Miss Lucy
← All judgments

M.P.Power Generation Co.Ltd.. And Anr vs Ansaldo Energia Spa And Anr

Supreme Court16 April 2018L. Nageswara Rao · S.A. Bobde

Ratio decidendi

The rule this decision rests on

1. Where a contract stipulates that a bank guarantee can be invoked only upon 'non-fulfillment of contractual obligations', the beneficiary cannot invoke such conditional bank guarantee without first establishing that a material breach has occurred and providing notice and opportunity to cure in accordance with the contract's terms; invocation of the bank guarantee prior to the completion of default notice and cure period procedures violates the conditions precedent to invocation. 2. A party may avoid a contract on the ground of misrepresentation under Sections 18 and 19 of the Indian Contract Act, 1872, where the other party makes a positive assertion not warranted by the information available to it, of facts which are not true, even if the asserting party believed them to be true; the exception to Section 19 that a contract is not voidable if the party asserting misrepresentation had the means of discovering the truth with ordinary diligence does not apply where the relevant records and documents necessary to verify the truth were not furnished despite repeated requests. 3. A court exercising powers under Section 34 of the Arbitration and Conciliation Act, 1996 cannot interfere with findings of fact made by an arbitral tribunal on appreciation of oral and documentary evidence, provided the tribunal has applied a judicial approach and its conclusions are not perverse or so unreasonable as to shock the conscience of the court. 4. Where a contract requires a letter of comfort or letter of credit to be furnished as a fundamental condition, and the parties do not insist on it as a pre-condition to the commencement date but reserve the right to seek it later in accordance with the contract's amendment clauses, the party cannot be deemed to have waived such requirement; the requirement remains a fundamental condition and failure to furnish it constitutes breach. 5. A claimant is entitled to recover amounts actually expended on work performed and equipment procured in partial performance of a contract that has been wrongfully terminated, where voluminous documentary evidence establishes such expenditure and the termination is found to be unlawful. 6. Where a contract distinguishes between different categories of bank guarantees—some conditional (for advance payments made) and one unconditional (for performance)—and a party rightfully rescinds the contract due to material breach and wrongful termination, it is entitled to refund of the performance bank guarantee but not the conditional bank guarantees given for amounts actually advanced and retained.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

Non-Reportable
IN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
Civil Appeal No. 3804 of 2018(Arising out of S.L.P. (Civil) No. 39067 of 2013)
M.P. POWER GENERATION CO. LTD. & ANR..... Appellants
Versus
ANSALDO ENERGIA SPA & ANR.….Respondents
JUDGMENT
L. NAGESWARA RAO, J.
Leave granted.
1. M.P. Power Generation Co. Ltd. formerly known as

Madhya Pradesh Electricity Board (hereinafter

referred to as ‘the Board’) invited proposals for

refurbishment of Units 3 and 4 of the Thermal Power

Plants at Amarkantak having the capacity of 120 MW

by a notice inviting tender dated 24th October, 1996.

A provisional Letter of Intent for refurbishment of

Thermal Power Plant of 2 x 120 MW Phase–II was

issued by the Board to Respondent No.1, ANSALDO

Energia SPA (for short ‘the Claimant’) on 11th May,

1 1999. Thereafter, on 24th August, 1999 four

Agreements were signed between the Claimants and

the Board viz Overall Coordination Agreement,

Offshore Supply Contract, Onshore Supply Contract

and Onshore Services Contract.

2. A Bank Guarantee dated 22 nd February, 2000 was

furnished by the Claimants as per Clause 9.2 (a) of

the Onshore Supply Contract for Rs. 9,29,20,000/-

(10 per cent of the Onshore Supply Contract price).

Another Bank Guarantee was furnished by the

Claimants on 23rd February, 2000 as per the

stipulation in Clause 9.2(a) of the Offshore Supply

Agreement for US $ 1,708,100/-. The above Bank

Guarantees were given towards advance payment

that was to be made by the Board. On 24 th

February, 2000, a Performance Bond was executed

by the ANZ Grindlays Bank Limited on behalf of the

Claimants for Rs.18,48,00,000/- (10 per cent of the

total Contract price) pursuant to Clause 4.1 of the

Overall Coordination Agreement. The Board

subsequently made advance payments of the

2 amounts equivalent to the two Bank Guarantees

dated 22nd February, 2000 and 23rd February, 2000

given by the Claimant.

3. The Zero Date (i.e. effective date of Contract) as per

Clause 7 of the Overall Coordination Agreement is as

follows:

“7. Notice to Proceed 7.1 Zero Date (Effective Date of Contract) The zero date of the Contract shall mean the date on which the all the following conditions are fulfilled:

(i) Signature of the Contract (ii) Receipt by ANSALDO of the Notice to Proceed (iii) Receipt by MPEB the Bank Guarantee from

ANSALDO for the Advance Payment (10% of the Contract Price)

(iv) Receipt by ANSALDO of the Advance Payment

(v) Receipt by ANSALDO of the Letter of Credit for the Offshore Supply and Letter of Comfort/ Support for Onshore Supply and Onshore Services

(vi) Financial tie-up of PFC loans

7.2 If the Start Date has not occurred on or before six (6) months after the date hereof, then the Contract will automatically expire, without any liability on either side and the price will cease to be valid and will be subject to renegotiation.

7.3 MPEB may not issue a Notice to Proceed under any of the Refurbishment Contracts without issuing a Notice to Proceed under all of the Contracts.”

4. It was agreed between the parties that the Zero

Date would be 9th March, 2000. Thereafter, there

was exchange of correspondence and several

meetings held between the Claimant and the Board

for resolution of certain issues. In response to a 3 letter written by the Board on 15 th June, 2001, the

Claimant wrote to the Board on 21 st June, 2001 to

treat the Agreement as expired. The Claimant

stated in the said letter that it was suspending the

performance of the Agreement. There was a

reference to violation of a fundamental condition of

the Contract i.e. non-furnishing of a Letter of

Comfort from the Power Finance Corporation as

provided in Clause 5.6 of the Onshore Supply

Contract. The Claimant further complained of a

misrepresentation of the warranty contained in

Clause 19.2 (vii) of both the Onshore and Offshore

Supply Contracts and Clause 20.2 of the Onshore

Services Contract.

