Miss Lucy
← All judgments

M/S Abci Infrastructures Pvt Ltd vs Union Of India

Supreme Court14 February 2025Sanjay Kumar

Ratio decidendi

The rule this decision rests on

Where a bidder in a public contract makes a material mistake of fact in the bid that is patent, self-evident, and undisputed, and the bidder acts promptly upon discovery of the mistake to inform the authority and request withdrawal before a formal contract is entered into, equitable relief may be granted to permit withdrawal of the bid, provided the mistake could not have been avoided by the exercise of ordinary care on the part of the bidder and the offeree authority did not have knowledge of the mistake. Where a public authority, aware of a patent error in a bid that is self-evident and mathematically impossible given the nature and scale of the work tendered, adopts an obdurate and overly legalistic stance by demanding justification of the bid rather than permitting withdrawal, and thereafter declares the bidder a defaulter and forfeits the bid security, such conduct is disproportionate and inequitable, particularly where the authority itself contributes to project delays through its refusal to acknowledge the genuine error and its unwarranted cancellation of the bidding process. Where a bidder has made a genuine mistake in submitting a bid and has promptly notified the authority of the error, the authority's subsequent demand for forfeiture of the entire bid security as a consequence of that mistake is disproportionate to the fault committed, and relief may be granted by requiring only a reasonable monetary payment in lieu of forfeiture of the full security deposit.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2025 INSC 215 REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. OF 2025 (Arising out of Special Leave Petition (Civil) No. 25394 of 2023)

M/S. ABCI INFRASTRUCTURES PVT. LTD. ..... APPELLANT

VERSUS

UNION OF INDIA AND OTHERS ..... RESPONDENTS

JUDGMENT

SANJIV KHANNA, CJI.

Leave granted.

2. This is an avoidable litigation. No doubt, there was a mistake on the part

of the Appellant – M/s ABCI Infrastructure Private Limited, albeit,

instead of taking a pragmatic approach, Respondent No. 2 - Border Signature Not Verified Digitally signed by babita pandey Date: 2025.02.14 16:33:26 IST Reason: Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 1 of 12 Road Organisation1 under the Ministry of Defence, Union of India,

adopted an obdurate and overly legalistic stance, causing a delay in the

project's execution.

3. We begin by briefly discussing the facts of the case:

o On 23.02.2023, BRO invited bids for the design and construction

of two-lane twin tunnels, approximately 4.1 kilometres long, at

Shinkun La Pass, including civil, electrical, and mechanical work,

with approaches connecting the Darcha-Padam Highway to

NHDL specifications in Himachal Pradesh and Ladakh. The

estimated cost of the project was Rs.15,04,64,00,000/- (Rs.

1,504.64 crores). The project was to be completed within 48

months. The bid security amount was Rs.15,04,64,000/- (Rs.

15.04 crores)

o Ten bidders, including the Appellant, had submitted their online

Technical and Financial Bids on 03.06.2023. The Appellant, like

others, had furnished a bank guarantee of Rs.15,04,64,000/-.

o On 05.06.2023, technical bids were opened and seven bidders,

including the Appellant, were declared technically qualified.

o On 24.08.2023, the financial bids of seven bidders, including the

Appellant, were opened and the results were declared.

1 Hereinafter, “BRO.”

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 2 of 12 o The Appellant was ranked as L-1 bidder, with the bid price of

Rs.1,569/- (Rupees One thousand five hundred and sixty-nine

only). According to the Appellant, they had quoted a bid price of

Rs.1,569 crores. However, due to what they claim was a system

error, the quoted amount appeared as just Rs.1,569.

o The Appellant claims that they discovered the mistake on

24.08.2023 when the financial bids were opened and announced,

and therefore, on the next day, 25.08.2023, they informed the

authorities that their actual bid was Rs.1,569 crores, not

Rs.1,569. They attributed the error to a typographical mistake or

a critical technical issue with the server. While we would not

accept the plea of system error, the figure quoted was clearly

unrealistic, a patent error and a mistake given the scale and

nature of the work tendered. Though the mistake was bald-faced,

what followed is incomprehensible, with BRO, insisting on

accepting the bid, in spite of letters from the Appellant wanting to

withdraw from the tender.

o BRO, guided by the Evaluation Committee, instead of accepting

the obvious, vide letter dated 26.08.2023, called upon the

Appellant to justify the quoted amount of Rs.1,569 by providing a

detailed price analysis, including the scope of work, completion

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 3 of 12 schedule, risk allocation, safety requirements, and proof of

capability to complete the project, by 31.08.2023.

o On 30.08.2023, the Appellant reiterated that their intended bid

was Rs.1,569 crores, not Rs.1,569, attributing the error to a

technical or typographical mistake.

o On 07.09.2023, the Appellant sent another letter stating they

should not be considered the L1 bidder, and the bank guarantee

of Rs.15,04,64,000 may be returned to them without encashment.

o On 12.09.2023, the Appellant again wrote emphasizing that the

bid was an error and that the bid security should not be forfeited.

o Vide letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s

bank, the State Bank of India, stating that the Appellant had been

declared a defaulter, and their bid security was to be forfeited.

