes Internet: Yes

http://www.judis.nic.in 25 of 26 O.P.No.485 of 2014

SENTHILKUMAR RAMAMOORTHY, J.

rrg

Pre Delivery order in O.P.No.485 of 2014

08.11.2019

http://www.judis.nic.in 26 of 26

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free