M.P. Power Management Company Limited, Jabalpur vs M/S Sky Power Southeast Solar India Private Limited & Others
- SCC(2023) 2 SCC 703
- Neutral2022 INSC 1206
- SCR[2022] 8 SCR 800
Ratio decidendi
The rule this decision rests on
A contract entered into by a State instrumentality (as defined under Article 12 of the Constitution) that incorporates terms derived from bidding guidelines issued under Section 63 of the Electricity Act, 2003 does not become a statutory contract merely by virtue of such incorporation; a contract becomes statutory only if the statute mandates that prescribed terms and conditions be incorporated as an indispensable part of the contract, or if the terms themselves are statutory in character providing for rights and obligations of the contracting parties derived from statute. The evolution of Indian constitutional law has moved beyond the position established in Radhakrishna Agarwal v. State of Bihar that a writ petition is not maintainable to challenge breach of a non-statutory contract by the State; a State instrumentality acting in a contractual matter remains subject to Article 14 of the Constitution, and judicial review on the ground of arbitrary action is maintainable even where the contract is not statutory, provided the action is shown to be palpably unreasonable, uninformed by reason, or bereft of principle. Judicial review of State action in contractual matters post-contract entry is permissible where: (1) the action infringes principles of natural justice; (2) the action is demonstrably arbitrary or lacks rational basis; (3) the case involves a public law element flowing from the impact of the decision on public interest (though public interest cannot be determined by reference to monetary gain or loss alone, or by post-contract changes in market rates); (4) the writ remedy provides an effective and fair means of preventing injustice from palpably unreasonable State action; and (5) the matter does not involve genuinely disputed questions of fact requiring oral evidence, though documentary interpretation may be entertained. A default notice under a contractual provision requiring pre-termination notice must satisfy the substantive requirements of the provision itself; where a contract provides for a default notice giving the defaulting party an opportunity to cure within a specified period before termination, a notice addressing a different default or issued before the relevant contractual event occurs cannot be treated as compliance with the contractual mandate, and the subsequent termination notice issued without strict adherence to the prescribed procedure will be arbitrary. Where a contractual term prescribes a mandatory procedure for termination (such as issuing a default notice and allowing a cure period) before exercising a right of termination, failure to follow that procedure constitutes arbitrary action violating Article 14, particularly where: (1) the default could have been remedied within the prescribed period; (2) the prior termination attempt was itself found to be illegal; and (3) the subsequent termination attempts to resurrect claims that had attained finality in prior judicial proceedings. An earlier judgment setting aside a termination order and granting liberty to take fresh action "in accordance with law" operates as a bar to the party taking fresh action on the same or overlapping grounds that were adjudicated in the earlier proceeding, unless the fresh action strictly complies with the contractual procedures mandated by the PPA and does not seek to revisit matters already decided on merits. The existence of an alternate remedy (such as civil suit or arbitration) is a discretionary factor in deciding whether to entertain a writ petition in contractual matters, not an absolute bar; the court's discretion depends on: (1) whether disputed questions of fact are central to the relief sought; (2) whether the issue can be resolved on documentary evidence alone; (3) whether the case involves a public law element; and (4) whether the writ remedy provides effective redress where the alternate remedy would not. Where a State-instrumentality is party to a contract involving large-scale investment, substantial public interest (such as renewable energy generation), and where the contract expressly provides procedural safeguards (such as default notices and cure periods) before termination, failure to observe those procedures constitutes arbitrary action notwithstanding that the right to terminate may exist in theory, because such failure deprives the other contracting party of a meaningful opportunity to perform and prevents the court from fulfilling its constitutional duty to prevent arbitrary State action. The concept of "overwhelming public interest" justifying non-interference by the writ court with State action in contractual matters applies principally at the stage of contract award (to prevent wasteful expenditure or ensure fairness in competitive bidding), not equally at the stage of contract performance or termination; when a contract has been entered into following competitive bidding at determined rates, subsequent market changes or cheaper availability of similar goods/services do not constitute public interest warranting deprivation of the contractor's vested rights, and reliance on such changed circumstances to justify termination without following contractual procedures amounts to arbitrary action.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.__________________OF 2022 (Arising out of SLP (C) Nos.4609-4610 OF 2021)
M.P. POWER MANAGEMENT COMPANY LIMITED, JABALPUR …APPELLANT(S)
Versus
M/S. SKY POWER SOUTHEAST SOLAR INDIA PRIVATE LIMITED & OTHERS …RESPONDENTS(S)
JUDGMENT
K.M. JOSEPH, J.
1. Leave granted.
2. The appellant impugns the Judgment of the High
Court dated 27.02.2020 in Writ Petition No. 420 of
2019. It further challenges the Order dated 28.12.2020
in Review Petition No. 682 of 2020. By the said Judgment
in the Writ Petition, the High Court allowed the Writ
Petition filed by the first respondent and quashed the Signature Not Verified Digitally signed by Jagdish Kumar Date: 2022.11.16
Order 17:24:39 IST Reason: dated 07.07.2018, which was passed by the
appellant, terminating the Power Purchase Agreement 1 (hereinafter referred to as ‘the PPA’, for short),
which was entered into by the appellant and the first
respondent. The review filed by the appellant was
dismissed. Hence the appeals.
THE FACTS
3. The appellant, which is “a wholly owned company of
the Government of Madhya Pradesh” (as described by the
appellant in the Special Leave Petition), is
responsible for the bulk purchase of electricity in the
State of Madhya Pradesh for onward sale/supply to the
distribution utilities (DISCOMS). The appellant issued
a request for proposal (RFP) dated 06.05.2015 for long-
term procurement of 300 MW of solar energy through
tariff-based competitive bidding. The bid of M/s Sky
Power Southeast Asia Holding Limited was accepted. It
was declared the successful bidder for three units of
50 MW each at different tariff rates. The bidder
subsequently incorporated the first respondent, viz.,
M/s Sky Power Southeast Solar India Private Limited as
a special purpose company. This was for developing one
project of 50 MW. The rate, which is applicable in
2 respect of the first respondent, was Rs.5.109 per unit.
In respect of the other two bids, the bidder
incorporated other companies, viz., M/s Sky Power Solar
India Private Limited and M/s Sky Power Southeast Asia
One Private Limited. The rates applicable in respect
of said companies for the other two projects consisting
of 50 MW each was Rs.5.298 per unit and Rs.5.051 per
unit, respectively. The PPA was entered into on
18.09.2015. The agreement, inter alia, provided for
pre-commissioning activities. They are described as
satisfaction of conditions subsequent by the seller.
The first respondent is the seller under the PPA.
4. The Agreement contemplated completion of the
conditions subsequent, within a period of 210 days. In
other words, the Agreement, admittedly, provided that
the first respondent was to achieve fulfilment of
conditions subsequent by 15.04.2016. The Agreement
further contemplates an extension of the period of
fulfilment of the condition subsequent on payment of
penalty for a further period of nine months. Thus,
calculating 210 days and an additional nine months from
18.09.2015, which is the date of the PPA, the period
3 would come to an end on 15.01.2017. A communication was
addressed dated 12.01.2017 by the first respondent. The
first respondent purported to refer to Article 2.1 of
the PPA, which, inter alia, reads as follows:
“Article 2.1 Seller agrees and undertaken to duly perform and complete all of the following activities seller's own cost and risk within 210 days from the effective Date unless such completion is affected by any force Majeure event, or if any of the Effective is specifically waived in writing by MPPMCL:
a) The Seller shall obtain all Consents, Clearance and Permits required for supply of Power to MPPMCL as per the terms of this Agreement;”
5. The first respondent purported to present certain
documents and contend that there was compliance of its
obligations under the PPA. This led to communication
dated 22.02.2017 addressed by the appellant to the
first respondent. It referred to the status of the
documents, which the appellant noted. Furthermore,
appellant sought certain documents. It is, inter alia,
pointed out by the appellant that the first respondent
had no documents in regard to 34.12 hectare of land and
an unregistered lease deed for only 12 months was
submitted, which could not be considered as fulfilment
4 of the condition subsequent. Thereafter, it was stated
that the PPA is liable to be terminated in terms of
Article 2.5.1 of the PPA. Explanation/justification if
any was called for from the first respondent. Acting
on the request of the first respondent, the appellant
granted time for response of the first respondent till
10.03.2017. The response, which was given on
10.03.2017, reads as follows:
“Firstly, we are thrilled to update you that the project is under advanced construction and all equipment order for the project have been placed and construction happening on site we expect that the project will be top quality using the best equipment in the market and constructed by a top-tier EPC, for the benefit of both Sky Power and the state of MP.
1. Satisfaction of Condition subsequent regarding Construction Financing
MPPMCL Comment: "Loan sanction letter of Mis L&T Finance vide letter No. S07201A03/16-17 DATED 29.08.2016 Copy of facility agreement and affecting compliance documents as stated in above letters are required to be submitted"
SKY POWER comment: reference is made to paragraph 2.1.1.(b) of the PPA, reproduced below:
Sd/-
D.G.M. (Commerical-3) R.0. MPMCL, Bhopal”
5
6. Thereafter, the first respondent sent
communication dated 14.03.2017. It reads as follows:
“SKY POWER GLOBAL
March 14, 2017 To, The Managing Director MP Power Management Company Limited Bittan Market, Bhopal-462016
Attention: Chief General Manager Commercial, MPPMC, Jabalpur.
Ref: Submission of Documents to MP Power Management Company limited ("MPPMCL") for fulfilment of Conditions subsequent by SkyPower southeast solar India private Limited ("Sky Power")
Reference: 1. Sky Poer Letter dated 10 March 2017,
2. Sky Power Letter SKP2/MP/SOLAR MPPMCL/2015- 16/06 dated 12 Jan 2017
3. Agreement (PPA) dated September 18, 2015 between MPPMCL and Skypower
Dear Sir,
Further to our office letter dated 10 March 2017 & skyP2/MP/SOLAR/MPPMCL/2015-16/06 dated 12 Jan 2017 we hereby submit that we have completed the entire acquisition for land 29, 85 Acres including balance 87.S Acres of land parcels.
The relevant land registration documents have been enclosed for your perusal
6 We hereby submit that we have duly completed land registration for 249,85 Acer for the project
Thanking you in anticipation.
MIS SKYPOWER SOUTHEAST SOLAR INDIA PRIVATE LIMITED
Sd/- Shivani Jhariya (Authorized Signatory)
Sd/-
D.G.M. (Commerical-3) R.O. MPMCL, Bhopal”
7. After a gap of nearly five months, the next date,
which is invoked by the appellant, is 09.08.2017. It
is the case of the appellant that as the first
respondent had failed to comply with the conditions
subsequent, by misrepresentation and manipulation, it
purported to obtain approval from the Chief Electrical
Inspector General (CEIG) under Regulation 32 of the
Central Electricity Authority (Measures relating to
safety and electricity supply) Regulation, 2010 read
with Section 162 of the Act. According to the
appellant, the Report of the CEIG came to the knowledge
of the appellant on 20.08.2017. Prior to the said date,
the appellant purported to terminate the PPA in terms
of Article 2.5.1(d) of the PPA, considering it to be
7 mandatory by communication dated 11.08.2017. In short,
according to the appellant, as the maximum period,
within which, the conditions subsequent, had to be
fulfilled, had run out on 15.01.2017, under the PPA,
the appellant had no other option but to terminate the
Agreement. This led to the first Writ Petition filed
by the first respondent. The said Writ Petition, viz.,
Writ Petition No. 12880 of 2017, came to be allowed by
the High Court by Judgment dated 20.06.2018. The
relevant portion of the Judgment reads as follows:
“2. The contract has been terminated on account of 54 days delay in achieving the first milestone i.e., procurement of land, financial closure and necessary permissions from the competent authority within 2 I 0 days from the date of execution of agreement for completing the first part of the project. The only reason to terminate the agreement is that the petitioner has failed to achieve first milestone within 210 days though the condition of - procurement of land was modified after 210 days on 20.04.2016. The delay in achieving the first milestone is visited with penalty in terms of Clause 2.5. of the agreement.
3. Similar communication terminating the contract was set aside by this Court in Writ Petition No.12432/2017 (Renew Clean Energy Private Limited vs M.P. Power Management Company Limited and another) vide order dated 18.08.2017. In the said petition, the petitioner has admittedly commissioned the
8 power project within the time prescribed except that there was delay of 16 days in achieving the first milestone. The said order has been affirmed on 05.04.2018 by the Hon'ble Supreme Court in Civil Appeal No.3600/2018 (M.P. Power Management Company Limited vs Renew Clean Energy Private Limited and another).
4. The parties are not ad idem about the stage of commissioning of the power project in the present petition.
5. Mr. Kaurav sought to justify the termination of the Power Purchase Agreement (PPA) asserting that the petitioner has not commissioned the power project within the time fixed in the agreement, but the lack of commissioning of power project is not the reason for terminating of the contract. Since, such is not the reason mentioned in the order terminating the agreement, therefore, the respondents cannot supplement the reasons for termination of the contract by virtue of additional assertions in the return and/or in the arguments raised in view of the Supreme Court decision in Mohinder Singh Gill v. Chief Election Commissioner (1978) 1 SCC 405.
6. In view of the fact that the similar reason of termination of the agreement has not been found to be justified in the matter of Renew Clean Energy Private Limited (supra), therefore, the impugned communication dated 11.08.2017 is hereby set aside. However, liberty is granted to the respondents to pass fresh orders in terms of Power · Purchase Agreement dated 18th September, 2015 in accordance with law.”
8. On 07.07.2018, the appellant issued the fresh
termination notice. This came to be challenged by the
9 first respondent by Writ Petition No. 420 of 2019.
After exchange of pleadings, by the first impugned
judgment dated 27.02.2020, the High Court set aside the
termination order. Thereafter the appellant in
September, 2020 filed review petition which came to be
dismissed by the second impugned order. On 15.04.2021
this court issued notice and stayed the impugned
orders.
9. We have heard Mr. K.M. Natraj, learned Additional
Solicitor General on behalf of the appellant and
Dr. A.M. Singhvi, learned Senior Counsel along with Mr.
Naman Nagrath, learned Senior Counsel on behalf of the
first respondent. We also heard Shri V. Giri, learned
Senior Counsel appearing for the fifth respondent
(Madhya Pradesh State Load Despatch Centre).
10. Shri K.M. Natraj, learned Additional Solicitor
General submits that the impugned judgments are clearly
unsustainable. He would firstly point out that the writ
petition filed by the first respondent is not
maintainable. The PPA in question is not a statutory
contract and therefore interference with the order
terminating the contract was not justifiable. In this
10 regard he drew support from the judgment of this Court
in Kerala State Electricity Board and Another v. Kurien
E. Kalathil and Others1. He would next contend that
the PPA contemplated provisions to resolve disputes.
He further contended that first respondent should have
resorted, if at all, to a civil suit to claim redress.
He pointed out that a writ petition is a public law
remedy. The contract in question not being statutory
in nature, there was no public law element so as to
justify the approach under Article 226. He would next
contend that there is no basis for the High Court to
have interfered at all. This is a case where broadly
the contract contemplated fulfilment of conditions at
two stages. The first stage related to various
conditions that had to be fulfilled by the first
respondent which are described as conditions subsequent
in the PPA. They are also aptly described as the pre-
commissioning stage. The PPA clearly contemplated
fulfilment of these conditions on an indisputable basis
on or before 15.01.2017. In arriving at this date, the
maximum period of 9 months contemplated under the PPA
1 (2000) 6 SCC 293 11 as the period which can be extended on payment of
penalty is also included. However, the first respondent
did not fulfil the conditions subsequent except with a
further delay of 56 days. The PPA clearly provides that
if the time limit is exceeded which in this case was
15.01.2017, the appellant shall terminate the contract.
This is not a question of power or a discretion. This
is a right which inhered with the appellant, a party
to a contract. In this regard he would emphasise that
while the State may be burdened with the obligation to
act in a fair manner, it does not take away the rights
available to the State as a party to a contract to
exercise the right with it under the contract. In other
words, the appellant as State within the meaning of
Article 12 should not be denied the very right which
could be duly exercised by a private party if it stood
in the shoes of the appellant in similar circumstances.
This is all that has been done by the appellant. Coming
to the second stage, namely, commissioning of the
project by the first respondent, our attention was
drawn to Article 2.6 of the PPA. He contended that
agreement contemplated commissioning of plant within
12 12 months from the date of the financial closure
subject to Force Majeure. He would point out that there
were no circumstances for invoking Force Majeure. The
period of 12 months from the date of financial closure
determined the maximum period within which the
commissioning had to take place. He would submit that
first respondent was in breach of even commissioning.
Therefore, on that score also, there is no
justification for the High Court to have interfered in
the matter. He would further submit that there is
another vital circumstance which should have dissuaded
the High Court from granting relief. The case threw up
disputed questions of facts. On the one hand, it was
the case of the first respondent, that the first
respondent had proceeded to do everything within the
time which is a period of two years from 18.09.2015,
the date of the PPA, and it was only if commissioning
was not done within the said period that what is
described in the agreement as Seller’s default occurs.
Here is a case where the first respondent had not
actually on the ground carried out necessary
installation. In this regard, he would contend that
13 while the CEIG has given its approval, the approval was
granted without the first respondent having complied
its obligations under the contract. In this regard
essentially two aspects are projected. It is firstly
pointed out that while the first writ petition was
pending consideration, the appellant carried out an
inspection on 19.04.2018. A report ensued on
21.04.2018. It was revealed that the approval which is
granted by the CEIG may not advance the case of the
first respondent as certain lacunae emerged. It was
found by the inspecting team of the appellant that in
the blocks 9 and 10 (the project of 50MW consisted of
10 blocks of 5 MW each), 61 inverters were missing. It
was further revealed that in regard to 258 invertors,
there was duplication of numbers. In other words,
without there being the professed numbers of invertors
as required under the contract, the approval of the
CEIG was procured. In fact, this aspect, which when it
was discovered by the appellant, formed the foundation
for the review petition but was not favourably
considered by the High Court. A writ petition in the
facts of this case would not lie. He would submit that
14 while a writ petition may be maintainable when the
State is awarding its largesse in the form of award of
contract, once it enters into a contract there would
arise no occasion for the court to do judicial review
and strike it down. Action taken by the state as
contracting party when it is within the four walls of
the contract is immune in public law proceedings. That
an action may lie for breach of contract where the
aggrieved party can seek damages should have weighed
with the court. He would further contend that there is
yet another dimension which has been overlooked by the
High Court. The overwhelming public interest in the
facts of this case did not favour the writ court
interfering in the matter. In this regard he would
expatiate by pointing out that the interference by the
High Court will produce the following results:
The PPA casts an obligation on the appellant
to purchase power at the rate of Rs.5.109 per unit
for a period of 25 years. Power is available in the
market at a far cheaper rate. The inevitable result
of implementing the order of the High court would
be that the appellant would have to purchase power
15 at a much higher rate and what is more disturbing
and should have troubled the High Court to decline
jurisdiction is the aspect that the increased rate
would have to be passed on to the end consumer. Put
it differently, when the appellant being entitled
to terminate the contract and would be in a position
to purchase power at a cheaper rate and charge the
consumers at the lower rate, by the court granting
relief to the first respondent, the appellant is
compelled to purchase power at the higher rate and
that too for a long period of 25 years, and what is
more, compelled to pass on the burden to the hapless
consumer. Thus, public interest in fact in the case
lay in the court declining to grant relief to the
first respondent. He would further point out that
the impugned judgment does not deal with any of the
aspects, be it the factual dimensions or the legal
requirements. The judgment is bereft of discussion
of the contentions raised by the appellant. He would
therefore contend that the impugned judgments
should be set aside and appeals allowed.
16 11. Per contra, Dr. A.M. Singhvi, learned Senior
Counsel for the first respondent would point out that
there is absolutely no basis for maintaining the appeal
in the facts. He would point out that this is a case
where the first respondent turned out to be the lowest
bidder in respect of the project in question and what
is more an incredible number of 182 bidders
participated. It is trouncing its competitors that the
holding company of the first respondent turned out to
be the lowest bidder (here we must notice that during
the course of the arguments the appellant did propose
that first respondent could come up with proposal which
apparently should involve rates lower than the contract
rate so that the public interest concern is adequately
addressed whereas the first respondent pointed out
since it has planned for the project on the basis which
made it the lowest bidder, it would not be feasible for
it to reduce the rate any further). Dr. Singhvi pointed
out that there is no basis for discriminating the case
of the first respondent and M/s. Renew Energy. It is
pointed out that the High Court in the first round of
litigation had interfered with the termination order
17 following the judgment in Renew Energy. In the case of
Renew Energy, it could achieve fulfilment of the
conditions subsequent with a delay of 16 days which was
condoned finally. In the case of the first respondent,
the delay happened to be 56 days. Otherwise, their
cases are similar. Renew Energy was allowed to
commission whereas the first respondent was at the
receiving end of discrimination without any basis. He
would point out that the first respondent under the
contract had 24 months from 18.09.2015 to commission
the project. Well before the expiry of 24 months, the
project was ready. The respondent was prevented from
commissioning. A party cannot take advantage of its own
wrong. He would point out that the law has not stood
still after this Court adopted a hands off approach in
the decision in Radhakrishna Agrawal and others v.
State of Bihar and others2. Imbibing the grand mandate
in Article 14 that it behoves the State to steer clear
of unfairness in all its acts, this Court has weaved a
taboo against arbitrary action by the state even after
it entered into a contract. He would point out in this
2 (1977) 3 SCC 457 18 regard the judgment of this Court in ABL International
Ltd. v. Export Credit Guarantee Corpn. of India Ltd.3
and the decisions following the same approving of the
writ court granting relief in contractual matters also.
He would point out that, present arbitrariness, be it
after a contract is entered into, the State has no
place to hide when action is challenged and its action
must pass the scrutiny of the constitutional court. It
must demonstrate that the action was fair. The action
of the State falls far short of the exacting standard
of fairness that the Constitution demands in the case
at hand for the following reasons:
12. Outbidding an unusually large body of competitors,
a bid based on competitive tariff, the first respondent
which is a global player in Renewable Energy (solar
power) bids at a rate which was very much acceptable
to the appellant and investment was made by the first
respondent in the region of nearly Rs. 350 crores.
There was an initial hiccup. One of the conditions
subsequent was that the first respondent had to acquire
3 (2004) 3 SCC 553 19 land for the project by way of sale deeds. There were
insuperable obstacles which upon the first respondent
pointing them out to the appellant, the appellant
realized the genuine difficulty and amended the
Article. This, in fact, would necessarily mean that the
period of 210 days would commence not from the date of
the agreement but thereafter on the basis of the
amended Article. The first respondent engaged the
services of a company for the purposes of purchase and
installation of the parts of the project. It had
procured, inter alia the invertors which were to be
installed, from abroad. There are irrefutable
documents in the form of invoices, bills of lading,
lorry receipts which fortify the first respondent in
its stand that it had installed all the invertors. The
project was ready to take off well within 24 months.
