Miss Lucy
← All judgments

M/s Andhra Pradesh Power Generation Corporation Limited vs M/s Tecpro Systems Limited & Others

Supreme Court17 December 2025Pamidighantam Sri Narasimha

Ratio decidendi

The rule this decision rests on

At the referral stage under Section 11(6) of the Arbitration and Conciliation Act, 1996, the referral court is confined to a prima facie determination of the existence of an arbitration agreement and must refrain from entering into contentious factual or legal issues related to authority, capacity, arbitrability, or maintainability; a detailed inquiry into whether a non-signatory to an agreement or a member of a consortium seeking to invoke arbitration is a veritable party to the arbitration agreement must be left to the Arbitral Tribunal under Section 16. The referral court may undertake a prima facie examination of whether a member of a consortium qualifies as a "party" to an arbitration agreement based on the terms of the principal contract and the Consortium Agreement without conducting a detailed evidentiary inquiry; the question whether a particular member has the right or capacity to invoke arbitration does not admit of uniform answer but depends on examination of the specific contractual terms, and is a matter for determination by the Arbitral Tribunal on the substantive evidence and application of legal doctrine. Where an arbitration agreement is prima facie shown to exist between parties, the referral court must constitute the Arbitral Tribunal and refer the dispute to it, leaving for the Tribunal's determination under Section 16 all preliminary objections relating to jurisdiction, including whether the invoking party is a veritable party to the agreement, whether a consortium continues to exist, whether consent of other consortium members was necessary, and whether claims are maintainable after insolvency proceedings.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2025 INSC 1447 REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. OF 2025 ARISING OUT OF SLP (C) NO. 8998 OF 2023

M/S ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED (APGENCO) ...APPELLANT(S)

VERSUS

M/S TECPRO SYSTEMS LIMITED & ORS. …RESPONDENT(S) WITH

CIVIL APPEAL NO. OF 2025 ARISING OUT OF SLP (C) NO. 13200 OF 2023

JUDGMENT

I. Introduction:

1. Leave granted.

2. These two civil appeals arise from an order passed by the High

Court for the State of Telangana at Hyderabad1 under Section 11(6) of the

Arbitration and Conciliation Act, 19962 constituting an Arbitral Tribunal

(AT) for resolution of dispute as per the arbitration clause 22.2 in General

Conditions of Contract (GCC). The contest by the two appellants is on the Signature Not Verified Digitally signed by Jayant Kumar Arora Date: 2025.12.17 15:38:29 IST 1 In Arbitration Application No. 81 of 2019 dated 17.02.2023. Reason:

2 Hereinafter, “Act, 1996”.

Page 1 of 21

ground that first respondent, being one of the members of the Consortium,

could not have invoked arbitration in its individual capacity. This is based

on the simple plea that the arbitration agreement is only between the

appellant APGENCO, the purchaser and the “Consortium”. While

considering an application under Section 11, we are of the opinion that

the High Court was justified in constituting the AT on the basis of a prima

facie test of arbitrability. We have further held that it is for the AT to

examine the preliminary issue in detail by considering the contractual

provisions and the surrounding evidence. We have thus upheld the order

passed by the High Court constituting the AT.

II. Facts:

3. Facts that are necessary for disposal of these appeals are that the

appellant APGENCO, floated a tender inviting bids from a Consortium of

companies for an EPC contract pertaining to works for their Rayalseema

Thermal Power Plant. The tender specifications incorporated the

Instructions to Bidders (IB) and the General Conditions of Contract (GCC),

comprising of dispute resolution through arbitration under Clause 22.2.

4. A Consortium comprising respondent nos. 1, 2 and 3 namely M/s

Tecpro Systems Ltd., M/s VA Tech Wabag Ltd., and M/s Gammon India

Ltd. was constituted on 17.08.2010 for exclusively participating in the

Page 2 of 21 tender process, with Tecpro Systems Ltd., the first respondent designated

as the Leader of the Consortium. The Consortium emerged successful,

and a Letter of Intent (LOI) dated 30.10.2010 was issued to the

Consortium through the first respondent, being the lead member.

Thereafter, three Purchase Orders, dated 15.12.2010 were issued in

favour of the Consortium and execution commenced, each member

undertaking its respective scope of work.

