Miss Lucy
← All judgments

M.K. Abraham & Co vs State Of Kerala & Anr

Supreme Court7 July 2009J M Panchal · R V Raveendran

Ratio decidendi

The rule this decision rests on

Where a contract consists of multiple layers of documents—including printed standard forms, cyclostyled amendments, typed additions and deletions, and handwritten corrections—all of which contain terms dealing with the same subject matter, the following rules of construction apply to resolve apparent or irreconcilable inconsistencies: (i) cyclostyled amendments prevail over printed terms; (ii) typewritten additions prevail over printed terms and cyclostyled amendments; (iii) handwritten corrections prevail over all earlier forms. Where inconsistency arises between documents finalized at different points in time, the document finalized subsequently in point of time normally prevails over the earlier document. Where a standard form contract applicable to government works of one category (here, Public Works Department contracts) is employed for works of a different category with a different policy requirement (here, National Highway projects), and a specific cyclostyled amendment signed by both parties is appended to the standard form incorporating provisions required by the second category, that cyclostyled amendment prevails over the bars to arbitration contained in the original standard form, even if those bars are repeated in multiple printed clauses. Accordingly, an arbitration agreement exists where the parties have executed a cyclostyled attachment slip to the contract agreement expressly incorporating by reference an arbitration clause prescribed by the contracting agency. Whether no-claim certificates were obtained through coercion is a question of fact to be determined on the merits in proceedings under Section 11 of the Arbitration & Conciliation Act, 1996, but this determination is not precluded by a prior finding that an arbitration agreement exists between the parties.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

Reportable IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 4151 OF 2009 (Arising out of SLP [C] No.11118 of 2006)

M.K. Abraham & Co. ... Appellant

Vs.

State of Kerala & Anr. ... Respondents

WITH

CIVIL APPEAL No. 4155/2009 (Arising out of SLP (C) No11119/2006)

Vijay Constructions ... Appellant

Vs.

State of Kerala & Anr. ... Respondents

JUDGMENT

R.V. RAVEENDRAN, J.

Delay condoned as appellants were pursuing the remedy by way of

writ petition till 14.12.2005. Leave granted.

2

FACTS (M.K. ABRAHAM & CO.)

2. A section of the work relating to NH-49 was awarded to the appellant

under letter of acceptance dated 1.12.1999 issued by the second respondent

[Project Director (SE), National Highway (ADB), Circle Edappally,

Cochin]. A formal contract agreement was executed by them on the same

day. By letter dated 9.10.2001, the appellant-contractor called upon the

Executive Engineer, National Highways (Roads) Division to pay certain

amounts as compensation for the losses caused on various accounts. The

Executive Engineer denied the claim by a reply sent in December, 2001

contending that there was a full and final settlement of the claims by paying

the amounts due under the final bill. Being dissatisfied with the said

rejection, the appellant by notice dated 1.4.2002 called upon the Executive

Engineer to refer the disputes in regard to its claims aggregating to

Rs.42,26,432/58 to arbitration. As there was no response, the appellant by

letter dated 26.8.2002 nominated his arbitrator and called upon the second

respondent to nominate the department's arbitrator in terms of the contract

so that the Director-General (Road Development), Ministry of Surface &

Transport, could nominate the Chairman - Arbitrator. The second respondent

failed to comply. Therefore, the appellant by letter dated 28.10.2002

requested the Director-General to appoint the arbitrator on behalf of the 3

employer as also the Chairman of the Arbitration Committee. As the

Director-General also failed to comply, the appellant filed an application

dated 9.4.2003 under section 11 of the Arbitration & Conciliation Act, 1996

(for short `the Act'). The designate of the Chief Justice dismissed the

application by order dated 19.12.2003.

FACTS (VIJAY CONSTRUCTIONS)

3. A section of the work relating to NH-49 was awarded to the appellant

under letter of acceptance dated 7.9.2000 issued by the second respondent. A

formal contract agreement was executed on 26.9.2000 between them. The

work was completed on 30.4.2001. According to Appellant, the Executive

Engineer informed him that unless it gave a no claim certificate, even the

admitted dues would not be released. Under such coercion, it gave such a

certificate on 23.1.2002, so that it can receive at least the admitted amounts.