The first respondent would suffer grave avoidable
financial loss, besides fall in esteem as a global
player, if the termination dated 07.07.2018 is allowed
to stand. Under the contract, the first respondent was
obliged to sell power at an agreed rate for a period
of 25 years. The fact that in view of the play of market
20 forces, there has been a fall in the price of solar
power and it would be open to the appellant to procure
solar power at a cheaper rate should not allow the
appellant to resile from its contractual obligations.
In fact, it is pointed out that the appellant is
purchasing power even now at even higher rates. Being
State under Article 12, the appellant should not be
permitted to seek shelter under the theory of alternate
remedies. This Court is reminded of the chronology of
events commencing from the date of the PPA in the year
2015. The first respondent has succeeded before the
High court on two occasions. In this regard he would
point out that in the impugned termination order dated
07.07.2018, the appellant has purported to revive the
closed chapter relating to non-fulfilment of conditions
subsequent. The contention runs that by the judgment
in the first writ petition the impugned order therein
which was based on the first respondent not fulfilling
the conditions subsequent was quashed. This was done
being inspired by the judgment of the High court in the
case of Renew Energy which has received the seal of
approval by this Court as well. As far as the only
21 other aspect about commissioning not being in time Dr.
Singhvi addressed two submissions. Firstly, he would
point out that admittedly, the appellant has not issued
the pre-termination notice contemplated in Article 9.1
of the PPA. This suffices to sustain the judgment.
Secondly, equally importantly the appellant has acted
arbitrarily in not realizing that the first respondent
had 24 months to commission the project and before the
expiry of the same, the respondent was fully ready to
fulfil its obligation. The learned senior counsel would
also submit that contention of there being disputed
questions of fact is premised on red herrings. In this
regard he would point out that on 09.07.2017, a notice
was issued by the first respondent to the appellant
calling upon the appellant to inspect and it would be
ready to commission the project and that it was ready
to supply power. However, no inspection was carried by
the appellant till 19.04.2018. The competent body
namely the CEIG had carried out inspection which spread
over a few days. The Body was fully satisfied with the
first respondent being compliant. All that happened was
after the inspection, in September, 2017 since the
22 first respondent was visited with the first order of
termination dated 11.08.2017 which was challenged in
the High Court, there was a shortage of personnel
around the project site. This facilitated thefts of the
parts which were installed. FIRs promptly registered
in September 2017 should rule out the possibility of
the case of theft being an afterthought. This is as the
inspection was carried by the appellant much later on
19.04.2018. It is further pointed out that as far as
the duplication is concerned in the number of certain
invertors, it has been established as inconsequential
by the first respondent. The inspection and the report
of the CEIG cannot be lightly brushed aside on such a
case. Still furthermore, it is pointed out that having
regard to the massive cost of the project which stood
at nearly Rs. 350 crores, what is involved is a
miniscule percentage. In this regard learned counsel
would emphasise the contravention of Article 9.1 under
which the appellant was obliged to serve a notice in
case of the alleged seller’s default for not
commissioning the project in 24 months from the date
of PPA. If such a notice had been given, the first
23 respondent would have had an opportunity if at all even
proceeding on the basis of appellant’s contention being
tenable to procure invertors which are portable and
available in the market and redress the problem. When
the project has progressed in the manner, it had to
deny the first respondent the fruits of its labour,
acting under a solemn contract awarded to it would be
clearly unfair. The mere fact that there had been a
fall in the market price of solar power should not
persuade this Court to find that there is no
overwhelming public interest. In this regard he also
sought to draw support from recent Judgment of this
Court in Vice Chairman & Managing Director, City and
Industrial Development Corporated of Maharashtra Ltd.
and Another v. Shishir Realty P. Ltd. and others. He
would further point out that solar power being
renewable energy and green energy must be encouraged
and it was on this basis that the first respondent
participated in the global tender and was selected,
upon it being the lowest bidder amongst a large number
of bidders. Dr. Singhvi would point out that for
various reasons the contract in question is a statutory
24 contract. He would submit that any rate irrespective
of being statutory contract or not, it is but a fact
in deciding whether the writ applicant should be
relegated to an alternate remedy. The jurisdiction of
the High Court under Article 226 in the overpowering
presence of Article 14 would embrace the power to
strike at arbitrary action by the State, even in the
working out of rights in a non-statutory contract.
13. Shri V. Giri, learned senior counsel for respondent
No.5 would support the appellant in its stand that the
first respondent was in clear breach of the contract.
It is the case of fifth respondent that there are
various steps to be undertaken and completed under
regulations extant before which commissioning can be
permitted. It is the case of the fifth respondent that
the first respondent could not therefore be said to
have acted in compliance with the regulations and
therefore cannot be heard to say that it had
commissioned the project.
14. Shri K.M. Natraj, Additional Solicitor General
would submit that the judgment of the High court in the
first-round litigation left it open to the appellant
25 to take fresh proceedings under the contract. It is for
the said reason that the said judgment was not
challenged by the appellant. He would also point out
at any rate even proceeding on the basis that the High
Court is bound by the earlier judgment at any rate, as
far as this Court is concerned, it would be free to
consider the issue as to whether on account of there
being an admitted delay of 53 days by the first
respondent beyond the maximum time contemplated under
the contract for fulfilling conditions subsequent,
whether the appellant was justified being duty bound
in the matter of terminating the contract? He further
pointed out that there was a distinction in the case
of the first respondent and the case of Renew Energy.
In the case of Renew Energy, this Court while refusing
to interfere with the judgment of the High Court had
made it clear that it is not pronouncing on the question
as to the delay in fulfilling the conditions subsequent
and its impact. Secondly, it is pointed out that in the
case of Renew Energy, the said company had gone ahead
and commissioned the project and the only aspect was
the delay of 16 days whereas in the case of the first
26 respondent the contract was liable to be terminated
both for the reasons that the conditions subsequent was
not fulfilled within the maximum time and also for the
reason that the first respondent had not commissioned
the project within the time provided under the
contract.
15. After hearing the learned counsel for the parties,
we find that the following points arise for our
consideration.
(1)Whether the PPA in question, is a statutory
contract?
(2)What is the scope of judicial review of action by
the State in a matter arising from a contract and
what is the effect of the contract not being
statutory? What is arbitrariness?
(3)What is the concept of public law in judicial
review in a contractual matter?
(4)Whether there is an arbitration clause in regard
to the subject matter?
(5)Whether the order dated 07.07.2018 terminating the
contract based on first respondent not fulfilling
the conditions subsequent is sustainable having
27 regard to the judgment rendered by the High Court
in the earlier round of litigation on 20.06.2018?
And will the said judgment bar the appellant from
terminating the contract on the ground of non-
fulfilment of conditions subsequent?
(6)Whether the writ petition must be dismissed as
the case involves disputed questions of facts?
(7)Whether the case of the first respondent is on
par with Renew Energy?
(8)What is the effect of non-compliance of Article
9.1 of the PPA, namely, the effect of appellant
not issuing notice contemplated therein before
issuing the impugned termination dated
07.07.2018?
(9)What is overwhelming public interest in the
context of judicial review in a contractual
matter? Is the concept applicable only to cases
which involve challenge to award of largesse by
the State or is it applicable across the Board
irrespective of the stage when the matter arises
in relation to a contract?
28 (10) Whether this Court should interfere with the
judgment of the High Court in the totality of
facts?
16. Before we proceed to consider the question whether
what is involved is a statutory contract or not, we may
make the following prefatory remarks:
Under Article 298 of the Constitution, the
Executive Power of the Union and each State, inter
alia, extends to making of contracts for any
purpose. Article 299 provides for manner in which
contracts made in the exercise of the executive
power of the Union or the State is to be made.
17. In this case, we are dealing not with a case where
a contract has been made by the State in exercise of
its executive power within the meaning of Article 298.
The PPA is a contract which has been entered into by
the appellant, which is a fully owned Government
Company. It is one thing to hold that the appellant,
as a fully owned Government Company, would be State for
the purpose of Article 12 of the Constitution of India
and, quite another, to find that a contract is one
29 which is made in the executive power of the State within
the meaning of Article 162 of the Constitution. What
is contemplated, is the power of the Union or the State
read in conjunction with Article 73 and Article 162 of
the Constitution of India, respectively. In other
words, for the purpose of Article 298, the broader
concept of State, as defined in Article 12 of the
Constitution, which, no doubt, would include the
appellant, is inapposite and inapplicable. The
appellant, being a Company, would not be entitled to
exercise the executive power contemplated in Article
162 of the Constitution, which is the power with the
Union or the State Governments. In this regard we may
notice that the present avtar of Article 298 is born
by substituting in 1956 the original version and the
present version reads as follows: -
“298. Power to carry on trade, etc. The executive power of the Union and of each State shall extend to the carrying on of any trade or business and to the acquisition, holding and disposal of property and the making of contracts for any purpose:
Provided that —
(a) the said executive power of the Union shall, in so far as such trade or business or
30 such purpose is not one with respect to which Parliament may make laws, be subject in each State to legislation by the State; and
(b) the said executive power of each State shall, in so far as such trade or business or such purpose is not one with respect to which the State Legislature may make laws, be subject to legislation by Parliament.”
It is pertinent to notice the Objects and Reasons.
“Clause 19.-In this clause it is proposed to revise and amplify the scope of article 298, mainly to make it clear that Union Government, as well as the State Governments, are competent to carry on any commercial or industrial undertaking, whether or not it is related to a matter within the legislative competence of the Union, or, as the case may be, of the State. Similarly, the holding, acquisition and disposal of property and the making of contracts by the Union or a State could be for any purpose without constitutional impropriety. At the same time, the revised article provides that this extended executive power of the Union and of the States will be subject, in the former case, to legislation by the State, and in the latter case, to legislation by Parliament.”
WHETHER THE PPA IS A STATUTORY CONTRACT?
18. Moving on to the concept of the Statutory Contract,
the learned Additional Solicitor General, no doubt,
sought to draw considerable support from the Judgment
of this Court reported in Kerala SEB and another v.
31 Kurien E. Kalathil and others4. That was a case, which
involved, a Writ Petition filed by a contractor, who
was awarded the work of construction of a dam, staking
a claim, for enhanced minimum wages, which the
contractor claimed, he had paid to his workers. There
was no dispute that the workmen were entitled to the
enhanced wages under a Notification. The appellant-
Board, however, contended that the respondent-
contractor had failed to prove the payment of the
enhanced wages to the workmen. The High Court allowed
the Writ Petition and this Court, while setting aside
the Judgment, proceeded to make the following
statement:
“10. We find that there is a merit in the first contention of Mr Raval. Learned counsel has rightly questioned the maintainability of the writ petition. The interpretation and implementation of a clause in a contract cannot be the subject-matter of a writ petition. Whether the contract envisages actual payment or not is a question of construction of contract. If a term of a contract is violated, ordinarily the remedy is not the writ petition under Article 226. We are also unable to agree with the observations of the High Court that the contractor was seeking enforcement of a
4 (2000) 6 SCC 293 32 statutory contract. A contract would not become statutory simply because it is for construction of a public utility and it has been awarded by a statutory body. We are also unable to agree with the observation of the High Court that since the obligations imposed by the contract on the contracting parties come within the purview of the Contract Act, that would not make the contract statutory. Clearly, the High Court fell into an error in coming to the conclusion that the contract in question was statutory in nature.
11. A statute may expressly or impliedly confer power on a statutory body to enter into contracts in order to enable it to discharge its functions. Dispute arising out of the terms of such contracts or alleged breaches have to be settled by the ordinary principles of law of contract. The fact that one of the parties to the agreement is a statutory or public body will not by itself affect the principles to be applied. The disputes about the meaning of a covenant in a contract or its enforceability have to be determined according to the usual principles of the Contract Act. Every act of a statutory body need not necessarily involve an exercise of statutory power. Statutory bodies, like private parties, have power to contract or deal with property. Such activities may not raise any issue of public law. In the present case, it has not been shown how the contract is statutory. The contract between the parties is in the realm of private law. It is not a statutory contract. The disputes relating to interpretation of the terms and conditions of such a contract could not have been agitated in a petition under Article 226 of the Constitution of India. That is a matter for
33 adjudication by a civil court or in arbitration if provided for in the contract. Whether any amount is due and if so, how much and refusal of the appellant to pay it is justified or not, are not the matters which could have been agitated and decided in a writ petition. The contractor should have relegated to other remedies.”
19. As to what is a statutory contract, fell for
consideration before this Court in the case reported
in India Thermal Power Ltd. v. State of M.P. and
others5. Incidentally, it dealt with generation,
distribution and supply of electricity and, what is
more, emanated from the State of Madhya Pradesh. While
negotiations were going on between the respondent-
State, Electricity Board and independent power
producers, on the basis of State inviting offers from
potential private investors, for establishing power
projects, the Central Government amended the earlier
Tariff Notification. The Electricity Board decided to
prioritize the projects, which offered the least
tariff. The appellant-independent power producer
challenged the said decision in a Writ Petition. It
5 (2000) 3 SCC 379 34 must be noticed that MoU and Power Purchase Agreement
had been entered into by the appellant therein. The
Division Bench of the High Court took the view that
the PPAs therein were statutory contracts, entered into
under Sections 43 and 43(A) of the Electricity Supply
Act, 1948. This Court, while dealing with this aspect
and rejecting the contention that the Electricity Board
could not unilaterally alter the conditions of the
contract and invite bids, held as follows:
“11. It was contended by Mr Cooper, learned Senior Counsel appearing for appellant GBL and also by some counsel appearing for other appellants that the appellant/IPPs had entered into PPAs under Sections 43 and 43-A of the Electricity Supply Act and as such they are statutory contracts and, therefore, MPEB had no power or authority to alter their terms and conditions. ………………
……… Merely because a contract is entered into in exercise of an enabling power conferred by a statute that by itself cannot render the contract a statutory contract. If entering into a contract containing the prescribed terms and conditions is a must under the statute then that contract becomes a statutory contract. If a contract incorporates certain terms and conditions in it which are statutory then the said contract to that extent is statutory. A contract may contain certain other terms and conditions which may not be of a statutory character and which have been incorporated therein as a result of mutual agreement between 35 the parties. Therefore, the PPAs can be regarded as statutory only to the extent that they contain provisions regarding determination of tariff and other statutory requirements of Section 43-A(2). Opening and maintaining of an escrow account or an escrow agreement are not the statutory requirements and, therefore, merely because PPAs contemplate maintaining escrow accounts that obligation cannot be regarded as statutory.” (Emphasis supplied)
20. The decision in India Thermal Power Ltd. (supra),
dealing with the concept of statutory contract, came
to be considered in the light of Section 6A of U.P.
Industrial Area Development Act of 1976. The said
provision reads as follows:
“6A. Power to authorize a person to provide infrastructure or amenities and collect tax or fee. - Notwithstanding anything to the contrary contained in any other provisions of this Act and subject to such terms and conditions as may be specified in the regulations, the Authority may, by agreement, authorize any person to provide or maintain or continue to provide or maintain any infrastructure or amenities under this Act and to collect taxes or fees, as the case may be, levied therefor.”
21. This Court interpreting a contract entered into
under Section 6A in Jaypee Kensington Boulevard
36 Apartments Welfare Association and others v. NBCC
(India) Ltd. and others6, took the view that the
agreement in question did not acquire the status of a
statutory contract merely for having been executed in
terms of the power under Section 6A.
22. The contention of the respondent is that the PPA
is a statutory contract since it incorporates essential
features such as tariff determined through bidding
(paragraph-4.7-CUF, paragraph-4.4-change in law,
paragraph-4.5-payment security, paragraph-4.6-and
bidding process, paragraphs-5.4 and 5.5-prescribed
under the guidelines for tariff based competitive
process for grid connected power project based on
renewable energy resources issued by the MNRE under
Section 63 of the Act).
23. The respondent relies on India Thermal Power Ltd.
(supra) to contend that if the contract incorporates
certain statutory terms and conditions, it is
statutory.
6 (2022) 1 SCC 401 37
24. Section 63 of the Electricity Act, 2003, reads as
follows:
“63 (Determination of tariff by bidding process) Notwithstanding anything contained in Section 62, the appropriate Commission shall adopt the tariff, if such tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.”
25. In the PPA in question, under the definition clause
(Article 1), bidding guidelines have been defined as
follows:
"Bidding Guidelines" shall mean the "Guidelines for Tariff Based Competitive Bidding Process for Grid Connected Power Projects Based on Renewable Energy Sources"
issued by Government of lndia, Ministry of New and Renewable Energy on December, 2012 under Section - 63 of the Electricity Act and as amended from time to time;”
26. We are of the view that it may not be appropriate
to describe the PPA as a Statutory Contract. Section
63 of the Electricity Act, 2003 must be understood in
the background of immediately preceding provision,
viz., Section 62, In a paradigm shift from the earlier
regime, the task of determining the tariff has been
38 conferred on the appropriate Commission. Section 62
indicates the procedure. Section 63, on the other hand,
compels the Commission to adopt the tariff determined
through a transparent process of bidding. However, the
transparent process of bidding must be in accordance
with the guidelines issued by the Central Government.
Thus, it is for the purpose of applying the tariff
determined under Section 63 for the purpose of adopting
the tariff under Section 62, that the guidelines issued
by the Central Government become relevant. It is true
that there is reference to the guidelines made under
Section 63 in the PPA. However, it is for the purpose
of conducting the bidding that the guideline would
become relevant. That the tariff has been arrived at
in accordance with the transparent process of bidding,
which is in tune with the guidelines under Section 63,
may not be sufficient to make the PPA a Statutory
Contract. What is contemplated in India Thermal Power
Limited (supra), is that a contract containing
prescribed terms and conditions being mandatory under
the Statute, results in the contract becoming a
Statutory Contract. If this test is applied, we fail
39 to see how the reference to the bidding guidelines,
under which the bids were made and finally the PPA is
entered into, can be treated as tantamounting to saying
that the PPA contains prescribed statutory terms and
conditions as an indispensable part of a Statute. We
are not shown also as to how the PPA can be described
as containing terms and conditions, which are statutory
in nature. The expression ‘terms and conditions’, which
are statutory in nature, must be understood as those
statutory terms and conditions, which provide for
rights and obligations of the contracting parties. Such
reference is conspicuous by its absence in the PPA. It
is common case that the appellant is incorporated under
the Companies Act. It is not a statutory body or a
corporation. Therefore, we would come to the conclusion
that we cannot describe the contract as a Statutory
Contract. We must also notice that the PPA is not made
either in purported compliance with the statutory
dictate, either in the form of parent enactment or a
subordinate legislation. The terms and conditions of
the PPA are not transplanted into the PPA from any
Statutory provision. The appellant being company under
40 the Companies Act, would be free as any other
contracting party, subject, no doubt, to its position
as an instrumentality of the State under Article 12 of
the Constitution of India and the law otherwise.
Moreover, the terms, which are relevant to the lis
before us, viz, the Articles relating to the fulfilment
of the condition subsequent and the provisions relating
to commissioning, sellers’ default and power of
termination, are not demonstrated to be statutory in
nature.
What is the scope of judicial review of action by the State in a matter arising from a contract and what is the effect of the contract not being statutory?
What is the concept of public law in judicial review in a contractual matter?
What is ‘arbitrary’ action?
27. In Radhakrishna Agarwal and Ors. v. State of Bihar
and Ors.7 writ petitions were filed against orders of
the State Government revising the rate of royalty under
7 (1977) 3 SCC 457 41 a lease. The contention was both against the revision
of rate of royalty during the period of the lease and
the cancellation of the lease on various grounds. Though an attempt was sought to draw support from the
judgment of this Court in Erusian Equipment and
Chemicals Limited v. State of West Bengal8, the Court
took the view that the said case involved
discrimination at the threshold or at the time of
deciding as to whether the Government should enter into
the contract. The Court took the view that the only
question which normally arises in such cases is as to
whether the action complained of was in conformity with
the agreement. We may notice the earlier opinions of
this Court which came to be dealt with in the following
statement:
“We do not think that any of these cases could assist the appellants or is at all relevant. None of these cases lays down that, when the State or its officers purport to operate within the contractual field and the only grievance of the citizen could be that the contract between the parties is broken by the action complained of, the appropriate remedy is by way of a petition under Article 226 of the Constitution and not an ordinary suit. There is a formidable
8 (1975) 1 SCC 70 42 array of authority against any such a proposition. In Lekhraj Satramdas Lalvani v.
N.M.Shah, Deputy Custodian-cum-Managing Officer, Bombay (supra) this Court said:
“In our opinion any duty or obligation falling upon a public servant out of a contract entered into by him as such public servant cannot be enforced by the machinery of a writ under Article 226 of the Constitution.”
In Banchhanidhi Rath v. The State of Orissa and
Ors.9, this Court declared:
“If a right is claimed in terms of a contract such a right cannot be enforced in a writ petition.”
In Har Shankar and Ors. vs. The Dy. Excise and
Taxation Commr. and Ors.10, a Constitution Bench of this
Court observed:
“The appellants have displayed ingenuity in their search for invalidating circumstances but a writ petition is not an appropriate remedy for impeaching contractual obligations.”
9 (1972) 4 SCC 781 10 (1975) 1 SCC 737 43
28. The Court also took the view “the correct view is
that it is the contract and not the executive power
regulated by the Constitution which governs the
relations of the parties on facts apparent in the case
before us”. No doubt the learned Additional Solicitor
General asserts that the destiny of the appeals before
us must be governed by the law laid down in Radhakrishna
Agarwal (supra). However, as shall be presently noticed
the law has not stood still.
29. In Ramana Dayaram Shetty v. International Airport
Authority of India11 this court inter alia held as
follows:
“10. Now, there can be no doubt that what para (1) of the notice prescribed was a condition of eligibility which was required to be satisfied by every person submitting a tender.
The condition of eligibility was that the person submitting a tender must be conducting or running a registered IInd Class hotel or restaurant and he must have at least 5 years' experience as such and if he did not satisfy this condition of eligibility, his tender would not be eligible for consideration. This was the standard or norm of eligibility laid down by Respondent 1 and since the Respondents 4 did not satisfy this standard or norm, it was not competent to Respondent 1 to entertain the tender of Respondents 4. It is a well-settled rule of administrative law that an executive
11 (1979) 3 SCC 489 44 authority must be rigorously held to the standards by which it professes its actions to be judged and it must scrupulously observe those standards on pain of invalidation of an act in violation of them. This rule was enunciated by Mr Justice Frankfurter in Viteralli v. Saton [359 US 535 : Law Ed (Second series) 1012] where the learned Judge said:
“An executive agency must be rigorously held to the standards by which it professes its action to be judged .… Accordingly, if dismissal from employment is based on a defined procedure, even though generous beyond the requirements that bind such agency, that procedure must be scrupulously observed .... This judicially evolved rule of administrative law is now firmly established and, if I may add, rightly so. He that takes the procedural sword shall perish with the sword.”
