Miss Lucy
← All judgments

M/S Chalet Hotels Limited vs M/S Hindustan Aeronautics Limited

Karnataka High Court29 May 2020B. Veerappa

Ratio decidendi

The rule this decision rests on

1. The cancellation of a "No Objection Certificate" (NOC) issued for construction cannot extend to the entire building if only part of it is alleged to violate the permissible height limits. The authority issuing the NOC must specify which portion of the structure violates the conditions, and the burden lies on the authority to establish both: (a) that the applicant's submitted data is established to be materially different, and (b) that such difference would adversely affect aircraft operations. Mere allegation of difference, unsupported by material documentation, is insufficient to justify cancellation of the entire NOC including the permissible construction. 2. An authority charged with issuing NOCs must verify the accuracy of the applicant's data before issuing the certificate in accordance with applicable guidelines. Where an authority issues an NOC without conducting independent verification, and subsequently discovers (after a lapse of time) that data differs from its own records, it cannot cancel the NOC retroactively based on its own prior failure to verify, especially where the applicant relied upon certificates from competent authorities at the time of application. 3. The doctrine of estoppel applies against public authorities: where a public authority had access to information and could have known the truth through due diligence at the time of decision-making, it cannot later rely upon that same information as grounds for reversing its prior decision, particularly where reliance upon that decision has been acted upon by private parties. 4. A public authority cannot approbate and reprobate by taking advantage of favorable portions of an instrument or notification while ignoring conditions that would protect the applicant. The authority must be consistent in applying all terms and conditions of the instrument it has issued. 5. Where the resolution of a factual dispute requires determination of ground-level elevation and the extent of any breach, and such determination is susceptible to technical survey, the Court has jurisdiction under Article 226 to remand the matter to a competent surveying authority rather than dismiss the petition, particularly where the authority itself has called for resurvey in its correspondence. 6. The cancellation of permission or NOC after substantial reliance, investment, and completion of construction raises equitable considerations favoring a fair procedure giving opportunity to be heard and requiring clear establishment of violation before complete cancellation, even in matters concerning public safety, provided the applicant has otherwise complied with procedural requirements.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1RIN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 29TH DAY OF MAY, 2020
BEFORE
THE HON' BLE MR. JUSTICE B. VEERAPPA
WRIT PETITION No.37571/2013(GM-RES)
BETWEEN:
M/s CHALET HOTELS LIMITED,HAVING ITS REGISTERED OFFICE ATRAHEJA TOWER, PLOT NO.C-30,BLOCK-G, OPP: SIDBI,BANDRA KURLA COMPLEX,BANDRA (EAST), MUMBAI 400051.ANDHAVING ITS BRANCH OFFICE ATNO.17/2, RAHEJA POINT,# 202-203, 2ND FLOOR,MAGRATH ROAD, ASHOKNAGAR,BANGALORE 560025.REPRESENTED BY ITSAUTHORISED SIGNATORY ANDMANAGING DIRECTORMR. SURESH SINGARVELU ...PETITIONER
(BY SRI UDAY HOLLA, SENIOR COUNSEL A/WSRI KAMLESH SAMPAT, ADVOCATE)
AND:
1. M/S HINDUSTAN AERONAUTICS LIMITED,AIRPORT SERVICES CENTREBANGALORE COMPLEX,BANGALORE 560017.REPRESENTED BY ITS CHAIRMAN.
2. MR. ASHOK CHUNILAL BAJAJS/O CHUNILAL HASSAINGH BAJAJ, DELETED AS PERR/AT NO.704, 7TH MAIN, ORDER DATED 9.4.2019HAL II STAGE, INDIRANAGAR,BANGALORE 560 008.2
3. MR. AMEET HARIANIS/O MR. PRATHAP SINGH HARIANIR/AT CHANDAN, 2ND FLOOR, 62-B,PEDDAR ROAD, MUMBAI 400026.
4. MR. SACHINS/O SHASHIKANT SAPRER/AT NO. A 304,
5. MR. BIJU MATHEWS/O MR. MATHEW P. K.R/AT NO.B 613,
6. MR. KALYAN SUNDRAMS/O MR. GANAPATHY,R/AT NO.A 201,
7. MR. MUKUND PANDURANJ SURANGES/O PANDURANJ SURANGER/AT NO.B 313,
8. MR. RABINDRA NATH RAULS/O DUARI RAULR/AT NO.A 307,
9. MR. PAWAN MATHURS/O MR. M. P. MATHURR/AT NO.A 306,
10 . MR RACHIT GUPTAS/O MR. JAYA GUPTAR/AT NO.A 406,
R4 TO R10 ARE AT FLORINA ESTATES,NO.53, SARJAPUR ROAD,1ST CROSS, 3RD BLOCK,KORAMANGALA, BANGALORE 560 034.
11. MEKIN MAHESHWARI,S/O MR. PRABHU DAYAL MAHESHWARI,AGED ABOUT 33 YEARS,FLAT No.215, BLOCK C, RAHEJA RESIDENCY,3RD BLOCK, KORAMANAGALA,BANGALORE-560034.3
12. MANOJ ATTAL,S/O MR. HARINARAYAN ATTAL,AGED ABOUT 42 YEARS,No.L-108, 3RD B MAIN,SECTOR 6, HSR LAYOUT,BANGALORE-560102.
13. SUBRATAMITRA,S/O LATE BHAKTA MOHAN MITRAAGED ABOUT 48 YEARS,A 401, MANTRI ELEGANCE,BANNERGHATTA ROAD,BANGALORE-560076.
14. SIRISH KUMAR,S/O J.P.V. (LATE) REDDY, DELETED AS PERORDER DATED 9.4.201915. SUNIL AGARWAL,S/O SHRI SHUBHKARANJI HAKIN
16. MANEESH DHIR,S/O DR. M.P. DHIR,AGED ABOUT 48 YEARS,611, EMBASSY TRANQUIL,8TH MAIN, 3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
17. MANJUKUCHHAL,W/O MR. RAJIV KUCHHAL,AGED ABOUT 42 YEARS,612, EMBASSY TRANQUIL,8TH MAIN, 3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
18. RAJIV KUCHHAL,S/O MR. R.D. KUCHHAL,AGED ABOUT 47 YEARS,612, EMBASSY TRANQUIL,8TH MAIN, 3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
19. DILEEP RANJEKAR,S/O MR. KAMALAKAR,AGED ABOUT 62 YEARS,6B, NITISH MAYFAIR,4
31, KASTURBA ROAD CROSS,BANGALORE-560001.
20. MR. SANJAY NAYAK,S/O MR. S.S. NAYAK,AGED ABOUT 48 YEARS,529, 17TH D MAIN, 6TH BLOCK,KORAMANGALA, BANGALORE-560034.
21. MR. SHASHIDHAR PATIL,S/O MR. LINGANAGOWDA PATIL,AGED ABOUT 57 YEARS,PRATHAM, 508, 15TH MAIN,3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
22. MS. ZENOBYA S BURJORJEE,W/O MR. SAROSH N. BURJORJEEAGED ABOUT 58 YEARS,288, 18TH D MAIN, 6TH BLOCK,KORAMANGALA,BANGALORE-560095.
23. MR. GURTEJSODHI,REPRESENATED BY POA VINEET CHHABRA,S/O (LATE) MR. BALBIR S. SODHI,AGED ABOUT 54 YEARS,No.14, 80 FEET ROAD, 4TH BLOCK,KORAMANGALA,BANGALORE-560034.
24. MR. VINEETCHHABRA,S/O (LATE) MR. B.K. CHHABRA,AGED ABOUT 47 YEARS,No.906, OLYMPUS III, ACROPOLIS,HOSUR ROAD, BANGALORE-560029.
25. MR. ARNOB ROY,S/O LATE MR. NIRMALYA ROY,AGED ABOUT 49 YEARS,17, 2ND CROSS, 12TH MAIN,4C BLOCK, KORAMANGALA,BANGALORE-560034.5
26. MR. N.S. VINODH, DELETED AS PERS/O (LATE) MR. N.S. SRINIVASAN, ORDER DATED 9.4.2019
27. MR. SALILPUNALEKAR & DEEPA PUNALEKAR,S/O SITARAM PURUSHOTTAM PUNALEKAR,AGED ABOUT 43 YEARS,1061, SOBHA JASMINE, OUTER RING ROAD,BANGALORE-560103.
28. MS. KSHITIJAKRISHNASWAMYW/O MR. SRIDHAR VISWANATHANAGED ABOUT 46 YEARS,IB, LAKESHORE MANOR,GANGADHAR CHETTY ROAD,BANGALORE - 560042.
29. MS. TANYA BALI,W/O MR. VISHAL BALI,AGED ABOUT 43 YEARS,3C3, REGENCY PLACE, No.7,RICHMOND ROAD,BANGALORE-560025.
30. MR. PANGAL KISHORE NAYAK,S/O MR. P. SUNDERNATH NAYAK, DELETED AS PERORDER DATED 9.4.201931. MR. PRASHANTH PRAKASH,S/O MR. P. M. PRAKASH,
32. MR. MAYANK, PRASAD BHATNAGAR,S/O MR. RAJESWAR PRASAD,AGED ABOUT 37 YEARS,D-89, PRESTIGE OZONE,WHITEFIELD MAIN ROAD,BANGALORE-560066.
33. MR. SANJAY SHARMA & RADHIKA SHARMA,S/O LATE MR. MADAM M.L. SHARMA,AGED ABOUT 45 YEARS,FLAT No. 01, INDRAPRASTHAENERO,9 KINGSTON ROAD, RICHMOND ROAD,BANGALORE - 560025.
34. MR. G.V. SARATHCHANDRASHEKAR,S/O MR. G.V. PURUSHOTHAM RAO,6
AGED ABOUT 48 YEARS,APT. 3013, SOBHA JASMINE,OUTER RING ROAD,BELLANDUR, BANGALORE - 560103.
35. MR. JASSERAND JEAN MICHEL DELETED AS PERS/O MR. JULES JASSERAND ORDER DATED 9.4.2019
36. MS. ROSEMARY JOSHI,W/O MR. ASHUTOSHI JOSHI,AGED ABOUT 38 YEARS,F-208, REDWOOD, RAHEJA RESIDENCY,3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
37. MR. M R RAVISHANKAR,S/O MR. M.B. RAJASHEKARAIAH,AGED ABOUT 47 YEARS,E-505, RAHEJA RESIDENCY,7TH CROSS, 3RD BLOCK, KORAMANAGALA,BANGALORE-560034.
38. MS. SANGEETA AGRAWAL,W/O MR. VINEET AGRAWAL,AGED ABOUT 49 YEARS,A1, BRUNTONRUSTOMJI APARTMENTS,BRUNTON ROAD, BANGALORE-560025.
39. MR. ZARIRBATLIWALA, DELETED AS PERS/O (LATE) D.J. BATLIWALA, ORDER DATED 9.4.2019
40. MR. VENUGOPAL S REDDY,S/O MR. S.V. PAPA REDDY,AGED ABOUT 61 YEARS,No.780, APPENZELL DRIVE,HUMMEL TOWN, PA 17036, USA
41. MR. GOUDHAMAN BALASUBRAMANIAN,S/O MR. BALASUBRAMANIAN,AGED ABOUT 35 YEARS,B 605, MANTRI CLASSIC APARTMENTS,1ST MAIN ROAD,, 8TH MAIN,SRINIVAGILU, FRIENDS COLONY,ST. BED LAYOUT, KORAMANGALA 4TH BLOCK,BANGALORE-560034.7
42. MR. PANDURANGAKUMARJIGUDA,S/O MR. SHYAM SUNDER KUMARJIGUDA,AGED ABOUT 45 YEARS,402E, PINE BLOCK, RAHEJA RESIDENCY,3RD BLOCK, KORAMANGALA,BANGALORE-560034.
43. MR. VIRENDRA PALIWAL,S/O LATE MR. BALMUKUND PALIWAL,AGED ABOUT 43 YEARS,VILLA No.60, PURVAPARKRIDGE,GOWSHALA ROAD, MAHADEVAPURA,BANGALORE-560048.
44. MR. THOMAS VARGHESE,S/O (LATE) MR. P. THOMAS VARGHESE,AGED ABOUT 53 YEARS,103, CYPRESS BLOCK, RAHEJA RESIDENCY,KORAMANGALA 3RD BLOCK,BANGALORE-560034.
45. MR. SANJAY ANANDARAM,S/O LATE H.N. ANANDARAM,AGED ABOUT 49 YEARS,709, PINE BLOCK, RAHEJA RESIDENCY,KORAMANGALA 3RD BLOCK, 8TH C MAIN,BANGALORE-560034.
46. MR. RAKESH BHARDWAJ, DELETED AS PERS/O MR. K.C. BHARDWAJ, ORDER DATED 9.4.2019
47. MR. SUDHINDRANATHPAI K,S/O MR. RAMACHANDRAPAI KASTURI,AGED ABOUT 46 YEARS,No.308, PURVA IRIS, 54,M.S.O. COLONY, COX TOWN,BANGALORE-560005.
48. MR. RITESH SACHDEVS/O DR. GOVIND SACHDEVAGED ABOUT 38 YEARS,E 2419, PALAM VIHAR,GURGAON 1220178
49. MR. ARTI JAINW/O MR. DAVINDER JAIN,
50. MR. MANOJ SHENOY,S/O MR. K.R. SHENOY,
51. MR. NAGESWARA RAO POLISETTI, DELETED AS PERS/O MR. GANGARAJU POLISETTI, ORDER DATED 9.4.2019
52. M/S SIC STOCKS & SERVICES PVT. LTD. DELETED AS PERREPRESENTED BY SIDHARTHHANDA, ORDER DATED 8.6.2015
53. MS. RESHMI JAIN, DELETED AS PERW/O MR. PANKAJ JAIN, ORDER DATED 9.6.2019
54. MR. SAIKUMAR SHAMANNA,S/O LATE R SHAMANNA,AGED ABOUT 43 YEARS,No.42, VASWANI WHISPERING PALMS,NEAR INNOVATIVE MULTIPLEX,OUTER RING ROAD, MARATHAHALLI,BANGALORE-560037.

55. MR. KISHORE C NAIR, S/O MR. PERUMANA KONDONA DELETED AS PER CHANDRASEKHARAN NAIR, ORDER DATED 9.4.2019

56. MR. RAHUL AGARWAL, S/O MR. PADAM KUMAR AGARWAL, AGED ABOUT 38 YEARS, O-202, PRESTIGE ST. JOHN'S WOODS APARTMENTS TAVAREKERE MAIN ROAD, BANGALORE-560029.

57. MR. NITIN SAREEN S/O MR. KRISHAN KUMAR SAREEN AGED ABOUT 36 YEARS, A-33, BIRCH, TATA SHERWOOD, BASAVANAGAR, BANGALORE-560037.

58. MR. PUNEET AGARWAL POA HOLDER VINEET AGRAWAL, S/O LATE MAJ. GEN. V.N. AGRAWAL AGED ABOUT 52 YEARS, 9

A1, BRUNTONRUSTOMJI APARTMENTS, BRUNTON ROAD, BANGALORE-560025.

59. MR. DHRUV MAHENDRAJHAVERI, S/O MR. MAHENDRA JHAVERI AGED ABOUT 31 YEARS, No.25A, SARAT BOSE ROAD, "SINDU APARTMENT" 5TH FLOOR, FLAT No.5A, KOLKATTA-700020.

60. MR. PANKAJ KULSHRESHTHA, S/O MR. V.B. KULSHRESHTHA, AGED ABOUT 41 YEARS, S-64, GOLDEN ENCLAVE, AIRPORT ROAD, BANGALORE-560017.

61. MR. MOHAN KUMAR V S/O MR. (LATE) M.R. VENKATAPPA, AGED ABOUT 43 YEARS, No.702, REDWOOD, RAHEJA RESIDENCY, 3RD BLOCK, KORAMANGALA, BANGALORE-560034.

62. MR. N. ARJUN S/O MR NARAIN AGED ABOUT 57 YEARS, S2, ITTINA SIRI, 160, KORAMANGALA 1ST BLOCK, BANGALORE

63. MR. R. SIVADAS, DELETED AS PER S/O MR. K. RAGHAVA MENON ORDER DATED 9.4.2019

64. MR. JOHN LOUIS PINTO, S/O MR. LIGOURI SIMON PINTO, AGED ABOUT 76 YEARS, 2302, OAKWOOD APTS, 1ST CROSS, 8TH MAIN, III BLOCK, KORAMANGALA BANGALORE-560034.

65. MR. PREM PRADEEP DELETED AS PER S/O MR. HARISH CHANDRA ORDER DATED 9.4.2019 10

66. MR. MURALI MAHALINGAM, DELETED AS PER S/O MR. K. MAHALINGAM ORDER DATED 8.6.2015

67. MR. VENKATRAMAN M IYER & VIJAYA VENKAT S/O MR. MADHAVAN IYER, AGED ABOUT 55 YEARS, B-405, RAHEJA RESIDENCY 3RD BLOCK, KORAMANGALA, BANGALORE-560034.

68. MR. PAVANKARETI DELETED AS PER S/O MR. SRINIVASULU REDDY KARETI ORDER DATED 9.4.2019

69. MR. KUSH SHAH, S/O MR. N.K. SHAH, AGED ABOUT 40 YEARS, 202, SURAJ VISTA, K.D. MARG, PRABHADEVI, MUMBAI-400028.

70. MR. Y.C. RAMA REDDY, DELETED AS PER S/O MR. Y. KOTAREDDY, ORDER DATED 9.4.2019

71. MR. MARTAND RAMADHYANI, S/O R.K. RAMADHYANI, AGED ABOUT 61 YEARS, E-14/9, VASANT VIHAR, NEW DELHI-110057.

72. MR. K. ANJANAMURALI, DELETED AS PER S/O (LATE) MR. K.N. MURALI, ORDER DATED 9.4.2019

73. MR. V. RENGANATHAN, S/O MR. VENKATAPATTY, AGED ABOUT 51 YEARS, S1/S2, ITTINA SIRI, 160, KORAMANGALA 1ST BLOCK, BANGALORE-560034.

74. MS. UJWALAPRABHU, W/O MR. RAMESH JAYARAMAN, AGED ABOUT 48 YEARS, 12, DEEPAK APARTMENTS 22, 5TH AVENUE, 11

BESANT NAGAR, CHENNAI-600090. ...RESPONDENTS

(BY SRI ANANTH MANDAGI, SENIOR COUNSEL A/W SRI PRADEEP SAWKAR, ADVOCATE FOR C/R1; SRI SAJAN POOVAYYA, SENIOR COUNSEL FOR SMT. NALINA MAYEGOWDA, ADVOCATE FOR R3, R11 TO R13, R16 TO R25, R27 TO R29, R32 TO R34, R36 TO R38, R40 TO R45, R47, R48, R54, R56 TO R62, R64, R67, R69, R71, R73 AND R74; SRI ADITHYA SONDHI, SENIOR COUNSEL A/W SRI KARAN JOSEPH, ADVOCATE FOR R4 TO R10; VIDE ORDER DATED 9.4.2019 R2, R14, R15, R26, R30, R31, R35, R39, R46, R49, R50, R51, R52, R53, R55, R63, R65, R66, R68, R70, AND R72 ARE DELETED ...

THIS WRIT PETITION IS FILED UNDER ARTICLES 226 & 227 OF THE CONSTITUTION OF INDIA PRAYING TO QUASH THE LETTER DATED 16.8.13 ISSUED BY THE RESPONDENT VIDE ANNEXURE-AQ, DIRECT THE RESPONDENT TO PERMIT THE PETITIONER TO CONSTRUCT UPTO THE MAXIMUM HEIGHT WHICH DOES NOT ADVERSELY AFFECT AIRCRAFT OPERATIONS AS MAY BE DETERMINED IN THE AERONAUTICAL STUDY TO BE DETERMINED IN THE AERONAUTICAL STUDY TO BE CONDUCTED BY THE RESPONDENT THROUGH AA1 OR ICAO OR ANY OTHER RECOGNISED AGENCY ETC.

THIS WRIT PETITION HAVING BEEN HEARD AND RESERVED FOR ORDERS, COMING ON FOR PRONOUNCEMENT OF ORDERS THIS DAY, THE COURT MADE THE FOLLOWING:

ORDER

The petitioner in the above writ petition has

sought for a writ of certiorari to quash the letter bearing

No.ASC/DGM(AO)/131/526/2013 dated 16.08.2013,

issued by the 1st respondent vide Annexure-AQ,

canceling the No Objection Certificate issued in favour 12

of the petitioner and for a writ of mandamus to direct

the respondent to permit the petitioner to construct

upto the maximum height which does not affect the

aircraft operations as may be determined in the

aeronautical study based on the notified parameters for

HAL airport as on the date of issue of the NOC, to be

conducted by the respondent through Airports

Authority of India or International Civil Aviation

Organization or any other recognized agency and direct

the 1st respondent to revalidate the No Objection

Certificate dated 28.10.2011 issued by it, for a further

period of five years from the date of the final order, by

setting aside cancellation of the NOC.

I. Factual Matrix of the Case

2. It is the case of the petitioner that, the

petitioner owns the property bearing Sy.Nos.21, 22, 42,

52 and 1B situated at Koramangala Industrial Layout,

Jakkasandra village, BBMP Ward No.68, Bengaluru, 13

wherein, it is constructing a large residential complex

comprising of 2 basements, ground and 17 upper floors

in multiple wings. Construction of 5 wings was

completed upto 17th upper floors as far back as in June

to September 2012, inter alia on the basis of a No

objection Certificate ('NOC' for short) dated 28.10.2011

issued by the 1st respondent. The said property is

within the consideration zone of HAL Aerodrome and

therefore, construction of structures therein requires a

NOC from the 1st respondent. It is further case of the

petitioner that the 1st respondent was vested with the

responsibility to issue NOC for construction of

structures around HAL aerodrome by Notification

No.S.O.84(E) dated 14.01.2010 issued by the Ministry of

Civil Aviation, Government of India, in exercise of

powers conferred under the provisions of Section 9A of

the Aircraft Act, 1934, to regulate construction for the

safety of aircraft operations. Prior to the said

notification, similar notification relating to HAL were 14

issued by the Airports Authority of India ('AAI' for short).

It is further case of the petitioner that HAL aerodrome is

listed at item 5 in Annexure IIIC of S.O.84(E)

notification. As provided in Clause 1 of S.O.84(E), the

provisions in Annexures I and II govern the HAL

aerodrome. As provided in Clause 2(b), the respondent

is responsible for issuing NOC in accordance with the

notification- S.O.84(E). Therefore, provisions of

Annexures I and II are fully applicable to the 1st

respondent. The practice and procedure adopted by the

1st respondent regarding NOCs is the same as followed

by the AAI. The requirements include a surveyor's

report of having surveyed the Site Location Co-ordinates

in WGS-84 (deg min sec) format and Site Elevation

Certificate from Government Body, viz., Municipal

Authority/Corporation/etc., undertakings in Form 1A

and 1B, etc. to be submitted after applying for the NOC. 15

3. In Bengaluru, the practice and procedure

followed by the Municipal Authority i.e., Bruhat

Bengaluru Mahanagara Palike ('BBMP' for short) to

issue site elevation certificate is verified by Government

of Karnataka aided autonomous institution, such as Dr.

Ambedkar Institute of Technology. The petitioner

followed the aforesaid procedure and appointed M/s

Precision Surveys (India) Pvt. Ltd., ('the surveyor'), a

reputed surveying agency to carry out the survey. The

surveyor inspected the site, conducted the survey,

determined and certified the value as stated in its

certificate dated 05.09.2011. The values submitted by

the surveyor were checked and verified and were

certified to be correct by Dr.Ambedkar Institute of

Technology ('the Institute') as stated in its certificate

dated 05.09.2011. The petitioner filed the requisite

application dated 21.09.2011 with the 1st respondent for

issue of NOC for a structure upto 25 upper floors with a

maximum height of 110 meters. The said application 16

was reviewed by the NOC Committee of HAL, as stated

in 1st respondent's letter dated 28.09.2011, whereby, it

directed the petitioner to submit revised documents,

restricting the height to 62 mtrs (as against the height

of 110 mtrs applied for earlier). The BBMP, through its

Assistant Director, Town Planning, issued a Certificate

of Elevation dated 30.09.2011, as per the letter of Dr.

Ambedkar Institute of Technology. As directed by the

1st respondent on the recommendation of its NOC

Committee, the petitioner filed the revised documents

along with letter dated 03.10.2011.

4. The 1st respondent, considering the entire

material on record, issued the NOC dated 28.10.2011,

vide Annexure-A for construction of the proposed

residential building with a height of 62 meters i.e., 932

meters Above Mean Sea Level ('M AMSL' for short) and

the said NOC was issued with the approval of the

Competent Authority, with certain conditions. On the 17

basis of the said NOC, the petitioner obtained sanction

to modified plans for construction of the residential

building with 10 wings comprising of 2 basements,

ground and 17 upper floors (upto 17 floors) and club

house, and commenced and carried out the

construction as per the modified plan dated 24.02.2012

issued by the competent authority. It is further

contended that the Phase I comprising of 5 wings (B to

F) were completed upto 17th floor as long back as in

June to September 2012 and finishing works are under

process therein. Phase II comprises of 6 wings (A, G, H,

J, K and proposed wing L. There is no wing 'I'). Wing A

was completed upto the 15th floor. Wing G was

completed upto the 13th floor, wing H was completed

upto 12th floor and wing J was completed upto 11th

floor. The floors referred are the upper floors. The

petitioner has spent more than Rs.400 crores till the

end of July 2013 for the said project. Out of the total

number of the proposed 289 flats in the 10 wings, 202 18

flats have been booked by flat purchasers. From these

289 flats, 102 flats are on the 12th to 17th floors in the

10 wings, out of which 70 flats have been booked by

various purchasers. The purchasers have paid various

amounts for the flats. Several banks and financial

institutions have given loans for the flats and the

project, inter alia by creation of a security interest on

the said flats and the project. There has been no

complaint of any obstruction received by the petitioner

regarding aircraft operations or safety, at any time over

the last about one year during which the structures, the

full height upto 17th floor as permitted by the said NOC,

have been in existence.

5. It is further contended that, petitioner was

shocked and surprised, because, after lapse of nearly a

year after issue of the NOC, petitioner received a letter

dated 15.09.2012 from the 1st respondent, alleging that

the elevation submitted by the petitioner (870 mtr) 19

vastly differs from the data available with the 1st

respondent. There was no detail or description of the

data referred in the said letter and stated to be available

with the respondent, or any indication of when such

data became available; whether it was new data or data

available/considered at the time of the NOC Committee

restricting the height to 62 mtrs or the Competent

Authority approving grant of the said NOC. In the said

letter, it was stated that there could be a reduction in

the permissible height above ground level, and

petitioner was requested to carry out the re-survey for

purpose of finding the elevation in the presence of HAL-

NOC Committee and petitioner sought a meeting with

the Officers of the 1st respondent and met them at their

office on 04.10.2012. In the said meeting, petitioner,

inter alia offered to carry out a comprehensive survey

and follow applicable procedure for a conclusive

solution and suggested to review the matter in a further

meet considering the fact that the matter was of a 20

highly technical nature are that there are very few

persons having the specialized knowledge and

experience to effectively deal with the peculiar situation

in the present case.

6. It is further contended that 1st respondent-

HAL, it is primarily a public sector undertaking carrying

on manufacturing activity, and the responsibility to

issue NOCs was entrusted to them very recently in

2010. Consequently, the Officers of the 1st respondent

were themselves not completely sure of the conclusive

way forward. It is further case of the petitioner that,

after lapse of some time, 1st respondent sent letter dated

19.02.2013 advising to carry out a resurvey in the

presence of the HAL-NOC Committee. The 1st

respondent also wrote a letter dated 21.02.2013 to the

BBMP indicating that there is a doubt about the

accuracy of the ground elevation and the difference

could be in the range of 15-20 meters. That letter was 21

not marked or sent to the petitioner. The petitioner was

understandably alarmed at the doubt raised and the

consequences regarding air safety and sought advice on

how to conclusively ascertain the maximum permissible

height which would not adversely affect aircraft

operations. The petitioner also sent a reply dated

15.03.2013 to the 1st respondent setting out the

complete facts showing that the petitioner had followed

the practice and procedure and filed the requisite

documents and thereafter, 1st respondent issued NOC.

It is further contended that the petitioner was advised

that in view of the structure having been completed

upto 17 floors, an aeronautical study would be

necessary to conclusively determine the maximum

permissible height which would not adversely affect

aircraft operations, in accordance with the applicable

criteria of Anex 14 of ICAO and as provided in S.O.84(E)

notification. Therefore, the petitioner requested

Mr.R.C.Khurana (the retired Executive Director, 22

Airports Authority of India and who was the earlier

Chairman of the NOC Committee of the Airports

Authority of India), to conduct a detailed aeronautical

study and confirm the maximum permissible height for

aircraft safety, who, after conducting Aeronautical

Study, submitted the Aeronautical Study Report ('ASR'

for short) dated 12.03.2013 to the petitioner. The said

report, inter alia confirms that from AGA and Procedure

for Air Navigation Services ('PANS' for short) Obstract

Protection Surface ('OPS' for short) criterion, the height

is restricted to 964 M AMSL.

7. It is further case of the petitioner that,

petitioner's anxiety regarding air safety were justifiably

alleviated after the said findings of the ATM expert as

set out in the ASR. The ASR confirmed that the existing

structure upto 17 floors was below the said 964/957

mtr AMSL even assuming (for the sake argument) that

there was a possible 15/20 meters difference in the 23

ground level as alleged by the 1st respondent i.e., even if

the ground levels were 885/890 meters as alleged by

the 1st respondent on the basis of the Maps of Survey of

India, the structure with the height of 62 meters as

constructed would reach a maximum height of 947/953

meters AMSL, which was still below the aforesaid

maximum permissible height of 964/957 mtr AMSL

which would not adversely affect aircraft operations. It

is further case of the petitioner that, the 1st respondent

by letter dated 28.03.2013, asked for re-survey in the

interest of air safety and stated that no surveyor or

certifier was authorized by HAL-NOC-Committee to

survey or to certify the location and elevation of a site,

that 1st respondent insist only on 'Location and

Elevation Certificate' from BBMP, the 1st respondent's

NOC Committee has no role in surveying and verifying

the elevation of a site and the practice being followed by

AAI is adopted by HAL. Thereby, 1st respondent 24

effectively precluded a re-survey by the petitioner

through any private surveyor or certifier.

8. It is further case of the petitioner that, 1st

respondent had expressly admitted in the letter dated

28.03.2013 that the 1st respondent's NOC Committee

did not verify the site elevation from the co-ordinates

certified by the surveyor/institute/BBMP, by comparing

them with the site elevation given in the Survey of India

Maps. It is the duty of the 1st respondent to provide Site

Elevation details and site elevation data was available to

Survey of India Maps prior to application and grant of

NOC. But the 1st respondent did not perform its duty of

verifying the data available with it since inception, and

now, seeks to blame and shift the burden on to the

petitioner by relying on unreasonable disclaimers and

conditions, in paragraph 3 of the NOC. It is further

contended by the petitioner that the 1st respondent, by

the letter dated 12.04.2013, for the first time, claimed 25

that, it is found that the site elevation varies from the

data available with it, such as the elevation of nearby

sites and marks. Again, the 1st respondent requested

the petitioner, in the interest of air safety, to have a re-

survey conducted by a government agency like Survey of

India ('SOI' for short) or Karnataka State Remote

Sensing Application Centre ('KSRSAC' for short) to

measure the elevation and geographical co-ordinates of

the site. Thus, the object of the survey is in the interest

of air safety, which can be conclusively ascertained only

by an aeronautical study as per notification S.O.84(E)

read with Annex 14 of ICAO. Accordingly, by the letter

dated 20.05.2013, petitioner approached SOI for the

survey, filed the plans and enquired about the fee to be

deposited. By letter dated 21.05.2013, the petitioner

informed the 1st respondent that they have approached

SOI and are following up with SOI for the survey as

desired by the 1st respondent. But, the 1st respondent

did not forward the demand draft provided by the 26

petitioner for the fees of SOI as required by SOI and SOI

did not carry out any survey.

9. When things stood thus, the 1st respondent

by the letter dated 20.05.2013, abruptly and wrongly

sought to advise the petitioner to suspend construction

of all the towers near the structure under dispute (i.e.,

the 5 completed wings upto the 17th floor), till the

survey to find out the elevation of the site is carried out

by SOI and the permissible top elevation at the site is

arrived at, based on the survey report. Thereafter, the

petitioner met the 1st respondent's Officers at their

Office on 21.05.2013 and appraised them of the various

material facts, including the matters being pursued with

SOI and with AAI and discussed regarding the letter for

suspension of work. As per the said discussion, the

petitioner agreed to suspend the vertical construction

temporarily as more particularly set out therein. It was

stated by the petitioner that the proposed survey and 27

aeronautical study would reconcile the issue and clear

all doubts and that the petitioner would revert on

completion of the process with SOI and AAI.

Accordingly, same was communicated by the petitioner

to the 1st respondent on 24.05.2013. The petitioner was

informed that AAI had written to the 1st respondent and

indicated its willingness to conduct the study, if the 1st

respondent approached AAI and tendered the fees of

Rs.22,47,200/-. However, 1st respondent did not

respond or take any steps whatsoever, in this regard.

The petitioner had agreed to bear the costs of

Rs.22,47,200/- accordingly, delivered the demand draft

in favour of AAI to the 1st respondent and requested to

do the needful. However, the 1st respondent, by the

letter dated 07.08.2013, has incorrectly and for the first

time stated that, 'HAL has not advised you to get the

aeronautical study done by AAI' and asked the

petitioner to take back the demand draft claiming that

HAL was a third party. By the letter dated 14.08.2013, 28

the 1st respondent, returned the demand draft of

Rs.22,47,200/- to the petitioner.

10. It is further case of the petitioner that, in the

meanwhile, the BBMP had sent a letter dated

05.06.2013 to the 1st respondent, inter alia requesting

the 1st respondent to conduct the resurvey and confirm

whether the building is in conformity with permissible

parameters. The petitioner, by the letter dated

24.06.2013, replied to the BBMP stating that, it had

already initiated the desired process for measuring the

site elevation and for the aeronautical study and would

revert with the reports on completion of the process

with SOI and AAI. Since it did not appear that SOI

would carry out the survey applied for by the petitioner,

the 1st respondent by its letter dated 21.06.2013,

informed the petitioner to consider the KSRSAC as an

alternative to carry out the survey of the site.

Thereafter, the petitioner repeatedly contacted SOI, who 29

finally indicated that it would require the 1st respondent

to deposit Rs.15,000/- towards the fees. Accordingly,

by letter dated 11.07.2013, the petitioner delivered the

original demand draft for the fees of Rs.15,000/- to the

1st respondent with a request to forward the same to

SOI with a letter for initiating the process of the survey.

But, the 1st respondent, by the letter dated 27.07.2013,

inter alia informed the petitioner that the 1st respondent

has requested KSRSAC to give priority in carrying out

the survey. Accordingly, KSRSAC, by the letter dated

29.07.2013, informed the petitioner about the fees for

providing latitude, longitude and MSL by carrying out

DGPS field survey work and fly leveling survey or auto

levels. In the meanwhile, 1st respondent, by the letter

dated 31.07.2013, returned the demand draft fro

Rs.15,000/- which petitioner had provided for the

payment to SOI. Thereafter, petitioner, by the letter

dated 03.08.2013, addressed to the KSRSAC, requested 30

for a revised pre-receipt bill including therein charges

for the aeronautical study.

11. When things stood thus, on various

correspondences between the petitioner, 1st respondent

and the agencies for aeronautical study stated supra, 1st

respondent passed the impugned Order dated

16.08.2013 canceling the NOC granted. Hence, the

present writ petition is filed for the relief sought for.

II Objections filed on behalf of the 1st respondent-HAL

12. The 1st respondent has filed objections to the

main writ petition on 5.9.2013 contending that the writ

petition filed for the relief sought for is not maintainable

and is liable to be dismissed. It is further contended

that the respondent-Company is incorporated under the

provisions of the Companies Act, 1956 having its

Registered Office at Bangalore and it is the Government

Department and primarily a Public Sector Undertaking 31

coming under the Control of Department of Defence

Procurement, Ministry of Defence, Government of India.

One of the Divisions of the respondent-Company is the

Airport Services Centre (ASC) which deals with various

aspects of Air Traffic Management and is also directly

involved in testing activities for Pilots and Prototypes.

13. It is further contended by the 1st respondent

that the provisions of the Aircraft Act, 1934 (for short,

'the Act') has been enacted to make provisions for the

control of the manufacture, possession, use, operation,

sale, import and export of Aircrafts and in furtherance

of the said object, Section 9-A empowers the Central

Government to prohibit or regulate construction of

buildings and also restrict the height of such buildings

for the purposes of ensuring safety of Aircraft

operations. The provisions of Section 9-A(I)(i) provides

that the Central Government may issue a Notification

directing that no building or structure shall be 32

constructed or erected on any land within 20 Kms.,

from the Aerodrome Reference Point (ARP) and also

direct the owner or person having control of such

building/structure to demolish such building or

structure. Section 9-A(I)(ii) provides that the Central

Government may by such notification direct that no

building or structure higher than such height as may be

specified in the notification shall be constructed or

erected on any land within such radius not exceeding

20 Kms from the ARP. Further, it stipulates that where

the height of any such building within the said radius is

higher than that stipulated in the notification, the

owner or person in control of the said structure can be

directed to demolish the building so as to conform to the

stipulated height. In pursuance of the provisions of

Section 9-A of the Act, the Central Government has

issued a Gazette Notification dated 14.1.2010 regulating

the constructions in and around different Aerodromes.

Admittedly the HAL Aerodrome is a Defence Aerodrome 33

as may be seen from Annexure-III C to the notification

Annexure-B. The height restriction for construction of

any building within four kilometers radius from the HAL

ARP is 45 meters from the Aerodrome elevation. The

Aerodrome elevation of HAL Airport has been notified as

888 meters in the notification, Annexure-B. Adding the

maximum permissible height of 45 meters, the

maximum permissible height of any building within

Inner Horizontal Surface (IHS) of HAL Airport is 888+45

equivalent to 933 meters. The data available with HAL

Airport indicates that the elevation of the HAL Airport is

887.5 and hence, the respondent has taken the lower

figure i.e., 887+45 meters, the maximum permissible

limit and therefore, the maximum permissible

limit/height would work out to 932 meters. Clause 1.4

of the Notification provides for dimension and

permissible height of Inner Horizontal Surface. Since

the runway length of HAL Airport is 3306 meters, above

1800 meters, item No.4 of Clause 1.4.1 would apply and 34

it stipulates that the maximum permissible height of

Inner Horizontal Surface should be at 45 meters both in

respect of instrument and non-instrument runways.

14. The 1st respondent further contended that it

issued NOC purely on the basis of the material provided

by the petitioner in respect of the elevation of the sital

area where construction was sought to be put up

wherein the elevation has been shown as 870 meters

above the Mean Sea Level. It did not do any

independent survey of the site, where the petitioner

intended to put up construction and solely on the basis

of the material provided by the petitioner, NOC Dated

28.10.2011 was issued as per Annexure-A. However, it

has been clearly specified in the said NOC that the

construction shall not exceed 932 meters above the

Mean Sea Level and if at any stage, it is established that

the data tendered by the applicant is actually different

on site which would adversely affect Aircraft operation, 35

the structure in respect of which NOC was issued will

have to be demolished at its own cost. Since the

notification, Annexure-B, clearly stipulates the

maximum elevation at 932 meters above Mean Sea Level

and any construction above such height would

adversely affect Aircraft operations, since the Central

Government only after undertaking such study relating

to Aircraft operations, has stipulated the height

restrictions in the said notification and there is no

requirement for any authorities including Airport

Authority of India to undertake any fresh study

regarding the adverse affect of the height sought to be

achieved.

15. It is further contended by the 1st respondent

that the primary purpose of issuing NOCs to high rise

buildings is to restrict obstacles within the imaginary

limiting surfaces called Obstacle Limitation Surfaces

(OLS) and any penetration of the limiting surfaces 36

endangers safety. The Gazette Notification dated

14.1.2010 has been developed and promulgated keeping

in view the operation at Civil Aerodromes. At para 2(b)

of the Gazette Notification, it is categorically stated that

for Defence Aerodromes, Defence Authorities shall be

responsible for issuing NOCs in accordance with the

Notification and subject to any other restrictions and

conditions which such authorities deem fit. Under the

circumstances, imposition of additional restrictions or

conditions are necessary due to the nature of operations

and traffic characteristics which are as under:

(a) Operation of Single Engine Aircrafts;

(b) Single occupancy Cockpit and consequent High Cockpit workload;

(c) Very high rate of descent, Climb and Turn;

(d) Higher sped of operation including higher landing speed;

(e) formation flying;

(f) Low endurance flying;

(g) Low level flying requirement;

37 (h) Tactical combat training (sudden variations in altitude and direction);

(i) Large number of Aircrafts launched and recovered within short durations;

16. HAL Aerodrome is a unique Defence

Aerodrome in comparison to all other Defence

Aerodromes for the following reasons:

(a) HAL is the sole premier Aircraft, Design and Manufacturing Organisation in the country promoting a safe test flying environment which is critical for National Defence;

(b) Flying operations at HAL involve test flying of experimental, unproven, developmental Aeroplanes and Helicopters;

(c) Test flying of prototypes and pre- production models;

(d) Special exercises are carried out such as "Practice Forced 38

Landing",(PFL) which involves an unconventional approach to land;

(e) Carrying out Single Engine landing of a multi engine Aircraft for test purposes;

(f) Flying in poor weather conditions (low visibility);

(g) Switching off engines and re-ignition in mid-air;

(h) Post production Test flying.

