Miss Lucy
← All judgments

Kailash Nath & Associates vs New Delhi Municipal Committee

Delhi High Court19 April 2002Dalveer Bhandari · Vikramajit Sen

Ratio decidendi

The rule this decision rests on

1. Where a contractor fails to lodge a contemporaneous protest or caveat at the time an extension of completion is granted, reserving the right to claim damages for delay, the contractor cannot subsequently claim damages on account of that delay, even if the delay is partly attributable to the employer's breach; this principle applies by operation of Section 55 of the Contract Act, which requires that notice of intention to claim compensation must be given at the time of acceptance of delayed performance. 2. An unconditional grant of extension of time for a construction contract constitutes a novation of the contract by mutual consent under Sections 62 and 63 of the Contract Act; where parties mutually agree to enlarge the time for completion without express reservations regarding liability for damages, neither party is entitled to claim damages on account of delay occurring up to that point, as the original stipulated date is substituted by the extended date without liability. 3. In standard form contracts containing exclusion clauses, the principle of contra preferentem requires that such clauses be strictly construed against the party responsible for drafting them; an exclusion clause dealing with increase in prices of materials and wages cannot be stretched to exhaust all claims arising from delay unless the language is explicit and unambiguous to that effect. 4. Where a contractor raises a fresh claim in a second arbitration that is substantially identical in nature and subject matter to a claim that was expressly declined to be referred in an earlier arbitration, the principle of res judicata bars consideration of such claim in the second arbitration if the earlier refusal was not assailed by the contractor at that time. 5. An arbitrator possesses the discretion to decline to award damages where the claimant has failed to prove damages; such findings of fact by an arbitrator will not be disturbed by courts, particularly where the arbitrator possesses specialized knowledge and experience relevant to the subject matter in dispute, and courts should be slow to interfere with awards made by skilled persons selected by the parties themselves. 6. Where a contractor has obtained a substantial settlement sum in a second arbitration without explicitly reserving rights in relation to claims decided in a first arbitration, and has received payment of that settlement without disclosure of the pendency of the first arbitration appeal, the conduct indicates waiver or abandonment of the first claim and constitutes evidence against the credibility of the contractor's assertion that the two claims are wholly distinct.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