5. During execution, first respondent encountered severe financial

distress, resulting in project delays. Consequently, VA Tech, being jointly

and severally liable as a consortium member, undertook first respondent’s

scope of work and was subsequently recognised as the Lead Member

vide correspondence dated 04.04.2014, resulting in amendment of the

Consortium Agreement. Billing continued to be raised in the name of first

respondent for administrative purposes, while payments flowed directly to

each member in agreed proportions. Later, the first respondent was

admitted into Corporate Insolvency Resolution Process (CIRP) on

07.08.2017, followed thereafter by an order initiating liquidation.

6. After the first respondent ceased to be the lead member, the

appellant, APGENCO issued a letter dated 04.10.2017 to first respondent

that it was responsible for substantial delays in execution of the project.

Page 3 of 21 In reply, first respondent denied the allegations and asserted that the

appellant had committed various breaches, because of which the

company suffered losses, amounting to approximately Rs. 1951.59

crores. By letter dated 11.12.2017 the first respondent demanded

payment of the said amount and also indicated that, if the claim is

disputed, the letter should be treated as a notice invoking the arbitration

clause under the GCC. In its response, the appellant APGENCO, rejected

these allegations and asserted counter claims predicated on losses

alleged to have been suffered due to first respondent’s non-performance.

Gammon India Ltd. (respondent no. 3) also protested first respondent’s

unilateral communication, asserting that it lacked authority to act without

the consent of other consortium members.

7. As the appellant did not release the claimed amount, first

respondent issued another letter dated 03.04.2018, stating that disputes

had clearly arisen between the parties. Through this communication, first

respondent formally invoked the arbitration clause and nominated a

former Judge of this Court as its nominee arbitrator, and called upon the

appellant to appoint its arbitrator. Appellant neither responded to said

notice nor has taken steps to constitute the AT. Aggrieved by this inaction,

first respondent instituted proceedings under Section 11(6) before the

High Court, and the appellant promptly objected to maintainability on the

Page 4 of 21 ground that the first respondent as an individual member, cannot

unilaterally invoke arbitration.

8. The High Court, however, allowed the Section 11(6) application and

referred the disputes to arbitration. The said judgment is assailed in the

present appeals.

III. Submissions:

9. In view of our conclusion that the grounds raised by the appellant

and the respondent can and should be considered by the AT, it is

necessary to note in detail each and every submissions made by appellant

and the respondent. This is necessary to determine whether a submission

is beyond the remit of the AT, or that, the question must be considered at

the referral stage itself.

A. Submissions on behalf of the Appellants:

10. We have heard Mr. N. Venkataraman, learned A.S.G. appearing on

behalf of appellant, APGENCO and Mr. Guru Krishnakumar, Senior

Advocate on behalf of M/s. VA Tech Wabag Ltd., appellant in the

connected civil appeal. The cumulative submissions on behalf of the

appellants are as follows:

Page 5 of 21

10.1 At the referral stage, Court exercising jurisdiction under Section 11

of the Act, 1996 is obliged to prima facie satisfy itself as to the existence

of an arbitration agreement between the parties. Prima facie satisfaction

necessarily includes an examination of the arbitration agreement and the

parties to such arbitration agreement. Upon such examination, it would be

evident that no arbitration agreement exists between APGENCO and first

respondent.

10.2 The arbitration agreement contained in Clause 22.2 of GCC is

enforceable against APGENCO by the “Contractor”, that is, the

Consortium, and not by any individual member. The term “Parties” in

Clause 1.1.63 of the GCC is defined to mean the “Purchaser” or the

“Contractor”, and “Purchaser” is defined in Clause 2.1, as APGENCO and

that “Contractor” is defined as “the person whose tender has been

accepted by the Purchaser and the legal successors in title to such

person”. It is therefore argued that the expression “person” expressly

includes the Consortium, and therefore it is only the Consortium, which is

a party to the arbitration agreement. The definitions of “contractor”,

“bidder”, “person” and “party”, read conjointly, demonstrate that the

contracting counterparty was the “Consortium” and not any individual

constituent entity. Hence, first respondent, in its individual capacity, could

not have approached the High Court for appointment of an arbitrator.