The nature of work stated supra carried out in HAL

Aerodrome entail a high level of risk and hence, safety

margins from the obstacle on ground around the Airport

are essential and therefore, additional restrictions are

imposed such as no violation of obstacle limitation

surface shall be permitted under any circumstances as

they are inviolable and non-negotiable and also as a

corollary, no requests for Aeronautical studies in the 39

event of a violation of the said surface shall be

entertained.

17. It is further contended by the 1st respondent

that the petitioner-Company is a Mumbai based

Company involved in building and construction of

residential and commercial properties. Since the site at

which the petitioner proposed to undertake construction

activity fell within the HIS of HAL Aerodrome, an

application seeking 'No Objection' was filed on

21.9.2011 by the petitioner along with an undertaking

that they proposed to construct to the maximum height

of 110 meters and enclosed a Certificate issued by M/s

Precision Surveys (India) Private Limited dated 5.9.2011

depicting the MSL level of the site to be 870 meters.

Another certificate issued by the Professor and Head,

Department of Civil Engineering, Dr. Ambedkar

Institute of Technology on the very same date, was

produced certifying that the Latitude, Longitude and 40

MSL level submitted by M/s Precision Surveys was

found to be correct upon verification. On receipt of the

said application, it informed the petitioner by letter

dated 28.9.2011 that the height clearance is restricted

to the height of 932 meters and therefore, the petitioner

was asked to submit revised undertaking along with

building plans/revised elevation and location plan to

respondent restricting the same to 932 meters AMSL.

Therefore, the petitioner filed another application dated

3.10.2011 along with a revised drawing and also gave

an undertaking restricting the construction upto 932

meters AMSL, pursuant to which, it issued 'No

Objection Certificate' dated 28.10.2011 to the petitioner.

18. It is the further contention of the 1st

respondent that in the 'No Objection Certificate' dated

28.10.2011, the same was being issued on the express

understanding that the site elevation of the proposed

building is 870 meters AMSL and therefore, a structure 41

to the height of 62 meters was permissible (870+62=932

meters AMSL). It was also clarified therein that in the

event, at any stage, it was established that the said data

is actually different from the data tendered along with

the application, then the structure would have to be

demolished at the cost of the petitioner and therefore,

on their own interest, it was advised to verify elevation

and other data furnished before embarking on the

proposed construction. It was also clarified that the

petitioner could be called upon to demolish the

structure in whole or part pursuant to the provisions of

Section 9-A of the Act, or any other notifications issued

pursuant to the same.

19. It is the further contention of the 1st

respondent that during August-September 2012, eight

months after the issuance of 'No Objection Certificate', it

conducted a random check of NOC applications with

Survey of India maps, which revealed that there was 42

vast difference in AMS Levels between what was

submitted by the petitioner and the data available with

them. A copy of the Survey of India map pertaining to

Bangalore District is produced as Annexure-R1.

Therefore, the petitioner was put on notice of the same

on 15.9.2011 and was once again informed that the

'NOC' was issued based on the express understanding

that the site elevation tendered was incorrect and

therefore, in view of the vast difference with the

available data, the petitioner was advised to carry out

re-survey of the proposed site in the presence of the

HAL, NOC Committee within 30 days at the mutually

convenient date and time. Inspite of the said notice,

neither positive action was taken nor was any response

given regarding the same by the petitioner. In view of

the evasive attitude of the petitioner in not conducting a

re-survey as advised, it was constrained to issue

another reminder on 19.2.2013 (Annexure-O) reminding

the petitioner to carryout a re-survey in presence of the 43

HAL-NOC-Committee within 30 days at a mutually

convenient date and time.

20. It is the further contention of the 1st

respondent that on 15.3.2013, the petitioner for the first

time replied by issuing a letter stating that the co-

ordinates and AMSL values were determined by reputed

company (allegedly authorized by HAL to conduct

topographical surveys) and therefore, stated that the

construction activity was in order and were willing to

provide further clarifications on the same. In the

meanwhile, it appears that the petitioner also conducted

an Aeronautical Study on its own without any

requirement or advice from HAL in this regard by an

Aviation Consultant, who submitted a report on

12.3.2013. However, the report disclosed that the study

was conducted on the basis of data available in the

public domain and there may be minor variations to an

extent of 5% (which is a very high margin in Defence 44

Aviation). The said Aeronautical Study was conducted

on the petitioner's request to examine the impact of a

structure at the height of 970 meters AMSL and it was

found that the structure was restricted to an height of

964 meters AMSL. The petitioner was not required to

conduct any Aeronautical Study and the only

requirement for them was to conduct a re-survey of the

site to arrive at the correct site elevation which cannot

be done through an Aeronautical Study and can only be

done by a ground level survey on the basis of the

Longitude and Latitude co-ordinates of the construction

site.

21. It is further contended that on 28.3.2013,

respondent informed the petitioner by the letter that no

surveyor or certifier is authorized by HAL and HAL

insists on Location and Elevation Certificate from a

Local Municipal Authority and once again advised to

conduct a re-survey in view of the vast difference in 45

AMS Levels between what was submitted by the

petitioner and the data available with it. On 12.4.2013,

it informed the petitioner that they have to conduct an

authentic survey by a Government Agency, such as the

Survey of India or Karnataka State Remote Sensing

Application Centre (KSRSAC). On 15.5.2013, the 1st

respondent issued a letter to the Survey of India

requesting them to carry out survey and submit the

report directly wherein the scope of the survey was also

mentioned and simultaneously issued a letter to the

petitioner informing that Survey of India has agreed to

undertake the survey and to co-ordinate with them to

ensure that the same is completed in a timely manner.

The petitioner, accordingly, co-ordinated with the

Survey of India to carry out the said survey. In the

meanwhile, the 1st respondent issued a letter dated 20th

May, 2013 to the petitioner advising them to stop

further construction until the survey is carried out and

the permissible Top Elevation is arrived at. Responding 46

to the said letter, the petitioner on 20.5.2013 stated

that they have suspended vertical construction activity

and also informed that the proposed survey would

reconcile the issue.

22. But surprisingly, for the first time, the

petitioner stated that they had undertaken an

Aeronautical Study with the AAI inspite of no advice

having been given by it to that effect. Thereafter, the

petitioner had also issued a letter to the Chairman, AAI

stating that they are required to approach AAI to

urgently conduct an Aeronautical Study which is wholly

contrary to the correspondence being exchanged. It was

never its case that it was required to conduct an

Aeronautical Study, but in fact, it was consistently

advising the petitioner to have the field survey done by

either Survey of India or Karnataka State Remote

Sensing Application Centre (KSRSAC). Inspite of several

reminders, the petitioner failed to conduct the survey 47

through the Survey of India and therefore, on

21.6.2013, the petitioner was informed to alternatively

contact the Director, KSRSAC to carry out the survey in

order to avoid any further delay. On 25.6.2013, the 1st

respondent was informed by the KSRSAC that they are

willing to take up the field survey at the site of the

petitioner and also that they had the requisite expertise

to do so. Accordingly, it made a request dated

27.7.2013 to the KSRSAC to give priority to the survey

proposed to be conducted by the petitioner. Obliging to

its request, the KSRSAC issued a pre-revised bill on

29.7.2013 for the Digital Global Positioning Systems

Field Survey Work to provide Latitude, Longitude and

AMS levels. The survey was tentatively scheduled to be

conducted on 5.8.2013. On 3.8.2013, the petitioner

issued another letter to KSRSAC informing them that

the survey should also include an Aeronautical Study to

determine maximum permissible height and requested 48

them to include charges for the Aeronautical Study in

the pre-revised bill.

23. It is further contended that on 7.8.2013, it

wrote another letter to the petitioner stating that they

have failed to pay the fees and get the survey done by

KSRSAC inspite of it having been scheduled to be held

on 5.8.2013 and that the survey of the site had nothing

to do with an Aeronautical Study. The petitioner was

informed that they were necessarily marginalizing the

issue and further it was quite surprising that they had

sent to the HAL, a Demand Draft drawn in favour of AAI

to conduct an Aeronautical Study. Inspite of no advice

having been given to that effect, the petitioner was

advised to get the survey done by KSRSAC and report

the same before 16.8.2013 failing which suitable action

would have to be taken. The petitioner responded to the

said letter on 14.8.2013 and once again insisted for

Aeronautical Study inspite of being informed of the 49

difference between Civil and Defence Aircraft activities.

Even as on 16.8.2013, the petitioner failed to submit a

re-survey report conducted by KSRSAC and therefore,

left with no other option, it was constrained to cancel

the 'No Objection Certificate' on 16.8.2013.

Accordingly, the petitioner was informed that for re-

issuance of the 'NOC', a survey report from KSRSAC

should be submitted showing AMS Levels. It is against

the said information, the present writ petition is filed.

24. It is the further case of the 1st respondent

that the petitioner has contended that the point on

controversy can be reconciled by conducting an

Aeronautical Study by the AAI on the basis of the ICAO

guidelines at Annex-14. It is respectfully submitted that

the Airports Authority of India or the International Civil

Aviation Organization (has come into existence

pursuant to the Chicago Convention, 1944) are only

concerned with Civil aircraft operations and does not 50

regulate any Aerodromes which are of Defence character

and Aeronautical Study can be conducted by AAI in

respect of Civil Airports only. It is further contended

that on 6.9.2011 a letter came to be issued by the AAI

to M/s Shobha Developers Limited, Bangalore informing

that AAI conducts Aeronautical Study only in respect of

Civil Airports. Accordingly, a letter dated 7.8.2012 was

addressed to M/s Britania Industries Limited stating

that Aeronautical Study cannot be done by AAI since

Bangalore Airport is a Defence Aerodrome. Copy of the

letter of the KSRSAC dated 25.6.2013 along with the

procedure adopted by them for conducting the survey

AAI has also made it abundantly clear in their letter

dated 25.6.2013 that they cannot accept individual

applications for Aeronautical Study for sites which fall

within its jurisdiction. It is only in the event, if the HAL

approaches AAI to conduct the same, it would do so. It

is further contended that the AAI do not conduct

Aeronautical Study even for the purpose of issuance of 51

NOCs around Civil Aerodromes. As stated, the point in

dispute is the AMS Level of the construction site which

can be ascertained only by a field survey. Therefore, the

1st respondent sought to reject the writ petition.

25. The 1st respondent has denied the averments

made in each paragraph of the writ petition by filing

statement of objections, contending that there is no

arbitrariness, illegality or lack of application of mind as

urged by the petitioner in cancellation of NOC as the

same is being done for the detailed reasons stated

therein and in the larger interest of public/aircraft

safety. The averment of the petitioner that the

respondent has erred in limiting the construction to 932

meters AMSL is denied. The respondent has arrived at

the said figure after a conclusive examination of the site

elevation at HAL Airport, runway strip and Approach

Funnel, Inner Horizontal Surface of the HAL Aerodrome.

Hence, the action of the 1st respondent cannot be said 52

to be arbitrary to warrant inference under the

extraordinary jurisdiction vested with this Court under

Article 226 of the Constitution of India.

26. I have heard the learned Counsel for the

parties to the lis.

III Arguments advanced by the learned Counsel for the petitioner

27. Sri Udaya Holla, learned Senior Counsel

appearing for the petitioner has contended that the

impugned order passed by the 1st respondent,

Annexure-AQ canceling the 'No Objection Certificate' for

height clearance is erroneous and contrary to the

material on record. He would further contend that the

provisions of Section 9-A of the Aircrafts Act, 1934

provides height of the building around Airports and the

Central Government is empowered to issue notification,

if necessary and expedient so to do for the safety of

aircraft operations, it may, by notification in the Official 53

Gazette. He would further contend that the NOC dated

28.10.2011 clearly stipulates that, if however, at any

stage, it is established that the said data as tendered by

the said applicant is actually different from one

tendered and which could adversely affect aircraft

operations, the structure of part(s) thereof in respect of

which the NOC is being issued will have to be

demolished at his own costs as may be directed by the

HAL Airport, Bangalore. The applicant(s) is/are

therefore advised in his/their own interest to verify the

elevation and other data furnished for the site, before

embarking on the proposed construction.

28. The learned Senior Counsel would further

contend that in view of the Notification dated 14.1.2010

bearing No. S.O.84(E) issued by the Ministry of Civil

Aviation as per Annexure-B stipulates that no building

or structure shall be constructed or erected and no tree

shall be planted on any land within the limits specified 54

in Annexure- I and II from Civil and Defence

Aerodromes and Aeronautical communication stations

listed in Annexure-IIIA, IIIB, IIIC, IIID and IIIE without

obtaining 'No Objection Certificate'. Clause-2(b) of the

said notification stipulates that for Defence aerodromes,

defence authorities shall be responsible for issuing No

Objection Certificate in accordance with the notification

and subject to any other restriction or condition which

such authorities deemed fit for issuing the 'No Objection

Certificate'. Clause-3 of the said notification stipulates

that no building or structure higher than the height

specified in Annexure-I and II shall be constructed or

erected and no tree which is likely to grow or ordinarily

grows higher than the height specified in the said

Annexure I and II shall be planted on any land within a

radius of twenty kilometers from the aerodrome

reference point. He would further contend that

Annexure-II of the said notification dated 14.1.2010, the

height or permissible elevations shall be calculated 55

based upon the Annex 14 obstacle limitation surfaces,

the radio navigation aids based on Annex 10 and the

operational requirements for minimum altitudes of

various segments of published instrument approach

procedures based on Document 8168, VOL II of

International Civil Aviation Organisation (ICAO).

29. The learned Senior Counsel would further

contend that in the very notification, Clause 1.4

specifies the Inner Horizontal Surface. Clause 1.4.1

Dimensions and permissible heights of Inner Horizontal

Surface are given in the table as under:

RUNWAY INSTRUMENT NON-INSTRUMENT Code Length Radius Height Radius Height No. (Meter) (Meter) (Meter) (Meter) (Meter) 1 <800 3500* 45 2000* 45

2 800<1200 3500* 45 2500* 45

3 1200<1800 4000** 45 4000** 45

4 1800 and 4000** 45 4000** 45 above

wherein it has been mentioned that the radius shall be

measure from the Aerodrome Reference Point and the 56

Radius shall be measured from the extremities of the

Runway.

30. The learned Senior Counsel would further

contend that under Clause 4 of the very notification

dated 14.1.2010 prescribes the Shielding Benefit,

wherein the shielding principles are employed with

respect to natural terrain/duly authorized existing

obstacles which penetrate above the obstacle limitation

surfaces described and as contained in this document,

subject to aeronautical study, if considered necessary

by the competent authority. It is further contended that

Clause-5 of the said notification prescribes Conduct of

Aeronautical Study providing the guidelines which are

as follows:

(i) The request for aeronautical study shall be processed by Airports Authority of India on case to case basis;

57 (ii) Aeronautical study shall be undertaken by a predetermined and approved agency and as per guidelines;

(iii) Recommendations of aeronautical study after approval of the competent authority shall be considered by Airports Authority of India for issuing No Objection Certificate for the height sought.

31. The learned Senior Counsel would further

contend that in the very notification as per Clauses

6.1.1.- Annex-14 Criteria -

(i) The site of the proposed buildings/installations shall be marked on the zoning map of the aerodrome, prepared by the aerodrome operator, where Annex 14 surfaces have been drawn;

(ii) If the location is within the approach/take off surface, the permissible applicable heights in the approach/take off climb surface, transitional surface, Inner Horizontal Surface/conical surface shall be calculated;

58

(iii) If the site is located outside the approach/take off climb surface, the height shall be determined as per the location applicable to the relevant surface (transitional, Inner Horiztontal Surface, Conical or Outer Horizontal Surface).

The learned Senior Counsel has drawn the attention of

the Court to Clause 6.3 of the very notification

prescribing that the lowest height determined based on

Annex 14, Annex 10 and Procedure for Air Navigation

Service Operations (PANS OPS) shall be the permissible

height of the proposed building/installations for which

No Objection Certificate is to be issued.

The learned Senior Counsel drawing attention of the

Court to Annexure-IIIC of the very notification providing

List of Defence Aerodromes wherein at Serial No.5

Bengaluru (HAL) Airport is mentioned as follows:

S. COORD.LAT/LO ELEV.(IN RUNWAY DIMENSION OWNER Nos.

59

AIRPORT STATE NG(IN MTRS.) ORIENTA DEGREES TION

5 BENGALURU KARNATAKA 125703N 888 09/27 3306x45 HAL

0773957E

32. The learned Senior Counsel further

contended that paragraphs 2 and 4 of the letter dated

28.3.2013 written by the Deputy General Manager

(Aerodrome) to M/s Chalet Hotels Limited, reads as

under:

"2. No surveyor or certifier is authorized by HAL- NOC Committee to survey or to certify the location and elevation of a site. HAL insists only on "Location and Elevation Certificate"

from the local municipal authority (i.e., BBMP in your case). HAL-NOC-

Committee has no role in surveying and verifying the elevation of a site. This practice is being followed by Airports Authority of India (AAI) and the same is adopted by HAL."

60

"4. In para 3 of the NOC issued, it is clearly mentioned that the clearance for 932 M AMSL (870M (Site Elevation)+ 62M (Height of the structure)) was issued based on the information provided by you. You were also advised in your own interest, to verify the site elevation and other data furnished for the site by you, before embarking on the proposed construction, to avoid any possible violation of the permissible elevation of 932M in the future."

The learned Senior Counsel further contended that the

Airport Authority of India has granted NOC to various

projects and cancellation of NOC for height clearance as

per Annexure-AQ dated 16.8.2013. During the random

checkup, the site elevations were compared with that of

given in the Survey of India (SOI) maps and it was

observed that the declared elevation of 870 M AMSL for

the above mentioned site varies significantly i.e., Actual 61

elevation could be as high as 890 M AMSL. Various

letters were referred for advising which read as under:

(a) Ref.No.ASC/DGM(AO)/131/697/2012 dated 15/9/2012.

(b) Ref.No.ASC/DGM(AO)/131/123/2013 dated 19/2/2013.

(c) Ref.No.ASC/DGM(AO)/131/241/2013 dated 12/4/2013.

(d) Ref.No.ASC/DGM(AO)/131/287/2013 dated 27/4/2013.

(e) Ref.No.ASC/DGM(AO)/131/340/2013 dated 20/5/2013.

(f) Ref.No.ASC/DGM(AO)/131/420/2013 dated 21/6/2013.

(g) Ref.No.ASC/DGM(AO)/131/433/2013 dated 2/7/2013.

(h) Ref.No.ASC/DGM(AO)/131/494/2013 dated 27/7/2013.

for getting resurvey done. However, in the said letter, it

was observed that inspite of several reminders; the

petitioner had failed to carry out resurvey done. It was

also noted that vide letter

No.KSRSAC/48/dgps(PB)/(12)/2012 dated 29th July, 62

2013 addressed to the petitioner, Karnataka State

Remote Sensing Application Centre (KSRSAC) had

offered to carry out the survey of the site on 5th August,

2013, and the opportunity of which was also not utilized

by the petitioner in getting the resurvey done. Inspite of

this, one more opportunity was given to get resurvey

done within 16th August 2013. Consequently, NOC

issued was cancelled as per Annexure-AQ. He further

contend that before cancellation of NOC, the

respondents ought to have considered the provisions of

Section 9-A of the Act and Rules 3 and 6 of the Aircraft

(Demolition of Obstructions Caused by Buildings and

Trees Etc.) Rules, 1994 (for short, 'the Rules').

Therefore, an NOC for height clearance of 62 meters

Above Ground Level (AGL)/932M Above Mean Sea Level

(AMSL) was issued by the HAL, vide letter

No.ASC/CM(AO)/181/HAL-BG-238/2011 dated 28th

October 2011, for construction of residential building at

the site bearing Sy.Nos.21, 22, 42, 52 and 1B, located 63

at Koramangala Industrial Layout, Jakkasandra village,

BBMP Ward No.68, Bangalore, based on the site

elevation of 870M AMSL declared by it in the NOC

application.

33. The learned Senior Counsel would further

contend that International Standards and

Recommended Practices, Annex-14 to the Convention

on International Civil Aviation Aerodromes, Clause 4.2 -

Obstacle limitation requirements prescribes the

requirements for obstacle limitation surfaces specified

on the basis of the intended use of a runway i.e., take-

off or landing and type of approach, and are intended to

be applied when such use is made of the runway. In

cases where operations are conducted to or from both

directions of a runway, then the function of certain

surfaces may be nullified because of more stringent

requirements of another lower surface. Clauses

4.2.4 prescribes Recommendation where New objects or 64

extensions of existing objects should not be permitted

above the conical surface or inner horizontal surface

except when, in the opinion of the appropriate

authority, the object would be shielded by an existing

immovable object, or after aeronautical study, it is

determined that the object would not adversely affect

the safety or significantly affect the regularity of

operations of Aeroplanes.

34. Under Clauses 4.2.5 prescribes

Recommendation wherein existing objects above any of

the surfaces required by 4.2.1 should as far as

practicable be removed except when, in the opinion of

the appropriate authority, the object is shielded by an

existing immovable object, or after aeronautical study, it

is determined that the object would not adversely affect

the safety or significantly affect the regularity of

operations of aeroplanes.

65

There is also a Note that because of transverse or

longitudinal slopes on a strip, in certain cases the inner

edge or portions of the inner edge of the approach

surface may be below the corresponding elevation of the

strip. It is not intended that the strip be graded to

conform with the inner edge of the approach surface,

nor is it intended that terrain or objects which are above

the approach surface beyond the end of the strip, but

below the level of the strip, be removed unless it is

considered they may endanger aeroplanes. Clause 4.2.6

prescribes Recommendation in considering proposed

construction, account should be taken of the possible

future development of an instrument runway and

consequent requirement for more stringent obstacle

limitation surfaces.

35. Learned Senior Counsel further contended

that Table 4.1 provides Dimensions and Slopes of

Obstacle Limitation Surfaces-Approach Runways, 66

prescribing Inner Horizontal height as 45 m and radius

as 4000 m. He further contended that the Air Traffic

Management Circular No.4 of 2010 (ATMC) is issued by

the Airports Authority of India and - The procedure for

issuance of NOC under the said Circular is as under:

Clause 4.2 prescribes that the applicant shall submit

the application for NOC on prescribed form (Appendix-

1). The applicant will provide the exact location of the

proposed construction on the grid map/zoning map of

the concerned aerodrome along with the coordinates in

WGS-84 system. The applicant shall be responsible for

the correctness and integrity of site data furnished in

the application. The applicant shall also submit an

undertaking to the effect that the data furnished in the

application is correct in all respect and in case, at any

stage, the data provided by the applicant is found to be

incorrect, the NOC issued shall automatically stands

cancelled. The application should be accompanied by 67

the site elevation of the proposed construction duly

authenticated by the Local Authorities.

Clause 4.11 prescribes that RED/APD may constitute a

Committee at Regional/ Station Level for verification of

proposed site.

Clause 4.12 prescribes that the Regional/Station Level

NOC Committee shall be competent to issue NOC for

permissible heights, in all cases, both within the

applicable Obstacles Limitation Surfaces (OLS) as well

as beyond the limits of OLS.

36. The learned Senior Counsel further

contended that in paragraph 23 of the reply to the

rejoinder statement of the petitioner by respondent i.e.,

M/s Hindustan Aeronautics Limited, in W.P.No.37571/

2013, the respondent has stated that, "It is true that

elevation certificates of M/s Precision Surveys have

been accepted by the respondent in the past, however,

there was no discrepancy or difference in the data 68

furnished therein." He further contended that the

Precision Surveys (I) Pvt. Ltd., is on par with the

petitioner. The same was accepted by respondents and

same Precision Surveys done in respect of petitioner is

not accepted by the respondents.

37. The learned Senior Counsel further

contended that in Writ Petition No.11486/2008 an

affidavit is filed by the 2nd respondent - Mr. Rajender

Sharma, Head, Airport Service Centre, HAL, Bangalore,

and paragraphs 2, 7, 9 and 10 of the affidavit read thus:

"2. I state that the petitioner preferred the above said writ petition challenging the agreement entered into between BIA and the Union of India in the year 2008 itself. The second respondent has also filed statement of objection dated 10th Dec 2008. The second respondent is a Public Sector Undertaking under the Ministry of Defence, Government of India. The Company is engaged in 69

Design, Manufacture and Maintenance of Aerospace, Defence Equipments and was operating HAL Airport for Commercial (Passenger/ Cargo) as well as for Defence purposes prior to 23.5.2008. The HAL Airport was closed consequent upon Notification dated 16.5.2008. However the use of HAL Airport continued to operate Defence and General Aviation purposes.

7. I state it is pertinent to mention here that separation standards prescribed in ICAO (International Civil Aviation Organisation) documents and DGCA Guidelines are strictly adhered by HAL ATC for both civil and military aircraft movement at all times. The safety measures for all the flights whether it is Defence or Civil Flights is one and the same and the facilities which are extended cannot be distinguished between Civil Flights as well as Defence Flights.

70 9. I state that before closure of the Airport dated 23.5.2008 the revenue earning was about Rs.250 crores during the year 2007-2008. Though the Domestic Air Service has been abandoned the said airport is intact with all its infrastructure and paraphernalia and the HAL Airport is ready and fit condition if the domestic airlines is ready to operate from the HAL Airport. Once if the domestic airlines are allowed to operate from HAL Airport we are ready to support such operations. In such an event the present HAL Airport is in a position to accommodate domestic airlines.

10. I state that if a chance is proved or an opportunity is extended to HAL we are ready to undertake and provide all facilities and infrastructure for the purpose of running the Domestic/International flights."

71 38. The learned Senior Counsel further

contended that the opinion expressed by the experts,

Mr. Satendra Singh, Senior Independent Expert, Former

DGCA, and Mr. V. Somasundaram, Senior Independent

Expert, Former Member (ANS), AAI, is reproduced as

under:

"3. The Aeronautical Study conducted by AAI pursuant to the direction of the Hon'ble High Court for the structure constructed and to be constructed by CHPL, is in accordance with the notified parameters for HAL airport and the notifications issued under Section 9A of the Aircraft Act, 1934 [i.e., S.O.84(E) dated 14.1.2010 and G.S.R.751 dated 30.9.2015 which has superseded S.O.84(E)].

The Aeronautical Study conducted by AAI has concluded that the structure height of 954.41 mtrs. AMSL is 72

permissible and would not adversely affect aircraft operations.

In our opinion, the objections raised by HAL would not affect the outcome of the Aeronautical Study Report of AAI."

He further contended that in the Order dated

05.11.2015 passed by this Court in the present writ

petition i.e., WP No. 37571/2013, it has been observed

that "in order to elucidate and amplify the direction at

paragraph 45 of the order dated 31.07.2014, it is

appropriate to modify/ clarify as follows:

"That the aeronautical study of Bengaluru (HAL) Aerodrome is for the purpose of ascertaining as to whether or not the building constructed or to be constructed to the height of 62 meters above the ground level of property in question in accordance with notified parameters and Annexure-B to the 73

petition for HAL Airport would affect (safety) of the Airport operations."

39. The learned Senior Counsel further

contended that the procedure for issue of NOC for

height clearance by HAL is that all the cases will be

decided in accordance with the provisions of Govt. of

India Gazette and additional restrictions imposed by

HAL authorities. At present, there are three additional

restrictions/conditions imposed by HAL to facilitate

special test flying at low level. This is a deviation from

S.O.84(E):

"(i) Maximum permissible elevation within a radius of 20KM from Aerodrome Reference Point (ARP) of HAL Airport:

"1037 AMSL (150M above Aerodrome Elevation of HAL Airport 887M AMSL) instead of 1187 M AMSL (300M above 74

Aerodrom Elevation of HAL Airport as per S.O.84(E))

(ii) Criteria for the structures which do not constitute "Large Objects" mentioned in para 2.5 and 2.6 of

S.O.84(E) are not to be implemented.

(iii) Aeronautical Study for permitting more height is not applicable."

He would further contend that through the letter dated

23.11.2013, the Deputy General Manager (Aerodrome),

HAL, sought for the information as under:

a) Revised and detailed procedure for issue of NOC for height clearance was issued on 26th September 2013.

b) The procedure is effective from 26th September 2013.

c) Objections from general public were neither required nor invited.

75 d) Para 2(b) of Govt. of India Gazette Notification S.O. 84(B) dated 14th January 2010.

40. The learned Senior Counsel for the petitioner

further contended that on 12.03.2015, HAL sought for

information under RTI and invited the attention of the

Court to eAIP INDIA, VOBG AD 2.10 Aerodrome

Obstacles which gives details of the buildings and trees

which are obstacle to HAL, but they have not notified

the petitioner's building as obstacle. He would further

contend that the NOC granted by the Appellate

Committee to various authorities from 30.7.2015 to

6.1.2016 at Sl.No.31, the project is Spaceage

Consultants, Dadar, Mumbai; Distance from nearby

Airport is 3.8 Kms; height granted is 215.05 and the

remark is, as conducted and the requested height is

permitted. The Minutes of the meeting of the Appellate

Committee for height clearance held on 4.12.2015

states that, as per NOCAS, the proposed site lies in 76

Inner Horizontal Surface at a distance of 3155 meters

from runway 27 of Santa Cruz Airport. He further

contended that the said Committee on 24.6.2015

considered the Aeronautical Study report and the

maximum permissible height as per Aeronautical Study

report, taking into consideration the CNS & PANS-OPS

Criteria is 606.50 m AMSL. When the Committee asked

to recalculate the maximum allowable AGA OLS

penetration through Aeronautical Study by using

formula i.e., PE=Aerodrome Elevation +45+{1.27(x-

465)\100} where 'x' is the distance of nearest runway

extremity, the maximum allowable penetration of AGA

OLS using the above formula comes to 599.20 m AMSL.

41. The learned Senior Counsel for the petitioner

would further contend that M/s. S.B. Developers,

Mumbai also was given NOC at a distance of 56.90

mts., AMSL vide AAI Letter dated 15.4.2014. The

applicant thereafter applied for revised height of 81 m 77

AMSL vide letter dated 7.6.2014 and NOC was given

and the Aeronautical Study was conducted for 81mts.

AMSL. He further contended that the Appellate

Committee Decision for permissible height (81m AMSL)

as contained in the report was submitted to the

Chairman of the Appellate Committee consisting of

three Members, who had signed the decision for

permissible height as contained in the report to be

communicated to the applicant. The learned Senior

Counsel further contended that a Notification was

issued by the Ministry of Civil Aviation dated 30th

September, 2015 bearing No.G.S.R.751(E) framing

certain rules in exercise of Section 9A of the Act and in

supersession of the Ministry of Civil Aviation

Notification No.S.O.84(E) dated 14th January, 2010. It

was further contended that under Rule 133A Sub-rule

(2) of the Aircraft Rules, 1937 prescribes that the Civil

Aviation Requirements under Sub-rule(1) shall be

issued after placing the draft on the website of the 78

Directorate General of Civil Aviation for a period of

thirty days inviting objections and suggestion from all

persons likely to be affected thereby:

(1) The Director General under Section 133A of the Aircraft Rules 1937 may through Notices to Airmen (NOTAMS), Aeronautical Information Publication, Aeronautical Information Circulars (AICs), Notice to Aircraft Owners and Maintenance Engineers and Publication entitled (Civil Aviation Requirements) issue special directions not inconsistent with the Aircraft Act, 1934 (22 of 1934) or these rules, relating to the operation, use, possession, maintenance or navigation of aircraft flying in or over India or of aircraft registered in India;

(2) CIVIL AVIATION REQUIREMENTS SECTION 9 - AIR SPACE AND AIR TRAFFIC MANAGEMENT SERIES 'I' PART I ISSUE II, 8TH JANUARY 2010, 79

covers all aspects of aeronautical information services which include NOTAM.

(3) Definition of NOTAM - A classified notice to airmen is distributed by means of telecommunication containing information concerning the establishment, condition or change in any aeronautical facility, service, procedure or hazard, the timely knowledge of which is essential to personnel concerned with flight operations;

(4) The responsibility of issuing NOTAM is with Airports Authority of India;

(5) The NOTAMs for HAL Airports (VOBG) as seen on monthly NOTAM Summary document for January 2016 found on AAI website shows 4 NOTAMs and none of them mention anything about the impugned construction being a hazard to safety." 80

The NOTAM valid on 01.01.2016 includes A 1792/14,

VOBG stipulates Avoid ARR/DEP 0015 min prior to and

0045 min after sunset due BAT activity over the Airport.

A0305/15 states Arrester Barrier Instl at both ends of

RWY LCA RWY09. He would further contend that the

guidelines for Aeronautical study for the purpose of

evaluating the existing or the proposed structures

penetrating the obstacle limitation surfaces, reads as

under:

"3. The prime objective of the study is to ensure:-

3.1 The safety of air navigation, efficient utilization of airspace and airport by the aircraft, based on the instrument/visual flight procedures in operation and planned instrument flight procedures during normal aircraft operations and;

81 3.2 To protect the service volume of CNS facilities and their performance from either electromagnetic interference or due to physical hindrance/restriction."

42. The learned Senior Counsel for the petitioner

invited attention of the Court to the Scope of

Aeronautical study which reads as under:

"4.1 An existing or proposed structure, penetrating or expected to penetrate the obstacle limitation surfaces as detailed in ICAO Annex 14, resulting in deviation from the Standards, is presumed to be a hazard to air navigation unless the Aeronautical study determines that safety and regularity of aircraft operations is not adversely affected during the normal aircraft operations.

4.2 An aeronautical study must identify the effect of the proposed structure:

82 4.2.1 On existing and the proposed instrument flight procedures, PBN procedures, departure and arrival procedures, and the minimum flight altitudes of the air-routes, OCA, MSA and Radar Vectoring Altitudes, during normal aircraft operations.

4.2.2. Regarding physical, electromagnetic, or line-of-sight interference on the existing and the proposed, communications, navigation and surveillance (CNS) facilities.

4.2.3. Whether marking and/or lighting of the structure is necessary.

4.3. However, safety impact on the aircraft operations in degraded

operational performance mode is not analysed."

43. The learned Senior Counsel for the petitioner

further contended that the Regional/Station Level NOC

Committee shall be competent to issue NOC for 83

permissible heights, in all cases, both within the

applicable Obstacles Limitation Surfaces (OLS) as well

as beyond the limits of OLS. He also invited the

attention of the Court to Clause-5 of the Schedule-II of

the Notification issued by the Ministry of Civil Aviation

(Height Restrictions for Safeguarding of Aircraft

Operations) Rules, 2015. Relevant portion of Clause 5

reads as under:

"Conduct of Aeronautical Study and CNS Simulation Study

5.1 - The Aeronautical Study, as referred to in the Civil Aviation Requirements Section-4, Series 'B', Part I on Aerodrome Design and Operations and ICAO Annex 14, may be conducted to determine that the existing object or the proposed new object would not adversely affect the safety or significantly affect the regularity of operations of aeroplanes in pursuance of the ICAO provisions as given below:

84 New objects or extensions of existing objects should not be permitted above the conical surface and the inner horizontal surface except when, in the opinion of the appropriate authority, after aeronautical study it is determined that the object would not adversely affect the safety or significantly affect the regularity of operations of aeroplanes.

Note 2: Existing objects above an approach surface, a transitional

surface, the conical surface and inner horizontal surface should as far as practicable be removed except when, in the opinion of the appropriate authority, after aeronautical study it is determined that the object would not adversely affect the safety or significantly affect the regularity of operations of aeroplanes.

5.1.1 The request for aeronautical study shall be considered by the Member (Air 85

Navigation Services), Airports Authority of India, on case to case basis.

5.1.2 Aeronautical Study shall not be carried out in Approach and Transition surfaces.

5.1.3 Aeronautical Study, as per the established guidelines, shall be carried out by AAI, ICAO or any other agency, approved for the purpose by Ministry of Civil Aviation.

5.1.4 Based on the Aeronautical Study report, including a revised height clearance if necessary, shall be communicated to the applicant by AAI.

5.1.5 Guidelines are available at NOCAS at www.aai.aero."

44. Learned Senior Counsel for the petitioner

further contended that in pursuance of the Order dated

5.11.2015 passed by this Court in the present writ

petition, the Airports Authority of India has submitted 86

the Aeronautical Study Report in December-2015. At

Clause 1.12 of the report, it is stated that Site Elevation

Certificate issued by Karnataka State Remote Sensing

Applications Centre has reported site elevation of

892.41 meters. He further contended that as per Clause

1.3 of Aeronautical Study Report , the AAI Team

comprising of three officers viz., Shri Pan Singh, Sri

Rajkumar and Shri L. Mohanty visited the site on 30th

December 2015 to verify details of the existing structure

submitted by the party.

The learned Senior Counsel also invited the attention of

the Court to Clauses 2, 3.4, 5, 6.2 and 7 of the

Aeronautical Study Report which read as under:

"2. Aeronautical Study for the existing structure is conducted as per the guidelines approved by the Appellate Committee in its meeting held on 11th July 2014 and 26th March 2015 to ensure that:

87

2.1.1 Safety, Efficiency and Regularity of Flight Operations are maintained during normal aircraft operations.

2.1.2 Protection surfaces of existing and proposed instrument Approach procedures are not infringed.

2.1.3 Aerodrome operating minima of instrument approach procedures are safeguarded.

2.1.4 Signal-in space & performances of existing and the proposal CNS facilities are not affected.

2.2 Guidance Material

2.2.1 ICAO Criteria

i) Annex 14, Chapter 4(Obstacle Limitation Surfaces)

ii) Procedure for Air Navigation Services(DOC8168), VOL II

iii) Airport Services Manual (Part IV-

Visual Aids) 88

iv) Airport Services Manual (Part VI-

Control of Obstacles) v) ICAO DOC 9774 Aerodrome Certification

2.2.2 National Regulations i) DGCA India CAR SECTION-4 SERIES 'B', PART I on Aerodrome Design and Operations,

ii) Govt. of India notification GSR 751(E)

3.4 For non-precision and circling procedures, safety is ensured through the application Minimum Obstacle Clearance (MOC) margin above the obstacles. However, sometimes, it may result in the increase of OCA/H and thus, increasing the aerodrome operating minima (i.e. minimum visibility to land) and adversely affecting the regularity of aircraft operations. Therefore, it shall be ensured that the existing construction 89

would not raise the OCA/H of any procedure to maintain the efficiency and regularity.

5. Process of conducting of aeronautical study

5.1 The same methodology, adopted for the aeronautical study of the earlier cases of Mumbai, has been adopted for this project also.

5.2 The existing structure has been analyzed with reference to

a) Obstacle Limitation Surface criteria(Para 6)

b) PANS-OPS criteria(Para 7 & 8)

c) CNS criteria (PARA 9)

Limitation of Study: Safety impact, of allowing the OLS penetration on the aircraft operations in degraded performance mode, such as one engine 90

failure during takeoff or landing, is not analyzed as there was no laid down procedure for the same.

7. PAN-OPS Safety and Regularity Analysis 7.1 CHQ Reference No.AAI/20012/171/14 ARI-

NOC(CHALET Hotel PVT.LTD,BANGALORE) i) Coordinates : (12 55 32.743.077 37 48.999E) ii) Location : Location from RWY THRESHOLD RWY X-distance(M) Y-distance(M) 09 +2785 2312 27 -6113 2312

Location from VOR RWY FAT X-distance(M) Y-distance(M) 09 089 +5656 2312 27 262 -5895 1595

iii) Requested Top Elevation :954.41M(3131.22 feet) AMSL 91

Ultimately, the three members of the AAI Team has

come to the following conclusion in the report :

9.Conclusions:

a) The existing structure, for requested top elevation 954.41mtr AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin of 21.23 M which exceeds the permissible height of 45M by 47.17%.

b) The desired height of 954.41m AMSL is within the maximum allowable penetration of OLS as per the Aeronautical Study guidelines.

c) The Safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

c) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

92 d) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

f) Airport Operator should ensure that the applicant/owner/builder carry out marking and lighting of the structure as per the DGCA CAR and the obstacle is published.