The bank was asked to encash the bank guarantee and remit

Rs.15,04,64,000 to BRO.

o The Appellant filed a writ petition before the High Court of

Himachal Pradesh at Shimla, which stands dismissed by the

impugned judgment dated 07.10.2023.

4. The short question before us is whether BRO was justified in accepting

the bid of Rs.1,569, and on the failure of the Appellant to execute the

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 4 of 12 agreement asking for forfeiture vide encashment of bank guarantee of

Rs.15,04,64,000.

5. A mistake may be unilateral or mutual, but it is always unintentional. If it

is intentional, it ceases to be a mistake. Mistakes or errors, though

avoidable, are committed inadvertently. They have varied

consequences in law. As per Section 20 of the Indian Contract Act,

18722 whereby both parties to an agreement are under a mistake as to

matter of fact essential to an agreement, the agreement is void. The

explanation to Section 20 says that an erroneous opinion as to the

value of the thing which forms the subject matter of an agreement is not

deemed to be a mistake as a matter of fact. This will not be a case

covered by Section 20 of the Contract Act. However, this is not the first

time that this question has arisen either before this Court or Courts

outside of India. In West Bengal State Electricity Board v. Patel

Engineering Company Limited and Others3, this Court referred to

paragraph 84 of American Jurisprudence (2nd Edition, Volume 64 at

page 944), which reads:

“As a general rule, equitable relief will be granted to a bidder for a public contract where he has made a material mistake of fact in the bid which he submitted, and where, upon the discovery of that mistake, he acts promptly in informing the public authorities and requesting withdrawal 2 Hereinafter, “Contract Act.” 3 (2001) 2 SCC 451.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 5 of 12

of his bid or opportunity to rectify his mistake particularly when he does so before any formal contract is entered into.”

6. Thereafter, reference was made to two decisions of the Supreme Court

of the United States in Moffett, H. and C. Co. v. Rochester4 and

Hearne v. New England Marine Ins. Co.5 wherein it is observed that

where the mistake is apparent and the party promptly informs the other

as soon as it is discovered but before entering into a contract, equitable

orders may be passed. However, the mistake should be clear, explicit,

and undisputed. Further, a mistake on one side may be a ground for

rescinding but not for reforming a contract where the minds of the

parties have not met, yet there is no contract and hence none to be

rectified. Relief may not be granted where it is inequitable. While

accepting this legal position, this Court in West Bengal State

Electricity Board (supra) has propounded the following exceptions to

the general principle on a person seeking relief in equity on account of

mistake:

“ 27. ……..

(1)Where the mistake might have been avoided by the exercise of ordinary care and diligence on the part of the bidder; but where the offeree of the bid has or is deemed to have knowledge of the mistake, he cannot be permitted to take advantage of such a mistake.

4 178 U.S. 373 (1900).

5 22 L. Ed. 395.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 6 of 12 (2) Where the bidder on discovery of the mistake fails to act promptly in informing to the authority concerned and request for rectification, withdrawal or cancellation of bid on the ground of clerical mistake is not made before opening of all the bids.

(3) Where the bidder fails to follow the rules and regulations set forth in the advertisement for bids as to the time when bidders may withdraw their offer; however where the mistake is discovered after opening of bids, the bidder may be permitted to withdraw the bid.”

7. This judgment also refers to a decision of the Superior Court of New

Jersey in Spina Asphalt Paving Excavating Contractors, Inc. v.

Borough of Fairview.6 The said case is related to the rectification of

mistakes in the bid specifications. Relief granted in the said case was

upheld by the Superior Court with the caution that generally an error in

the statement of a price would not be treated as immaterial and it is only

when the case of error was patent and the true intent of the bidder

obvious that such an error might be disregarded.

8. In West Bengal State Electricity Board (supra), the private party, the

bidder did not succeed for several reasons, including the factum that the

error was not obvious and self-evident. Further, the correction of such

mistakes after one and a half months after the opening of the bids

would have violated the express clauses relating to the computation of

6 304 NJ Super 425.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 7 of 12 the bid amount. Thus, waiver of the rule or conditions in favour of the

one bidder would have created unjustifiable doubts in the minds of

others impairing the rule of transparency and fairness and providing

room for manipulation for awarding contracts.

9. The decision in West Bengal State Electricity Board (supra) was

referred to and followed where a relief to the bidder was apparent

before this Court in M/s Omsairam Steels & Alloys Pvt. Ltd. v.

