M/S. Associated Construction vs Pawanhans Helicopters Pvt. Ltd

Supreme Court7 May 2008Tarun Chatterjee · Harjit Singh Bedi

Ratio decidendi

The rule this decision rests on

1. Where a contract contains a clause barring escalation of price during the contractual period but also contains a clause providing compensation for loss and expense resulting from delay attributable to the other party, and the contract specifies that time is the essence, an embargo on escalation claims does not extend beyond the contractual period; a contractor may claim compensation for loss and expense incurred during the extended period when the delay is attributable to the other party's conduct. 2. In interpreting contract clauses that restrict claims for additional payment, a clause providing for indemnity in respect of specific circumstances (such as delay caused by the other party) must be read as qualifying any blanket prohibition on additional claims, particularly where the clause expressly states that its remedies are without prejudice to other rights and remedies available to the contractor. 3. An award made by an arbitrator cannot be set aside merely because the court would have arrived at a different conclusion on the same evidence or would have given a stricter interpretation to the contract terms, provided the arbitrator's view is a permissible interpretation of the contract and the arbitrator has acted within his jurisdiction and applied no violation of natural justice. 4. A "No Claim Certificate" or "No Dues Certificate" submitted by a contractor under duress—where the other party has withheld payment and made payment conditional on such submission—does not bind the contractor and is not a bar to the contractor subsequently raising genuine claims supported by voluminous contemporaneous correspondence showing economic hardship and repeated requests for payment without such certification.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

CASE NO.:Appeal (civil) 3376-3377 of 2008
PETITIONER:M/s. Associated Construction
RESPONDENT:Pawanhans Helicopters Pvt. Ltd
DATE OF JUDGMENT: 07/05/2008
BENCH:TARUN CHATTERJEE & HARJIT SINGH BEDI
JUDGMENT:
JUDGMENT
REPORTABLE
IN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
CIVIL APPEAL Nos.3376-3377/2008(arising out of SLP (C) Nos. 17335-17336/2007)
M/s. Associated Construction ..........Appellant
Vs.
Pawanhans Helicopters Pvt. Ltd. .........Respondent
JUDGMENT
HARJIT SINGH BEDI,J.
1. Leave granted.

2. The respondent, Pawanhans Helicopters Pvt. Ltd.

(hereinafter called "Pawanhans") a Government of India

undertaking, floated two tenders for allocation of work for

construction of a compound wall and a bridge over a nala.

Pursuant to the aforesaid information, several tenders were

received and the tenders of the appellant (hereinafter called

the "contractor") were ultimately accepted. Pursuant to the

aforesaid, two formal agreements providing for the terms and 2

conditions of the contract in the shape of general conditions

of the contract and special conditions of the contract

governing the execution of work were duly signed on 12th

October 1999. As per the contract the work was required to

be completed within four months. It appears that on account

of some delay which was attributable to Pawanhans, the work

did not proceed as per schedule and the contractor

accordingly informed Pawanhans by letters dated 15th

February 1990, 23rd February 1990, 24th March 1990, 26th

June 1990 and 6th July 1990 that the work was getting

delayed as the requisite facilities for its completion had not

been provided and highlighting several factors attributable to

it had supervened which had led to the delay. The contractor

also in the meanwhile vide letters dated 27th July 1990 and 6th

August 1990 requested the respondent to release the

outstanding bills against the work already completed and also

requested for the "Virtual Completion Certificate" vide letter

dated 25th August 1990. As some work on the compound wall

still remained to be completed, the contractor agreed to take

up this assignment subject to waiver of the discount of 8.2% 3

which was to be given to Pawanhans till then and the

completed works were duly handed over to Pawanhans on the

12th November 1990. The contractor had also submitted a bill

dated 23rd June 1991 and it was conveyed to Pawanhans that

it expected compensation on account of the variation in the

terms of the contract. Pawanhans thereupon advised the

contractor to submit a final bill which too was submitted. The

bill was verified by Pawanhans and referred to the contractor

yet again with objections. The contractor vide letter dated 21st

November 1991 disputed the verification as being without any

foundation and also reserved its right to seek arbitration.

