M/S. Delhi Airtech Servies Pvt. Ltd. vs State Of U.P
- SCC(2024) 17 SCC 610
- Neutral2022 INSC 1084
- SCR[2022] 13 SCR 1084
Ratio decidendi
The rule this decision rests on
1. Section 11A of the Land Acquisition Act, 1894, which provides that acquisition proceedings shall lapse if an award is not passed within two years from the date of publication of the declaration under Section 6, is applicable to acquisitions initiated under the urgency provisions of Section 17(1) of the Act. 2. The requirement to tender and pay eighty per centum of estimated compensation before taking possession, as mandated by Section 17(3A), is mandatory and must be complied with before possession can legally be taken and the land can vest absolutely in the Government; absence of such compliance means the possession is not taken in accordance with law and vesting is not absolute. 3. When Section 17(3A) of the Act has been complied with and eighty per centum of estimated compensation has been tendered and paid before possession is taken, the land vests absolutely in the Government notwithstanding the failure to pass an award within two years, and Section 11A will not apply to render the entire proceedings for acquisition lapsed; the land loser's remedy in such circumstances is to enforce the passing of an award and recovery of the balance compensation. 4. When the pre-requisite condition of tendering and paying eighty per centum of estimated compensation before taking possession has not been complied with, the acquisition loses its character as being under Section 17, and if an award is not passed within two years from the date of declaration, the acquisition will lapse; however, this benefit is available only to be invoked by the land loser and not by the acquiring authority or beneficiary. 5. The decision in Satendra Prasad Jain v. State of U.P. does not lay down the ratio that acquisition does not lapse under any circumstance if the urgency provision under Section 17 is invoked, but only disapproves applying Section 11A and 17(3A) against the land loser; it does not prevent the land loser from invoking these provisions to protect their rights.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
M/s Delhi Airtech Services Pvt. Ltd & Anr. .… Appellant(s)
Versus
State of U.P & Anr. …. Respondent(s)
JUDGMENT
A.S. BOPANNA, J.
1. This appeal has a chequered history. The appeal was
heard by a Bench consisting of two Hon’ble Judges (Justice
A.K. Ganguly and Justice Swatanter Kumar) and was decided
by the Judgment dated 18.08.2011 with divergent opinion. In
the process, after consideration, Hon’ble Justice A.K. Ganguly
Signature Not Verified arrived at the conclusion that taking over possession of the Digitally signed by DEEPAK SINGH Date: 2022.10.14 14:40:01 IST Reason: land without complying the requirement under Section 17(3A)
of the Land Acquisition Act, 1894 (for short ‘Act, 1894’) is
1 clearly illegal and in violation of the statutory provision which
automatically violates the constitutional guarantee under
Article 300A of the Constitution. However, on taking note
that the land had been utilised and developed by the
beneficiary of the acquisition, had allowed the retention of the
land by directing to pass an award by construing the date of
filing the writ petition i.e. 01.03.2006 as the date of Section 4
notification to reckon the market value as against the actual
date of notification. Hence allowed the appeal in those terms.
2. On the other hand, Hon’ble Justice Swatanter Kumar,
however, disagreed with the said conclusion and for the
separate reasons assigned by the learned Judge, arrived at
the conclusion that Section 11A of Act, 1894 has no
application to acquisition under Section 17 of Act, 1894. It
was further held that the default in complying with Section
17(3A) of Act, 1894 does not invalidate or vitiate the entire
acquisition proceedings. The learned Judge while deciding so
had however misconstrued that 80% of the estimated value in
terms of subsection (3A) of Section 17 had been paid to the
land loser and in that context held that the interest provided
in terms of Section 34 will be payable. In that view, the
2 learned Judge ordered dismissal of the appeal in terms of the
directions issued.
3. In that backdrop, in view of the divergence of opinion
between the learned Judges, they had ordered the matter to
be placed before Hon’ble the Chief Justice of India for
reference to a larger Bench to resolve the conflict. It is in that
circumstance Hon’ble the Chief Justice has ordered the
matter to be placed before a Bench consisting of three Judges.
However, no specific question has been formulated and
referred for decision by a threemember Bench. Hence, we
have heard the matter based on the factual aspects involved
in this case denovo, so as to determine the legal aspects
which touch upon the same.