Immediately on receiving the admitted dues, the appellant claims to have

informed the respondents by letter dated 2.2.2002 that it signed the no claim

undertaking under coercion and therefore, it had no legal effect. It also

called upon the respondent to redress its grievances and claims. As there was

no response, the appellant by notice dated 19.8.2002 called upon the

Executive Engineer, who was the "Engineer" under the contract to give his

decision on its claims, in terms of the contract. As the "Engineer" failed to 4

do so within 60 days, the appellant wrote to the Director-General (Road

Development), Ministry of Surface & Transport on 26.10.2002, to appoint a

sole Arbitrator to adjudicate upon the disputes. The appellant filed a petition

under section 11 of the Arbitration & Conciliation Act, 1996 (for short `the

Act') contending that the contract between the parties provides for

settlement of disputes by arbitration and that in spite of appellant taking

necessary pre-arbitration steps in terms of the arbitration clause, there was

no compliance. The designate of the Chief Justice dismissed the application

by order dated 19.12.2003.

COMMON ISSUE

4. In both cases, the appellants contend that there is an arbitration

agreement in their contracts dated 1.12.1999 and 26.9.2000. They submitted

that each was entrusted a section of the project "National Highway 49 -

Mathura Cochin Road" which was executed by the Ministry of Surface

Transport, Government of India through the respect State Public Works

Department. The Ministry of Surface Transport, Government of India, by

communication dated 28.9.1994 informed all the State Public Works

Departments and all Chief Engineers in all States dealing with National

Highways, that a standard contract clause prescribing the procedure to be

followed for appointment of arbitrators was finalized by the Ministry and 5

enclosed a copy of the arbitration provision and with instructions to

incorporate the said clause in the bidding conditions for the National

Highway works and to ensure that the said arbitration clause was

compulsorily made a part of the bidding conditions in the respective States.

The relevant portions of the `contract clause for inclusion in the bidding

conditions for wholly domestic funded NH works' enclosed to the

Ministry's letter dated 28.9.1994 reads thus:

"2. Arbitration

All disputes or differences in respect of which the decision, if any, of the Engineer has not become binding as aforesaid and amicable settlement has not been reached, shall, on the initiative of either party, be referred to the adjudication. The sole Arbitrator for claims upto Rs.5.00 lakhs shall be appointed by the State Chief Engineer. Such appointed Arbitrator shall be a person not below the rank of Executive Engineer and not connected with the contract. The claims above Rs.5.00 lakhs and upto Rs.25.00 lakhs shall be settled by a sole arbitrator to be nominated by the Director General (Road Development), Ministry of Surface Transport, Government of India, New Delhi. A copy of the order shall be supplied to both the parties. The claims of more than Rs.25.00 lakhs shall be referred to the adjudication of a Committee of three arbitrators. The Committee shall be a composed of one arbitrator to be nominated by the Employer, one to be nominated by the Contractor and the third, who will also act as the Chairman of the Committee, to be nominated by the Director General (Road Development), Ministry of Surface Transport (Roads Wing); Government of India, New Delhi. If either of the parties abstain or fail to appoint his arbitrator, within 60 days after receipt of notice for the appointment of such arbitrator, then the Director-General (Road Development), Ministry of Surface Transport (Roads Wing), Government of India, shall also appoint such arbitrator(s). A certified copy of the appointment made by the Director General (Road Development), Ministry of Surface Transport (Roads Wing), Government of India, shall be furnished to both parties. The decision about the appointment of the arbitrators by the Ministry of Surface Transport shall be final and binding on both the parties. Any person appointed as Arbitrator shall not be connected with the work.

Save as otherwise provided in the Contract, the Arbitration shall be conducted in accordance with the provisions of the Indian Arbitration Act 6

1940 or any statutory modifications or enactment thereof and shall be held at such place and time in India as the arbitrator or the Committee of Arbitrators may determine. The decision of the Arbitrator(s) shall be final and binding as may be determined by the Arbitrator(s)."

In view of the said communication, a slip signed by both parties was

attached to the respective contracts of the appellants. The attachment slip

reads thus:

"Arbitration Clause as per Ministry of Surface Transport's letter No.RW/NH-34041/3/94-DO-III dated 28.9.94 will be applicable."

The contractors contend that the contracts entered by the respondents,

contain a provision for arbitration.