This Court accepted the rule as valid and applicable in India in A.S. Ahluwalia v. Punjab [(1975) 3 SCC 503, 504 :
1975 SCC (L&S) 27 : (1975) 3 SCR 82] and in subsequent decision given in Sukhdev v. Bhagatram [(1975) 1 SCC 421, 462 : 1975 SCC (L&S) 101 : (1975) 3 SCR 619] , Mathew, J., quoted the above-referred observations of Mr Justice Frankfurter with approval. It may be noted that this rule, though supportable also as an emanation from Article 14, does not rest merely on that article. It has an independent existence apart from Article 14. It is a rule of administrative law which has been judicially evolved as a check against exercise of arbitrary power by the executive authority. If we turn to the judgment of Mr Justice Frankfurter and examine it, we find that he has not sought to draw support for the rule from the equality clause 45 of the United States Constitution, but evolved it purely as a rule of administrative law. Even in England, the recent trend in administrative law is in that direction as is evident from what is stated at pp. 540-41 in Prof Wade's “Administrative Law”, 4th Edn. There is no reason why we should hesitate to adopt this rule as a part of our continually expanding administrative law. Today with tremendous expansion of welfare and social service functions, increasing control of material and economic resources and large scale assumption of industrial and commercial activities by the State, the power of the executive Government to affect the lives of the people is steadily growing. The attainment of socio-economic justice being a conscious end of State policy, there is a vast and inevitable increase in the frequency with which ordinary citizens come into relationship of direct encounter with State power-holders. This renders it necessary to structure and restrict the power of the executive Government so as to prevent its arbitrary application or exercise. Whatever be the concept of the Rule of Law, whether it be the meaning given by Dicey in his “The Law of the Constitution” or the definition given by Hayek in his “Road to Serfdom” and “Constitution of Liberty” or the exposition set forth by Harry Jones in his “The Rule of Law and the Welfare State”, there is as pointed out by Mathew, J., in his article on “The Welfare State, Rule of Law and Natural Justice” in “Democracy, Equality and Freedom” [ Upendra Baxi, Ed. : Eastern Book Co., Lucknow (1978) p. 28] “substantial agreement in juristic thought that the great purpose of the rule of law notion is the protection of the individual
46 against arbitrary exercise of power, wherever it is found”. It is indeed unthinkable that in a democracy governed by the rule of law the executive Government or any of its officers should possess arbitrary power over the interests of the individual. Every action of the executive Government must be informed with reason and should be free from arbitrariness. That is the very essence of the rule of law and its bare minimal requirement. And to the application of this principle it makes no difference whether the exercise of the power involves affectation of some right or denial of some privilege.”
This case while it dealt with the issue of
arbitrariness at the stage of award of largesse by the
State, it paved the way for future development in this
field of law.
30. No doubt, in Bareilly Development Authority and
another v. Ajai Pal Singh and others12, the appellant-
Authority constituted under the U.P. Planning and
Development Act, 1973, issued advertisement offering
to register the names of applicants desirous of
purchasing houses/flats. The terms and conditions were
sought to be revised. The Court went on to hold as
12 (1989) 2 SCC 116 47 follows:
“22. There is a line of decisions where the contract entered into between the State and the persons aggrieved is non-statutory and purely contractual and the rights are governed only by the terms of the contract, no writ or order can be issued under Article 226 of the Constitution of India so as to compel the authorities to remedy a breach of contract pure and simple — Radhakrishna Agarwal v. State of Bihar [(1977) 3 SCC 457 : (1977) 3 SCR 249] , Premji Bhai Parmar v. Delhi Development Authority [(1980) 2 SCC 129 : (1980) 2 SCR 704] and DFO v. Biswanath Tea Company Ltd. [(1981) 3 SCC 238 : (1981) 3 SCR 662]”
31. In Mahabir Auto Stores and others v. Indian Oil
Corporation and others13, the appellant complained that
the respondent, which was a company incorporated under
the Companies Act was denying or discontinuing to deal
with the appellant, which had been dealing with the
respondent for nearly eighteen years. We listen to the
following words spoken by this Court:
“12. It is well settled that every action of the State or an instrumentality of the State in exercise of its executive power, must be informed by reason. In appropriate cases, actions uninformed by reason may be questioned as arbitrary in proceedings under Article 226 or Article 32 of the Constitution. Reliance in
13 (1990) 3 SCC 752 48 this connection may be placed on the observations of this Court in Radha Krishna Agarwal v. State of Bihar [(1977) 3 SCC 457].
It appears to us, at the outset, that in the facts and circumstances of the case, the respondent company IOC is an organ of the State or an instrumentality of the State as contemplated under Article 12 of the Constitution. The State acts in its executive power under Article 298 of the Constitution in entering or not entering in contracts with individual parties. Article 14 of the Constitution would be applicable to those exercises of power. Therefore, the action of State organ under Article 14 can be checked. See Radha Krishna Agarwal v. State of Bihar [(1977) 3 SCC 457] at p. 462, but Article 14 of the Constitution cannot and has not been construed as a charter for judicial review of State action after the contract has been entered into, to call upon the State to account for its actions in its manifold activities by stating reasons for such actions. In a situation of this nature certain activities of the respondent company which constituted State under Article 12 of the Constitution may be in certain circumstances subject to Article 14 of the Constitution in entering or not entering into contracts and must be reasonable and taken only upon lawful and relevant consideration; it depends upon facts and circumstances of a particular transaction whether hearing is necessary and reasons have to be stated. In case any right conferred on the citizens which is sought to be interfered, such action is subject to Article 14 of the Constitution, and must be reasonable and can be taken only upon lawful and relevant grounds of public interest.
49 Where there is arbitrariness in State action of this type of entering or not entering into contracts, Article 14 springs up and judicial review strikes such an action down. Every action of the State executive authority must be subject to rule of law and must be informed by reason. So, whatever be the activity of the public authority, in such monopoly or semi- monopoly dealings, it should meet the test of Article 14 of the Constitution. If a governmental action even in the matters of entering or not entering into contracts, fails to satisfy the test of reasonableness, the same would be unreasonable. In this connection reference may be made to E.P. Royappa v. State of Tamil Nadu [(1974) 4 SCC 3 : 1974 SCC (L&S) 165] , Maneka Gandhi v. Union of India [(1978) 1 SCC 248] , Ajay Hasia v. Khalid Mujib Sehravardi [(1981) 1 SCC 722 : 1981 SCC (L&S) 258] , R.D. Shetty v. International Airport Authority of India [(1979) 3 SCC 489] and also Dwarkadas Marfatia and Sons v. Board of Trustees of the Port of Bombay [(1989) 3 SCC 293] . It appears to us that rule of reason and rule against arbitrariness and discrimination, rules of fair play and natural justice are part of the rule of law applicable in situation or action by State instrumentality in dealing with citizens in a situation like the present one. Even though the rights of the citizens are in the nature of contractual rights, the manner, the method and motive of a decision of entering or not entering into a contract, are subject to judicial review on the touchstone of relevance and reasonableness, fair play, natural justice, equality and non- discrimination in the type of the transactions
50 and nature of the dealing as in the present case.
17. We are of the opinion that in all such cases whether public law or private law rights are involved, depends upon the facts and circumstances of the case. The dichotomy between rights and remedies cannot be obliterated by any strait-jacket formula. It has to be examined in each particular case. Mr Salve sought to urge that there are certain cases under Article 14 of arbitrary exercise of such “power” and not cases of exercise of a “right” arising either under a contract or under a statute. We are of the opinion that that would depend upon the factual matrix.
18. Having considered the facts and circumstances of the case and the nature of the contentions and the dealing between the parties and in view of the present state of law, we are of the opinion that decision of the State/public authority under Article 298 of the Constitution, is an administrative decision and can be impeached on the ground that the decision is arbitrary or violative of Article 14 of the Constitution of India on any of the grounds available in public law field. It is true that there is discrimination between power and right but whether the State or the instrumentality of a State has the right to function in public field or private field is a matter which, in our opinion, depends upon the facts and circumstances of the situation, but such exercise of power cannot be dealt with by the State or the instrumentality of the State without informing and taking into confidence, the party whose rights and powers are affected
51 or sought to be affected, into confidence. In such situations most often people feel aggrieved by exclusion of knowledge if not taken into confidence.” (Emphasis supplied]
32. In the judgment of this Court rendered by a Bench
of two learned Judges decided in Shrilekha Vidyarthi
(Kumari) v. State of U.P14, the court was concerned with
a challenge to a general order by which the appointment
of all government counsel in all the districts of the
state of U.P. came to be terminated. The writ petition
was filed under Article 32 of the Constitution of
India. Important and apposite are the following
observations:
“22. There is an obvious difference in the contracts between private parties and contracts to which the State is a party. Private parties are concerned only with their personal interest whereas the State while exercising its powers and discharging its functions, acts indubitably, as is expected of it, for public good and in public interest. The impact of every State action is also on public interest. This factor alone is sufficient to import at least the minimal requirements of public law obligations and impress with this character the contracts made by the State or its instrumentality. It is a different matter
14 (1991) 1 SCC 212 52 that the scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes. However, to the extent, challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also falls within the domain of contractual obligations would not relieve the State of its obligation to comply with the basic requirements of Article 14. To this extent, the obligation is of a public character invariably in every case irrespective of there being any other right or obligation in addition thereto. An additional contractual obligation cannot divest the claimant of the guarantee under Article 14 of non-arbitrariness at the hands of the State in any of its actions.
24. The State cannot be attributed the split personality of Dr Jekyll and Mr Hyde in the contractual field so as to impress on it all the characteristics of the State at the threshold while making a contract requiring it to fulfil the obligation of Article 14 of the Constitution and thereafter permitting it to cast off its garb of State to adorn the new robe of a private body during the subsistence of the contract enabling it to act arbitrarily subject only to the contractual obligations and remedies flowing from it. It is really the nature of its personality as State which is significant and must characterize all its actions, in whatever field, and not the nature of function, contractual or otherwise, which
53 is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters. There is a basic difference between the acts of the State which must invariably be in pubic interest and those of a private individual, engaged in similar activities, being primarily for personal gain, which may or may not promote public interest. Viewed in this manner, in which we find no conceptual difficulty or anachronism, we find no reason why the requirement of Article 14 should not extend even in the sphere of contractual matters for regulating the conduct of the State activity.
27. Unlike a private party whose acts uninformed by reason and influenced by personal predilections in contractual matters may result in adverse consequences to it alone without affecting the public interest, any such act of the State or a public body even in this field would adversely affect the public interest.
28. Even assuming that it is necessary to import the concept of presence of some public element in a State action to attract Article 14 and permit judicial review, we have no hesitation in saying that the ultimate impact of all actions of the State or a public body being undoubtedly on public interest, the requisite public element for this purpose is present also in contractual matters. We, therefore, find it difficult and unrealistic
54 to exclude the State actions in contractual matters, after the contract has been made, from the purview of judicial review to test its validity on the anvil of Article 14.” (Emphasis supplied)
33. As to what constitutes arbitrariness is captured
in paragraph 36 and it reads as follows:
“36. The meaning and true import of arbitrariness is more easily visualized than precisely stated or defined. The question, whether an impugned act is arbitrary or not, is ultimately to be answered on the facts and in the circumstances of a given case. An obvious test to apply is to see whether there is any discernible principle emerging from the impugned act and if so, does it satisfy the test of reasonableness. Where a mode is prescribed for doing an act and there is no impediment in following that procedure, performance of the act otherwise and in a manner which does not disclose any discernible principle which is reasonable, may itself attract the vice of arbitrariness. Every State action must be informed by reason and it follows that an act uninformed by reason, is arbitrary. Rule of law contemplates governance by laws and not by humour, whims or caprices of the men to whom the governance is entrusted for the time being. It is trite that ‘be you ever so high, the laws are above you’. This is what men in power must remember, always.”
34. The pronouncement made by this Court would later
become the springboard or the charter for the further
evolution of the concept of public law element as also
55 premise for the superior courts invoking Article 14 in
various contractual matters.
35. In State of U.P and others v. Bridge and Roof
Company (India) Ltd.15, the Court was dealing with a
case of a writ petition filed by the respondent therein
which was a public sector corporation and seeking
payment allegedly due from the appellant state. The
Court noted that the contract in question contained
Articles providing inter alia for settlement of
disputes by reference to arbitration. The very resort
to Article 226 was found to be misconceived in the
circumstances.
The Court also laid down as follows: -
“Firstly, the contract between the parties is a contract in the realm of private law. It is not a statutory contract. It is governed by the provisions of the Contract Act or maybe, also by certain provisions of the Sale of Goods Act. Any dispute relating to interpretation of the terms and conditions of such a contract cannot be agitated, and could not have been agitated, in a writ petition. That is a matter either for arbitration as provided by the contract or for
15 (1996) 6 SCC 22 56 the civil court, as the case may be. Whether any amount is due to the respondent from the appellant-Government under the contract and, if so, how much and the further question whether retention or refusal to pay any amount by the Government is justified, or not, are all matter which cannot be agitated in or adjudicated upon in a writ petition. The prayer in the writ petition, viz., to restrain the Government from deducting a particular amount from the writ petitioner’s bill(s) was not a prayer which could be granted by the High Court under Article
226. Indeed, the High Court has not granted the said prayer.”
36. In Verigamto Naveen v. Govt. of A.P. and others16,
the case involved, mining leases granted to a
corporation and a sub-lease, which was permitted by the
Government. Thereafter, the permission was sought to
be withdrawn. The withdrawal of the permission, was the
subject matter of challenge in writ proceedings, inter
alia. Against, the Order of the Full Bench of the High
Court, (which is reported in AIR 1995 A.P.1), appeals
were carried to this Court. On the issue relating to
16 (2001) 8 SCC 344 57 the jurisdiction of the Court in cases arising out of
contract, this Court held as follows:
“21. … Though there is one set of cases rendered by this Court of the type arising in Radhakrishna Agarwal case [(1977) 3 SCC 457 : AIR 1977 SC 1496] much water has flown in the stream of judicial review in contractual field. In cases where the decision-making authority exceeded its statutory power or committed breach of rules or principles of natural justice in exercise of such power or its decision is perverse or passed an irrational order, this Court has interceded even after the contract was entered into between the parties and the Government and its agencies. We may advert to three decisions of this Court in Dwarkadas Marfatia & Sons v. Board of Trustees of the Port of Bombay [(1989) 3 SCC 293] , Mahabir Auto Stores v. Indian Oil Corpn. [(1990) 3 SCC 752] and Shrilekha Vidyarthi (Kumari) v. State of U.P. [(1991) 1 SCC 212 : 1991 SCC (L&S) 742 :
AIR 1991 SC 537] Where the breach of contract involves breach of statutory obligation when the order complained of was made in exercise of statutory power by a statutory authority, though cause of action arises out of or pertains to contract, brings it within the sphere of public law because the power exercised is apart from contract. The freedom of the Government to enter into business with anybody it likes is subject to the condition of reasonableness and fair play as well as public interest. After entering into a contract, in cancelling the contract which is subject to terms of the statutory provisions, as in the present case, it cannot be said that the matter falls purely in a contractual field. Therefore, we do not think it would be 58 appropriate to suggest that the case on hand is a matter arising purely out of a contract and, therefore, interference under Article 226 of the Constitution is not called for. This contention also stands rejected.” (Emphasis supplied)
The basis for interference was located in a statute
which made its presence felt.
37. In Binny Ltd. and Another v. V. Sadasivan and
Others17, this Court was dealing with termination of
services of respondents who were working as Members of
the Management, staff of the appellant company. The
appellant company purported to terminate their
services. The respondents thereupon filed a writ
petition under Article 226 of the constitution of
India. The appellant company contended that it was
neither a public authority nor did its action involve
a public law element, and a writ of Mandamus would not
lie. The High Court granted only the declaratory relief
to the effect that the termination was illegal. We
notice the following: -
“30. A contract would not become statutory simply because it is for construction of a public utility and it has been awarded by a
17 (2005) 6 SCC 657 59 statutory body. But nevertheless, it may be noticed that the Government or government authorities at all levels are increasingly employing contractual techniques to achieve their regulatory aims. It cannot be said that the exercise of those powers are free from the zone of judicial review and that there would be no limits to the exercise of such powers, but in normal circumstances, judicial review principles cannot be used to enforce contractual obligations. When that contractual power is being used for public purpose, it is certainly amenable to judicial review. The power must be used for lawful purposes and not unreasonably.” (Emphasis supplied)
38. The Court went to hold that the decision of the
employer to terminate the services of the employees
could not be said to have any element of public policy.
The Court did not find any public element in the
termination of the employees. We may at once notice
that the appellant in the said case was not a public
sector unit as the appellant in the present case.
39. In G. Bassi Reddy v. International Crops Research
Institute and another18, the services of the appellant
came to be terminated by the respondent-ICRISAT. The
18 (2003) 4 SCC 225 60 Court went on to hold that the respondent could not be
treated as State under Article 12. The Court further
proceeded to hold that the Writ Petition was not
maintainable against the respondent, noticing that
neither was the respondent set up by a Statute nor were
its activities statutorily controlled.
40. ABL (supra) marks a milestone, as it were, in the
matter of the superior court interfering in contractual
matters where the State is a player even after the
contract is entered into. A petition was filed under
Article 226 wherein the respondent which was
incorporated under the Companies Act repudiated an
insurance claim made by the appellant-writ petitioner.
This Court undertook an elaborate discussion of the
earlier case law. We find that this Court dealt with
several obstacles which were sought to be posed by the
respondent. They included disputed questions of facts
being involved, availability of alternate remedy, and
the case involving entertaining a money claim. This
court went on to hold as follows:
“27. From the above discussion of ours, the following legal principles emerge as to the maintainability of a writ petition:
61 (a) In an appropriate case, a writ petition as against a State or an instrumentality of a State arising out of a contractual obligation is maintainable.
(b) Merely because some disputed questions of fact arise for consideration, same cannot be a ground to refuse to entertain a writ petition in all cases as a matter of rule.
(c) A writ petition involving a consequential relief of monetary claim is also maintainable.”
41. No doubt, we must also notice para 28 which serves
as an admonition against considering the availability
of the remedy under Article 226 as an absolute charter
to invoke jurisdiction in all cases.
“28. However, while entertaining an objection as to the maintainability of a writ petition under Article 226 of the Constitution of India, the court should bear in mind the fact that the power to issue prerogative writs under Article 226 of the Constitution is plenary in nature and is not limited by any other provisions of the Constitution. The High Court having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. The Court has imposed upon itself certain restrictions in the exercise of this power. (See Whirlpool Corpn. v. Registrar of Trade Marks [(1998) 8 SCC 1].) And this plenary right of the High Court to issue a prerogative writ will not normally be exercised by the Court to the exclusion of other available remedies unless such action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which
62 the Court thinks it necessary to exercise the said jurisdiction.” (Emphasis supplied)
42. We may also notice how this Court steered clear
of the criticism that it was not following the
principle laid down by this Court in State of U.P. v.
Bridge & Roof Co. (India) Ltd.19. The Court noted that
the said case did involve a contract which contained
an arbitration clause. It is found that in the case
before it there was no arbitration clause. In regard
to the question as to whether the first respondent in
the said case was discharging a public duty or public
function was involved while repudiating the claim of
the appellants arising out of the contract, the Court
drew support from the judgment in Kumari Shrilekha
Vidyarthi (supra).
43. In Noble Resources Ltd. v. State of Orissa20, this
court followed ABL (supra). However, in the facts of
the said case again the matter involving refusal by a
public authority to honour the contract in the matter
19 (1996) 6 SCC 22 20 (2006) 10 SCC 236 63 of purchase of Iron ore, the Court held as follows:
“15. It is trite that if an action on the part of the State is violative of the equality clause contained in Article 14 of the Constitution of India, a writ petition would be maintainable even in the contractual field. A distinction indisputably must be made between a matter which is at the threshold of a contract and a breach of contract; whereas in the former the court's scrutiny would be more intrusive, in the latter the court may not ordinarily exercise its discretionary jurisdiction of judicial review, unless it is found to be violative of Article 14 of the Constitution. While exercising contractual powers also, the government bodies may be subjected to judicial review in order to prevent arbitrariness or favouritism on their part. Indisputably, inherent limitations exist, but it would not be correct to opine that under no circumstances a writ will lie only because it involves a contractual matter.”
44. The court went on to approve of ABL (supra) and
observed that this Court had declared that no decision
lays down as an absolute rule that in all cases of
disputed questions of fact, the parties should be
relegated to a civil Court. We may also notice
paragraph 29:
“29. Although the scope of judicial review or the development of law in this field has been noticed hereinbefore particularly in the light of the decision of this Court in ABL International Ltd. [(2004) 3 SCC 553] each case, however, must be decided on its own
64 facts. Public interest as noticed hereinbefore, may be one of the factors to exercise the power of judicial review. In a case where a public law element is involved, judicial review may be permissible. (See Binny Ltd. v. V. Sadasivan [(2005) 6 SCC 657 : 2005 SCC (L&S) 881] and G.B. Mahajan v. Jalgaon Municipal Council [(1991) 3 SCC 91]”
45. Of further relevance to notice is the case of the
respondent therein that only because the price of iron
ore increased in the international market, the
appellant had filed the writ petition only in February
2004. It was found that the said contention was not
wholly misconceived. Thereafter the court went on to
following observations:
“41. The submission of Mr Desai that rise in international price would not by itself be a relevant consideration to rescind the contract may be correct, but then the same was not the sole ground for Respondent 2 to refuse to supply iron ore fines to the appellant.
42. Moreover, certain serious disputed questions of fact have arisen for determination. Such disputed questions of fact ordinarily could not have been entertained by the High Court in exercise of its power of judicial review.”
46. In the context of upgradation of aided schools and
a complaint of discrimination, we notice the following
65 observations of this court in State Of Kerala and
others v. K. Prasad and another21.
” Para 11. This Court in Shrilekha Vidyarthi v. State of U.P. [(1991) 1 SCC 212: 1991 SCC (L&S) 742] held that every State action, in order to survive, must not be susceptible to the vice of arbitrariness which is the crux of Article 14 and basic to the rule of law, the system which governs us, arbitrariness being the negation of the rule of law. Non-arbitrariness, being a necessary concomitant of the rule of law, it is imperative that all actions of every public functionary in whatever sphere must be guided by reason and not humour, whim, caprice or personal predilections of the persons entrusted with the task on behalf of the State and exercise of all powers must be for public good instead of being an abuse of power.”