Page 6 of 21 10.3 No arbitration agreement exists between the first respondent in its

individual capacity, and APGENCO. The reliance placed by first

respondent upon the arbitration clause contained in the GCC is

misplaced. The GCC is a pre bid document. Upon acceptance of the bid

by a consortium, the contractual relationship culminates into Purchase

Orders. In fact, the three Purchase Orders contain identical jurisdictional

clauses conferring exclusive jurisdiction upon civil courts at Hyderabad or

Secunderabad, with no provision for arbitration as a dispute resolution

mechanism. The Purchase Orders constitute the principal contracts

governing the relationship between the purchaser on one hand and the

Consortium, as a collective entity, on the other.

10.4 Relying on the judgments of the Delhi High Court in Consulting

Engineers Group Ltd. v. National Highway Authority of India (NHAI) 3 and

the Bombay High Court in MSEDCL v. Godrej and Boyce Manufacturing

Company Ltd. 4, it is urged that an individual consortium member lacks the

competence to invoke arbitration in the absence of authority from the other

members of the consortium.

3 2022 SCC OnLine Del 3253.

4 2019 SCC OnLine Bom 3920.

Page 7 of 21 10.5 The Group of Companies doctrine is wholly inapplicable as per the

judgment of this Court in Cox and Kings Ltd. v. SAP India Pvt. Ltd. 5, which

clarifies that mutual intention is indispensable and cannot be implied so

as to override an express contractual structure, which envisages action

only through the Consortium and excludes unilateral action by individual

members.

10.6 First respondent lost Consortium leadership in 2014 due to non-

performance; VA Tech Wabag took over and completed the work. First

respondent later entered CIRP in 2017 but still issued a unilateral

arbitration notice, contrary to the stand of the other Consortium members,

who oppose arbitration against APGENCO. Claims relating to the

Consortium cannot be raised unilaterally by a defaulting and insolvent

member.

10.7 High Court failed to appreciate the distinction, as affirmed in ASF

Buildtech P. Ltd. v. Shapoorji Pallonji & Co. P. Ltd.6, between the

“existence” of an arbitration agreement and the “capacity to invoke” such

agreement. While an arbitration agreement undoubtedly exists, only the

5 (2024) 4 SCC 1.

6 (2025) 9 SCC 76.

Page 8 of 21 Consortium, and not an individual member, has the contractual capacity

to invoke it.

10.8 Claim of first respondent to be a “legal successor” of the

Consortium, and therefore falling within the definition of Contractor as per

the GCC is entirely misconceived. The term successors in title envisages

one to whom ownership/title is transferred, and would not be applicable to

a Consortium such as the present one.

10.9 The attempt of first respondent to invoke arbitration independently,

despite default, insolvency and cessation of leadership, constitutes a

misuse of the arbitral process and is contrary to the contractual framework

and commercial common sense. Reliance is also specifically placed upon

the order dated 07.11.2023 passed by Hon’ble Justice M. B. Lokur in

arbitration proceedings relating to Telangana State Power Generation

Corporation Limited (TSPGCL), wherein identical claims raised by first

respondent were rejected on the ground that it could not act independently

of the consortium.

B. Submissions on behalf of first respondent:

11. Mr. Anirudh Krishnan, Advocate on behalf of the first respondent, on

the other hand submits the following:

Page 9 of 21

11.1 Objections raised by appellants are fundamentally misconceived

because the contractual framework, properly construed, recognises that

first respondent had both the right and the authority to invoke arbitration.

The tender floated by APGENCO envisaged participation by single

bidders as well as consortiums, and that the Consortium of respondent

nos. 1 to 3 was duly constituted in accordance with the tender terms. The

Purchase Orders issued pursuant to the Letter of Intent explicitly

incorporated the Tender Specification, which in turn incorporated the GCC

including Clause 22.2 which contains the operative arbitration agreement.

11.2 In view of the principles laid down in M.R. Engineers and

Contractors Pvt. Ltd. v. Som Datt Builders Ltd. 7, Inox Wind Ltd. v.

Thermocables Ltd. 8, and NBCC (India) Ltd. v. Zillion Infraprojects Pvt.

