LDA vs Gopal Das
- SCC(2019) 8 SCC 172
- Neutral2019 INSC 804
- AIRAIR 2019 SC 4317
- SCR[2019] 9 SCR 1133
Ratio decidendi
The rule this decision rests on
When land acquired under the Land Acquisition Act, 1894 is sought to be restored under Section 17 of the Uttar Pradesh Urban Planning and Development Act, 1973, development charges may be claimed by the development authority at the time of restoration if the land forms part of an area in which development has been carried out, even if the particular plot itself has not been planned or allotted, provided that the development in the broader acquired area constitutes the relevant context for assessing whether development has occurred. The authority's quantification of development charges cannot be imposed without giving the landowner an opportunity of hearing, and a demand for such charges raised without such opportunity must be set aside, leaving the authority free to recalculate and reissue the demand in accordance with law.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
LUCKNOW DEVELOPMENT AUTHORITY & ANR. .....APPELLANT(S)
VERSUS
GOPAL DAS (DECEASED) THROUGH LRs & ORS. .....RESPONDENT(S)
JUDGMENT
HEMANT GUPTA, J.
Leave granted.
2) The appellant-Lucknow Development Authority1 is aggrieved
against the judgment and order passed by the Division Bench of
Lucknow Bench of the Allahabad High Court on January 15, 2014
whereby the order dated July 29, 2011 passed by LDA was
quashed. The appellants were also made liable to pay costs of
Rs.1,00,000/- with the direction to recover the costs from the
authorities who have been instrumental in passing the impugned
order.
1 for short, ‘LDA’
Page 1 of 8
3) The facts leading to the present appeal are that LDA acquired total
land measuring 168.592 hectares (666 Bigha, 7 Biswa, 8 Biswansi,
8 Kachwansi) vide notification dated November 12, 1981 under
Section 4 of the Land Acquisition Act, 1894 for development of
Sitapur Road City Extension Scheme for residential purposes.
Notification under Section 6 read with Section 17 was issued on
December 3, 1981 and the award was published on January 15,
1986.
4) The land of the respondents measuring 1.200 hectares forming
part of land acquired was sought to be released from acquisition
from the State Government under Section 17 of the Uttar Pradesh
Urban Planning and Development Act, 19732. The land was
released from acquisition on May 23, 2011 whereby an order of
restoration of land in question of Khasra Nos. 416 and 417 was
passed in favour of the respondents along with an order of
payment of development fee in terms of Section 17 of the Act.
The respondents were directed to deposit an amount of
Rs.1,57,22,056/- within one week being Rs.1,38,780/- as the cost
of acquisition and Rs.1,55,83,276/- as the amount of development
fee vide separate letter dated July 29, 2011. It is the said order
which has been set aside by the High Court vide order impugned in
the present appeal. The High Court held as under:
2 for short, ‘Act’
Page 2 of 8 “33. In view of the aforesaid interpretation of word, "development", it shall be obligatory on the part of the development authorities like LDA in the present case, to make some development in accordance to statutory mandate over the land and its vicinity to make it entitle to impose development charges in terms of proviso of sub-
section (1) of Section 17 of the Act. Further, the development charges co-relate with the expenditure incurred with regard to development activities. The development activities should be in the vicinity where citizens' plots, flats or houses exist. In the present case, from the lay out plan and material on record, it appears that no development activities have been done towards west side of the railway line. Whatever development has been done, it seems to have been done in the Sector-A of the Scheme towards eastern side of railway line. Neither any material has been brought on record nor there is any pleading on record that electricity, sewer line, road constructed by the LDA is utilized by the petitioner. There is no material on record which may prove that electricity connection has also been provided to the petitioner's premises from the infrastructure of the LDA. National Highway No.24 is the old road connecting Lucknow and Sitapur and it does not seem to be part of the development project of the LDA.
34. …Nothing has been brought on record to establish the expenditure incurred on development work done over the land in dispute or in its close vicinity in terms of Section 8 and 9 of the Act from which the petitioner may be benefited. In absence of any benefit provided to the petitioner by the development work done by the development authority or the Lucknow Development Authority as the case may be, the petitioner or a citizen may not be subjected to payment of development charges.”
5) Such development charges at the time of restoration are
contemplated in terms of proviso to Section 17(1) of the Act, which
reads as under:
“17. Compulsory acquisition of land.-(1) If in the opinion of the State Government, any land is required for the purpose of development, or for any
Page 3 of 8 other purpose, under this Act, the State Government may acquire such land under the Provisions of the Land Acquisition Act,1894:
Provided that any person, from whom any land is so acquired, may after the expiration of a period of five years room the date of such acquisition apply to the State Government for restoration of that land to him on the ground that the land has not been utilised within the period for the purpose, for which it was acquired and if the State Government is satisfied to that effect it shall order restoration of the land to him on re-payment of the charges which were incurred in connection with the acquisition together with interest at the rate of twelve per cent per annum and such development charges, if any, as may have been incurred after acquisition.
(2) Where any land has been acquired by the State Government, that Government may, after it has taken possession of the land transfer the land to the Authority or any local authority for the purpose for which the land has been acquired on payment by Authority or the local Authority of the compensation awarded under that Act and of the charges incurred by the Government in connection with the acquisition.”