4. It would therefore be necessary for us to at the outset
take note of the factual matrix involved in this case. The New
Okhla Industrial Development Authority (NOIDA) –
Respondent No.2 was to implement a planned Industrial
layout in Gautam Budh Nagar District for which purpose the
requisite land was to be acquired. The project was envisaged
by the State of U.P–Respondent No.1 as a part of planned
Industrial Development. Hence, Respondent No.1 being the
appropriate Government, issued the Notification dated
3 17.04.2002 invoking the special power due to urgency. The
Notification was therefore issued under Section 4(1) read with
Section 17(1) and (4) of Act, 1894, whereby the requirement of
procedure under Section 5A of the Act, 1894 was dispensed.
Pursuant thereto, the declaration under Section 6 of the Act,
1894 was notified and published on 22.08.2002 declaring that
the area was required by the Government for planned
industrial development. It was also stated that after the
expiry of 15 days from the date of publication of notification
under subsection (1) of Section 9 of the Act, 1894, possession
of the acquired land will be taken.
5. In the large extents of land that was notified, an extent
measuring 2061/30 Bighas situated in village Haldauni,
Tehsil and Pargana Dadri, District Gautam Budh Nagar, an
‘Abadi’ land was also included. The Appellant, a company
incorporated under the provisions of the Companies Act, 1956
claims to be the owner of the said small extent of land. The
Appellant alleges that they were not served with the notice
contemplated under Section 9(1) of Act, 1894. However, it is
not disputed that possession was nevertheless taken on
04.02.2003. But the grievance raised by the Appellant is that
4 neither the initial requirement of tendering and paying 80% of
the estimated compensation contemplated under subsection
(3A) to Section 17 of Act, 1894 was complied nor was the
requirement of Section 11A of the Act, 1894 to pass the award
within two years from the date of declaration under Section 6
of Act, 1894 complied. In that view, the Appellant filed the
writ petition on 01.03.2006 since more than three and half
years had elapsed and neither of the provisions had been
complied. The appellant therefore contended that the
acquisition in so far as the land belonging to the Appellant
has lapsed and the same should revert to the Appellant.
6. The High Court having considered the matter was of
the opinion that Section 11A of Act, 1894 is not attracted to
the proceedings for acquisition in exercise of the power under
Section 17 of Act, 1894. In that regard, the High Court relied
on the decision of this Court in Satendra Prasad Jain Vs.
State of U.P (1993) 4 SCC 369 and dismissed the writ
petition by order dated 28.08.2006, which has given rise to
the above appeal which was earlier heard by a Bench
consisting of two Hon’ble Judges who have differed as noted
supra. While taking note of the decision in Satendra Prasad
5 Jain, rendered by a Bench of three Hon’ble Judges, Justice
A.K. Ganguly has found it to be subsilentio and per incuriam
in the face of the provision contained in the statute. Justice
Swatanter Kumar, the other Hon’ble Judge however relied on
the decision in Satendra Prasad Jain (supra) holding that
compliance with Section 17(3A) of the Act, 1894 is not
mandatory. Hence even in the circumstance of non
compliance, the benefit of interest as provided in Section 34 of
the Act, 1894 was held as the entitlement. Section 11A of Act,
1894 was also held not applicable to the acquisition under
Section 17 of Act, 1894. Though detailed reasons have been
tendered by both the learned Judges for their respective
opinion and has also been referred to by the learned Senior
Counsel for the parties, we do not propose to go into the same
since the entire matter has been placed before us and the
case put forth by the parties is to be independently examined
by us.
7. In the above background we have heard Shri Sudhir
Chandra, learned senior counsel for the appellant, Shri
Ravindra Kumar, learned senior counsel for the Respondent
No.1, Shri Ravindra Raizada, learned senior counsel for
6 Respondent No.2, exhaustively and have perused the appeal
papers.
8. In the light of the contentions urged, the following
questions arise for our consideration.
a. Is the requirement to tender payment of 80% of the estimated compensation as contemplated under subsection(3A) to Section 17 of Act, 1894, mandatory to ensure absolute vesting of the notified land.
b. Whether the requirement to pass the award within the time frame contemplated under Section 11A applicable to the acquisition notified under Section 17 of Act, 1894.
c. Can the case in Satendra Prasad Jain (supra) be considered as a decision laying down ratio decidendi on the above questions?
9. In order to decide the scope and ambit of the
provisions under consideration it would be appropriate to
reproduce Section 11A and Section 17 of the Act, 1894 in its
entirety and keep the same in perspective. Needless to
mention that if the plain meaning of the provision does not
admit of any ambiguity no other external aid will be necessary
to interpret the provision except to give it the plain meaning.