After a protracted correspondence, Pawanhans vide letter of

9th December 1991 advised the contractor to submit a "No

Claim Certificate" as a pre-condition for the release of the

balance payment. The contractor wrote to Pawanhans that it

was in dire need of finances and was being subjected to

duress but nevertheless submitted a "No Dues Certificate"

dated 17th February 1992 once again specifically highlighting

that the same was being issued under duress. It appears that

despite the issuance of the aforesaid certificate, Pawanhans 4

still did not release the payment on which the contractor wrote

another letter dated 5th May 1992 and several letters

thereafter but again to no effect, and on the contrary received

a letter dated 8th June 1992 from Pawanhans asking for a "No

Dues Certificate" as per the enclosed specimen without

attaching any condition to the same. The contractor, now in a

desperate situation, submitted yet another "No Claim

Certificate" dated 18th June 1992 as per directions. After

receiving the aforesaid document, Pawanhans in its letter

dated 9th February 1993 informed the contractor that a period

of two months would be required for the scrutiny of its bills

and vide letter dated 21st May 1993 also intimated that the

bills had been submitted for verification by the

Architect/Engineer as per the terms of the contract and that

in case it was willing to defray the payment, the matter could

be referred to arbitration. The contractor finally received a

communication dated 8th June 1993 pointing out that as all

payments due under the contract had been made and as a "No

Dues Certificate" had been furnished, no further amount was

due. The contractor accordingly served a notice dated 28th 5

June 1993 on Pawanhans invoking the clause relating to

arbitration. The matter was referred to arbitration by two

registered Architects as per the clause. The contractor

submitted its statement of claim for the outstanding amount

plus compensation and damages on 6th August 1994. The

arbitrators passed two awards on 31st December 1996, one

with respect to the contract for the compound wall and the

second for the construction of the bridge awarding certain

amounts to the contractor. Aggrieved by the awards,

Pawanhans filed two separate petitions under sections 30 and

33 of the Arbitration Act, 1940 before the Bombay High Court

for a direction that the awards be set aside. The learned

Single Judge in his judgment and order dated 9th December

1998 held that clauses 18 and 34 of the contract when read

together, provided for the payment of escalation charges as

the work had not been completed within four months on

account of the fault on the part of the respondent and that the

said clauses did not prohibit such a payment, more

particularly as time was the essence of the contract and as the

contract was not on a fixed price, the prohibition of escalation 6

was if at all to be read during the period of contract only. The

learned Single Judge also repelled the arguments of the

respondent that after having submitted the final bill on 25th

October 1991, it was not open to the appellant herein to

submit a second final bill on 2nd February 1993 by observing

that the payment received on the 4th July 1993 as a

consequence of the bills submitted on 25th October 1991, was

under duress and it is on that account that the appellant had

given the aforesaid certificate. Some objections raised by the

respondent herein were however accepted by the learned

Single Judge and the award was accordingly modified and it is

the admitted case that the aforesaid modification has been

accepted and was not challenged before the Division Bench by

the contractor.

2. Two appeals were thereafter filed by Pawanhans before

the Division Bench of the Bombay High Court. The

Division Bench vide its order dated 7th June 2007

allowed the appeals and set aside the order dated 9th

December 1998 of the learned Single Judge as also the

two awards dated 31st December 1996 by highlighting as 7

a preface that it could not be disputed that the scope for

interference by the court under section 30 or 33 of the

Arbitration Act was limited as the court could not sit as a

court of appeal on the decisions arrived at by the

arbitrator. The Court then applied the aforesaid

principle to the facts of the case and relied on clauses 18

and 34 ibid observed that a plain reading of the said

clauses did not visualize any claim for escalation or

reduction towards the cost of the work and again

reiterated that clause 34 of the agreement prohibited the

contractor from claiming any extra amount on account of

fluctuation of price. The Court further observed,

somewhat in contradiction, that a remedy towards the

escalation of price had been provided by clause 43 of the

contract and clause 43-1(E) specifically provided, the

procedure whereby such a claim could be made and as

the procedure prescribed by the clause had not been

adopted, it was not open to the contractor to contend

before the arbitrator that it was entitled to some 8

payments on account of price escalation. The Court

finally concluded that:

"Once it is clear that the respondents are not entitled to claim escalation charges and the entire dispute, which is the subject matter of the appeals being related to the escalation charges, the impugned orders, to the extent they confirm the award in relation to the escalation charges, are liable to be set aside and the petitions filed by the appellants challenging the awards in relation to the grant of the escalation charges are liable to be allowed to that extent. Consequently, the claims for interest on the amount of damages awarded towards the escalation are also liable to be set aside."