5. The Board invoked the three Bank Guarantees on

23rd June, 2001. Thereafter, the Board proceeded to

issue a notice for default as provided in Clause 16.3

of the Offshore and Onshore Supply Contracts and

Clause 17.3 of Onshore Services Contracts on 29 th

August, 2001. The Board complained of substantial

breach of Agreement on the part of the Claimant.

The Claimant was given 30 days’ time for curing the 4 defaults. The Claimant responded by submitting a

representation on 8th January, 2000. Not satisfied

with the explanation given by the Claimant, the

Board terminated the contract. The Claimant raised

a dispute which was referred to Arbitration. The

Arbitral Tribunal passed an award in favour of the

Claimant on 23rd September, 2004 in the following

terms:

“1) It is declared that:

a) The three Bank Guarantees were wrongfully invoked and encashed by the Respondent. b) The agreements were wrongfully terminated by the Respondent. c) The agreements are voidable at the option of the Claimants and have been avoided by them. 2) The Respondent shall pay to the Claimants: i) the sum of Rs 39,80,98,429/- with

interest thereon at the rate of 12% per annum from 5th July, 2001 till the date of the Award and thereafter until payment or realization.

ii) the sum of Rs.11,14,55,042/- with interest thereon at the rate of 12% per annum from 29th July, 2002, being the date of the claim, till the date of the Award and thereafter until payment or realization.

iii) The respondent shall pay to the Claimants the sum of Rs.2000000 as and by way of costs, including the costs of the arbitration proceedings."

5 6. The Petition filed by the Board under Section 34 of

the Arbitration and Conciliation Act, 1996 (for short

“the Act”) was allowed by the learned 7 th Additional

District Judge, Jabalpur and the award dated 23 rd

September, 2004 of the Arbitral Tribunal set aside.

The learned Additional District Judge upheld the

findings of the Arbitral Tribunal on Issues No.1 to 7.

Breach of contract by the Board in view of (a)

violation of a fundamental condition of the contract

i.e., not furnishing Letter of Comfort from Power

Finance Corporation and, (b) misrepresentation by

the Board in Clause 19.2 (vii) of the agreements as

concluded by the Arbitral Tribunal were approved by

the learned Additional District Judge. However, the

Learned Additional District Judge found fault with the

award pertaining to Bank Guarantees and the

amounts specified in Exhibit- GG of the Claim

Petition. On the basis of the opinion that the Arbitral

Tribunal had acted in excess of its jurisdiction in

granting relief to the Claimant under the above

heads, the learned Additional District Judge set aside

the award.

6

7. Aggrieved by the rejection of Issue No.13 by the

Arbitral Tribunal which pertains to amounts

mentioned in Exhibit- HH to the Statement of

Claim(Damages for the wrongful breach of Contract),

the Claimant preferred an application under Section

34 of the Act. The said application was dismissed by

the learned Additional District Judge. The Appeal

filed by the Claimant against the judgment of the

learned Additional District Judge was later withdrawn

and the dismissal has attained finality. We are not

concerned with the said claim in this case.

8. The Claimant filed an appeal before the High Court

challenging the judgment of the Additional District

Judge by which the Award of the Arbitral Tribunal

was set aside. The High Court set aside the

judgment of the learned Additional District Judge

and restored the award of the Arbitral Tribunal. The

High Court held that the Additional District Judge

committed a serious error in interfering with the

finding of the Arbitral Tribunal on Issues 9 to 12 after

upholding the award in respect of Issues 1 to 7. The

7 High Court observed that Bank Guarantees are

independent contracts between the Bank and the

beneficiary. Relying upon the conditions in the Bank

Guarantees which related to the invocation only on

the ‘non-fulfillment of contractual obligations’, the

High Court approved the findings of the Arbitral

Tribunal that the Board could not have invoked the

Bank Guarantees without proving breach of

contractual obligations on the part of the Claimant.

Aggrieved by the judgment of the High Court, the

Board has filed the above Appeal.

The Agreements

9. As stated above, the Contract between the Claimant

and the Board pertains to refurbishment of Units 3

and 4 of the Amarkantak Thermal Power Station

located in Shadol District of Madhya Pradesh. Four

Agreements in all were entered into between the

Claimant and the Board. An Overall Coordination

Agreement was executed on 24th August, 1999

which provided for three other Agreements which

are :

(i) Offshore Supply Contract,

(ii) Onshore Supply Contract, 8

(iii) Onshore Services Contract.

10. It is necessary to refer to the relevant provisions

of the Agreements for a better understanding of the

issues involved in this case. As per the

Agreements, the target completion period for the

first and the second Unit was 18 ½ months and 22 ½

months from the issuance of notice to proceed

respectively.

11. Clause 4 of the Overall Coordination Agreement

which deals with Performance Guarantees is as

follows:

“4. Performance Guarantees 4.1 ANSALDO shall deliver to MPEB within fifteen days from the Zero Date, as defined in Clause 3 of each of the Offshore Supply Contract, the Onshore Supply Contract and the Onshore Services Contract, a performance bond (as per attachment to this Co-ordination Agreement) in the sum of ten per cent (10%) of the total Contract Price which may be drawn against only in the event that ANSALDO does not perform the activities towards faithful fulfillment of all the terms and conditions of this Agreement except for the fulfillment of the Guaranteed Parameters, which are covered in clauses 4.2 and 4.3 herein. The validity of the Bank Guarantee shall expire upon the earlier of

(i) the Completion Date plus six (6) months towards Claim Period;

(ii) the date of termination of this Agreement pursuant to Clause 17 of the Offshore Supply and Onshore Supply Contract or Clause 18 of the Onshore Services Contract plus six (6) months towards Claim Period provided the termination is not due to breach of Contract on part of ANSALDO;

9

(iii) upon submission of Guarantee Bond as per clause 4.3 of this Agreement.