The relevant provision read as hereunder:
7
“Section 11A Period within which an award shall be made (1) The Collector shall make an award under section 11 within a period of two years from the date of the publication of the declaration and if no award is made within that period, the entire proceeding for the acquisition of the land shall lapse:
Provided that in a case where the said declaration has been published before the commencement of the Land Acquisition (Amendment) Act, 1984, the award shall be made within a period of two years from such commencement.
Explanation In computing the period of two years referred to in this section, the period during which any action or proceeding to be taken in pursuance of the said declaration is stayed by an order of a Court shall be excluded.” “Section 17 Special powers in case of urgency – (1) In cases of urgency whenever the [appropriate Government], so directs, the Collector, though no such award has been made, may, on the expiration of fifteen days from the publication of the notice mentioned in section 9, subsection (1), [take possession of any land needed for a public purpose]. Such land shall thereupon [vest absolutely in the [Government], free from all encumbrances.
(2) Whenever, owing to any sudden change in the channel of any navigable river or other unforeseen emergency, it becomes necessary for any Railway Administration to acquire the immediate possession of any land for the maintenance of their traffic or for the purpose of making thereon a riverside or ghat station, or of providing convenient connection with or accesses to any such station, [or the appropriate Government considers it necessary to acquire the immediate possession of any land for the purpose of maintaining any structure or system
8 pertaining to irrigation, water supply, drainage, road communication or electricity,] the Collector may, immediately after the publication of the notice mentioned in subsection (1) and with the previous sanction of the [appropriate Government], enter upon and take possession of such land, which shall thereupon [vest absolutely in the [Government]] free from all encumbrances:
Provided that the Collector shall not take possession of any building or part of a building under this subsection without giving to the occupier thereof at least fortyeight hours’ notice of his intention so to do, or such longer notice as may be reasonably sufficient to enable such occupier to remove his movable property from such building without unnecessary inconvenience.
(3) In every case under either of the preceding subsections the Collector shall at that time of taking possession offer to the persons interested compensation for the standing crops and trees (if any) on such land and from any other damage sustained by them caused by such sudden dispossession and not excepted in section 24; and, in case such offer is not accepted, the value of such crops and trees and the amount of such other damage shall be allowed for in awarding compensation for the land under the provisions herein contained.
[(3A) Before taking possession of any land under subsection (1) or subsection (2), the Collector shall, without prejudice to the provisions of subsection (3)
(a) tender payment of eighty per centum of the compensation for such land as estimated by him to the persons interested entitled thereto, and
9
(b) pay it to them, unless prevented by some one or more of the contingencies mentioned in section 31, subsection (2), and where the Collector is so prevented, the provisions of section 31, subsection (2) (except the second proviso thereto), shall apply as they apply to the payment of compensation under that section.
(3B) The amount paid or deposited under section (3A), shall be taken into account for determining the amount of compensation required to be tendered under section 31, and where the amount so paid or deposited exceeds the compensation awarded by the Collector under section 11, the excess may, unless refunded within three months from the date of Collector's award, be recovered as an arrear of land revenue].
[(4) In the case of any land to which, in the opinion of the [appropriate Government], the provisions of subsection (1) or sub section (2) are applicable, the [appropriate Government] may direct that the provisions of section 5A shall not apply, and, if it does so direct, a declaration may be made under section 6 in respect of the land at any time [after the date of the publication of the notification] under section 4, subsection (1).”
10. At the outset, the learned senior counsel for
Respondent No.1, in an attempt to sustain the acquisition
strenuously contended with regard to eminent domain of the
State in the matter of acquisition of land for public purpose
and relied upon the case in Coffee Board, Karnataka,
10 Bangalore Vs. Commissioner of Commercial Taxes,
Karnataka and Others (1988) 3 SCC 263. To be fair to him,
though we have noted, we are however clear on that aspect
that the State has the power. But the position of law is also
well established that in view of Articles 300A and 31A of the
Constitution, the owner of land can be divested only in
accordance with law after appropriately compensating if such
land is required by the State for public purpose. Since such
power of eminent domain is not in dispute, we need not advert
to the decision referred in detail.