5. The respondents contend that there was no provision for arbitration as

it was specifically excluded, relying upon clauses 24 and 24(a) of the

"Notice Inviting Tenders for Works" and clause (3) in the printed standard

form of Agreement executed between the parties extracted below:

"Clauses 24 and 24(a) of Notice Inviting Tender for Works

24. Arbitration shall not be a means of settlement of dispute or claim arising out of the contract relating to the work.

(G.O.Ms.No.10/86/PW & T dated 27.10.1986)

24(a). All disputes and differences arising out of the contract that may be executed in pursuance of this notification shall be settled only by the Civil Court in whose jurisdiction the work covered by the contract is situated or in whose jurisdiction the contract was entered into in case the works extends to the jurisdiction of more than one Court. (G.O.Ms.53/88/PW & T dated 30.9.1988)

Clause (3) of standard form of Agreement 7

(3) The parties to this contract agreed to undertake the condition that arbitration shall not be a means of settlement of disputes or claim or anything on account of this contract."

6. The designate of the Chief Justice of the High Court held that having

regard to the specific bar against arbitration contained in clauses 24 and

clause 24(a) of the `Notice inviting Tenders for Works' and clause (3) of the

standard form of Agreement, there cannot be any reference to arbitration.

The Court also rejected the claim of the contractors that there is a provision

for arbitration by holding :

"The notification relied on by the applicant has not been accepted by the respondents and it had not become part of the contract. The file did not disclose the acceptance of any such notification."

The appellants challenged the orders of the designate of the Chief Justice

holding that there was no arbitration agreement, in writ petitions which were

dismissed by a common order dated 14.12.2005 as not maintainable.

Thereafter, the appellants have challenged the orders of the designate of the

Chief Justice in these appeals by special leave contending that the High

Court ignored the relevant attachment to the contract which incorporated the

arbitration clause by special reference.

7. The common question that arises for consideration in these appeals is

whether there is an arbitration agreement between the parties. 8

THE CONTRACT DOCUMENT

8. To decide the issue, it is necessary to refer to and understand the

evolution of the contract document. In Kerala, in regard to the construction

contracts, the Public Works Department, enters into a short `contract

agreement' to serve as a preamble to which are annexed a standard printed

form of Articles of Agreement, the conditions of contract, notice inviting

tender for works, special conditions, and Madras Detailed Standard

Specifications (MDSS for short). All these attachments are printed forms

with added amendments in cyclostyled forms. In addition there will be other

annexures including tender schedule, plans, additional special conditions etc.

8.1. Clause 73 of the MDSS contained a provision for arbitration. The

State Government took a decision in or about 1986 to delete the provision

for arbitration clause in PWD contracts. As a consequence, the standard

form of `Notices inviting Tenders for Works' [clauses 24 and 24(a)] and the

standard form of Agreement (clause 3) contain specific printed conditions

which bar arbitration. Further the preamble to the standard form of

Agreement also clearly states "whereas the contractor has also signed the

copy of the Madras Detailed Standard Specifications excluding clause 73

and other clauses relating to arbitration contained therein......" 9

9. If the contract was a contract entered into by the Public Works

Department contract of the State Government, necessarily the said bar

against arbitration would operate. There is no doubt that if the contract

contained a provision specifically barring arbitration, there can be no

reference to arbitration. But the position is different where the standard

format of the State PWD is used with modifications in regard to construction

contracts of another department which has taken a policy decision to have a

provision for arbitration compulsorily in all its contracts, and in view of it,

the arbitration clause is made a part of the contract by a further addition to

the standard form of Agreement. In fact Government of Kerala by its G.O.

(MS). No. 68/88/PWD dated 19.11.1988 clarified, while barring arbitration

in regard to PWD contracts, that if any work is financed by an agency which

requires a provision for arbitration, then a provision for arbitration may be

provided in the agreements relating to such works. In these cases, we are

concerned, not with regular PWD contracts, but contracts relating to another

agency, that is the National Highway Project, entered by Project Director

(S.E.), National Highway (ADB) Project Circle. The said National Highway

Projects has special provision relating to arbitrations which does not find a

place in the Kerala PWD contracts. In such a situation, merely because the

standard forms of PWD were used for entering into contracts, or because the 1 0

contracts were executed through PW Department of the State Government, it

cannot be contended that special provisions applicable to National Highway

Projects specifically added to the contract should be ignored.