45. The learned Senior Counsel for the petitioner

further contended that the Aeronautical Study Report

was submitted to Star Global Aero Solutions Limited,

New Delhi and after study, in its comments Star Global

Aero Solutions Limited has observed at paragraphs-7, 8

and 9 as under:

"7. Re: HAL's Statement in 1st part of Paragraph 4(iii) of its Objections:

...that the study conducted by AAI is incomplete because it has not undertaken the study of the risk analysis through degraded operational 93

performance especially when, admittedly, HAL Bengaluru Airport is a unique Defence Airport carrying out unique operations as stipulated in para- 5 of the Statement of Objections and the objections to I.A.No.1 of 2015, viz.,

"Further, HAL Aerodrome supports test flying and experimental flying pertaining to various Government Agencies like Aeronautical Development Agency; Aircraft & systems Testing Establishment of IAF National Aerospace Laboratories, Aeronautical Developmental Establishment, Centre for Air Borne Systems, etc."

SASL Comments

(a) AAI Report on page 7 states " there is no laid down procedure for aircraft operation in degraded performance mode."

All regulations for permissible height assume that aircraft operates at normal performance. All parameters for 94

calculating the permissible height, including OLS (Which is 45 mtrs. in the 4km-IHS), or shielding benefit, or aeronautical study, are and can be valid for normal operations only. The guidelines for aeronautical study clarify this aspect repetitively, as demonstrated on a plain reading of The GUIDELINES FOR AERONAUTICAL STUDY issued and published by AAI on its website, which inter alia provide as follows:-

1) The aeronautical study is for the purpose of Evaluating the Existing or the Proposed Structures penetrating the Obstacle Limitation Surfaces (i.e., for higher heights above the OLS.).

2) The PRIME OBJECTIVE OF THE STUDY IS TO ENSURE the safety of air navigation, efficient utilization of airspace and airport by the aircraft, based on the instrument/visual flight procedures in operation and planned 95

instrument flight procedures during normal aircraft operations;

3) The SCOPE OF AERONAUTICAL STUDY is to verify whether an existing or proposed structure,

penetrating or expected to penetrate the obstacle limitation surfaces as detailed in ICAO Annex 14, resulting in deviation from the Standards, is presumed to be a hazard to air navigation unless the Aeronautical Study determines that safety and regularity of aircraft operations is not adversely affected during the normal aircraft operations.

4) An Aeronautical study must identify the effects of the proposed structure:

i) On the existing and the proposed instrument flight procedures, PBN procedures, departure & arrival procedures, and the minimum flight altitudes of the air- 96

routes, OCA, MSA and Radar Vectoring Altitudes, during normal aircraft operations.

ii) Regarding physical, electromagnetic, or line-of- sight interference on the existing and the proposed, Communications, Navigation and Surveillance (CNS) facilities.

iii) Whether marking and/ or lighting of the structure is necessary. 5) However, Safety impact on the aircraft operations in degraded

operational performance mode is not analysed.

6 c) It may be stated that even in the case of Mumbai Airport which would be operating around 800 flights per day and where structures above the OLD are permitted on the basis of Aeronautical Study.

97

8. Re. HAL's Statement in 2nd part of paragraph 4(iii) of its Objections.

HAL Airport is the only Airport in the Country where activities pertaining to design, development and test flying of various types of aircrafts are undertaken by/on behalf of Indian Airforce, Indian Army and Indian Navy. Admittedly AAI has not undertaken the study keeping in view the aforesaid typical activities which are unique to the airport in question and hence the Report is not worthy of acceptance as it is potentially dangerous to allow the buildings in question to stand at the present level of 954.41M instead of the maximum stipulated level of 932M AMSL. Permitting such a height of 954.41M would, thus, 98

not be in the public/national interest as it would have a direct impact on safety of aircraft operations and safety of general public at large who reside in and around the Airport;

9. Re. HAL's Statement in paragraph 4(iv) of its Objections:

4.(iv) that the AAI has failed to take into consideration the notified eAIP parameters of HAL Aerodrome which clearly stipulates that HAL Airspace is a 'restricted airspace" involved in the activity of test flying. The report does not refer to this notified parameter nor has a study been conducted by taking this peculiar aspect into consideration.

99 It is further submitted that the Star Global Aero

Solutions Private Limited has come to the following

conclusion:

"31. Conclusion:

(a) The Aeronautical Study conducted by AAI pursuant to the direction of the Hon'ble High Court for the structure constructed and to be constructed by CHPL, is as per the notified parameters for HAL airport and the Notifications issued under Section 9A of the Aircraft Act, 1934 [i.e.S.O.84(E) dated 14.1.2010, and G.S.R.751 dated 30.9.2015 which has superseded S.O.84(E)].

(b) The Aeronautical Study conducted by AAI has concluded that the structure height of 954.41 mtrs AMSL is permissible, and would not adversely affect aircraft operations.

(c) In our opinion, the Objections raised by HAL would not affect the outcome of the Aeronautical Study Report of AAI."

100 46. The learned Senior Counsel for the petitioner

further contended that Section 9 of new Notification

provides that a panel of Chartered Engineers and

Surveyors may be assigned by Airport Authority to carry

out physical verification of details of site elevation and

coordinates as submitted by the applicant (This shows

that HAL ought to have verified details submitted by the

Precision Surveyors). He further contended that there is

no exception carved out for defence aerodromes, that

these provisions will not apply to defence aerodromes,

or that Aeronautical Study is prohibited for defence

aerodromes. The only exception carved out in this new

notification for defence aerodromes is to limit maximum

permissible height in outer-horizontal surface (upto 15

kilometers) to 150 meters and this would not apply in

the present case, since it is in respect of inner-

horizontal-surface of 4 kilometers. There is also no

exception carved out for defence aerodromes, to limit

maximum permissible height to 45 meters in inner- 101

horizontal-surface. He further contended that if the

contention of HAL that 45 Meters is the maximum

permissible height in inner-horizontal-surface is

accepted and there can be no higher building if found

safe by aeronautical study, then the following would be

rendered otiose/illegal:

1) S.9-A of the Aircraft Act

2) International Standards and Recommended Practices of ICAO

3) Notification S.O. 1589(E)

4) Notification S.O. 84(E)

5) Present GSR 751 issued under Sec.9A in supersession of SO84(E)

6) Aircraft Rule 33-A

7) CAR Series B Part I

8) ATC Management Circulars

9) Guidelines for Aeronautical-study

10) All orders of Appellate-Committee of AAI constituted by Ministry of Civil Aviation for height of above 45M.

102 If it is now held or interpreted as desired by HAL, that 45M is maximum height in the IHS, and anything above is not permissible even if found safe in aeronautical study, hundreds of structures will have to be demolished.

47. The learned Senior Counsel for the petitioner

further contended that HAL notified parameters are on

the website of HAL, accessible to any public. HAL

Aerodrome obstacles are also notified at para 2.10

where it notifies (un-named) Building, Jayanagar

Complex, Public Utility Building etc., as obstacles.

Jayanagar Complex building height indicated is 3209

FT. A dot with 3209 FT is towards the southwest of the

runway and virtually lying in the trajectory. The public

utility building is 3291 FT and it is on the northeast of

the runway and is indicated by the dot. Admittedly, the

building of the petitioner has not been notified as HAL

aerodrome obstacle.

103

48. Sri Udaya Holla, learned Senior for the

petitioner contended that this Court while disposing off

W.P.No.15688/2016 dated 06.06.2016 at paragraphs 3

and 4 held as under:

"3. Mr. Pradeep S. sawkar, learned advocate, appears and files the statement of objections on behalf of the respondent. It is submitted that all possible steps have been taken and the apprehension of the writ petitioner is imaginary.

4. We record the submission of Mr. Sawkar that the HAL has undertaken all possible steps as required under Section 9-A of the Aircraft Act, 1934, and there is no apprehension of danger to the population residing in and around HAL airport."

He further contended that, at paragraph-5 of the

statement of objections filed by the respondent-HAL in

the present writ petition it is stated as under: 104

"5. The primary purpose of issuing NOCs to high rise buildings is to restrict obstacles within the imaginary limiting surfaces called Obstacle Limitation Surfaces (OLS) and any penetration of the limiting surfaces endangers safety.

The Gazette Notification dated 14.01.2010 has been developed and promulgated keeping in view the

operation at Civil Aerodromes. At para 2(b) of the Gazette Notification, it is categorically stated that for Defence Aerodromes Defence Authorities shall be responsible for issuing NOCs in accordance with the Notification and subject to any other restrictions and conditions which such authorities deem fit. Under the circumstances imposition of additional restrictions or conditions are necessary due to the nature of operations and traffic characteristics which are as under:

(a) Operation of Single Engine Aircrafts:

105 (b) Single occupancy Cockpit and consequent High Cockpit workload;

(c) Very high rate of descent, Climb and Turn;

(d) Higher sped of operation including higher landing speed;

(e) formation flying;

(f) Low endurance flying;

(g) Low level flying requirement;

(h) Tactical combat training (sudden variations in altitude and direction);

(i) Large number of Aircrafts launched and recovered within short durations;

49. Sri Udaya Holla, learned Senior Counsel

further contended that, it is not the case of the HAL that

the petitioner has violated any parameters fixed by the

HAL. In paragraph 5 of the objections filed to 106

I.A.No.2/2014 by the 1st respondent for modification of

the order dated 31.07.2004, it is stated as under:

"The primary object of fixing the maximum height under Section 9-A of the Aircrafts Act, 1934, is to secure safety of Aircraft operations in and around the Aerodrome. Thus, the only way in which it can be ascertained is through Aeronautical study of Aircraft operations based on notified parameters for HAL Airport."

He further contended that the proviso to Rule 6C of the

Aircraft Rules, 1937 prescribes that,

"6C. xxxx xxx

"Provided also that the test flight is carried out within the specified area and in accordance with the conditions stipulated by the Director-General in his behalf and prior notice of the flight is given to the officer-in-charge of the 107

aerodrome from which the flight is to be made."

Sri Udaya Holla, learned Senior Counsel further

contended that under Civil/Military Cooperation in Air

Traffic Management approved by the Secretary General

and published under its authority by International Civil

Aviation Organization, Regulation 5.2.16 reads as

under:

"5.2.16 Experimental/trial aircraft:

Experimental/trial aircraft activity includes acceptance testing for new aircraft, aerodromes and systems research on military and non-military aircraft. The activities range in variety and ATM requirements; however each will most likely require temporary dedicated airspace to ensure safety."

50. Sri Udaya Holla, learned Senior Counsel

further contended that the Government of India, Civil

Aviation Department, at Section 2-Airworthiness, Series

F Part XVIII, Issue I, of Civil Aviation Requirements, 108

dated 23.10.1992, has enumerated the construction,

certification and operation of experimental/ amateur

built aircraft, as under:

2. "Applicability:

Aircraft Rule 15 and 50 empowers the DGCA to issue, renew or revalidate, permit to Fly and Certificate of Airworthiness respectively. Aircraft Rule 15 further requires that all aircraft registered in India possess a current and valid certificate of Airworthiness (C of A) before it is flown unless it is flown for the purpose of flight test for issuance/renewal of C of A in the vicinity of the departing Aerodrome.

3. Scope:

This part of CAR provides guidance/requirement concerning the

building, certification and operation of amateur built aircraft, explains how much fabrication and assembly, the builder must do for the aircraft to be eligible for amateur built certification in 109

the Experimental/amateur built category, and describes the role of the DGCA in the certification process."

Sri Udaya Holla, learned Senior Counsel, further

contended that, clause 7.2.3 of the said regulation

stipulates that:

"Unless otherwise authorized by the DGCA, no person may operate an aircraft that has an experimental certificate, over a densely populated or in a congested area, unless it is for the purpose of landing/take off and/or approached for landing/take off."

He further contended that paragraphs 43 to 45 of the

Order dated 31.07.2014 passed in the present writ

petition read as under:

"43. In the circumstances, prima-facie the re-survey of elevation of the 'land in question' by itself and nothing more, without an aeronautical study, cannot determine the maximum permissible 110

height of the building to be reckoned as 45 meters AMSL. Viewed in this perspective, declining the interim relief

(b) would be travesty of justice occasioning grave injustice to the petitioner.

44. Sri Udaya Holla, learned senior counsel for the petitioner is correct in his submission that the petitioner must either succeed or fail on the basis of the aeronautical study report, since it is essential for decision making over the final relief.

45. In the circumstances, no injustice will be caused to the first respondent if directed to request AAI to process petitioner's application to conduct an aeronautical study of the Bengaluru (HAL) Aerodrome at the cost of the petitioner, after due process, in compliance with clause-5 of Annexure II to the notification, Annexure-B. The 1st respondent is directed accordingly." 111

51. Against the said Order passed by the learned

single Judge, W.A.No.2572/2014 was filed and the

Division Bench of this Court, while disposing of the

Appeal, at paragraphs 5, 6, 7 and 11, has held as

under:

"5. The Hon'ble Single Judge, by the order impugned, directed the Airport Authority of India to process the application of the writ petitioner to conduct an aeronautical study of the Bengaluru (HAL) Aerodrome at the cost of the writ petitioner.

6. By the order impugned, no rights of the parties have been decided. The report that would be submitted before the Hon'ble Single Judge would be subject to the result of the writ petition.

7. Mr. Pradeep S. Sawkar, learned advocate, strenuously, submits that once the notification has been issued under Section 9-A of the Aircrafts Act, 112

1934, it was impermissible to issue another aeronautical study.

11. We, however, request the Hon'ble Single Judge to expedite the hearing of the writ petition as far as possible and to decide the matter uninfluenced by the observations made in the order impugned."

52. Sri Udaya Holla, learned Senior Counsel for

the petitioner, further contended that in the absence of

aeronautical study, it is not possible to contend that

petitioner has violated the terms and conditions of the

notification issued by the Central Government and this

Court, by the Order dated 01.09.2016, granted interim

order. He further contended that the Division Bench of

the High Court of Judicature at Bombay, in the case of

Yeshwanth Shenoy vs. The Union of India and others, in

Public Interest Litigation No.86/2014 dated 01.09.2016,

held that, 'before grating NOC from the competent

authority, care should be taken to see that height is 113

properly calculated and mean sea level is fixed. If any

appeal is filed to the appellate authority against the

order, the authorities should not exercise its discretion,

firstly, in respect of those structures which are within

the funnel area, and also those structures which fall

within four kilometers of the runway and approaches.

53. Sri Udaya Holla, learned Senior Counsel,

further contended that, in paragraph-5 of the said

judgment, it is observed by the Division Bench that, "we

are informed by the learned ASG appearing on behalf of

the Airport Authority of India that in fact discretion is

not being exercised for the purpose of relaxing the

height restrictions. We also direct the Municipal

Corporation and other planning authorities to again

calculate the height and ensure that height is calculated

from the mean sea level and only thereafter occupation

certificate may be granted. He further contended that,

in the Notice to Motion (L) No.88 of 2017 in PIL 114

No.86/2014, the High Court of Judicature at Bombay,

at paragraph-6, held that, "no prejudice would be

caused to any party if the appellate authority is directed

to process such applications which are received by it

against the rejection of height increase by the Airport

authority and the said appellate authority shall process

the said application in accordance with Clause 5 of

Schedule II of the GSR". However, the appellate

authority was directed to take final decision. The said

judgment of the Bombay High Court has been

suppressed by the HAL. He further contended that,

against the said Order passed by the Bombay High

Court dated 05th and 06th April 2018, the aggrieved

party filed SLP No.14948/2018 before the Hon'ble

Supreme Court, which came to be dismissed on

12.10.2018.

54. Sri Udaya Holla, learned Senior counsel

appearing for the petitioner brought to the notice of the 115

Court that, the order dated 23.03.2017 passed by the

Division Bench of High Court of Judicature at Bombay

in PIL No.86/2014, wherein at paragraphs 2,4,5,6,7,9

and 12 it is held as under:

"2. While hearing PIL No.86 of 2014, this Court was pleased to give certain directions by way of an interim arrangement, and had given general directions. In para 4 of an order dated 1st September, 2016, passed in the said PIL this Court has observed as under:

"4.....If any appeal is filed to the appellate authority against this order, the authorities should not exercise its discretion, firstly, in respect of those structures which are within the funnel area, and also those structures which fall within four kilometers of the runway and approaches."

116 4. In our view, the said order was passed since at the relevant time, it was not clear as to what are the exact height restrictions which were imposed. The height restrictions have been imposed by the various authorities and the several directions have been given by the Ministry of Aviation and by the appellate authority, and as such therefore, at that stage, for a limited period the said restriction was imposed by this Court.

5. It is an admitted position that so far as the appellate authority is concerned, it has powers to consider an appeal against the rejection of application for consideration of height restrictions i.e., increase in height imposed by the Airport Authority. The statutory regulations are framed under section 9A of the Aircraft Act. The said regulations empower the appellate authority to examine the appeal filed by any person being aggrieved by the rejection of the 117

application for increase in height outside the funnel area.

6. In our view, at this stage, no prejudice would be caused to any party if the appellate authority is directed to process such applications which are received by it against the rejection of height increase by the Airport authority and the said appellate authority shall process the said application in accordance with Clause 5 of Schedule II of the GSR. However, the final decision may not be taken by the appellate authority.

7. We are of the view that there are some ambiguities, firstly, regarding the actual height restriction which is imposed outside the funnel area and in the inner horizontal surface. We are also of the view that this issue can be considered expeditiously on the next date. The Airport Authority of India has also filed a notice of motions. Few other notice of motions and review petitions 118

have also been filed. All these motions and review petitions shall be placed for further hearing on 12th April, 2017 at 12.30 p.m., so that once for all the legal provisions will be taken into consideration, and secondly, the manner and method in which the calculation of the height restriction is to be done, will also be taken into consideration.

9. Airport Authority of India shall also submit AAI study report mentioned in Ministry of Civil Aviation guidelines dated 26th March, 2015 before the next date, and if possible supply its copies to all the parties.

12. We hope and trust that all the developers and builders will file an application for increase of height if they are satisfied that such an increase is within permissible limits.

119

55. Sri Udaya Holla, learned Senior Counsel for

the petitioner further contended that in the very case,

i.e., PIL No.86/2014, by the Order dated 04.05.2017, it

is clarified that all pending applications before the

appellate authority may be processed. He further

contended that the Division Bench of the High Court of

Judicature at Bombay in PIL No.86/2014 by the order

dated 5th & 6th April 2018, at paragraphs 15, 17,20 and

40 it is held as under:

"15. As clarified above, we are not presently expressing any opinion on these aspects highlighted and by relying on the written arguments. What we have before us and tendered on behalf of the Airport Authority of India is G.S.R. 751(E). After this PIL was filed, the Ministry of Civil Aviation has issued a Notification dated 30th September 2015 and it is duly published in the Gazette of India - Extraordinary [Part II - Section 3(i)]. This Notification notifies the Rules to be called as "Ministry of 120

Civil Aviation (Height Restrictions for Safeguarding of Aircraft Operations) Rules, 2015 ("2015 Rules" for short). These Rules are made in exercise of the powers conferred by sub-section (1) and clause (o) and clause (r) of sub- section (2) of Section 5 read with Section 9A of the Aircraft Act, 1934. Pertinently, these Rules supersede the Ministry of Civil Aviation Notification No. S.O. 84(E) dated 14th January 2010 published in the Gazette of India, Part II Section 3 sub-section (ii), except as respect things done or omitted to be done before such supersession. The objections or suggestions on the draft Standing Order were called from the stakeholders and it is claimed that they are duly considered by the Government to the extent admissible. In the public interest, the Rules are notified by seeking exemption from putting the Rules again in the public domain.

121 17. The Aircraft Rules, 1937 are also in place. There are also Aircraft (Demolition of obstruction caused by buildings and trees etc.) Rules, 1994. These Rules are made in exercise of powers conferred by sub-section (2) of Section 11 of the Aircraft Act, 1934. The said Rules of 1994 now have been highlighted by the Government as also on behalf of Airport Authority of India by the learned Additional Solicitor General. It is the Notification of Ministry of Civil Aviation dated 30th September 2015 and the Rules notified thereunder which would guide the Authorities.

What we have noted is that after these Rules were brought to the notice of the parties and some of them were highlighted, it is clear that the petitioner is not entirely happy with the same. In the affidavit dated 23rd August 2016 filed by Mr. Sudhir Raheja, Chairman, Airport Authority of India, it is stated that the NOC for height clearance is given by AAI in accordance with 122

Government of India, Ministry of Civil Aviation Gazette Notification No.GSR- 751(E) dated 30th September 2015.

Thus, these Rules are now governing the field. The petitioner has raised number of issues other than legality and validity of the Rules themselves. It is in these circumstances that we are of the opinion that the present petition can be disposed of by clarifying that all contentions in relation to legality and validity of these Rules and particularly the matters concerning civil aviation safety, as raised in the PIL, are kept open and it will be for the petitioner to take further steps as was orally indicated by him. The petitioner has made several allegations and the denials are on record, but presently we express no opinion thereon. In the event the petitioner desires to challenge the new Rules, then he can raise appropriate pleas and include in them what is highlighted in this petition and in the affidavits filed by him in answer 123

to the stand of the Central Government, particularly the Department of Civil Aviation, Directorate General of Civil Aviation and Airport Authority of India so also Mumbai International Airport Limited. We clarify that we have not expressed any opinion on the rival contentions.

20. On 3rd August 2015, this Court had passed an order observing that the PIL raises certain very important issues regarding aircraft safety and safety of the residents staying near the Airport. This Court noted that according to the petitioner, the Airport Regulatory Authority appears to have violated some of the regulations and has permitted increase of illegal height of the buildings around the Airport which has resulted in obstruction when aircrafts take off/land at Chhatrapati Shivaji International Airport as also Domestic Airport. This Court also observed that certain other issues regarding safety 124

norms to be followed have been raised. At that time, this Court observed that the pleadings are complete. When that order was passed, there was no notification notifying the Rules.

40. In our view, therefore, the PIL petitioner or the intervenor Mrs. S. Mangala or such other public spirited citizens, who are intending to challenge the legality and validity of the 2015 Rules, have enough time at their disposal to move a competent Court and in appropriate proceedings. We do not intend to continue the embargo or the prohibition placed by this Court on the Appellate Committee, particularly restraint on passing the final orders indefinitely. Let the Appellate Committee, if at all it is to meet on 26th April 2018, so meet and take up the cases, if at all they are placed before it, consider them strictly in accordance with the 2015 Rules and pass the final orders. We do not think all this can 125

happen in a single day as apprehended and before the scheduled hearing, the aggrieved parties like Mr. Shenoy can move the competent Court. We do not think it appropriate and proper to place a restraint on the Committee's functioning and its power any further.

The interim order passed in the PIL stands vacated with the above modifications observations."

Sri Udaya Holla, learned Senior Counsel further

contended that in the minutes of the Meeting of the

Appellate Committee for height clearance held on

22.05.2018, with regard to Aeronautical Study Cases

and Committee Decision, it is observed as under:

The Appellate Authority on 23.3.2016 approved the conduct of an Aeronautical Study for a height of 73.50m AMSL.

The Aeronautical Study Report was earlier taken up by the Appellate Committee in its meeting held on 126

28.4.2017 and was submitted to the Hon'ble High Court of Bombay as per court directive w.r.t. PIL 86 of 2014.

The Committee was informed that Aeronautical Study has indicated that the requested height of 73.50m AMSL is admissible. The Committee observed that the permitted top elevation of 73.50m AMSL is the minimum as derived from allowable penetration of OLS (through Aeronautical Study), CNS and PANS-OPS criteria.

Committees' decision: The permitted top elevation (P.T.E.) of 73.50m AMSL is approved.

Serial Nos.1 to 42 pertain to building permitted height based on aeronautical study. In so far as Serial Nos.42 to 49, shielding benefit was given.

Sri Udaya Holla, learned Senior Counsel for the

petitioner further contended that as per Committees'

decision the Permitted Top Elevation (PTE) of 145.46mtr 127

AMSL is approved. He further contended that in the

Ministry of Civil Aviation Notification dated 30.9.2015,

GSR 751(E) has been referred. The purpose mentioned

in Schedule-II reads as under:

Purpose:

The height or permissible elevation for the structure, requiring grant of NOC, shall be calculated based upon the international Civil Aviation Organization (ICAO) Annex 14 Obstacle Restriction and Removal, Annex 10 the Radio Communication, Navigation and Surveillance (CNS) aids and Doc. 8168, Vol. II defining the operational requirements for minimum altitudes of various segments of published or proposed instrument approach procedures.

Sri Udaya Holla, learned Senior Counsel for the

petitioner also referred to Obstacles Limitation Surfaces

(based on ICAO Annex 14 and DGCA India Civil Aviation

Requirements (CARs) on Aerodrome Design and 128

Operations), Clause 1.4 pertaining to Inner Horizontal

Surface (IHS), Clause 4 pertaining to Shielding criteria.

At 4.1 (iii), it is observed that inner horizontal surface

(IHS) with a distance of 2500 meters from the runway

centre line, in case of multiple runways, area

encompassed by 2500M from center line of all runways.

57. The learned Senior Counsel further

contended that Guidelines for issue of 'No Objection

Certificate (NOC) for building constructions states that

these instructions will not apply where constructions

are regulated by the provisions of the existing

acts/notification viz., Cantonments Act, 2006, Air Craft

Act, MoCA, 1934, Gazette Notification SO 84(E) dated

14.01.2011 (as revised from time to time), Works of

Defence Act, 1903, etc. In such cases the provisions of

the concerned Act/Notification will continue to prevail.

The learned Senior Counsel further contended that

Dr.A.K.Singh, Director (L & C), Government of India, 129

Ministry of Defence, addressed a letter dated

18.05.2011 to the Chief of Army Staff, Chief of Air Staff,

Chief of Naval Staff, New Delhi with regard to the

Guidelines for issue of 'No Objection Certificate' (NOC)

for building constructions stating that, of late issue of

NOC for construction on lands adjacent to Defence

Establishments has generated avoidable controversies

particularly in two recent cases viz., Sukna and Adarsh,

etc.

The learned Senior Counsel referred to the General

Procedure wherein Sl.No.5.9 prescribes that all the

cases will be decided in accordance with the provisions

of Government of India Gazette and additional

restrictions imposed by HAL authorities. At present,

there are three additional restrictions /conditions

imposed by HAL, to facilitate special test flying at low

level. This is a deviation from S.O.84(E): 130

i) Maximum permissible elevation within a radius of 30KM from Aerodrome Reference Point (ARP) of HAL Airport:

1037M AMSL (150M above Aerodrome Elevation of HAL Airport 887M AMSL) instead of 1187 M AMSL (300 M above Aerodrome Elevation of HAL Airport as per S.O. 84 (E))

ii) Criteria for the structures which do not constitute 'Large Objects" mentioned in Para 2.5 and 2.6 of S.O.84(E) are no to be implemented.

(iii) Aeronautical Study for permitting more height is not applicable.

58. The learned Senior Counsel for the petitioner

further contended that the impugned Annexure-AQ is

with regard to Cancellation of "No Objection Certificate"

(NOC) for height clearance. Paragraph 4 refers to copy

of the NOC attached (Appendix 'A'). In para 3 of the

NOC, the petitioner was advised in its own interest to 131

verify the elevation and other date, before embarking on

the construction. Para-3 also states that if it is

established that the said date tendered by you is

different from the actual one, the structure in respect of

which 'NOC' was issued will have to be demolished at its

cost and accordingly NOC stands cancelled. Sri Udaya

Holla, learned Senior Counsel further contended that

Gazette Notification dated 14.01.2010 refers to Civil and

Defence Aerodromes. He also contended that

Notification S.O.84(E) and GSR 751 (E) both refer to

Annex-14 to the Convention on International Civil

Aviation issued under Section 9.A (1) to Section 9.A(2)(b)

of the Act which read as under:

"Section 9A POWER OF CENTRAL GOVERNMENT TO PROHIBIT OR REGULATE CONSTRUCTION OF

BUILDINGS, PLANTING OF TREES, ETC.

(1) If the Central Government is of opinion that it is necessary or expedient 132

so to do for the safety of aircraft operations it may by notification in the Official Gazette,-

(i) direct that no building or structure shall be constructed or erected, or no tree shall be planted on any land within such radius not exceeding twenty kilometers from the aerodrome reference point as may be specified in the notification and where there is any building, structure or tree on such land, also direct the owner or the person having control of such building, structure or tree to demolish such building or structure or, as the case may be, to cut such tree within such period as may be specified in the notification;

(ii) direct that no building or structure higher than such height as may be specified in the notification shall be 133

constructed or erected or no tree, which is likely to grow or ordinarily grows higher than such height as may be specified in the notification shall be planted, on any land within such radius, not exceeding twenty kilometers from the aerodrome reference point, as may be specified in the notification and where the height of any building or structure or tree on such land is higher than the specified height, also direct the owner or the person having control of such building, structure, or tree to reduce the height thereof so as not to exceed the specified height, within such period as may be specified in the notification.

(2) In specifying the radius under clause (i) or clause (ii) of sub-section (1) and in specifying the height of any building, structure or tree under the said clause (ii), the Central Government shall have regard to-

134 (a) the nature of the aircraft operated or intended to be operated in the aerodrome; and

(b) the international standards and recommended practices governing the operation of aircraft."

Sri Udaya Holla, learned Senior Counsel contended that

Rule 29C of the Rules refers to-

29C. Adoption of the Convention and

Annexes-

(1) The Director-General may lay down standards and procedures not inconsistent with the Aircraft Act, 1934 (22 of 1934) and the rules made thereunder to carry out the Convention and any Annex thereto.

(2) The Director-General shall formulate the State Safety Programme and oversee its implementation." Explanation.- For the purposes of this sub-rule, "State Safety Programme" means an integrated set of 135

requirements and activities aimed at improving safety."

59. Sri Udaya Holla, learned Senior Counsel for

the petitioner further contended that this Court, by the

Order dated 07.12.2015, in the present writ petition, at

paragraphs 16, 22 and 23, held as under:

"16. In the circumstances, there appears to be sufficient misunderstanding of aspects to be reckoned by the Airport Authority of India in the matter of conducting a survey, in compliance with the directions in the order dated 05.11.2015. Suffice it to notice that the modification/clarification of the order dated 31.07.2014 is based upon pleadings of both parties and the specific direction to the AAI was to conduct the Aeronautical study of Bengaluru (HAL) Aerodrome to ascertain as to whether or not the building constructed or to be constructed to the height of 62 meters above the ground 136

level of the property in question, in accordance with the notified parameters and Annexure-B for HAL Airport, would affect (safety) of the Airport operations.

22. Sri Uday Holla, learned Senior submits that the parameters for HAL Airport are provided on e-AIP website, more appropriately Annexures-BL1 and BL2 to the memorandum of writ petition, while Sri Pradeep Sahukar, learned counsel for respondent No.1 HAL on instructions submits that the said website is that of the AAI and contents therein bind the HAL Airport authorities. The website of e-AIP of India, it is argued, contains a document with the nomenclature AD-2.10BG relating to HAL Airport, Bengaluru/domestic, furnishing all material particulars over location and administrative data constituting sufficient material to conduct Aeronautical study by AAI.

137 23. Having regard to the specific stand of respondent /HAL in its statement of objections to I.A. No.2/2014 following which by the order dated 5.11.2015 directed modification of the order dated 31.07.2014, undoubtedly, the AAI is required to comply with the said order to conduct Aeronautical study of Bengaluru (HAL) Aerodrome in terms of notified parameters, Annexure-B (S.O.84(E), to the petition for HAL Airport to ascertain as to whether or not the building constructed or to be constructed above 62 meters from the ground level of petitioner/s property would affect the safety of Airport operation and submit the report in any event by the 31st December 2015."

The learned Senior Counsel also referred the letter

written by A.K.Bhardwaj, GM(ATM-NOC), Airports

Authority of India to the General Manager (LCA-Tejas),

Hindustan Aeronautics Ltd. (HAL) dated 27th January, 138

2016 with reference to the report on the Aeronautical

Study conducted as directed by this Court in the

present writ petition (Chalet Hotels -vs- HAL) and in

the said report, at paragraph-9, has come to the

conclusion as under:

9.Conclusions:

a) The existing structure, for requested top elevation 954.41mtr AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin of 21.23 M which exceeds the permissible height of 45M by 47.17%.

b) The desired height of 954.41m AMSL is within the maximum allowable penetration of OLS as per the Aeronautical Study guidelines.

c) The Safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

139 d) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

e) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

f) Airport Operator should ensure that the applicant/owner/builder carry out marking and lighting of the structure as per the DGCA CAR and the obstacle is published.

60. The learned Senior Counsel for the petitioner

further contended that the experts from the National

Flights Test Centre (NFTC) say that, 'there is always a

degree of uncertainty during test flights'. But we carry

out the test at least 50 nautical miles south or south-

east of Bengaluru, so that it does not take place over

residential areas. He further contended that Section 11 140

of the Aircraft Act, 1934, refers to penalty for flying so

as to cause danger, which reads as under:

"11. Penalty for flying so as to cause danger.--Whoever willfully flies any aircraft in such a manner as to cause danger to any person or to any property on land or water or in the air shall be punishable with imprisonment for a term which may extend to six months, or with fine which may extend to one thousand rupees or with both."

Sri Udaya Holla, learned Senior Counsel for the

petitioner further contended that the affidavit filed by

HAL states that, eversince the beginning, the Company

and the Aircraft activity is directly under the control of

Ministry of Defence, Government of India. Various

types of test flying activities are being carried on in the

Airport by following the norms laid down in the Aircrafts

Act, 1934. The HAL airport has been in existence from

1940 and the activity being carried on within the airport 141

has never posed any danger to the inhabitants of the

nearby area. Further, the test flying activities are

undertaken in designated test flying airspaces as

notified in the eAIP manual and as such, do not fall

within the purview of the DGCA and are carried out

based on parameters set out by the military. Learned

Senior Counsel also referred to the provisions of sub

Rule (18) of Rule 3 of the Aircraft Rules, 1937, which

refers to 'Director General' means Director General of

Civil Aviation. Learned Senior Counsel referred to Rule

133A of the Aircraft Rules, 1937, which reads as under:

133A. Directions by Director- General-

(1) The Director-General may, through Notices to Airmen (NOTAMS), Aeronautical Information Publication, Aeronautical Information Circulars (AICs), Notices to Aircraft Owners and Maintenance Engineers and publication entitled Civil Aviation Requirements, 142

issue special directions not inconsistent with the Aircraft Act, 1934 (22 of 1934) or these rules, relating to the operation, use, possession, maintenance or navigation of aircraft flying in or over India or of aircraft registered in India.

(2) The Civil Aviation Requirements under sub-rule(1) shall be issued after placing the draft on the website of the Directorate General of Civil Aviation for a period of thirty days for inviting objections and suggestions from all persons likely to be affected thereby;

Provided the Director General may, in the public interest and by order in writing, dispense with the requirements of inviting such objections and suggestions or reduce the period for submitting such objections and suggestions.

(3) Every direction issued under sub- rule(1) shall be complied with by the 143

person or persons to whom such direction is issued.

61. Sri Udaya Holla, learned Senior Counsel for

the petitioner contended that in the letter dated

25.06.2013, written by General Manager, Airport

Authority of India, addressed to the General Manager

(ASC & LCA), HAL, it is specifically stated that, if

HAL/Defence Authorities approach, Airports Authority

of India can conduct Aeronautical Studies for HAL. A

fee of Rs.20 lakhs -Service Tax (Total Rs.22,47,200/-)

per Aeronautical Study case is to be paid to the Airports

Authority of India in the form of a Demand Draft

payable at Delhi along with an Agreement for

conducting Aeronautical Study. Normally it takes two

months' time for Aeronautical Study after signing of

agreement and receipt of the Guidelines for conducting

Aeronautical Study for HAL airport. He also invited

attention of the Court to the Order passed by this Court

dated 31.07.2014 that in the circumstances, prima 144

facie, the re-survey of elevation of the 'land in question'

by itself and nothing more, without an aeronautical

study, cannot determine the maximum permissible

height of the building to be reckoned as 45 mtr AMSL.

Viewed in this perspective, declining the interim relief

(b) would be travesty of justice occasioning grave

injustice to the petitioner". In the said Order, it is also

stated that "in the circumstances, no injustice will be

caused to the first respondent if directed to request AAI

to process petitioner's application to conduct an

aeronautical study of the Bengaluru (HAL) Aerodrome at

the cost of the petitioner, after due process, in

compliance with clause-5 of Annexure-II to the

notification, Annexure-B. The 1st respondent is directed

accordingly."

Sri Udaya Holla, learned Senior Counsel for the

petitioner further contended that the respondent HAL

made request dated 23.01.2017 to the Secretary, 145

Ministry of Civil Aviation, Government of India, Rajiv

Gandhi Bhawan, Safdarjung Airport, New Delhi to re-

open HAL Airport, Bangalore for shortfall scheduled

commercial operations and consider it as an RCS

Airport under the Airport Regional Connectivity Scheme

- UDAN. In para-6 of the said letter it is stated that 're-

opening of HAL Airport for commercial operations would

ease congestion of Kempegowda International airport.

This would also benefit commercial airline operations as

HAL airport will become de-facto primary alternate

airport for KIA leading to less operating costs for airlines

Currently Chennai is the primary alternate airport. In

view of the above, we look forward to a positive response

from you end for re-opening of HAL Airport.

62. The learned Senior Counsel for the petitioner

further contended that in the affidavit filed by Rajendra

Sharma in W.P.No. 11486/2008 (GM)(PIL) preferred by

the Airport Authority of India Employees Union at para- 146

4 it is stated that 'HAL Airport at Bangalore was

operating Domestic and International flights until May

23, 2008 with 360 Aircraft Movements daily on an

average. Capacity of the airport was 30 aircraft

movements/ hour and the terminal had handled 10.2

million Passengers in the year before the closure and

managed 60,000 tons of cargo during the year 2007-08.

The learned Senior Counsel also referred to para-7

wherein it is stated that 'it is pertinent to mention that

separation standards prescribed in ICAO (International

Civil Aviation Organisation) documents and DGCA

Guidelines are strictly adhered by HAL ATC for both

civil and military aircraft movement at all times. The

Safety measures for all the flights whether it is Defence

or Civil Flights is one and the same and the facilities

which are extended cannot be distinguished between

Civil Flights as well as Defence Flights.' In para-9 of the

affidavit it is stated that, before closure of the Airport

on 23.05.2008, the revenue earning was about Rs.250 147

crores during the year 2007-2008. Though the

Domestic Air Service has been abandoned the said

airport is intact with all its infrastructure and

paraphernalia and the HAL Airport is ready and fit

condition if the domestic airlines is ready to operate

from the HAL Airport. Once, if the domestic airlines are

allowed to operate from HAL Airport we are ready to

support such operations. In such an event the present

HAL Airport is in a position to accommodate domestic

airlines. The learned Senior Counsel further contended

that at para-10 of the affidavit, it is stated that, if a

chance is provided or an opportunity is extended to

HAL, they are ready to undertake and provide all

facilities and infrastructure for the purpose of running

the Domestic/International flights. Further at para-11,

it is stated that HAL Airport has handled Civil and

Military aircrafts in the past and has continued the

same till date without compromising air safety. Further

it is reiterated that HAL has got all necessary 148

infrastructure for handling commercial scheduled

flights along with military flying.

63. Sri Udaya Holla, learned Senior Counsel for

the petitioner further contended that, the Civil

Aviation Requirements, Section 9 - AIR SPACE AND AIR

TRAFFIC MANAGEMENT SERIES 'I' PART I ISSUE II,

8TH JANUARY 2010, issued by the Director General of

Civil Aviation covers all aspects of aeronautical

information services which include NOTAM. NOTAM- A

notice to airmen distributed by means of

telecommunication containing information concerning

the establishment, condition or change in any

aeronautical facility, service, procedure or hazard, the

timely knowledge of which is essential to personnel

concerned with flight operations. The responsibility of

issuing NOTAM is with Airports Authority of India. A

NOTAM is filed with an aviation authority to alert

aircraft pilots of any hazards en route or at a specific 149

location. The authority in turn provides a means of

disseminating relevant NOTAMs to pilots. The aviation

authorities typically exchange NOTAMs over AFTN

circuits. Software is available to allow pilots to identify

NOTAMs near their intended route or at the intended

destination. The Civil Aviation Requirement is issued

under the provisions of Rule 29C and Rule 133A of the

Aircraft Rules, 1937, for provision of aeronautical

information service to ensure the flow of

information/data necessary for the safety, regularity

and efficiency of air navigation.

64. Sri Udaya Holla, learned Senior Counsel

further contended that under clause 2.1, 2.1.1 of the

Civil/aviation requirement refers to Responsibilities and

Functions, which reads as under:

2.1. Responsibilities

2.1.1 Aeronautical information service (excluding publication of Aeronautical 150

Information Circulars (AIC) shall be provided by Airports Authority of India (AAI). AIC shall be published by DGCA.