4.2 ANSALDO shall deliver to MPEB a Bank Guarantee (as per attachment to this Co-ordination Agreement in the sum of twelve and one half per cent (12 ½ %) of the Total Contract Price to guarantee the successful achievement of the Guarantee Parameters (Indemnity Bank Guarantee). Such Bank Guarantee shall be delivered to MPEB on the date ANSALDO submits its initial monthly invoice for payment to MPEB. The validity of such Bank Guarantee shall expire on the earlier of:

(i) Completion Date plus six (6) months towards Claim Period;

(ii) the date of termination of this Agreement pursuant to Clause 17 of the Offshore Supply and Onshore Supply Contract or Clause 18 of the Onshore Services Contract plus six (6) months towards Claim Period provided the termination is not due to breach of Contract on part of ANSALDO.

For the sake of administration of the Indemnity Bank Guarantee, the following will apply:

(i) Tolerances for the various guaranteed parameters, will be as per the International Standards (BS, ASME, DIN, Japanese and Russian)

(ii) If there are any shortfalls beyond the tolerances, ANSALDO will be provided reasonable time for rectifying the defects, with no financial implications to MPEB. Such reasonable periods will not be considered for computation of the Contractual Delivery Period.

(iii) Beyond the occurrence of item (i) and (ii) above, the Indemnity Bank Guarantee can be drawn.

4.3 ANSLDO shall deliver to MPEB a Bank Guarantee (as per attachment to this Co-ordination Agreement) in the sum of 15% of the Total Contract Price no later than the First Unit Completion Date which may be drawn only in the event the Guarantee Parameters for Three Years are not met, with respect to each of Unit No.3 and Unit No.4 during the applicable Guaranteed Period for Three Years. The validity of such Bank Guarantee shall expire at the end of the third year after the date of the Second Unit Completion Date.”

10 Clause 9.2 of the Offshore and Onshore Supply

Contracts which provides for issuance of Bank Guarantee

against submission of advance payment, reads as under:

OFFSHORE SUPPLY CONTRACT “9 Contract Price and Terms of Payment 9.1 As payment for ANSALDO’S performance of the supplies and obligations under this Contract, MPEB shall pay to ANSALDO an amount of Seventeen Million Eighty One Thousand (17.081 Million) US Dollars, as per the price breakdown furnished in the Sixth Schedule.

9.2 TERMS OF PAYMENT

a) MPEB shall pay to ANSALDO an interest free advance payment “the Advance Payment”) equal to ten per cent (10 %) of the Contract Price on the date on which MPEB issues the Notice to Proceed Against submission of Advance Payment Bank Guarantee on declining basis, of equivalent value, valid upto the date of completion of the last supplies.”

ONSHORE SUPPLY CONTRACT “9. Contract Price and Terms of Payment 9.1 As payment for ANSALDO’S performance of the supplies and obligations under this Contract, MPEB shall pay to ANSALDO an amount of Rs. Nine Hundred Twenty Nine Million Two Hundred thousand (929.20 Million Rs.), as per the price breakdown furnished in the Sixth Schedule.

9.2 TERMS OF PAYMENT

a) MPEB shall pay to ANSALDO an interest free advance payment “the Advance Payment”) equal to ten per cent (10 %) of the Contract Price on the date on which MPEB issues the Notice to Proceed Against submission of Advance Payment Bank Guarantee on declining basis, of equivalent value, valid upto the date of completion of the last supplies.”

Clause 16.3 of the Offshore Supply Contract requires

a written notice to be issued to the defaulting party in case

of a substantial breach of the Agreement. A cure period of 11 30 days is provided in Clause 16.4 to the defaulting party

after receipt of the notice under Clause 16.3. Termination

of the agreement as per Clause 17 is in the following

terms:

“17. Termination 17.1 If (i) a substantial breach specified in a notice under clause 16.3 is not remedied within the Cure Period; or (ii) a Force Majeure has occurred and has continued as indicated in Clause 15.5; then the non-Defaulting Party in the circumstances of sub-Clause (i), and either party, in the circumstances of sub-clause (ii), may without prejudice to any other right or remedy in respect of any pre-existing breach, terminate this agreement by further notice in writing to the Defaulting Party.

17.2 Upon termination of this Agreement, MPEB shall pay to ANSALDO, in full the following:

(i) the value of the Equipment supplied and any other work performed up to the date of termination which was not previously paid by MPEB;

(ii) any cost incurred by ANSALDO after the date of termination incurred as a result of the termination due to fault of MPEB;

17.3 Upon termination of this Agreement, any remaining Equipment for which payment has been received by ANSALDO in the performance of its obligations or delays its performance under this agreement.”

Representations and warranties on the part of the

Board are dealt with in Clause 19.2. Clause 19.2 (vii)

which is relevant for the purpose of this case reads as

under:

“19.2 MPEB represents and warrants to ANSALDO that:

….

….

(vii) Each of Unit No.3 and Unit No.4 was designed and constructed to achieve the Operating Parameters, 12 and did in fact operate at 120 MW when operating in accordance with Good Industry Practice.”

Similar provisions relating to default notice,

termination and warranties in the Offshore Supply Contract

are there in the Onshore Supply and Onshore Services

Contracts as well.

Award of the Arbitral Tribunal

12. The Arbitral Tribunal framed the following issues

for determination of the dispute raised by the

Claimant:

“1. Whether the Respondent had supplied the technical documents and information to the Claimants as required by Clause 5.8 (iv) of the Onshore Services Agreement?

2. Whether the Claimants had waived the production of the Letter of Comfort of the Power Finance Corporation as required by Clause 5.6 of the Onshore Supply Contract and Schedule 7?