Ltd.9 , the arbitration clause stands validly incorporated by reference into

the Purchase Orders. The jurisdiction clause contained in the Purchase

Orders, which confers jurisdiction on courts at Hyderabad, is not

inconsistent with the GCC, thereby indicating that Hyderabad was

intended to be the juridical seat of arbitration.

7 (2009) 7 SCC 696.

8 (2018) 2 SCC 519.

9 2024 SCC OnLine SC 323.

Page 10 of 21 11.3 Identical issues were examined in proceedings arising out of the

same project with TSPGCL, the successor of the appellant in Telangana

after bifurcation of the State, where this Court appointed a former judge

of this Court as arbitrator after rejecting identical objections to first

respondent’s capacity to invoke arbitration. The objections now raised are

substantially the same and do not warrant reconsideration at the

Section 11 stage; the AT alone is competent to address them.

11.4 The appellant’s assumption that “Contractor” refers only to the

Consortium acting jointly misconstrues the definition. Clause 2.1 of

Invitation to Bid defines ‘Contractor’ in two facets. First, the ‘Person’

whose Tender has been accepted. Second the legal successors in title of

such person. The latter applies when the Consortium ceases to exist. The

Consortium Agreement dated 17.08.2010 at Clause 16(d) states that it

ceases to operate on a party becoming insolvent. This provision is carried

through in the Supplementary Agreements. Therefore, the expiry of the

Consortium Agreement will result in each party being represented by

themselves or their legal successors.

11.5 Even if the Consortium were to be treated as continuing, it has no

independent legal personality under Indian law unless expressly

constituted as such. Reliance is placed on New Horizons Ltd. v. Union of

Page 11 of 21 India10, Dulichand Laxminarayan Firm v. Commissioner of Income Tax,

Nagpur11, and Ramanlal Bhailal Patel v. State of Gujarat 12, which affirm

that a consortium or joint venture, unless incorporated, is neither a juristic

person nor a separate legal entity distinct from its members. Clause 4 of

the Consortium Agreement expressly states that the Consortium is not a

separate legal entity. Hence, the appellant cannot assert that only the

Consortium, as an independent juridical unit, could invoke arbitration.

11.6 The Consortium was a bidding arrangement; members retained

separate scopes of work, distinct performance obligations, and

independent payment streams. Payments were made directly to each

member. The division of work under the Consortium Agreement and the

amended Purchase Orders demonstrates that each member held an

identifiable, severable, and independently enforceable contractual

interest.

11.7 The existence of counterclaims or potential liabilities against first

respondent is irrelevant for the purpose of determining its right to invoke

arbitration. Counterclaims may be raised in the arbitration and adjudicated

together. Appellant, VA Tech has no locus to oppose first respondent’s

10 (1995) 1 SCC 478.

11 (1956) 1 SCC 269.

12 (2008) 5 SCC 449.

Page 12 of 21 independent invocation when its claims arise from its allocated scope of

work and relate to moneys allegedly due to it.

11.8 The appellant’s objections concern the entitlement to invoke

arbitration, not the existence of the arbitration agreement. Such issues fall

squarely within the AT’s jurisdiction under Section 16.

IV. Analysis and Reasoning:

12. The reason for referring to the submissions of the appellants as well

as the respondent in detail is only to flag and highlight certain preliminary

and jurisdictional questions that will fall for consideration before the AT in

the event we hold that the referral court need not examine these questions

in view of Sections 11(6-A) and 16 of the Act, 1996.

13. We must, at the outset, address an important submission advanced

on behalf of the appellants, namely, that in the present case there exists

no arbitration agreement insofar as the individual constituent of a

consortium is concerned. This submission is founded upon certain

decisions of the Delhi High Court 13 and the Bombay High Court 14 which

have taken the view that a member of a consortium, in its individual

capacity, cannot invoke the jurisdiction of the Court under Section 11 of

13 2022 SCC OnLine Del 3253, Consulting Engineers Group Ltd. v. National Highway Authority of India

(NHAI).

14 2019 SCC OnLine Bom 3920, MSEDCL v. Godrej and Boyce Manufacturing Company Ltd.

Page 13 of 21 the Arbitration and Conciliation Act, 1996. The appellants contend that in

the absence of a direct arbitration agreement between the employer and

the individual consortium member, the very assumption of jurisdiction by

the referral court would be impermissible.