3. The Division Bench then examined the issues raised by

the contractor as to whether that "No Due Certificate" had

been given under duress and held that there was no evidence

to show that the said certificate had been given under duress

or coercion and as the certificate itself provided a clearance of

no dues, the contractor could not now turn and say that any

further payment was still due on account of the second final 9

bill. The Division Bench accordingly allowed the appeal. The

matter is before us in these circumstances.

4. Mr. Shyam Divan, the learned senior counsel for the

contractor, has raised several arguments before us during the

course of the hearing. He has first pointed out that the

awards rendered by the arbitrator were non-speaking and in

this view of the matter, the scope for judicial interference was

extremely limited and interference with the findings of the

Arbitrators was, therefore, not called for. He has also pleaded

that clauses 18 and 34, as per their plain interpretation

themselves visualized a claim for escalation where the delay

had been caused by the opposite party and that in any case,

the bar on the escalation, if at all, could be restricted only for

the period of contract i.e. four months and not thereafter. He

has also submitted that clause 43-1(C) on which reliance had

been placed by the Division Bench for non-suiting the

contractor, was misplaced as this clause too did not

specifically or even by implication whittle down the effects of

clauses 18 and 34. It has also been argued that the finding of

the Division Bench that there was no duress on the contractor 10

relating to the issuance of the "No Claim Certificates" was

incorrect in the light of the voluminous evidence to the

contrary on record.

5. Mr. Raju Ramachandran, the learned senior counsel

appearing for Pawanhans has fairly and at the very outset

pointed out that the award in question was non-speaking and

as such the scope for interference by the court was limited.

He has further contended that it would perhaps be difficult to

read into the clauses a complete bar towards escalation, as a

court would be reluctant to visualize such a bar in the light of

some unforeseen situations that might arise in the execution

of a work and the gates, thus, could not for ever be closed, but

has submitted that clause 43 provided for such an opening

and as this procedure had not been adopted by the contractor,

the claim under clauses 18 and 34 was not maintainable. He

has also submitted that the "No Dues Certificate" having once

being given by the contractor, it was not open to it to make a

volte-face and to challenge the said certificate on the ground

that it had been given under duress and the finding of the

Division Bench on this point was, therefore, correct. 11

6. We have heard the learned counsel for the parties and

gone through the record. As would be apparent, the matter

would rest on an interpretation of clauses 34, 43 (1) and (2) of

the General Conditions of the Contract and clause 18 of the

Special Conditions of the Contract. We reproduce herein

below the clauses abovementioned:

"34. The contractor shall not claim any extras for fluctuation of price and the contract price shall not be subject to any rise or fall of prices.

43 (1) E. Architect's instructions issued in regard to the postponement of any work to be executed under the provisions of this contract; and if the written application is made within a reasonable time of it becoming apparent that the progress of the work or of any part thereof has been affected as aforesaid:

Then the Architect shall ascertain the amount of such loss and/or expense. Any amount from time to time so ascertained shall be added to the amount which would otherwise be stated as due in such certificate.

43 (2) The provisions of this condemn are without prejudice to any other rights and remedies which the contractor may possess.

18. It is specifically pointed out that the contractor shall not be entitled to any compensation whatsoever on account of:

12 1. Any delay in supply of any material.

2. Any increase in costs of any material.

3. Any subsequent increase in cost of any material due to increase in other charges like Railway, Steamer, freights or taxes and duties.