47. We may notice that as to what constitutes
arbitrariness fell for consideration by this court in
a case which involved cancellation of the examination
held as part of a recruitment process, in East Coast
Railway and another v. Mahadev Appa Roa and others22.
We notice the following passages which are apposite for
this case.
“19. Black's Law Dictionary describes the term “arbitrary” in the following words:
21
(2007) 7 SCC 140 22 (2010) 7 SCC 678 66 “Arbitrary. —1. Depending on individual discretion; specif., determined by a judge rather than by fixed rules, procedures, or law.
2. (Of a judicial decision) founded on prejudice or preference rather than on reason or fact. This type of decision is often termed arbitrary and capricious.”
20. To the same effect is the meaning given to the expression “arbitrary” by Corpus Juris Secundum which explains the term in the following words:
“Arbitrary.—Based alone upon one's will, and not upon any course of reasoning and exercise of judgment; bound by no law; capricious; exercised according to one's own will or caprice and therefore conveying a notion of a tendency to abuse possession of power; fixed or done capriciously or at pleasure, without adequate determining principle, non-rational, or not done or acting according to reason or judgment; not based upon actuality but beyond a reasonable extent; not founded in the nature of things; not governed by any fixed rules or standard; also, in a somewhat different sense, absolute in power, despotic, or tyrannical; harsh and unforbearing. When applied to acts, ‘arbitrary’ has been held to connote a disregard of evidence or of the proper weight thereof; to express an idea opposed to administrative, executive, judicial, or legislative discretion; and to imply at least an element of bad faith, and has been compared with ‘willful’.”
xxx xxx xxx
23. Arbitrariness in the making of an order by an authority can manifest itself in different forms. Non-application of mind by the authority making the order is only one of them. Every order
67 passed by a public authority must disclose due and proper application of mind by the person making the order. This may be evident from the order itself or the record contemporaneously maintained. Application of mind is best demonstrated by disclosure of mind by the authority making the order. And disclosure is best done by recording the reasons that led the authority to pass the order in question. Absence of reasons either in the order passed by the authority or in the record contemporaneously maintained is clearly suggestive of the order being arbitrary hence legally unsustainable.”
48. We would, therefore, sum up as to when an act is
to be treated as arbitrary. The court must carefully
attend to the facts and the circumstances of the case.
It should find out whether the impugned decision is
based on any principle. If not, it may unerringly point
to arbitrariness. If the act betrays caprice or the
mere exhibition of the whim of the authority it would
sufficiently bear the insignia of arbitrariness. In
this regard supporting an order with a rationale which
in the circumstances is found to be reasonable will go
a long way to repel a challenge to state action. No
doubt the reasons need not in every case be part of the
order as such. If there is absence of good faith and
the action is actuated with an oblique motive, it could
68 be characterised as being arbitrary. A total non-
application of mind without due regard to the rights
of the parties and public interest may be a clear
indicator of arbitrary action. A wholly unreasonable
decision which is little different from a perverse
decision under the Wednesbury doctrine would qualify
as an arbitrary decision under Article 14. Ordinarily
visiting a party with the consequences of its breach
under a contract may not be an arbitrary decision.
49. We may now notice the judgment of this court in
Joshi Technologies International Inc. v. Union of India
and others23, which is also relied upon by the learned
Additional Solicitor General. The said case actually
involved the complaint of the writ petitioner therein
that it was entitled to the benefit of Section 42 of
the Income Tax Act, 1961 which provided for certain
deductions. The petitioner had entered into an
agreement with the respondent, the Government of India.
The case of the respondent, inter alia, was one denying
the case of the petitioner that the omission of Section
23 (2015) 7 SCC 728 69 42 was by oversight. The prayer in the writ petition
itself inter alia was essentially to declare
entitlement to the deduction under Section 42, inter
alia. It is while dealing with the said case that this
court no doubt proceeds to, inter alia, lay down as
following after adverting to ABL limited (supra) also:-
“69. The position thus summarised in the aforesaid principles has to be understood in the context of discussion that preceded which we have pointed out above. As per this, no doubt, there is no absolute bar to the maintainability of the writ petition even in contractual matters or where there are disputed questions of fact or even when monetary claim is raised. At the same time, discretion lies with the High Court which under certain circumstances, it can refuse to exercise. It also follows that under the following circumstances, “normally”, the Court would not exercise such a discretion:
69.1. The Court may not examine the issue unless the action has some public law character attached to it.
69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact which are of complex nature
70 and require oral evidence for their determination.
69.4. Money claims per se particularly arising out of contractual obligations are normally not to be entertained except in exceptional circumstances.”
“70. Further, the legal position which emerges from various judgments of this Court dealing with different situations/aspects relating to contracts entered into by the State/public authority with private parties, can be summarised as under:
70.1. At the stage of entering into a contract, the State acts purely in its executive capacity and is bound by the obligations of fairness.
70.2. State in its executive capacity, even in the contractual field, is under obligation to act fairly and cannot practise some discriminations.
70.3. Even in cases where question is of choice or consideration of competing claims before entering into the field of contract, facts have to be investigated and found before the question of a violation of Article 14 of the Constitution could arise. If those facts are disputed and require assessment of evidence the correctness of which can only be tested satisfactorily by taking detailed evidence, involving examination and cross-examination of witnesses, the case could not be conveniently or satisfactorily decided in proceedings under Article 226 of the Constitution. In such cases the Court can direct the aggrieved party to resort to alternate remedy of civil suit, etc.
70.4. Writ jurisdiction of the High Court under Article 226 of the Constitution was not intended
71 to facilitate avoidance of obligation voluntarily incurred.
70.5. Writ petition was not maintainable to avoid contractual obligation. Occurrence of commercial difficulty, inconvenience or hardship in performance of the conditions agreed to in the contract can provide no justification in not complying with the terms of contract which the parties had accepted with open eyes. It cannot ever be that a licensee can work out the licence if he finds it profitable to do so: and he can challenge the conditions under which he agreed to take the licence, if he finds it commercially inexpedient to conduct his business.
70.6. Ordinarily, where a breach of contract is complained of, the party complaining of such breach may sue for specific performance of the contract, if contract is capable of being specifically performed. Otherwise, the party may sue for damages.
70.7. Writ can be issued where there is executive action unsupported by law or even in respect of a corporation there is denial of equality before law or equal protection of law or if it can be shown that action of the public authorities was without giving any hearing and violation of principles of natural justice after holding that action could not have been taken without observing principles of natural justice.
70.8. If the contract between private party and the State/instrumentality and/or agency of the State is under the realm of a private law and there is no element of public law, the normal course for the aggrieved party, is to invoke the remedies provided under ordinary civil law rather than approaching the High Court under Article 226 of the Constitution of India and invoking its extraordinary jurisdiction.
72 70.9. The distinction between public law and private law element in the contract with the State is getting blurred. However, it has not been totally obliterated and where the matter falls purely in private field of contract, this Court has maintained the position that writ petition is not maintainable. The dichotomy between public law and private law rights and remedies would depend on the factual matrix of each case and the distinction between the public law remedies and private law field, cannot be demarcated with precision. In fact, each case has to be examined, on its facts whether the contractual relations between the parties bear insignia of public element. Once on the facts of a particular case it is found that nature of the activity or controversy involves public law element, then the matter can be examined by the High Court in writ petitions under Article 226 of the Constitution of India to see whether action of the State and/or instrumentality or agency of the State is fair, just and equitable or that relevant factors are taken into consideration and irrelevant factors have not gone into the decision-making process or that the decision is not arbitrary.
70.10. Mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirements of due consideration of a legitimate expectation forms part of the principle of non-arbitrariness.
70.11. The scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to
73 remedies provided for adjudication of purely contractual disputes.”
50. In State of Kerala v. M.K. Jose24, the specific
question with which we are concerned with, namely,
entertaining a writ petition in a contractual matter
and where the specific question was the validity of the
termination of the contract, fell for consideration.
We may notice the following:
“13. A writ court should ordinarily not entertain a writ petition, if there is a breach of contract involving disputed questions of fact. The present case clearly indicates that the factual disputes are involved.”
51. Thereafter, the court went on to consider in detail
the judgment of this Court in ABL (supra) and found
that it was a case where the court granted relief as
the facts were absolutely clear from the documentary
evidence and it pertained to interpretation of such
clauses of the contract of insurance. We need notice
only paragraph 20 in M.K. Jose (supra). It reads as
under:
“20. We have referred to the aforesaid authorities to highlight under what
24 (2015) 9 SCC 433 74 circumstances in respect of contractual claim or challenge to violation of contract can be entertained by a writ court. It depends upon facts of each case. The issue that had arisen in ABL International [(2004) 3 SCC 553] was that an instrumentality of a State was placing a different construction on the clauses of the contract of insurance and the insured was interpreting the contract differently. The Court thought it apt merely because something is disputed by the insurer, it should not enter into the realm of disputed questions of fact.
In fact, there was no disputed question of fact, but it required interpretation of the terms of the contract of insurance. Similarly, if the materials that come on record from which it is clearly evincible, the writ court may exercise the power of judicial review but, a pregnant one, in the case at hand, the High Court has appointed a Commission to collect the evidence, accepted the same without calling for objections from the respondent and quashed the order of termination of contract.”
(Emphasis supplied)
52. In State of U.P. v. Sudhir Kumar Singh and Others25,
the first respondent the successful tenderer had worked
the contract for a year when he was visited with
cancellation. This Court exhaustively referred to the
earlier case law including ABL (supra) and Joshi
Technology (supra) and held, inter alia, as follows: -
“23. It may be added that every case in which a citizen/person knocks at the doors of the writ court for breach of his or its fundamental
25 2020 SCC Online 847 75 rights is a matter which contains a “public law element”, as opposed to a case which is concerned only with breach of contract and damages flowing therefrom. Whenever a plea of breach of natural justice is made against the State, the said plea, if found sustainable, sounds in constitutional law as arbitrary State action, which attracts the provisions of Article 14 of the Constitution of India - see Nawabkhan Abbaskhan v. State of Gujarat (1974) 2 SCC 121 at paragraph 7. The present case is, therefore, a case which involves a “public law element” in that the petitioner (Respondent No. 1 before us) who knocked at the doors of the writ court alleged breach of the audi alteram partem rule, as the entire proceedings leading to cancellation of the tender, together with the cancellation itself, were done on an ex parte appraisal of the facts behind his back.”
53. We have already concluded that PPA is not a
Statutory Contract. However, that would not be the end
of enquiry. Dr. A.M. Singhvi, learned Senior Counsel,
would point out that the contract, not being a
statutory contract, assumes relevance only for the
purpose of deciding as to whether the Court should
relegate the writ applicant, to alternate remedies. In
other words, while the Court would retain its
discretion to entertain the petition or decline to do
so, in the facts of each case, there is no absolute
taboo against the Court granting relief, even if the
challenge to the termination of a contract is made in
76 the case of a contract, which is not statutory in
nature, when the offending party is the State. In other
words, the contention is that the law in this field
has witnessed an evolution and, what is more, a
revolution of sorts and a transformatory change with a
growing realisation of the true ambit of Article 14 of
the Constitution of India. The State, he points out,
cannot play the Dr. Jekyll and Hyde game anymore. Its
nature is cast in stone. Its character is inflexible.
This is irrespective of the activity it indulges in.
It will continue to be haunted by the mandate of Article
14 to act fairly. There has been a stunning expansion
of the frontiers of the Court’s jurisdiction to strike
at State action in matters arising out of contract,
based, undoubtedly, on the facts of each case. It
remains open to the Court to refuse to reject a case,
involving State action, on the basis that the action
is, per se, arbitrary.
54. We may cull out our conclusions in regard to the
points, which we have framed:
i. It is, undoubtedly, true that the writ
jurisdiction is a public law remedy. A matter,
77 which lies entirely within a private realm of
affairs of public body, may not lend itself for
being dealt with under the writ jurisdiction of
the Court.
ii. The principle laid down in Bareilly Development
Authority (supra) that in the case of a non-
statutory contract the rights are governed only
by the terms of the contract and the decisions,
which are purported to be followed, including
Radhakrishna Agarwal (supra), may not continue
to hold good, in the light of what has been laid
down in ABL (supra) and as followed in the recent
judgment in Sudhir Kumar Singh (supra).
iii. The mere fact that relief is sought under a
contract which is not statutory, will not
entitle the respondent-State in a case by itself
to ward-off scrutiny of its action or inaction
under the contract, if the complaining party is
able to establish that the action/ inaction is,
per se, arbitrary.
iv. An action will lie, undoubtedly, when the State
purports to award any largesse and, undoubtedly, 78 this relates to the stage prior to the contract
being entered into [See R.D. Shetty (supra)].
This scrutiny, no doubt, would be undertaken
within the nature of the judicial review, which
has been declared in the decision in Tata
Cellular vs. Union of India26.
v. After the contract is entered into, there can be
a variety of circumstances, which may provide a
cause of action to a party to the contract with
the State, to seek relief by filing a Writ
Petition.
vi. Without intending to be exhaustive, it may
include the relief of seeking payment of amounts
due to the aggrieved party from the State. The
State can, indeed, be called upon to honour its
obligations of making payment, unless it be that
there is a serious and genuine dispute raised
relating to the liability of the State to make
the payment. Such dispute, ordinarily, would
include the contention that the aggrieved party
26 (1994) 6 SCC 651 79 has not fulfilled its obligations and the Court
finds that such a contention by the State is not
a mere ruse or a pretence.
vii. The existence of an alternate remedy, is,
undoubtedly, a matter to be borne in mind in
declining relief in a Writ Petition in a
contractual matter. Again, the question as to
whether the Writ Petitioner must be told off the
gates, would depend upon the nature of the claim
and relief sought by the petitioner, the
questions, which would have to be decided, and,
most importantly, whether there are disputed
questions of fact, resolution of which is
necessary, as an indispensable prelude to the
grant of the relief sought. Undoubtedly, while
there is no prohibition, in the Writ Court even
deciding disputed questions of fact,
particularly when the dispute surrounds
demystifying of documents only, the Court may
relegate the party to the remedy by way of a
civil suit.
viii. The existence of a provision for arbitration,
80 which is a forum intended to quicken the pace of
dispute resolution, is viewed as a near bar to
the entertainment of a Writ Petition (See in
this regard, the view of this Court even in ABL
(supra) explaining how it distinguished the
decision of this Court in State of U.P. and
others v. Bridge & Roof Co.27, by its
observations in paragraph-14 in ABL (supra)].
ix. The need to deal with disputed questions of fact,
cannot be made a smokescreen to guillotine a
genuine claim raised in a Writ Petition, when
actually the resolution of a disputed question
of fact is unnecessary to grant relief to a writ
applicant.
x. The reach of Article 14 enables a Writ Court to
deal with arbitrary State action even after a
contract is entered into by the State. A wide
variety of circumstances can generate causes of
action for invoking Article 14. The Court’s
approach in dealing with the same, would be
27 (1996) 6 SCC 22 81 guided by, undoubtedly, the overwhelming need to
obviate arbitrary State action, in cases where
the Writ remedy provides an effective and fair
means of preventing miscarriage of justice
arising from palpably unreasonable action by the
State.
xi. Termination of contract can again arise in a
wide variety of situations. If for instance, a
contract is terminated, by a person, who is
demonstrated, without any need for any argument,
to be the person, who is completely unauthorised
to cancel the contract, there may not be any
necessity to drive the party to the unnecessary
ordeal of a prolix and avoidable round of
litigation. The intervention by the High Court,
in such a case, where there is no dispute to be
resolved, would also be conducive in public
interest, apart from ensuring the Fundamental
Right of the petitioner under Article 14 of the
Constitution of India. When it comes to a
challenge to the termination of a contract by
the State, which is a non-statutory body, which
82 is acting in purported exercise of the
powers/rights under such a contract, it would be
over simplifying a complex issue to lay down any
inflexible Rule in favour of the Court turning
away the petitioner to alternate Fora.
Ordinarily, the cases of termination of contract
by the State, acting within its contractual
domain, may not lend itself for appropriate
redress by the Writ Court. This is, undoubtedly,
so if the Court is duty-bound to arrive at
findings, which involve untying knots, which are
presented by disputed questions of facts.
Undoubtedly, in view of ABL Limited (supra), if
resolving the dispute, in a case of repudiation
of a contract, involves only appreciating the
true scope of documentary material in the light
of pleadings, the Court may still grant relief
to an applicant. We must enter a caveat. The
Courts are today reeling under the weight of a
docket explosion, which is truly alarming. If a
case involves a large body of documents and the
Court is called upon to enter upon findings of
83 facts and involves merely the construction of
the document, it may not be an unsound discretion
to relegate the party to the alternate remedy. This is not to deprive the Court of its
constitutional power as laid down in ABL
(supra). It all depends upon the facts of each
case as to whether, having regard to the scope
of the dispute to be resolved, whether the Court
will still entertain the petition.
xii. In a case the State is a party to the contract
and a breach of a contract is alleged against
the State, a civil action in the appropriate
Forum is, undoubtedly, maintainable. But this is
not the end of the matter. Having regard to the
position of the State and its duty to act fairly
and to eschew arbitrariness in all its actions,
resort to the constitutional remedy on the cause
of action, that the action is arbitrary, is
permissible (See in this regard Kumari Shrilekha
Vidyarthi and others v. State of U.P. and
84 others28). However, it must be made clear that
every case involving breach of contract by the
State, cannot be dressed up and disguised as a
case of arbitrary State action. While the
concept of an arbitrary action or inaction
cannot be cribbed or confined to any immutable
mantra, and must be laid bare, with reference to
the facts of each case, it cannot be a mere
allegation of breach of contract that would
suffice. What must be involved in the case must
be action/inaction, which must be palpably
unreasonable or absolutely irrational and bereft
of any principle. An action, which is completely
malafide, can hardly be described as a fair
action and may, depending on the facts, amount
to arbitrary action. The question must be posed
and answered by the Court and all we intend to
lay down is that there is a discretion available
to the Court to grant relief in appropriate
cases.
28 (1991) 1 SCC 212) 85 xiii. A lodestar, which may illumine the path of the
Court, would be the dimension of public interest
subserved by the Court interfering in the
matter, rather than relegating the matter to the
alternate Forum.
xiv. Another relevant criteria is, if the Court has
entertained the matter, then, while it is not
tabooed that the Court should not relegate the
party at a later stage, ordinarily, it would be
a germane consideration, which may persuade the
Court to complete what it had started, provided
it is otherwise a sound exercise of jurisdiction
to decide the matter on merits in the Writ
Petition itself.
xv. Violation of natural justice has been recognised
as a ground signifying the presence of a public
law element and can found a cause of action
premised on breach of Article 14. [See Sudhir
Kumar Singh and Others (supra)].
WHETHER THERE IS AN ARBITRATION CLAUSE?
55. Before we proceed to deal further with the matter,
86 we would have to first find whether there is any
arbitration clause. We have already referred to the
dispute resolution clause, namely, Article 13.2.1 and
Article 13.2.3. They would appear to indicate that the
clauses may not constitute an arbitration clause. As
far as Article 13.3.1. is concerned, to which resort
is to be made when the dispute remains unresolved under
13.2.3, it deals with disputes arising from a claim for
any matter relating to the tariff. Therefore, we would
take the view that it may not be a case where the PPA
provides for an arbitration clause capable of
determining the lis in question. The situation
therefore contemplated in U.P. Roof (supra) as laid
down in ABL (supra) does not exist.
THE IMPACT OF THE JUDGMENT IN THE FIRST WRIT PETITION
56. Taking up point no. 5., viz., the effect of the
judgment of the High Court in the earlier round, we
must notice indeed that this is a case which represents
the second round of the litigation. In the earlier
round the respondents had successfully invoked the
87 jurisdiction under Article 226 when it was served with
the order of termination of the contract dated
11.08.2017. We have already noticed the fate of the
said case. The first battle which commenced in the year
2017 resumed as it were with the present writ petition.
We are not oblivious to the fact that the appellant
did not think it fit to challenge the verdict in the
first round of litigation. No doubt, the case of the
appellant is that the appellant was of the view that
the court has left it free to the appellant to take
steps under the contract for termination of the
contract. It is the case of the appellant in fact, that
the judgment of the High Court in the earlier round
would not be an obstacle for the appellant to revisit
and terminate the contract for the reason that the PPA
made it incumbent on the appellant to terminate the
contract under Article 2.1(d) if the contractor did not
fulfil the conditions subsequent even after the expiry
of 210 days and a further period of nine months after
the commencement of PPA. We must examine whether the
earlier judgment, in fact, in law permits the appellant
to re-open the said issue. A perusal of the judgment
88 dated 20.6.2017 would reveal that the court was dealing
with the challenge to the order dated 11.08.2017. The
order dated 11.08.2017 would reveal that the appellant
has found that there is a delay of 54 days in achieving
the condition subsequent deadline. After considering
the representation by the respondent, the appellant
found that there is no merit in the case of force
majeure and there was no justification for the delay
in achieving conditions subsequent. Thereafter, the
appellant, in terms of Article 2.5.1(d), terminated the
PPA. Still further, a sum of Rs.1180.50 lakhs was found
recoverable as penalty in terms of Article 2.5. It is
this order which was challenged. Thereafter we find
that the High court went on to notice that in a similar
case, viz., relating to New Clean Energy Pvt. Ltd., the
petitioner therein admittedly commissioned the project
within the time prescribed except that there was a
delay of 16 days in achieving the first milestone.
57. Here we must understand the word ‘first milestone’
as fulfilment of the conditions subsequent. In regard
to fulfilment of said milestone for which there was a
delay of 16 days in the case of Renew clean Energy,
89 there was a delay of 54 days in the case of the first
respondent. It is further noticed by the High Court
that there was an order passed in favour of the Renew
clean energy setting aside the termination of the
contract in the said petitioner’s case as confirmed by
this Court. Next the High Court went on to record that
there is a dispute as to whether the respondent had
commissioned the power project in the present case. We
notice that an attempt was made by the appellant to
justify the termination on the basis that the
respondent had not commissioned the power project
within the time fixed. The High Court proceeds to
notice that the aspect of commissioning the project was
not the basis for terminating the contract. Relying
on Mohinder Singh Gill29, the appellants were not
permitted to supplement the reasons for termination.
Finally, the High court has proceeded to find that
since the similar reason for termination of the
agreement in the communication dated 11.8.2017 was not
found justified in the case of Renew Clean Energy, the
impugned communication dated 11.08.2017 was set aside.
29
(1978) 1 SCC 405 90 It is thereafter that the liberty was given to the
appellants to pass fresh orders in terms of the PPA in
accordance with law.