JUDGMENT
Vikramajit Sen, J.
1. This Appeal is directed against the Judgment ofthe Learned Single Judge dated 26.2.1996 who hasdismissed the Objections filed by the appellantContractor and has made the Award passed by Shri P. P.Dharwadkar rule of the Court. Since Objections to anAward essentially partake of the nature of an appealagainst the Award, proceedings before us partake of thecharacter of a Second Appeal, necessitating theexistence of issues of significant importance forjustifying further consideration. When it is furtherkept in mind that even the proceedings before the SingleJudge are akin to revisory and not appellatejurisdiction, it will become palpably obvious that thescope of interference by the Division Bench is minimal.A miscarriage of justice of some moment should haveoccurred; in our opinion in the present case it hasnot. It will be relevant to mention that ShriDharwadker retired as the CMD of NBCC and possessed vastexperience specifically relating to the disputes uponwhich he was called to arbitrate. He had been appointedby the Administrator of the NDMC by virtue of the powersconferred on the latter by virtue of Clause 25 of theAgreement No. EE/C-II/AB/15/90-91 which was for anestimated amount of Rs. 2,77,53,295/- for the work ofconstruction of Sub District Cum Community Centre, DIZArea, Phase-I, Gole Market , New Delhi.
2. This Reference of the present disputes had beeninitiated because of the Contractor's letter dated20.11.1992, which contained the following List of Claims:
"Claim No. 1 The claimant claimsenhancement of rates over theiragreement rates @ 33.50% on all worksto be executed beyond stipulated dateof completion.
Claim No.2 The claimant claims24% interest on all the amounts fromdue dates.
Claim No. 3 The claimant claimsloss of business and damages sufferedduring stipulated period due to nonhanding of full site. =Rs. 25 lacs
Claim No. 4 The claimant claimsthe cost of arbitration proceeding =Rs. 40,000/-"
All these disputes except for Claim No.3 were referredfor Arbitration. It is not in dispute that theContractor did not take any action on theAdministrator's refusal to refer Claim No.3. This isof some significance.
3. After the completion of the work and thepreparation of the Final Bill circa 1996, furtherdisputes were raised by the Contractor. The NDMCadopted the position that since these later claims wereraised by the Petitioner after the acceptance of thepayment under the Final Bill, the same could not beentertained. Another objection was that these laterClaims had not been included in the earlier Referenceand were therefore barred under Order II Rule 2 of theCPC. In these circumstances, the Contractor hadapproached this Court under Section 8 and 20 of theArbitration Act, in Suit No. 1066-A/1996. Anil DevSingh, J. by Order dated January 21, 1997 referred thelater claims for arbitration leaving it to theArbitrator to decide these two questions also. TheChairperson of the NDMC, appointed Shri V. K. Sharma,Director, Central Electricity Authority, Seva Bhawan,New Delhi by Memo dated 4.4.1997. Shri Sharma publishedhis detailed and reasoned Award on 30th September, 1998.He rejected both the arguments taken by the NDMC beforeHon'ble A. D. Singh J. It appears that, subsequent tothe passing of the Second Award, the parties had enteredinto a settlement whereby the Contractor, in terms ofits letter dated 23.11.98, agreed to accept the paymentof Rs. 17 Lakhs in full and final settlement of theclaims adjudicated by Shri Sharma. [What impact, ifany, the second Award would have on the impugned Award(the first Award) will be discussed later in thisjudgment.] This letter is reproduced below in order tohighlight that the Contractor did not draw even thefaintest reference to the pendency of the presentproceedings, and did not also record that the settlementwas without prejudice to the claims under the firstAward. The present Appeal was filed in July 1996, wasadjourned on several dates of hearing, and was finallyargued by Mr. Lakhanpal as late as on 25.11.97, when itwas Admitted. As notice of the pendency of this Appealhas not been served on the NDMC/Respondent it would havebeen unaware of the filing of this Appeal. The positiontherefore was that at the time of the compromise theNDMC may have been labouring under the misconceptionthat the disputes covered by the First Award stoodfinally closed.
"Kailash Nath & Associates
WITHOUT PREJUDICE
November 23, 1998.
Ref. No. KNA/NDMC/98/2075
The Financial Advisor,
New Delhi Municipal Council,
Palika Kendra,
New Delhi - 110001.
Subject : Arbitration Award dated 30.9.98of Sole Arbitrator, Shri V. K.Sharma with respect toconstruction of Sub-District-Cum-Community Centre, Phase I,DiZ Area, Gole Market, NewDelhi - 110001.
Dear Sir,
This has reference to thenegotiations held in your office on23.11.1998 in concootion with the abovementioned Arbitration Award.
As stated during the saidnegotiations, we have had a longassociation with the NDMC, and sharedexcellent, cordial and harmoniousrelations. We had also brought to yourkind notice certain relevant points andalso submitted a brief note, during oursaid negotiations which, again, wereheld in a most cordial atmosphere andmutual understanding of each other.Keeping this spirit of cordiality, wehad agreed to accept the lumpsum amountof Rs. 17,00,000.00 (Rupees Seventeenlakhs only) from you in full and finalsettlement of the amount ofRs. 19,54,649.20 (Rupees nineteen lakhsfifty-four thousand six hundredforty-nine and nineteen paise twentyonly) awarded to us by the said SoleArbitrator Shri V. K. Sharma, subject toyour not challenging the award andfurther making payment to us of the saidamount by the date stipulated below;