4. Any increase in labour costs."

7. We have examined the arguments raised by the learned

counsel in the light of the aforesaid and other provisions. It is

the admitted position that as per clause 38, the date of the

commencement of the contract was 1st November. 1989 and

the date stipulated for the completion of the work was 28th

February 1990. It is also clear from sub-clause (7) of clause 1

of the General Conditions that time would be the essence of

the contract. We also see from clause 43 aforequoted that this

clause has within itself the clear indication that the embargo

placed by clauses 18 and 34 was not sacrosanct as has been

found by the Division Bench as there could be a situation

where the contractor had suffered loss for whatever reasons

which was required to be reimbursed as per procedure 13

prescribed in clause 43. Clause 43 (2) also specifically

provided that clause 43 was without prejudice to any other

rights and remedies that the contractor might possess. We

find from a reading of the judgment of the Division Bench that

the contractor has been non-suited on the plea that it had

failed to proceed under clause 43. On the contrary we believe

that Clause 43 is a clause which should be read in aid of the

contractor as it clearly provides for indemnity in case there

was a delay in the completion of the work which could be

attributable to Pawanhans. We are, further, of the opinion

that even assuming for a moment that there could be no price

escalation during the period of 4 months i.e. during the

pendency of the contract, such embargo would not be carried

beyond that period as time was the essence of the contract.

The learned Division Bench has relied upon a large number of

judgments in support of its decision that in case of a clause

barring the escalation in the price, it was not open to the

contractor to claim any amount under that head. A perusal of

the aforesaid judgments, however, do not show any provision

in terms of clause 43, and that in any case, these judgments 14

pertain to a claim of price escalation during the period of

contract. It must also be borne in mind that a court does not

sit as one in appeal over the award of the arbitrator and if the

view taken by the arbitrator is permissible, no interference is

called for on the premise that a different view was also

possible. We also feel that in commercial transactions all

situations cannot be visualized and the positive and

unchallenged finding in the present case is that the delay in

the execution of the work was occasioned on account of

reasons attributable to Pawanhans. It cannot, therefore, be

said that the award of the arbitrator was so unconscionable

that it required interference. In MCD vs. M/s.Jagan Nath

Ashok Kumar & Anr. (1987) 4 SCC 497, it was observed

thus:

"In this case, there was no violation of any principles of natural justice. It is not a case where the arbitrator has refused cogent and material factors to be taken into consideration. The award cannot be said to be vitiated by non-reception of material or non- consideration of the relevant aspects of the matter. Appraisement of evidence by the arbitrator is ordinarily never a matter which the court questions and considers. The parties have selected their own forum and the 15

deciding forum must be conceded the power of appraisement of the evidence. In the instant case, there was no evidence of violation of any principle of natural justice. The arbitrator in our opinion is the sole judge of the quality as well as quantity of evidence and it will not be for this Court to take upon itself the task of being a judge of the evidence before the arbitrator. It may be possible that on the same evidence the court might have arrived at a different conclusion than the one arrived at by the arbitrator but that by itself is no ground in our view for setting aside the award of an arbitrator."

and further concluded:

"After all an arbitrator as a judge in the words of Benjamin N. Cardozo, has to exercise a discretion informed by tradition, methodized by analogy, disciplined by system, and subordinated to "the primordial necessity of order in the social life".

8. P.M.Paul vs. Union of India (1989) Supp 1 SCC 368 is

a case which is almost identical on facts. In this matter the

work could not be completed during the period of the contract

and the contractor was accordingly granted extension of time

to complete the same. By an order of this Court, the dispute

was referred to an Arbitrator on the reference as to who was 16

responsible for the delay in the completion of the work, what

were to be the repercussions of the delay and how to

apportion the responsibility and the consequences. The

arbitrator made an award in favour of the contractor which

was duly challenged by the Union of India with the matter

finally reaching this Court at the instance of the contractor

and this is what the Court had to say.

"It was submitted that if the contract work was not completed within the stipulated time which it appears was not done then the contractor has got a right to ask for extension of time, and he could claim difference in price. This is precisely what he has done and has obtained a portion of the claim in the award. It was submitted on behalf of the Union of India that failure to complete the contract was not the case. Hence, there was no substance in the objections raised. Furthermore, in the objections raised, it must be within the time provided for the application under Section 30 i.e., 30 days during which the objection was not specifically taken, we are of the opinion that there is no substance in this objection sought to be raised in opposition to the award. Once it was found that the arbitrator had jurisdiction to find that there was delay in execution of the contract due to the conduct of the respondent, the respondent was liable for the 17

consequences of the delay, namely, increase in prices. Therefore, the arbitrator had jurisdiction to go into this question. He has gone into that question and has awarded as he did."