2.1.2 AAI shall ensure that the provision of aeronautical data and aeronautical information covers its own territory and those areas over the high seas for which it is responsible for the provision of air traffic services.

5.1 refers to Origination.

5.1.1.1. A NOTAM shall be originated

and issued concerning the following

information:

a)xxxx

b)xxxx

c)xxxx

d)xxxx

.....

l) presence of hazards which affect air navigation (including obstacles, military exercises, displays, races and major 151

parachuting events outside promulgated sites)

He further contended that, Annexure-CX, Monthly

NOTAM Summary, A Series NOTAM are valid on 01

January 2016, NOTAM not included in the list have

been cancelled, time expired, superseded by AIP

Supplement or incorporated in the AIP, as under:

BANGALORE VOBG

A1482/14 1408011130/PERM FUEL AVBL AVGAS 100LL REFUELLING NOT AVBL

A1792/14 1409200508/PERM XXXX AVOID ARR/DEP0015 MIN PRIOR TO AND

0045 MIN AFT SUNSET DUE BAT ACTIVITY OVER THE AIRPORT

A0305/15 1502210630/PERM RWY ARRESTER BARRIER INSTL AT BOTH ENDS OF RWY09 DUMBELL40M BEYOND THR AND RWY27 DUMBELL 32M BEYOND THR.

BARRIER IS RAISEDONLY FOR FIGHTER OPS. BARRIER WHEN RAISED AT THE END OF ACTIVERWY HAS HGT OF APRX 3.4M.

BARRIER ARMS IN LOWERED PSN HASHGT OF APRX 0.25M ON EITHER SIDE BEYOND DUMBELL. BARRIER ISREMOTELY 152

CONTROLLED FM TWR. PILOTS TO EXER CTN WHILE LDG AND

TKOF

BANGALORE VOBG INTERNATIONAL

A1184/12 1206251030/PERM XXXX

HAL AIRPORT BENGALURU VOBG

A1482/14 1408011130/PERM FUEL AVBL A1792/14 1409200508/PERM XXXX A0305/15 1502210630/PERM RWY A2058/15 1511031100/PERM ILS

Sri Udaya Holla, learned Senior Counsel for the

petitioner contended that as per VOBG AD 2.10

AERODROME OBSTACLES, different obstacle types

includes Tree (Pipal), Mobile RD TFC, TV Tower,

Jayanagar Complex, Public Utility Building etc. and in 153

the aeronautical study report submitted in June 2015

by the Airport Authority of India, the following

conclusion is arrived.

(b) The safety impact of the proposed structure due to the degraded aircraft performance operations is not in the scope of this study.

(c) The proposed structure of 71.34m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

(d) The proposed structure of 71.34m AMSL within the specified geo coordinates will not adversely affect the performance of the CNS equipment.

As per the above conclusions, the requested permissible

height of 71.34m AMSL may be permitted.

The conclusion arrived at in the comments of the Star

Global Aero Solutions Limited, New Delhi, on the 154

affidavit filed by the HAL, Bengaluru, in the above writ

petition is as under:

(a) The Aeronautical Study conducted by AAI pursuant to the direction of the Hon'ble High Court for the structure constructed and to be constructed by CHPL, is as per the notified parameters for HAL airport and the Notifications issued under Section 9A of the Aircraft Act, 1934 [i.e.S.O.84(E) dated 14.1.2010, and G.S.R.751 dated 30.9.2015 which has superseded S.O.84(E)].

(b) The Aeronautical Study conducted by AAI has concluded that the structure height of 954.41 mtrs AMSL is permissible, and would not adversely affect aircraft operations.

(c) In our opinion, the Objections raised by HAL would not affect the outcome of the Aeronautical Study Report of AAI by the experts, former DGA, AAI dated 29.03.2016.

155

65. Sri Udaya Holla, learned Senior Counsel

further contended that the Prime Objective of the study

is to ensure the safety of air navigation, efficient

utilization of airspace and airport by the aircraft, based

on the instrument/visual flight procedures in operation

and planned instrument flight procedures during

normal aircraft operations. The SCOPE OF

AERONAUTICAL STUDY is to verify whether an existing

or proposed structure, penetrating or expected to

penetrate the obstacle limitation surfaces as detailed in

ICAO Annex 14, resulting in deviation from the

Standards, is presumed to be a hazard to air navigation

unless the Aeronautical Study determines that safety

and regularity of aircraft operations is not adversely

affected during the normal aircraft operations. He

further contended that in the letter dated 28.10.2013

issued by the Karnataka State Remote Sensing

Applications Centre, addressed to the petitioner-Chalet

Hotels Private Limited, it is specifically stated that 156

Finding out the permissible height of constructions and

other Aeronautical studies are not within the scope of

the work authorized by HAL.

Referring to the statement of objections filed in the

present writ petition, Sri Udaya Holla, learned Senior

Counsel contended that, during August-September

2012, eight months after the issuance of 'No Objection

Certificate', 1st respondent conducted a random check of

NOC applications with Survey of India maps, it was

revealed that the AMSL submitted along with the

application was vastly different from the data available

with them as per Annexure-R1. Para-32 of statement of

objections states that, respondent had arrived at the

said figure (932 meters) after a conclusive examination

of the site elevation at HAL Airport, Runway strip and

Approach Funnel, Inner Horizontal Surface, Outer

Conical Surface, Outer Transitional Surface and Outer

Horizontal Surface of the HAL Aerodrome. 157

66. Finally, Sri Holla, learned Senior Counsel for

the petitioner, contended that, the judgments cited by

HAL are on facts and issues which are completely

different from the facts and issues in the present

petition, and are all distinguishable in the light of the

core facts, i.e.,

1. Implementation of (a) the condition "and which could adversely affect aircraft operations, the structure or part (s) thereof ...... will have to be demolished...." as specified by HAL itself in the NOC, and (b) the Regulations i.e., the Aircraft Act, Aircraft Rules, ICAO, Notification S.O.84(E), Notification GSR 751(E).

Admittedly HAL Published "deviation" from the Notification after filing of the petition, to prohibit Aeronautical Study prospectively, and omitted the said condition while issuing further NOC's after filing of the petition.

158

2. Petitioner applying for height NOC of 110 mtrs, reduced to 62 mtrs by HAL after a conclusive examination by HAL NOC Committee (but without checking the SOI map or elevation of nearby sites and marks which were available with HAL at the time grant of NOC). Petitioner constructing 62 mtrs as expressly permitted by the HAL NOC. The construction by the petitioner was not without any NOC or an illegal construction.

3. Subsequently HAL checked the SOI map and discovered a difference of AMSL which was quantified by KSRSAC Survey Report to be of 22 mtrs.

4. AAI offering to conduct the Aeronautical Study, if requested by HAL.

5. HAL thereafter expressly admitting that - " The primary object of fixing the maximum height under Section 159 9A of the Aircraft Act, 1934 is to secure safety of Aircraft operations in and around the Aerodrome. Thus, the only way in which it can be ascertained is through Aeronautical Study of aircraft operations based on notified parameters for HAL Airport".

6. Aeronautical Study report of AAI confirming that the existing and the proposed wings do not adversely affect aircraft operations.

7. The undisputed fact, that HAL cannot and does not carry out test flying activities over the densely populated areas of Bengaluru, and HAL's admission that the safety measures for civil and defence flights is one and the same.

8. 7 experts in the field, including 2 ex- DGCAs (Director Generals of Civil Aviation), 1 former Chairman of NOC Committee of AAI, confirming the 160

procedure and safety by Aeronautical Study Report.

67. Sri Udaya Holla, learned senior counsel

relied upon the following judgments:

1. Mobilix Vs, Kirusa reported in 2017(11)SCALE 754 - Para-29

2. Shrishti Infrastructure made in W.P. 7652/2015 - Paras 10,16,18,19

3. P. Radhakrishna Naidu Vs. Govt, of A.P. reported in (1977) 1 SCC 561 - Para 13

4. New Okhla Industrial Development Authority reported in (2006) 9 SCC 524 - Paras 11,12

5A. State of U.P. vs. Lakshmi Sugar and Oil Mills reported in (2013) 10 SCC 509 - Para 20

5B. State of Bihar vs. Jain Plastics reported in (2002) 1 SCC 216- Para 7 line 2 onwards.

6. Chameli Singh Vs. State of U.P. reported in (1996) 2 SCC 549 -Para 18 Public purpose.

161 7. Indian Bank Vs. Satyam Fibres (India) Pvt.

Ltd., reported in 1996(5) SCC 558 - Para 20 & 23.

8. Bhaurao dagdu Vs. State of Maharashtra reported in (2005) 7 SCC 605 - Paras 9-12

9. T. Vijendradas Vs. M. Subramaniam reported in (2007) 8 SCC 751 - Paras 18,19,27 & 28,

10. Amresh Tiwari Vs. Lalta Prasad reported in (2000) 4 SCC 440 -- Para 10 - interim orders

11. (2007) 8 SCC 449, Para 33-36- Prestige Lights Para 34 & 35 - suppression

12. 2017 SAR 100 Tahsildar, Taluk Office, Tanjore Vs. G. Thambidurai & another, Para 24

II. Party cannot approbate & reprobate:

1. Shyam Telelink Ltd., vs. Union of India reported in 2010(10) SCC 165 (Paras 3,23,25 & 26) A Party cannot approbate and reprobate.

A Party cannot take advantage of one part of a document and reject the rest. Law 162

does not permit a person to approbate and reprobate.

III. Plead of fraud to be specifically pleaded and proved

2. M/s National Technological Institutions (NTI) Housing Co-operative Society Ltd., and Others vs. The Principal Secretary to the Government of Karnataka, Revenue Department and others reported in ILR 2012 KAR 3431 (Paras 28 & 29)

When fraud is charged against the opposite party, there must be express allegation of fraud in the pleading and all material facts in support of the allegations must be laid down in full and with high degree of precision. Fraud being a question of fact, has to be pleaded and proved in the Writ Proceedings.

3. Ranganayakamma vs. K.S. Prakash reported in AIR 2005 KAR 426 (Paras 46 to 51) 163

Plead of fraud is to be raised in the pleadings by furnishing particulars, which should be concise but also precise and it is not enough to use the general word such as 'fraud'. The degree of proof of fraud is extremely high.

4. Bishundeo Narain and another vs. Seogeni Rai and Jagernath reported in AIR 1951 SC 280 (Para 27 & 28) In cases of fraud, undue influence and coercion, the parties pleading it must set forth full particulars as laid. General allegations are insufficient even to amount to an averment of fraud.

5. Sri Krishnan Vs. Kurukshethra University, Kurukshethra reported in 1976(1) SCC 311 (Para 7) Where a person on whom fraud is committed is in a position to discover the truth by due diligence, question of fraud does not arise.

164

6. Svenska Handelsbanken vs. M/s Indian Charge Chrome & others reported in 1994(1) SCC 502 (Paras 41, 42 & 87) Fraud cannot be found merely on suspicion. Material evidence must show it.

7. Kale and others vs. Deputy Director of Consolidation and others reported in 1976 (3) SCC 119 (Head note & Para 29)

Allegations of fraud must be clearly pleaded and proved by clear and cogent evidence. (Para 29- line 7)

IV. Plea of estoppel not permissible if facts could be known to a party by exercise of ordinary diligence

8. ILR 1929 ALL 248 (Page 250 last 11 lines & Page 251, 6 lines) Where truth is accessible to a party, the plea of estoppel upon representation tails. If the defendant behaved diligently and prudently and pushed their enquiries further afield, it would be have been 165

impossible for them not to know the truth.

9. Lachman Singh vs. Collector of Moradabad and another reported in AIR 1933 ALL 641 (Para 4) If a fact could have been known to a party by exercise of ordinary diligence, the plea of estoppel cannot be raised

V. Court should be slow in interfering with opinion of experts

10. State of Madras vs. N.K.Nataraja Mudaliar reported in AIR 1969 SC 147 (Para 34)

Views of an expert committee on a subject so complicated as tax on inter-state sales, is entitled to great weight. In the very nature of things it is difficult for courts to ascertain various factors that impede the free flow of trade or to assess their importance. In assessing the strength of economic force in a given matter, the views of a person who may be expected to be familiar with the subject is entitled to 166

weight and in the absence of clear proof to the contrary or unless it is shown that their conclusions are obviously wrong, it will be proper for the court to proceed on the basis that the conclusions reached by them are correct.

11. N.D.Jayal and another vs. Union of India and others reported in 2004 (9) SCC 362 (Paras 16,17,20 & 21) Construction of Tehry dam was assailed in a writ petition before the Supreme Court in a petition under Article 32 on the ground that of increased seismic vulnerability of the Himalayan region where the Tehry dam was being constructed would pose danger to the dam.

The respondents in their objections stated that there were scientific studies conducted by experts and all the experts have opined that there would be no danger to the dam on account of seismic activities.

167

HELD: Court cannot sit in judgment of cutting edge of scientific analysis relating to safety of any project (Para 20)

Any scientific matters of complex thing, reference has to be made to specialized / technical expert bodies ... Court cannot site in judgment over decision of experts especially when there is no difference of opinion among the experts. (Para 21 )

12. G.Sundarrajan vs. Union of India reported in 2013 (6) SCC 620 (PARA 209, 210) Court should be slow to interfere with the opinion expressed by experts and it would be normally be wise and safe for courts to leave the decision to experts who are more familiar with the problems. (Para 209)

Court cannot sit in judgment on the views expressed by technical and scientific bodies regarding safety and security of a nuclear plant. (Para 210)

VI. Courts are empowered to appoint a commissioner and accept/rely on his report 168

13. Bandhua Mukti Morcha vs. Union of India reported in 1984(3) SCC 161 (Paras 14 &

15) It would not be correct to say that report of the commissioner has no evidentiary value since statements are not tested by cross examination (Para 15 pg 206 last 15 lines to pg 207, 9 lines).

High Court while exercising powers under Article 226 has wider power to appoint a commissioner not only for enforcement of a fundamental right but also for enforcement of any legal right. Report of the commissioner has evidentiary values and the court can rely upon such report(Para 15 )

VII. Suspicion not substitute to proof

14. Ajay Hasia and others vs. Khalid Mujib Sehravardi and others reported in 1981(1) SCC 722 (Para 19 at Page 746) Chart does create strong suspicion that marks awarded at viva voce might have 169

been manipulated. But suspicion cannot take place of proof and plea of malafides cannot be held to be established (Civil case)

15. Rajkumar Singh vs. State of Rajasthan reported in 2013 (5) SCC 722 (Head Note

- G & Para 21) Suspicion no matter how strong cannot and must not be permitted to take place of proof.

16. Bhandari Construction Co. vs. Narayan Gopal Upadhye reported in 2007 (3) SCC 163 (Para 15) Mere suspicion that builders of the country are prone to take part of sale amount in cash is no ground to accept the claim of payment of Rs.4.00Lakhs in cash. (Civil case)

VIII. Party shall not make inaccurate, untrue and misleading statement before court

17. Hari Narain vs. Badridas reported in AIR 1963 SC 1558 (Para 9) 170

It is utmost important that in making material statements before court, care must be taken not to make any statements which are inaccurate, untrue or misleading. It would be unfair to betray the confidence of the court by making statements which are untrue and misleading.

Hence, Sri Udaya Holla, learned Senior Counsel

sought to allow the writ petition as prayed for.

IV ARGUMENTS ADVANCED BY SRI SAJAN POOVAYYA, LEARNED SENIOR COUNSEL FOR RESPONDENT Nos.3, 11 to 13, 16 to 25, 27 to 29, 32 to 34, 36 to 38, 40 to 45, 47, 48, 54, 56 to 62, 64, 67, 69, 71, 73 and 74 - PURCHASERS

68. Sri Sajan Poovayya, learned senior counsel

appearing for Respondent Nos.3, 11 to 13, 16 to 25, 27

to 29, 32 to 34, 36 to 38, 40 to 45, 47, 48, 54, 56 to 62,

64, 67, 69, 71, 73 and 74 contended that the said

respondents are purchasers of apartments from the

petitioner, but possession was not delivered to them 171

because of non-completion of the apartments, in view

of the interim order passed by this Court. He would

further contend that on 28.10.2011 HAL given NOC to

the petitioner to build upto a height of 62 meters as per

Annexure-A and subsequently cancelled on 16.8.2013.

That is, HAL allowed the petitioner to construct the

building with NOC for a period of 22 months and

thereafter cancelled the NOC. On 15.9.2012 HAL

expressed doubt about permissible height of

construction. On 20.5.2013 HAL directed the petitioner

to stop construction without issuing any public notice.

In view of the conduct on the part of the HAL, it is

necessary to conduct aeronautical study by the

competent authority (AAI). He also invited the

attention of the Court to the notification - S.O. 84(E)

dated 14.1.2010, wherein at Sl.No.2(b) it is stated that

for Defence aerodromes, defence authorities shall be

responsible for issuing NOC in accordance with the

said notification and subject to any other restriction or 172

condition which such authorities deemed fit for issuing

the NOC. He further contended that while issuing NOC

to the petitioner on 28.10.2011, two conditions were

imposed at Serial No.3 to the effect that if at any stage

it is established that the said data as tendered by the

said applicant is actually different from one tendered

and which could adversely affect aircraft operations, the

structure or part(s) thereof in respect of which "NOC" is

issued will have to be demolished at his own cost as

may be directed by the HAL Airport, Bangalore.

69. Sri Sajan Poovayya, learned Senior Counsel

further contended that while issuing NOC, 870 meters

(site elevation) + 62 meters (height of the construction)

i.e., 932 meters AMSL was granted. While canceling

NOC on 16.8.2013, it was cancelled in its entirety and it

amounts to giving room to demolish the entire building,

which is arbitrary and in violation of Article 14 of the

Constitution of India. He would further contend that 173

cancellation order does not disclose with regard to the

violation of conditions of grant of NOC. He would

further contend that cancellation of NOC without

aeronautical study is impermissible. He contended that

in the objections filed by the HAL at paragraph-15, it is

stated that it is only in the event HAL approaches AAI to

conduct the same, it would do so. A copy of the letter

dated 25.06.2013 issued by AAI to respondent is

produced as Annexure-R5. In the objections, it is

stated that the AAI does not conduct Aeronautical Study

even for the purpose of issuance of NOCs around Civil

Aerodromes. It is also stated that the point in dispute is

the AMS Level of the construction site which can be

ascertained only by a field survey.

70. Sri Sajan Poovayya, learned senior counsel

also contended that at paragraph-5 of the objections

filed by the HAL to the I.A. filed by the petitioner, it is

stated that the primary object of fixing the maximum 174

height under Section 9-A of the Aircrafts Act,1934 is to

secure safety of Aircraft operations in and around the

Aerodrome. Thus, the only way in which it can be

ascertained is through Aeronautical Study of Aircraft

operations based on notified parameters for HAL

Airport. He further contended that in the letter dated

6th November 2015 written by HAL to the Airport

Authority of India, a request has been made to conduct

an Aeronautical Study to ascertain whether the existing

building/proposed construction to the height of 62

meters above ground level would adversely affect the

safety of Aircraft operations at HAL Aerodrome based on

the notified parameters as on 28.10.2011 (date of

issuance of NOC) and the statutory stipulations in

Gazette Notification S.O.84(E) dated 14.01.2010 issued

by the Ministry of Civil Aviation. A Memorandum of

instructions containing the relevant details for the

conduct of the Aeronautical Study was also enclosed to

the said letter and it is also stated in the letter that 175

required data in this regard may be intimated to the

HAL.

71. Sri Sajan Poovayya, learned senior counsel

further contended that in terms of the order passed by

this Court and the regulations made by the HAL, AAI

has submitted report on 15.12.2015 and come to the

following conclusions:

a) The existing structure, for requested top elevation 954.41 Mtr. AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin of 21.23M which exceeds the permissible height of 45M by 47.17%

b) The desired height of 954.41m AMSL is within the maximum allowable penetration of OLS as per the Aeronautical Study guidelines

c) The safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

d) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of the PANS-OPS criteria.

176

e) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

f) Airport Operator should ensure that the applicant/owner/builder carry out marking and lighting of the structure as per the DGCA CAR and the obstacle is published.

72. Sri Sajan Poovayya, learned senior counsel

invited the attention of the Court to the International

Standards and Recommended Practices (Annex 14 to

the Convention on International Civil Aviation) wherein

at 4.2.20 it is stated that new objects or extensions of

existing objects should not be permitted above the

conical surface and the inner horizontal surface except

when, in the opinion of the appropriate authority, an

object would be shielded by an existing immovable

object, or after aeronautical study it is determined that

the object would not adversely affect the safety or

significantly affect the regularity of operations of

aeroplanes. As per 4.2.21 of Annex 14 to the 177

Convention of International Civil Aviation, existing

objects above an approach surface, a transitional

surface, the conical surface and inner horizontal surface

should as far as practicable be removed except when, in

the opinion of the appropriate authority, an object is

shielded by an existing immovable object, or after

aeronautical study it is determined that the object

would not adversely affect the safety or significantly

affect the regularity of operations of aeroplanes.

73. Sri Sajan Poovayya, learned Senior Counsel

would further contend that in the statement of

objections filed by the 1st respondent at paragraph 32, it

is stated that the averment that the respondent has

erred in limiting the construction to 932 meters AMSL is

denied as the respondent has arrived at the said figure

after a conclusive examination of the site elevation at

HAL Airport, Runway strip and Approach Funnel, Inner

Horizontal Surface, Outer Conical Surface, Outer 178

Transitional Surface and Outer Horizontal Surface of

the HAL Aerodrome and contended that, the action of

the 1st Respondent cannot be said

to be arbitrary to warrant interference by this Court.

By a reading of the statement of objections filed by the

1st respondent, it is found that if the HAL authority after

conclusion and examination granted NOC, it is not open

for the HAL to now cancel the NOC on the ground that

the petitioner has given wrong data of the ground level,

which is impermissible. Before cancellation of the

NOC, no notice or opportunity was given to respondent

Nos. 2, 3, 11 to 74 - the purchasers from the petitioner-

builder.

Sri Sajan Poovayya, learned Senior Counsel would

further contend that in the letter written by Wg.Cdr.

M.P. Srinivasan, Retired Deputy General Manager

(Aerodrome) to the present petitioner - M/s. Chalet

Hotels Limited, it is specifically stated at para-2 that 179

HAL-NOC-Committee has no role in surveying and

verifying the elevation of a site. This practice is being

followed by Airports Authority of India (AAI) and the

same is adopted by HAL. He further pointed out from

para-3 that though the NOC for 932M was issued by

HAL, in later stages, it was found that the site elevation

of 870M varying drastically from the elevations of

nearby sites and landmarks. Hence, in the interest of

Air Safety, the petitioner was advised to carry out the

resurvey of the site and check the site elevation.

74. Sri Sajan Poovayya, learned senior counsel

further contended that Clause 4.6 of the Air Traffic

Management Circular No.02 of 2013 prescribes that the

Regional NOC cells and the station level NOC cells shall

handle NOC cases of buildings, structures and masts.

Accordingly the following NOC cells with their

designated officers have been established.

180

Regional level NOC cell Designated Officer

i) RHQ, Delhi General Manager (AERO) Northern region

ii)RHQ, Kolkata General Manager (AERO) Eastern region

iii) RHQ, Chennai General Manager (AERO) Southern region

iv) RHQ, Mumbai General Manager (AERO) Western region

v)RHQ,Guwahati General Manager (AERO) East region

Sri Sajan Poovayya, learned Senior Counsel would

contend that Clause 4.11 of the Air Traffic Management

Circular No.02 of 2013 prescribes that the NOC

Committee at the Regional Level shall comprise the

following:-

i) General Manager (Aero), Region Designated Officer and Chairman

ii) Jt. GM (N&S)/ Dy. GM (N&S) Member

iii) Dy. GM (IAL) SM(IAL) Member 181

iv) Representative of Airport Member Operator as applicable

v) Dy. GM(NOC)/ Senior Member Secretary Manager (NOC)

Sri Sajan Poovayya, learned senior counsel would

further contend that Clause 4.12 of the Air Traffic

Management Circular No.02 of 2013 reads as under:

"The NOC Committee at the Station Level shall compromise the following:-

i) General Manager(ATM) Designated Officer Jt.GM(ATM)/ Dy.GM(ATM) and Chairman

ii) JT. GM(N&S)/ Dy. GM (N&S) Member

iii) Dy.GM(IAL)/SM(IAL) Member

iv) Representative of Airport Member Operator as applicable

v) Senior Manager (NOC)/ Member Secretary"

Manager (NOC)

75. Sri Sajan Poovayya, learned senior counsel

would further contend that in terms of Clause 4.13 of

the Air Traffic Management Circular No.02 of 2013, the

site plotted on the grid map/zoning map of the 182

aerodrome or on a map of suitably large scale and the

site plotted by NOCAS for calculation of the permitted

height needs to be checked for accuracy. Thereafter,

the case will be put before the Committee to permit the

proper examination in which PANS-OPS criteria shall

also be considered. Therefore he would contend that

unless and until aeronautical study is conducted by the

competent authority, the respondent - HAL cannot

cancel the NOC without assigning any reasons.

Therefore, he sought to allow the writ petition.

76. In support of his contentions, learned

counsel relied upon the following judgments:

1. LEVER FINANCE LIMITED .vs. WESTMINSTER (CITY) LONDON BOROUGH COUNCIL reported in (1970)3 WLR 732,

wherein it is observed that there are authorities which say that a public authority cannot be estopped by any representations made by its officers 183

and cannot be estopped from doing its public duty.

2. GODREJ AND BOYCE MANUFACTURING COMPANY LIMITED AND ANOTHER .vs. STATE OF MAHARASHTRA AND OTHERS reported in (2014)3 SCC 430 (paragraphs 83, 84 and 85)

V Arguments advanced by the Learned Counsel for the 1st Respondent-HAL

77. Per contra, Sri Ananth Mandagi, learned Senior Counsel for respondent No.1 mainly raised three points:

i) That the writ petition filed by the petitioner for the relief sought for is not maintainable;

ii) That because of the conduct and fraud played by the petitioner, it is not entitled to the relief sought for; and

iii) That the aeronautical study is not provided as per the Notification dated 14th January, 2020 issued by the Civil Aviation, Annexure-B to the 184

Defence Airports and is only for Civil Airports.

He would further contend that the petitioner's building

is the only highest building within four kilometers of the

Inner Horizontal Surface at 954 meters AMSL and no

other building is situated within four kilometers of Inner

Horizontal Surface. The permissive limit in terms of

Annexure-B is only 932 meters AMSL. He would further

contend that the said notification issued by the Central

Government fixing the parameters is not challenged by

the petitioner i.e., 800 + 45 + 933 meters. The

petitioner's building is within 3.35 klms., instead of 4

klms., as prescribed in the Notification, Annexure-B.

and the Central Government is not made as a party to

the writ petition. Therefore, the writ petition is liable to

be dismissed on that ground alone.

78. The learned Senior Counsel for the 1st

respondent further contended that in the statement of 185

objections filed in the present writ petition by the HAL

at paragraph-5, it is stated that the primary purpose

for issuing NOC for high rise buildings is to restrict

obstacles within the imaginary limitation surfaces called

'Obstacle Limitation Surfaces (OLS) and any penetration

of the limiting surfaces endangers safety. The

Notification dated 14.1.2010 has been developed and

promulgated keeping in view the operation at Civil

Aerodromes. It is further contended that in the said

Notification, it is categorically stated that for Defence

Aerodromes, the Defence Authorities shall be

responsible for issuing 'No Objection Certificate' in

accordance with the said Notification and subject to any

other restrictions and conditions which such authorities

deemed fit. Therefore, imposition of additional

restrictions or conditions are necessary due to the

nature of operations and traffic characteristics which

are as under:

186

(a) Operation of Single Engine Aircrafts:

(b) Single occupancy Cockpit and consequent High Cockpit workload;

(c) Very high rate of descent, Climb and Turn;

(d) Higher sped of operation including higher landing speed;

(e) formation flying;

(f) Low endurance flying;

(g) Low level flying requirement;

(h) Tactical combat training (sudden variations inaltitude and direction);

(i) Large number of Aircrafts launched and recovered within short durations;

79. The learned Senior Counsel further

contended that the HAL Aerodrome is a Unique Defence

Aerodrome in comparison to all other defence

aerodromes for the following reasons:

(j) HAL is the sole premier Aircraft, Design and Manufacturing Organisation in the country 187

promoting a safe test flying environment which is critical for National Defence;

(k) Flying operations at HAL involve test flying of experimental, unproven, developmental Aeroplanes and Helicopters;

(l) Test flying of prototypes and pre-

production models;

(m) Special exercises are carried out such as "Practice Forced Landing",(PFL) which involves an unconventional approach to land;

(n) Carrying out Single Engine landing of a multi engine Aircraft for test purposes;

(o) Flying in poor weather conditions (low visibility);

(p) Switching off engines and re-ignition in mid-air;

(q) Post production Test flying.

188

The nature of work stated supra carried out in HAL

Aerodrome entail a high level risk and hence, safety

margins from the obstacle on ground around the Airport

are essential and therefore, additional restrictions are

imposed such as, no violation of obstacle limitation

surface shall be permitted under any circumstances as

they are inviolable and non-negotiable and also as a

corollary, no requests for Aeronautical studies in the

event of a violation of the said surface shall be

entertained.

80. The learned Senior Counsel for the HAL

further contended that the Notification, Annexure-B

dated 14.1.2010 issued by the Central Government in

exercise of powers under the provisions of Section 9A of

the Act is also not challenged by the petitioner. He

would further contend that, International Standard and

Aviation Practices issued by the International Civil

Aviation Standards 2004 stipulates Annex-14 to the 189

Convention on the International Civil Aviation pertains

to Civil Aviation and not for the Defence. Therefore, this

Court cannot grant the relief sought in prayer No.2 in

the present writ petition as this Court cannot legislate

by granting such relief. He further contended that

under Clause 5 of the Notification, Annexure-B dated

14.1.2010, the conduct of Aeronautical study stipulates

only for civil airports and not for defence airports. He

would further contend that the letter dated 6th

September, 2011 issued by the Air Force Authority of

India to the Vice President, Legal and Land Force - M/s.

Shoba Developers is subject to issue of NOC for

construction of Military Search.

81. Sri Ananth Mandagi, learned Senior Counsel

for the Respondent No.1 - HAL contended that in

paragraph-15 of the writ petition, the petitioner has

stated that: "the matter was of a highly technical nature

with there being very few persons having the specialized 190

knowledge and experience to effectively deal with the

peculiar situation in the present case. It is relevant that

the respondent is primarily a public sector undertaking

carrying on manufacturing activity, and the responsibility

to issue NOCs was entrusted to them very recently in

2010. Consequently, the officers of the respondent were

themselves not completely sure of the conclusive way

forward." Therefore, the respondent No.1 - HAL is not

the competent authority to allow the petitioner to

construct the buildings beyond the limits fixed by the

Central Government under the provisions of Section 9A

of the Aircraft Act as per Annexure-B - notification.

The learned Senior Counsel for the 1st respondent-HAL

would further contend that it is not the case of the

petitioner in the entire pleadings of the writ petition that

the petitioner has not violated the 'Undertaking' that

was given by him at the time of obtaining 'No Objection

Certificate' and he has not constructed building beyond 191

932 meters and NOC was wrongly withdrawn by the

respondent. Therefore, the 1st prayer sought in the

present writ petition to quash the letter dated 16.8.2013

issued by respondent vide Annexure-AQ canceling the

NOC issued to the petitioner in respect of height

clearance is just and proper and the petitioner has not

stated as to what is the mistake committed by the

respondent No.1 while withdrawing NOC. He would

further contend that the 2nd prayer sought in the writ

petition is to direct the respondent No.1 to permit the

petitioner to construct up to the maximum height which

does not adversely affect aircraft operations as may be

determined in the aeronautical study to be conducted

by the 1st respondent through AAI or ICAO or any other

recognized agency and the said prayer cannot be

granted as AAI or ICAO is not the authority under

Section 9A of the Aircraft Act. He would further

contend that in the entire writ petition, the petitioner

has not stated regarding the maximum height which 192

does not adversely affect the aircraft operations and the

maximum height that is allowed in law.

82. Sri Ananth Mandagi, learned Senior Counsel

would further contend that the petitioner has

deliberately produced a portion of Convention on

International Civil Aviation as per Annexure-AZ instead

of producing in full. As per Annexure-R16 produced

along with statement of objections, Convention on

International Civil Aviation was held at Chicago on

7.12.1944 and it pertains to civil airports, but not

defence airports. In fact Section 4 of the Aircraft Act

deals with Convention relating to International Civil

Aviation held at Chicago. Annexure-AZ is Annex 14

to the Convention on International Civil Aviation and it

pertains to only civil aviation and there was no need to

produce the said document by the petitioner since the

said document is not relevant for the present case. He

would further contend that Article 3 of Annexure-R16 193

pertains to Civil and State aircrafts. As per Article 3(a)

of the Convention, the Convention shall be applicable

only to civil aircraft and is not applicable to state

aircraft. As per Article 3(b) of the Convention, Aircraft

used in military, customs and police services shall be

deemed to be state aircraft. In fact, the heading of

Article 3 of the Convention itself is "Civil and State

aircrafts".

83. Sri Ananth Mandagi, learned Senior Counsel

for Respondent No.1 would further contend that

Annexure-BC is Air Traffic Management Circular issued

by Airports Authority of India. Clause 4.1 of the said

Circular specifies that the applicant shall submit the

application for NOC on prescribed form (Appendix-1)

and he should provide the exact location of the

proposed construction on the grid map/zoning map of

the concerned aerodrome along with the coordinates in

WGS-84 system; The applicant shall be responsible for 194

the correctness and integrity of site data furnished in

the application; The applicant shall also submit an

undertaking to the effect that the data furnished in the

application is correct in all respects and in case at any

stage the data provided by the applicant is found to be

incorrect, the NOC issued shall automatically stand

cancelled. He further contended that on the revised

undertaking affidavit filed by the petitioner on

3.10.2011 as per Annexure-H in the writ petition, the

authorities issued 'No Objection Certificate' dated

28.10.2011 as per Annexure-A with certain conditions

prescribing that the top of the proposed structure when

erected shall not exceed 870 meters (site elevation) + 62

meters (Height of the structure) i.e., 932 meters AMSL

(above mean sea level). Admittedly in the present case,

the petitioner has constructed buildings to a height of

954 meters i.e., beyond the limit prescribed in the NOC

given by the HAL. Therefore the impugned Annexure-

AQ came to be issued on 16th August 2013 cancelling 195

NOC issued by HAL as per letter dated 28.10.2011 for

height clearance.

84. Sri Ananth Mandagi, learned Senior Counsel

for Respondent No.1 while referring to the Sketch -

Annexure R15, contended that the existing building

elevation as on the date of filing the writ petition was

954.41 meters AMSL and the maximum permissible

level is 932 meters AMSL in terms of Annexure-B

notification. The petitioner has made extra construction

to an extent of 22.41 meters. He would further contend

that 'No Objection Certificate' dated 28.10.2011 as per

Annexure-A has been issued by the Chief Manager

(Aerodrome), HAL Airport on the basis of the

Undertaking given by the petitioner dated 03.10.2011.

In the 'No Objection Certificate', it is specifically stated

that the applicant(s) is/are advised in his/their own

interest to verify the elevation and other data furnished

for the site, before embarking on the proposed 196

construction. He would further contend that in

paragraph-3 of Annexure-A it is stated that "If however,

at any stage it is established that the said data as

tendered by the applicant is actually different from one

tendered and which could adversely affect aircraft

operations ....." and the word 'and' used in Annexure-A

should be read as 'or'. In support of his contention, he

relied upon the Judgment of the Hon'ble Supreme Court

in the case of MOBILOX INNOVATIONS PRIVATE

LIMITED Vs. KIRUSA SOFTWARE PRIVATE LIMITED

reported in (2017)11 SCALE 754, wherein the Hon'ble

Supreme Court held at paragraph-29 as under:

29. It is, thus, clear that so far as an operational creditor is concerned, a demand notice of an unpaid operational debt or copy of an invoice demanding payment of the amount involved must be delivered in the prescribed form. The corporate debtor is then given a period of 10 days from the receipt of the 197

demand notice or copy of the invoice to bring to the notice of the operational creditor the existence of a dispute, if any. We have also seen the notes on clauses annexed to the Insolvency and Bankruptcy Bill of 2015, in which " the existence of a dispute" alone is mentioned. Even otherwise, the word "and" occurring in Section 8(2) (a) must be read as "or" keeping in mind the legislative intent and the fact that an anomalous situation would arise if it is not read as "or". If read as "and", disputes would only stave off the bankruptcy process if they are already pending in a suit or arbitration proceedings and not otherwise. This would lead to great hardship; in that a dispute may arise a few days before triggering of the insolvency process, in which case, though a dispute may exist, there is no time to approach either an arbitral tribunal or a court. Further, given the fact that long limitation periods are allowed, where disputes 198

may arise and do not reach an arbitral tribunal or a court for upto three years, such persons would be outside the purview of section 8(2) leading to bankruptcy proceedings commencing against them. Such an anomaly cannot possibly have been intended by the legislature nor has it so been intended.

85. Sri Ananth Mandagi, learned Senior Counsel

for Respondent No.1 would further contend that at

Clause-4 of the No Objection Certificate (Annexure-A), it

is specified that the NOC issued is further subject to the

provisions of Section 9A of the Aircraft Act, 1934 and

those of any notifications issued thereunder from time

to time and under which, the applicant may be called

upon by the HAL Airport, Bangalore to demolish in

whole or in part, the structure that is being authorized

vide NOC. Therefore he contended that even assuming

the petitioner constructed on par with the permission

granted, still the authority has got power to call upon 199

the applicant to demolish in whole or part of the

structure. Therefore it is not a right given for ever.

The NOC issued is subject to the conditions prevailing

at that time. It may vary in future in terms of Section

9A of the Aircraft Act. He would further contend that

the petitioner has not made out any case that either AAI

or ICAO can execute aeronautical study in respect of

the defence airports (HAL) and both the builder and

buyer should be aware of the norms fixed by the Central

Government in respect of the defence airports.

Knowing fully well the norms fixed, the petitioner has

exceeded beyond the NOC given and now he cannot

seek for a mandamus directing the respondents to

permit him to construct up to maximum height which

does not adversely aircraft operations. He specifically

pressed the words used in Annexure-A i.e., "NOC FOR

HEIGHT CLEARNACE ONLY". Therefore the petitioner

cannot make construction beyond the permissive level

i.e., 932 Meters AMSL.

200

86. Sri Ananth Mandagi, learned Senior Counsel

for Respondent No.1 would further contend that the

supplement to the Aeronautical Study on Gujarat

International Financial Tech-city (GIFT) deals with

policy matter that relates to aeronautical studies and

the same was prepared by the International Civil

Aviation Organisation. The policy in question relates to

the recent changes in the obstacle limitation surfaces

specified in Ministry of Civil Aviation Notification No.

S.O. 1589 (E) dated 30th June 2008 as amended on 17th

April 2009. In the said supplement, it is stated that a

number of previous aeronautical studies undertaken by

ICAO for AAI have stressed the need to preserve free of

obstacles the airspace between the Annex 14 OLS

(including the OHS) and the PANS-OPS obstacle clearance

surfaces to cater for non-normal operations. This is

because major accidents involving a relaxation of ICAO

practices may have consequences which go beyond the 201

immediate casualties and damage, and raise wider

public discussion. Accidents which involve large number

of fatalities or casualties at schools, hospitals or high rise

buildings (particularly if approved through an

aeronautical study) would raise public concern. Cost

benefit analysis cannot by itself address fully the

concerns raised in such cases. Therefore, there are

circumstances in which more stringent safety measures

should be retained, even though they may not be directly

cost-beneficial.

87. Sri Ananth Mandagi, learned Senior Counsel

would further contend that in the letter dated 15.9.2012

(Annexure-N) addressed to the petitioner by the

respondent, it is clearly stated that the NOC for height

clearance of 62 Meters for the proposed building at the

site in question was issued based on the express

understanding that the site elevation is 870 meters

AMSL as tendered by the petitioner was correct. It is 202

found that the elevation submitted by the petitioner

(870 meters) vastly differs from the data available with

the respondent and this may lead to reduction in the

permissible height above ground level for the proposed

building. Therefore the petitioner was advised to carry

out a resurvey of the proposed site for the purpose of

finding the elevation, in presence of HAL-NOC

committee within 30 days. Sri Ananth Mandagi would

further contend that as per Annexure - 'O' dated

19.2.2013, the respondent - HAL reminded the

petitioner to carry out a resurvey of the proposed site for

the purpose of finding the elevation, in the presence of

HAL-NOC Committee.