11. In the normal circumstance, the process for
acquisition would commence with the notification under
Section 4, after which the procedure under Section 5A is
complied. The declaration under Section 6 is thereafter made,
when the requirement of the land for public purpose is
confirmed. Thereafter, the process for determining the
compensation and taking possession through Section 11 and
Section 16 of Act, 1894 is contemplated, which is undertaken
after issue of notice under Section 9 of Act, 1894. In so far as
the said process, in order to protect the interest of the land
loser to be compensated within a time frame, failing which, to
11 give him benefit of his own land, Section 11A was inserted by
Act 68 of 1984, w.e.f 24.09.1984. The said provision leaves
no ambiguity whatsoever that if the award is not made within
the period of two years from the date of publication of the
declaration under Section 6 of Act, 1894, the entire
proceedings will stand lapsed. The only option for the
acquiring authority if the land is still required for the public
purpose is to notify afresh from the stage of issuing
notification under Section 4 of Act, 1894. The computation of
two years would however exclude the period if the process was
stayed by an order of the Court. This aspect has been
clarified by this Court in Yusufbhai Noormohmed
Nandoliya Vs. State of Gujarat and Anr. (1991) 4 SCC 531,
placed for our consideration by the learned senior counsel for
the appellant.
12. So far so good, the question however is as to whether
the rigour of Section 11A of Act, 1894 will apply when the
appropriate Government exercises its special power in cases of
urgency, which does not contemplate the same procedure as
in the normal acquisition process noted above. In this regard
also this Court in Yusufbhai Noormohmed Nandoliya 12 (supra) has held Section 11A is applicable to acquisition
under Section 17, though without detailed discussion. From
the provision of Section 17 reproduced supra, it is seen that
the acquiring authority will be entitled to take possession
without taking recourse to the procedure which is otherwise
provided under Section 16 of Act, 1894 wherein it
contemplates the passing of an award before taking
possession. But under Section 17 of Act, 1894, possession is
permitted to be taken even before the award is passed.
Though such power was absolute earlier, subsection (3A) was
inserted by Act 68 of 1984, w.e.f 24.09.1984 whereby the pre
condition imposed before taking possession is that 80% of the
estimated compensation is to be tendered and paid to the
persons interested in the land. The tendered amount should
be paid unless prevented by one or more of the contingencies
mentioned in Section 31(2) of Act, 1894. It would necessarily
mean that Section 31 will come into play and the 80% of the
estimated compensation amount, though no award is passed,
will have to be tendered and paid to the persons interested. If
tendered, but not able to pay due to valid reasons, it is to be
deposited in Court. The word employed in subsection (3A) of
13 Section 17 of the Act, 1894 is “shall” and it is to be tendered
and paid “before taking possession”. Hence it cannot be
understood as providing any discretion to the acquiring
authority. In fact, the last sentence of subsection (1) of
Section 17 uses the word “thereupon” with respect to vesting.
This word “thereupon” is correlated to taking possession and
payment in terms of subsection (3A) is a sine qua non for
taking possession. Therefore (1) payment of 80% (2) taking
over possession thereafter and (3) vesting of land in the
government take place in a sequence. Absent anyone of these
in the sequence, the emergency provision fails. It is a pre
requisite condition to acquire and take possession of the land
since such acquisition is permitted by exempting the
requirement of the procedure under Section 5A and
possession is permitted to be taken prior to an award being
passed under Section 11 of Act, 1894.
13. That apart, subsection (4) to Section 17 of Act, 1894
provides the discretion to the appropriate Government to
waive the application of the provisions of Section 5A and make
the declaration under Section 6 in respect of the land at any
time after the initial publication of the notification under
14 Section 4 of Act, 1894. This makes it clear that even in a case
where the appropriate Government exercises its power to
invoke the special power in case of urgency, all other
procedure contemplated under the Act except the requirement
under Section 5A of Act, 1894 is to be complied. Therefore,
after issue of the initial notification under Section 4 read with
Section 17(1) and on taking possession after issue of notice
under Section 9, the declaration under Section 6 of Act, 1894
is to be made so as to complete the process of acquisition,
which indicates that the objection to acquisition of land shall
alone stand muted and not the right to compensation which is
to be paid in strict compliance of the requirement in that
regard.
14. Hence, insofar as payment of compensation for the
acquired land even if it is acquired under Section 17 of Act,
1894, it is evident that an award as contemplated under
Section 11 of Act, 1894 is required to be passed so as to
determine the compensation payable. Since subsection (3A)
to Section 17 mandates payment of 80% of the estimated
compensation, such amount paid would get included in the
amount to be determined and offered through the award. In
15 that context it is clear that Section 17(4) contemplates, that
the declaration is to be made under Section 6 even when an
urgency provision is invoked and an award under Section 11
is to be passed to determine the compensation.