6) Learned counsel for the appellants submits that the land in
question is 138575.25 sq. feet i.e. 12878.741 sq. meters and is
situated between railway line of Aishbagh-Mailani Section and
National Highway No. 24. Since the land in question is part of a
planned scheme of LDA, all necessary external infrastructural
developments like construction of road, electricity, water and sewer
lines have been made available in the area. It is also pointed out
that development under the Act means development of the entire
area as a whole and not only the land of the one or two
landowners. The land in question is part of Master Plan and the
Page 4 of 8 development of the area cannot be seen in piecemeal. In the
impugned order before the High Court, the competent authority
has recorded the following facts:
“11. …Under the scheme of Sitapur City Extension Scheme in question, the land admeasuring 168.529 hect. was acquired in the year 1981. This land is completely developed land and under this land approx.. 97.1% of the land is planned land. All the public facilities like Roads, Electricity, Water, Sewer etc. has been made available over this land by the authority. In between Railway Line and National Highways there is total 34-1-0-0 bigha land which is covered with road (National Highway), hence it comes within the category of developed land. Since before, the facilities of roads, electricity and water are available here. The total acquired land except 19-6-0-0 bigha has been allotted. However, the land in question is reserved for future development, and any decision in this regard are not available in the record. The land in question comes under the scheme of Sitapur City Extension Scheme. Any zonal Plan of land situated in between Railway Line and National Highway is not approved, but by clubbing this area, the “Road Network Plan” of complete scheme in which all the sectors have been shown is approved. The aforesaid plan exists at present and there are no necessity to renew the lay-out plan of Schemes of the Authority.
12. …In accordance to Report of the Authority, approx. 34 Bigha land between National Highway Lucknow Sitapur Road and Railway Line has been acquired which is an Pattinuma, and out of which 15 Bigha land has been allotted and approx. 19 Bigha land is remain as it is. The land of the petitioner Shri Gopal Das is included in this 19 Bigha land and out of this aforesaid 19 Bigha land, over the land of 12 Bigha there are personal buildings etc. are existed being the encroachment. In this way when the land of the petitioner has not been planned and has not been allotted and in part of the land his paint business is running, then it does not reveal justified in any manner that the land has been used by the Lucknow Development Authority. Because the land in question of petitioner has been acquired by the Lucknow Development Authority for the use of residential provisions, but the same has not been used for the said provisions. Therefore on the basis
Page 5 of 8 of all the aforesaid facts and circumstances, the balance of convenience is revealed in favour of the petitioner.
Therefore, in such circumstances, the transfer of land in question is to be considered in favour of petitioner under Section 17 of the Uttar Pradesh Urban Planning and Development Act, 1973.”
7) The learned counsel for the appellants submits that the land in
question is situated between railway line and National Highway,
which is measuring 34 Bighas, out of which 15 Bighas has been
allotted and remaining 19 Bighas of land including 12 Bighas of the
respondents has not been allotted. It is the said averment made in
Para 15 which was taken into consideration by the High Court and
returned a finding that the development charges could not be
claimed as there is no development work on the land of the
respondents. It is the said finding which is sought to be supported
by Mr. V.K. Garg, learned senior counsel appearing for the
respondents.
8) Learned counsel for the respondents pointed out that in respect of
some other land, part of the same acquisition has been released in
terms of Section 24 of the Fair Compensation and Transparency in
Land Acquisition, Rehabilitation and Resettlement Act, 2013.
Therefore, the respondents cannot be treated in a discriminatory
manner.
9) We do not find that the findings recorded by the High Court are
sustainable in law. As per the averments made in the counter
Page 6 of 8 affidavit filed before the High Court and also in the impugned
order, it is stated that 97.1% of the total land acquired is planned
land. Small portion of 19 Bighas including the land of the
respondents has not been planned for the reason that there were
buildings on such area. Therefore, when the appellants state that
the land of the respondents has not been planned or allotted is in
the context that the area has not been plotted. It does not mean
that the appellants have not carried out any development on the
land in question. It is not some part of the land acquired is
required to be taken into consideration, to find out as to whether
any development has been carried out in the land acquired. The
findings of the High Court that the land in question or the vicinity
has not been developed is not the correct reading of the impugned
order passed as it has been clearly stated that 97.1% of the land
acquired has been developed. The development is to be examined
in respect of the land acquired. It is categorical stand of the
appellants that they have constructed road, provided electricity,
water and laid sewer lines and, therefore, the respondents cannot
avoid payment of development charges while seeking restoration
of land in terms of Section 17 of the Act.
10) In view thereof, we find that the judgment passed by the High
Court setting aside the claim of development charges is not
sustainable. Consequently, the appeal is allowed and the said
finding is set aside.
Page 7 of 8
11) We find that the order quantifying the development charges of
Rs.1,57,22,056/- was raised without giving any opportunity of
hearing to the respondents. Consequently, the demand
letter/order dated July 29, 2011 is set aside with liberty to the
appellants to communicate the amount incurred on acquisition and
development charges in accordance with law. It shall be open to
the respondents to seek remedy, if any, under the Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 in accordance with law.
.............................................J. (L. NAGESWARA RAO)
.............................................J. (HEMANT GUPTA)
NEW DELHI;
JULY 24, 2019.
Page 8 of 8
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free