88. Sri Ananth Mandagi, learned Senior Counsel

further contended that in Annexure-R10 dated

15.9.2012 addressed to one Dr. C. Nanjunda Swamy,

Professor and Head, Department of Civil Engineering,

Dr. Ambedkar Institute of Technology, it is stated that 203

the NOC for height clearance of 62 meters for the

proposed building at the site was issued by the HAL-

NOC Committee, based on the Coordinates and

Elevations of the site checked and verified by Dr.

Ambedkar Institute of Technology. The same was

enclosed along with the application for NOC by the

petitioner. In Annexure-R10 dated 15.9.2012, the

respondent - HAL has categorically stated with regard to

resurvey of the site i.e, it is found that the elevation

(870 meters AMSL) of the site certified vastly differs

from the data available with the respondent - HAL,

thereby advised to carry out a re-survey of the site and

submit the report to the respondent - HAL within 15

days from the date of receipt of the letter. He further

contended that either the petitioner or the authorities

who have issued the height clearance certificate in

favour of the petitioner did not come forward for joint

survey or replied the notice. He would further contend

that with regard to re-survey, reminder made by the 204

respondent to the petitioner is admitted by the

petitioner in paragraphs 16 and 17 of the writ petition

and there is no further averment with regard to the

approach of the HAL for re-survey or with regard to

the authorities who have issued height clearance

certificate in the name of the petitioner. Therefore the

contention of the petitioner that there was no

opportunity provided to him before withdrawing NOC

cannot be accepted.

89. Sri Ananth Mandagi, learned Senior Counsel

for the 1st respondent contended that, on the basis of

the complaint made by Respondent Nos.4 to 10 to the

Ministry of Defence in respect of certain violations made

by the petitioner, the 1st respondent verified from the

survey map of India, Bengaluru district and declared

that height of the land belonging to the petitioner at

Koramangala is 892 meters AMSL. But the petitioner

declared the height of their land in the application as 205

per Annexure - E1 at 870 meters AMSL. The Karnataka

State Remote Sensing Applications Centre appointed at

the instance of both the parties by this Court on

28.08.2013 submitted report as per Annexure-R6,

which clearly depicts that the elevation is 892.33 mtr

AMSL. Both the parties have not disputed the report

filed by the Karnataka State Remote Sensing

Applications Centre except the petitioner filing

objections. As per the report, the co-ordinates of the

Benchmark are as follows:

Location Latitude Longitude Elevation Id. AMSL (m)

BM 12 55' 21.234" N 77 37'52.575" E 892.33 No.1124

Learned Senior Counsel for the 1st respondent further

contended that at paragraphs 18 and 19 of the writ

petition, it is stated that the petitioner was advised that

in view of the structure having been completed up to 17

floors, an aeronautical study would be necessary to 206

conclusively determine the maximum permissible height

which would not adversely affect aircraft operations, in

accordance with the applicable criteria of Annex 14 of

ICAO and as provided in S.O. 84(E). The opinion of one

Mr.R.C.Khurana, the retired Executive Director,

Airports Authority of India confirms that the height is

restricted to 964 Meters AMSL. The petitioner's anxiety

regarding air safety were justifiably alleviated after the

findings of the ATM expert as set out in the ASR. The

ASR confirmed that the existing structure upto 17 floors

was below the said 964/957 Meters AMSL. The said

averments made cannot be accepted, which are

impermissible in view of Section 9A of the Aircrafts Act

and the notification issued by the Central Government

as per Annexure-B dated 14.01.2010 and the NOC given

by the respondent in favour of the petitioner.

90. The learned Senior Counsel further

contended that on 15.03.2013 the petitioner wrote a 207

letter (Annexure-P) to the 1st respondent and in the said

letter, it is stated that the NOC application was

considered and the height clearance upto 932 meters

AMSL was recommended by NOC Committee of HAL

and only thereafter the HAL has issued 'NOC for Height

Clearance' of 932 meters AMSL i.e, 62 meters (height of

the structure) and 870 meters (site elevation) in terms of

NOC dated 28.10.2011. In the said letter it is also

stated that BBMP had sanctioned plans for wings A to K

upto 17 floors vide its order dated 24.02.2012 issued by

the Joint Director, Town Planning, BBMP and further

based on the NOC issued for 62 meters, they have

constructed the building for the said height. Sri Ananth

Mandagi, learned Senior Counsel further contended

that the HAL issued notice dated 28.03.2013

(Annexure-R) to the petitioner for resurvey of the site

and in the said notice it is specifically stated at

paragraph 2 that no Surveyor or certifier is authorized

by HAL-NOC Committee to survey or to certify the 208

location and elevation of a site. HAL-NOC committee

has no role in surveying and verifying the elevation of a

site. The said practice is being followed by Airports

Authority of India (AAI) and the same is adopted by

HAL. It is further stated in paragraph-3 of the said

notice that though the NOC for 932 mtr was issued by

HAL, it was found that the site elevation of 870M

varying drastically from the elevations of nearby sites

and landmarks and hence in the interest of Air safety,

the petitioner was advised to carry out the resurvey of

the site, to check the site elevation and ultimately

advised to verify the site elevation and other data

furnished for the site before embarking on the proposed

construction, to avoid any possible violation of the

permissible elevation of 932M in the future. The

petitioner was also advised to carry out a resurvey of the

site for the purpose of finding the elevation, in the

presence of HAL-NOC Committee within 30 days after

the receipt of the letter. The convenient date and time 209

may be mutually agreed upon with the 1st respondent -

HAL. He would further contend again one more letter

dated 12.04.2013 (Annexure-S) was issued by the HAL

to the same effect with regard to re-survey and as per

Annexure-T, the petitioner addressed letter to the

respondent and intimated that they along with ATM

expert Mr. R.C. Khurana explained their view points in

the meeting and substantiated the same with an

Aeronautical Study report prepared by Mr.R.C.

Khurana.

91. Learned Senior Counsel for the 1st

respondent further contend that as per Annexure-U, the

respondent addressed a letter to the petitioner and

clarified that HAL airport pertains to Military and the

study has not taken into consideration the requirement

of low flying by fixed wing and rotary wing aircraft and

the location of the site falls on the right base leg for

runway 09 and due to peculiarity of Test flying the 210

maximum elevation of the building has been restricted

to 932 meters. He further contended that as per

Annexure-V dated 15.05.2013 once again the

respondent requested the petitioner for measuring of

site elevation by Survey of India and it is stated in the

said document that the survey has to be done for at

least four corners of the site and advised the petitioner

to comply with the requirements of Survey of India. He

further contended that as per Annexure-W dated

15.05.2013, the respondent addressed letter to the

Director, Karnataka Geo-spatial Data Centre (KGDC)

and requested to carry out survey of the site belonging

to the petitioner and send one set of survey report to the

respondent - HAL and the fees towards the survey of the

site and the mode of payment be intimated to the

respondent as well as petitioner. It is also contended

that the respondent issued notice finally on 20.05.2013

to the petitioner as per Annexure-Z for suspension of

construction work in the site advising the petitioner to 211

stop the construction of all the towers till the survey to

find out the elevation of the site is carried out by Survey

of India and the permissible Top Elevation at the site is

arrived at, based on the survey report. Learned Senior

Counsel for the 1st respondent further contended that

very strangely the petitioner addressed a letter to the 1st

respondent dated 24.05.2013 (Annexure-AA) that as

required by the 1st respondent, they had approached the

Survey of India office and have followed up with their

letter dated 21.05.2013 requesting them to carry out

the survey as desired by the 1st respondent and in the

said letter, it is also stated that they have intimated the

Airports Authority of India to carry out the Aeronautical

Study on an urgent basis considering substantial

completion of construction work on site. As per

Annexure-AD dated 21.06.2013, the 1st respondent

wrote a letter to the petitioner regarding survey of site,

wherein it has sought information as to whether the

survey of site has been carried out by Survey of India 212

and if so, the survey report shall be sent to the

respondent at the earliest and if not alternatively, the

petitioner may contact the Director, Karnataka State

Remote Sensing Application Centre for carrying out the

survey of site to avoid any delay.

92. Sri Ananth Mandagi, learned Senior Counsel

further contended that as per Annexure-AE dated

02.07.2013, one more letter written by the 1st

respondent to the petitioner regarding survey of site. As

per Annexure-AG dated 12.07.2013, the petitioner wrote

a letter to the Karnataka State Remote Sensing

Application Centre and copy thereof to the respondent.

As per the Court order dated 28.08.2013, the Karnataka

State Remote Sensing Application Centre produced the

report as per Annexure-R6, which clearly depicts that

the elevation has to be only 892.33 meters. Very

strangely the petitioner written one more letter to the

Karnataka State Remote Sensing Application Centre as 213

per Annexure-AL dated 03.08.2013 for aeronautical

study. The learned Senior Counsel for respondent No.1

further contended that, inspite of several opportunities

given by the 1st respondent to the petitioner for survey

of the site to know the height of the building, the

petitioner has not availed opportunity and ultimately

the 1st respondent has no option except to withdraw the

No Objection Certificate on the ground that the

petitioner has violated the conditions of NOC. Therefore

the contention of the petitioner that no opportunity was

given before canceling NOC dated 28.10.2011 issued by

the HAL, cannot be accepted.

93. Sri Ananth Mandagi, learned senior counsel

for 1st respondent - HAL contended that NOC has been

issued in favour of the petitioner imposing certain

conditions. He would further contend that in the reply

by the 1st respondent - HAL as per Annexure- 'AO' to

the petitioner's letter dated 3.8.2013 i.e., before 214

cancellation of the NOC, it is specifically stated that

"The survey of site has nothing to do with Aeronautical

study". In the reply, it is also stated that HAL has not

advised the petitioner for any Aeronautical study and

the Demand Draft submitted by the petitioner was also

returned. He would further contend that in the

impugned letter of cancellation of NOC as per

Annexure-AQ dated 16th August 2013 at paragraph-4, it

is specifically stated that in NOC, it was advised in the

interest of the petitioner to verify the elevation and other

data, before embarking on the construction. In

paragraph-6 of the said letter dated 16.8.2013, it is

specifically stated that: "if you want a fresh NOC, you

are advised to apply for the same after getting the

survey done by Karnataka State Remote Sensing

Application Centre (KSRSAC) or Survey of India". He

would further contend that in the objections filed by the

1st respondent - HAL in the present writ petition at

paragraph-5, it is stated that imposition of additional 215

restrictions or conditions are necessary due to the

nature of operations and traffic characteristics.

94. Sri Ananth Mandagi, learned Senior

Counsel for the 1st respondent further contended that

after receipt of the report from the concerned authority

as per Annexure-BJ dated 3.9.2013, this Court by the

order dated 23.10.2013 observed as under:

"The Court makes it clear that from this day onwards, the petitioner shall not modify/alter/renovate/develop the building construction in the property in question, above 40 meters from ground level. In other words, no further alterations shall be made to the existing building, above 40 mtrs.

The petitioner shall not sell or agree to sell or enter into an agreement with third parties in whatsoever manner in respect of any portion of the building, above 40 meters.

216 The petitioner shall notify all the persons, who have already purchased or agreed to purchase the flats above 40 meters, about the pendency of this writ petition and that the sale of flats would be subject to the result of this writ petition. Petitioner shall also notify that such purchasers shall not claim equity based on purchases or agreements made by them.

It is needless to observe that the construction already made by the petitioner/portion of the building would be subject to the result of this writ petition."

The said order dated 23.10.2013 passed by this Court

has become final and conclusive.

95. Sri Ananth Mandagi, learned Senior Counsel

would further contend that this Court by the order

dated 31.7.2014 (paragraphs 43 to 45) has permitted to

conduct Aeronautical study. Subsequently, this Court 217

by the order dated 15.10.2014 clarified the said order.

The said orders are subject matter of Writ Appeal

No.2572/2014 before the Division Bench of this Court.

The Division Bench dismissed the said Writ Appeal on

3rd September 2015. The relevant portion of the

Judgment passed by the Division Bench in the said Writ

Appeal is as under:

"5. The Hon'ble Single Judge, by the order impugned, directed the Airport Authority of India to process the application of the writ petitioner to conduct an aeronautical study of the Bengaluru (HAL) Aerodrome at the cost of the writ petitioner.

6. By the order impugned, no rights of the parties have been decided. The report that would be submitted before the Hon'ble Judge would be subject to the result of the writ petition.

7. Mr. Pradeep S. Sawkar, learned advocate, strenuously, submits that 218

once the notification has been issued under Section 9-A of the Aircrafts Act, 1934, it was impermissible to issue another aeronautical study. "

The said Judgment passed by the Division Bench of this

Court has reached finality.

96. Sri Ananth Mandagi, learned Senior Counsel

for the 1st respondent contended that the Aeronautical

Study Report submitted in December - 2015 and

paragraph-1.2 of the said report refers that the

applicant has been granted an height of 932 meters

AMSL and the Site Elevation Certificate issued by the

Karnataka State Remote Sensing Application Centre has

reported site elevation of 892.41 meters. In the same

report at para-3.3 it is referred that the existing

structure is penetrating the Inner Horizontal Surface

and the study is being conducted to examine its impact

on the safety and regularity of the aircraft operations.

This aeronautical study is applicable for normal aircraft 219

operations only. ICAO in some Aeronautical Studies

conducted for AAI, has opined the need to preserve (free

of obstacles) the airspace between the Annex-14 OLS

and the PANS-OPS (Procedural for Air Navigation

Service) (Obstacle System Operations) surfaces to cater

for non-normal operations. In the said report, he also

refers to paragraphs-6.1 and 6.2, which read as under:

6.1 The Site has been marked in the AAI Zoning map of Bangalore and lies in Inner Horizontal (IHS) at a distance of 3376m from Rwy09 of Bangalore Airport.

Aerodrome Elevation of Bangalore Airport:888.18m

Height of Inner Horizontal Surface above the aerodrome elevation:45m

Admissible Top Elevation due due to OLS:-888.18M+45M=933.18m

6.2 Existing Structure of 954.41M AMSL (62M AGL+S.E.892.41M) will be penetrating the Inner Horizontal Surface 220

is to protect airspace for visual circling prior landing possibly after a descent through cloud aligned with a runway other than in use for landing. (ICAO DOC.9137 part 6) Penetration of OLS by the Structure may create collision hazard between the structure and aircraft. During Aeronautical study it is to be determined that the structure would not adversely affect the safety or significantly affect the regularity of aircraft operations.

Safety risk analysis needs to be carried out as indicated in the flow diagram (Source: A methodology to assess the safety of aircraft operations when aerodrome standards cannot be met by Hermut Fricke) during the normal and degraded mode of aircraft operations.

Limitation of Study: Safety impact of allowing the OLS penetration on the aircraft operations in degraded performance mode, such as one engine failure during takeoff or landing, is not 221

analyzed as there was no laid down procedure for the same.

97. Sri Ananth Mandagi, learned Senior Counsel

for the 1st respondent further contended that the as per

the report, safety impact of allowing the OLS

penetration on the aircraft operations in degraded

performance mode, such as one engine failure during

takeoff or landing, is not analyzed as there was no

procedure laid down for the same. He would further

contend that the HAL is the degraded airport and

therefore aeronautical study is not applicable to the

HAL. He also invited the attention of the Court to the

conclusions of the report submitted by the AAI, which

read as under:

9. Conclusions:

a) The existing structure for requested top elevation 954.41 Mts AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin 222

of 21.23M which exceeds the permissible height of 45M by 47.17%.

b) The desired height of 954.41m AMSL is within the maximum allowable penetration of OLS as per the Aeronautical Study guidelines.

c) The safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

d) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

e) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

f) Airport Operator should ensure that the applicant/owner/builder carryout marking and lighting of the structure as per DGCA CAR and the obstacle is published.

223

98. Sri Ananth Mandagi, learned Senior Counsel

stressed his argument to para-9(b) of the report that the

desired height of 954.41 meters AMSL is within

maximum allowable penetration of OLS (Obstacle

Limitation Surface) as per the Aeronautical Study

guidelines. He would submit that the said guidelines

apply only to civil airports. He would further contend

that as per paragraph 9(c) of the said report, the safety

impact of the existing structure due to the degraded

aircraft performance operations is not in the scope of

this study. He would further contend that the airport

operator should ensure that the

applicant/owner/builder carry out marking and lighting

of the structure as per the DGCA (Director General of

Civil Aviation) CAR (Civil Aviation Requirement) and the

obstacle is published. The learned Senior Counsel for

the 1st respondent would further contend that the

restricted supplement to the report of the Gujarat

International Financial Tech-City (GIFT) prescribes that 224

number of previous aeronautical studies undertaken by

ICAO for AAI have stressed the need to preserve free of

obstacles the airspace between the Annex 14 OLS

(including the OHS) and the PANS-OPS obstacle

clearance surfaces to cater for non-normal operations.

This is because major accidents involving a relaxation of

ICAO practices may have consequences which go

beyond the immediate casualties and damage, and raise

wider public discussion. Accidents which involve large

number of fatalities or casualties at schools, hospitals

or high rise buildings raised in such cases. Thus there

are circumstances in which more stringent safety

measures should be retained, even though they may not

be directly cost-beneficial. He would further contend

that the ICAO report on the Aeronautical Study of

obstacles for Gujarat International Financial Tech-City

has given a charitable interpretation to the amendment

of 17th April 2009 by considering the new 300 mts.

outer horizontal surface as an upper limit on any NOC 225

issued by AAI, and recommended the 150 mts. surface

be re-identified as the OHS. This was charitable in that

it has overlooked the interpretation placed on it by the

Times of India, in which it was hailed as a gift to

property developers. It is clear that this later

interpretation is one that appears the more likely one to

be used by individuals and agencies unaware of the

concept of non normal operations and societal risk.

Therefore he submits that the very report submitted by

the respondent pertains to civil airports only.

99. Sri Ananth Mandagi, learned Senior Counsel

for the 1st respondent further draws the attention to the

terms of the memo dated 12.7.2018 filed by the 1st

respondent and the guidelines for Aeronautical Study,

wherein at para-1.5 and 1.6 it is stated as under:

1.5 Objective of regulating the build environment around airport is to protect obstacle limitation surfaces of the airport so that Safety, Efficiency and 226

Regularity of flight operations are maintained and also to prevent the aerodrome from becoming unusable by the growth of obstacles.

1.6 Applicants, who are not satisfied with the height granted by the NOC office, may appeal to the Chairman, Appellate Committee, Ministry of Civil Aviation, RAjiv Gandhi Bhawan Safadarjung airport, New Delhi-110003 for seeking redressal.

Sri Ananth Mandagi, learned Senior Counsel further

contended that the Scope of Aeronautical Study is

stated at para-4 of the Guidelines, which reads as

under:

" 4. SCOPE OF AERONAUTICAL STUDY

4.1 An existing or proposed structure, penetrating or expected to penetrate the obstacle limitation surface as detailed in ICAO Annex 14, resulting in deviation from the Standards, is presumed to be a 227

hazard to air navigation unless the Aeronautical Study determines that safety and regularity of aircraft operations is not adversely affected during the normal aircraft operations.

4.2 An Aeronautical study must identify the effects of the proposed structure:

4.2.1.On the existing and the proposed instrument flight procedures, PBN procedures, departure & arrival procedures, and the minimum flight altitudes of the air-routes, OCA, MSA and Radar Vectoring Altitudes, during normal aircraft operations.

4.2.2 Regarding physical, electromagnetic, or line-of-sight interference on the existing and the proposed, Communications,

Navigation and Surveillance (CNS) facilities.

228

4.2.3 Whether marking and/or lighting of the structure is necessary.

4.3 However, safety impact on the aircraft operations in degraded

operational performance mode is not analysed."

100. Sri Ananth Mandagi, learned Senior

Counsel for Respondent No.1 contended that under

Article 1.8 of the Guidelines for Aeronautical Study, it

is stated that the Appellate Committee, after

considering the request of the applicant for carrying

out the Aeronautical Study, may order for an

Aeronautical Study. He further contended that in the

objections filed by Respondent No.1 to the Aeronautical

Study report submitted by Airports Authority of India,

it is contended that disputed facts and hyper-technical

issues cannot be decided in the writ petition.

Therefore, he sought to dismiss the writ petition. 229

101. In support of his contentions, Sri Ananth

Mandagi, learned Senior Counsel for Respondent No.1

relied upon the following judgments:

i) Shristi Infrastructure Development Corporation Limited & others -vs- Union of India & others -

W.P. No.7652/2015 dated 24th June, 2015, which was case identical to the present case wherein the very impugned notification dated 14.1.2010 was challenged.

ii) Tahsildar, Taluk Office, Tanjore and others -vs-

Thambidurai and another reported in 2017 SAR (Civil) 800

iii) P. Radhakrishna Naidu -vs- Governmetn of Andhra Pradesh and others reported in (1977)1 SCC 561 (paragraph 24)

iv) State of Bihar -vs- Jain Plastics and Chemicals Ltd., reported in (2002)1 SCC 216 (Paragraph-7)

v) New Okhla Industrial Development Authority vs. Kendriya Karamchari Sahkari Grih Nirman Samiti 230

reported in (2006)9 SCC 524 .. (paragraphs 11 and

12)

vi) State of U.P -vs- Lakshmi Sugar & Oil Mills Ltd., reported in (2013)10 SCC 509 .. (paragraph-18)

vii) Prestige lights Ltd., -vs- State Bank of India reported in (2007)8 SCC 449.. paragraphs 33, 35 and 36.

viii) Bhaurao Dagudu Paralkar -vs- State of Maharashtra reported in (2005)7 SCC 605 - (paragraphs 9, 11 and 12)

ix) T. Vijendradas and another -vs- M. Subramanian reported in (2007)8 SCC 751 . (paragraphs 18,19, 27 and 28)

x) Indian Bank -vs- Satyam Fibres (India) Private Limited reported in (1996)5 SCC 550

xi) Amresh Tiwari -vs- Lalta Prasad Dubey reported in (2004)4 SCC 449; and

xii) Chameli Singh -vs- State of U.P. reported in (1996)2 SCC 549 (paragraph 18)

xiii) Mobilox Innovations Private Limited vs. Kirusa Software Private Limited reported in (2017)11 SCALE 754 231

xiv) Yeshwanth Shenoy and others -vs- Union of India and others in PIL No.86/2014 and connected matters decided on 1st September 2016 (paragraphs 3 and 4)

VI. Arguments advanced by Sri Aditya Sondhi, Learned Senior Counsel for Respondent nos.4 to 10

102. Sri Aditya Sondhi, learned Senior Counsel

for Respondent Nos.4 to 10 contended that at the

instance of Respondent Nos.4 to 10, the 1st respondent

- HAL has initiated the proceedings and cancelled the

NOC and the same is in accordance with law. The

Respondent Nos.4 to 10 are neighbours of the

petitioner's building, who will be affected directly, if any

mishaps happen. He would further contend that in

Annexure-R2 issued by the Koramangala Infrastructure

Task Force dated 1.8.2013 addressed to the Defence

Ministry produced along with the impleading

application, a reference is made to the illegal structures

put up by the petitioner. He further contended that 232

the provisions of Section 9A of the Aircrafts Act

contains the word 'prohibit' and therefore, what was

permitted was only 932 meters. After noticing the

illegal constructions beyond 932 meters, HAL issued so

many notices and ultimately cancelled the NOC.

Admittedly, construction put up as on the date of the

cancellation was about 954 meters. He would further

contend that the report submitted by the AAI is not

applicable to the defence airports. He would further

contend that the paragraph 3.3 of the aeronautical

study report relates to 'assessment criteria', wherein it

is stated that "the existing structure is penetrating the

inner horizontal surface and study being conducted to

examine its impact on the safety and regularity of the

aircraft operations". This aeronautical study is

applicable for normal aircraft operations only.

Therefore, he submits that the said report is not

applicable to the defence airports and HAL aircraft is 233

degraded aircraft performances. Therefore, the report

is not applicable.

103. He further contended that in Annexure -

R3 issued by the Assistant General Manager, Airport

Authority of India to the Vice-President, Legal and Land

Affairs, M/s Shobha Developers, it is stated that HAL

Airport, Bangalore is listed in the defence aerodrome

list in SO 84(E) dated 14.1.2010. Hence, the same

cannot be reviewed by the Airports Authority of India.

The aeronautical study conducted by AAI is in respect

of civil airports only and HAL is the defence Airport.

He would further contend that Annexure - B9 produced

along with the objections and the opinion of the Air

Marshal Philip Rajkumar depicts that the nature of

operations being non-standard test flying, it is

imperative that the inner horizontal surface specified

under Section 9A of the Aircraft Act, 1934 be

maintained clear in perpetuity of any structure, which 234

exceeds the laid down height restriction of 45 meters

above the height of airfield reference point (887 meters)

i.e., 887 + 45 = 932 meters AMSL. It is also stated

that this measure will ensure the safety of aircraft

undertaking test flights and citizens living in the

vicinity of the airport. Finally, he contended that

inspite of granting NOC with specific conditions for

building construction, the petitioner constructed in

violation of the NOC conditions. Therefore, the HAL

rightly cancelled the NOC and illegal unauthorized

construction has to be demolished. Therefore, he

sought to dismiss the writ petition.

104. In support of his arguments, Sri Adithya

Sondhi, learned Senior Counsel for Respondent Nos. 4

to 10 relied upon the following judgments:

1. Union of India and others vs. Asian Food Industries -

(2006)13 SCC 542 (paragraph-43)

2. Esha Ekta Apartments Cooperative Housing Society Limited and others vs. Municipal Corporation of 235

Mumbai and others - (2013)5 SCC 357 (paragraphs 2, 4, 5 and 56. )

VII. Points for determination:

105. In view of the rival contentions urged by

the learned counsel for the parties, the points that arise

for determination in the present writ petition are:

(i) Whether the 1st respondent-HAL is justified in canceling the NOC in respect of the entire building including permissive limit height of 62 mtrs + 870 = 932 mtrs (17 floors) ignoring the affidavit of undertaking filed by the petitioner dated 03.10.2011, Annexure-

H1 and the No Objection Certificate issued by the HAL NOC Committee dated 28.10.2011, Annexure-A, without any resurvey of the site property of the petitioner in question?

(ii) Whether the petitioner has made out a case to refer the dispute for the Aeronautical Study by the AAI or any 236

authorized agency, in the facts and circumstances of the present case?

VIII Consideration

106. I have given my thoughtful consideration to

the arguments advanced by the learned Senior Counsel

for the parties and perused the entire material on

record, carefully.

107. It is the specific case of the petitioner that

the petitioner is the owner of the site property in dispute

and is interested in constructing a large residential

complex comprising of 2 basement, ground and 17

floors in multiple wings. Accordingly, approached the

1st respondent-HAL for issuance of NOC. The 1st

respondent-HAL NOC Committee, considering the entire

material, by the letter dated 28.10.2011, has given the

No Objection for construction of the proposed building

with a height of 62 mtrs i.e., 932 mtr AMSL and said

NOC was issued with the approval of the competent 237

authority with certain conditions and after obtaining

necessary sanction modified plans from the

jurisdictional authorities. The petitioner commenced

and carried out the construction of I phase comprising

of 5 wings (B to F) and completed upto 17th floor as long

back as in June to September 2012 and finishing works

are under progress. Phase II comprises of 6 wings (A,

G, H, J, K and proposed wing L. Wing A was completed

upto the 15th floor. Wing G is completed upto the 13th

floor, wing H is completed upto 12th floor and wing J is

completed upto 11th floor. The floors referred are the

upper floors. The petitioner has spent more than

Rs.400 crores and out of the total number of the

proposed 289 flats in 10 wings, 202 flats have been

booked by flat purchasers. 102 flats are on the 11th to

17th floors in the 10th wing, out of which 70 flats have

been booked by various purchasers. When things stood

thus, HAL has cancelled the NOC without verifying the 238

documents and without giving an opportunity of being

heard.

108. It is the specific case of the 1st respondent-

HAL that the petitioner has proceeded to construct the

building contrary to the conditions of NOC issued and

in violation of the provisions of Section 9A of the Aircraft

Act, 1934. Though NOC granted to the petitioner

specifies that the building shall not exceed 932 mtr

AMSL, the petitioner proceeded to construct 954 mtr

AMSL, i.e., 22 mtr more than the height permitted by

the HAL NOC Committee. Therefore, the NOC has been

cancelled by the HAL.

109. In view of the controversy, it is profitable to

refer to the condition Nos.2 and 3 of the NOC dated

28.10.2011, which reads as under:

"2. This Office has no objection to the construction of the proposed Residential Building by M/s Chalet Hotels Ltd., herein after referred to as 239

the applicant(s) at location, Sy.No. 21, 22, 42, 52 and 1B, Koramangala Industrial Layout, Jakkasandra Villager, BBMP Ward No.68, Bangalore, (Coord: Latitude N12˚55'38.28 Longitude E077˚37'55.74') to height 62 Mts. (Sixty Two Meters only) ABOVE GROUND LEVEL, so that the top of the proposed structure when erected shall not exceed 870 Mts (site elevation) + 62 Mts (height of the structure) i.e., 932 Mts.AMSL (ABOVE MEAN SEA LEVEL).

3. This No Objection Certificate is being issued on the express understanding that the sitte-elevation reduced level (height above mean sea level) vis. 870Mts AMSL relative location of the proposed building/structure and its distances and bearings from the ARP, Runway ends as tendered by the applicant(s) are correct. If however at any stage it is established that the said data as tendered by the said applicant is actually different from one tendered 240

and which could adversely affect aircraft operations, the structure of part(s) thereof in respect of which this No Objection Certificate is being issued will have to be demolished at his own cost as may be directed by HAL Airport, Bangalore. The applicant(s) is/are therefore advised in his/their own interest to verify the elevation and other data furnished for the site, before embarking on the proposed construction."

A careful reading of the said conditions makes it clear

that the HAL has no objection for the construction

proposed by the petitioner in the properties Latitude

N12"55'38.28 Longitude E077"37'55.74' to height 62

Mts. (Sixty Two Meters only) ABOVE GROUND LEVEL,

so that the top of the proposed structure when erected

shall not exceed 870 Mts (site elevation) + 62 Mts

(height of the structure) i.e., 932 Mts.AMSL (ABOVE

MEAN SEA LEVEL). If however, at any stage, it is 241

established that the said data as tendered by the

petitioner is actually different from one tendered and

which could adversely affect aircraft operations, the

structure of part(s) thereof in respect of which this No

Objection Certificate is being issued will have to be

demolished at the cost of the petitioner as may be

directed by HAL Airport, Bangalore, and therefore, it

was advised that the petitioner shall verify the elevation

and other data furnished for the site, before embarking

on the proposed construction. Paragraph-8 of the No

Objection Certificate dated 28.10.2011 clearly states

that, day and night markings with the secondary power

supply may be provided as per ICAO standards.

"NOC FOR HEIGHT CLEARANCE ONLY"

It is also specifies that the certificate is issued with the

approval of the competent authority. 242

IX. Provisions of Aircraft Act and Rules relied upon

110. In view of the controversy, it is relevant to

refer to the provisions of the Aircraft Act, 1934.

Section 2(1) defines that "aircraft" means any

machine which can derive support in the atmosphere

from reaction of the air [other than reactions of the air

against the earth's surface] and includes balloons,

whether fixed or free, airships, kites, gliders and flying

machines;

Section 2(2) defines that "aerodrome" means any

definite or limited ground or water area intended to be

used, either wholly or in part, for the landing or

departure of aircraft, and includes all buildings, sheds,

vessels, piers and other structures thereon or

appertaining thereto;

Section 2(A) defines that "aerodrome reference

point" in relation to any aerodrome, means a designated 243

point established in the horizontal place at or near the

geometric centre of that part of the aerodrome reserved

for the departure or landing of aircraft.

The provisions of Section 5 refers to the Power of

Central Government to make rules, and reads as

under:-

Power of Central Government to make rules.

(1) [Subject to the provisions of section 14, the Central Government] may, by notification in the Official Gazette, make rules regulating the manufacture, possession, use, operation, sale, import or export of any aircraft or class of aircraft 2[and for securing the safety of aircraft operations.]

(2) Without prejudice to the generality of the foregoing power, such rules may provide for--

(a) the authorities by which any of the powers conferred by or under this Act are to be exercised;

244 [(aa) the regulation of air transport services,and the prohibition of the use of aircraft in such services except under the authority of and in accordance with a licenceauthorising the establishment of the service;

[(ab) the economic regulation of civil aviation and air transport services, including the approval, disapproval 5[or revision on tariff of operators of air transport services [other than the tariff referred to to in clause (a) of sub-section (1) of section 13 of the Airports Economics Regulatory Authority of India Act, 2008]] or revision of tariff of operators of air transport services; the officers or authorities who may exercise powers in this behalf; the procedure to be followed and the factors to be taken into account by such officers or authorities; appeals to the Central Government against orders of such officers or authorities and all other matters connected with such tariff.

Explanation.--For the purposes of this clause, "tariff" includes fares, rates, valuation 245

charges and other charges for air transport of passengers or goods, the rules, regulations, practices or services affecting such fares, rates, valuation charges and other charges and the rates, terms and conditions of commission payable to passenger or cargo sales agents;]

[(ac) the information to be furnished by an applicant for, or the holder of, a licence authorising the establishment of an air transport service to such authorities as may be specified in the rules;]

[(b) the licensing, inspection and regulation of aerodromes, the conditions under which aerodromes may be maintained and the prohibition or regulation of the use of unlicensed aerodromes;

(ba) the fees which may be charged at those aerodromes to which the Airports Authority of India Act, 1994(55 of 1994) does not apply or is not made applicable;] 246

(c) the inspection and control of the manufacture, repair and maintenance of aircraft and of places where aircraft are being manufactured, repaired or kept;

(d) the registration and marking of aircraft;

(e) the conditions under which aircraft may be flown, or may carry passengers, mails or goods; or may be used for industrial purposes and the certificates, licences or documents to be carried by aircraft;

(f) the inspection of aircraft for the purpose of enforcing the provisions of this Act and the rules thereunder, and the facilities to be provided for such inspection;

(g) the licensing of persons employed in the operation, manufacture, repair or maintenance of aircraft;

[(ga) the licensing of persons engaged in air traffic control;

(gb) the certification, inspection and regulation of communication, navigation and surveillance or air traffic management facilities;

247

(gc) the measures to safeguard civil aviation against acts of unlawful interference;]

(h) the air-routes by which and, the conditions under which aircraft may enter or leave [India], or may fly over 8[India], and the places at which aircraft shall land;

(i) the prohibition of flight by aircraft over any specified area, either absolutely or at specified times, or subject to specified conditions and exceptions;

(j) the supply, supervision and control of air-route beacons, aerodrome lights, and lights at or in the neighbourhood of aerodromes or on or in the neighbourhood of air-routes;

[(jj) the installation and maintenance of lights on private property in the neighbourhood of aerodromes or on or in the neighbourhood of air-routes, by the owners or occupiers of such property, the payment by the Central Government for such installation and maintenance, 248

and the supervision and control of such installation and maintenance, including the right of access to the property for such purposes;]

(k) the signals to be used for purposes of communication by or to aircraft and the apparatus to be employed in signaling;

(l) the prohibition and regulation of the carriage in aircraft of any specified article or substance;

(m) the measures to be taken and the equipment to be carried for the purpose of ensuring the safety of life;

(n) the issue and maintenance of log-books; .

(o) the manner and conditions of the issue or renewal of any licence or certificate under the Act or the rules, the examinations and tests to be undergone in connection therewith, the form, custody, production, endorsement, cancellation, suspension or surrender of such licence or certificate, or of any log-book;

(p) the fees to be charged in connection with any inspection, examination, test, certificate or licence, made, issued or renewed under this Act; 249

(q) the recognition for the purposes of this Act of licences and certificates issued elsewhere than in 11[India] relating to aircraft or to the qualifications of persons employed in the operation, manufacture, repair or maintenance of aircraft;

[(qq) the prohibition of slaughtering and flaying of animals and of depositing rubbish, filth and other polluted and obnoxious matter within a radius of ten kilometers from the aerodrome reference point; and]

(r) any matter subsidiary or incidental to the matters referred to in this sub-section.

111. The provisions of Section 6 refers to the

Power of Central Government to make orders in

emergency, and reads as under-

Power of Central Government to make orders in emergency.

(1) If the Central Government is of opinion that in the interest of the public 250

safety or tranquility the issue of all or any of the following orders is expedient, it may, by notification in the Official Gazette,--

(a) cancel or suspend, either absolutely or subject to such conditions as it may think fit to specify in the order, all or any licences or certificates issued under this Act;

(b) prohibit, either absolutely or subject to such conditions as it may think fit to specify in the order, or regulate in such manner as may be contained in the order, the flight of all or any aircraft or class of aircraft over the whole or any portion of 1[India];

(c) prohibit, either absolutely, or conditionally, or regulate the erection, maintenance or use of any aerodrome, aircraft factory, flying-school or club, or place where aircraft are manufactured, repaired or kept, or any class or description thereof; and 251

(d) direct that any aircraft or class of aircraft or any aerodrome, aircraft factory, flying-school or club, or place where aircraft are manufactured, repaired or kept, together with any machinery, plant, material or things used for the operation, manufacture, repair or maintenance of aircraft shall be delivered, either forthwith or within a specified time, to such authority and in such manner as it may specify in the order, to be at the disposal of Government for the public service.

[(1A) Any order made under sub-section (1) shall have effect notwithstanding anything inconsistent therewith contained in any rule made under this Act.]

(2) Any person who suffers direct injury or loss by reason of any order made under clause (c) or clause (d) of sub-

section (1) shall be paid such compensation as may be determined by 252

such authority as the Central Government may appoint in this behalf.

(3) The Central Government may authorise such steps to be taken to secure compliance with any order made under sub-section (1) as appear to it to be necessary.

(4) Whoever knowingly disobeys, or fails to comply with, or does any act in contravention of, an order made under sub-section (1) shall be punishable with imprisonment for a term which may extend to three years, or with fine, or with both, and the Court by which he is convicted may direct that the aircraft or thing (if any) in respect of which the offence has been committed, or any part of such thing, shall be forfeited to Government.

112. The provisions of Section 9A refers to Power

of Central Government to prohibit or regulate 253

construction of buildings, planting of trees, etc., as

under-

[9A. Power of Central Government to prohibit or regulate construction of buildings, planting of trees, etc. -- (1) If the Central Government is of opinion that it is necessary or expedient so to do for the safety of aircraft operations, it may, by notification in the Official Gazette,--

(i) direct that no building or structure shall be constructed or erected, or no tree shall be planted on any land within such radius, not exceeding twenty kilometers from the aerodrome reference point, as may be specified in the notification and where there is any building, structure or tree on such land, also direct the owner or the person having control of such building, structure or tree to 254

demolish such building or structure or, as the case may be, to cut such tree within such period as may be specified in the notification;

(ii) direct that no building or structure higher than such height as may be specified in the

notification shall be constructed or erected, or no tree, which is likely to grow or ordinarily grows higher than such height as may be specified in the notification, shall be planted, on any land within such radius, not exceeding twenty kilometers from the aerodrome reference point, as may be specified in the notification and where the height of any building or structure or tree on such land is higher than the specified height, also direct the owner or the person having control of such building, structure or tree to 255

reduce the height thereof so as not to exceed the specified height, within such period as may be specified in the notification.

(2) In specifying the radius under clause

(i) or clause (ii) of sub-section (1) and in specifying the height of any building, structure or tree under the said clause

(ii), the Central Government shall have regard to--

(a) the nature of the aircraft operated or intended to be operated in the aerodrome; and

(b) the international standards and recommended practices

governing the operation of aircraft.

(3) Where any notification has been issued under sub-section (1) directing the owner or the person having control of any building, structure or tree to demolish such building or structure or to cut such tree or to reduce the height of 256

any building, structure or tree, a copy of the notification containing such direction shall be served on the owner or the person having the control of the building, structure or tree, as the case maybe, --

(i) by delivering or tendering it to such owner or person; or

(ii) if it cannot be so delivered or tendered, by delivering or tendering it to any officer of such owner or person or any adult male member of the family of such owner or person or by affixing a copy thereof on the outer door or on some conspicuous part of the premises in which such owner or person is known to have last resided or carried on business or personally worked for gain; or failing service by these means;

(iii) by post.

257

(4) Every person shall be bound to comply with any direction contained in any notification issued under sub-

section (1).]

A careful reading of the said provisions makes it clear

that, no building or structure shall be constructed or

erected, or no tree shall be planted on any land within

such radius, not exceeding twenty kilometers from the

aerodrome reference point, as may be specified in the

notification and where there is any building, structure

or tree on such land, also direct the owner or the person

having control of such building, structure or tree to

demolish the same within the period specified in the

notification; and no building or structure specified in

the notification shall be constructed or erected, or no

tree, which is likely to grow or ordinarily grows higher

than the point specified in the notification shall be

planted in any land within such radius , not exceeding

twenty kilometers from the aerodrome reference point, 258

as specified in the notification and where the height of

any building or structure or tree on such land is higher

than the specified height, the owner be directed to

reduce the height of the building or tree so as not to

exceed the specified height, within such period specified

in the notification.