all other terms and conditions of thesaid Award remaining unaltered. We had,further agreed not to claim any intereston the amount awarded beyond 23.11.1998,provided the amount along with interestis paid to us by the 18th December,1998. We confirm th,at on receipt ofthe said amount within the stipulatedperiod, as stated above, we shallneither be left with any claim againstthe aforesaid Award dated 30.09.1998,nor we shall make any fresh claim infuture against NDMC with respect to theaforesaid project, and this chaptershall be treated as closed and alldisputes relating to above standsettled.
You are, therefore, requested tokindly, arrange to get the paymentreleased to us urgently.
Thanking you,
Yours faithfully,
for Kailash Nath & Associates.
Sd/-
PARTNER
C.C. 1) Chief Engineer, C-1, NDMC,Palika Kendra, New Delhi forinformation please.
2) The Executive Engineer(Project)NDMC, Shaheed Bhagat Singh PlaceNew Delhi for information."
4. The contention of Mr. Lakhanpal learned Counselfor the Contractor is that there are variousconcomitants of a Tender of Rates, which would include,inter alia, (i) cost of material and labour, (ii)establishment costs, (iii) tools and plant (iv)electricity and water etc. Once it is established thatinordinate delay had occured and occasioned due todefaults ascribable to the NDMC, the Contractor's remedyfor claiming damages did not stand completelycircumscribed by Clause 10CC of the Agreement, sincethis Clause contemplates the grant of escalation only inrespect of material and labour. Accordingly expensesneedlessly incurred by the Contractor on establishment,tools and plant, electricity and water etc. do not fallwithin the sweep of Clause 10CC. The argument proceedsthat all the damages that are suffered by a party due tothe default of the other party must be compensated forunless mutually agreed otherwise. To the contrary, Mr.Shah, learned Counsel appearing for the NDMC has arguedthat Clause 10CC covers and exhausts the entire gamut ofcompensation payable to the Contractor.Compensation/damages not awardable under Clause 10CCcannot be granted by the Arbitrator; if he does so hewould be exceeding the jurisdiction vested in him, justas if he had travelled beyond the terms of the Referencemade to him. He has further submitted that since ClaimNo. 3, which was for 'loss of business and damagessuffered during stipulated period due to non handing offull site', having not been referred, this Claim cannotbe resurrected under any of the other Claims. It isstrenuously argued by Mr. Shah that after havingreceived a substantial payment of compensation under thesecond Award, the Contractor is attempting to transformhis claim of enhancement of rates into the claim fordamages which was specifically not referred forArbitration as far back as 17th December, 1992.
5. It is trite to state that every contract containsreciprocal promises or obligations, since without themthe essential 'consideration' would be found wanting.For example, in a simple contract for the purchase of achattel or an immovable property, the seller isobligated to transfer possession and title on receipt ofthe agreed price. Variations on the handing over ofpossession and title, and payment of the price may besimultaneous or staggered. In building contracts,multiplicity of reciprocal promises usually exist. Inits rudimentary aspect, the Builder/Contractorundertakes to complete the work according to time andspecification, and the owner correspondingly agrees tomake payments. However, usually there are many otherobligations, such supply of material and/or drawingsetc. to be performed at different stages of thecontract. A default in respect of any of them wouldresult in delay, giving rise to claims for damages. Letus consider a typical building contract where the workis to be completed within one year. The owner must makethe site available and on his failure to do so withinthe agreed time, it would be unfair to hold theContractor bound to his time of delivery. TheContractor may, however, estimate that despite the delayin handing over the site, he would nonetheless be ableto complete the project within the contracted time. Hemay succumb to the pressure of the likelihood of hissecurity deposit being forfeited; or the uncertaintyand delay in collecting damages. He may also not wantto lose the profits that he had calculated he would earnfrom the project. He would thus prefer take over thesite on the day on which it is offered to him by theowner rather than treat the contract as having beenbreached. In doing so without any recordedreservations, he would be precluded from claimingdamages at a later date. It is also conceivable thatimmediately prior to expiry of the said one year periodhe finds himself unable to complete the project. Inthese circumstances he would approach the owner,convince him that either the delay is a consequence ofthe owner's initial default in handing over the site orbecause of any reason for which neither party can befaulted. If the parties are both cordial andcommercially pragmatic, the owner would extend time.But on the completion of the project neither party wouldbe entitled to claim compensation for delay, if they hadnot made it categorically clear that the extension wouldbe subject to a claim for damages. This is for atleasttwo reasons, both of which are articulated in Section 55of the Contract Act, namely, acceptance of theperformance of obligations, and failure to give noticeof claim for compensation. Experience has shown thatadherence to time schedules in building contracts,whether time is of the essence or not, is the exceptionand not the norm. Disputes on this issue arecommonplace. It is unfortunate that despite acceptingand/or granting extensions without any reservations,parties nonetheless lodge claims for damages founded ondelay. Such claims are legally untenable on thestrength of Section 55 and other provisions of ChapterIV of the Contract Act, and on the grounds of estoppel.