3. Thereto and Clause 5.14 of the Onshore Services Contract and Schedule 7 thereto?

4. Whether the issuance of the Letter Comfort/ Support by Power Finance Corporation to Asia Power Projects Pvt. Ltd. (Claimant No.2) (“ASPL”) was a fundamental condition of the contract agreements?

5. Whether Units 3 and 4 of the Amarkantak Power Station did in fact operate at a capacity of 120 MW when they were first installed in 1997 when operating in accordance with Good Industry Practice as warranted by the Respondent in Clause 19.2 (vii) of the conditions of contract for Offshore and Onshore Supplies and Clause 20.2

(vii) of the conditions of contract for Onshore Services?

6. Whether the Respondent co-operated with the Claimants in carrying out the RLA tests?

7. Whether the Respondent’s insistence on approving the Claimants’ vendors was legal?

13 8. Whether the unilateral amendment by the Respondent of the Letter of Credit without the consent in writing of ANSALDO Energia S.P.A. – Claimant No.1 (“ANSALDO”) was wrongful and whether such amendment required the consent of ANSALDO and of its bankers?

9. Whether the invocation and encashment by the Respondent of the Bank Guarantees was wrongful, premature, illegal and fraudulent?

10. Whether the termination of the Contract Agreements by the Respondent was wrongful?

11. Whether the Claimants are entitled to the amount claimed in Exhibit FF to the Statement of Claim?

12. Whether the Claimants are entitled to the amount claimed in Exhibit GG to the Statement of Claim?

13. Whether the Claimants are entitled to the amount claimed in Exhibit HH to the Statement of Claim?

14. Whether the Respondent is entitled to any of the amounts/ claimed by it in its Counter Claim?

15. Whether the Tribunal should award the continuation of the Interim Order of the Jabalpur District Court dated July 6 and 7, 2001?

16. What order should the Tribunal pronounce for costs? ”

13. The Arbitral Tribunal held that there was

misrepresentation on the part of the Board in

respect of the capacity of the Plant as well as its

operating parameters and breach of a fundamental

condition of the contract relating to Letter of

Comfort not being furnished. Termination of the

contract was found to be bad in law. Issues No.1

and 4 were answered as follows:

“Dealing with Issue No.4 first, the terms of the representation and warranty clause needs to be noted. The Respondent “represents and warrants” to the Claimants that “each of Unit

14 Nos.3 and 4 was designed and constructed to achieve the operating parameters and, in fact, operated at 120 MW when operated in accordance with good industry practice”. The representation that the Respondent made and warranted was twofold; first, in respect of the operating parameters that the Units were designed and constructed to achieve and, secondly that the Units did, in fact, operate at 120 MW, when operating in accordance with good industry practice.

It would appear from the evidence of the Respondent’s witness Saxena that the first representation and warranty was made only of the strength of the manufacturer’s plaque attached to the Units, but this representation and warranty is of far less import than the representation and warranty that the Units had, in fact, operated at 120 MW when operated in accordance with good industry practice. It is an admitted position that no performance test upon commissioning of the Units had been carried out. It is clear upon the evidence that the only record which the Respondent had which showed that the Units had in fact operated at 120 MW were the log sheets of February 23,26, 27, 1983 for Unit Nos.3 and December 29, 30 and 31, 1982 and February 24, 25, 26 and 27, 1983 for Unit No.4. In the first place, these do not show and it is not the case that they show that the operation of the Units at those times was in accordance with good industry practice. Moreover, even if one were to ignore the inconsistencies pointed by the Claimants’ witnesses in the log sheets, a representation and warranty of this magnitude was unwarranted for the language of the representation and warranty suggests that the Units were operated over a span of time, of about 25 years, to produce 120 MW when operated in accordance with good industry practice. The inconsistencies cannot, however, be ignored for they suggest that what was recorded in the concerned log sheet was not, in fact, the production of 120 MW. When, for the same hour of the same day, the production is measured at 120 MW at one spot and 115 MW at another, it cannot be said with any confidence that the production was in fact 120 MW. The representation and warranty given to the Respondent as aforesaid, must, therefore, be held to be a positive assertion in a manner not

15 warranted by the information of the Respondent, of that which was not true, though the Respondent might believe it to be true. In other words, the representation and warranty was a misrepresentation as defined by Section 18 of the Contract Act. The evidence of the Claimant’s witness Richetti is that the Claimants entered into the contracts only because of this representation and warranty and his evidence to that effect has not been dented in cross examination. Under Section 19 of the Contract Act, when consent to an agreement is caused by misrepresentation, the agreement is a contract voidable at the option of the party whose consent was so caused. The Claimants desire to avoid the contracts and we think that, in the circumstances they are entitled to do so.

In so far as Issue No.1 is concerned, the Respondent contracted to make available to the Claimants, free of charge, “all relevant records of the power station and the existing Operations and Maintenance Manual of the power station.” Mr. Agnihotri submitted that the words “relevant records” meant such records as were in the possession of the Respondent. We do not find this interpretation acceptable. “All relevant records of the power station” covers each and every record relating to the power station that is relevant for the purpose of the refurbishment thereof. The phraseology used leads to the conclusion that the Respondent was stating that it had in its possession all the relevant records and would make them available to the Claimants, along with the operations and maintenance manual. The evidence on record shows clearly that the Respondent possessed very few of the relevant records of the Units. The failure of the Respondent to supply to the Claimants the relevant records of the Units was very likely to have a material adverse effect on the ability of the Claimants to perform their obligations under the contract and, as such, was a substantial breach by the Respondent of the contract.”

14. The Arbitral Tribunal determined Issues 2 and 3

in favour of the Claimant by observing that there

16 was no waiver on the part of the Claimant regarding

production of the Letter of Comfort. The production

of the Letter of Comfort was a fundamental

condition of the Agreements and the failure to

produce the same was a breach on the part of the

Board. The invocation of Bank Guarantees by the

Board was found to be improper by the Arbitral

Tribunal in its findings on Issues 8 and 9. According

to the Tribunal, the Contract could have been

terminated only after expiry of 30 days’ cure period.