Sub Section (2) of Section 9A of the Act envisages that,

in specifying the radius and the height of any building,

structure or tree, under clauses (i) and (ii) of sub

Section (1) of Section 9A, the Central Government shall

have regard to the nature of the aircraft operated or

intended to be operated in the aerodrome and the

international standards and recommended practices

governing the operation of aircraft. Sub Section (3) of

Section 9A of the Act envisages that, where any

notification has been issued under sub-Section (1)

directing the owner or the person having control of any

building, structure or tree to demolish such building or 259

structure or to cut such tree or to reduce the height of

any building, structure or tree, a copy of the notification

containing such direction shall be served on the owner

or person having control of the building, structure or

tree, by delivering or tendering it to such owner or

person, or if it cannot be so delivered or tendered, a

copy thereof shall be affixed on the outer door or on

some conspicuous part of the premises and by post and

that every person shall be bound to comply with such

direction contained in any notification issued under sub

Section (1) of Section 9A.

113. The provisions of Section 11B refers to

Penalty for failure to comply with directions issued

under Section 9A, which reads as under:

[11B. Penalty for failure to comply with directions issued under section 9A.-- (1) If any person wilfully fails to comply with any direction contained in any notification issued under section 260

9A, he shall be punishable with imprisonment for a term which may extend to [two years, or with fine which may extend to ten lakh rupees], or with both.

(2) Without prejudice to the provisions of sub-section (1), if any person fails to demolish any building or structure or cut any tree or fails to reduce the height of any building, structure or tree in pursuance of any direction contained in any notification issued under sub-

section (1) of section 9Awithin the period specified in the notification, then, subject to such rules as the Central Government may make in this behalf, it shall be competent for any officer authorised by the Central Government in this behalf to demolish such building or structure or cut such tree or reduce the height of such building, structure or tree:] 261

[Provided that the power to make rules under this sub-section shall be subject to the provisions of section 14.]

114. The provisions of Sub Rule (1C) of Rule 3 of

the Aircraft Rules, 1937 defines that 'air traffic' means,

all aircraft in flight or operating on the manoeuvring

area of an aerodrome.

Sub Rule (1D) of Rule 3 defines that 'Air Traffic

Controller' means a person on duty in an air traffic

services unit and entrusted with the task of giving

instructions, clearance or advice to aircraft by approved

means of communication in the interest of safety of

aircraft operations.

Sub Rule (2) of Rule 3 defines that 'Aerodrome'

means any definite or limited ground or water area

intended to be used, either wholly or in part, for the

landing or departure of aircraft, and includes all 262

buildings, sheds, vessels, piers and other structures

thereon or appertaining thereto.

Sub Rule (4A) of Rule 3 defines that 'Aeronautical

beacon' means an aeronautical ground light visible at

all azimuth either continuously or intermittently to

designate a particular point on the surface of the earth.

Sub Rule (4B) of Rule 3 defines that 'Aeronautical

ground light' means any light provided as an aid to air

navigation other than a light displayed on an aircraft.

Sub Rule (5) of Rule 3 defines that 'Aeroplane'

means a power-driven heavier-than-air aircraft, deriving

its lift in flight chiefly from aerodynamic reactions on

surfaces which remain fixed under given conditions of

flight.

Sub Rule (13A) of Rule 3 defines that 'convention'

means the convention relating to International Civil 263

Aviation signed at Chicago on the 7th day of December,

1944, as amended from time to time.

Sub Rule (17A) of Rule 3 defines that 'Defence

Aerodrome' means an aerodrome owned and operated

by Indian Air Force, Indian Navy or Indian Army.

Sub Rule (27) of Rule 3 defines that 'Government

aerodrome' means an aerodrome which is maintained

by or on behalf of the Central Government and includes

an airport to which the Airports Authority of India Act,

1994 (55 of 1994) applies or is made applicable.

Sub Rule (33) of Rule 3 defines that 'landing area'

means that part of an aerodrome reserved for the

departure or landing of aircraft.

Sub Rule (34A) of Rule 3 defines that

'Manoeuvring area' means that area of an aerodrome

which is to be used for the take-off and landing of an 264

aircraft and for the movement of aircraft associated with

the take-off and landing.

Sub Rule (35A) of Rule 3 defines that 'Movement

Area' means the area of an aerodrome which is intended

for the surface movement of an aircraft and includes the

manoeuvring area and aprons.

Sub Rule (48A) of Rule 3 defines that 'safety'

means the state in which the risk of harm to persons or

of property damage is reduced to and maintained at or

below an acceptable level of safety through a continuing

process of hazard identification and risk management.

Sub Rule (48B) of Rule 3 defines that 'safety

oversight function' means a function by means of which

the safety-related standards and recommended

practices and associated procedures contained in the

Annexes to the Convention are implemented. 265

A careful reading of the provisions of the Aircraft Act,

1934 and the Aircraft Rules, 1937, referred to above,

clearly indicates that a person who obtains NOC from

the HAL NOC Committee for construction, has to follow

the procedures and conditions imposed therein and

should not dilute the same.

115. According to the petitioner, he has not

violated any of the terms and conditions of the NOC.

But according to the respondent No.1, the petitioner has

violated the conditions of NOC and sought resurvey of

site and cancelled the NOC to the entire building

instead of restricting the cancellation of NOC to the

unauthorized construction made beyond the permissive

limit granted under the NOC. A careful reading of

Annexure-AQ, Cancellation of No Objection Certificate

for height clearance, dated 16.08.2013, depicts as to

what is the basis for the first respondent to come to the

conclusion that the petitioner has violated condition 266

No.3 and 4 of the NOC dated 28.10.2011 and has not

recorded any finding with regard to violation and how

the construction would affect the aircraft operations as

per condition No.3 already stated supra, that at any

stage, if it is established that the data tendered by the

applicant is actually different from one tendered and

which could adversely affect aircraft operations, the

structure of part(s) thereof in respect of which NOC is

issued will have to be demolished. It only refers to the

fact that, during a random check, the site elevations

were compared with that given in the Survey of India

(SOI) maps. It was observed that the declared elevation

of 870 mtrs AMSL for the site varies significantly, i.e.,

actual elevation could be as high as 890 mtrs AMSL. It

is also not in dispute that the petitioner has not

challenged the NOC for height clearance of 62 mtr

Above Ground Level/932 mtrs AMSL in the site property

in question. According to the petitioner, he has not

violated the terms and conditions of NOC and he has 267

taken a specific contention with regard to construction

of the building blocks 'A' to 'L' and taken a specific

contention in the grounds, at paragraphs 66, 73, 75, 80

and 83 of the memorandum of writ petition, which

reads as under:

"66. No power exists in either the Aircraft Act or the Rules or in the NOC authorizing the 1st respondent to cancel the NOC. Further, nearly two years have lapsed from the date of issue of the NOC and that being the case, it would be wholly inequitable for the respondent to cancel the same after the petitioner has acted upon the said NOC and has spent enormous amounts of money and major portion of construction upto 17 floors has been completed since long, and after purchasers have booked the flats and paid monies for the same by themselves or through bank loans.

73. The respondent has failed to notice that the delay in conducting 268

detailed survey and the aeronautical studies have been only because of the dithering stand of the respondent who has on the one breath asked the petitioner to go ahead with the survey and aeronautical study and in the other breath have not cooperated with the petitioner in getting the same done. The AAI has written to the respondent and indicated its willingness to conduct an aeronautical survey. The petitioner even sent a demand draft favouring the AAI covering the fees prescribed for the study. Despite the same, the respondent has not at all cooperated in getting the aeronautical study done.

75. The respondent has sought to cancel the NOC without giving an opportunity of hearing to the petitioner and in this regard, there have been gross errors of principles of natural justice.

269 80. The respondent being issued the NOC and the BBMP having sanctioned the plan based on such NOC, and based on which the petitioner having constructed the complex by expending huge sums of money, the respondent are estopped from canceling the NOC and sanction plan.

83. The respondent has erred in limiting the construction in the said property to only 932 mts AMSL, when in fact the ASR would indicate that the height at which the aircraft operations would not get affected is 964 mts. There is absolutely no justification for the height of 932 mts when the petitioner is actually entitled to construct to the full height of 964 mts., which would not adversely affect aircraft operations."

Even in the order of cancellation of NOC as per

Annexure-AQ dated 16.08.2013, at paragraph-7, it is

stated that, 'if the petitioners wants a fresh NOC, he is 270

advised to apply for the same after getting the survey

done by Karnataka State Remote Sensing Application

Centre (KSRSAC) or Survey of India'. Therefore, it is

clear that the HAL is not sure about the alleged

violation by the petitioner and no material is produced

before this Court to establish that the construction

made is contrary to the data tendered by the petitioner

and which could adversely affect aircraft operations or

the structures of part(s) thereof in respect of which the

NOC is issued.

116. This Court, in the present writ petition, by

the Order dated 31.07.2014, while granting interim

Order, held that, 'in the circumstances, no injustice will

be caused to the first respondent if directed to request

AAI to process petitioner's application to conduct an

aeronautical study of the Bengaluru (HAL) Aerodrome at

the cost of the petitioner, after due process, in

compliance with clause-5 of Annexure II to the 271

notification, Annexure-B'. The said Order was

subsequently modified by the Order dated 05.11.2015

to the effect that, 'the aeronautical study of Bengaluru

(HAL) Aerodrome is for the purpose of ascertaining as to

whether or not the building constructed or to be

constructed to the height of 62 meters above the ground

level of property in question in accordance with notified

parameters and Annexure-B to the petition for HAL

Airport would affect (safety) of the Airport operations'.

The said Order was subject matter of Appeal in

W.A.No.2572 of 2014 and the Division Bench of this

Court, by the Order dated 03.09.2015, at paragraphs 5,

6, 7, 8, 9, 10, 11 and 12, held as under:

"5. The Hon'ble Single Judge, by the Order impugned, directed the Airport Authority of India to process the application of the writ petitioner to conduct an aeronautical study of the Bengaluru (HAL) Aerodrome at the cost of the writ petitioner.

272 6. By the order impugned, no rights of the parties have been decided. The report that would be submitted before the Hon'ble Single Judge would be subject to the result of the writ petition.

7. Mr.Pradeep S. Sawkar, learned advocate, strenuously, submits that once the notification has been issued under Section 9-A of the Aircrafts Act, 1934, it was impermissible to issue another aeronautical study.

8. We are not concerned with the issue at this stage inasmuch as the Hon'ble Single Judge has not decided any point for consideration; His Lordship only directed an aeronautical study. We do not know what shall be the report.

9. We, therefore, decide not to interfere with the order impugned as nothing has been decided between the parties.

10. The writ appeal is, therefore, dismissed.

273 11. We, however, request the Hon'ble Single Judge to expedite the hearing of the writ petition as far as possible and to decide the matter uninfluenced by the observations made in the order impugned.

12. We express no opinion on the merits of the case."

This would clearly indicate that the Division

Bench has held that the learned single Judge has not

decided the rights of the parties and report would be

submitted before the learned single Judge and that

would be subject to the result of the writ petition and

directed the learned single Judge to expedite the writ

petition.

117. In pursuance of the order passed by the

learned single Judge, the HAL submitted the report in

the month of December 2015 and at paragraph-9 has

come to the conclusion as under:

274

"9.Conclusions:

a) The existing structure, for requested top elevation 954.41mtr AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin of 21.23 M which exceeds the permissible height of 45M by 47.17%.

b) The desired height of 954.41m AMSL is within the maximum allowable penetration of OLS as per the Aeronautical Study guidelines.

c) The Safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

d) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

e) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

275

f) Airport Operator should ensure that the applicant/owner/builder carry out marking and lighting of the structure as per the DGCA CAR and the obstacle is published."

It is relevant to state at this stage that in the writ

petition filed by the Airport Authority of India

Employees Union vs. the Union of India and others in

W.P.No.11486/2008 (GM-PIL), the HAL filed affidavit of

one Mr.Rajender Sharma, working as Head, Airport

Service Centre, HAL, Bengaluru Complex, Bengaluru,

dated 04.07.2015, wherein at paragraphs 6 and 7, it is

stated as under:

"6. I state presently HAL airport being used only for military flying, test flights, chartered and VVIP flights. HAL airport continues to operate 24 x 7 to support these flights without any downgrade in the infrastructure and services provided, which are presently under utilized considering the volume of 276

aircraft movement handled earlier. HAL airport also supports Test flying and experimental flying pertaining to Aeronautical Development Agency (ADA), Aircraft Systems Test Measurement (ASTE), National Aeronautical Laboratory (NAL), Centre for Airborne Systems (CABS) and it also provides support for proving out new systems/UAVs (Unmanned Arial Vehicles) which involves very complex navigation.

7. I state it is pertinent to mention here that separation standards prescribed fin ICAO (International Civil Aviation Organization) documents and DGCA Guidelines are strictly adhered by HAL ATC for both civil and military aircraft movement at all times. The safety measures for all the flights whether it is defence or civil flights is one and the same and the facilities which are extended cannot be distinguished between Civil Flights as well as Defence Flights."

277 118. It is also pertinent to note the relevant

clauses of the procedure for issue of NOC for height

clearance by HAL, which reads as under:

"2.1 The Indian Aircraft Act, 1934 Section 9A empowers the Central Government to restrict the construction of buildings and other structures within a radius of 20 kms of an aerodrome. The current gazette notification on the subject is Government of India, Ministry of Civil Aviation Notification S.O.84(E) dated 14th January 2010. The criterial employed in this notification are based on Obstacle Limitation Surfaces as discussed in ICAO Annex 14, and other ICAO documents such as Annex 10 and Doc 8168.

5.9 All the cases will be decided in accordance with the provision of Government of India Gazette and

additional restrictions imposed by HAL authorities. At present, there are three additional restrictions/conditions imposed 278

by HAL, to facilitate special test flying at low level. This is a deviation from S.O.84(E):

(i) Maximum permissible elevation within a radius of 20 km from Aerodrome Reference Point (ARP) of HAL Airport:

1037M AMSL (150M above Aerodrome Elevation of HAL Airport 887M AMSL) instead of 1187 M AMSL (300 M above Aerodrome Elevation of HAL Airport as per S.O.84(E).

(ii) Criteria for the structures which do not constitute "Large Objects" mentioned in para 2.5 and 2.6 of

S.O.84(E) are not to be implemented.

(iii) Aeronautical study for permitting more height is not applicable."

In response to the directions issued by the HAL for the

revised proposal, the petitioner filed an undertaking

dated 03.10.2011 wherein, at paragraph-3, the 279

petitioner has specifically undertaken that, "No radio/

television/microwave/telecom aerial mast, lightning

arrestors, staircase room, lift machine room, vent pipes,

overhead water tanks and attachments or super

structures of any description will project above 932.00

mtrs of the structures which are not indicated in the

submitted drawings. Based on such an undertaking,

the HAL issued NOC dated 28.10.2011, with certain

conditions.

119. It is the specific case of the petitioner that

based on the HAL's - NOC Committee permission for

construction of building to a height of 62 meters and as

per the BBMP sanction plan for construction the

building of 17 floors i.e., 62 meters has been

constructed and not 954 meters as alleged, and it has

not constructed more than 62 meters (17 floors) above

the ground level as permitted under the NOC. The

height of the existing building is in terms of the NOC 280

permitted height is 62 meters above ground level and

not 62 meters + 22 meters as alleged by the 1st

respondent. It is the further case of the petitioner that

though it had applied for sanction of NOC by the letter

dated 21.9.2011 to construct a structure of 110 meters,

upto 25 floors and an affidavit of undertaking was also

filed in Form No.1A dated 19.9.2011 wherein at para-3

of the affidavit it has specifically stated that no

structure will project above 980 meters of the structure

which are not indicated in the submitted drawings, the

HAL by a letter dated 28.9.2011 had directed the

petitioner to file a revised application for NOC reducing

the height and to file an affidavit to the effect that 'the

Height Clearance upto restricted height of 62 meters

above ground level/932 meters AMSL is recommended

by NOC Committee and it was required to submit the

revised undertaking (Form 1A) and building plans

showing sanction/revised elevations/site location plans

(i.e., for the reduced structure height of 62 meters) as 281

per the drawings showing the height/floors for NOC

applications. Accordingly, the petitioner by the letter

dated 3.10.2011 applied for height clearance of 62

meters as recommended with the revised drawing for 62

meters 17 floors and revised Undertaking. In para-3 of

the revised undertaking, it has been specifically stated

that no structure will 'project above 932.00 meters of

the structure which are indicated in the submitted

drawings'. Accordingly, the HAL considering the revised

application with sanctioned plan and revised

undertaking filed, has issued NOC dated 28.10.2011 for

a height upto 62 meters. According to the petitioner,

construction of the structure is to an height of 62

meters (17 floors) as permitted under the HAL-NOC

Committee and sanctioned plan by BBMP. Therefore,

there is no difference in height permitted by the HAL-

NOC Committee and no extra/illegal construction in

violation of NOC/Undertaking made by the petitioner. 282

120. It is also not in dispute that the 1st

respondent is aware of the discrepancy being

inadvertent error by Precision Surveys, whose site

elevation certificates have been regularly accepted by

the HAL. As can be seen from Annexure-BQ,

commencing from 8.11.2010 to 30.6.2011 about 36

sample certificates have been issued by Precision

Surveys and accepted by HAL for issuing height NOCs.

The same is admitted by the HAL in the reply to the

rejoinder statement of the petitioner in the present writ

petition. At para-7, it is stated that 'the Gazette

Notification dated 14.1.2010 as well as Annex-14 of the

ICAO Guidelines are consistent with each other in as

much as the Inner Horizontal Surface is the surface

which extends to 45 meters above an Aerodrome and its

environs measured from a Reference Point established

for the said purpose and no fixed objects shall be

permitted above the said surface. In the instant case,

the construction site of the petitioner is within the Inner 283

Horizontal Surface and therefore, the proposed

structure cannot exceed the said surface i.e., 45 meters

from the Aerodrome Reference Point i.e., 887 meters.'

In para-20 of the said rejoinder, it is specifically stated

by the HAL that 'it is true that elevation certificates of

M/s Precision Surveys have been accepted by the

respondent in the past, however, there was no

discrepancy or difference in the data furnished therein.'

It is also admitted by the HAL in the affidavit dated

16.10.2017 filed by Sri Rajender Sharma, Additional

General Manager (Civil Helicopter), who has duly sworn

to, wherein at para-4 he has stated that in respect of a

few other NOCs when the discrepancy regarding site

elevation was notified, the original NOC issued on the

basis of incorrect site elevation was treated as null and

void and the Builders/Developers were directed to apply

afresh after resurvey of the property and accordingly,

fresh NOCs have been issued to those applicants, who

conducted a re-survey in accordance with the 284

stipulations prescribed in the Notification dated

14.1.2010.

121. In identical circumstances, the Co-ordinate

Bench of Delhi High Court in the case of KGA

INVESTMENTS -VS- UNION OF INDIA AND OTHERS in

W.P.(C) 9509/2018 AND C.M.NO.38741/2018

D.D.20.11.2018 has held as under:

"Apparently, the Municipal Corporation had also issued certificates with regard to the height of the site elevation in respect of various sites, which were now found to be inaccurate. This issue was discussed at a joint meeting held between the representatives of the AAI, the Municipal Corporation and MIAL on 10.10.2017. At the said meeting, it was decided that the list of such buildings would be prepared by the Municipal Corporation and that list would be provided to the AAI. AAI in turn would send the list to the concerned authority with a request to 285

conduct Aerodrome Study without issuing orders for demolition of the excess height."

122. It is also not in dispute that the respondent-

HAL on 15.9.2012 had directed the M/s. Precision

Surveys (India) Private Ltd., for resurvey of the site

located at Sy.Nos.21, 22, 42, 52 and 1B, Koramangala

Industrial Layout, Jakkasandra Village, BBMP Ward

No.68, Bangalore (petitioner property) specifically

stating that the NOC for height clearance of 62 Meters

for the proposed building at the above mentioned site

was issued by HAL-NOC-Committee, based on the

Coordinates and Elevations of the site, checked and

verified by it. However, it was found that the elevation

(870M AMSL) of the site surveyed by it vastly differed

from the data available with them. Hence, it was

advised to carry out a resurvey of the site and submit a

report to the undersigned, within 15 days after the

receipt of that letter. Similar reminders were also 286

issued to that effect and ultimately, the HAL by a

reminder dated 19.2.2013 to the M/s. Precision Surveys

(India) Private Ltd., at para-4 specifically stated that

'However, no letter was received from you till date.

Hence, you are reminded to do the resurvey and submit

the report within 15 days from the receipt of this letter.'

It is also not in dispute that 1st respondent has neither

filed any counter nor denied or disputed the documents

or statements of M/s Precision Surveys regarding

inadvertent error committed by the said Survey

Authority which clearly indicates that the difference is

not on account of excess construction of a permitted 62

meters building, but it seems to be due to the difference

in site elevation as earlier arrived at by Precision

Surveys and later arrived at by KSRSAC. Admittedly in

the present case, the height of the NOC issued by the

Committee on the basis of the Site Elevation data

provided to the petitioner, Municipal Corporation has 287

sanctioned building plans based on and for height

permitted under the NOC; Structure constructed as per

the height permitted under the NOC; Discovery of

variation in site elevation after completion of

construction; Discrepancy due to site elevation

certificate issued by the third party i.e., Corporation,

was later found to be 'inaccurate'; the difference of

survey conducted by the two survey authorities in site

elevation has resulted in a difference of the derived top

elevation of the constructed structure.

123. It is the specific case of the 1st respondent-

HAL that for granting the prayer sought in the present

writ petition, the petitioner has not made out any legally

and statutorily enforceable right and therefore, no relief

can be granted under Article 226 of the Constitution of

India for doing something which is not provided under

the height regulations and therefore, the writ is not

maintainable. It is not in dispute that the 1st 288

respondent HAL has issued NOC for construction of

building upto 62 meters. If on the difference of opinion

by two survey authorities, it has come to the conclusion

that due to the difference in site elevation the 1st

respondent cannot cancel and withdraw the NOC, de-

regularizing the entire permitted existing 62 meters

structure, if for any reason, the petitioner has violated

the conditions of NOC and constructed the above

permissive limit of 62 meters, in terms and conditions of

NOC, there is no requirement for the petitioner to apply

for fresh NOC. It has to be ascertained onlyafter

resurvey done by the competent survey authorities.

After verification in terms of the Regulations of HAL, if

procedure permits, it can apply for NOC and the

construction, if made above permissible limit in terms of

NOC, what is the extent it has constructed beyond

permissive limit and whether it adversely affects the

aircraft operations, has to be verified. If, however, it is

established based on the material documents that the 289

data tendered by the applicant is actually different from

the one tendered which would adversely affect the

aircraft operations, the structure of parts thereof in

respect of which this 'NOC' is being issued will have to

be demolished at his own costs and not the entire

building (permitting existing 62 meters structure).

Ultimately, after conducting resurvey, if the petitioner

has constructed structure beyond permission granted

by the NOC Committee and prohibits further

construction beyond 62 meters, then necessary action

has to be taken with regard to unauthorized

construction in accordance with the provisions of

Section 9A of the Act and Rules 3 and 6 of the Aircraft

(Demolition of Obstructions caused by Buildings and

Trees, etc) Rules,1994 and in accordance with law, if

the structure would affect the aircraft operations.

124. The 1st respondent ignoring NOC conditions

and regulations as stated in reply dated 5.10.2013 to 290

the rejoinder of the statement of the petitioner has

stated that there is no requirement in law to establish

as to which portion of the structure would affect Aircraft

Operations once it has been established that the said

structure penetrates over and above Obstacle Limitation

Surface which clearly indicates that the HAL has

ignored its own terms and conditions of NOC and

Regulations. Therefore, the said contention cannot be

accepted. The authority, who issued NOC before

cancellation should act based on the established

material documents on record whether the construction

is beyond permissive limit and whether it affects the

Aircraft Operations. Without ascertaining or

establishing which portion of the construction would

actually affect the Aircraft Operations, withdrawal of

entire NOC including the permitted construction cannot

be sustained and the petitioner in the present writ

petition cannot seek regularization of illegal structure, if

any. The entire case of the petitioner is the protection 291

of a structure constructed within the permissive limit in

terms and conditions of NOC issued and it is not the

case of the 1st respondent that the permissive limit of

construction under 'NOC' issued in favour of the

petitioner would adversely affect the aircraft operations.

In view of the above, the 2nd relief sought for, in the

present writ petition for a writ of mandamus seeking

regularization of unauthorized construction, if any, is

not maintainable. It is for the concerned competent

authority to resurvey the site elevation to verify the

illegal construction, if made, by the petitioner.

125. It is also relevant to state that the 1st

respondent- HAL has not produced any material as to

how the permitted 62 meters construction would

adversely affect the Aircraft Operations inspite of the

report submitted by the AAI confirming that 62 meters

structure with top elevation of 954 meters AMSL, does

not adversely affect aircraft operations and is within the 292

permissible limits. Though the order passed by the

learned Single Judge directing the AAI to submit a

report was the subject matter of writ appeal and the

Division Bench of this Court has not expressed any

opinion on merits and has not interfered with the orders

passed by the learned Single Judge directing the AAI to

submit a report, admittedly, the report submitted by the

AAI is not at all challenged by the 1st respondent. But

the fact of granting NOC for construction of the building

with an height of 62 meters above ground level, so that

the top of the proposed structure when erected shall not

exceed 870m (site elevation) + 62m i.e, 932 meters

AMSL as per Annexure-A and the Notification dated

14.01.2010 fixing the parameters by the Central

Government as per Annexure-B, is not challenged by

the petitioner. Of course as stated above, the Division

Bench has observed that the report of AAI is subject to

the result of the present writ petition. Therefore, it is

necessary to consider, whether the 1st respondent-HAL 293

is justified in canceling the NOC for the entire 62 meters

(17 floors) ignoring its own NOC recommendation and

undertaking of the petitioner.

126. It is relevant to state at this stage that

Seven Experts have given their opinions confirming the

safety of Aeronautical Study in the present case which

are as under:

I. Mr. Ramesh Chander Khurana, Aviation Consultant (Annexure-AV), dated 18.9.2013:

Supplementary Report

"1. x x x x

2. x x x x

3. Aeronautical Study as provided in Cl.5 - Ann.II of the Notification No.S.O.84(E) dated 14.1.2010 read with Cl.4.2.20 and 4.2.21 of Annex 14 of ICAO, is the only method to ascertain if (and to what extent) the height of a building could adversely affect aircraft operations. The Aeronautical Study is done 294

by taking into consideration procedures and other information published in the Aeronautical Information Publication of India. Presently in India, only the Airport Authority of India has the expertise to carry out the Aeronautical Study to determine whether and to what extent an existing structure above the prescribed level, could adversely affect the aircraft operations.

II Mr. H.S. Khola, Ex. Director General of Civil Aviation (DGCA) on 20th September, 2013 with regard to aeronautical study by AAI dated 20th September, 2013 has opined that Annexure-IIIC of the Notification SO 84(E) dated 14th January, 2010 issued by the Ministry of Civil Aviation clearly indicates the list of Civil and Defence Aerodromes which includes Bengaluru (HAL) Aerodrome at Sr.No.5. With regard to the method to ascertain if an object would adversely affect safety of aircraft operations, it is pertinent to refer to provisions of paragraph numbers 4.2.20 and 4.2.21 of ICAO Annex 14.

Annex 14 provides that the aeronautical study is method to determine the effect of an object on safety or regularity of 295

operations and the Airports Authority of India and ICAO are the competent agencies for conducting aeronautical studies.

III Mr. Rajkumar, Joint General Manager (ATM-NOC) of AAI;

IV Mr. Pan Singh, General Manager (CNS-COM);

and

V Mr. L.Mohanty, Joint General Manager (ATM-IAL) who carried out aeronautical study as Officers of AAI have come to the conclusion as under:

9. Conclusions:

a) The existing structure, for requested top elevation 954.41mtr AMSL, penetrates the Inner Horizontal surface of Bangalore airport by margin of 21.23 M which exceeds the permissible height of 45M by 47.17%.

b) The desired height of 954.41m AMSL is within the maximum allowable 296

penetration of OLS as per the Aeronautical Study guidelines.

c) The Safety impact of the existing structure due to the degraded aircraft performance operations is not in the scope of this study.

d) The existing structure of 954.41m AMSL will not affect adversely the safety and regularity of aircraft from PANS-OPS criteria.

e) The existing structure of 954.41m AMSL will not adversely affect the performance of the CNS equipment.

f) Airport Operator should ensure that the applicant/owner/builder carry out marking and lighting of the structure as per the DGCA CAR and the obstacle is published.

VI Mr. V. Somasundaram, Senior Independent Expert, Former Member (ANS),AAI and

VII Mr. Satendra Singh Senior Independent Expert and Former DGCA who dealt 297

with each and every objections raised by HAL have opined as per Annexure-CL at para-3 as under:

"3. Conclusions:

The Aeronautical Study conducted by AAI pursuant to the direction of the Hon'ble High Court for the structure constructed and to be constructed by CHPL, is in accordance with the notified parameters for HAL airport and the notifications issued under Section 9A of the Aircraft Act, 1934 [i.e., S.O.84(E) dated 14.1.2010 and G.S.R.751 dated 30.9.2015 which has superseded S.O.84(E)].

The Aeronautical Study conducted by AAI has concluded that the structure height fo 954.41 mtrs. AMSL is permissible and would not adversely affect aircraft operations.

In our opinion, the objections raised by HAL would not affect the 298

outcome of the Aeronautical Study Report of AAI.

127. The International standards and

recommended practices governing the operation of

Aircraft are issued under Section 9A (2)(b) of the

Act. Annex-14 to the Convention on International

Civil Aviation - provisions of ICAO are applicable in

respect of height around airports including

recommendation of 4.2.16 read with Table-4 read

with 4.2.20 and 4.2.21 for precision approach

runways like HAL aerodrome, as under:

"4.2.16: The heights and slopes of the surfaces shall not be greater than, and their other dimensions not less than, those specified in Table 4-1, except in the case of the horizontal section of the approach surface.

4.2.20: Recommendation:- New objects or extensions of existing objects should not be permitted above the conical surface and the inner horizontal surface except when, in the opinion of the appropriate authority, an 299

object would be shielded by an existing immovable object, or after aeronautical study it is determined that the object would not adversely affect the safety or significantly affect the regularity of operations of aeroplanes.

4.2.21: Recommendation:- Existing objects above an approach surface, a transitional surface, the conical surface and inner horizontal surface should as far as practicable be removed except when, in the opinion of the appropriate authority, an object is shielded by an existing immovable object, or after aeronautical study it is determined that the object would not adversely affect the safety or significantly affect the regularity of operations of aeroplanes."

Thus the ICAO criteria specifically provides for an

height of 45 meters in the 4 kilometers radius inner

horizontal surface and higher above that if aeronautical

study determines that the existing or new structures

will not adversely affect the aircraft operations. 300

Therefore, the ICAO criteria under the provisions of

Section 9A(1)(ii) of the Aircraft Act is mandatory. The

words under Section 9A of the Act depicts that the

Government 'shall have' in Section 9A(2)(b) indicates

ICA0 recommendations as a mandatory requirement

and consequently while publishing notifications

pursuant to Section 9A , the Government has to include

and has included all the aforesaid ICAO Annex-14

Recommendations to calculate the height or permissible

elevations in the Notification stated supra. So also in

the NOC issued by the 1st respondent HAL dated

28.10.2011 at paragraph-8 it is specifically stated that

Day and Night markings with the secondary power

supply may be provided as per ICAO standards.

128. It is relevant to state at this stage that the

affidavit dated 4.7.2015 filed by the Rajendra Sharma,

who was Head of Airport Service Centre, HAL in

W.P.No.11486/2008 (GM)(PIL) between Airport 301

Authority of India -vs- Union of India and Others

has specifically stated at paragraph-7 that "the

separation standards prescribed in ICAO (international

Civil Aviation Organisation) documents and DGCA

Guidelines are strictly adhered by HAL ATC for both

civil and military aircraft movement at all times. The

Safety measures for all the flights whether it is Defence

or Civil Flights is one and the same and the facilities

which are extended cannot be distinguished between

Civil Flights as well as Defence Flights. Therefore, the

contention raised by the learned Counsel for the 1st

respondent that ICAO is applicable only to Civil Airports

and not to Defence Airports including HAL cannot be

accepted.

129. It is an undisputed fact that Hindustan

Aeronautics Limited (HAL), which is established in the

year 1964 is engaged in design, testing, manufacture

and maintenance of aerospace/defence equipment and 302

it operated HAL Airport for commercial and defence

purposes with average 360 aircraft movements daily,

till closure of civil/commercial operations on 23.5.2008

due to BIAL starting operations. Capacity of the

airport was 30 aircraft movements/hour and the

terminal had handled 10.2 million passengers in the

year before the closure and managed 60,000 tons of

cargo during the year 2007-08. HAL airport continues

to be used for defence/general aviation purposes,

military, test, chartered & VVIP flights as is admitted

by the HAL in the affidavit filed before this Court dated

4.7.2015 in Writ Petition No.11486/2008 (GM-PIL) filed

by the Airport Authority of India Employees Union

against Union of India and others. The Central

Government issued Notification No.S.O. 1589(E) dated

30.6.2008 exercising the powers under the provisions

of Section 9A of the Aircraft Act, 1934 providing for

heights of buildings around airports. Paragraph-3 of

the said notification clearly depicts that Airport 303

Authority of India shall be responsible for issuing the

NOC on behalf of the Central Government for any

construction in respect of all civil aerodromes in India,

including the State Government aerodromes and the

private aerodromes where civil commercial flights have

been operating and listed at Annexure VII. For military

aerodromes, defence authorities shall be responsible for

issue of NOC. Defence authorities shall follow the

guidelines as specified in this notification in addition to

any other additional restriction as deemed fit for issue

of NOC. The defence aerodromes listed in Part-I of

Annexure - III. HAL Airport is listed in Part-III of

Annexure-VII as 'privately owned licensed aerodrome'.

Accordingly, AAI was responsible to issue NOC for HAL

Airport which is indicated at serial No.4 in the said

Annexure.

130. It is also not in dispute that the

Government of India, Ministry of Civil Aviation issued

notification dated 14th January 2010 in S.O. 84(E) 304

exercising the powers under the provisions of Section

9-A of the Aircraft Act and in supersession of the

Notification No.S.O. 1589(E) dated 30.6.2008, being of

the opinion that it is necessary and expedient so to do

for the safety of aircraft operations.

Clause-1 of the above notification clearly depicts

that no building or structure shall be constructed or

erected and no tree shall be planted on any land within

the limits specified in Annexure I and II from Civil and

Defence Aerodromes and Aeronautical communication

stations listed in Annexure-IIIA, IIIB, IIIC, IIID and IIIE

without obtaining 'No Objection Certificate'.

Clause-2 of the above notification clearly depicts

that for defence aerodromes, defence authorities shall

be responsible for issuing NOC in accordance with this

notification and subject to any other restriction or

condition which such authorities deemed fit for issuing

the NOC. It is also not in dispute that the 1st 305

respondent has accepted the site elevation certificate of

precision Surveys Private Limited for issuing NOCs

(about 36 NOCs. are issued as per Annexure-BQ).

List of defence aerodromes are listed in Annexure-

IIIC and serial No.5 of the said annexure indicates

'Bengaluru (HAL) - Karnataka - 888 - Runway

Orientation 9/27 - Dimension - 3306 x 45". AAI

guidelines provide for applicant's responsibility for

accuracy of site location coordinates. AAI Circulars

relating to procedure for issue of NOC, mandate the

site elevation and location to be verified by the

authority.

131. As per clause 4.6 of the Air Traffic

Management Circular ('ATMC' for short) No.4/2010

dated 20.7.2010, the site shall be plotted on the grid

map/zoning map of the aerodrome and the calculations

for the permitted height made from the Annex 14 as

well as CNS criteria and thereafter, the case will be put 306

before the Committee to permit the proper examination

in which PANS-OPS criteria shall also be considered.

Clause 4.11 of the said Circular stipulates that

RED/APD may constitute a Committee at

Regional/Station Level for verification of proposed site.

Clause 4.12 of the said Circular stipulates that

Regional/Station Level NOC Committee shall be

competent to issue NOC for permissible heights, in all

cases, both within the applicable Obstacles Limitation

Surfaces (OLS) as well as beyond the limits of OLS.

As per Clause 4.7 of the ATMC Circular

No.6/2012 dated 1.8.2012, the site plotted on the grid

map/zoning map of the aerodrome or on a map of

suitably large scale and the site plotted by NOCAS (No

Objection Certificate Application System) for calculation

of the permitted height needs to be checked for

accuracy and thereafter, the case will be put before the

Committee to permit the proper examination in which

PANS-OPS criteria shall also be considered. Clause 307

4.10 of the said Circular stipulates that RED/APD may

constitute a Committee at Regional/Station Level for

verification of proposed site with respect to site

elevation and location.

As per Clause 4.7 of the ATMC Circular

No.2/2013 dated 4.1.2013, the online 'NOCAS (No

Objection Certificate Application System)' for buildings

and masts height clearances is accessible from AAI

website www.aai.aero for submission of NOC

application online. With this system, applicants will

not only be able to apply online but also will be able to

track the status of their applications. After submission

of the online application, the applicant will take the

print out of the application and forward the same to

nearest airport along with the requisite hard copies of

documents.

Clause 4.13 of the ATMC Circular No.2/2013

stipulates that the site plotted on the grid map/zoning 308

map of the aerodrome or on a map of suitably large

scale and the site plotted by NOCAS for calculation of

the permitted height needs to be checked for accuracy

and thereafter, the case will be put before the

Committee to permit the proper examination in which

PANS-OPS criteria shall also be considered. Clause

4.16 of the said Circular stipulates that RED/APD may

constitute a Committee at Regional/Station Level for

verification of proposed site with respect to site

elevation and location.

132. A careful perusal of ATMC Circulars stated

supra clearly indicate that before issuing NOC, it is

mandatory on the part of the 1st respondent that the

site plotted by NOCAS (No Objection Certificate

Application System) for calculation of the permitted

height needs to be checked for accuracy and thereafter,

the case will be put before the Committee to permit the

proper examination in which PANS-OPS criteria shall

also be considered. Admittedly, it is not the case of 309

the 1st respondent - HAL that before issuing the NOC

in the month of October 2011, it has checked the

accuracy of the permission sought for by the petitioner

in the application and granted NOC. There is no

reference in the impugned order (Annexure-AQ) relating

to 'cancellation of NOC for height clearance' that the

1st respondent has checked for accuracy and issued

NOC and thereafter the petitioner has changed. It is

only stated in the impugned order that during a

random check, the site elevations were compared with

that given in the Survey of India (SOI) maps and it was

observed that the declared elevation of 870 meters

AMSL for the site in question varies significantly i.e.,

actual elevation could be as high as 890 meters AMSL.

The cancellation order only stated that the petitioner

has not properly verified the elevation and other data

before embarking on the construction. The same

cannot be accepted. As per the guidelines and

Circulars issued by the AAI stated supra, it is mandate 310

on the part of the competent authority to verify the

location and the site elevation and other data and

check for its accuracy. The same has been admitted by

the 1st respondent by the letter dated 28.03.2013 that

"the 1st respondent-Committee did not verify the site

elevation from the co-ordinates certified by the

surveyor/BBMP by comparing with them with the site

elevation given in the survey of India maps". Therefore

on that ground alone, the impugned cancellation order

cancelling NOC issued by the 1st respondent - HAL for

height clearance of the entire building including for the

permitted height of 62 meters of the structure (i.e., 932

meters AMSL) cannot be sustained.

133. The 1st respondent though issued NOC on

28.10.2011, checked for accuracy of the site elevation

of the petitioner only on 15.9.2012 as per their advisory

letter i.e., nearly after one year. By that time, the

petitioner has constructed the building up to 17 floors 311

as alleged. It is not in dispute that the 1st respondent

for the first time issued advisory letter dated 15.9.2012

and stated that the elevation of 870 Meters differs from

the data available with the 1st respondent - HAL and

advised the petitioner to carry out re-survey of the

proposed site for the purpose of finding the elevation,

in presence of the HAL - NOC Committee within 30

days from the date of receipt of letter. The advisory

letters as per Annexures - N, O, S, U, X, AE and AH

clearly indicate that the 1st respondent requested the

petitioner to conduct re-survey of the site and submit

the report. In all the advisory letters issued by the 1st

respondent, it is not the case of the 1st respondent that

after receipt of the application from the petitioner for

construction of the building, the competent authority

has verified the location and site elevation and checked

for its accuracy before the same was placed before the

1st respondent's NOC Committee to permit the proper

examination and to issue NOC. In order to verify 312

whether the petitioner has violated the terms and

conditions of the NOC and whether the 1st respondent

has issued NOC after following the guidelines in terms

of the Circulars issued by the AAI stated supra, no

records have been placed before the Court by the 1st

respondent. The 1st respondent in the statement of

objections filed in the present writ petition has

admitted that it has issued NOC purely on the basis of

the material provided by the petitioner in respect of the

elevation of the sital area of 870 mtr AMSL and it did

not conduct any independent survey of the site of the

petitioner. In the absence of the same, the cancellation

of the NOC to the entire building including the

construction made within the permissive limit, is

erroneous and contrary to law.