58. The appellants would persuade us to hold that the
High Court intended, by the liberty granted to leave
it open to the appellant to pass orders invoking its
power under the PPA which would not only include
termination of the PPA based on respondent not
commissioning the project within the time but also
revisit the aspect relating to non-fulfilment of the
conditions subsequent. The respondent would join issue
with the appellant on the score that judgment of the
High Court must be understood as meaning that on the
issue relating to non-fulfilment of the conditions
subsequent the court made its pronouncement on merits
with reference to the decision in Renew Clean Energy.
All that was left open was the question related to the
delay in commissioning the project.
59. Learned Additional Solicitor General apart from
reiterating his contention would point out that the
earlier judgment should not be treated as res judicata
and the only reason appellant did not challenge the
91 High court judgment, dated 20.06.2018, was the liberty
granted. He would further submit that at any rate even
proceeding on the basis that the High court could not
revisit the issue of the non-fulfilment of the
conditions subsequent, the decision of the High Court
would not stand in the way of this Court considering
whether the order which is impugned in this case which
includes the issue relating to non-fulfilment of the
conditions subsequent is sustainable. This is apart
from pointing out that even in the case of Renew Clean
Energy, this Court in its order refusing to interfere
in the judgment of the High Court has made it clear
that it was not going into the merits of the said
contention having regard to observations which had been
made, namely, that the contractor therein being faced
with unavoidable circumstances as also the factum of
huge investment made in the project.
60. Having noticed the contents of the decision of the
High court dated 20.06.2018 and also bearing in mind
the terms of the notice of termination dated 11.08.2017
we are of the view that the High Court must be treated
as having interfered with the order based no doubt on
92 the order of the said court as affirmed by this Court
in the case of Renew Clean Energy. Noticing, however,
the contentions based on the aspect relating to project
not being commissioned by the respondent within time
and further clearly finding that the impugned order was
not premised on project not being commissioned the
impugned order was set aside finding that the
termination was not justified as regards to non-
fulfilment of conditions subsequent. It is thereafter
that the liberty was granted and it had to pass fresh
order in terms of the PPA. We have to take the order
as it is and we are of the firm view that the analysis
of the order leads us to only one conclusion which is
that the High Court intended to only leave open the
right of the appellant to invoke its power under the
contract in regard to the issue relating to
commissioning of the project or rather in the matter
of default in commissioning the project. It would
neither be legal nor equitable to permit the appellant
to contend that the issue relating to not having
fulfilled the conditions subsequent can be canvassed
all over again.
93 AN ASIDE?
THE STATE LOAD DISPATCH CENTRE (RESPONDENT NO.5): ITS STAND AND THE IMPACT OF THE SAME
61. Respondent No.5 filed a counter affidavit in this
Court. It claims to be the ‘Authority charged to
perform functions under Section 32 (2) of the
Electricity Act, 2003. Its responsibility is limited
to monitoring and controlling of existing Grid elements
and generating stations keeping the account of energy
transmitted through the Grid. It specifically states
that its role emerges after commissioning of the
generating plant. It further states all activities
prior to readiness of generator to inject power into
the Grid are beyond its purview. The further stand is
that none of the regulatory provisions allows it to
interfere in pre-requisite regulatory compliance by the
generator before injecting of power into the Grid.
There is reference to short-term open access for which
there are regulations. In respect of Renewable Energy
generators intending to connect with the Grid, certain
regulatory requirements, before injecting of power
94 therein, are to be complied with. They are
registration, data and speech communication facility,
interface metering and communication of meter data
through automatic meter reading.
Single line diagram indicating connectivity with
the grid duly certified by MPPTCL (fourth respondent),
when connected to 132KV and above, inter alia, copy of
connection agreement with the fourth respondent, inter
alia, information regarding sale of power under long-
term access, medium-term open access or short-term open
access, approval of CEIG for construction, operation
and maintenance of electrical plans and electrical
lines under Section 73C of the Electricity Act, 2003
and approval of Power, Telecommunication and
Coordination Committee (PTCC). It is further stated
that on compliance with procedures it first issues a
unique code for charging power evacuation line. When
the line holds for a reasonable time, unique code for
injection is issued. Real time generation is monitored.
If it is satisfied with the data recorded by the
interface meters (Main and check) then a generating
station is deemed to be commissioned. It is pointed
95 out by letters dated 2.12.2015 and 3.11.2016 respondent
No.5 requested Respondent No.1 for compliance of the
procedure/ response. Mandatory documents were not
submitted for injecting of Grid except registration.
CEIG approval is only for renewable energy generation
units and equipments installed in the Switchyard.
Respondent No.1 has not obtained CEIG approval of
transmission line. The details of the interface
meters, metering equipments are not mentioned in the
report of CGIG. It is pointed out that other units
including M/s. New Clean Energy was ready for
evacuation of power with all regulatory requirements.
62. In the reply affidavit filed by the first
respondent to the said counter affidavit, it is
complained that respondent No.5 though a party in the
earlier writ petition as also in the present writ
petition it never responded, objecting to the readiness
of first respondent in August 2017. The belated reply
in the High Court is stated to seem as ill motivated
and done at the instance of the appellant.
Furthermore, the first respondent points out that it
is not the case of the first respondent that its project
96 was commissioned. Its case was that it was complete in
all respects and would have commissioned before the
expiry of 24 months but for the illegal termination on
two occasions as noted. In regard to non-compliance
with certain regulatory requirements, various steps
taken by it are referred to.
63. As far as registration is concerned, it was
completed on 15.12.2016. In regard to data and speech
communication facility, it is stated by Respondent No.1
that it is completed on 23.03.2017. In the said
communication, on a letterhead showing the name of the
fourth respondent and also showing the name of the
fifth respondent, it is stated that the telemetry
scheme for the 100MW solar power plant was generally
in order and accepted for implementation, subject to
four conditions stipulated therein. Thereafter, it is
stated that “it is, therefore, required that the
telemetry and voice communication from the control
centre of the proposed power plant upto Back Up SLDC
Bhopal/Sub-LDC Indore/SLDC Jabalpur be arranged before
synchronization of your power plant. It may please be
noted that synchronization of plant with grid shall not
97 be allowed without commissioning of telemetry and voice
communication.” It is seen signed by the Superintending
Engineer (LD:E&T), SLDC, MPPTCL, Jabalpur. As far as
the requirement of connection agreement, it has been
stated in the reply affidavit of the first respondent
that such connection agreement was, indeed, executed
between Respondent No.1 and Respondent No.4. The
agreement is dated 18.05.2017. At this juncture, we may
notice that a Sur-Rejoinder has been filed by
Respondent No.5. Having regard to the connection
agreement, all that is stated is, till date, Respondent
No.5 was not provided with a copy by the first
respondent. It is also stated that Respondent Nos. 4
and 5 are two distinct entities and, therefore, it was
required for compliance that the same should have been
submitted to Respondent No. 5. We have already noticed
that letter dated 23.07.2017 is on the same letterhead,
showing the names of Respondent Nos. 4 and 5 and signed
by the Superintending Engineer, wherein also, the names
of Respondent Nos. 4 and 5 appear. It is a little
intriguing and strange, that the fifth respondent did
not know about the agreement and referred to it as a
98 requirement and as though it had not been complied with
by the first respondent. The first respondent has
stated that, with regard to the single-line diagram
indicating connectivity with the grid, that it was
completed on 19.10.2016. An extension was sought for
by Respondent No.1, in which required diagrams were
furnished to Respondent No. 4. Respondent No.4, it is
stated, has granted permission for charging the
transmission line connected from the project to the
STU. Diagrams were also, it is stated, approved by the
CEIG. The answer of Respondent No.5 in the Sur-
Rejoinder that the letter dated 29.08.2017 was not
issued by Respondent No.5 but by Respondent No.4. It
is admitted that it is stated therein that the line is
ready for charging but further necessary action, like
issuing of charging code, has to be taken from
Respondent No.5 by Respondent No.1. It is again stated
that Respondent No.1 has never approached Respondent
No.5 with copy of letter dated 29.08.2017 and CEIG
approval for readiness of evacuating line. It is again
stated that Respondent No.5 is not an arm or even unit
of Respondent No.4. In regard to the contention that
99 information regarding sale of power for access,
including long-term access, was not made available by
the first respondent. It is pointed out that the first
respondent set up the project to supply power to the
appellant only as per the PPA and the said requirement
was not applicable.
64. The fifth respondent in the Sur-Rejoinder
responded by pointing out that Respondent No.5 is the
Nodal Body for managing the grid operations and within
the State and it is generally seen that if the plant
is commissioned the same cannot be left idle and be
allowed to inject power into the grid, and it was in
this regard, it was mentioned that if a third-party
sale was to be undertaken by Respondent No.1 so that
its plant was not left idle, then, it was incumbent on
Respondent No.1 to have obtained open access. We find
that as per Article 9.8 of the PPA, the first respondent
was obliged to sell the contracted capacity for a
period of twenty-five years from COD. Elaborate
provisions have been made, which would visit the first
respondent with monetary compensation to be paid to the
appellant, in case of breach. Article 9.7 also provides
100 for the obligation of the appellant to buy power for
twenty-five years. It is only if there was refusal or
inability to buy by the appellant, fully or partially,
or in the event of default, as per Article 9.5, leading
to termination, the first respondent was left free to
sell power to a third party, which sale was to be
regulated by certain terms.
65. As regards another requirement, viz., approval of
the CEIG for construction, operation and maintenance
of the electrical plants and electrical lines, it is
the case of the first respondent that such approval was
obtained by letter dated 10.08.2017. It was also marked
to Respondent No.4. CEIG approval for the electrical
plant was received on 09.08.2017. Respondent No.4, it
is pointed out, had also, on 24.08.2017, issued a Joint
Inspection Report certifying that the project may be
charged. In fact, we find, in the Joint Inspection
Report issued by the fourth respondent that:
“Newly constructed 132KV D.C.D.S. line from 400KV PS Chhegaon to 50MW Pooling Station of M/S Sky Power Solar India Pvt. Ltd. And 50MW Pooling Station of M/S Sky Power Southeast Solar India Pvt. Ltd. At village Chhirbel has been jointly inspected with EE (EHT-M) MPPTCL, Indore on dt.24/08/2017.
101 During Joint Inspection No. any major defects has been found and line. May be charged.” (Emphasis supplied)
66. In regard to the same, Respondent No.5 in the Sur-
Rejoinder would state that it is misleading and
incorrect on the basis that it has been averred by
Respondent No.1 that the approval of the CEIG for
readiness of 132KV double circuit line for connection
with the grid was submitted by the sister concern of
Respondent No.1, while requesting code for charging the
132KV line for the sister concern. It is stated that
in the approval issued on 10.08.2017, there is no
mention that the second line will be utilised by
Respondent No.1. The letter of the CEIG dated
10.08.2017 is said to be addressed to the sister
concern. There was to be a specific approval of CEIG
in favour of Respondent No.1. Copy was not marked to
Respondent No.5 but only marked to Respondent No.4. It
again reiterated that they are two different entities.
67. It appears to us that though letter dated
10.08.2017 is addressed to the sister concern of
Respondent No.1, viz., Sky Power Solar India Pvt. Ltd.,
102 what was the subject matter of the communication was
for 100MW solar power project, and what is more, and
it was for the establishment of 132KV ‘dual’ circuit
transmission. This understanding of this CEIG Report
is clear from the Joint Inspection Report of Respondent
No.4 as Respondent No.1 has entered into a PPA for
50MW, and the sister concern, apparently, had a PPA for
50MW. Lastly, even given an opportunity, this is a
matter which could have been clarified by the CEIG, for
which no opportunity appears to have been given. We
bear in mind Article 9.1 of the PPA. From the Joint
Inspection Report, bearing in mind that 132KV line had
a dual circuit, the same line was to be used by the
first respondent and its sister concern. This appears
to be the only possible meaning on a joint reading of
the CEIG Report dated 10.08.2017 and Joint Inspection
Report dated 24.08.2017. We stand fortified in this
regard by the report dated 21.04.2018 also where it is
inter alia stated as follows:-
“1. Present Status of Transmission Line for power evacuation from Power Plant to Grid Substation 132 kV DCDS line is found erected between Pooling Substation to 400 kV Chhegaon (Torni)Substation. One circuit is used for 103 already existing 50 MW plant of M/s Sky Power and 2nd circuit is proposed to be used for M/s Sky Power South East Solar India Pvt.
Ltd. at village Chirbel, Distt. Khandwa, for which site verification visit is conducted.”
68. The next requirement, according to the fifth
respondent was that approval of the PTCC was required.
The first respondent has, in the reply, stated the said
requirement was completed on 05.09.2017. We find that
Chief Engineer (Procurement) of the fourth respondent
has recorded in the communication dated 05.09.2017 that
PTCC had accorded PTCC route approval:
“With reference to the subject cited above, DET (PTCC), Mumbai has accorded PTCC route approval for charging 132KV DCDS line from 400kV S/s Chhegaon to 100MW Solar Power Project of M/s SkyPower Solar India & M/s SkyPower Southeast Solar India Pvt. Ltd. Chhirbel, Dist. Khandwa.”
69. The fifth respondent, in the Sur-Rejoinder, in
response to the same, would respond by stating that the
Respondent No.4 granting approval, did not mean that
the same was issued with the knowledge or concurrence
of Respondent No.5. We only remind ourselves that in
the Counter Affidavit filed by Respondent No.5,
Respondent No.5 had only stated against Requirement
104 No.VIII that there was the requirement of approval of
PTCC. What is reflected in letter dated 05.09.2017 is
that DET [PTCC] has accorded PTCC route approval. The
approval is not granted by the fourth respondent. We
are a little mystified by the statement that the PTCC
approval should be one issued with the knowledge and
concurrence of the fifth respondent.
70. It is, no doubt, true that as regards the
contention of the fifth respondent that there must be
interface metering and communication of the meter data
through automatic meter reading (AMR), which details
are to be provided to the SLDC before the commissioning
of the plant, there is no specific averment by the
first respondent. Here we must notice that it is for
the first time such a plea is being raised by the fifth
respondent. Even proceeding on the basis that it was a
requirement; it is required to be provided before
commissioning. This is not a matter, which could not
be set right at any rate, if an opportunity to remove
a defect was provided, as we shall see, may be
contemplated under Article 9.1. It is also true that
as far as the data and speech communication facility,
105 the first respondent has claimed that it was completed
on 23.03.2017. We have already referred to it also. The
stand of the fifth respondent is that there is approval
but it is only in principle. It is complained that till
date, the telemetry and voice communication was not
working, in spite of the fact that by letter dated
03.04.2017, relevant IP address for real time data
communication was furnished. It is not functional till
date, in the case of the first respondent, whereas, in
regard to its sister concern, it is operational. A
letter dated 14.10.2021 is produced to indicate that
the telemetry of the first respondent was not
integrated and no real time data was received from the
IP address provided to it. Even, in regard to this
matter, if an opportunity was to be given in law, to
the first respondent under Article 9.1, it is not
something which may be not achievable.
71. We are also dealing with these aspects on the basis
of an affidavit filed raising such issues for the first
time by the fifth respondent. The fifth respondent had
all the opportunity in the writ petition to raise such
contentions. Even in the Review Petition, there is only
106 adoption of the contentions of the appellant.
72. Emphasis is placed on the statement of Respondent
no.5 by respondent no.1 wherein it is stated “whereas
though the generating station is ready for generation
of power but the power cannot be evacuated into the
grid in the absence of transmission line”. This is
taken as an admission of the readiness of the first
respondent for generation of power. It is pointed out
further that necessary approval was taken before
December 2016 to August 2017 for operating the
transmission line. Respondent No.1 was not allowed to
commission. Reliance is also placed on the inspection
report of the appellant to show that the transmission
line was ready. The examples about other operators are
brushed aside as irrelevant. It is the generator’s
prerogative to sell power in the open market.
73. A Sur-Rejoinder is filed by respondent No.5.
Therein, it has interestingly produced its return in
the review petition filed by the appellant before the
High court. Therein we may notice that it referred to
Section 32(2) of the Electricity Act and its functions.
Thereafter it has stated as follows:
107
“3. That, in accordance with Electricity act, 2003, role of SLDC comes after commissioning of the generating plant and its evacuating transmission lines. On receipt of commissioning certificate of a generator, connectivity with the Grid, metering arrangement and other regulatory compliances, SLDC accords permission of injection of power into the Grid. Further, SLDC schedules power of generator to the beneficiary/ consumer if the valid Power Purchase Agreement exists between buyer and seller.
4. That, writ proceeding in the instant petition is regarding completion of commissioning of solar Generating Plant of M/s. Sky Power Southeast Solar India Pvt. Ltd., whereas the responsibility of SLDC begins after commissioning of the Solar Generating Plant and other regulatory compliances. As per provisions of Electricity Act, 2003 and MPEGC, commissioning certification is beyond the jurisdiction of SLDC.
6. That, the answering respondent is more of a formal respondent as the agreement was entered into between MPPMCL and the Original Petitioner in Writ Proceedings which is M/s. Sky Power.”
74. No doubt, it has also stated in paragraph-7 that
it adopts all the facts and grounds raised by the review
petitioner, namely, the appellant.
75. It will be noticed that though respondent no.5 was
a party to the earlier writ petition as much as it is 108 a party in the present writ petition, respondent no.5
has not filed any counter affidavit in either of the
writ petitions. It is only in the review petition that
the respondent no.5 has filed a reply and we have
noticed its stand. The stand appears to be that it is
more of a formal respondent. Its role comes in only
after commissioning. It is in this Court that there
has been blossoming of its case for the first time. It
is also admitted by respondent No.5 that it is not
concerned with the pre-commissioning. It is its
specific stand that all the activities prior to
readiness of the generator to inject power are beyond
its purview. It has specifically stated that its role
comes only after commissioning the project. First
respondent states that it has not commissioned the
project. Its only case is that it was ready to
commission the project within 24 months as provided in
the PPA but it was illegally prevented from doing it.
76. We may only observe that the fifth respondent has,
in the Sur-Rejoinder, owned up letter dated 23.03.2017
as the letter it has sent. The said letter is in the
letterhead of the fourth respondent and therein the
109 name of the fifth respondent is also shown. It would
appear that the fifth respondent is created under
Section 31 of the Electricity Act, 2003. Section 31
reads as follows:
“Constitution of State Load Despatch Centres.—(1) The State Government shall establish a Centre to be known as the State Load Despatch Centre for the purpose of exercising the powers and discharging the functions under this Part.
(2) The State Load Despatch Centre shall be operated by a Government company or any authority or corporation established or constituted by or under any State Act, as may be notified by the State Government:
Provided that until a Government company or any authority or corporation is notified by the State Government, the State Transmission Utility shall operate the State Load Despatch Centre:
Provided further that no State Load Despatch Centre shall engage in the business of trading in electricity.”
77. Therefore, it would appear to us that actually the
fifth respondent is to be operated by the State
Transmission Utility, which is defined in Section 2(67)
as the Board (defined as the State Electricity Board)
or the Government company specified by the State
Government under Section 39(1), unless it is operated
by a Government company or any authority or corporation
110 established or constituted by or under and State Act.
It would, therefore, appear to us that if the fourth
respondent is the State Transmission Utility, it would
be the Body to operate the fifth respondent. The
attempted disassociating of the fifth respondent from
the fourth respondent, appears to us to be without
justification. However, we leave the matter there. We
may conclude nearly that all the requirements were met.
There remained the metering requests and the aspects
about furnishing data. They clearly appear to be
matters which could have been remedied at any rate if
a default notice was given.
THE NARRATIVE RESUMES
78. At this juncture, we must make certain
observations. While the law has evolved from the
hands-off approach to one of contracts lending ground
for writ courts making a foray into decisions by State
and its instrumentalities even in contractual matter,
there are certain principles which we have already in
fact generally noticed. We have already found that the
contract in question, i.e., the PPA, is not a statutory
111 contract. We have also noticed that even if it is a
non-statutory contract, there is no absolute bar in
dealing with a cause of action based on acts or omission
by the State or its instrumentalities even during the
course of the working of a contract. We again reiterate
that a monetary claim arising from a contract may be
successfully urged by a writ applicant but the premise
would not be a mere breach of contract. Being part of
public law the case must proceed on the basis of there
being arbitrariness vitiating the decision. The matter
should not fall within a genuinely disputed question
of facts scenario. The dispute which must be capable
of being resolved on a proper understanding of
documents which are not in dispute may furnish a cause
of action in a writ court. Such was the case in ABL
(supra). What is this litigation all about? This
litigation is not about enforcing a monetary claim.
The writ petition lays a challenge to the termination
of the contract. A termination of the contract, no
doubt, again may not be immune if it is found to be
afflicted with the vice of arbitrariness. Interference
again may be refused if the court finds that the case
112 really belongs to the small area with unclear contours
where it can be appropriated as a private law dispute.
The distinction between public law and private law has
concededly been reduced to nearly imperceptible terms
but the distinction in law remains. As far as the
public law aspect is concerned, we are inclined to take
the view that in view of what has been laid down in Shri Vidhyarthi Lekha (supra), the impact of the action
in a contractual matter in the facts by public
authority is felt in public domain. We are dealing
with the action of the appellant in terminating the
contract dealing with the right to generate renewable
energy and for supplying it to the consumers. Supply
of power and its consumption are imperative and
indispensable needs for not only the common man but
also for the efficient functioning of trade and
industry. Decisions in this domain do impinge on public
interest. Therefore, we would not be inclined to shut
the doors on the first respondent in this matter. We
also bear in mind that this is the second round of
litigation. As noticed already, in the first round, the
first respondent did succeed.
113
79. Having found that though a non-statutory contract
and that there is no absolute prohibition against
judicial review on the score that action is shown to
be arbitrary, the questions which would fall for
further consideration are: (1) whether action is
arbitrary (2) the projected disputes of facts and their
impact; (3) what is the impact of the principle that
there must be overwhelming public interest in favour
of the writ applicant for the writ court to interfere.
THE ARGUMENT OF ‘OVERWHELMING PUBLIC INTEREST’
80. The case based on ‘overwhelming public interest
not being present in this case is based on the following
submissions by the learned Additional Solicitor
General. It is pointed out that under the PPA, if the
appellants are compelled to comply with the impugned
Judgment and that too for a period of twenty-five
years, it would be liable to purchase power at the rate
of Rs. 5.109/- unit. On the other hand, if the Writ
Petition filed by the first respondent is dismissed,
there would be no obligation and consequent burden. It
114 is important to notice that the appellant would be
compelled to pass on the burden to the ultimate
consumers. All of this is to be viewed in the scenario,
when power is available at a cheaper rate in the market.
In other words, public interest lies not in favour of
exercise of jurisdiction under Article 226 of the
Constitution of India. The High Court erred in not
bearing in mind this fundamental principle the argument
runs. The appellant relied on the decision in All India
Power Engineer Federation and others v. Sasan Power
Limited and others30, for the proposition that the Court
must be mindful of public interest, which consists of
interest of the consumers ultimately.