14. In our considered view, these objections must be answered in the

broader perspective of the nature and scope of the jurisdiction exercised

by a referral court under Section 11 of the Act. With the introduction of the

statutory restraint under Section 11(6A), the Legislature has consciously

confined the domain of judicial scrutiny to the mere “existence of an

arbitration agreement”. This legislative design is further reinforced by the

express empowerment of the AT under Section 16 to rule on; (i) its own

jurisdiction, (ii) objections with respect to the very existence of the

arbitration agreement, and also, (iii) objections relating to the validity of

such an agreement. The statutory scheme thus envisages a clear

demarcation between the limited threshold scrutiny at the referral stage

on the one hand and the substantive jurisdictional adjudication to be

undertaken by the AT on the other.

15. The legislative policy under the Act 1996 strongly favours minimal

judicial intervention at the pre arbitral stage. A long line of precedents,

Page 14 of 21 such as Duro Felguera SA v Gangavaram Port Ltd15, the Constitution

Bench decision in Interplay Between Arbitration Agreements under

Arbitration and Conciliation Act, 1996 and Stamp Act, 1899, In Re16, and

SBI General Insurance Co Ltd v Krish Spinning Mills Pvt Ltd17 have

authoritatively settled that the enquiry under Section 11 is confined to a

prima facie determination of the existence of an arbitration agreement and

no further. The referral court is required to undertake only a prima facie

determination of the existence of an arbitration agreement 18, and refrain

from entering into contentious factual or legal issues related to authority,

capacity, arbitrability, maintainability, or merits of claims.

16. It is certainly a matter of institutional discipline for the referral courts

to enable “parties” to identify and exercise alternative remedies,

particularly that of arbitration, with clarity and consistency. The question

whether a member of a consortium can itself invoke Section 11 of the Act,

1996 is not one that admits of a monolithic or a uniform answer. Answer

to that question will necessarily depend on enquiry into the terms of the

principal contract, as well as the Consortium Agreement. The specific

terms of the Consortium Agreement, parties to that agreement, and the

15 (2017) 9 SCC 729.

16 (2024) 6 SCC 1.

17 (2024) 12 SCC 1.

18 Goqii Technologies (P) Ltd. v. Sokrati Technologies (P) Ltd., (2025) 2 SCC 192.

Page 15 of 21 nature of the rights and mutual obligations that the agreement creates will

have to be examined in detail. Reference court will, however, confine its

enquiry only to a prima facie satisfaction as to whether a member of a

consortium qualifies as a “party” to the arbitration agreement. This prima

facie satisfaction is sufficient for the referral court to constitute and refer

the dispute to the AT. Thereafter, it is for the AT to undertake the detailed

enquiry as to whether a member of the consortium is in fact a veritable

party to the arbitration agreement or not. This is exactly the limited enquiry

permitted and prescribed in Cox & Kings (supra), the relevant portion of

which is as under:

“126. Evaluating the involvement of the non-signatory party in the negotiation, performance, or termination of a contract is an important factor for a number of reasons. First, by being actively involved in the performance of a contract, a non-signatory may create an appearance that it is a veritable party to the contract containing the arbitration agreement; second, the conduct of the non-signatory may be in harmony with the conduct of the other members of the group, leading the other party to legitimately believe that the non-signatory was a veritable party to the contract; and third, the other party has legitimate reasons to rely on the appearance created by the non-signatory party so as to bind it to the arbitration agreement.

169. In case of joinder of non-signatory parties to an arbitration agreement, the following two scenarios will prominently emerge : first, where a signatory party to an arbitration agreement seeks joinder of a non-signatory party to the arbitration agreement; and second, where a non-signatory party itself seeks invocation of an arbitration agreement. In both the scenarios, the referral court will be required to prima facie rule on the existence of the arbitration agreement and whether the non-signatory is a veritable party to the arbitration agreement. In view of the complexity of such a determination, the referral court should leave it for the Arbitral Tribunal to decide whether the non-signatory party is indeed a party to the arbitration agreement on the basis of the factual evidence and application of legal doctrine.