6. A perusal of some of the Clauses of the Contract thatare relied upon by the parties, may now be consideredClause 2 of the General Conditions of Contract iscaptioned - 'compensation for delay'. It empowers theChief Engineer to quantify the amount of damagesleviable on the Contractor for every day that the workremains uncommenced or unfinished by the Contractorafter the proper dates up to a maximum of 10% of theestimated cost of work as shown in the Tender. ThisClause obviously has no application where delay iscaused because of failures on the part of the NDMC orthe Authority concerned. Thereafter, Clause 5 of theGeneral Conditions of Contract is captioned - 'Extensionof time'. It records that if the Contractor desires anextension of time for completion of the work on theground of his having been unavoidably hindered in itsexecution or on any other ground, he shall apply inwriting to the Engineer-in-Charge within thirty days ofthe date of hindrance on account of which he desiressuch extension. The concerned officer shall, if in hisopinion reasonable grounds be shown, authorise suchextension of time. Some points need to be immediatelyemphasised. Firstly, that the Contractor must apply inwriting for an extension of time specifying the reasonsfor the delay on the part of the NDMC. To this extentthe compact between the parties incorporates a departurefrom Section 63 of the Contract Act, which wouldotherwise have made parole evidence admissible on thequestion of the terms, if any, surrounding the grant ofextension of time. Secondly, it would also be expectedof the Contractor at this very stage of seeking anextension, to specify his claims, if any, on account ofthe delay which he attributes to the NDMC. Indubitably,Clause 5 protects the interests of the NDMC, as has beenopined by the Arbitrator also. If the Contractor failsto reserve his right to claim damages, once theextension is granted and acted upon, no claim fordamages would be tenable. Thirdly and for the samereasons, if the Authority grants an unconditionalextension, it would not be entitled to raise any demandsfor damages on account of delay up to this stage, on alater date. Fourthly, it is not logical to contend thatonce an unconditional extension is granted, it amountsto an admission that the Authority was responsible forthe delay. There is no barrier in the way of theAuthority to waive its claims for damages. ThesePrinciples should be strictly adhered to, also for thereason that they ensure that no frivolous or unfairclaims are raised later on. Parties must at all timesbe ad idem and therefore, the terms and conditions ofextensions to the period for the completion of theproject should be meticulously spelt out at the relevantand contemporary time. We are unable to accept theargument of Mr. Lakhanpal that Clause 5 deals only withthe extension of time and does not touch upon theadmissibility or quantum of damages as a consequence ofdelay. Clauses 2 and 5 complement each other, andshould be read conjointly.
7. Thereafter, Clause 10-C permits the Contractor toclaim payments where there has been an increase in theprice of materials to be supplied by him or increase inwages of labour. This is provided these have occurredas a consequence of any fresh statutory rule or order(but not due to any changes of sales tax), and secondly,the increase should exceed 10% of the price/wagesprevailing at the time of tendering. These provisionsapply mutates mutants in the event of a decrease in theprice/wages in excess of 10% of that prevailing at thetime of tendering. It is necessary to underscore thatthese claims can be made even during the duration of thecontract period of any extension thereto, unless thedelay in the execution of the contract is attributableto the Contractor. Clause 10C does not contemplate theclaim of imposition of damages of compensation. TheContractor is contractually bound to give notice of hisclaims under this Clause, within a reasonable time. Weconcur with the Arbitrator's view that this Clause alsoprotects the interests of the NDMC.
8. The next Clause is of paramount importance, andhas been relied upon by the NDMC. The relevant portionreads as follows:
"10CC If the prices of materials(not being materials supplied orservices rendered at fixed prices bythe department in accordance withclause 10 and 34 thereof) and/orwages of labour required forexecution of the work increase, thecontractor shall be compensated forsuch increase as per provisionsdetailed below and the amount of thecontractor shall accordingly bevaried, subject to the condition thatsuch compensation for escalation inprices shall be available only forthe work done during the stipulatedperiod of the contract including suchperiod, for which the contract isvalidly extended under the provisionsof Clause 5 of the contract withoutany action under Clause 2 and alsosubject to the condition that no suchcompensation shall be payable for awork for which the stipulated periodof completion is 6 months orless......."