The invocation of Bank Guarantees in this case was

done on 23rd June, 2001 which was prior to the

issuance of the notice of default on 29 th August,

2001. The termination of the Agreement by the

Board was found to be bad in law. Exhibit–FF

annexed to the Statement of Claim sought for by the

Claimant pertains to the return of the amounts for

which Bank Guarantees were given by the Claimant

and invoked by the Board, along with interest.

Exhibit- GG to the Statement of Claim includes

amount spent by the Claimant towards the Residual

Life Assessment (R.L.A.) Study and other material 17 procured including electric drum level indicator, UPS

system– 20 KVA, boiler pressure parts, etc. After a

detailed scrutiny of the evidence on record, the

Arbitral Tribunal awarded the Claimant amounts

mentioned in Exhibits- FF and GG appended to the

Statement of Claim. Issue No. 13 was answered

against the Claimant. Claim forming part of Ex. HH

(damages for wrongful termination of contract) to

the statement of claim was rejected.

Submissions

15. We have heard Shri Dushyant Dave, learned

Senior Counsel for the Appellants and Shri S.U.

Kamdar, learned Senior Counsel for the

Respondents. Shri Dave submitted that the award of

the Arbitral Tribunal suffers from fundamental flaws

and requires interference. He relied upon the

judgments of this Court to contend that the award is

perverse and is vitiated due to patent illegality. He

found fault with the finding of the Arbitral Tribunal

that there was misrepresentation on the part of the

Board. He submitted that the plant was

manufactured by BHEL in the year 1972 which 18 certified that the Units have the capacity of 120 MW.

Commenting on the representation and warranties

found in Clause 19.2 (vii) of the Agreements, he

stated that it cannot be said that there was any

misrepresentation on the part of the Board. He

placed reliance on the log sheets to show that the

plant was running to its capacity of 120 MW. He

further submitted that there were about 13

inspections conducted by experts from the

Claimants’ side and it is inconceivable that they did

not know about the capacity and performance of the

plant. He argued that all the available records were

furnished to the Claimant. According to him, the

Claimant had full knowledge about the capacity and

the performance of the plant in spite of which they

did not perform their part of the Contract for reasons

best known to them. Shri Dave proceeded to submit

that after a series of meetings and exchange of

letters, the Claimant agreed for the Zero Date as 9 th

March, 2000. After such agreement, the Claimant is

said to have waived its right of claiming the Letter of

Comfort from the Power Finance Corporation. 19 According to him, the Letter of Comfort was not a

fundamental condition of the Contract and it had no

bearing on the performance of the obligation on the

part of the Claimant. He further stated that the

Claimant was aware of the fact that the amounts

advanced to the Claimant were given by the Power

Finance Corporation to the Board. He found fault

with the finding of the Arbitral Tribunal that the

termination of the Contract by the Board was illegal.

16. Shri Dave highlighted the error committed by

Arbitral Tribunal in treating all the Bank Guarantees

as furnished in pursuance of Clause 4 of the Overall

Coordination Agreement. The conclusion of the

Arbitral Tribunal that the invocation of the Bank

Guarantee was not proper as it was done prior to the

termination of the Contract was challenged by Shri

Dave. He further urged that the award towards

Issue No.12 deserves to be set aside as the Claimant

has been awarded compensation for the goods

which were not supplied. According to Shri Dave,

the Claimant neither supplied nor commenced any

work according to the Contract in spite of which the 20 Arbitral Tribunal has allowed these claims. There is

a lack of judicial approach on the part of arbitral

Tribunal for which reason Shri Dave urged that the

award deserves to be set aside.

17. Shri S.U. Kamdar, learned Senior Counsel

contended that the award of the Arbitral Tribunal is

well reasoned after taking into account the entire

material on record and it does not suffer from any

infirmity. He submitted that the parameters for

exercise of power by the Courts under Section 34 of

the Act are well settled. Applying the principles laid

down by this Court in several judgments, Shri

Kamdar contended that this Appeal should not be

entertained. He further submitted that a plain

reading of the Clause 19.2 (vii) pertaining to the

representation and warranties would show that there

was a misrepresentation on the part of the Board.

The Clause which was added after deliberations

between the parties is to the effect that both Units 3

and 4 operated at 120 MW when operating in

accordance with good industry practice. He referred

to the evidence on record before the Tribunal to 21 argue that there is no material to show that the

plant operated at 120 MW. He stated that the

incomplete log sheets that were filed by the Board

also suffer from internal discrepancies as rightly held

by the Arbitral Tribunal. Shri Kamdar further

submitted that the Arbitral Tribunal correctly found

furnishing a Letter of Comfort by Power Finance

Corporation to be a fundamental condition which

was breached by the Board. He relied upon Clause

22 of both the Supply Contracts to submit that the

counsel for the Board was not right in arguing that

there was a waiver on the part of the Claimant. He

further argued that there is voluminous oral and

documentary evidence on record to demonstrate

that material was procured and equipment was

manufactured for supply as per the terms of the

contract. He also stated that the equipment which

was specially designed for the Thermal Plants at

Amarkantak will be of no use to any other plant. It

was only due to the breach on the part of the Board

that the supply did not take place. Concluding his

22 submissions, Shri Kamdar submitted that the appeal

deserves to be dismissed.

Section 34 of the Act - ‘Public Policy’

18. It is necessary to refer to the settled law on the

scope of Sections 34 of the Act. In this case we are

concerned with the point as to whether an arbitral

award can be set aside for being in conflict with the

public policy of India. An arbitral award can be set

aside if it is contrary to (a) fundamental policy of

Indian law, or (b) the interest of India, or (c) justice

or morality. (Renusagar Power Co. Ltd. v.