The Tribunal can delve into the factual, circumstantial, and legal

Page 16 of 21 aspects of the matter to decide whether its jurisdiction extends to the non-signatory party. In the process, the Tribunal should comply with the requirements of principles of natural justice such as giving opportunity to the non-signatory to raise objections with regard to the jurisdiction of the Arbitral Tribunal. This interpretation also gives true effect to the doctrine of competence-competence by leaving the issue of determination of true parties to an arbitration agreement to be decided by the Arbitral Tribunal under Section 16.

170.12. At the referral stage, the referral court should leave it for the Arbitral Tribunal to decide whether the non-signatory is bound by the arbitration agreement.” (emphasis supplied)

17. Beyond the prima facie enquiry, it should be the discipline of the

referral court to refrain from undertaking a detailed enquiry on basis of

evidence to arrive at a finding of fact in the nature of a ‘proof’. The scope

of such an enquiry, by virtue of Section 11(6-A) is very well articulated in

the decision of this Court in Interplay Between Arbitration Agreements

under Arbitration and Conciliation Act, 1996 and Stamp Act, 1899, In Re19

wherein this Court observed:

“165. The legislature confined the scope of reference under Section 11(6-A) to the examination of the existence of an arbitration agreement. The use of the term “examination” in itself connotes that the scope of the power is limited to a prima facie determination. Since the Arbitration Act is a self-contained code, the requirement of “existence” of an arbitration agreement draws effect from Section 7 of the Arbitration Act. In Duro Felguera [Duro Felguera, S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC (Civ) 764], this Court held that the Referral Courts only need to consider one aspect to determine the existence of an arbitration agreement — whether the underlying contract contains an arbitration agreement which provides for arbitration pertaining to the disputes which have arisen between the parties to the agreement. Therefore, the scope of examination under Section 11(6-A) should be confined to the existence of an arbitration agreement on the basis of Section 7. Similarly, the validity of an arbitration agreement, in view of Section 7,

19 (2024) 6 SCC 1.

Page 17 of 21

should be restricted to the requirement of formal validity such as the requirement that the agreement be in writing. This interpretation also gives true effect to the doctrine of competence-competence by leaving the issue of substantive existence and validity of an arbitration agreement to be decided by Arbitral Tribunal under Section 16. We accordingly clarify the position of law laid down in Vidya Drolia [Vidya Drolia v. Durga Trading Corpn., (2021) 2 SCC 1 : (2021) 1 SCC (Civ) 549] in the context of Section 8 and Section 11 of the Arbitration Act.

166. The burden of proving the existence of arbitration agreement generally lies on the party seeking to rely on such agreement. In jurisdictions such as India, which accept the doctrine of competence- competence, only prima facie proof of the existence of an arbitration agreement must be adduced before the Referral Court. The Referral Court is not the appropriate forum to conduct a mini-trial by allowing the parties to adduce the evidence in regard to the existence or validity of an arbitration agreement. The determination of the existence and validity of an arbitration agreement on the basis of evidence ought to be left to the Arbitral Tribunal. This position of law can also be gauged from the plain language of the statute.

167. Section 11(6-A) uses the expression “examination of the existence of an arbitration agreement”. The purport of using the word “examination” connotes that the legislature intends that the Referral Court has to inspect or scrutinise the dealings between the parties for the existence of an arbitration agreement. Moreover, the expression “examination” does not connote or imply a laborious or contested inquiry. [P. Ramanatha Aiyar, The Law Lexicon (2nd Edn., 1997) 666.] On the other hand, Section 16 provides that the Arbitral Tribunal can “rule” on its jurisdiction, including the existence and validity of an arbitration agreement. A “ruling” connotes adjudication of disputes after admitting evidence from the parties. Therefore, it is evident that the Referral Court is only required to examine the existence of arbitration agreements, whereas the Arbitral Tribunal ought to rule on its jurisdiction, including the issues pertaining to the existence and validity of an arbitration agreement. A similar view was adopted by this Court in Shin-Etsu Chemical Co. Ltd. v. Aksh Optifibre Ltd. (2005) 7 SCC 234.”