As has been mentioned above, the contention on behalfof the NDMC is that Clause 10CC prohibits any claimsnot envisaged and allowable therein. However, thelanguage employed indicates that claims under thisClause would include not only these statutory increasesmentioned in the preceding Clause, but also all otherincreases. The words an "increase as a direct resultof the coming into force of any fresh law or statutoryrule or order" found in the immediately precedingclause, is conspicuous by its absence. Quiteobviously, claims predicated under the umbrella of'statutory increases' would be placed under 10C and notunder 10CC although they would be entertainable evenunder the latter clause because of its generality. Itis also noteworthy that Clause 10CC applies tocontracts stretching beyond six months. It isaxiomatic that the longer the duration of a contractthe greater is the possibility if not certainty ofescalations in prices. Whilst the Contractor may be ina position to anticipate or take into account anyincrease in prices in the short duration of six monthsinto the future, expectedly he would not be able toforesee escalations beyond that period and take theminto account with any precession. On a conjointreading of Clauses 10C and 10CC, while the statutoryincrease of price/wages can always be treated as havingbeen factored into the contract, other increases wouldbe claimable only if the contract period stretchesbeyond six months. On a reasonable understanding ofthese Clauses, they permit a claim on account ofstatutory increases/decreases at any time of theContract, and permit claims under all heads, if thecontract period spreads beyond six months. Nonstatutory claims are excluded where the contractduration is less than six months.
9. In the Special Conditions of Contract, Clause2A stipulates that in the interpretation of theagreement the order of descending importance for anyambiguity or discrepancy shall be as follows:
i) Schedule of quantities.
ii) Special conditions andadditional specifications ofcontracts and drawings.
iii) CPWD specifications ofwork and materials with up to datecorrection slips.
iv) General conditions andspecifications.
v) ISI codes.
10. The intention behind this Clause is to givepre-eminence to the Special Conditions of Contractviz-a-viz the General Conditions and Specifications.The first Clause of the Special Conditions of Contractcontains an exclusion Clause, and also incorporatesforce majeure. It reads as under :-
1(a) The contractor must getacquainted with the proposed site for theworks and study specifications andconditions carefully before tendering.The work shall be executed as perprogramme approved by theArchitect/Engineer-in-charge. If part ofthe site is not available for any reasonor there is some unavoidable delay insupply of materials stipulated byDepartment the programme of constructionshall be modified accordingly and thecontractor shall have no claim for anyextras or compensation on this account.
We shall now apply all these terms of theengagement between the parties to the facts of the case.In order to appreciate the argument of counsel for theparties, it would be convenient and proper to reproducethe Award in its entirety.
"Mr. B. M. Lal Mr. O. P. Tripathi,Project Manager Executive Engineer
Kailash Nath & Associates (Projects),1006, Kanchanjunga, N. D. M. C18, Barakhamba Road, Palika KendraNew Del,hi - 110001. (16th Floor),Sansad Marg,New Delhi - 110001.
(Claimants) (Respondents)
Sub: In the matter of arbitrationbetween M/s. Kailash Nath & Associates, NewDelhi (KNA) and New Delhi Municipal Corporation,New Delhi (NDMC) for the work of construction ofSub-District-cum-Community Centre in D. I. Z.Area, Gole Market Phase II - Agreement No.EE/C-II/AB/15/90-91.
*****************
Whereas I, P. P. Dharwadkar, retiredC. M. D. of N. B. C. C., H-501, Palam Vihar, Dist.Gurgaon, Haryana -122001, was appointed as SoleArbitrator by Mr. Ramesh Chandra,Administrator, NDMC, by virtue of powersconferred on him under Clause 25 of the abovereferred Agreement, vide his letter dated 17thDecember, 1992, to decide and make my reasonedAward regarding three claims/disputes of theClaimants KNA and counter-claims of RespondentsNDMC which were to follow in due course, subjectto certain conditions therein, and which wasaccepted by me vide my letter dated 21.12.1992;and Whereas I entered into reference videmy letter dated 8.1.93 and the time for makingand publishing the Award was extended from timeto time up to 7-11-93 with the consent of theparties.
And Whereas the parties submittedrespective claims and counter-claims andproduced cases, through theirexecutives/counsel/law officer in 11 hearingsheld till 18.8.93, when they completed theirrespective submissions in the case, and agreedthat they have been given adequate time forarguments and were afforded full opportunity torepresent their respective cases before theArbitrator, and stated that they have nothingfurther to add/adduce in evidence, etc. beforethe Arbitrator and requested the Arbitrator tomake and publish his Award.