General Electric Co.1 ) Patent illegality was added

to the above three grounds in ONGC v. Saw Pipes

Ltd.2. Illegality must go to the root of the matter

and incase the illegality is of trivial nature it cannot

be held that the award is against the public policy. It

was further observed in the said judgment (ONGC

v. Saw Pipes (supra)) that an award could also be

set aside if it is so unfair and unreasonable that it

shocks the conscience of the Court. In Delhi

Development Authority v. M/s. R.S. Sharma &

1 (1994) Supp.1 SCC 644 2 (2003) 5 SCC 705 23 Co.3 it was held that an award can be interfered with

by the Court under Section 34 of the Act when it is

contrary to :

a) substantive provisions of law; or

b) provisions of the 1996 Act; or

c) against the terms of the respective contract; or

d) patently illegal; or

e) prejudicial to the rights of the parties

The fundamental policy of India was explained in

ONGC Ltd. v. Western Geco International Co. Ltd.4 as

including all such fundamental principles as providing a

basis for administration of justice and enforcement of law

in this country. It was held inter alia, that a duty is cast on

every tribunal or authority exercising powers that affect

the rights or obligations of the parties to show a ‘judicial

approach’. It was further held that judicial approach

ensures that an authority acts bona fide and deals with the

subject in a fair, reasonable and objective manner and its

decision is not actuated by any extraneous considerations.

It was also held that the requirement of application of mind

on the part of the adjudicatory authority is so deeply

embedded in our jurisprudence that it can be described as

a fundamental policy of Indian law. This Court further

3 (2008) 13 SCC 80 4 (2014) 9 SCC 263 24 observed that the award of the Arbitral Tribunal is open to

challenge when the arbitrators fail to draw an inference

which ought to be drawn or if they had drawn an inference

which on the face of it is untenable resulting in miscarriage

of justice. The Court has the power to modify the offending

part of the award in case it is severable from the rest

according to the said judgment (Western Geco ltd.

(supra)).

19. The limit of exercise of power by Courts under

Section 34 of the Act has been comprehensively

dealt with by Justice R.F. Nariman in the case of

Associate Builders v. Delhi Development

Authority5. Lack of judicial approach, violation of

principles of natural justice, perversity and patent

illegality have been identified as grounds for

interference with an award of the Arbitrator. The

restrictions placed on the exercise of power of a

Court under Section 34 of the Act have been

analyzed and enumerated in Associated Builders

(supra) which are as follows:

5 (2015) 3 SCC 49 25

a) The Court under Section 34(2) of the Act, does not

act as a Court of appeal while applying the ground of

“public policy” to an arbitral award and consequently

errors of fact cannot be corrected.

b) A possible view by the arbitrator on facts has

necessarily to pass muster as the Arbitrator is the sole

judge of the quantity and quality of the evidence.

c) Insufficiency of evidence cannot be a ground for

interference by the Court. Re-examination of the facts to

find out whether a different decision can be arrived at is

impermissible under Section 34 (2) of the Act.

d) An award can be set aside only if it shocks the

conscience of the Court.

e) Illegality must go to the root of the matter and

cannot be of a trivial nature for interference by a Court. A

reasonable construction of the terms of the contract by the

arbitrator cannot be interfered with by the Court. Error of

construction is within the jurisdiction of the Arbitrator.

Hence, no interference is warranted.

f) If there are two possible interpretations of the

terms of the contract, the arbitrator’s interpretation has to

26 be accepted and the Court under Section 34 cannot

substitute its opinion over the Arbitrator’s view.

Application of the Law

20. The Arbitral Tribunal held that the termination of

the contract by the Board on 08.01.2002 was illegal.

This finding was on the basis that the Board

committed a breach of the contract. The breach of

the contract on the part of the Board was due to the

failure in furnishing Letter of Comfort from the Power

Finance Corporation, non-supply of the technical

documents and information as required by Clause

5.8 (iv) of the Onshore Service Agreement and

misrepresentation.

Letter of Comfort and Waiver

21. Clause 5.14 of the Onshore Services Contract

and Clause 5.6 of the Onshore Supply Contract

provide for an irrevocable Letter of Comfort to be

issued by the Power Finance Corporation in favour of

the Claimant, on the date of issuance of the Notice

to Proceed by the Board. There is a further

requirement in the said Clauses that the Board shall

ensure that the Letter of Comfort is maintained in

27 full force and effect throughout the term of the

agreements. The Claimant’s contention before the

Arbitral Tribunal was that the production of the

Letter of Comfort was a fundamental condition of

the agreements and the failure to produce it was a

breach of the contract. The Board’s response to

such contention was that the Claimant is deemed to

have waived the production of the Letter of Comfort.

Waiver was pleaded by the Board on the basis of a

letter dated 10.03.2000 written by the Claimant

accepting the Zero Date as 09.03.2000 and the oral

concession made by Sh. G. Ravindran, a

representative of the Claimant.

22. The Arbitral Tribunal opined that the production

of Letter of Comfort was a fundamental condition of

the agreements and the Claimant cannot be said to

have waived the production of Letter of Comfort.

The contention of oral concession made by

Sh.G.Ravindran was considered by the Arbitral

Tribunal with reference to the evidence on record.

The oral evidence of Sh. Saxena, Superintending

Engineer and Sh.Shrivastava, Additional 28 Superintending Engineer of the Board was referred

to by the Arbitral Tribunal to hold that they admitted

to the fact that there was no waiver to the

production of Letter of Comfort in writing by the

Claimants. Sh.Saxena, Superintending Engineer of

the Board stated in his evidence that

Sh.G.Ravinderan made a concession of waiver of

production of the Letter of Comfort in a meeting.

However, the details of the meeting could not be

given by Sh.Saxena. The Arbitral Tribunal refused to

accept the point canvassed by the Board relating to

waiver on the basis of the evidence of Sh.Saxena.

The contents of the letter dated 10.03.2000, written

by the Claimant to the Board were examined by the

Arbitral Tribunal to conclude that there was no

waiver of production of the Letter of Comfort.