81. Per contra, the submission of the first respondent
is that the Court must not be oblivious to certain
facts. The rate per unit, in the case of the first
respondent, is Rs.5.109 per unit. In respect of another
project, where the PPA was entered into with a sister
concern of the first respondent, the project price was
Rs.5.298 per unit. The project stands commissioned. The
30 (2017) 1 SCC 487 115 tariff was arrived at on the basis of highly
competitive bids. There were, in fact, 183 bids. It is
further contended that the bid of the first respondent
was found to be the lowest in the competitive bidding.
The appellant is, in fact, buying power at higher
tariff from at least 5 generators, who commissioned
their projects in the year 2017-2018. It was further
contended that the daily demand of the appellant is
approximately 15000 megawatts. The quantum of the
project of the first respondent is only 50 megawatts,
which constitutes 0.33 per cent of the total demand.
Purchasing such a small capacity, in terms of the rate
under the PPA, would make no difference to the consumer
tariff. This is apart from countenancing the appellant
reneging on a binding contract, which involves reaching
a reward for arbitrary State action, besides,
destroying an investment of Rs.331 crores. In this
regard, reliance is placed on the Judgment of this
Court in Vice Chairman & Managing Director, City and
Industrial Development Corporation of Maharashtra Ltd.
and another v. Shishir Realty Private Limited and
116 others31. Public interest cannot be determined with
reference to monetary considerations alone, it is
pointed out.
82. As far as All India Power Engineer
Federation (supra) is concerned, in fact, the Court was
dealing with Civil Appeals, which were filed under the
Electricity Act, 2003. The question about public
interest arose in the context of the provision in the
contract, which provided for waiver, which would be a
unilateral act under Article 18.3 of the PPA therein.
The Court also discussed the effect of Section 63 of
the Indian Contract Act, 1872. The Court, while dealing
with waiver and public interest, held as follows:
“21. Regard being had to the aforesaid decisions, it is clear that when waiver is spoken of in the realm of contract, Section 63 of the Contract Act, 1872 governs. But it is important to note that waiver is an intentional relinquishment of a known right, and that, therefore, unless there is a clear intention to relinquish a right that is fully known to a party, a party cannot be said to waive it. But the matter does not end here. It is also clear that if any element of public interest is involved and a waiver takes place by one of the parties
31 (2021) SCC Online SC 1141 117 to an agreement, such waiver will not be given effect to if it is contrary to such public interest. This is clear from a reading of the following authorities.
xxx xxx xxx
25. It is thus clear that if there is any element of public interest involved, the court steps in to thwart any waiver which may be contrary to such public interest.”
83. In the said case, the Court further held that the
moment the electricity tariff gets affected, the
consumer interest comes in and public interest gets
affected and further that there is a statutory
recognition for the same in Sections 61 to 63 of the
Electricity Act, 2003. Therefore, this Judgment, though
in the context of a Statutory Appeal, has laid down
that consumer interest in tariff is intertwined with
public interest.
84. On the other hand, in Vice Chairman & Managing
Director, City and Industrial Development Corporation
of Maharashtra Ltd. (supra), this Court, while dealing
with a case involving the question of award of
contract, held as follows:
118
“58. When a contract is being evaluated, the mere possibility of more money in the public coffers, does not in itself serve public interest. A blanket claim by the State claiming loss of public money cannot be used to forgo contractual obligations, especially when it is not based on any evidence or examination. The larger public interest of upholding contracts and the fairness of public authorities is also in play. Courts need to have a broader understanding of public interest, while reviewing such contracts.”
85. In fact, the principle of public interest has found
expression in cases which involved challenge to the
legality of the award of contract.[See in this regard
Tata Cellular v. Union of India (1994) 6 SCC 65132
(supra) and Raunaq International Ltd. v. I.V.R.
Construction Ltd. and Others, (1999) 1 SCC 492.
86. In Michigan Rubber (India) Limited v. State of
Karnataka and Others33 after referring to Tata Cellular
and Raunaq International Limited (supra), the Court
inter alia held as follows: -
“35. As observed earlier, the Court would not normally interfere with the policy decision and in matters challenging the award of contract
32 (2017) 1 SCC 487 33 (2012) 8 SCC 216 119 by the State or public authorities. In view of the above, the appellant has failed to establish that the same was contrary to public interest and beyond the pale of discrimination or unreasonable.”
87. In Raunaq International Ltd. v. I.V.R. Construction
Ltd. and Others34 the case involved award of contract
for the purpose of Thermal Power Station. In fact, the
Appeals in this court were maintained against the grant
of an interim order against the appellant to whom the
contracts stood awarded. The case also involved
relaxation of the criteria which was based on valid
principles it was found. It was further found that the
construction of two Thermal Power Units was being held
up due to the dispute. The Court, inter alia, held as
follows: -
“9. However, because the State or a public body or an agency of the State enters into such a contract, there could be, in a given case, an element of public law or public interest involved even in such a commercial transaction.
10. The elements of public interest are: (1) Public money would be expended for the purposes of the contract. (2) The goods or services which are being commissioned could be for a public purpose, such as, construction of roads, public buildings, power plants or other public utilities. (3) The public would be directly
34 (1999) 1 SCC 492 120 interested in the timely fulfilment of the contract so that the services become available to the public expeditiously. (4) The public would also be interested in the quality of the work undertaken or goods supplied by the tenderer. Poor quality of work or goods can lead to tremendous public hardship and substantial financial outlay either in correcting mistakes or in rectifying defects or even at times in redoing the entire work — thus involving larger outlays of public money and delaying the availability of services, facilities or goods, e.g., a delay in commissioning a power project, as in the present case, could lead to power shortages, retardation of industrial development, hardship to the general public and substantial cost escalation.
11. When a writ petition is filed in the High Court challenging the award of a contract by a public authority or the State, the court must be satisfied that there is some element of public interest involved in entertaining such a petition. If, for example, the dispute is purely between two tenderers, the court must be very careful to see if there is any element of public interest involved in the litigation.
A mere difference in the prices offered by the two tenderers may or may not be decisive in deciding whether any public interest is involved in intervening in such a commercial transaction. Price may not always be the sole criterion for awarding a contract.”
88. Therefore, on a conspectus of the case law, we find
that the concept of overwhelming public interest has
essentially evolved in the context of cases relating to
the award of contract by the State. It becomes an
important consideration in the question as to whether
121 then the State with whatever free play it has in its
joints decides to award a contract, to hold up the
matter or to interfere with the same should be
accompanied by a careful consideration of the harm to
public interest. We do not go on to say that
consideration of public interest should not at all
enter the mind of the court when it deals with a case
involving repudiation of a claim under a contract or
for that matter in the termination of the contract.
However, there is a qualitative difference in the
latter categories of cases. Once the State enters into
the contract, rights are created. If the case is brought
to the constitutional court and it is invited to
interfere with State action on the score that its action
is palpably arbitrary, if the action is so found then
an appeal to public interest must be viewed depending
on the facts of each case. If the aspect of public
interest flows entirely on the basis that the rates
embodied in the contract which is arbitrarily
terminated has with the passage of time become less
appealing to the State or that because of the free play
of market forces or other developments, there is a fall
122 in the rate of price of the services or goods then this
cannot become determinative of the question as to
whether court should decline jurisdiction. In this
case, it is noteworthy that the rates were in fact
settled on the basis of international competitive
bidding and in which as many as 182 bidders participated
and the rate offered by the first respondent was
undoubtedly the lowest. The fact that power has become
cheaper in the market subsequently by itself should not
result in non-suiting of the complaint of the first
respondent, if it is found that a case of clear
arbitrariness has been established by the first
respondent.
89. In other words, public interest cannot also be
conflated with an evaluation of the monetary gain or
loss alone.
POINTS NO. 6 - 8 AND 10
90. The time is now ripe to take a closer look at the
relevant clauses of the PPA. Article 2 deals with the
pre commissioning activities. Article 2.1 deals with
satisfaction of the conditions subsequent by the
123 respondent. Clause 2.1.1 contemplates that the
respondent must complete all the conditions which are
set out at his own cost and risk within 210 days from
the effective date. The only two exceptions were ‘force
maejure’ or if any of the conditions subsequent was
specifically waived by the appellant in writing. The
consequences of non-fulfilling the condition subsequent
is dealt with in Article 2.2 which related to force
majeure obstructing the fulfilment of the conditions
subsequent. Article 2.2.2 in fact provided that any
increase in the time period for completion of the
conditions subsequent mentioned under Article 2.1 would
also lead to an equal extension in the scheduled
commissioning date. Article 2.5 provided for delay in
achieving the conditions subsequent. Article 2.5.1
reads as follows:
“2.5.1. In case of delay in achieving any of the Conditions Subsequent under clause 2.1 (a to h), as may be applicable, MPPMCL shall encash CPG (submitted by Seller @ Rs. 30 Lakhs/MW) as under, subject to Force Majeure: -
a) Delay from 0-3 months - 1 % per week.
124 b) Delay from 3-6 months - 2% per week for the period exceeding 3 months, apart from (a) above.
c) Delay from 6-9 months - 3% per week for the period exceeding 6 months, apart from (a) and (b) above.
d) In case of delay of more than 9 months, MPPMCL shall terminate PPA and release balance amount of CPG."
91. Thereafter, PPA deals with the aspect of
commissioning. Article 2.6 deals with commissioning
and it reads as follows:
“2.6. COMMISSIONING In case of Solar Project of capacity up to 50 MW, commissioning of plant shall be within 12 months from the date of financial closure subject to Force Majeure. In case of Solar Project of capacity beyond 50 MW and up to 100 MW, commissioning of plant shall be within 15 months from the date of financial closure subject to Force Majeure For capacity beyond 100 MW, commissioning period shall be within 18 months from the date of financial closure subject to Force Majeure..1
In case of failure to achieve this milestone, provision of PPA as mentioned below shall apply: -
MPPMCL shall en cash the CPG in the following manner for the capacity not commissioned, subject to Force Majeure:-
125 a) Delay from 0-3 months - 1% per week.
b) Delay from 3-6 months - 2% per week for the period exceeding 3 months, apart from (a) above..
c) Delay of more than 6 months – 3% per week for the period exceeding 6 months, apart from (a) and (b) above.
Part Commissioning: In case of Solar PV Projects, Part commissioning of the Project shall be accepted by MPPMCL subject to the condition that the minimum capacity for acceptance of part commissioning shall be 5 MW. Or in multiple of 5 MW
COD means the commissioning date of just units (s) of the power project where upon the seller starts injecting power from full contracted capacity of the power project to the delivery point; as approved by competent authority of the Transco/Discom. The PPA will remain in force for a period of25 month from the COD.”
92. There are other Articles which need not detain us.
Article 3 deals with Supply Arrangements under Open
Access. Article 3.1.1 reads as under:
“3.1.1. The power generated through 50 MW Solar Power Project (PY/Thermal Technology) installed by the Seller Located at Village bedhsya, Tai: Khandwa, Dist: Khandwa, State: Madhya Pradesh shall be injected into the Transmission/Distribution system of
126 Transco/Discom on 33kV or above side of 33kV /EHV Substation situated at Deshgaon at injection point for sale to MPPMCL, subject to fulfilling the terms and conditions and protection schemes by the Seller as approved by the concerned Transco/Discom's.
3.1.2. The Seller shall ensure to interconnect and operate the solar power plant in parallel with the grid of Transco/Discom (in the area of the location of the generating unit) system subject to the terms and provisions of this agreement. The Seller shall be fully responsible for obtaining and maintaining any or all licenses and permissions required by law. The Seller shall abide by any law, rules, regulations or any notification or order issued there under by the Central Govt. or State Govt. or Commission or Local Authority or any other Authority prescribed under the law connected with the project of the Seller.
The Seller shall be fully responsible for the design, construction, testing, operation and maintenance of the solar power plant in accordance with Standard Utility Practices, relevant technical standards and specifications.
b) For the power plant situated in MP State, the power evacuation infrastructure laid by the Seller shall be the property of the concerned licensee (Transco/Discom) in whose territorial area the above lines are located -
notwithstanding the fact that the cost of the said infrastructure has been paid by the Seller and the same . shall then be maintained by the concerned licensee at its cost. A separate transfer agreement 127 shall be subsequently signed in this regard with the concerned licensee, if required.
3.1.3. The Seller shall obtain all statutory and non-statutory permissions as required. The seller supplying power from outside of MP State shall require to obtain long term open access permission as per relevant regulations of central and state regulators, as the case may be, from the state or regional load dispatch center and/or the state/central transmission utilities.”
93. Article 4 deals with System Operations. Article
4.2 deals with system operation and scheduling. We may
notice Articles 4.2.1 and 4.2.4.
“4.2.1. The State Load Despatch Center shall be the Nodal Agency if the project is located in MP, for system operation, power accounting, scheduling, etc. The foes and charges of SLDC as approved by the MPERC shall be payable by the Seller to the SLDC. In case of the system is located in any other state, the Seller has to follow the regulations of the particular SLDCIRLDC and the fees and charges shall be payable by the seller accordingly.”
“4.2.4. SLDCs/Control Centers of the States/UTs/DVC, in which the solar power plant is located, shall provide the 15- minute block-wise data of schedule and actual generation from Solar Grid Connected Power Plant as recorded in the Energy Meters to the concerned RLDC and NLDC on a weekly basis as per the requirement of SLDCIRLDC/NLDC. All the
128 data shall be submitted in the form prescribed by the NLDC.”
94. Article 4.3 deals with open access. Article 5.1
deals with commercial operations date (COD). COD has
been defined in the agreement as meaning the
commissioning date of the last unit(s) of the power
project whereupon the seller starts injecting power
from full contracted capacity of the power project to
the delivery point as approved by competent authority
of the TRANSCO/DISCOM. DISCOM has been defined as a
licensee authorised to operate and maintain a
distribution system for supplying electricity to the
consumers in the State of Madhya Pradesh. Article 5.1
reads as under:
“5.1. COMMERCIAL OPERATIONS DATE
The Commercial Operation Date of the plant shall mean the commissioning date of last unit (s) of the power project where upon the seller starts injecting power from contracted capacity of the power project to the delivery point as approved by competent authority of the Transco/discom.
After Each part commissioning and/por CoD of the contracted capacity, the commissioning certificate (s) certified by Transco/Discom shall be attached as
129 Annezure- XII to the Power Purchase Agreement
However part commissioning of the plant shall be accepted as laid out in clause 2.6 and the energy supplied from the same shall be considered for billing and payment of the energy supplied from such commissioned units.”
95. Article 5.2. deals with Pre-Commercial Operations
and it inter alia provides that the discom shall take
all power produced through the STU/CTU during the
testing of the plant without any charges. Thereafter
5.3 deals with Notice of Commercial Operations. It
reads as follows:-
“5.3 NOTICE OF COMMERCIAL OPERATIONS:-
The Seller will specify in a written notice to the MPPMCL that:
a) The Plant is constructed in accordance with this Agreement and is ready to deliver Solar Power in accordance with the terms hereof;
b) All permissions and approvals required for the Plant to sell Solar Power at the rates and terms specified under this Agreement have been obtained and
c) All interconnection facilities are available to receive Solar Power from the Plant.
Such notice shall take effect and the Commercial Operations Date will be achieved following the Transco/Discom’s declaration that all of the conditions set forth in this Article have been satisfied or waived by the STU/CTU/MPPMCL/Transco/Discom i.e.:
a) The Seller has successfully completed 130 the testing of the Plant in accordance with the manufacturer’s recommendations and the Seller has obtained and provided to the STU/CTU/Transco/Discom Certificates from the Electrical Inspectorate of GoMP or any other state government authorised agency, and the STU/Transco/Discom’s officer as may be designated; in case project is located in MP. In case project is located outside MP, similar certificates be obtained from the concern authority of respective state.
b) The Seller has delivered to the Transco/Discom a list of the Plant’s equipment, showing the make, model, serial number and certified the installed capacity of the Plant;
c) The Plant has achived initial synchronization with the
Transco/Discom’s/STU/CTU Grid System and has demonstrated the reliability of its communications systems and communications with the STU/CTU/Transco/Discom;
d) The Seller has operated the Plant without experiencing any abnormal or unsafe operating conditions on any interconnected system;
e) The Seller shall also have notified the MPPMCL/Trancso/Discom/STU/CTU no later than 30 days prior to the Commercial Operations Date that all the Conditions Subsequent as laid out in clause 1.01 have been met and MPPMCL shall verify the same and shall provide the Seller a written endorsement in this behalf acknowledging the documents, certificates, approvals etc provided by the Seller in this regard.”
The respondent was duty bound to notify to the
appellant that the plant is constructed as per PPA and 131 it was ready to produce solar power and that all
permissions and approvals to sell power at the rates
and terms under the agreement had been obtained and all
inter connection facilities were available to receive
solar power from the plant. The PPA further
contemplates that the said notice would take effect and
the COD be achieved upon the TRANSCO/DISCOM declaring
that all conditions in this Article were either
fulfilled or waived. The PPA further deals with Sale
and Purchase of Solar Power in Article 6 commencing at
COD date. The seller, that is, the respondent was to
sell and the appellant was to purchase and accept 50MW
solar power at the point of delivery. The respondent
undertook not to sell any solar power (all of which is
committed to the appellant) to any other person.
Article 7 deals with Metering and Measuring. Article 8
deals with Billing and Power Accounting. Article 9
deals with Events of Default and Remedies. Article 9.1
is relevant and it deals as follows:
“9.1. DEFAULTS AND TERMINATION.
In case of default, the non-defaulting party shall issue a default notice to the defaulting party. If the default is not
132 fully set right within three months from the date of issue of the default notice, then in case of default by the Seller, the MPPMC.L by giving seven days termination notice in writing, may terminate the agreement. In case of default by MPPMCL, the Seller may in the same way terminate the agreement.”
96. Article 9.4 deals with various events which are
described as seller event of default. The relevant
provision reads, inter alia:
“9.4. SELLER EVENT OF DEFAULT
The occurrence and continuation of any of the following events, unless any such event occurs as a result ofa Force Majeure Event, shall constitute Seller Event of Default:
a) The failure to commence supply of power to MPPMCL up to the Contracted, · Capacity, relevant to the Scheduled Commissioning Date, by the end of 24 months; or”
97. Article 9.5 provides for appellant’s events of
default. Article 9.7 falling under 9.6 which generally
deals with ‘Remedy’. It reads as follows:
“9.7. MPPMCL commits to buy power, as indicated in Article Error! Reference source not found. of PPA, from Seller at Rs. 5.051 per kWh for a period of 25 years from COD. In case MPPMCL refuses or is unable to buy the said power, fully or partially, or there is an event of default
133 as per Clause 9 .5 of PPA leading to termination of the PPA, the seller would be free to sell the said power to a Third Party at any rate which will be decided between the Seller and the said Third Party and such sale would be governed by the following principles:” (Emphasis supplied)
The principles are set out providing for two cases.
98. Article 11.6.3 deals with Change in Law. Article
13 deals with Jurisdiction and Dispute Resolution.
Article 13.2.1 reads as follows:
“13.2.1. Either Party is entitled to raise any claim, dispute or difference of whatever nature arising under, out of or in connection with this Agreement ("Dispute") by giving a written notice (Dispute Notice) to the other Party, which shall contain:
• a description of the Dispute;
• the grounds for such Dispute; and • all written material in support of its claim
13.2.2. The other Party shall, within thirty (30) days of issue of Dispute Notice issued under 13.2.1, furnish:
• counter-claim and defences, if any, regarding the Dispute; and
• all written material m support of its defences and counter-claim.
13.2.3. Within thirty (30) days of issue of Dispute Notice by any Party pursuant to Article 13 .2.1 if the other Party does 134
- not furnish any counter claim or defence under Article 13.2.2 or thirty (30) days from the date of furnishing counter claims or defence by the other Party, both the Parties to the Dispute shall meet to settle such Dispute amicably. If the Parties fail to resolve the Dispute amicably within thirty (30) days from the later of the dates mentioned in this Article, the Dispute shall be referred for dispute resolution in accordance with Article 13.3.”
99. Article 12.2 reads as follows:
“12.2 GRID CODE DISCIPLINE The concerned Transco/Discom and the Seller shall observe the State/Indian Electricity Grid Code or its amendment if any, and operate their systems to the best of their capacity and resources.”
100. Article 13.3.1 reads as follows:
“13.3.1. Where any Dispute arising from a claim made by any Party for any matter related to Tariff or claims made by any Party which partly or wholly relate to any change in the Tariff or determination of any of such claims could result in change in the Tariff, shall be submitted to adjudication by the MPERC. Appeal against the decisions of MPERC shall be made only as per the provisions of the Electricity Act, 2003, as amended from time to time.”
101. Article 15.1.4. deals with Compliance with Law and
in substance it provides that the provisions of the
Electricity Act, 2003 will prevail in case of
135 repugnancy or deviation from the terms of the agreement
from the Act.
102. In the impugned judgment the High Court has
proceeded to hold inter alia that the respondent has
invested Rs. 350 crores in establishing the unit and
after replacing the stolen parts, the unit is ready for
commissioning on any date. The High court has further
proceeded on the basis that the project involved two
milestones and the High court has set aside the earlier
order which dealt with delay in achieving the first
milestone. Thereafter, the finding is that the project
was certified to be completed much prior to 24 months
which period ended on 19.9.2017 and the notice of
commissioning was given on 4.7.2017. The CEIG approval
was also granted on 9.8.2017. It is further found that
another inspection was done on 19.04.2018 after nine
months of the notice of commissioning and the CEIG
approval. It is despite the same that the impugned
order has been passed. Still further the High court
proceeds to find that it is undisputedly established
that both the milestones of the project were completed
whereas only some of the invertors were stolen for
136 which an FIR was also lodged. It is again found that
it is not in dispute that the aforesaid parts have been
replaced by the respondent. Support was drawn from the
case of Renew Energy and the courts discretion to
interfere in the matter was reiterated. The decision
was found to be arbitrary. The court directed the
respondent to file necessary application for statutory
sanction for operation of the unit and the appellant
was to decide on the application. To complete the
narrative a review petition, was filed by the
appellant. The appellant sought to project the aspect
of fraud. The fraud consisted of the act of the
respondent relying on unique/distinctive serial
numbers of the invertors in regard to a number of
invertors which were found to be common/duplicate. In
other words, the case of the appellant was that the
project for 50 MV was divided into 10 blocks of 5
megawatt. Each block had 116/117 invertors. A fraud was
committed on the CEIG. In other words, it was the
appellants case that the respondent had not complied
with the PPA in regard to the installing of the required
number of invertors. The first respondent took the
137 stand that the all the serial number of the invertors
were quite legible though the contrary was contended.