15. However, on a careful composite perusal of all the
provisions noted above, it is evident that the requirement to
tender and pay 80% of the estimated compensation before
taking possession assumes significance so as to carve out an
exception for nonapplicability of ‘lapsing’ as contemplated
under Section 11A of Act, 1894. This is so, since the terms
“vesting absolutely” and “lapsing” cannot coexist and cannot
go hand in hand. Post amendment w.e.f 24.09.1984, two
elements have been inserted in Section 17 for the land to vest
absolutely in the Government for public purpose even before
the award is passed. One, is that possession should be taken.
The other is, by inserting subsection (3A) it has been made
mandatory to tender payment of 80% of estimated
compensation before taking possession. Therefore, 80% of the
estimated compensation, the payment of which only if
tendered and paid, the vesting would become absolute and in
such event the consequence of lapsing in respect of absolutely
16 vested land cannot occur and as such, in that circumstance
alone Section 11A though applicable will not take effect. The
right of the land loser would be to enforce passing of award
which will include the balance 20% of compensation even if it
is beyond two years and get adequately compensated in terms
of Section 23 and 34 of Act, 1894 for the delay if any.
16. But it is a different matter altogether, when Section
17(1) is invoked but the requirement thereunder which is a
prerequisite condition is not complied. As noted, subsection
(3A) has been inserted w.e.f. 24.09.1984, whereunder it is
made mandatory to tender and pay 80% of the estimated
compensation before taking possession. Therefore, even if
possession is taken, such possession cannot be considered as
legal so as to vest the land absolutely if the prerequisite
condition for payment of 80% before taking possession is not
complied. In such circumstance, by legal fiction it looses its
character as an acquisition under Section 17 and since the
absolute vesting does not take place, it will lapse if the further
process is not complied and the award is not passed within
two years from the date of declaration. However, even when
the precondition is not complied, if the land loser does not
17 challenge the acquisition and/or taking of possession as
illegal, but concedes to the position, the possession taken
does not become perse illegal and the vesting will be absolute
and in such event it cannot be considered to have lapsed until
the land loser exercises the right. We consider it so, since,
both Section 11A and subsection (3A) to Section 17 of Act,
1894 were inserted in Act,1894 to enable the land losers to
exercise their right conferred on them. As such, the said right
is to be exercised by the land loser and none other, not even
the acquiring authority or beneficiary nor would the said
provision become automatically applicable unless it is
triggered by the land loser.
17. Therefore, we are of the considered view that Section
11A though applicable to the cases of acquisition initiated
under Section 17(1) of Act, 1894 the consequence of it will not
affect the case where the land has absolutely vested on
compliance of subsection (3A) to Section 17 of Act, 1894 and
80% of estimated compensation is tendered and paid. Hence,
when there is a challenge by the land loser, each case will
have to be considered on its own merits to determine whether
the prerequisite condition to tender and pay as contemplated
18 under subsection (3A) is made before possession is taken. If
in the case concerned the mandatory prerequisite is not
complied, such acquisition will loose its character as being
under Section 17 and if the award is not passed within two
years from the date of the declaration, it will lapse and not
otherwise. The benefit of said provision is available only to be
invoked by the land loser and cannot be invoked by the
acquiring authority to claim lapse by pointing to non
compliance since the ‘vice’ of noncompliance cannot be
permitted to be converted into a ‘virtue’.
18. Though the learned counsel for the beneficiary
Respondent No.2 placed reliance on the decision in Indore
Development Authority Vs. Manoharlal & Others (2020) 8
SCC 129 rendered by the Constitution Bench to contend that
it has been held therein that “paid” as contained in Section
24(2) of RFCTLARR Act, 2013 does not include deposit of
compensation in Court, we are of the considered opinion that
the same will not be applicable to the question under
consideration before us in this case. In the instant case, the
requirement to tender and pay 80% of the estimated
compensation and the consequent lapsing as considered
19 above is in the context of exercise of urgency provision which
permits a deviation from the normal process of acquisition
and the payment envisaged is to take benefit of the said
provision. In contradistinction, the consideration in the cited
case is about the effect of Section 24 (2) of Act, 2013 in the
circumstance contemplated therein.