Director of Mines and Geology, BBSR & Ors.7 This decision observes

that while the Court must exercise a lot of restraint in exercising the

power of judicial review in contractual commercial matters, the doctrine

of proportionality nevertheless applies when the error or mistake is writ

large and equity merits the grant of some relief. Reference was made

to the decision in Coimbatore District Central Cooperative Bank v.

Coimbatore District Central Cooperative Bank Employees

Association and Another8 where discussing the question of

proportionality or punishment imposed on the striking workmen it is

observed:

“18. “Proportionality” is a principle where the court is concerned with the process, method or manner in which the decision-maker has ordered his priorities, reached a conclusion or arrived at a decision. The very essence of decision-making consists in the attribution of relative importance to the factors and considerations in the 7 2024 INSC 520.

8 (2007) 4 SCC 669.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 8 of 12

case. The doctrine of proportionality thus steps in focus true nature of exercise—the elaboration of a rule of permissible priorities.

19. de Smith states that “proportionality” involves “balancing test” and “necessity test”. Whereas the former (balancing test) permits scrutiny of excessive onerous penalties or infringement of rights or interests and a manifest imbalance of relevant considerations, the latter (necessity test) requires infringement of human rights to the least restrictive alternative. [Judicial Review of Administrative Action (1995), pp. 601-05, para 13.085; see also Wade & Forsyth: Administrative Law (2005), p. 366.]

20. In Halsbury's Laws of England (4th Edn.), Reissue, Vol. 1(1), pp. 144-45, para 78, it is stated:

“The court will quash exercise of discretionary powers in which there is no reasonable relationship between the objective which is sought to be achieved and the means used to that end, or where punishments imposed by administrative bodies or inferior courts are wholly out of proportion to the relevant misconduct. The principle of proportionality is well established in European law, and will be applied by English courts where European law is enforceable in the domestic courts.

The principle of proportionality is still at a stage of development in English law; lack of proportionality is not usually treated as a separate ground for review in English law, but is regarded as one indication of manifest unreasonableness.”

Accordingly, in the said case the Appellant was directed to make

a payment of Rs.3 crores within the stipulated period and on the said

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 9 of 12 payment the security deposit in the form of a bank guarantee of over

Rs.9 crores was directed to be refunded.

10. The present case does not fall under any exception, for the error or

mistake in quoting a price of Rs.1,569/-, does not require any argument

and cannot be debated as it is self-evident. A contract of this nature for

an estimated value of more than Rs.1,500 crores spread over 48

months requiring construction of roads and tunnels of the length of more

than 4 kilometres in a hilly terrain can never be executed for a mere

Rs.1,569/-.

11. At the same time, we agree with BRO, that the Appellant was at fault

and had made the mistake, of having failed to add the required zeros in

the financial bid. The plea of a system glitch should not be accepted, as

others had successfully uploaded their bids without a problem.

12. BRO justified encashing the bank guarantee by citing delays caused by

issuing a second notice inviting bids. This claim is baseless, as BRO

was aware of the Rs.1,569/- error. Instead of declaring the bid non est

due to the clear mistake, BRO asked the appellant to justify the bid,

cancelled the notice, declared the Appellant a defaulter, invoked the

bank guarantee, and issued a fresh notice inviting bids.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 10 of 12

13. Thus, BRO’s claim that the delay was entirely due to the Appellant’s

mistake is flawed, ignoring BRO’s own lapses. Mistakes, including by

authorities, should be resolved through corrective steps. A practical

approach could have avoided the delay, which was caused by BRO’s

refusal to acknowledge the Appellant’s genuine error and the

unwarranted cancellation of the bid.

14. The alleged two-month delay by the Appellant is incorrect. The error,

submitted on 03.06.2023, became apparent only when financial bids

were opened on 24.08.2023. The Appellant promptly acknowledged the

mistake on 25.08.2023.

15. A fresh tender was issued, and financial bids opened on 09.01.2024

revealed the lowest bid of Rs.1,290 crores, lower than the earlier

Rs.1,351 crores. Thus, while delayed, the contract was awarded at a

lower cost.

16. In view of the aforesaid discussion, we direct the Appellant to pay Rs.1

crore to BRO, as a consequence of their error. Upon receiving this

payment, BRO shall return the Appellant’s original bank guarantee or

demand draft of Rs.15.04 crores within one week.

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 11 of 12

17. The impugned judgment is set aside, and the appeal is allowed in the

aforesaid terms. There would be no order as to costs.

......................................CJI.

(SANJIV KHANNA)

…......................................J. (SANJAY KUMAR)

…......................................J. (K.V. VISWANATHAN)

NEW DELHI;

FEBRUARY 14, 2025

Civil Appeal a/o. SLP (C) No. 25394 of 2023 Page 12 of 12

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free