According to the Arbitral Tribunal, the Claimant did

not insist on the Letter of Comfort to be produced as

a pre-condition to the Zero Date, which did not

preclude to their seeking the same at a later date as

per Clause 16.5 of the Overall Co-ordination

Agreement and Clause 22 & 23 of the Supply and 29 Services Contracts respectively. The production of

the Letter of Comfort was a fundamental condition

of the agreements and the failure to produce the

same was a breach by the Board. The above findings

on the Letter of Comfort are on appreciation of

evidence. We do not see any reason to differ with

the said findings.

Non-Supply of Documents and Misrepresentation

23. The evidence of Sh. Cesare Ricchetti, Electrical

Engineer working with the Claimant is to the effect

that he took part in the negotiations which led to the

signing of the contract. He deposed that he

requested for information from the Station Director

of the Board at Amarkantak and Sh. B.S. Chouhan,

Member Generation, as to whether Units 3 and 4

were originally designed and constructed to achieve

a capacity of 120 MW. The Station Director

responded to the query and confirmed that the Units

had been designed and constructed to achieve a

capacity of 120 MW. Sh.Ricchetti further stated that

it was not possible on a visual inspection to assess

the originally installed capacity. The capacity could

30 have been assessed by examining the parameters

and methods used during the original design, the

operational log data and the original performance

test. These records were not furnished to the

Claimants despite repeated requests by the

Claimants. As the Claimants were not satisfied with

the material, they insisted on a formal warranty,

which was included in Clause 19.2 (vii) of the

Onshore Supply Agreement, Clause 19.2(vii) reads

as follows:

“19.2 MPEB represents and warrants to ANSALDO that:

…….

(vii) each of Unit No.3 and Unit No.4 was designed and constructed to achieve the operating parameters, and did in fact operate at 120 MW when operating in accordance with good industry practice.”

24. Sh. Ricchetti categorically stated in his evidence

that Claimants would not have signed the contracts

without the above warranty. Sh.Saxena, Additional

Superintending Engineer deposed before the Arbitral

Tribunal that the warranty was made on the strength

of the manufacturer’s plaque attached to the Units.

He stated that the Units had, in fact, operated at

120 MW when the performance was in accordance 31 with good industrial practice. The Arbitral Tribunal

took note of the fact that no performance test was

carried out upon commissioning of the Units.

Considering the log sheets that were filed on behalf

of the Board for three days in December, 1982 and

four days in February, 1983, the Arbitral Tribunal was

of the opinion that the said records do not show that

the Units operated at 120 MW was in accordance

with good industrial practice. Moreover, the Tribunal

found that there were inconsistencies in the

readings recorded in the log sheets. The Arbitral

Tribunal concluded that the positive averment by the

Board that the Units were, in fact, operating at 120

MW for over a period of 25 years was clearly a

misrepresentation. According to the Arbitral

Tribunal, the Claimant was entitled to avoid the

contract as the consent to the contract was obtained

by a misrepresentation.

25. Sh. Dave submitted that the Arbitral Tribunal

committed a serious error in concluding that there

was misrepresentation on the part of the Board. He

also criticized the findings of the Arbitral Tribunal on 32 Section 19 of the contract by relying upon

illustration (b) therein. It will be useful to reproduce

Sections 18 and 19 of the Indian Contract Act, 1872

which read as under:

“18. "Misrepresentation" defined "Misrepresentation" means and includes-

(1) the positive assertion, in a manner not warranted by the information of the person making it, of that which is not true, though he believes it to be true; (2) any breach of duty which, without an intent to deceive, gains and advantage to the person committing it, or any one claiming under him; by misleading another to his prejudice, or to the prejudice of any one claiming under him;

(3) causing, however innocently, a party to an agreement, to make a mistake as to the substance of the thing which is the subject of the agreement.

19. Voidability of agreements without free consent

When consent to an agreement is caused by coercion, fraud or misrepresentation, the agreement is a contract voidable at the option of the party whose consent was so caused.

A party to a contract, whose consent was caused by fraud or misrepresentation, may, if he thinks fit, insist that the contract shall be performed, and that he shall be put on the position in which he would have been if the representations made had been true.

Exception: If such consent was caused by misrepresentation or by silence, fraudulent within the meaning of section 17, the contract, nevertheless, is not voidable, if the party whose consent was so caused had the means of discovering the truth with ordinary diligence.

Explanation: A fraud or misrepresentation which did not cause the consent to a contract of the party on whom such fraud was practiced, or to whom such misrepresentation was made, does not render a contract voidable.

33 Illustrations

(a) .....

(b) A, by a misrepresentation, leads B erroneously to believe that five hundred mounds of indigo are made annually at A's factory. B examines the accounts of the factory, which show that only four hundred maunds of indigo have been made. After this B buys the factory. The contract is not voidable on account of A's misrepresentation.”

26. On appreciation of the oral and documentary

evidence produced by the parties, the assertion

made by the Board that the Units were achieving a

capacity of 120 MW when operating in accordance

with the good industrial practice, was found to be

incorrect by the Arbitral Tribunal. We do not intend

to take a different view on the findings of the fact

recorded by the Arbitral Tribunal.

27. Even if the Board believed that Units 3 and 4

were in fact designed for a capacity of 120 MW and

operated at 120 MW, if it was found later that the

assertion relating to the said capacity and

functioning was not true, a clear case of

misrepresentation, as per Section 18 of the Contract

Act was made out.

34

28. Mr.Dave relied upon the exception to Section 19.

According to the exception, a contract is not

voidable if the party whose consent was taken had

the means of discovering the truth with ordinary

diligence, even if the consent was caused by

misrepresentation. He also relied upon illustration

(b), which deals with sale of a factory by B on the

representation of A that 500 mounds of Indigo are

made annually in the factory belonging to A. As B

purchased the factory after examining the accounts

of the factory, the contract was not voidable on

account of A’s misrepresentation. Sh. Dave relied

upon a judgment of the Full Bench of the Judicial

Commissioner’s Court, Nagpur, in (Hazi) Mahomad

Hazi Wali Mahomad v. Ramappa 6. In that case,

the Defendant in the suit represented to the Plaintiff

that the value of the property was about Rs.9,000/-.