9. A similar view has been taken by this Court in

K.N.Sathyapalan (D) By Lrs. vs. State of Kerala & Anr.

(2006) 12 SCALE 654. It has been held as under:

"We have intentionally set out the background in which the Arbitrator made his award in order to examine the genuineness and/or validity of the appellant's claim under those heads which had been allowed by the Arbitrator. It is quite apparent that the appellant was prevented by unforeseen circumstances from completing the work within the stipulated period of eleven month and that such delay could have been prevented had the State Government stepped in to maintain the law and order problem which had been created at the work site. It is also clear that the rubble and metal, which would have been available at the departmental quarry at Mannady, had to be obtained from quarries which were situated at double the distance, and even more, resulting in doubling of the transportation charges. Even the space for dumping of excess earth was not provided by the respondents which compelled the appellant to dump the excess earth at a place which was for away from the work site entailing extra costs for the same.

18 In the aforesaid circumstances, the Arbitrator appears to have acted within his jurisdiction in allowing some of the claims on account of escalation of costs which was referable to the execution of the work during the extended period, In our judgment, the view taken by the High Court was on a rigid interpretation of the terms of contract and the Supplemental Agreement executed between the parties, which was not warranted by the turn of events."

10. We are, therefore, of the opinion in the light of the

aforesaid judgments, that it was open to the contractor to

contend that it was liable to be compensated on account of the

fact that delay had been occasioned on account of reasons

attributable to Pawanhans. It is significant that the Division

Bench of the High Court has been silent on this aspect of the

matter and has not referred to the finding of the learned Single

Judge with regard to the responsibility for the delay.

11. We are further of the opinion that clause 43 and 43 (1)

and (2) when read together clearly visualize escalation of price

on account of reasons beyond the control of the contractor

and attributable to the other side. Moreover clause 43 (2)

clearly states that the remedy under clause 43(1) would be in 19

addition to such other remedy that may be open to the

contractor under the other provisions.

12. We have also gone through the record with respect to the

finding of the Division Bench that there was no duress or

coercion on the contractor which had compelled it to give a

"No Dues Certificate". Mr. Raju Ramachandran has, however,

submitted that the story about duress was an after thought in

the background that the first final bill had been submitted by

the contractor on the 3rd June 1991 and the second final bill

on 2nd February 1993 i.e. almost 2 years later and that in any

case, a second final bill was not visualized under the contract.

He has submitted that the observation of the arbitrator that

submission of the second final bill was sanctioned as a trade

practice was without any basis. We have gone through the

record in the light of the submissions of the learned counsel.

We first refer to the letter of the contractor of 11th July 1990 to

which reference has been made by the Division Bench

requesting Pawanhans to ensure a regular power supply. The

letter of 27th July 1990 by the contractor refers to the

statement of accounts submitted by it and requests for 20

payment as per the accounts which had been cleared by the

Architect. It is to be noted that these letters are on the record

and were written by the contractor at the time when the work

was in the process of completion. The desperate tone of the

contractor is however supported by the letter of 10th January

1991 in which it was noted that though repeated requests had

been made for the payment atleast against the bills certified

by the Architect, a huge amount had been blocked arbitrarily

over a long period of time and a request was made for its

release. The letter dated 21st November 1991 is again a

reminder to Pawanhans asking for payment and that in case

there was a dispute, the matter be referred to the arbitrator

and submitting that payment should be made atleast with

respect to those dues which had been certified by the

Architect. The letter dated 9th December 1991 from

Pawanhans to the contractor shows that payment could be

considered provided the contractor submitted a "No Claim

Certificate". It appears that such certificate was indeed issued

but with no result on which the contractor in his letter dated

26th December 1991 in reply to the letter dated 9th December 21

1991, once again submitted that the payments be released in

so far as they had been certified by the

Architects/Consultants and if there was a dispute regarding

the other payments, they should be referred to an arbitrator

and in desperation further adds:

"However, if you want to hold us to economic duress by not paying what you wish to pay, without "No Claim Certificate", we shall treat it as "Duress" and issue you such a certificate much against our willingness as we cannot afford to liquidate our dues by such a certificate.

Please do not hold us to a ransom and arrange to pay. In case you would still like to insist, let us know, so that we could issue you such a certificate under duress as we have serious financial problems."