18. Following this Court’s mandate in the above decision, this Court in

Managing Director Bihar State Food and Civil Supply Corporation Limited

Page 18 of 21 v. Sanjay Kumar20 explaining the contemporary legal position of the

referral court emphasised that:

“27. The curtains have fallen. Courts exercising jurisdictions under Section 11(6) and Section 8 must follow the mandate of sub-section (6A), as interpreted and mandated by the decisions of this Court and their scrutiny must be “confine(d) to the examination of the existence of the arbitration agreement”.”

19. Once the High Court was satisfied that an arbitration agreement

prima facie existed, an aspect neither seriously disputed nor refutable at

this stage, its decision to constitute the AT cannot be faulted. In the earlier

part of our judgment, we have reproduced the detailed arguments of the

appellants and respondents on the issue of maintainability only to draw a

distinction between a prima facie consideration of such contentions for the

purpose of Section 11 on the one hand and for a detailed examination by

the AT. While we hold that there is certainly a prima facie case for referring

the dispute to arbitration under Section 11, a detailed scrutiny on the basis

of evidence must be left to AT. Whether first respondent has validly

invoked arbitration individually, whether the Consortium continues to

exist, whether consent of other Consortium partners was necessary, and

whether claims are maintainable after commencement of liquidation, are

all matters which may legitimately be raised, contested and determined

before the AT under Section 16. Entertaining these questions here would

20 2025 SCC OnLine SC 1604: 2025 INSC 933.

Page 19 of 21 amount to conducting a mini trial at the Section 11 stage, contrary to the

settled principles of minimal judicial intervention and kompetenz-

kompetenz.

20. Returning to facts of the present case, it is significant to note that

with respect to the very same underlying contractual framework that was

bifurcated after the formation of the States of Andhra Pradesh and

Telangana, this Court21 by its order dated 29.11.2021 constituted the AT

and referred the dispute for detailed consideration, of all issues to an AT.

The relevant portion of the reference order is as under;

“Without going into the question whether the reasoning which weighed with the High Court was correct or not, in our view, the ends of justice would be met if there be comprehensive arbitral proceedings before a sole Arbitrator which would encompass claims arising out of the agreement amongst members of Consortium consisting of (a) M/s Tecpro Systems Limited, (b) M/s Gammon India Ltd and (c) M/s VA Tech Wabag Ltd. and the claims arising pursuant to letter of Intent dated 13.10.2010.

It is therefore directed that:

(a) A sole arbitrator shall consider all the claims arising out of both the agreements.

(b) Mr. Justice M. B. Lokur, former Judge of this court shall be the sole arbitrator.

(c) M/s Telangana State Power Generation Corporation Limited, M/s Tecpro Systems Limited, M/s VA Tech Wabag Ltd and M/s Gammon Engineers & Contractors Pvt. Ltd. shall be parties to the arbitration.

(d) Let a claim statement be filed by M/s Tecpro Systems Ltd. within 15 days from today before the learned Arbitrator.

21 In Civil Appeal Nos.7119 of 2021 and 7120 of 2021.

Page 20 of 21

(e) M/s Telangana State Power Generation Corporation Ltd. and other members of the Consortium shall be entitled to put in their counter statement/response and/or raise fresh claim/counter claims, if any.

(f) The parties shall appear before the learned Arbitrator on such date as the learned Arbitrator may choose. A communication in that behalf shall be sent to the learned Arbitrator by the Registry of this Court immediately alongwith a copy of this order.

The afore-stated directions are in substitution of the directions issued by the High Court.

All the appeals are disposed of accordingly. No costs.”

It is also an admitted fact that the AT thereafter examined the issue as to

whether the applicant is a veritable party or not.

V. Conclusion:

21. Having considered the matter in detail, we are of the opinion that the

High Court has not committed any error in constituting the AT in exercise

of its powers under Sections 11(6) and 11(6-A) of the Act, 1996. The AT

will consider all questions including preliminary objections relating to

maintainability of the arbitration on their own merit.

22. Civil Appeals, arising out of order dated 17.02.2023 passed by the

High Court are accordingly dismissed. No order as to costs.

………………………………....J. [PAMIDIGHANTAM SRI NARASIMHA]

………………………………....J. [ATUL S. CHANDURKAR] NEW DELHI;

DECEMBER 17, 2025

Page 21 of 21

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free