Jackson A.J.C. held that even if such a statement was

made by the Defendant, the Plaintiff was not entitled

for a decree on the ground that it was impossible to

believe that the Plaintiffs solely relied upon the

6 AIR 1929 Nagpur 254 35 statement of the Defendant as to the value of the

property. It was further held that the Plaintiff could

have obtained the value of the property without

much trouble. In view of the above facts, the

Judicial Commission observed as follows:

“Under S.19, Contract Act, the rights given to a party who has entered into a contract under fraud or misrepresentation, are to avoid the contract or to insist on the contract being performed. The section does not entitle the party to insist on an entirely different contract being performed. Moreover, the rights given by S.19 are given only to a party whose consent to the contract was, in fact, caused by the fraud or misrepresentation.”

The said judgment has no application to the facts of

this case. Similarly, Ganga Retreat & Towers Ltd. v.

State of Rajasthan7 relied upon by Sh.Dave would not be

of any assistance to him.

29. As discussed earlier, the evidence on record

discloses that the Claimants could not ascertain the

actual capacity and the functioning of the Units in

spite of their best efforts. The relevant records were

not furnished by the Board to enable the Claimants

to ascertain the actual facts. The evidence on

record supports the contention of the Claimants that

it was not possible to ascertain the capacity and

7 (2003) 12 SCC 91 36 functioning of the Units only on the basis of visual

inspections. We are afraid that we cannot agree with

the submission of Sh.Dave on the point of

misrepresentation as we find no good reason to

differ from the view taken by the Arbitral Tribunal.

Ext.GG- Value of the Equipments Supplied and Works Performed

30. An amount of Rs.11,14,55,042/- with interest

was claimed towards the value of the RLA study and

the performance of work relating to drum level

system, UPA system, pressure parts and engineering

drawings which could not be supplied due to the

termination of the agreements. A detailed affidavit

was filed by Sh.Fabio Rolla in lieu of his

examination-in-chief. Voluminous evidence was

produced to show the actual expenditure towards

the above works. There was no meaningful

cross-examination of Sh. Fabio Rolla on behalf of the

Board. The determination of Issue No.12 by the

Arbitral Tribunal holding that the Claimants are

entitled to the amounts claimed in Ex.GG annexed to

the statement of claim i.e. Rs.11,14,55,042/- is on

37 the basis of appreciation of evidence. We have no

hesitation in approving the said finding of fact of the

Arbitral Tribunal.

Ext. FF- Refund of amounts of Bank Guarantees

31. The Claimants furnished three Bank Guarantees.

Two Bank Guarantees dated 22.02.2000 and

23.02.2000 were for Rs.9.29 crores and US $

1,708,100/- towards the advance payment to be

paid by the Board. The third Bank Guarantee was

given by ANZ Grindlays Bank, New Delhi on behalf of

the Claimant for Rs.18.48 crores which was towards

performance guarantee under Clause 4.1 of the

Overall Coordination Agreement. The Bank

Guarantees dated 22.02.2000 and 23.02.2000 were

in terms of Clause 9.2 of the Onshore and Offshore

Supply Contracts respectively. All the three Bank

Guarantees were invoked by the Board on

23.06.2001. The Bank Guarantees given on

22.02.2000 and 23.02.2000 were conditional. The

condition for invocation of such Bank Guarantees

was ‘non-fulfillment of the contractual obligations by

the debtor’. The third Bank Guarantee of

38 24.02.2000 was an unconditional Bank Guarantee.

The Arbitral Tribunal was of the opinion that the

invocation of the Bank Guarantee was improper as it

was not preceded by a Notice of Default as

contemplated in Clause 16.3 of the Supply Contracts

and a subsequent notice of termination under

Clause 17.1 of the Supply Contracts. In view of the

finding of the Arbitral Tribunal that the Board

committed a serious breach of the contract and

wrongfully terminated the contract, the Claimant

was held to be entitled to return of the amounts for

which the Bank Guarantees were given.

32. The Bank Guarantee given on 24.02.2000 was a

Performance Bank Guarantee and the Claimant is

entitled for return of the amount for which the Bank

Guarantee was given. The Arbitral Tribunal,

however, failed to take notice of the fact that the

other two Bank Guarantees were given for the

amounts to be advanced by the Board. In fact, the

Board had advanced the said amounts to the

Claimants. We are of the opinion that the Claimant

is not entitled for return of the amounts involved in 39 the Bank Guarantees dated 22.02.2000 and

23.02.2000 as they were towards the amounts

advanced by the Board. The rejection of the claim

pertaining to the damages mentioned in Ex. HH of

the statement of claim which includes loss of profit,

over-heads and loss of commercial opportunities

clearly indicates that the Arbitral Tribunal never

intended to grant any damages to the Claimant.

The claims allowed by the Arbitral Tribunal pertained

only to the return of the Claimants’ money involved

in the Bank Guarantees and the amounts actually

spent by the Claimants.

Conclusion

33. We uphold the award of the Arbitral Tribunal with

the modification that the Claimants are not entitled

for the amounts involved in the Bank Guarantees

dated 22.02.2000 and 23.02.2000 given by the

Claimants.

34. To avoid confusion, the Award of

Rs.11,14,55,042/-, with interest at the rate of 12%

per annum from 29th July, 2002 until payment or

realization towards the claim in Ex.GG and

40 Rs.18,48,00,000/- with interest thereon at the rate of

12% per annum from 5th July, 2001 until payment or

realization, which is the amount pertaining to the

Performance Bank Guarantee, is affirmed.

35. For the afore-stated reasons, the appeals are

dismissed with the above modification.

........................................J. [S.A. BOBDE]

........................................J. [L. NAGESWARA RAO]

New Delhi, April 16, 2018

41

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free