19. In considering the effect of Satendra Prasad Jain
(supra) it would be appropriate to take note of the decision
relied on by the learned senior counsel for the appellant in
Laxmi Devi Vs. State of Bihar (2015) 10 SCC 241 wherein it
is analysed as hereunder:
“26. This is also in line with a plain reading of Section 17(1), which states that “once possession of the land is taken by the Government under Section 17, the land vests absolutely in the Government, free from all encumbrances”. In Section 48(1) the taking over of the possession of the land is of seminal significance in that the provision succinctly states that “the Government shall be at liberty to withdraw from the acquisition of any land the possession of which has not been taken”. The next subsection covers calculation of compensation for the aborted occupation.
26.1. The same position came to be reiterated in Satendra Prasad Jain by a threeJudge Bench of this Court. The acquisition proceedings including the exclusion of Section 5A had obtained the imprimatur of the Allahabad High Court; the urgency and public purpose had received curial concurrence. Possession of the
20 land was taken by the State from the landowners. Previously, the special leave petition filed by the landowners had been dismissed by this Court. Ironically, the subsequent stance of the State was that the acquisition of land under the urgency provisions was required to be set aside for the reason that the State had failed to pass an award under Section 11 within two years and had also failed to pay eighty per cent of the estimated compensation required under Section 17(3A). Whilst the State endeavoured to withdraw from the acquisition, the erstwhile landowners opposed it. This Court directed the State “to make and publish an award in respect of the said land within twelve weeks from today”.
The abovementioned discussion bears out that this Court was concerned only with the issue of the land being returned by the State to the erstwhile owner. It does not go so far as to limit or restrict the rights of landowners to fair compensation for their expropriated property, as that is a constitutional right which cannot be nullified, neutralised or diluted.
26.2. We think it justified to again refer to the opinion in Satendra Prasad Jain that : (SCC p. 374, para 16) “16. … Section 11A cannot be so construed as to leave the Government holding title to the land without the obligation to determine compensation, make an award and pay to the owner the difference between the amount of the award and the amount of eighty per cent of the estimated compensation.”
26.3. The second issue, one that we feel must be kept in mind in the interpretation in the law laid down by this Court, is the factual matrices involved in both Satendra Prasad Jain and Avinash Sharma. In both these precedents, as well as in innumerable others that have relied upon them, the Government's attempt was to misuse its own omissions to 21 achieve its own oblique purposes. It was in this context that this Court declined to accede to the pleas of the Government. This Court poignantly repelled the State's attempt to nullify the acquisition on the predication of its non compliance with Sections 16 and 17(3A). The judicial intent was not to cause any loss to landowners, but to protect them. The pernicious practice that was becoming rampant, that is to make partial compliance with the statute and to follow the acquisition procedure in a piecemeal manner, and then to argue that its own lapses rendered its acquisition illegal, was roundly repulsed. Although this strictly constitutes obiter, we think it appropriate to clarify that where the landowners do not assail the acquisition, it may be open to them to seek a mandamus for payment to them, after a reasonable period, of the remaining compensation, which will thereupon metamorphose from a mere estimation to the actual compensation for the expropriation.
28. We do, however, recognise that Satendra Prasad Jain has been interpreted more broadly in the past. In Allahabad Development Authority v. Nasiruzzaman, Deptt. of Telecommunications v. Madan Mohan Pradhan and Banda Development Authority v. Moti Lal Agarwal, this Court has dismissed the landowners' challenges to the respective acquisitions on the basis of Avinash Sharma and Satendra Prasad Jain. It is pertinent to note that all three of these cases were brief in their explanations of Avinash Sharma and Satendra Prasad Jain and did not examine their rationes decidendi, their innate contradictions, their intentions or their consequences at any length. We thus feel it appropriate to rely on our own detailed exploration of these cases, as opposed to simply placing reliance on the largely contradictory case
22 law that has developed over the years. It was for this reason that we had revisited the curial concept of ratio decidendi.
29. The scenario before us depicts the carelessness and the callousness of the State, quite different from the situation in Satendra Prasad Jain and Avinash Sharma. The appellants herein are being denied just and fair compensation for their land in proceedings which commenced in 1987, despite the directions of the High Court passed as early as in 1988 to pass an award within four months. The raison d'être behind the introduction of Section 11A was for the landowners to have a remedy in the event of an award not being passed expeditiously. If Satendra Prasad Jain is interpreted to mean that Section 11A will not apply to any acquisition under the urgency provisions, landowners such as the appellants before us will have no protection, even if they are not paid full compensation for their land for decades. This cannot be in keeping with the legislative intent behind this section. Furthermore, keeping empirical evidence in sight, we make bold to opine that circumstances require this Court to reconsider its view that even if the stated public interest or cause has ceased to exist, any other cause can substitute it, especially where the urgency provisions have been invoked.