The CEIG reported the physical readiness of the project
for commissioning. The respondent also drew upon the
inspection report of the appellant itself. The High
Court bearing in mind the limited jurisdiction
dismissed the review.
103. In the impugned Termination Notice dated
07.07.2018, after referring to the delay of 54 days in
fulfilling condition subsequent, it is mentioned that
the commercial operation date, as per
Article 2.6, was 14.04.2017. It was indicated that
there was no indication regarding commissioning against
the column ‘readiness of plant’ as on 11.08.2017. The
last date for commencement of supply was shown as
18.09.2017. The expiry date of three months period for
commencement of supply from the last due date was
18.12.2017. It is further provided that the expiry date
of seven days of PPA Termination Notice period was
25.12.2017. The status of the project as on 19.04.2018
was indicated as ‘not ready for commissioning’.
Thereafter, it is pointed out that there is no
138 justification for delay in achieving condition
subsequent. Still further, reference is made to the
Order passed by the High Court in the earlier Writ
Petition. Physical verification was carried out on
19.04.2018, whereupon, it was found that installation
work of plant and equipment was incomplete in Blocks 9
and 10. It was further pointed out that the copy of
the Inspection Report was enclosed, where installation
of invertors, installation of solar EV panels,
cabelling and earthing work, was yet to be completed.
It was further pointed out that even after more than
six months, after deadline of commissioning of project,
the plant is not ready for commissioning. Thus, there
was not only failure to achieve condition subsequent
but also failure to commission the project within time.
In comparison with the case of Renew Clean Energy, it
is pointed out that apart from failure to comply with
condition subsequent, even the outer timeline has not
been observed, whereas, in the case of Renew Clean
Energy, they were ready to commission by the scheduled
commissioning date. The timeline under Article 9.1 was
not conformed to. After referring to the Order of the
139 High Court, it was found that, with reference to
Article 2.5.1(d) and Article 9.1 of the PPA, the PPA
was terminated.
104. Let us demystify the case for termination. Apart
from non-fulfilment of the condition subsequent,
apparently, in tune with the liberty granted by the
High Court, the appellant has set out a case that the
last date of commencement of supply was 18.09.2017, and
even as on 19.04.2018, the respondent was not ready for
commissioning of the project. With reference to
Articles 5.1, 5.2 and 5.3 of the PPA, which consisted
of the commercial operation date, pre-commercial
operation and notice of commercial operation, it is
stated that the respondent has not intimated regarding
the schedule of commissioning, till the date of the
Termination Notice. A distinction is sought to be drawn
between Renew Clean Energy and the respondent, in that
the case of the first respondent, even the first
respondent was not ready to commission the project
within the stipulated time.
105. The case that the first respondent has projected
in the Writ Petition, on the other hand, is, inter
140 alia, as follows:
On 04.07.2017, while issuing letter to
respondent no.4, it issued notice for
commissioning by 31.07.2017, in terms of Article
5.1(c) of the PPA. Site inspection by the appellant
was solicited through its EPC. The respondent
obtained approval from the CEIG for commissioning
on 09.08.2017. The CEIG certified that all
infrastructure and installation pertaining to the
project were ready and the respondent may proceed
with the commissioning activities. CEIG approval
is requirement under Article 5.3(a). However, the
appellant proceeded to terminate the PPA by Order
dated 07.07.2018. Thus, it is stated that the
appellant, for reasons best known to it, chose to
ignore the first respondent’s request for
proceeding with the commissioning of the project.
The respondent also obtained in principle
connectivity for the project from the appellant.
It is the specific case of the respondent that
prior to 11.08.2017, first respondent had received
intimation from its EPC Contractor that the project
141 was ready for commissioning barring minor works
pending completion such as construction of
shed/cubical for the Guard which would have no
bearing on the project commissioning. The
respondent pointed out that the appellant was
obliged to issue default notice under Article 9.1
of the PPA. The respondent was entitled for a
period of three months. No such notice was issued.
As far as the Report of the Inquiry Committee dated
19.04.2018, relied on by the appellant, it is
pointed out that the challenge to the earlier
termination notice was pending and the respondent
was constrained to demobilise its staff/security
guards. Thefts took place. It is pointed out that
these thefts took place after the certification by
the CEIG. In other words, the respondent would
blame the appellant for not conducting an inquiry
immediately after the certification by the CEIG.
It is also the case of the first respondent that,
through its EPC Contractor, it had procured, inter
alia, 1163 string invertors. Some of the string
invertors were stolen, as stated earlier. That the
142 case of the respondent is not that the project had
been commissioned but that the appellant prevented
it from commissioning the project before the last
date. It is also seen stated that the project was
complete in all respects from the side of the
respondent but on account of theft of a very small
number of equipment, highlighted by the appellant
in its Inspection Report, the first respondent had,
in the meanwhile ensured to get these miscellaneous
equipments and parts reinstalled and the project
was complete in all respects as on that date. As
far as the theft is concerned, the first respondent
had lodged two FIRs through its EPC Contractor well
before the inspection carried out on 19.04.2018.
THE ASPECT OF DISPUTED QUESTIONS OF FACTS
106. What are the disputed questions of facts? The most
important disputed question of fact is as to whether
the first respondent was, in fact, ready to commission
the project by the end of the peremptory date, which
was fixed as a period of twenty-four months from the
date of the agreement. On the one hand, the appellant
143 would contend that first respondent was not ready to
commission the project. This is for the reason that in
the 9th and the 10th Blocks, certain string invertors
were found missing. On the other hand, the case of the
respondent is based on the Report of the CEIG, which
would show that the respondent was ready to commission
the project. As far as the CEIG Report is concerned,
the case of the appellant appears to be that the
respondent had played a fraud in obtaining the CEIG
Report. This was unsuccessfully canvassed before the
High Court in the Review Petition. In other words, the
case sought to be set up by the appellant is that as
many as 272 string invertors were bearing duplicate
numbers and, therefore, it was being held out by the
first respondent that it had performed its contractual
obligation, when it was not the case. As far as the
delay of 53 days in fulfilling the conditions
subsequent is concerned, there is no dispute that there
was such a delay. Though, an attempt was made by the
first respondent to contend that in view of the
amendment substituting one of the conditions
subsequent, viz., the condition relating to land and,
144 therefore, there would be further extension of time.
We do not think that we can allow the first respondent
to set up such a plea. However, we have already
concluded that the issue as to the right or power of
the appellant to terminate the PPA on account of the
delay of 53 days, may not be open to the appellant, in
view of the Judgment of the High Court.
107. The learned Senior Counsel for the first
respondent, Dr. A.M. Singhvi, would, in fact, contend
that this Court may proceed on the basis that actually
there is a disputed question of fact. This is on the
reasoning that even if this Court proceeds on the basis
of the Inspection Report dated 19.04.2018, a miniscule
percentage of Rs. 350 crores would be the subject
matter of the lacunae that was pointed out by the
Inspecting Team in its Report dated 19.04.2018. It is
pointed out that the first respondent should not be
visited with the highly arbitrary decision to terminate
the PPA when nearly Rs. 350 crores have been sunk into
the project. The project itself is an environment
friendly project. An unusually large number of
competitors had bid in the bidding process and the
145 first respondent had emerged as a lowest bidder, which,
at that time was hailed.
THE CASE UNDER ARTICLE 9.1 READ WITH ARTICLE 9.4(a)
108. One of the grounds taken by the first respondent
against the termination notices is that it is issued
without complying with Article 9.1 of the PPA. We have
already adverted to the said Article. We have also
referred to Article 9.4.(a). Let us divine what is
contemplated under the PPA. The PPA contemplates
Article 9 with its sub-divisions to provide for events
of default and remedies. Under Article 9, the sub-
Articles provide for seller’s event of default and the
appellant’s Event of default. Reading Article 9.1 with
Article 9.4 and, more particularly, Article 9.4.(a),
which alone is relevant, we understand the following
to be what is contemplated by the parties. Article 9.1
begins with the words ‘in case of default’. The default
in the case of seller’s event of default would be the
default, which is the subject matter of the
termination. Here, we can safely conclude that the
seller’s event of default, which is apposite, is the
146 failure to commence the supply of power to the
appellant at the contracted capacity, relevant to the
scheduled commissioning date by the end of twenty-four
months. The words ‘scheduled commissioning date’, have
been defined in the PPA itself, to mean, for solar
project of capacity 50MW as per the quantum indicated
in LOI, the commissioning period allowed shall be
nineteen months from the date of signing of the PPA.
The period of twenty-four months must be reckoned from
the date of the PPA and, so understood, since the date
of the PPA is 18.09.2015, twenty-four months therefrom
would expire on 18.09.2017. We, therefore, proceed on
the basis that such an event, constituting default on
the part of the first respondent, had taken place.
Continuing with the analysis of Article 9.1, what was
expected of the appellant was, as the non-defaulting
party, to issue a default notice to the defaulting
party, viz., the seller, which in this case is the
first respondent. Article 9.1 further clearly
contemplates that if the default is not fully set right
within three months from the date of issue of the
default notice, then, in the case of default by the
147 seller, the appellant was to serve a seven days’ notice
of termination. The notice was, undoubtedly, to be in
writing. It is by the second notice, which is to be of
the duration of seven days that the appellant could
validly terminate the agreement. Thus, PPA clearly
indicates the issuance of a default notice when seller
commits an act of default. Without issuing the first
default notice, giving three months’ time from the date
of issue of the notice, the second notice, which would
be a notice of termination, cannot be issued.
109. Now, let us find whether the appellant has followed
this procedure. In the impugned termination notice
dated 07.07.2018, what is indicated in a Table in
paragraph-9 is that there was a delay of 54 days in
the matter of fulfilment of conditions subsequent and
the scheduled commercial operation date, as per Article
2.6 was 14.04.2017. 11.08.2017 is noted as the date of
notice of termination. 18.09.2017, being the end of
twenty-four months from the date of signing of the PPA
is shown as the last date of commencement of supply of
the contracted capacity and Article 9.4 is referred to.
18.12.2017 is shown as the expiry date of three months,
148 apparently, from 18.09.2017, for commencement of supply
from the last due date. Thereafter, 25.12.2017 is shown
as the expiry date of seven days of the PPA termination
notice period. In paragraphs-21, 22 and 23 of the
impugned notices, the appellant takes the following
stand:
“21. As per table-I, time line for commissioning of project has been indicated. You were required to adhere to st1pulated provisions of the PPA. Whereas this has not been achieved by you, within the time line even considering provisions of Article 9.1 of the PPA i.e., 24 months (supply to power to. contracted capacity from date of PPA) + 3 months (default notice period) + 7 days (termination notice period), from the signing of the PPA have already being exhausted.
22. Whereas, in light of showcause notice issued vide this office letter no. 108 dated 22.02.2017 and liberty granted " by Hon'ble Court to MPPMCL, in its order dated 20.06.2018 for issuing fresh order in terms of PPA dated 18.09.2015 to you, in accordance with law, it is evident that you have failed to fulfil your contractual obligation as per PPA executed with you on 18.09.2015. Thus, the PPA qualifies for termination.
23. Therefore, in line and in compliance to the Hon'ble High Court judgment dated 20.06.2018 and pursuant to the provision under Article-2.5.1 (d) along with the consideration of the timeline stipulated in Article 9 .1 of the PPA and showcause notice 149 dated 22.02.2017, the PPA signed on 18 Sept.
2015, between Mis Sky Power Southeast Solar India Pvt. Ltd. New -Delhi, (SPV of Parent Company Sky power Southeast Asia Holding 2 Ltd.) and MPPMCL, for supply of Power from the proposed, 50MW. Solar PY plant located at Village-Bedhaya District - Khandwa and subsequently location changed to Village Chhibel, Teb-Khalliiwa, Distt- Khandwa at a rate of Rs. 5.091 per unit, is hereby terminated.”
110. Thus, we find the twenty-four months period from
the date of the PPA, plus three months default notice
period, plus seven days termination notice period, had
been already exhausted. In paragraph-22, support is
sought to be drawn from the show-cause notice dated
‘22.02.2017’ and the liberty granted by the High Court
in the first Writ Petition, for issuing a fresh Order.
The PPA, it was found by the appellant, qualified for
termination. In paragraph-23, it is explicitly stated
that based on Article 2.1.1(d) along with the timeline
stipulated in Article 9.1 and the show-cause notice
dated 22.02.2017, the PPA was terminated.
111. Therefore, the show-cause notice dated 22.02.2017
is what the appellant lays store by to conclude that
it was acting in compliance with the requirement of
150 issuance of the default notice under Article 9.1. It,
therefore, becomes necessary to advert to the notice
dated 22.02.2017. We may extract the following:
“MP POWER MANAGEMENT COMPANY LIMITED CIN: U4010MP2006SGC018637 (A Govt. of M.P. UNDERTAKING) Regd. Office: Shakti Bhawan, Rampur, Jabalpur, Madhya Pradesh, india-482008, Tel: 0761-2661111;-
2660500, Fax: 0761- 261696, website:-
www.mppmcl.com, email: md@mppmcl.com,
No. 05-01/Solar Bidding-III/PP A/108
'Jabalpur Date 22.02.2017
To, M/s Sky Power Southeast Solar Pvt. Ltd. 16A/20 W.E.A. Main Ajmal Khan Road, Karol Bagh, New Delhi-110005.
Subject: submission of documents for fulfilment of condition subsequent in respect of your 50MW Solar Power project proposed at Village Chhirbel, Tallika Dist Khandwa under Phase-III solar competitive bidding.
Ref: 1. Power purchase Agreement executed on 18.09.2015.
2. Your letter No. SKP/MP/SOLAR/MPPMCL/2015-
116/06, dated 12.01.2017
Dear Sir,
With reference to your latter cited above, this is to intimate that on scrutiny of the documents submitted by you for fulfilment of condition subsequent after 210 days from signing of PPA. In respect of your 50 MW solar power project proposed at village Chhirbel, Taluka & dist Khandwa, status of the documents found as under:
151
Sr. Location Status of Status of Details of land acquisition No. Proposed grid financial in connectivity closure PPA/Final Location Acqu- Mode of Remarks ired acquisition land in hectar e BEDHSYA, In principal Loan 99.06 64.94 HEET, Out of Khandwa/ connectivity sanction UNDER 34.12 chhibel issued by letter of REGISTERED Heet… Khandwa Transco vide M/s L&T SALE DEED 34.12 only letter No.04- finance HEET under 7.28 is 02/PSP-147-LI vide unregistered undue & 1.2/95 letter sale deed for Regi-
No.LTF/89 12 months only stered 7, Jabalpur, 2567/16- from Sterling sale dated 17 dated Wilson to sky deed to 19.10.16, 29.08.16, power Sterling which is L&T INFRA , generally vide balance found in letter is undue order No. Sauda S07201A0/ Raseed 16-17, to dated Sterling 29.08.16, Wilson copy of on facility Rs.500/- Agreement Stamp and Paper. affecting complian- ces documents as stated in above letters are require to be submitted .
D.G.M. (Commercial-3) R.0., MPPMCL, Bhopal
Chief General Manager (Commercial): Block No. 11, Shakti Bhawan, Rampur, Jabalpur (MP) 482008 Tel: 0761-2661245, 2702404, Fax: 0761-2661245, email: makarand.chincholkar@mppmcl.com
152 It needs to be mentioned here that as per provisions of amended clause 2.1 (f) of the PPA pertaining to acquisition of land for the project, Seller shall be required to furnish the following ~ documentary evidence:-
• Ownership or lease hold right (for at least 30 years) or right to use permission (for revenue land in Madhya Pradesh) in the name of seller and possession of 100% of the area of the land required for the allotted project.
• Requisite documents from the concerned and competent revenue registered authority for the acquisition ownership vesting of the land in the name of the seller and in case of private land clear title for ownership and/ or registered lease deed for land taken on lease.
As can be seen from the above table you have submitted clear title for ownership for only 64.94 hectare land. whereas for 34.12 hectare land you have submitted unregistered lease deed for only 12 months, which cannot be considered for fulfilment of condition subsequent as per provisions of the PPA as mentioned above.
Further, as per provision of clause 2.5.l (dO of the PPA, referred PPA is liable for termination. Therefore, you are requested to submit your explanation/ justifications, if any, within 10 days from the issue of this letter, for further - necessary action in the matter.
Chief General Manager Commercial MPPMCL, Jabalpur”
112. A perusal of this notice, would reveal the
following:
The subject matter of the said notice appears to
be the fulfilment of condition subsequent. It is
clearly mentioned that as per Article 2.5.1, the
153 PPA was liable for termination. The first
respondent was asked for the explanation within
ten days from the date of the letter for further
necessary action in the matter.
We are of the view that the said notice cannot
qualify as one which was issued as a default notice
under Article 9.1. We have already found that
Article 9.1, dealing with default, which in this
case, is the default by the seller, and,
furthermore, the default being non-observance of
the time limit of twenty-four months from the date
of agreement dated 18.09.2015, the notice dated
22.02.2017, could not have been issued, even before
the expiry of the period of twenty-four months from
18.09.2015. In other words, the seller’s event of
default under Article 9.4(a) could have become the
subject matter of a notice under Article 9.1 only
if there was failure on the part of the first
respondent to supply power, as provided in Article
9.4(a), within twenty-four months. That point of
time, viz., the expiry of twenty-four months from
154 18.09.2015, would arrive, at the earliest, only on
18.09.2017. Therefore, it is only after 18.09.2017
that the first notice or, what is described as the
default notice, could have been issued by the
respondent under Article 9.1. Apparently, what has
happened is the appellant has combined the default
alleged with reference to Article 2.5.1(d), to
which, undoubtedly, notice dated 22.02.2017, could
be said to be related and has projected the said
show-cause notice as the default notice within the
meaning of Article 9.1 read with Article 9.4.
Article 9.1 contemplates a default, the issuance
of default notice and, most importantly, giving a
period of three months for the seller (first
respondent) to set right things. It is if the
seller does not remedy the matter within three
months, that the second notice, which is
essentially an Order of termination of the PPA,
can be issued. A perusal of the notice dated
22.02.2017 does not make any reference to the
seller’s event of default contemplated in Article
9.4.(a). The reasons are not far to seek. For the
155 reasons, which we have indicated hereinbefore, the
notice could not have been issued based on there
being a seller’s default within the meaning of
Article 9.4.(a) on 22.02.2017. We reiterate that
as on 22.02.2017, the seller’s event of default
under Article 9.4.(a), could not exist in law or
in facts. Still further, we notice from the tenor
of the notice dated 22.02.2017 that the first
respondent was, in fact, asked to give its
justification within ten days from the date of
issue of the notice for necessary action in the
matter. This is totally incompatible with the
notice contemplated as a default notice within the
meaning of Article 9.1. Article 9.1 contemplates
the existence of a default by the seller and the
giving of a period of three months to the seller
to remove the defect. We are unable to understand
how notice dated 22.02.2017 could be understood as
affording any such opportunity as is contemplated
under Article 9.1. Therefore, we have no hesitation
in holding that the appellant cannot seek shelter
under notice dated 22.02.2017 to justify the notice
156 of termination dated 07.07.2018, if reliance is to
be placed on Article 9.1 read with Article 9.4.(a).
We have already found that the appellant cannot be
permitted to reopen the issue relating to the non-
fulfilment of the conditions subsequent, as the
issue has attained finality by virtue of the
Judgment of the High Court dated 20.06.2018.
113. Appellant has attempted to justify the notice dated
22.02.2017 as the show-cause notice within the meaning
of Article 9.1 based on the Judgment of the High Court
in the first round of litigation. We are of the view
that appellant would not be justified in drawing
support from the said Judgment to contend that the
issuance of notice dated 22.02.2017, would suffice and
it absolves the appellant from complying with Article
9.1. From a perusal of the said Judgment in Writ
Petition No. 12880 of 2017, we find that the High Court
found that an attempt was made by the appellant to
justify the earlier termination dated 11.08.2017 on the
ground that respondent had not commissioned the power
project within the time fixed in the agreement. The
High Court was not impressed as it found that the lack
157 of commissioning of the power project was not the
reason for terminating the contract and the appellant
could not supplement the reason in view of Judgment of
this Court in Mohinder Singh Gill and another v. Chief
Election Commissioner, New Delhi and others35. It is
thereafter, after setting aside the Order dated
11.08.2017, that liberty was granted to the appellants
to pass fresh Order in terms of the PPA, in accordance
with law. High Court, therefore, only permitted the
appellants to invoke the PPA with respect to the lack
of commissioning, and moreover, in accordance with law.
It becomes clear as day light that since by the date
of the Judgment, i.e., 20.06.2018, the period of
twenty-four months from the date of the agreement, had
expired, and if, in terms of the liberty granted by the
High Court, the appellant was to lawfully terminate the
contract, it could not have acted in breach of the
mandate of the PPA, which, in fact, the High Court had
specifically directed appellant to comply with. In
other words, though nearly nine months had gone by from
18.09.2017, when the High Court pronounced Judgment on
35 (1978) 1 SCC 405 158 20.06.2018, if the appellant wanted to terminate the
agreement, at least under the contract, the appellant
was obliged to issue the default notice. As we have
noticed, the appellant was perhaps persuaded to issue
the impugned termination notice on the basis of the
earlier notice dated 22.02.2017 as it felt that it was
entitled to ask the Court to revisit the issue relating
to the non-fulfilment of the condition subsequent as
well. The appellant has, in fact, proceeded in the
notice of termination that the three months period,
contemplated in Article 9.1, came to an end
automatically, on 18.12.2017 and things had not changed
on the ground, entitling it to issue the notice dated
07.07.2018, after the further expiry of seven days on
25.12.2017. The appellant, in this regard, appears to
have laboured under the apprehension that the mere
expiry of the period of three months, after the
occurring of the event of seller default, within the
meaning of Article 9.4.(a) and the further expiry of
another seven days, entitled it to issue the notice of
termination. What, on the other hand, Article 9.1 read
with Article 9.4.(a) contemplated was not the mere
159 running of time for a period of three months, after the
occurrence of the seller’s event of default but an
opportunity to the seller by the giving of a notice of
default and waiting for three months. It is only after
the seller was put on notice of the default, which it
had committed and an opportunity was granted to remove
fully the default and it persevered in breach, that a
valid Order of termination could be passed. On this
reasoning, there can be no dispute that the appellant
has clearly failed to act in terms of the clear mandate
of Article 9.1 read with Article 9.4.(a).
114. There is another vital aspect to be borne in mind.
The impugned notice dated 11.08.2017, brought about the
termination of the contract. This is while notice dated
04.07.2017 was issued by the first respondent, as
noticed. Therein, the appellant was specifically asked
to inspect the premises. The CEIG also issued the
certificate on 09.08.2017. Now the really significant
fact is that after the appellant terminated the
contract on 11.08.2017, it is wholly inconceivable and
arbitrary to predicate that the first respondent should
have commenced the project and complied with Article
160 9.4(a) by 18.09.2017. Even more unfair it would be to
find that the first respondent had three months period
from 18.09.2017 to cure the defect which period came
to an end on 18.12.2017. Yet, this very premise is
reflected in the impugned notice dated 07.07.2018.