10. If a contract consists of a printed form with cyclostyled amendments,

typed additions and deletions and handwritten corrections, an endeavour

shall be made to give effect to all the provisions. However, in the event of

apparent or irreconcilable inconsistency, the following rules of construction

will normally apply :

(i) The cyclostyled amendments will prevail over the printed terms;

(ii) The type-written additions will prevail over the printed terms and cyclostyled amendments;

(iii) Hand written corrections will prevail over the printed terms, cyclostyled amendments and typed written additions.

The above rules have evolved from the well known maxim of construction

that "written, stamped or typed additions, when inconsistent with the printed

terms, would normally prevail over the printed terms" and proceeds on the

assumption that the printed form contained the original terms, and changes

thereto were incorporated by the cyclostyled amendments, followed by

changes by type-written additions and lastly the hand written additions. The

logical explanation for such assumption is this: The printed form contains

standardized terms to suit all contracts and situations. It is not drafted with 1 1

reference to the special features of a specific contract. When such a standard

form is used with reference to a specific contract, it becomes necessary to

modify the standard/general terms by making additions/alterations/deletions,

to provide for the special features of that contract. This is done either by way

of an attachment of an annexure to the standard printed form, incorporating

the changes, or by carrying out the required additions/alterations/deletions in

the standard form itself. Such additions/alterations/deletions are done by

typing/stamping/hand. We may refer to the following oft-quoted enunciation

of the legal position by Lord Ellenborough in Robertson v. French [1803-

13] All ER Rep.350 with reference to printed form of contract with hand-

written additions :

"....... that the words super added in writing are entitled, nevertheless, if there should be any reasonable doubt on the sense and meaning of the whole, to have a greater effect attributed to them than to the printed words, inasmuch as the written words are the immediate language and terms selected by the parties themselves for the expression of their meaning and the printed words are a general formula adapted equally to their case and that of all other contracting parties on similar occasions and subjects".

Another parallel principle that is equally relevant is that where the contract

has several annexures/attachments, prepared at different points of time,

unless a contrary intention is apparent, the latter in point of time would

normally prevail over the earlier in point of time.

1 2

11. In this case, as noticed above, the contract consists of a type-written

contract agreement between appellant and second respondent (which does

not contain any terms and conditions, but which merely states that the

contract is for execution of the described work as per the accompanying

Articles of agreement, plan, specification and conditions of contract

approved by the Project Director (S.E.), National Highway (ADB), Circle

Adappally, Cochin) with several printed forms with cyclostyled additions as

annexures and hand written corrections. The printed form of Articles of

agreement has an attachment slip. The contract does not contain any hand

written terms in regard to arbitration. The contract has printed clauses

barring arbitration (clauses 24 and 24(a) of the Notice inviting Tenders for

Works and a preamble clause and clause 3 in the articles of agreement). A

cyclostyled slip signed by both parties containing the words "arbitration

clause as per Ministry of Surface Transport's letter No. RW/NH-

34041/3/94-DO-III dated 28.9.1994 will be applicable" is attached to the

printed articles of agreement. By applying the well settled principles relating

to construction of contract the following position will emerge: (i) the terms

of the articles of agreement will prevail over the terms of Notice inviting

Tenders for Works and (ii) the term contained in the cyclostyled attachment

to the printed form of articles of agreement will prevail over the terms of the

printed articles of agreement. Consequently, the contents of the attachment 1 3

slip to the printed form of Articles of Agreement providing for arbitration

will prevail over the bar on arbitration contained in the Notice inviting

Tenders for Works and the articles of agreement. As a result, it has to be

held that there is a provision for arbitration in regard to the disputes between

the respective appellant and the respondents.

12. In this case, the entire confusion arose on account of using outdated

printed forms and also adding deleting and modifying the terms and

conditions contained in several distinct documents which are made

annexures to the formal agreement. The contract terms and conditions will

have to be gathered from the Articles of Agreement, notice inviting tenders

for works, conditions of contract, Madras Detailed Standard Specifications,

Special Conditions and Additional Special Conditions. There are printed

forms, cyclostyled amendments and attachments and typed agreement. In

fact there is a typed `contract agreement' and printed `Articles of

Agreement' with blanks filled in hand. Standard forms which contain

provisions for several contingencies, most of which are inapplicable or

redundant were used, without making any effort to edit the various

documents and have a consolidated Agreement. For example, we fail to

understand why State of Kerala in 1999-2000 should use Madras Detailed

Standard Specification of 1930 vintage. Nor are we able to understand why 1 4

parties should execute a contract agreement and articles of agreement on the

same day. Be that as it may.