14. It appears that despite the pleading tone of the aforesaid

letter no payment was made on which the contractor wrote yet

another letter dated 17th February 1992 in which it was

submitted as under:

"Inspite of our claim statements, you have insisted on "No Claim Certificate", we hereby give you this certificate that we have "No Claims" and hence you pay us what you might have worked out as our "Final Dues".

22 In case, you have a particular draft in which a "No Claim" Certificate need be issued to receive our dues of our bill, please let us have the deft, or else this letter may be treated as the certificate of "No Claim"

from our side."

15. When no action was taken, another letter dated 5th May

1992 was addressed to Pawanhans by the contractor stating

that as they were facing economic duress on account of the

payment being held back, and as a "No Claim Certificate" had

been issued, the payment be defrayed as promised or else

they might have to refer the matter to the arbitrator. The

letter dated 8th June 1992 is again tell-tale and we reproduce

the contents hereunder:

"Kindly let us know what is it that we have to do to get money which you say is payable but only on your extracting "No Claim" certificate under duress. Please take note if you fail to pay us our dues, we shall be constrained to take you to court for which you will blame yourself if it inconvenience is caused. It is a clear 15 days notice please."

23 16. It appears however that no steps were taken on which

the contractor addressed a letter dated 2nd February 1993 for

payment of dues and again stated that if the payment was not

made, the dispute should be referred to the arbitrator. In

response to this letter, Pawanhans in its letter dated 9th

February 1993 replied that the matter was under scrutiny

and it would take about 2 months for verification and that the

contractor would be informed in due course. As no reply was

received, a letter dated 21st May 1993 was addressed by the

contractor relating to the undertaking

that the enquiry would be completed within 2 months but

complaining that nothing had been done and on the contrary

on 8th June 1993 the claim for any payment was rejected by

Pawanhans observing that as a "No Dues Certificate" had

been submitted by the contractor, the question of any balance

payment being due did not arise. It is at this stage that the

contractor had invoked the clause for arbitration. We have

reproduced the correspondence in extenso to show that the

contractor was compelled to issue a "No Dues Certificate" and

in this view of the matter, it could not be said that the 24

contractor was bound by what he had written. It is also clear

that there is voluminous correspondence over a span of

almost 2 years between the submission of the first final bill on

3rd June 1991 and the second final bill dated 2nd February

1993 and as such the claim towards escalation or the plea of

the submission of a "No Dues Certificate" under duress being

an after thought is not acceptable. In M/s. Ambica

Construction vs. Union of India (2006) 12 SCALE 149 it

was observed as under:

"A glance at the said clause will immediately indicate that a No Claim Certificate is required to be submitted by a contractor once the works are finally measured up. In the instant case the work was yet to be completed and there is nothing to indicate that the works, as undertaken by the contractor, had been finally measured and on the basis of the same a No Objection Certificate had been issued by the appellant. On the other hand, even the first Arbitrator, who had been appointed, had come to a finding that No Claim Certificate had been given under coercion and duress. It is the Division Bench of the Calcutta High Court which, for the first time, came to a conclusion that such No Claim Certificate had not been submitted under coercion and duress.

25 From the submissions made on behalf of the respective parties, and in particular from the submissions made on behalf of the appellant, it is apparent that unless a discharge certificate is given in advance, payment of bills are generally delayed. Although, Clause 43(2) has been included in the General Conditions of Contract, the same is meant to be a safeguard as against frivolous claims after final measurement. Having regard to the decision in the case of Reshmi Constructions's (supra), it can no longer be said that such a clause in the contract would be an absolute bar to a contractor raising claims which are genuine, even after the submission of such No Claim Certificate."

17. We are therefore of the opinion that the judgment of the

Division Bench is erroneous and we accordingly set it aside.

The judgment of the learned Single Judge is accordingly

restored. In the facts and circumstances of the case, in that

Pawanhans has taken advantage of a beleaguered contractor,

and has behaved in a most unbecoming manner in pushing it

ever deeper into the chasm, the contractor will have its costs

which are computed at Rs.10,000/-. The appeals are

accordingly allowed.

26

..................................J. (TARUN CHATTERJEE)

...................................J. ( HARJIT SINGH BEDI )

New Delhi, Dated: May 7, 2008

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free