134. The categorical stand taken by the 1st

respondent in the advisory letters dated 15.9.2012 to

27.7.2013 clearly depict that the 1st respondent has 313

disputed the information furnished by the petitioner

with regard to elevation of the site. It was also advised

in categorical terms by the 1st respondent in the

advisory letters directing the petitioner to expedite the

coordination process with Karnataka State Remote

Sensing Application Centre (KSRSAC), Bengaluru and

to carry out the survey of the site at the earliest. The

1st respondent-HAL also requested the Director,

KSRSAC, Bengaluru to give priority to carry out the

survey of the site mentioned and even in the impugned

cancellation order, it is specifically stated that

opportunity provided to the petitioner was not utilized

in getting re-survey done from KSRSAC and also given

an option that if the petitioner wants fresh NOC, he

was advised to apply for the same after getting survey

done by the KSRSAC or Survey of India. According to

the petitioner, he made construction within the

permissive height of 62 meters above the ground level,

so that the top of the erected structure shall not exceed 314

932 meters AMSL {870 meters (site elevation) + 62

meters (height of the structure)}. The same is disputed

by the 1st respondent and according to the 1st

respondent, the elevation of 870 meters mentioned by

the petitioner is not accurate and varies from the data

available with the 1st respondent. Therefore, in the

interest of air safety and also to have authentic survey

by the Government agency or KSRSAC, advised the

petitioner to re-survey the site to dispel the truth on

the variations noticed. In the peculiar facts and

circumstances of the present case, in the interest of

justice to both the parties, the site of the petitioner has

to be re-surveyed by the competent authority

mentioned in the advisory letters of the 1st respondent

to verify whether the petitioner has constructed the

building beyond the permissive limit, in violation of the

terms of conditions of the NOC and also to verify

whether it is established by the 1st respondent that the

data tendered by the petitioner is different from the 315

actual data and it would adversely affect the aircraft

operations. Therefore cancellation of the NOC to the

entire building including the construction made within

the permissive limit, is erroneous and contrary to law.

135. The material on record clearly depicts that

this Court by the order dated 31.7.2014 directed the

AAI to conduct aeronautical study and submit the

report. The said order passed by the learned Single

Judge is the subject matter of Writ Appeal. Though the

report submitted by the AAI is not challenged, the fact

remains that the Division Bench observed that any

report to be submitted by the AAI is subject to the

result of the present writ petition and further the re-

survey of the site has not been done during the

pendency of the writ petition either at the instance of

the petitioner or at the instance of the 1st respondent. 316

It is also not in dispute that the 1st respondent -

HAL has not challenged the interim orders passed by

this Court dated 5.11.2015 and 7.12.2015. The

operative portions of the said two orders read as under:

Order dated 5.11.2015:

In that view of the matter, and in order to elucidate and amplify the direction at paragraph 45 of the order dated 31.7.2014, it is appropriate to modify/clarify as follows:

"That the aeronautical study of Bengaluru (HAL) Aerodrome is for the purpose of ascertaining as to whether or not the building constructed or to be constructed to the height of 62 meters above the ground level of property in question in accordance with notified parameters and Annexure-B to the petition for HAL Airport would affect (safety) of the Airport operations"

317 Application is accordingly ordered.

Learned counsel for the first respondent submits that instructions would be issued to Airport Authority of India by the weekend and if so done, relist on 04.12.2015."

Order dated 7.12.2015:

Having regard to the specific stand of respondent/HAL in its statement of objections to I.A. No.2/2014 following which by the order dated 05.11.2015 directed modification of the order dated 31.7.2014, undoubtedly, the AAI is required to comply with the said order to conduct Aeronautical study of Bengaluru (HAL) Aerodrome in terms of the notified parameters, Annexure-B (S.O. 84(E), to the petition for HAL Airport to ascertain as to whether or not the boiling constructed or to be constructed above 62 meters from the ground level of petitioner's property would affect the safety of the Airport 318

operation and submit the report in any event by the 31st December 2015."

The interim orders stated supra have become final. It

is also not in dispute that the aeronautical study report

submitted before the Court clearly depicts that the

height of 954.41 meters AMSL is within the maximum

allowable penetration of OLS (of 45 meters) as per

Aeronautical Study Guidelines already stated supra.

136. Admittedly as on the date of the NOC issued

by the 1st responder on 28.10.2011, the Notification

No.SO.84E dated 14.1.2010 was in existence and the

Notification No.GSR 751(E) issued under Section 9A of

the Aircraft Act came into force on 30.9.2015 during

the pendency of the present writ petition and

Notification No.GSR 751(E) superseded the earlier

notification No.SO.84E. Admittedly the impugned

order relating to 'cancellation of NOC for height

clearance' issued on 16.8.2013 i.e., before the new 319

Notification came into force. Therefore, the NOC dated

28.10.2011 and the impugned order dated 16.8.2013

relating to cancellation of NOC, both are under the

Notification dated 14.1.2010 and the same hold good

in the facts and circumstances of the present case. A

careful reading of the pleadings and objections in the

writ petition clearly depicts that the 1st respondent has

issued cancellation of NOC Letter dated 16th August,

2013 as per Annexure-AQ mainly on the ground that

the petitioner has constructed the building

unauthorisedly in violation of the conditions of NOC

dated 28th October, 2011 permitted by the HAL for

construction of the building (Coord:Latitutde 'N12˚

55'38.28") Langitude (077˚ 37'55.74") to height 62

meters. (Sixty Two Meters only) ABOVE GROUND

LEVEL, so that the top of the proposed structure, when

erected shall not exceed 870 meters (Site elevation) +

62 meters (Height of the structure) i.e., 932 meters.

AMSL (above mean sea level). According to the 1st 320

respondent, the data furnished by the petitioner at the

time of filing the application i.e., 870 meters vastly

differs from the data available with the 1st respondent.

The said communication was made by the 1st

respondent only on 16th September, 2012. By that

time, the construction of the building upto 17 floors

was over as contended by the petitioner.

137. Though the learned senior counsel for the

petitioner has contended that HAL notified parameters

are on the website of the HAL and also notified

unnamed building, Jayanagar complex (height 3291

feet), public utility building (height 3291 feet and it is

on the north west of the runway and is indicated by the

dot) etc., as aerodrome obstacles and the petitioner's

building has not been notified by HAL as aerodrome

obstacle, the same cannot be accepted. Admittedly,

that is not the issue before this Court. According to

the 1st respondent, the petitioner's building is within

3.35 kilometers and whereas the notification dated 321

14.1.2010 (Annexure-B) stipulates the height

restriction for construction of any building within 4

kilometers radius from the HAL. ARP is 45 meters

from the aerodrome elevation. The petitioner cannot

claim any equity in illegality. My view is fortified by

the dictum of the Hon'ble Supreme Court in the case of

Fuljit Kaur vs. State of Punjab reported in (2010)11

SCC 455 : AIR 2010 SC 1937, wherein at paragraphs

11 and 12 it is held as under:

11. The respondent cannot claim parity with D.S. Laungia [AIR 1993 P&H 54] in view of the settled legal proposition that Article 14 of the Constitution of India does not envisage negative equality. Article 14 is not meant to perpetuate illegality or fraud.

Article 14 of the Constitution has a positive concept. Equality is a trite, which cannot be claimed in illegality and therefore, cannot be enforced by a citizen or court in a negative manner. If an illegality and irregularity has been committed in favour of an individual or a group of individuals or a 322

wrong order has been passed by a judicial forum, others cannot invoke the jurisdiction of the higher or superior court for repeating or multiplying the same irregularity or illegality or for passing a wrong order. A wrong order/decision in favour of any particular party does not entitle any other party to claim the benefits on the basis of the wrong decision. Even otherwise Article 14 cannot be stretched too far otherwise it would make function of the administration impossible. (Vide Coromandel Fertilizers Ltd. v. Union of India - AIR 1984 SC 1772] , Panchi Devi v. State of Rajasthan [(2009) 2 SCC 589 : and Shanti Sports Club v. Union of India [(2009) 15 SCC 705] .)

12. Thus, even if some other similarly situated persons have been granted some benefit inadvertently or by mistake, such order does not confer any legal right on the petitioner to get the same relief. (Vide Chandigarh Admn. v. Jagjit Singh [AIR 1995 SC 705] , Sneh Prabha v. State of U.P. [AIR 1996 SC 540] , Jalandhar Improvement Trust v. Sampuran Singh [AIR 1999 SC 1347] , State of Bihar v.

323

Kameshwar Prasad Singh [(2000) 9 SCC 94 : 2000 SCC (L&S) 845 : AIR 2000 SC 2306] , Union ofIndia v. Rakesh Kumar [(2001) 4 SCC 309 : 2001 SCC (L&S) 707 :

AIR 2001 SC 1877] , Yogesh Kumar v. Govt. of NCT, Delhi [(2003) 3 SCC 548 :

2003 SCC (L&S) 346 : AIR 2003 SC 1241] , Union of India v. International Trading Co. [(2003) 5 SCC 437 : AIR 2003 SC 3983] , Anand Buttons Ltd. v. State of Haryana [(2005) 9 SCC 164 : AIR 2005 SC 565] , K.K. Bhalla v. State of M.P. [(2006) 3 SCC 581 : AIR 2006 SC 898] and Krishan Bhatt v. State of J&K [(2008) 9 SCC 24 : (2008) 2 SCC (L&S) 783] .)

138. It is well settled by now that a person

cannot invoke Article-14 to claim a benefit extended to

someone similarly placed, if he is not lawfully entitled

to such benefit in the first instance. Article 14

embodied the concept of positive equality alone and not

negative equality. That is to say, it cannot be relied

upon to perpetuate the illegality or irregularity. My

view is fortified by the dictum of the Hon'ble Supreme 324

Court in the case of Basavaraj and another vs.

Special Land Acquisition Officer, wherein at

paragraph-8 it is held as under:

"8. It is a settled legal proposition that Article 14 of the Constitution is not meant to perpetuate illegality or fraud, even by extending the wrong decisions made in other cases. The said provision does not envisage negative equality but has only a positive aspect. Thus, if some other similarly situated persons have been granted some relief/benefit inadvertently or by mistake, such an order does not confer any legal right on others to get the same relief as well. If a wrong is committed in an earlier case, it cannot be perpetuated.

Equality is a trite, which cannot be claimed in illegality and therefore, cannot be enforced by a citizen or court in a negative manner. If an illegality and irregularity has been committed in favour of an individual or a group of individuals or a wrong 325

order has been passed by a judicial forum, others cannot invoke the jurisdiction of the higher or superior court for repeating or multiplying the same irregularity or illegality or for passing a similarly wrong order. A wrong order/decision in favour of any particular party does not entitle any other party to claim benefits on the basis of the wrong decision. Even otherwise, Article 14 cannot be stretched too far for otherwise it would make functioning of administration impossible

The said proposition has been recently affirmed by the

three-Judge Bench of the Hon'ble Supreme Court in the

case of State of Odisha & another vs. Anup Kumar

Senapati & another in Civil Appeal No.7295 of 2019

dated 16.9.2019.

139. The material on record clearly depicts that

the petitioner has not challenged the conditions of NOC

including structures of the construction to be made i.e., 326

upto 932 meters Above Mean Sea Level and the

notification dated 14.01.2010 issued by the Central

Government, Annexure-B and now it cannot turn back

and seek a writ of mandamus directing the 1st

respondent to permit it to construct maximum height as

it does not adversely affect the aircraft operations as

may be determined by the aeronautical study to be

conducted by the 1st respondent based on the notified

parameters of HAL Airport on the date of issue of NOC

to be conducted by the 1st respondent through AAI or

ICAO or any authorized agency and to direct the 1st

respondent to revalidate the No Objection Certificate

dated 28.10.2011 issued by it for a further period of 5

years, after setting aside cancellation of NOC. Such a

prayer cannot be granted as the petitioner has not

challenged the conditions of NOC fixing the height of

932 meters. The only issue is whether the petitioner

has violated the conditions of NOC and has constructed

the building beyond 870 meters +62 meters i.e., 932 327

AMSL or not. Since the 1st respondent while issuing

NOC has not verified the data available with them and

NOC granted by the 1st respondent-HAL Committee

considering the documents produced by the petitioner

along with the certificate issued as per Annexure-E4

M/s. Precision Surveys (India) Pvt. Ltd. and certified by

the Dr. Ambedkar Institute of Technology as per

Annexure-E5 and after a lapse of one year, the 1st

respondent has issued number of advisories to the

petitioner including the subsequent advise dated 15th

September 2012 to conduct the resurvey of the

proposed site/building for the purpose of finding out

site elevation in the presence of HAL NOC Committee.

As the petitioner has not taken any steps, NOC came to

be cancelled including the permissible construction and

a direction was issued to the petitioner to apply afresh

for the NOC after getting the resurvey done by the

competent authority.

328

140. It is also not in dispute that the first

respondent issued NOC dated 28.10.2011 to put up

construction of building to a height of 932 mtrs AMSL

i.e., 62 mtrs AMSL building above 870 mtrs AMSL the

elevation of the land in question, subject to the following

conditions:

(i) If it is established that the data furnished by the petitioner is actually different and which could adversely affect the aircraft operation, such part of the structure will have to be demolished at the cost of the petitioner, as may be directed by the HAL.

(ii) Petitioner is advised to verify the said data before construction of the building, and

(iii) NOC Issued subject to the provisions of Section 9A of the Aircraft Act, 1934 and the notification issued thereunder.

329 A careful reading of the said conditions makes it clear

that, it is the duty of the 1st respondent to verify the

data furnished by the petitioner over the accurate

elevation of the land in question when NOC issued. The

duty incumbent on 1st respondent has not been

discharged and for the first time, the 1st respondent

issued Annexure-N dated 15.09.2012, approximately

after 11 months from the date of issue of NOC stating

that the data furnished by the petitioner "vastly differs"

from the data available with it. The contents of the

letter dated 15.09.2012 does not disclose the details of

variation, its extent and the basis for such conclusions,

or the data available with the first respondent as on the

date of issue of NOC. In the statement of objections too,

nothing is forthcoming over specification of the

allegation of vast difference in data. Had the details of

the variation in data made available, it would have

obviated re-survey of the 'land in question'. Therefore,

prima-facie, there was no material with the first 330

respondent to support the plea that the data placed by

the petitioner was "established" to be different. Of

course, the sentence in the NOC, "if however at any

stage it is established that the said data as tendered by

the said applicant is actually different from the one

tendered", makes no sense, nevertheless, it ought to be

understood as data placed by the petitioner is

established to be different at a later date. The use of the

word "established" assumes importance, since, that is

the requirement in relation to violation of condition of

NOC. "Established" in common parlance means to

show to be valid or true; proof to establish the fact of

the matter. Therefore, a duty was cast upon the first

respondent to prove that the data made available by the

petitioner was established to be different, at a later date.

The first respondent was liable to make available all

material facts and appraise of the said discovery that

the data furnished by the petitioner was, in fact,

incorrect by showing the actual difference. But, the 331

letter issued by the 1st respondent, stated supra, does

not disclose the material particulars, relevant facts and

actual difference. Admittedly, the 1st respondent, either

before issue of NOC or at any time after issue of NOC

verified the data furnished by the petitioner over the

elevation of the 'land in question'. Since the said letter

advised the petitioner to have re-survey conducted to

find out the elevation in the presence of HAL NOC

Committee. The same was rebutted by the petitioner by

reply dated 15.03.2013 stating that in the meeting with

the 1st respondent and its committee, it was indicated

that the probable difference could be in the range of 15

to 20 mtrs AMSL. By conjoint reading of the word used

"established" and "over the data which could adversely

affect aircraft operation" stands violated if the data

made available by the petitioner is established to vastly

differ at a later date, and which data, adversely affects

aircraft operations. Both the conditions ought to be

fulfilled in order to establish violation of condition No.(i) 332

of the NOC. Merely because it is alleged that there is a

vast difference in data by itself does not amount to

breach of condition No.(i), but must be accompanied

with 'established' difference in the data which would

adversely affect aircraft operations supported by

material documents. In the absence of established

material which depicts vast difference at a later date, in

the data filed by the petitioner at the time of application

for issue of NOC in relation to the elevation of the 'land

in question' and the height of the building to be

constructed thereon, to adversely affect aircraft

operation, prima-facie, condition No.(i) is not shown to

be violated. If the 1st respondent-HAL NOC Committee

had the data with it as on the date of issue of NOC, it is

not known as to what prevented it from verifying the

said data with reference to the data furnished by the

petitioner or alternatively secure a separate survey of

the 'land in question' in the presence of petitioner and

the committee of the 1st respondent. The fact remains 333

that, on the date of issue of NOC, 1st respondent did not

have data of the elevation of the 'land in question'

indicating that the data made available by the petitioner

in that regard did vastly differ and which could

adversely affect aircraft operations.

141. In exercise of powers under Section 9A of

the Aircraft Act, 1934, the Government of India issued

notification dated 14.01.2010, Annexure-B. The list of

defence aerodromes is provided in Annexure-IIIC of the

said notification, whereunder, Bengaluru (HAL) Airport

is at Sl.No.5 specifying its latitude and longitude, in

degrees, the elevation as 888 meters, the runway

orientation as 09/27 while its dimension as 3306 x 45

meters, owned by the 1st respondent. Clause 2(b) of the

notification dated 14.01.2010, depicts that, 'for defence

aerodromes, defence authorities shall be responsible for

issuing NOC in accordance with this notification and

subject to any other restriction or condition which such 334

authorities deemed fit for issuing the NOC." Clause 3

depicts that, "no building or structure higher than the

height specified in Annexure I and II shall be

constructed or erected and no tree which is likely to

grow or ordinarily grows higher than the height

specified in the said Annexure I and II shall be planted

on any land within a radius of twenty kilometers from

the aerodrome reference point". Clause 7 depicts that,

"each aerodrome operator shall be responsible for

preparing zoning maps in conformity with the provisions

of this notification with digitized data in WGS84

Coordinates indicating all the latest features around the

airport."

In the light of various criteria to be reckoned for fixing

the minimum and maximum height of the building, the

1st respondent failed to place the actual calculation

based upon which 45 mtrs AMSL, was arrived at, and

the petitioner made out a prima-facie case that here was 335

no material for the 1st respondent to establish vast

difference" in the data furnished by the petitioner over

elevation of land in question which would adversely

affect aircraft operation and in the absence of material

to establish the maximum height of the building to be

45 mtrs AMSL above 870 mtrs AMSL, it is a fit case to

resurvey the site property in dispute by the competent

authority in the interest of the parties to the lis.

142. The definition of the term 'aerodrome' stated

supra does not make distinction between a civil and

defence aerodrome, while Annexure IIIC of the

notification, provides for a list of defence aerodromes

whereunder Bengaluru (HAL) Aerodrome owned by the

1st respondent is mentioned at Sl.No.5. It may be that

the defence aerodrome is put to use for testing aircraft

for defence of the Country, but the Bengaluru (HAL)

Aerodrome is also used as a civil aerodrome since it

allows operation of aircrafts, both domestic and private. 336

In calculating the maximum permissible height for issue

of NOC, no distinction is made based upon whether the

aerodrome is either civil or defence or put to use for

operation of civil and defence aircrafts. Therefore, the

contention of the learned Senior counsel for the first

respondent that the defence aerodrome is not same as a

civil aerodrome under the Aircraft Act, 1934, is

unacceptable.

143. Learned Senior Counsel for the 1st

respondent mainly relied upon the conditions of the

NOC dated 28.10.2011, Annexure-A, contending that

the petitioner has constructed the building in violation

of the conditions of NOC. Therefore, the 1st respondent,

after issuing several advice letters dated 15.09.2012,

19.02.2013, 12.04.2013, 27.04.2013, 20.05.2013,

21.06.2013, 02.07.2013 and 27.07.2013, issued the

Cancellation of NOC for height clearance dated

16.08.2013. But, the 1st respondent-HAL cannot take 337

advantage of portion of the letter i.e., NOC and ignore

condition No.3, i.e., "if, however, at any stage it is

established that the said data as tendered by the said

applicant is actually different from one tendered and

which could adversely affect aircraft operations, the

structure of part(s) thereof in respect of which this No

Objection Certificate is being issued will have to be

demolished at his own cost as may be directed by HAL

Airport, Bangalore". Admittedly, the 1st respondent has

not produced any material evidence on record to prove

the vast difference in the data furnished by the

petitioner. Therefore, the 1st respondent cannot take

advantage of a portion of the document in his favour

and reject the rest of the document against it.

X. Judgments relied upon

144. My view is fortified by the dictum of the

Hon'ble Supreme Court in the case of Shyam Telelink

Limited, now Sistema Shyam Teleservices Limited 338

vs. Union of India reported in (2010)10 SCC 165,

paragraphs 23, 25 and 26, which reads as under:

"23. The maxim qui approbat non reprobat (one who approbates cannot reprobate) is firmly embodied in English common law and often applied by courts in this country. It is akin to the doctrine of benefits and burdens which at its most basic level provides that a person taking advantage under an instrument which both grants a benefit and imposes a burden cannot take the former without complying with the latter. A person cannot approbate and reprobate or accept and reject the same instrument.

25. The view taken in the above decision has been reiterated by this Court in City Montessori School v. State of U.P. [(2009) 14 SCC 253] To the same effect is the decision of this Court in New Bihar Biri Leaves Co. v. State of Bihar [(1981) 1 SCC 537] where this Court said: (New Bihar 339

case [(1981) 1 SCC 537] , SCC p. 558, para

48)

"48. It is a fundamental principle of general application that if a person of his own accord, accepts a contract on certain terms and works out the contract, he cannot be allowed to adhere to and abide by some of the terms of the contract which proved advantageous to him and repudiate the other terms of the same contract which might be disadvantageous to him. The maxim is qui approbate non reprobate (one who approbates cannot reprobate). This principle, though originally borrowed from Scots law, is now firmly embodied in English common law. According to it, a party to an instrument or transaction cannot take advantage of one part of a document or transaction and 340

reject the rest. That is to say, no party can accept and reject the same instrument or transaction (per Scrutton, L.J., Verschures Creameries Ltd. v. Hull & Netherlands Steamship Co. Ltd.

[(1921) 2 KB 608 : 1921 All ER Rep 215 (CA)] ; ...)."

26. The decision of this Court in R.N. Gosain v. Yashpal Dhir [(1992) 4 SCC 683 :

AIR 1993 SC 352] brings in the doctrine of election in support of the very same conclusion in the following words: (SCC pp. 687-88, para 10)

"10. Law does not permit a person to both approbate and reprobate.

This principle is based on the doctrine of election which postulates that no party can accept and reject the same instrument and that:

341

'... A person cannot say at one time that a transaction is valid and thereby obtain some advantage, to which he could only be entitled on the footing that it is valid, and then turn round and say it is void for the purpose of securing some other advantage.'

(See Verschures Creameries Ltd.

v. Hull and Netherlands Steamship Co. Ltd. [(1921) 2 KB 608 : 1921 All ER Rep 215 (CA)] KB at p. 612, Scrutton, L.J.) According to Halsbury's Laws of England, 4th Edn., Vol. 16:

"1508. Examples of the common law principle of election.--After taking an advantage under an order (for example for the payment of costs) a party may be precluded from saying that it is invalid and asking to set it aside.' "

342 145. The 1st respondent has alleged that the

petitioner has furnished incorrect particulars while

applying for NOC and thereby, played fraud on the 1st

respondent and constructed building in violation of the

conditions of the NOC and the provisions of Section 9A

of the Aircraft Act, 1934. But, there is no plea in the

statement of objections nor produced any material

documents before the Court to prove the same. In the

absence of the same, the contention of the learned

Senior Counsel for the 1st respondent cannot be

accepted, in view of the dictum of the Division of this

Court in the case of M/s National Technological

Institutions (NTI) Housing Co-operative Society Ltd.,

and others vs. The Principal Secretary to the

Government of Karnataka, Revenue Department

and others reported in ILR 2012 KAR 3431,

paragraphs 28 and 29 reads as under:

343

"28. In fact the judgments of the Supreme Court in (1) H.M.T.'s case (2) Bangalore City Co-Operative Housing Society's case and (3) Vyalikaval's case, are not only precedents for the law laid down

therein but is also a classic example of how the judgments are to be delivered in writ jurisdiction, when fraud is alleged. Those judgments show the importance the Apex Court has given to the pleadings and the pains they have taken in carefully scrutinizing every piece of material placed before them and thereafter extracting the relevant portions of the documents in the judgments and on appreciation of the same, recording a factual finding. This is necessary because, when the allegation of fraud is disputed, in writ jurisdiction, generally no trial is conducted, evidence recorded and there is no opportunity to cross examine. The entire finding on fraud is to be based on the contents of documents, the 344

pleadings and any admissions in the pleadings and in the documents. This exercise undertaken by the Apex Court is worth emulating. In this background, the impugned judgment rendered by the Learned Single Judge do not pass the test prescribed by the Apex Court.

FRAUD

29. Fraud avoids all Judicial acts, ecclesiastical or temporal. Fraud is a conduct either by letter or words, which induces the other person or authority to take a definite determinative stand as a response to conduct of the former either by words or letter. It is not enough to use such general words as fraud, deceit or machinations. The rule is, pleadings have to be concise and they must also be precise, but the exception to the said rule is, where fraud is charged against the opposite party, it is plain and basic rule of pleadings that in order to make out a case of fraud, there must be:

345 (a) an express allegation of fraud.

(b) all material facts in support of the allegations must be laid down in full and with a high degree of precision.

It is an acknowledged rule of pleading. The object of the rule is that in order to have a fair trial, it is imperative that the party should state the essential material facts, so that the other party shall not be taken by surprise. When a person seeks relief on the ground of fraud, but no particulars of fraud are given in the pleading, the Court may allow him to amend the pleadings or they may reject the pleading. Hence, general allegations however strongly worded are insufficient to amount to a plea of fraud of which any Court ought to take notice. The plea of fraud is to be pleaded specifically and substantially proved by the party pleading fraud. A litigant who pleads fraud or other improper conduct should not be allowed to proceed with his case unless he places on record the precise particulars as to the 346

charges, even if no objection is taken on behalf of the parties who are interested in disproving the charges. The fraud is purely a question of fact. How the plea of fraud is to be pleaded is clearly set-out in Order 6 Rule 4 of Code of Civil Procedure. The Writ Rules make the provision of Code of Civil Procedure applicable to Writ Proceedings also. Fraud is a question of fact. Normally a trial is required to prove the same.

Normally recording of evidence is not undertaken in Writ Proceedings. It is not un-common that the Writ Courts do entertain plea of fraud and record finding on the basis of the materials produced before them. But the pleading of fraud whether it is a Civil Proceedings or Writ Proceedings is the same. In fact, in a Writ Proceedings, as normally evidence is not recorded, it is very much necessary the material particulars constituting fraud should be elaborately set-out, so that the other party has an opportunity to meet the case. However, elaborately the plea of fraud is pleaded, it is no substitute to 347

evidence. A plea of fraud is to be supported by documentary evidence in Writ Proceedings. Therefore, in a Writ Proceedings, the Court has to look into the pleadings, the defence of the opposite party and the documents which are produced before it to find out the case of fraud pleaded is made out or not. It is only when Court is convinced that the case of fraud is substantiated by documentary evidence produced along with the writ petitions, may be coupled with some admissions, the Court can record a factual finding of fraud, as a question of fact. Therefore it is necessary, if the Writ Court is going into the question of fact, the judgment should set-out a plea of fraud taken from the pleadings of the parties, then the documents which are produced in support of the plea of fraud is looked into to find out whether the plea of fraud is made out and then record a factual finding. It is only thereafter applying any law to the said facts would arise. If this exercise is not done by the Writ Court and 348

finding of fraud is recorded without setting out the plea of fraud in its order, without referring to the documentary evidence to substantiate the fraud, it would be patently illegal. A factual finding of fraud cannot be recorded on the basis of a finding in a report, which is produced in support of the plea. That report may be a piece of evidence on the basis of which the Court can record a finding. But a finding in a report by itself is not sufficient to hold the case of fraud pleaded by the party is established. Once fraud is proved, it vitiates judgments, contracts and all transaction whatsoever as fraud unravels everything."

146. In identical circumstances, the Hon'ble

Supreme Court, in the case of Bishundeo Narain and

another vs. Seogeni Rai and Jagernath reported in

AIR 1951 SC 280 paragraphs 27 and 28, held as

under:

349

"27. We turn next to the questions of undue influence and coercion. Now it is to be observed that these have not been separately pleaded. It is true they may overlap in part in some cases but they are separate and separable categories in law and must be separately pleaded.

28. It is also to be observed that no proper particulars have been furnished. Now if there is one rule which is better established than any other, it is that in cases of fraud, undue influence and coercion, the parties pleading it must set forth full particulars and the case can only be decided on the particulars as laid. There can be no departure from them in evidence. General allegations are insufficient even to amount to an averment of fraud of which any court ought to take notice however strong the language in which they are couched may be, and the same applies to undue influence and coercion. See Order 6 Rule 4 of the Civil Procedure Code."

350 147. The same view was taken by the Hon'ble

Supreme Court in the case of Svenska Handelsbanken

vs. Ms/ Indian Charge Chrome and others reported in

(1994)1 SCC 502, paragraphs 41, 42 and 87 reads as

under:

"41. Again it appears that the High Court found a strong prima facie case against defendant 4 merely on reading the plaint. Pleadings make only allegations or averments of facts. Mere pleadings do not make a strong case of prima facie fraud. The material and evidence has to show it. No material whatsoever is referred to by the High Court.

42. In A.L.N. Narayanan Chettyar v.

Official Assignee, High Court Rangoon [AIR 1941 PC 93 : 196 IC 404 : 1941 OWN 1392] the Privy Council held that:

"Fraud like any other charge of a criminal offence whether made in civil or 351

criminal proceedings, must be established beyond reasonable doubt. A finding as to fraud cannot be based on suspicion and conjecture."

87. The High Court was not right in working on mere suspicion of fraud or merely going by the allegations in the plaint without prima facie case of fraud being spelt out from the material on record."

148. The 1st respondent-HAL NOC Committee,

while accepting the application and the documents

furnished by the petitioner for issue of NOC, ought to

have verified the application and documents and

inspected the site and the data furnished by the

petitioner. But, no material is placed before the Court

to establish that the 1st respondent has verified the data

furnished along with data available with the 1st

respondent, with due diligence and prudently. Later,

after one year, the 1st respondent issued letter dated 352

15.09.2012 stating that the elevation submitted by the

petitioner 870 mtrs AMSL vastly differs from the data

available with the 1st respondent. The same cannot be

accepted, in view of the law of estoppel, as the 1st

respondent is an authority of the Central Government

ought to have acted as a public trustee. Every public

office is a trustee of the society and in all facets of

public administration, every public servant/office has to

exhibit honesty, integrity, sincerity and faithfulness in

implementation of the political, social, economic and

constitutional policies to integrate the nation, to achieve

excellence and efficiency in the public administration. A

public servant/office entrusted with duty and power to

implement constitutional policy under Articles 14, 21

and 300A and all inter-related directive principles of

state policy under the Constitution, should exhibit

transparency in implementation and of accountable for

due effectuation of constitutional goals. Therefore, the

contention of the learned Senior counsel for the 1st 353

respondent cannot be accepted. My view is fortified by

the dictum of the Division Bench of the Allahabad High

Court in the case of Muhammad Shafi and others vs.

Muhammad Said and another and Bhawani Prasad

reported in ILR 1929 ALL 248, wherein, it has been

held that, "where truth is accessible to a party, the plea

of estoppel upon representation tails. If the defendant

behaved diligently and prudently and pushed their

enquiries further afield, it would have been impossible

for them not to know the truth legal position.

149. The Division Bench of the Allahabad High

Court, in the case of Lachman Singh vs. Collector of

Moradabad and another reported in AIR 1933 ALL

641, at paragraph 4, held as under:

"4. The contesting defendant resisted the suit inter alia on the ground that the plaintiff-appellant was estopped from denying the title of the defendant to the property recorded in the name of Nawal Kunwar and purchased by the 354

predecessor-in-title of the defendant. This contention was overruled by the trial Court, but found favour with the lower appellate Court with the result that the lower appellate Court dismissed the plaintiff's claim for redemption with respect to the share recorded in the name of Nawal Kunwar. In second appeal before us it is argued that as the mortgagee auction-purchaser knew, or at any rate had the means of knowing, that Nawal Kunwar had no interest in the share recorded in her name and that share belonged to Gulab Singh and Baldeo Singh, the principle of estoppel has no application to the case. It is urged that by purchasing the share that was recorded in the name of Nawal Kunwar the mortgagee could not acquire the equity of redemption in that share and, accordingly, the lower appellate Court was wrong in dismissing the plaintiff's suit with respect to that share. We agree with the learned counsel for the appellant that the facts of the present case did not 355

invite the application of the doctrine of estoppel. It has been found by the Courts below that the entire Patti Debi Singh was owned by Baldeo Singh and Gulab Singh and that Nawal Kunwar had no right or interest in the same. It is further manifest that the fact as to who were the owners of Patti Debi Singh was known to the mortgagee or in any case could have been known to him by the exercise of ordinary diligence. It cannot therefore be said, that the mortgagee was, in any way, by the act, omission or declaration of Gulab Singh or Baldeo Singh, misled into the belief that Nawal Kunwar had a proprietary interest in the share recorded in her name. This being so, the plea of estoppel, in our judgment, was without substance and was rightly overruled by the trial Court."

150. It is also not in dispute that during

pendency of the present writ petition, in view of the

controversy between the parties, the petitioner 356

approached the experts in the filed about the

conducting of aeronautical study, who gave their

opinion As stated supra. The aeronautical study was

conducted by AAI in pursuance of the directions issued

by this Court, and the report depicts that construction

made by the petitioner is in accordance with the notified

parameters for HAL Airport and notification issued

under Section 9A of the Aircraft Act, 1934 i.e., S.O 84(E)

dated 14.01.2010 and notification dated 30.09.2015 in

GSR 751(E), which superseded S.O. 84(E) has to be

verified only after conducting resurvey of the site

property in dispute. The opinion expressed by the

experts and report submitted by the AAI without the

consent of the 1st respondent cannot be relied upon by

this Court at this stage, as the order passed by the

learned single Judge appointing AAI has not been

interfered by the Division Bench of this Court and held

that the report of the AAI is always subject to the result

of the present writ petition.

357

151. It is relevant to state at this stage that the

Division Bench of the Bombay High Court, in the case of

Yeshwanth Shenoy vs. The Union of India and

others in PIL No.86/2014 dated 01.09.2016, has

held that before granting NOC by the competent

authority, care should be taken to see that the height is

properly calculated and mean seal level is fixed, and at

paragraph-5 has held that, "we are informed by the

learned ASG appearing on behalf of the AAI that in fact

discretion is not being exercised for the purpose of

relaxing the height restrictions. We also direct the

Municipal Corporation and other planning authorities to

again calculate the height and ensure that height is

calculated from the mean sea level and only thereafter

occupation certificate may be granted. Care should be

taken that even any objection protruding above the

height restrictions, such as antenna, pole, etc., also

may be demolished and should not be allowed to violate 358

the height restriction. If the Corporation does not

possess such a special equipment, which is required for

the purpose of calculating the height from the mean

seal level, it should either purchase these special

equipments or outsource it or approach MIAL for the

purpose of carrying out the exercise and measuring the

height.

152. In view of the controversy between the

parties with regard to data furnished by the petitioner

and the construction made by the petitioner in violation

of the NOC as alleged by the 1st respondent, it has to be

thrashed out by re-survey by competent authority, in

order to dissolve the controversy between the parties,

permanently. Though the learned counsel for the

petitioner relied upon several judgments to the effect

that the Court should slow in interfering with the

opinion of the experts, they are not relevant at this

stage, as already stated supra the opinion expressed by 359

the experts who are not appointed at the instance of

both the parties. The main dispute between the

petitioner and the 1st respondent in the present case is

that, according to the petitioner, the petitioner has

constructed the building strictly in terms of the

conditions of the NOC issued as per Annexure-A dated

28.10.2011, and according to the 1st respondent, the

petitioner has constructed the building in violation of

the conditions of the NOC as well as the notification

dated 14.01.2010 issued as per Annexure-B and the

data furnished by the petitioner at the time of applying

for NOC, which vastly differs from the data available

with the 1st respondent.

153. This Court, while considering the rival

contentions of the learned Counsel for the parties, is of

the considered opinion that, before issuing NOC, the 1st

respondent did not verify the application, documents

and data furnished by the petitioner, with the data 360

available with the 1st respondent. Annexure-N dated

15.09.2012 was issued only after lapse of nearly one

year, holding that, the data furnished by the petitioner

vastly differs from the data available with the 1st

respondent and further advised the petitioner to carry

out resurvey of the proposed site for the purpose of

finding elevation in the presence of HAL NOC Committee

within 30 days from the date of receipt of the said letter

and also issued several advices to that effect. In view of

the aforesaid circumstances, in order to dissolve the

dispute between the parties, this Court has a wide

power to appoint a Commissioner for not only

enforcement of fundamental right, but also for

enforcement of legal right and the report of the

Commissioner has evidentiary value, as held by the

Hon'ble Supreme Court in the case of Bandhua Mukti

Morcha vs. Union of India and others reported in

(1984)3 SCC 161, para 15, reads as under: 361

"15. We may point out that what we have said above in regard to the exercise of jurisdiction by the Supreme Court under Article 32 must apply equally in relation to the exercise of jurisdiction by the High Courts under Article 226, for the latter jurisdiction is also a new constitutional jurisdiction and it is conferred in the same wide terms as the jurisdiction under Article 32 and the same powers can and must therefore be exercised by the High Courts while exercising jurisdiction under Article 226. In fact, the jurisdiction of the High Courts under Article 226 is much wider, because the High Courts are required to exercise this jurisdiction not only for enforcement of a fundamental right but also for enforcement of any legal right and there are many rights conferred on the poor and the disadvantaged which are the creation of statute and they need to be enforced as urgently and vigorously as fundamental rights."

362 154. It is also not in dispute that the respondent

Nos.2, 3, 11 to 74 are the alleged buyers of the flats/

apartments from the petitioner. According to the said

respondents, possession of the flats was not at all

delivered to them, because of non completion of the

construction. The 1st respondent-HAL has not issued

any public notice about the illegal construction made by

the petitioner and cancelled the NOC in its entirety. It

amounts to giving room for demolition of the entire

building, thereby the prospective buyers who are

innocent, cannot be made victimized in the hands of the

petitioner and 1st respondent. Admittedly, in the

present case, the 1st respondent has not produced any

material documents to notify the general public about

the illegal construction made by the petitioner and

only advisories were issued to the petitioner about

furnishing of wrong data by the petitioner at the time of

application for NOC and cancellation of NOC was issued 363

only after one year. By that time, according to the

petitioner, the construction was completed upto 17th

floors, different wings as already stated supra.

155. While considering the provisions of Article

14 and 300A of the Constitution of India, the Hon'ble

Supreme Court, in the case of Godrej & Boyce

Manufacturing Company Limited and another vs.

State of Maharashtra and others reported in (2014)3

SCC 430, at paragraph 83, 84, 85 and 86 held as

under:

"83. Looking at the issue from the point of view of the citizen and not only from the point of view of the State or a well- meaning pressure group, it does appear that even though the basic principle is that the buyer should beware and therefore if the appellants and the purchasers of tenements or commercial establishments from the appellants ought to bear the consequences of unauthorised construction, the well-

364 settled principle of caveat emptor would be applicable in normal circumstances and not in extraordinary circumstances as these appeals present, when a citizen is effectively led up the garden path for several decades by the State itself. The present appeals do not relate to a stray or a few instances of unauthorised constructions and, therefore, fall in a class of their own. In a case such as the present, if a citizen cannot trust the State which has given statutory permissions and provided municipal facilities, whom should he or she trust?