GENERAL OBSREVATIONS

13. The use of multi-layered agreements, with several printed annexures,

each with cyclostyled amendments, typed and hand written additions and

deletions lead to confusion, uncertainty, delays in execution and apart from

giving rise to avoidable disputes. Having a contract with different annexures

dealing with the same issues with various attachments, in construction

contracts (and some times insurance contracts) is a nightmare to anyone

wanting to understand, implement or enforce them. Complicating contracts

with several annexures and attachments with inconsistent, irrelevant,

superseded or redundant provisions results in creating a lush dispute

generating field. It helps greedy and unscrupulous contractors to make

bloated imaginary claims. It enables Rule-Minded or corrupt officers to play

havoc with honest and bonafide contractors. The best form of agreement is

where all the relevant clauses/terms are incorporated in a single

document with several sections dealing with different aspects/subjects,

avoiding any overlapping. The difficulty arises if the same subject is dealt

with in more than one section or in more than one document. Confusion and

difficulties also arise using certain forms with conditions which were 1 5

finalized and printed at an earlier point of time and using other sets of

conditions which are finalized and printed at different subsequent points of

time, without taking care to specify which of the earlier terms were deleted

or modified. For example in this case, we have the 1959 terms that is Madras

Detailed Standard Specifications forming part of the contract, and we have

the general conditions of the Kerala Government which were modified from

time to time in particular 1986 and we have the standard instructions of the

Ministry of Surface Transport of 1994 which were applicable to National

Highway Projects. The result is several years after completing of the work,

parties are still trying to find out what the agreed terms and conditions are

and whether there is a specified dispute resolution process by way of

arbitration. On account of such confusion, several efficient and honest

contractors stay away from participating in such tenders. The vagueness and

confusion give unwarranted discretion and freedom to officers, leading to

corruption and nepotism. Clear, simple and straight forward agreement is the

need of the hour. Tens of thousands of engineering contracts are being

entered all over the country everyday in regard to infrastructural works,

without the necessary clarity, leading to avoidable disputes and considerable

strain on the exchequer. With use of computers, with user friendly editing

procedures with cut and paste facilities, it is fervently hoped that contract

forms appropriate to the work would be prepared, to avoid redundancy, 1 6

confusion, vagueness and inconsistency and to increase efficiency,

expedition, reduction of disputes and saving of funds. Be that as it may.

CONCLUSION

14. Where a contract consisted of standard terms finalized in 1959 and

further terms which were finalized subsequently, necessarily the terms that

were finalized subsequent to 1959 terms, would prevail. That is why if it is a

PWD contract, even though the MDSS which is made a part of the contract,

specifically provided for arbitration in clause 73, the same is held to be

inapplicable, having regard to the subsequent additions incorporated by the

Government of Kerala in 1986 and 1988 barring arbitration. Where the said

form of PWD barring arbitration is used in respect of National Highways

Contracts, which has a policy of having arbitrations to settle disputes, a slip

signed by both the parties is attached to the standard form of agreement

stipulating that the arbitration clause will be applicable. It is clear that the

said slip will prevail over the printed conditions that there can be no

arbitration. We therefore conclude that there is an arbitration agreement

between the parties in terms of the standard arbitration clause prescribed by

the Ministry of Surface Transport, Government of India. 1 7

15. We find from the record that the respondents, apart from contending

that there was no arbitration agreement at all, had also contended that the

appellants had given full and final settlement receipt with a no claim

undertaking in regard to the respective contract and therefore no dispute

much less arbitral disputes can exist. On the other hand, appellants had

contended that such certificates have been obtained by coercion and

pressure. Whether no claim certificate were obtained by coercion or by

applying pressure is a question of fact that will have to be considered in the

proceedings under Section 11 of the Act. The High Court while deciding the

petitions under Section 11, considered only the question whether there is an

arbitration agreement or not. As it held that there was no arbitration

agreement, it did not examine the further objection of the respondents that

there was a full and final settlement and consequently there is no arbitral

dispute. In the absence of any material on that issue, we are not in a position

to decide the same.

16. We therefore allow these appeals and set aside the order of the High

Court, holding that there is an arbitration agreement between the parties in

both appeals. We remand the matter to the High Court to consider and

decide the other objections raised by the respondents in accordance with

law.

1 8

..............................J. (R V Raveendran)

New Delhi; .............................J. July 7, 2009. (J M Panchal)

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free