30. We feel it imperative to distinguish between the setting aside of an acquisition and the reversion of possession to the erstwhile landowners. While the LA Act and the judgments discussed above do not allow for the latter, we are of the considered opinion that this does not necessarily imply that the former is also not an option. Both the abovementioned cases dealt with a factual situation in which the Government was attempting to set the
23 acquisition of the land at naught so that they would not have to pay compensation to acquire it. Setting aside of the acquisition in those cases was tantamount to reverting the possession to the original owners. In this scenario, however, the two do not have to go hand in hand. In allowing the acquisition of land that the Government finds necessary to be set aside, we would not necessarily be holding that the land revert to the appellants, as the alternative of permitting the Government to keep possession provided it reacquires the land with a new Section 4 notification exists. This option, particularly in the present factual matrix, does the least violence to the intent and content of the LA Act, in that it upholds Section 11A even in cases of acquisition under Section 17 while preserving the requirement of Section 17 that the unencumbered possession of the land remain vested in the Government. It also protects the rights of the landowners, thus fulfilling the intent of Section 11A, while allowing the Government to acquire land in cases of emergencies without its title being challenged, which is the avowed intention of Section 17. Any other interpretation of the law would serve to protect only those landowners who had approached the court to stop the Government from undoing an emergency acquisition, while leaving in the cold equally aggrieved landowners seeking to enforce their right to fair compensation for their land. Even equity demands that the party bearing the consequence of the delay in the award ought not to be the innocent landowner, but the errant State.”
20. We are in agreement with the opinion expressed in
Laxmi Devi (supra) by a Bench of two Hon’ble Judges. In our
opinion also the philosophy based on which the decision in
24 Satendra Prasad Jain (supra) was rendered is as contained
in para17, which reads as hereunder:
"17. In the instant case, even that 80 per cent of the estimated compensation was not paid to the appellants although Section 17 (3A) required that it should have been paid before possession of the said land was taken but that does not mean that the possession was taken illegally or that the said land did not thereupon vest in the first respondent. It is, at any rate, not open to the third respondent, who, as the letter of the Special Land Acquisition Officer dated June 27, 1990 shows, failed to make the necessary monies available and who has been in occupation of the said land ever since its possession was taken, to urge that the possession was taken illegally and that, therefore, the said land has not vested in the first respondent and the first respondent is under no obligation to make an award."
(Emphasis supplied)
We have also in our view indicated above that the acquiring
authority and/or beneficiary cannot derive benefit of non
compliance of requirement of Section 17(3A) and take benefit
of Section 11A of Act, 1894. The benefit of the provision is for
the land loser. In Satendra Prasad Jain (supra) also this
Court was of the opinion that it was not open for the acquiring
authority or the beneficiary to take benefit of Section 11A and
Section 17(3A) which is intended to benefit the land owner to
25 ensure that award be made within time. Hence it is clear that
Satendra Prasad Jain (supra) does not lay down the ratio
that the acquisition does not lapse under any circumstance if
the urgency provision under Section 17 of Act, 1894 is
invoked but it only disapproved applying it against the land
loser.
21. In the above background it is noted that in the instant
acquisition from which this case arises, an extent in all
measuring 63.540 acres (1011517, 5/6 Bighas) was
acquired through the declaration under Section 6 of Act, 1894
for which a sum of Rs. 7,48,67,857.73 being 80% is stated to
have been deposited by Respondent No.2 – Beneficiary, with
Respondent No.1 and the balance amount is also deposited on
21.12.2002 so as to enable the collector to enter into an
agreement with the landowners and pay compensation.
Insofar as the extent of land belonging to the appellant, it is
stated by Respondent No.1 that a letter dated 01.01.2003 was
issued calling upon the appellant to come forward and
execute an agreement. Thereafter there is no effort to tender
and pay 80% of the estimated compensation or to pass an
26 award, which prompted the appellant to file the writ petition
before the High Court.
22. From the sequence of events, it is clear that the other
land losers have entered into an agreement and received
compensation. The appellant on the other hand was neither
tendered nor paid 80% of the estimated compensation as
required under subsection (3A) to Section 17 before taking
possession nor was an award passed and compensation paid
within two years from the date of declaration under Section 6
of Act, 1894.