84. Assuming the disputed land was a private forest, the State remained completely inactive when construction was going on over acres and acres of land and of a very large number of buildings thereon and for a few decades. The State permitted the construction through the development plans and by granting exemption under 365

the Urban Land (Ceiling and Regulation) Act, 1976 and providing necessary infrastructure such as roads and sanitation on the disputed land and the surrounding area. When such a large- scale activity involving the State is being carried on over vast stretches of land exceeding a hundred acres, it is natural for a reasonable citizen to assume that whatever actions are being taken are in accordance with law otherwise the State would certainly step in to prevent such a massive and prolonged breach of the law. The silence of the State in all the appeals before us led the appellants and a large number of citizens to believe that there was no patent illegality in the constructions on the disputed land nor was there any legal risk in investing on the disputed land. Under these circumstances, for the State or Bombay Environment Action Group to contend that only the citizen must bear the consequences of the unauthorised construction may not be 366

appropriate. It is the complete inaction of the State, rather its active consent that has resulted in several citizens being placed in a precarious position where they are now told that their investment is actually in unauthorised constructions which are liable to be demolished any time even after several decades. There is no reason why these citizens should be the only victims of such a fate and the State be held not responsible for this state of affairs; nor is there any reason why under such circumstances this Court should not come to the aid of victims of the culpable failure of the State to implement and enforce the law for several decades.

85. In none of these cases is there an allegation that the State has acted arbitrarily or irrationally so as to voluntarily benefit any of the appellants. On the contrary, the facts show that the appellants followed the 367

due legal process in making the constructions that they did and all that can be said of the State is that its Rip Van Winkleism enabled the appellants to obtain valid permissions from various authorities, from time to time, to make constructions over a long duration. The appellants and individual citizens cannot be faulted or punished for that.

86. These appeals raise larger issues of good administration and governance and the State has, regrettably, come out in poor light in this regard. It is not necessary for us to say anything more on the subject except to conclude that even if the State were to succeed on the legal issues before us, there is no way, on the facts and circumstances of these appeals, that it can reasonably put the clock back and ensure that none of the persons concerned in these appeals is prejudiced in any manner whatsoever."

368 156. The Hon'ble Supreme Court, while

considering the existence of the legitimate expectation,

in the case of Navjyoti Coop. Group Housing Society

and others vs. Union of India and others reported in

(1992)4 SCC 477, at paragraph 15, held as under.

"15. It also appears to us that in any event the new policy decision as contained in the impugned memorandum of January 20, 1990 should not have been implemented without making such change in the existing criterion for allotment known to the Group Housing Societies if necessary by way of a public notice so that they might make proper representation to the concerned authorities for consideration of their viewpoints. Even assuming that in the absence of any explanation of the expression "first come first served" in Rule 6(vi) of Nazul Rules there was no statutory requirement to make allotment with reference to date of registration, it 369

has been rightly held, as a matter of fact, by the High Court that prior to the new guideline contained in the memo of January 20, 1990 the principle for allotment had always been on the basis of date of registration and not the date of approval of the list of members. In the brochure issued in 1982 by the DDA even after Gazette notification of Nazul Rules on September 26, 1981 the policy of allotment on the basis of seniority in registration was clearly indicated. In the aforesaid facts, the Group Housing Societies were entitled to 'legitimate expectation' of following consistent past practice in the matter of allotment, even though they may not have any legal right in private law to receive such treatment. The existence of 'legitimate expectation' may have a number of different consequences and one of such consequences is that the authority ought not to act to defeat the 'legitimate expectation' without some overriding reason of public policy to justify its 370

doing so. In a case of 'legitimate expectation' if the authority proposes to defeat a person's 'legitimate expectation' it should afford him an opportunity to make representations in the matter. In this connection reference may be made to the discussions on 'legitimate expectation' at page 151 of Volume 1(1) of Halsbury's Laws of England, 4th edn. (re-issue). We may also refer to a decision of the House of Lords in Council of Civil Service Unions v. Minister for the Civil Service [(1984) 3 All ER 935] . It has been held in the said decision that an aggrieved person was entitled to judicial review if he could show that a decision of the public authority affected him of some benefit or advantage which in the past he had been permitted to enjoy and which he legitimately expected to be permitted to continue to enjoy either until he was given reasons for withdrawal and the opportunity to comment on such reasons."

371 157. The State functionaries must act fairly and

reasonably, including the first respondent-HAL. While

issuing NOC and canceling the NOC, HAL ought to have

acted fairly and reasonably, as held by the Hon'ble

Supreme Court in the case of Management of M/s

M.S.Nally Bharat Engineering Co. Ltd., vs. State of

Bihar and others reported in (1990)2 SCC 48 at

paragraph 13, held as under:

"13. What is thus important in the modern administration is the fairness of procedure with elimination of element of arbitrariness. The State functionaries must act fairly and reasonably. That is, however, not the same thing to state that they must act judicially or quasi- judicially. In Keshav Mills Co. Ltd. V. Union of India Mukherjea, J. said (SCC p. 387, para 8: SCR p.30)

"The administrative authority concerned should act fairly, 372

impartially and reasonably.

When administrative officers are concerned, the duty is not so much to act judicially as to act fairly"."

158. The Hon'ble Supreme Court, while

considering as to what is natural justice, in the case of

Dev Dutt vs. Union of India and others reported in

(2008)8 SCC 725, at paragraph 24, held as under:

"24.What is natural justice? The rules of natural justice are not codified nor are they unvarying in all situations, rather they are flexible. They may, however, be summarised in one word: fairness. In other words, what they require is fairness by the authority concerned. Of course, what is fair would depend on the situation and the context."

159. It is the case of the first respondent that the

petitioner has violated the terms and conditions of NOC

and the notification issued by the Central Government 373

under the provisions of Section 9A of the Aircraft Act,

1934. The same is disputed by the petitioner and

contended that the petitioner has constructed the

building in accordance with the NOC and has not

violated the terms and conditions of the NOC. The first

respondent, in series of advisories issued and at

impugned Order Annexure-AQ/cancellation of NOC

order, at paragraph 6, specifically, has stated, as under:

6. "If you want a fresh NOC, you are advised to apply for the same after getting survey done by the Karnataka State Remote Sensing Application Centre ('KSRSAC') or Survey of India."

In view of the controversy and in view of the categorical

statement made by the 1st respondent for re-survey of

the site in dispute, if the petitioners are permitted to

conduct re-survey done by the competent authority as

observed by the 1st respondent in terms of the NOC

issued by the 1st respondent dated 28.10.2011 and in 374

terms of the notification issued under Section 9A of the

Aircraft Act, 1934, after re-survey conducted by the

competent authority, if it is found that the construction

made by the petitioner is in violation of the NOC and it

affects the aircraft operation, certainly, the illegal

portion of the construction made by the petitioner

cannot be regularized, as the specific case of the 1st

respondent is that the illegal construction would

obstruct the aircraft operation in the HAL defence

aerodrome. It is not in dispute that HAL Aerodrome is a

unique Defence Aerodrome and it is the sole premier

Aircraft, Design and Manufacturing Organisation in the

country promoting a safe test flying environment which is

critical for National Defence; Flying operations at HAL involve

test flying of experimental, unproven, developmental

Aeroplanes and Helicopters; Test flying of prototypes and pre-

production models ; Special exercises are carried out such as

"Practice Forced Landing",(PFL) which involves an

unconventional approach to land; Carrying out Single Engine

landing of a multi engine Aircraft for test purposes; Flying in 375

poor weather conditions (low visibility); Switching off engines

and re-ignition in mid-air ; and Post production Test flying.

The nature of work stated supra carried out in HAL

Aerodrome entail a high level of risk and hence, safety

margins from the obstacle on ground around the Airport

are essential. In view of the peculiar facts and

circumstances of the present case, the interest of the

nation at large prevails over the individual interest of

the petitioner. My view is fortified by the dictum of the

Hon'ble Supreme Court in the case of Esha Ekta

Apartments Cooperative Housing Society Limited

and others vs. Municipal Corporation of Mumbai

and others reported in (2013)5 SCC 357, paragraphs

4, 5 and 6, as under:

"4. The aforesaid observations found their echo in Shanti Sports Club v. Union of India in the following words:

(SCC pp.743-44, paras 74 & 75) 376

"74. In the last four decades, almost all cities, big or small, have seen unplanned growth. In the 21st century, the menace of illegal and unauthorized constructions and encroachments has acquired monstrous proportions and everyone has been paying heavy price for the same. Economically affluent people and those having support of the political and executive apparatus of the State have constructed buildings, commercial complexes, multiplexes, malls, etc. in blatant violation of the municipal and town planning laws, master plans, zonal development plans and even the sanctioned building plans. In most of the cases of illegal or unauthorized constructions, the officers of the municipal and other regulatory bodies turn blind eye either due to the influence of the higher functionaries of the State or other 377

extraneous reasons. Those who construct buildings in violation of the relevant statutory provisions, master plan, etc. and those who directly or indirectly abet such violations are totally unmindful of the grave consequences of their actions and/or omissions on the present as well as future generations of the country which will be forced to live in unplanned cities and urban areas. The people belonging to this class do not realize that constructions made in violation of the relevant laws, master plan or zonal development plan or sanctioned building plan or the building is used for a purpose other than the one specified in the relevant statute or the master plan, etc., such constructions put unbearable burden on the public facilities/amenities like water, electricity, sewerage, etc. apart from creating chaos on the roads.

378 The pollution caused due to traffic congestion affects the health of the road users. The pedestrians and people belonging to weaker sections of the society, who cannot afford the luxury of air-conditioned cars, are the worst victims of pollution.

They suffer from skin diseases of different types, asthma, allergies and even more dreaded diseases like cancer. It can only be a matter of imagination how much the Government has to spend on the treatment of such persons and also for controlling pollution and adverse impact on the environment due to traffic congestion on the roads and chaotic conditions created due to illegal and unauthorized constructions. This Court has, from time to time, taken cognizance of buildings constructed in violation of municipal and other laws and emphasized that no compromise should be made with the town 379

planning scheme and no relief should be given to the violator of the town planning scheme, etc. on the ground that he has spent substantial amount on construction of the buildings, etc...

75. Unfortunately, despite repeated judgments by this Court and the High Courts, the builders and other affluent people engaged in the construction activities, who have, over the years shown scant respect for regulatory mechanism envisaged in the municipal and other similar laws, as also the master plans, zonal development plans, sanctioned plans, etc., have received encouragement and support from the State apparatus.

As and when the courts have passed orders or the officers of local and other bodies have taken action for ensuring rigorous compliance with laws relating to 380

planned development of the cities and urban areas and issued directions for demolition of the illegal/unauthorized constructions, those in power have come forward to protect the wrongdoers either by issuing administrative orders or enacting laws for regularization of illegal and unauthorized constructions in the name of compassion and hardship. Such actions have done irreparable harm to the concept of planned development of the cities and urban areas. It is high time that the executive and political apparatus of the State take serious view of the menace of illegal and unauthorized constructions and stop their support to the lobbies of affluent class of builders and others, else even the rural areas of the country will soon witness similar chaotic conditions." 381

5. In Priyanka Estates International (P) Ltd. Vs. State of Assam this Court declined the appellant's prayer for directing the respondents to regularize the illegal construction and observed SCC p.42, para 55)

"55. It is a matter of common knowledge that illegal and unauthorized constructions beyond the sanctioned plans are on rise, may be due to paucity of land in big cities. Such activities are required to be dealt with by firm hands otherwise builders/colonizers would continue to build or construct beyond the sanctioned and approved plans and would still go scot-free. Ultimately, it is the flat owners who fall prey to such activities as the ultimate desire of a common man is to have a shelter of his own. Such unlawful constructions are 382

definitely against the public interest and hazardous to the safety of occupiers and residents of multistoreyed buildings. To some extent both parties can be said to be equally responsible for this. Still the greater loss would be of those flat owners whose flats are to be demolished as compared to the builder."

6. A somewhat similar question was recently considered in Dipak Kumar Mukherjee v. Kolkata Municipal Corpn. While setting aside the order of the Division Bench of the Calcutta High Court, this Court referred to the provisions of the Kolkata Municipal Corporation Act, 1980 in the context of construction of additional floors in a residential building in violation of the sanctioned plan and observed: (SCC p.344, para 8)

"8. What needs to be emphasized is that illegal and 383

unauthorized constructions of buildings and other structures not only violate the municipal laws and the concept of planned development of the particular area but also affect various fundamental and constitutional rights of other persons. The common man feels cheated when he finds that those making illegal and unauthorized constructions are supported by the people entrusted with the duty of preparing and executing master plan/ development plan/ zonal plan. The reports of demolition of hutments and jhuggi jhopris belonging to the poor and disadvantaged section of the society frequently appear in the print media but one seldom gets to read about demolition of illegally/ unauthorisedly constructed 384

multi-storeyed structure raised by economically affluent people. The failure of the State apparatus to take prompt action to demolish such illegal constructions has convinced the citizens that planning laws are enforced only against poor and all compromises are made by the State machinery when it is required to deal with those who have money power or unholy nexus with the power corridors.""

160. There is no dispute that the respondent

Nos.3, 11 to 13, 16 to 25, 27 to 29, 32 to 34, 36 to 38,

40 to 45, 47, 48, 54, 56 to 62, 64, 67, 69, 71, 73 and

74, claiming that they are the agreement holders to

purchase of flats from the petitioner and possession is

not yet delivered, in view of the dispute between the

petitioner and 1st respondent with regard to height of

the building. According to the petitioner, he has not 385

violated the terms and conditions of the NOC and

constructed within the permissible limit i.e., 932 m

AMSL. But according to the 1st respondent-HAL, the

petitioner has violated the terms and conditions of the

NOC and has given wrong data while filing the

application. It is also relevant that though the said

respondents are claiming that they are agreement

holders/purchasers, the fact that the buyer should

beware and ascertain that whether the construction

made by the petitioner is legal or illegal before entering

into agreements/purchase, now, the prospective buyers

cannot support the petitioner for a writ of mandamus.

My view is fortified by the dictum of the Hon'ble

Supreme Court in the case of Godrej & Boyce Mfg.Co.

Ltd. And another vs. The State of Maharashtra and

others reported in (2014)3 SCC 430, at paragraph 81,

it is held as under:

"81. Looking at the issue from point of view of the citizen and not only from the 386

point of view of the State or a well meaning pressure group, it does appear that even though the basic principle is that the buyer should beware and therefore if the appellants and purchasers of tenements or commercial establishments from the appellants ought to bear the consequences of unauthorized construction, the well- settled principle of caveat emptor would be applicable in normal circumstances and not in extraordinary circumstances as these appeals present, when a citizen is effectively led up the garden path for several decades by the State itself. The present appeals do not relate to a stray or a few instances of unauthorized constructions and, therefore, fall in a class of their own. In a case such as the present, if a citizen cannot trust the State which has given statutory permissions and provided municipal facilities, whom should he or she trust?"

(emphasis supplied) 387

161. Further, it is well settled that 'buyer must

beware' and the buyer has to establish that he had

made the enquiry and took the requisite precautions to

find out about the genuineness of the construction,

before purchasing. My view is fortified by the judgment

of the Hon'ble Supreme Court in the case of

Commissioner of Customs (Preventive) vs. Aafloat

Textiles India Private Limited and others reported in

(2009)11 SCC 18, paragraphs 13 to 16, which reads as

under:

13. It was for the buyer to establish that he had no knowledge about the genuineness or otherwise of the SIL in question. The maxim caveat emptor is clearly applicable to a case of this nature.

14. As per Advanced Law Lexicon by P. Ramanatha Aiyar, 3rd Edn., 2005 at p.

721: Caveat emptor means "let the purchaser beware". It is one of the settled maxims, applying to a purchaser who is bound by actual as well as constructive 388

knowledge of any defect in the thing purchased, which is obvious, or which might have been known by proper diligence. "Caveat emptor does not mean either in law or in Latin that the buyer must take chances. It means that the buyer must take care." (See Wallis v. Russell [(1902) 2 IR 585 (CA)] , IR p. 615.)

15. "Caveat emptor is the ordinary rule in contract. A vendor is under no duty to communicate the existence even of latent defects in his wares unless by act or implication he represents such defects not to exist." (See William R. Anson, Principles of the Law of Contract 245, Arthur L. Corbin, ed., 3d Am. Edn. 1919.) Applying the maxim, it was held that it is the bounden duty of the purchaser to make all such necessary enquiries and to ascertain all the facts relating to the property to be purchased prior to committing in any manner.

16.Caveat emptor qui ignorare non debuit quod jus alienum emit. A maxim meaning "let a purchaser beware; who ought not to be ignorant that he is purchasing the rights 389

of another". (Hob. 99; Broom; Co., Litl: 102 a: 3 Taunt. 439.) As the maxim applies, with certain specific restrictions, not only to the quality of, but also to the title to, land which is sold, the purchaser is generally bound to view the land and to enquire after and inspect the title deeds; at his peril if he does not.

162. In view of the peculiar facts and

circumstances of the present case, in order to do justice

to the parties, viz., petitioner, 1st respondent, the

prospective buyers and the general public within the

vicinity of the building, the Court should act as Parens

Patriae. My view is fortified by the dictum of the

Constitutional Bench of the Hon'ble Supreme Court in

the case of Charan Lal Sahu vs. Union of India

reported in AIR 1990 SC 1480, wherein, at paragraph-

35, it is held as under:

"35. There is the concept known both in this country and abroad, called parens patriae. Dr B.K. Mukherjea in his "Hindu 390

Law of Religious and Charitable Trust", Tagore Law Lectures, Fifth Edition, at page 404, referring to the concept of parens patriae, has noted that in English law, the Crown as parens patriae is the constitutional protector of all property subject to charitable trusts, such trusts being essentially matters of public concern. Thus the position is that according to Indian concept parens patriae doctrine recognized King as the protector of all citizens and as parent. In Budhkaran Chaukhani v. Thakur Prosad Shah [AIR 1942 Cal 331 : 46 CWN 425] the position was explained by the Calcutta High Court at page 318 of the report. The same position was reiterated by the said High Court in Banku Behary Mondal v. Banku Behary Hazra [AIR 1943 Cal 203 : 47 CWN 89] at page 205 of the report. The position was further elaborated and explained by the Madras High Court in Medai Dalavoi T. Kumaraswami Mudaliar v. Medai Dalavoi Rajammal [AIR 1957 Mad 563 : (1957) 2 391

MLJ 211] at page 567 of the report. This Court also recognized the concept of parens patriae relying on the observations of Dr Mukherjea aforesaid in Ram Saroop v. S.P. Sahi [1959 Supp 2 SCR 583 : AIR 1959 SC 951] at pages 598 and 599. In the "Words and Phrases" Permanent Edition, Vol. 33 at page 99, it is stated that parens patriae is the inherent power and authority of a legislature to provide protection to the person and property of persons non sui juris, such as minor, insane, and incompetent persons, but the words parens patriae meaning thereby 'the father of the country', were applied originally to the King and are used to designate the State referring to its sovereign power of guardinaship over persons under disability. (emphasis supplied) Parens patriae jurisdiction, it has been explained, is the right of the sovereign and imposes a duty on sovereign, in public interest, to protect persons under disability who have no 392

rightful protector. The connotation of the term parens patriae differs from country to country, for instance, in England it is the King, in America it is the people, etc. The Government is within its duty to protect and to control persons under disability. Conceptually, the parens patriae theory is the obligation of the State to protect and takes into custody the rights and the privileges of its citizens for discharging its obligations. Our Constitution makes it imperative for the State to secure to all its citizens the rights guaranteed by the Constitution and where the citizens are not in a position to assert and secure their rights, the State must come into picture and protect and fight for the rights of the citizens. The Preamble to the Constitution, read with the Directive Principles, Articles 38, 39 and 39-A enjoin the State to take up these responsibilities. It is the protective measure to which the social welfare state is committed. It is necessary for the State to ensure the fundamental rights in 393

conjunction with the Directive Principles of State Policy to effectively discharge its obligation and for this purpose, if necessary, to deprive some rights and privileges of the individual victims or their heirs to protect their rights better and secure these further. Reference may be made to Alfred L. Snapp & Son, Inc. v. Puerto Rico [73 L Ed 2d 995 : 458 US 592 : 102 SCR 3260] in this connection. There it was held by the Supreme Court of the United States of America that Commonwealth of Puerto Rico have standing to sue as parens patriae to enjoin apple growers' discrimination against Puerto Rico migrant farm workers. This case illustrates in some aspect the scope of parens patriae. The Commonwealth of Puerto Rico sued in the United States District Court for the Western District of Virginia, as parens patriae for Puerto Rican migrant farmworkers, and against Virginia apple growers, to enjoin discrimination against Puerto Ricans in favour of Jamaican 394

workers in violation of the Wagner-Peyser Act, and the Immigration and Nationality Act. The District Court dismissed the action on the ground that the Commonwealth lacked standing to sue, but the Court of Appeal for the Fourth Circuit reversed it. On certiorari, the United States Supreme Court affirmed. In the opinion by White, J., joined by Burger, C.J. and Brennan, Marshall, Blackmun, Rehnquist, Stevens, and O'Connor, JJ., it was held that Puerto Rico had a claim to represent its quasi- sovereign interests in federal court at least which was as strong as that of any State, and that it had parens patriae standing to sue to secure its residents from the harmful effects of discrimination and to obtain full and equal participation in the federal employment service scheme established pursuant to the Wagner- Peyser Act and the Immigration and Nationality Act of 1952. Justice White referred to the meaning of the expression parens patriae. According to Black's Law 395

Dictionary, 5th edn. 1979, page 10003, it means literally 'parent of the country' and refers traditionally to the role of the State as a sovereign and guardian of persons under legal disability. Justice White at page 1003 of the report emphasised that the parens patriae action had its roots in the common law concept of the "royal prerogative". The royal prerogative included the right or responsibility to take care of persons who were legally unable, on account of mental incapacity, whether it proceeds from nonage, idiocy or lunacy to take proper care of themselves and their property. This prerogative of parens patriae is inherent in the supreme power of every state, whether that power is lodged in a royal person or in the legislature and is a most beneficent function. After discussing several cases Justice White observed at page 1007 of the report that in order to maintain an action, in parens patriae, the State must articulate an interest apart from the interests of particular parties, 396

i.e. the State must be more than a nominal party. The State must express a quasi-sovereign interest. Again an instructive insight can be obtained from the observations of Justice Holmes of the American Supreme Court in the case of State of Georgia v. Tennessee Copper Co. [51 L Ed 1038 : 206 US 230 (1906) : 27 SCR 618] , which was a case involving air pollution in Georgia caused by the discharge of noxious gases from the defendant's plant in Tennesee. Justice Holmes at page 1044 of the report described the State's interest as follows:

"This is a suit by a State for an injury to it in its capacity of quasi- sovereign. In that capacity the State has an interest independent of and behind the titles of its citizens, in all the earth and air within its domain. It has the last word as to whether its mountains shall be stripped of their forests and its inhabitants shall breathe pure air. It might have 397

to pay individuals before it could utter that word, but with it remains the final power....

... When the States by their union made the forcible abatement of outside nuisances impossible to each, they did not thereby agree to submit to whatever might be done.

They did not renounce the possibility of making reasonable demands on the ground of their still remaining quasi-sovereign interests..."

163. In view of the peculiar facts and

circumstances of the present case, until re-survey of the

site property of the petitioner is made by the Survey of

India or KSRSAC, the interest of the prospective buyers

should be protected. Ultimately, after re-survey, if the

authorities find that there is no violation of the

construction made by the petitioner in terms of the NOC

i.e., 62mtrs height and 870 mtrs site elevation i.e., 932 398

m AMSL, then the question of taking any action by the

1st respondent would not arise. If, after re-survey, in

the presence of the petitioner and other interested

respondents, if the construction made is found to be in

violation of the terms and conditions of the NOC, it is

for the 1st respondent, to take action against the illegal

construction, if any, after providing opportunity to the

petitioner and affected/interested respondents/general

public and in accordance in with law. In those

circumstances, it is the duty of the petitioner to

accommodate the prospective buyers in any other flats,

if available in the construction made within 932m AMSL

and if not available, it is for the prospective buyers to

take appropriate action to recover the amount already

paid, if any, in terms of the agreement or sale deeds and

recover the same before the appropriate competent

Court of law.

399

164. Learned Counsel for respondent No.1

contended that 'what may not be done under the

provisions of the Act may not be permitted to be done by

invoking Article 226 of the Constitution of India as held

by the Hon'ble Supreme Court in the case of Santosh

Kumar -vs- Central Warehousing Corporation and

Another reported in AIR 1986 SC 1164 wherein at

paragraph-4 it is held that "there cannot be any

possible doubt that the scheme of the Act is that, apart

from fraud, corruption or collusion, the amount of

compensation awarded by the Collector under Section

11 of the Act may not be questioned in any proceedings

either by the Government or by the Company or Local

Authority at whose instance the acquisition is made.

Section 50(2) and Section 25 of the Act lead to that in

inevitable conclusion. Surely what may not be done

under the provisions of the Act may not be permitted to

be done by invoking the jurisdiction of the High Court

under Article 226. Article 226 is not meant to avoid or 400

circumvent the process of the law and the provisions of

the statute. This Court has no quarrel with the law laid

down by the Hon'ble Supreme Court. It is well settled

that what is not provided under the provisions of any

particular Act cannot be done under Article 226 of the

Constitution of India. Granting relief is prohibited by

the Act. Admittedly, in the present case, the petitioner

is seeking to quash the cancellation of NOC dated 16th

August, 2013 as per Annexure-Q mainly on the ground

that the petitioner has not violated the conditions of the

grant and not constructed illegally with the maximum

height permitted under the NOC. This Court has to

verify from the records whether the petitioner has

violated the terms and conditions of NOC and whether

the 1st respondent was justified in canceling the entire

NOC including the permissible construction granted.

Therefore, the said judgment relied upon by the learned

Counsel for the 1st respondent has no application to the

facts and circumstances of the present case. 401

165. Another judgment relied upon by the

learned Counsel for the 1st respondent in the case of the

Martin Burn Ltd., -vs- Corporation of Calcutta

reported in AIR 1966 SC 529 at paragraph-8 is to the

effect that Court has no power to ignore the provision to

relieve what it considers a distress resulting from its

operation. A statute must of course be given effect to

whether a Court likes the result or not. This Court has

no quarrel with the law laid down by the Hon'ble

Supreme Court in the facts and circumstances of the

said case, as the issue in the present case is, only

construction made by the petitioner, is in violation of

the alleged NOC or not. Therefore, the said judgment is

also not applicable to the facts and circumstances of the

present case.

166. Another judgment relied upon by the

learned Counsel for the 1st respondent in the case of

Maharashtra State Board of Secondary and Higher 402

Secondary Education and Another -vs- Paritosh

Bhupesh Kurmarsheth, etc., reported in AIR 1984

SC 1543 is to the effect that subordinate legislation

must be read to give effect to the provisions of the

statute and should not substitute its own opinion. The

said case has no application to the facts and

circumstances of the present case.

167. The other two judgments relied upon by the

learned Counsel for the 1st respondent in the case of

Madhukar Sadbha Shivarkar -vs- State of

Maharashtra & Others reported in (2015) 6 SCC

557 and in the case of T. Vijendradas and Another -

vs- M. Subramanian and Others reported in (2007)8

SCC 751 is with regard to fraud vitiates the entire

proceedings. Though in the present case, the 1st

respondent has alleged that the petitioner had played

fraud on it while filing the application giving wrong

data, the same is denied by the petitioner contending 403

that the 1st respondent after considering the entire

material on record and considering the certificates

issued by the competent authorities i.e., M/s. Precision

Surveys (India) Pvt. Ltd., and Dr. Ambedkar Institute of

Technology as per Annexures- E, E4 and E5 has come

to the conclusion that the construction to be made by

the petitioner is only in accordance with the NOC i.e.,

870 meters (site Elevation) + 62 meters (height of the

structure) i.e., 932 meters above mean sea level (AMSL)

and not violative. Therefore, the said case referred to by

the learned Counsel involves completely different facts

which require evidence including the question of correct

dates/age, whether land was held or occupied for

cultivation, concurrent decision by three statutory

authorities on the basis of the material available with

them, whether trusts were public trust or private trust,

non supply of road/breach of contact, etc. Admittedly,

the present case does not involve disputed questions of

fact or issues which cannot be decided in the writ 404

petition. The issue in the present case relates to the

arbitrary action and acts of omission and commission

by the 1st respondent relating to the height of NOC and

cancellation thereof without ascertaining the adverse

affect on the aircraft operations as alleged by the

petitioner. Therefore, the said judgments have no

relevancy to the facts and circumstances of the present

case.

168. Another judgment relied upon by the learned

Counsel for the 1st respondent is State of UP and

Others -vs- Harish Chandra and Others reported in

AIR 1996 SC 2173 at para-10 to the effect that no

mandamus can be issued to the relief sought for to the

Government to refrain from enforcing the provisions of

law or opposed to law. This Court has no quarrel with

the law laid down by the Hon'ble Supreme Court that, if

the party, who has come to the Court, has not made out

any legally enforceable right, no mandamus can be 405

issued. Therefore, the said judgment is in no way

assistance to the case of the 1st respondent.

169. The learned Counsel for the 1st respondent

relied upon the dictum of the Hon'ble Supreme Court in

the case of Mobilox Innovations Private Limited -vs-

Kirusa Software Private Limited [Civil Appeal

No.9405/2017 Decided on 21.9.2017] reported in

(2017) 11 Scale 754 (SC) with regard to paragraph-29.

Relying upon the said judgment, the learned Counsel

interpreted the word 'and' which can also be read as 'or'

having regard to the context as can be seen from para-3

of NOC dated 28.10.2011, which was governed by the

Notification and if the Notification does not provide for

separate Aeronautical Study to find out independently

whether it affects aircraft operations, no person

including NOC Authority can permit any such study as

it is prohibited by the statute. The said judgment does

not interpret height NOC or related regulations. The 406

said judgment is with regard to the legislative intent of

Section 8 (2)(a) of the Insolvency and Bankruptcy Bill,

2015 and to avoid anomalous situation or hardship if

'and' was not read as 'or'. The said judgment has no

application to the facts and circumstances of the

present case.

170. The learned Counsel further relied upon the

dictum of the Hon'ble Supreme Court in the case of New

Okhla Industrial Development Authority -vs-

Kendriya Karamchari Sahkar Grih Nirman Smiti

reported in (2006) 9 SCC 524 with regard to

paragraphs 12 to 15 to the effect that suppression of

material facts disentitles any relief and no mandamus

can be issued in respect of disputed questions of fact. It

is no doubt true that any person who suppresses the

material facts is not entitled to any relief while

exercising the power under Article 226 of the

Constitution of India and no mandamus can be issued 407

in respect of disputed question of facts. The petitioner

is seeking quashing of cancellation of NOC on the

ground that the 1st respondent cannot cancel the NOC

mainly on the ground that the data furnished by the

petitioner while submitting the application that 870

meters vastly differs from the data available with the 1st

respondent and the advisory was issued admittedly,

after a lapse of one year i.e., on 15th September 2012.

Therefore, the said judgment has no application to the

facts and circumstances of the present case.

171. The learned Counsel for the 1st respondent

also relied upon an unreported judgment of the Delhi

High Court in the case of Shristi Infrastructure

Development Corporation Limited and Others -vs-

Union of India and Others in W.P.(C) 7652/2015 &

C.M.No.14940/2015 decided on 25.4.2016 by the

learned Single Judge with regard to reduction of height

wherein the Delhi High Court considering the provisions 408

of Section 9A of the Act has held that the process after

all cannot be made an endless one, particularly when

the petitioners by illegally raising construction and

enjoying the benefit thereof are interested in making

such process of reconsideration an indefinite one. In

fact, the learned Judge tend to agree with the

contention of the Senior Counsel for respondent No.2

AAI of the petitioners therein, having illegally gone

ahead with the construction, being not entitled to any

relief. The jurisdiction of the Court under Article 226 of

the Constitution of India is an equitable jurisdiction and

it is again a settled principle of law that one who comes

in equity must have come with clean hands and a clean

conscience. The equitable jurisdiction of this Court

cannot be permitted to be abused by those indulging in

illegal and unauthorized construction in contravention

of the rules. The petitioners therein had no reason to,

notwithstanding their NOC having lapsed, go ahead

with the construction and that too construction beyond 409

the height of 88.64 meters AMSL which had been

communicated to them on 13th December, 2010. The

petitioners by their such conduct alone were disentitled

from any relief from that Court. Admittedly the said

order passed by the learned Single Judge is pending in

LPA 503/2016 before the Division Bench of Delhi High

Court. In the present case, it is the specific case of the

1st respondent that while withdrawing the NOC., it is

stated that during the random check up, the site

elevations were compared with that given in the Survey

of India (SOI) maps and it was observed that the

declared elevation of 870 meters AMSL from the above

mentioned site varies. Consequently, the actual

elevation keeps assigned as 890 meters AMSL and the

petitioner has given the application as 870 meters

which vastly differs from the data available with the

HAL-1st respondent. In the present case, it has to be

verified whether the petitioner has violated the

conditions of the NOC and has constructed the building 410

beyond 870 meters site elevation + 62 meters height of

the structure i.e., 932 meters above mean sea level as

observed in the impugned cancellation NOC after the

resurvey done by the Karnataka State Remote Sensing

Application Centre or Survey of India as desired by HAL.

Therefore, the said judgment has no application to the

facts and circumstances of the present case.

172. The learned Counsel for the 1st respondent

also relied upon the latest judgment of the Division

Bench of the Bombay High Court in the case of

Siddheshwar Sahakari Sakhar Karkhana Ltd., -vs-

Director and District Magistrate, District Solapur

and Others reported in 2018 SCC Online Bom 2239

wherein it was a case where NOC granted for 493.96

meters was restricted, but the petitioner inspite of the

communication, constructed RCC Chimney of 90 meters

height violating the NOC and in breach of Rules.

Therefore, it was held that the assertions of the 411

petitioner, who says that it will not shift its Chimney

but now a new Airport site is identified so let the Airport

shift from the existing site at Hotgi to Boramani. Even

otherwise, until then this Airport is not going to be

made functional. Thus, the regional connectivity

scheme is sought to be defeated by the petitioner and it

seems to be more influential than the respondents for it

goes on then alleging discrimination and how only VIPs

were allowed to use it or permissions were given for the

aircrafts carrying them to the land with the obstacle at

site. This is a clear case of compromise with air safety

by accommodating a wrong-doer. Accordingly, the

Division Bench of Bombay High Court rightly dismissed

the writ petition. If after resurvey, as sought for by the

1st respondent HAL is conducted by the Karnataka State

Remote Sensing Application Centre or Survey of India,

the truth will come out, whether the petitioner has

constructed building unauthorisedly in violation of the

permissible limit granted in terms of NOC. 412

XI. Conclusion

173. For the reasons stated above, the 1st point

raised in the present writ petition has to be answered in

the negative holding that the 1st respondent-HAL is not

justified in canceling the NOC for the entire building

including the permitted construction 62 mtrs (17 floors

i.e., 932 mtrs AMSL) ignoring the recommendation of

HAL NOC Committee and undertaking of the petitioner.

Accordingly, the petitioner has made out a case to refer

the matter to the competent authority-Karnataka State

Remote Sensing Application Centre ('KSRSAC') or

Survey of India for resurvey of the site property of the

petitioner for the Digital Global Positioning Systems

Field Survey Work to provide Latitude, Longitude and

AMS levels, as sought for by the 1st respondent in series

of advisories as well as in the main order of

cancellation. Therefore, it is necessary to direct for

resurvey of the site in the presence of the petitioner and 413

the concerned officers of the HAL or any authorized

agency by the first respondent, in the facts and

circumstances of the present case, subject to the

petitioner depositing necessary charges for resurvey,

either before the competent authority, KSRSAC or

before the Survey of India and the 1st respondent-HAL,

shall proceed further in accordance with law.

174. It is also not in dispute that the 1st

respondent has issued NOC dated 28.10.2011 with a

condition that, the petitioner shall construct the

building to height 62m above ground level, so that the

top of the proposed structure when erected shall not

exceed 870 m (site elevation) + 62m (height of the

structure) i.e., 932m AMSL. Admittedly, the said NOC

granted by the 1st respondent has not been challenged

by the petitioner, nor filed any application to revise

height permitted for construction and the same has

reached finality. Now in the present writ petition, 414

petitioner is seeking a writ of mandamus to direct the

1st respondent to permit the petitioner to construct the

building up to maximum height which does not affect

Aircraft operations and to direct the 1st respondent to

re-validate the NOC for a period of 5 years, which is

nothing but, indirectly seeking regularization of the

building constructed beyond 932 mtrs, in terms of NOC

granted by the 1st respondent, which is impermissible

and therefore, prayers (ii) and (iii) sought in the present

writ petition are pre-mature, at this stage. Therefore,

the mandamus sought for by the petitioner cannot be

issued, unless the petitioner shows legally and judicially

enforceable right as held by the Hon'ble Supreme Court

in the case of Mani Subrat Jain etc. vs. State of

Haryana and others reported in AIR 1977 SC 276,

wherein at paragraph-9, it is held as under:

"9. The High Court rightly dismissed the petitions. It is elementary though it is to be restated that no one can ask for 415

a mandamus without a legal right. There must be a judicially enforceable right as a legally protected right before one suffering a legal grievance can ask for a mandamus. A person can be said to be aggrieved only when a person is denied a legal right by some one who has a legal duty to do something or to abstain from doing something".

For the reasons stated above, the point No.2 raised for

consideration in the present writ petition has to be

answered in the negative holding that the petitioner has

not made out any prima-facie case to refer the dispute

for Aeronautical study by the AAI or any other

authorized agency, in view of the fact that the point

No.1 raised for consideration in the present writ petition

has been answered in the affirmative, holding that the

site property in question requires to be resurveyed by

the competent authority.

416

XII Result/Decision

175. For the reasons stated above, I pass the

following order:

(i) The writ petition is allowed in part and the impugned cancellation order bearing No. ASC/ DGM (AO)/ 131/526/2013 dated 16th August 2013 passed by the 1st respondent -

HAL as per Annexure-AQ is hereby quashed, only in so far as cancellation of NOC dated 28.10.2011 for construction of the residential apartments/flats to a height of 62 meters above ground level (Coord: Latitude N12˚55'38.28"

Longitude EO77˚37'55.74''), so that the top of the proposed structure when erected shall not exceed 932 meters AMSL { 870 meters (site elevation) + 62 meters (Height of the structure)} as per Annexure-A. 417

(ii) The matter is remanded to the 1st respondent - HAL for re-survey of the site property of the petitioner in question either by the Survey of India or Karnataka State Remote Sensing Application Centre (KSRSAC), for the Digital Global Positioning Systems Field Survey Work to provide Latitude, Longitude and Above Mean Sea Level (AMSL).

(iii) The petitioner shall deposit the prescribed fee for re-survey of the site property in question, before the 1st respondent - HAL within a period of one month from the date of receipt of copy of this order. On such deposit, the 1st respondent shall take necessary steps to re-

survey the site property/building of the petitioner either by the Survey of India or Karnataka State Remote Sensing Application Centre (KSRSAC) after obtaining necessary consent from the petitioner.

418

(iv) The competent authority i.e, The Survey of India or Karnataka State Remote Sensing Application Centre (KSRSAC) after issuing notice to the parties to the lis, shall re-

survey the site property/building of the petitioner in presence of the parties within a period of six months from the date of receipt of a copy of this order, strictly in accordance with law and thereafter, based on such report shall proceed further in accordance with law.

(v) The 1st respondent - HAL shall not take any precipitative action against the petitioner in respect of the site property/apartments/flats in question until re-survey is made by the competent authority.

(vi) The petitioner shall not put up any further construction and shall not modify/alter/renovate/develop the building/apartments constructed in 419

the property in question. The petitioner shall not sell or agree to sell or enter into an agreement with third parties in whatsoever manner in respect of any portion of the building, till re-survey is made by the competent authority.

(vii) The writ petition is hereby dismissed in so far as prayer Nos.2 and 3 as premature, with liberty to the petitioner to file necessary application at the

appropriate/relevant point of time before the competent authority, if permissible in accordance with law.

(viii) The respondents, who claim to be agreement holders/ purchasers of flats from the petitioner, are at liberty to approach the petitioner for the alternative flat, if any constructed within the permissive limit as per the NOC dated 28.10.2011 vide Annexure-A. OR In 420

the alternative, it is needless to observe that they are at liberty to approach the competent Court for appropriate relief in accordance with law.

(ix) All the contentions of the parties with regard to aeronautical study are kept open to be urged before the appropriate Court/authority at the relevant point of time, if need arises, in future in accordance with law.

XIII. Acknowledgment

176. In crafting this judgment, the erudition of

the learned Senior Counsel and other Counsel, who

have appeared for the parties on 83 various hearing

dates, their industry, vision, sincerity and dedication

and above all, dispassionate objectivity in discharging

their role as Officers of the Court is commendable. 421

177. This Court acknowledges the valuable

assistance rendered by Sri Udaya Holla, learned Senior

Counsel along with Sri Kamlesh Sampat; Sri Ananth

Mandagi, learned Senior Counsel along with Sri

Pradeep Sawkar; Sri Sajan Poovayya, learned Senior

Counsel along with Smt. Nalina Mayegowda; Sri Aditya

Sondhi, learned Senior Counsel along with Sri Karan

Joseph and the same is placed on record.

Sd/-

JUDGE

Nsu/ Gss/ kcm

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free