There is no case at all for the appellant that
immediately on the expiry of 24 months contemplated in
Article 9.4(a), a notice was given under Article 9.1.
This could not be, also for the reason that the
appellant had well before 18.09.2017, on 11.08.2017,
terminated the contract. This is indisputable. Equally
significantly, termination of the contract dated
11.08.2017 clearly was illegal though it was found
later and set aside by judgment dated 20.06.2018.
Thus, we cannot also brush aside the complaint of the
first respondent that this is a case where it stood
prevented from commencing supply within the meaning of
Article 9.4(a). The fact of termination by order dated
11.08.2017 and its invalidation by the High court on
20.06.2018 are again not matters of dispute.
115. There is another aspect to the matter. The
termination of a contract, undoubtedly, results in the
161 intrusion into and deprivation of valuable rights,
which are vouchsafed to the awardee of the contract.
It could be argued that dehors a contractual provision,
unless it be that the contract peremptorily provides
for the termination of the contract expressly without
service of the notice on the occurrence of certain
stipulated events, principles of natural justice may
not be out of place and under the Theory of Fair State
Action, in consonance with Article 14, an opportunity
to the awardee as to why the contract should not be
terminated, may be just. In this regard, we may
recapitulate what this Court in State of U.P. v. Sudhir
Kumar Singh and Others36 has, inter alia, held:
“23. It may be added that every case in which a citizen/person knocks at the doors of the writ court for breach of his or its fundamental rights is a matter which contains a “public law element”, as opposed to a case which is concerned only with breach of contract and damages flowing therefrom. Whenever a plea of breach of natural justice is made against the State, the said plea, if found sustainable, sounds in constitutional law as arbitrary State action, which attracts the provisions of Article 14 of the Constitution of India -
see Nawabkhan Abbaskhan v. State of Gujarat (1974) 2 SCC 121 at paragraph 7. The 36 (2020) SCConline SC 847 162 present case is, therefore, a case which involves a “public law element” in that the petitioner (Respondent No. 1 before us) who knocked at the doors of the writ court alleged breach of the audi alteram partem rule, as the entire proceedings leading to cancellation of the tender, together with the cancellation itself, were done on an ex parte appraisal of the facts behind his back.”
No doubt, it related to a case of cancellation of
the tender after the tenderer had worked thereunder for
over a year and based on two ex parte enquiries. We may
bear in mind that Article 9.1 captures not really the
principles of natural justice as such but an
opportunity to set right a default by the seller.
116. Having found that the impugned termination Order
dated 07.07.2018 ill squares with the requirement of
Article 9.1, the question may arise, whether this is a
matter which should be the basis for interference in
powers of judicial review under Article 226. This is
not the basis on which the impugned Judgment is based.
Could it be said that this is a matter, which should
have formed the subject matter of a proceeding in a
civil court. In this regard, we may notice the
following aspects:
163
The object behind giving the default notice
under Article 9.1 is to provide an opportunity to
the seller under the PPA to comply with the PPA
and remove the default within the period of three
months. If it is a case where it is demonstrated
that removal of the default was an impossibility,
then, it would, indeed, be a futile exercise and
perhaps, at least, in a writ proceeding based on
infraction of Article 14 or that the action is
arbitrary, the Court may have refused to exercise
the extraordinary jurisdiction and relegate the
party to other forum to seek whatever relief it
may be entitled to. If on the other hand, complying
with Article 9.1 was, indeed, meaningful and the
default (Article 9.4.(a) could have been removed
as contemplated under Article 9.1, then,
undoubtedly, it may constitute arbitrariness to
deprive the first respondent of the benefit of a
default notice.
We cannot be totally unmindful of the fact
that such a Clause like Article 9.1 was inserted
with the understanding, that, in such large complex
164 projects, involving large sums of money being
invested, and furthermore, the successful
completion of the project being intended to augment
the production of energy, in this case solar
energy, there was an element of public interest
also involved in not allowing the curtains to be
rung down by an abrupt termination without
affording an opportunity to the seller to remove
the default. Therefore, we would also examine
whether there is a case where, it could be said
that the case of the first respondent is totally
bereft of bonafides or merit.
117. In this case, on 04.07.2017, the first respondent
addressed what it purports to be the notice of
commercial operations within the meaning of Article
5.3. It reads as follows:
“Ref No. SKP-2/MP/SOLAR/COMM/2017-18/026 Date: 04-07-2017
To The Chief Engineer (Planning & Design) M P Power Transmission Company Limited, Shakti Bhawan, Rampur, Jabalpur – 482008, Madhya Pradesh.
165 Subject: Notice to Commission on the 50 MW Solar Power Project of SkyPower Southeast Solar India Private Limited located at Village Chirbel, District Khandwa (“Project”), and Evacuation of Power from the Project to the 400 KV Chhagaon Sostation.
Reference: Power Purchase Agreement dated September 18, 2015 between Southeast Solar India Private Limited and MP Power Management Company Limited (“PPA”).
Dear Sir, As per above cited subject matter and reference, we hereby intimate you of our intention to commission the project by 31st July, 2017 (“Proposed Commissioning Date”). By the Proposed Commissioning Date, we are likely to procure and obtain all permissions and approvals required for the Plant and fulfil and obligations specified in Article 5.3 read with Annexure XII of the PPA.
In relating to the commissioning of the Project by the Proposed Commissioning Date, we would like to apprise you of the progress made by use in relation to completion of some of the critical path items for the Project-
• Transmission Line – 95% work has been completed as on 28th June, 2017 for the 132KV DCDS (double circuit double string) transmission line from location of the Project to the 400KV substation Chhegaon. Balance 5% is expected to be completed by 15th July, 2017 in all respect.
• Bay construction- 90% work on the 132 KV bay is completed (post receipt of connectivity approval from MP Power Transmission Company Limited (“MPPTCL”)
166 for the Project along with installation of specified equipment as required by MPPTCL. Balance 10% of the work, including testing, meter and CRP panel, is expected to be completed by 20th July, 2017.
• Connecting Agreement- Connection agreements have already been signed on 18th May, 2017 between Madhya Pradesh Power Transmission Company Limited, Jabalpur and M/s SkyPower Solar India Private Limited.
• SLDC connectivity- Connectivity from plant to the SLDC-Indore is already established through dedicated 2nox2mbps point to point lease lines from BSNL (as per approved scheme of SLDC on 23rd March, 2017 through letter no. SE./LD.
E&T/880, data can be transferred immediately on charging of plant).
Specified equipment as per approved scheme of SLDC has been installed at SLDC-Indore and at the Project. Even, IP scheme for both the routers has been allocated by the SLDC, Jabalpur (through letter no. SE/LD.E&T/06, dated 3rd April, 2017).
• CEIG Certification-We have initiated the process to obtain the CEIG certification, and the CEIG th certification is expected by 20 July, 2017. The CEIG certificate shall be produced to MPPTCL as an annexure to obtain the commissioning certificate, as required under the PPA.
Considering above facts on project progress we hereby request your kind needful and depute necessary officials and personnels to our site to undertake necessary inspection and testing and help us in the target commissioning dated of 31st July, 2017.
167 In the event, you require any further information from us, we will be happy to provide the same upon your request.” (Emphasis supplied)
118. No doubt, Article 5.3 contemplates a notice
whereunder the seller specifies that the plant was
constructed as per the agreement and it was ready to
deliver the solar power in accordance with its terms.
Secondly, it must be indicated that all permissions and
approvals required for the plant to sell solar power
at the rates and terms had been obtained. Still
further, all interconnection facilities were available
to receive solar power. Notice is to take effect,
however, only when the TRANSCO/DISCOM declares that all
the conditions in Article 5.3 stood satisfied (or
waived by it), inter alia, i.e., that the seller had
successfully completed the testing of the plant in
accordance with the manufacturer’s recommendations and
the seller had obtained and provided from the
Electrical Inspectorate of the Government of Madhya
Pradesh or other authorised agency, a certificate and
the seller had delivered a list of the equipments with
details. The further condition is that the plant had
168 achieved initial synchronisation with the appellant and
had demonstrated reliability of its communication
system, inter alia, that the seller had operated the
plant without experiencing any abnormal or any unsafe
operating condition on any interconnected system. The
seller was also to notify the appellant within no later
than 30 days prior to the commercial operations date,
that the conditions, as laid down in Article 1.01 have
been met.
119. However, the first respondent in the letter dated
04.07.2017 has intimated about the intention to
commission the project by 31.07.2017, which is on the
27th day after the notice. As far as transmission line
was concerned, 95 per cent of the work was claimed to
have been completed as on the 28.06.2017. Balance 5 per
cent, it is stated, would be completed by the
15.07.2017 in all respects. In regard to bay
construction, 90 per cent of work was stated to be
completed along with installation of certified
equipment. Here also, it is stated that the balance 10
per cent of the work including, testing, meter and CRP
panel would be completed by 20.07.2017. Connection
169 agreement is stated to have been signed on 18.05.2017.
As far as SLDC connectivity is concerned, it is stated
that connectivity to SLDC indoor was already
established through dedicated 2nox2mbps point to point
lease lines from BSNL. As far as the certification by
the CEIG, it is stated that the process to obtain the
CEIG certification would be initiated and it is
expected by 20.07.2017. Inspection was prayed for so
as to achieve the target commissioning date by
31.07.2017. No doubt, the appellant has proceeded on
the basis that the notice dated 04.07.2017 cannot be
treated under Article 5.3 of the PPA. As far as the
CEIG Report is concerned, it appears to be dated
09.08.2017. It could no doubt be found that what
Article 5.3 notice contemplates is a state of
accomplishment of conditions when the notice is sent.
However, the notice dated 04.07.2017 promised
completion by 31.07.2017. Article 5.3 provides for
waiver. If a default notice under Article 9.1, was
given on 07.07.2018, in place of the termination
notice, then, with the state of completion attained
and, if anything further remained, doing that also, and
170 issuing the notice, if insisted, the defect could have
been removed.
120. In this regard, we may notice a significant
distinction between Article 2.5.1 (d) which was used
as the sheet anchor by the appellant to contend that
in the event of non-achievement of condition subsequent
termination was mandatory. Article 2.5.1(d) is as
follows:
“d) In case of delay of more than 9 months, MPPMCL shall terminate PPA and release balance amount of CPG.” (Emphasis supplied)
121. When it comes to Article 9.1, we have noticed that
it contemplates the giving of default notice when an
event of default takes place. The seller is given three
months’ time to set right things fully. Thereafter,
Article 9.1 provides that in case of the default by the
seller not being removed fully, apparently, the
appellant by giving seven days termination notice ‘may’
terminate the agreement. The choice of the word ‘may’
importing discretion in Article 9.1 is in stark
contrast with Article 2.5.1 (d).
171
122. Apparently, it was so drafted so that in an event
like in a seller event of default under Article
9.4.(a), i.e., failure by the seller to supply power
within 24 months, bearing in mind the nature of project
and the stakes involved for both the appellant and the
seller, there may be cases where the seller may wish
to grant more time so that a project which has
progressed to a state of near completion may not be
aborted by the termination and grant of time would, on
the other hand, witness the full blossoming of the
project.
123. It would appear that the appellant did not carry
out any inspection. The inspection carried out by the
CEIG in first week of August, 2017 was an inspection
conducted by the five-member team and it is further
claimed that this inspection lasted for 3-4 days
beginning from 01.08.2017. The CEIG has certified that
the project was ready and that the first respondent can
proceed with the commissioning activity. We bear in
mind that the period of twenty-four months contemplated
in Article 9.4(a), would expire only on 18.09.2017. The
CEIG has given its Report on 09.08.2017 that the
172 project was ready for commissioning. The factum of the
Report cannot be treated as a disputed question of fact
as it is covered by a document. In fact, we find that,
the appellant proceeded on the basis admittedly that
it was reliable, but, however, on 11.08.2017 issued the
termination notice solely based on non-fulfilment of
conditions subsequent. This notice stood set aside on
20.06.2018. Maybe the manner in which the inspection
was carried out and the pitfalls in the same may be
characterised as the disputed questions of facts. Also,
though the appellant was invited to carry out the
inspection on 04.07.2017, the appellant carried out the
inspection only on 19.04.2018 and the Report was dated
21.04.2018.
124. If we go by the Report of the CEIG, the project of
the respondent would appear to have been completed for
the purposes of effecting commissioning. It may be
another matter that other formalities had to be
completed. When the team of the appellant carried out
the physical inspection, (it was done on 19.04.2018),
the appellant’s team also substantially endorsed the
Report of the CEIG. However, it was found that a certain
173 number of string inverters inter alia, were not found
at many locations in Block Nos. 9 and 10. It was found
as follows:
“4. Any other specified observation in respect of installation of solar P.V plant
In block 9 and 10, string inverters were not found at many location but those location had solar panels installed interconnections of PV panel (cabling) string work at there location are not found connected with each other Further, at some location the cable and earthing work is observed incomplieto & suspended.”
125. It is here that we must notice the case of the
first respondent to be that though the equipment was
installed as certified in the Report of the CEIG and
what remained was formal connectivity to the grid upon
which commissioning certificate would be issued, the
final event remained on account of non-issuance of
connectivity code for connection to the grid. It is
while so, when the challenge against the first
termination notice was under consideration and there
was demobilisation of manpower, certain string
inverters were stolen, the cost of which is stated to
be Rs.172000 per string inverter. Based on safety
174 concerns, the equipment was, according to the first
respondent, removed and kept in safe custody. The first
respondent has laid store by two first information
reports lodged. The first FIR was lodged on 12.09.2017
and another FIR was lodged on 04.03.2018 relating to
the theft of certain equipments. This is a case where
the first respondent has alleged that it has already
invested Rs.331 crores.
126. We will proceed on the basis that there was a CEIG
Report dated 09.08.2017 certifying that the project of
the first respondent was complete. This is well before
18.09.2017, which was the date by which the
commissioning had to be done. It is also clear that the
commissioning, as such, was not completed. Still
further, if we go by the CEIG Report, the case of the
first respondent of it being on the verge of
commissioning could not be brushed aside as wanting in
bonafides or merit. Still further, there is a case of
the appellant that the inspection carried out on
19.04.2018, resulting in Report dated 21.04.2018,
revealed certain deficiencies in the form of missing
inverters inter alia from Block Nos. 9 and 10 inter
175 alia. First respondent has a case of thefts occurring.
In fact, the first respondent has a definite case that
about 39 inverters involved were also replaced in June,
2018 based on Purchase Order of May 2018 [See Annexure
R12 produced before the High Court in Review Petition
No.682 of 2020]. This is even before 07.07.2018. No
doubt, the appellant has a case that the FIRs relied
on by the first respondent did not refer to inverters.
As to whether, it was a result of thefts that the
inverters etc. which were already there as on the date
of the CEIG inspection went subsequently missing or as
to whether it was as a result of the Report of the CEIG
being flawed and, therefore, the inverters etc. were
not there in the first place, even as on the date of
the CEIG Report, appears to us to be a disputed question
of fact. We proceed on the basis that the inverters in
question were not there. But as noticed, about 39
stolen invertors were already replaced in June 2018.
At any rate, if a default notice had been given pointing
out this aspect, the matter could possibly be put right
within three months of such a notice. We recall here
the few complaints (essentially two in number) which
176 remained of Respondent No.5. It could have been
pointed out as part of aspect of default if it was so
understood. We have also found that the joint
inspection of the respondent No.4 had found on
24.08.2017 that the line may be charged. What we can
find is only that this is not a case where the first
respondent could be said to be in a position where it
could be said that it would be unable to comply with
the terms of the default notice if it was warranted.
In other words, if as on 07.07.2018, instead of issuing
a termination notice, if notice had been given within
the meaning of Article 9.1, it is quite possible that
the first respondent would have remedied the defect as
alleged. We have also noted that even in 2017, no
notice was given under Article 9.1 and even the
contract was terminated illegally as found by the High
Court by notice dated 11.08.2017. The whole idea behind
the default notice under Article 9.1 was lost sight of
by the appellant. We have unravelled also, the impact
of the use of the word ‘may’ in Article 9.1. The action
of the appellant in departing from unambiguous regime
177 of the PPA without any justification would make its
actions arbitrary.
127. The other aspect projected by the appellant is what
was projected in the Review Petition filed before the
High Court. It was contended essentially as follows:
The first respondent had committed a fraud on
the Office of the Chief Electrical Inspector, the
appellant and on the Court. It was alleged that
the project was divided into 10 blocks of 5MW each
and each Block of 5MW would have 116/117 Inverters
approximately. Each of the Inverter was to have a
unique distinctive serial number. Each inverter
was to have 43KV rating, as indicated in the CEIG
Report. The fraud consisted of a discovery by the
appellant on an alleged ‘detailed’ analysis of the
serial numbers of the inverters, that in each
Block, there were several Inverters having numbers
which were common/duplicate and interchangeably
used in the same or other blocks. It was alleged
that for about 186 Invertors serial numbers were
commonly, duplicably and interchangeably used.
Some of the inverter numbers were not legible.
178 Therefore, it was alleged that there was lack of
due diligence by the authorised personnel of the
CEIG.
128. In this regard, the first respondent has countered
the case of the appellant not only by producing
invoices supplied by the overseas supplier and the bill
of entry issued by the Customs Department but the Lorry
Receipts, to establish the procurement of 1175
Inverters required for the first respondent Unit in
2017. It is also their case that the inverter serial
numbers themselves carry no significance. They were
mere identifiers for the purpose of record keeping,
warranty claims, etc. All the 1163 Inverters installed
by the first respondent had identical mechanical
specification and the mere mention of incorrect serial
numbers in the Report of the CEIG did not establish
that the first respondent was not ready to commission
the project. The first respondent also has pointed out
that on learning of the duplication of the few
inverters serial numbers in the Report of the CEIG, it
promptly approached the CEIG on 16.09.2020 with details
of the correct unique serial numbers and the
179 corresponding location of the inverters. It requested
the CEIG to inspect and verify the inverters and to
issue a corrigendum to the first Report dated
09.08.2017. In fact, there is reference to first
respondent in compliance with the first impugned
Judgment writing to the CEIG earlier on 15.04.2020, to
visit the project site for reissuing/revalidating the
approval for commissioning the project, since the
validity of the first report dated 09.08.2017 had
lapsed. It is specifically contended in the reply to
the Review Petition that due to non-cooperation of the
appellant on the excuse of Covid-19, the CEIG
inspection could not be undertaken. This stand is
reiterated, in fact, in the counter affidavit in this
Court also. It would appear that the first respondent
had deposited the inspection fee of Rs.66,14,000/-
which is said to be equipment based meaning thereby
that it was paid reckoning all the inverters. It would
appear that no inspection has been carried by the CEIG
based on the request for revisit. As far as this aspect
is concerned, apart from the fact that the CEIG has
conducted an inspection and given a Report on
180 09.08.2017, certifying the readiness of the Unit of the
first respondent, the first respondent has produced
documents like invoices from overseas sellers, bill of
entry with the Customs Department and certain lorry
receipts. The alleged fraud is the common number found
in 186 inverters in the Report of the CEIG. A physical
inspection by the CEIG, which was necessitated in terms
of the original Judgement, at any rate, for
revalidation of the Report was and is necessary and
inevitable even if the appeals fail. The first
respondent had alerted the CEIG for the need for a
reinspection for ascertaining the aspect relating to
duplication in numbers. It would appear that such
inspection has not been carried out. In this regard,
it is important to notice that the appellant carried
out an inspection on 19.04.2018 and it had not found
out any such discrepancy as it has not projected in
regard to the aspect of common numbers or illegibility
of numbers, in the inverters, in its Report dated
21.04.2018. At any rate, the PPA clearly provided for
the issuance of a default notice, providing an
181 opportunity to remove the defect. This obligation has
been observed in its breach.
129. Therefore, we would find that an inspection by the
CEIG would necessarily have to be carried out in which
the appellant would have to be involved to facilitate
the exercise. In the facts of this case, on being
satisfied, the CEIG would necessarily have to grant the
re-validation of the earlier Report. It would also
involve an opportunity to the CEIG to look into the
aspects which have been projected by the fist
respondent itself in its letter dated 16.09.2020. The
report would indeed indicate the state of affairs about
all the facets. As already noticed, even under the
impugned Judgement dated 27.02.2020, the first
respondent would have to submit necessary applications.
We only clarify that it may involve removing any
remaining deficiencies with the fifth respondent.
130. It may not be wholly irrelevant to notice the
following aspect which is reflected in the counter
affidavit filed by the respondent No.1 before this
Court.
182 “It is of utmost importance to mention here that while the challenge to the 2018 Termination Notice was pending, the Petitioner had proposed a so-called amicable resolution of the dispute with the Respondent No.1 and convened a meeting for this purpose on February 6, 2020. Occurrence of this meeting and the discussions held are recorded at paragraphs 7 and 8 of the Impugned Order
1. During this meeting, the Petitioner had attempted to impress upon the Respondent No.1 to explore ‘Third Party Sale’ from the project or, agree to a reduction in tariff in line with the recent auctions conducted by SECI for other solar power projects. Respondent No.1 had rejected both the option of ‘third Party Sale’ or, the attempts to reduce tariff specified in Article 9.7 of the PPA, which was discovered through a transparent competitive bidding process. The very fact that the Petitioner had proposed to the respondent No.1 to explore sale of power from the Project to third parties is proof enough that the Project was complete and ready for commissioning.”
In this regard, we may notice paragraph 4 of the
minutes of the meeting dated 06.02.2020 which reads as
follows: -
“4. MPPMCL further stated that, as the commissioning of the project has been substantially delayed and, in the meantime solar binding tariffs have been considerable reduced up to Rs. 2.61/ Unit for which MPPMCL has already entered into PPAs, therefore MPPMCL offered M/s Sky Power to supply power at reduced tariff of the project was the lowest in the bid and their investment was made during the FY 2016-2017 therefore, supplying power to MPPMCL at reduced tariff will not be viable hence not possible.” 183 We would think that essentially the appellant’s
attempt was to secure a reduction in the rate. The rate
of the first respondent was found to be the lowest after
a clearly keenly competitive international bidding,
involving a large number of bidders.
131. In the totality of facts, we would, therefore,
think that though for reasons, which may not be the
same as in the impugned judgment, we need not interfere
with the view taken by the High Court. The appeals fail
and are dismissed. Parties to bear their own costs.
………………………………………………………J. [ K.M. JOSEPH ]
………………………………………………………J. [ HRISHIKESH ROY ]
NEW DELHI;
DATED; NOVEMBER 16, 2022.
184
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free