23. In the normal circumstance, the acquisition would
lapse insofar as the appellant’s land in view of our conclusion
on the legal aspect. However, in the fact situation, the relief is
required to be moulded. This is for the reason that the land
belonging to the appellant is not a standalone extent. As
noted, the acquisition was for a planned industrial layout and
the total extent acquired and possession taken was 10115
17, 5/6 bighas of which, the land belonging to the appellant is
only 2061/30 bighas. In the planned layout, the land has
been utilized for various purposes and amenities. A ‘Mandi’
has been constructed over a larger extent of land of which the
smaller extent of land belonging to the appellant also forms a
27 part. Hence reversion of the land does not arise. Further, the
course as suggested in Laxmi Devi (supra) to issue a fresh
notification also would not be appropriate, since the very
scheme of acquisition and determination of compensation
under the old regime has undergone a sea change. As such it
would be unjust not only to the state exchequer but also the
other land losers under the same notification if the present
prevailing process is applied in determining the
compensation. Further, though after being nudged by the
High Court, the award in any event was passed on 09.06.2008
under the old regime which is now to be substituted with
adequate compensation.
24. On weighing all aspects of the matter, we deem it
appropriate that it will serve the ends of justice to direct the
respondents to determine the market value insofar as the
appellant’s land is concerned by reckoning the relevant date
as 09.06.2008 (i.e. the date on which the award was
ultimately passed), by applying the yardstick under Act, 1894.
It is made clear that only the market value be determined as
on that date but for awarding the statutory benefits, it shall
be calculated from the date of the original notification since
28 admittedly the appellant has been dispossessed on
04.02.2003 pursuant to the notification dated 17.04.2002.
Further, from the date on which the fresh award is passed
pursuant to this judgment, the appellant would get the cause
of action for seeking reference if dissatisfied with the quantum
of compensation awarded. It is made clear that the
determination of compensation, in this case, shall not give
rise to any right in favour of any other land loser whose land
was acquired under the same notification, to seek for re
determination of compensation where the same has already
attained finality.
25. The decision in this case based on the principle of law
settled herein, if it arises for consideration in any other case
under Act, 1894 or any other enactment relating to land
acquisition containing pari materia provisions shall be applied
only prospectively and cases which have attained finality shall
not be reopened.
26. In the result, we pass the following order:
(i) The provision contained in Section 11A of Act,
1894 shall be applicable to cases in which the
acquiring authority has not complied with the
requirement of subsection (3A) to Section 17 of
29 Act, 1894 by tendering and paying eighty per
centum of the estimated compensation before
taking possession since possession in such cases
cannot be considered to be taken in accordance
with law and the vesting is not absolute.
(ii) If the requirement is complied and possession is
taken after tendering and paying eighty per
centum, though there is need to pass an award
and pay the balance compensation within a
reasonable time, the rigour of Section 11A of Act,
1894 will not apply so as to render the entire
proceedings for acquisition to lapse in the context
of absolute vesting. The right of land loser in
such case is to enforce passing of the award and
recover the compensation.
(iii) In the instant case though Section 11A of Act,
1894 has become applicable, in the changed
circumstance we deem it proper to mould the
relief instead of holding the acquisition to have
lapsed. Hence for the reasons stated above, we
direct as follows:
30 (a) The respondents shall construe 09.06.2008
as the relevant date and determine the market
value prevailing as on that date applying the
yardstick under Act, 1894 in respect of the
acquired land.
(b) To calculate the statutory benefits on such
amount including interest, the same shall be
determined by taking into consideration the
date of the Section 4 notification dated
17.04.2002 since the appellant was
dispossessed on 04.02.2003 pursuant to the
same.
(c) The date on which the fresh award is passed
pursuant to this judgment and communicated
shall be the date of cause of action for seeking
enhancement of compensation if the appellant
is dissatisfied with the quantum of
compensation offered.
(d) The compensation determined in this case
shall not give the cause of action to any other
land loser whose land is acquired under the
31 same notification to seek redetermination of
compensation.
(e) The appellant shall be entitled to the cost
incurred in these proceedings.
27. The appeal is disposed of accordingly.
28. Pending application, if any, stands disposed of.
….…………………………J. (S. ABDUL NAZEER)
…...……………………….J. (A.S. BOPANNA)
…..…….
……………………J. (V. RAMASUBRAMANIAN) New Delhi, October 14, 2022
32
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free