And Whereas the parties further submittedsummaries of arguments in writing from theirside - the Claimants vide their letter dated9.9.93 and the Respondents vide their letterdated 22.9.93;
Now I, P. P. Dharwadker, Sole Arbitratorin the case, after having ,gone through all therelevant papers submitted to me, variousstatements and counter-statements of facts made,rejoinder and other documents as filed by theparties, pleadings of the parties, their otherdocumentary/oral evidence, precedents in theCourt cases, etc. as submitted, theirwritten/oral arguments as advanced in varioushearings and having studied all the papers anddocuments submitted to me by both the sides inconnection with their claims/counter claims,give my Award with reasoning as follows:
As per the contract agreement, the dateof the start of the work was 10th January 1991and was to completed within 21 months, i.e. by9th October 1992, but the work could not proceedsmoothly right from the beginning and theClaimants could establish that the site for thevarious blocks was handed over in piecemeal fromJanuary '91 to September '92 only a month beforethe actual scheduled date of completion of workwhich did come, at least in part in the way ofsmooth execution of work contracted. It hasalso evident that there was contributory delayon account of delay in supply of architectural/structural drawings, non-availability ofadequate quantity of steel reinforcement anddelay in fixing electrical conduits by a thirdagency, which in turn also contributed tofurther inevitable delay in the execution of thework by the Claimants.
The Respondents NDMC did not agree thatthe delay was entirely, due to non-fulfillment ofobligations from their side, though there wereminor hindrances which, according to them, wereinconsequential, but it was mainly due to slowprogress of work by the Claimants, which theycould establish in part. Though they went sofar as not even to take responsibility fordelayed supply of drawings by the Architectswhich is a 'third party' , the Architects couldnot be made a party to this dispute, as theagreement is bi-partite between the Claimantsand the Respondents only and the Respondentsmust share the blame for inadequate coordinationfrom their side on this account. There was,however, no worthwhile plan of action by theRespondents which they could enforce on theClaimants because of inadequacies from their ownside.
The Claimants were asked to give detailedjustification for the basis of enhancement of33.5% above the agreement rates as claimed bythem for the works executed beyond theoriginally contracted period, based on actualrate analysis, etc. of the items of work in thecontract agreement for which enhancement hasbeen sought. However, they have not done so andhave tried to justify the enhancement based onincrease in cost index over the 21 months periodfor other jobs allotted by NDMC. This may notstrictly hold good in this case as the nature ofthe work could make a difference in actualenhancement of the rates of individual items andthe total quantities of work as submitted by theClaimants are also disputed by the Respondents.
On the other hand the Respondents couldnot sustain that no loss has been suffered bythe Claimants due to established hindranceswhich impeded the progress of work atleast inpart, and the Claimants were entitled under thenormal rules of business for enhancement ofrates in the escalating economy, for no fault oftheirs.
Notwithstanding the above, theRespondents had raised preliminary objectionswith regard to avoidability of contract andwhether time is essence of the contract, and thejurisdiction of the Arbitrator, as alsomaintainability of the claim petition. TheArbitrator having been appointed by thecompetent authority as per the contractagreement to specifically settle the disputearisen on the three claims made by theClaimants, subject to the admissibility underclause 25 of the said agreement, has to make hisAward on the merits of the case and the contractagreement entered into between the parties.Though the contract work of the type shouldnormally be based on mutual obligations andresponsibilities and though the Claimant hadgiven due notice and after the stipulated dateof completion, they had reserved the right forclaiming enhancement, they had failed to get anywritten commitment before proceeding with thework from the side of the Respondents, whopreferred the dispute to be settled by theArbitrator appointed by them, in terms of theContract Agreement.
The Court cases cited by both the sideshave been considered to the extent they arerelevant to the case. In this case, though itcould be established by the Claimants thatatleast part of the delay was attributable tothe Respondents, it could not also be ruled outthat part of the delay is attributable to theClaimants themselves. I, therefore, in theabsence of information on the exact contributionby the two sides, hold them both equallyresponsible for the delay and the consequentaward/damages. However, as the contractagreement protects the interest of theRespondents (Clauses 2,5,10-CC & SpecialCondition 1(A) refers), the enhancement claimedby the Claimants is not maintainable (both mainclaim and interest thereon).
As regards the counter-claims made byRespondents NDMC, the same have proved to behypothetical and could not be sustained by themin terms of the agreement or based on facts.
Taking all factors into account, I givemy Award as follows:

AWARD S. No. Description of Claim Claim Award Remarks Amount ...........................................................

Claims by the Claimants(KNA) Claim

1. on account of enhanced rates over the agreement rates @ 33.5% on all works to be executed beyond stipulated date of completion. N.A. Nil Please see the reasoning.

2. Claim for 24% interest on all due amounts from due dates. N.A. Nil

3. Cost of arbitration proceedings. 40,000 Nil

------ ---

Total N.A. Nil ------ ---

Note: Each party will bear its own cost on this arbitration.

Counter-Claims by Respondents (NDMC)

1. Loss by way of rent. 32,70,379 Nil

--------- ---

Total. 32,70,379 Sd/- P. P. Dharwadker Sole Arbitrator"

11. Predicated on the Award itself, Mr Lakhanpal has submitted that once the Arbitrator had arrived at the conclusion that there was no worthwhile plan of action by the NDMC which could be implemented by the Contractor, the inevitable consequence that would ensue is that the latter should have been found to be entitled for compensation for the delay. What must be kept in mind is that penalty clauses are not legally enforceable in India and damages must be proved. If damages have been liquidated or preassessed in the contract itself, so long as they are realistically close to actual damages sustained, they can be given effect to. In India liquidated damages are indicative of the maximum damages awardable. In the present case the Arbitrator was not satisfied that this exercise had been completed by either of the parties. Therefore, regardless of whether Clauses 10C or 10CC or 1(a) of the Special Conditions of Contract envisage the damages claimed by the Contractor, they have been rejected by the Arbitrator as having not been proved. These are findings of fact which the Court would not interfere with. We feel that the Arbitrator has the experience and knowledge to record a finding on this complex issue, requiring not only engineering knowhow but also familiarity with prevailing prices. The Court would be ill-equipped and therefore sanguine to enter upon such technical issues; consequently jural interference is to be depricated. The following observation in Mediterraneam & Eastern Export Co. Ltd. v. Fortress Fabrics Limited (1948) 2 ALL ER 186 tested and followed for over fifty years immediately come to mind :-

"A man in the trade who is selected for his experience would be likely to know and indeed to be expected to know the fluctuations of the market and would have plenty of means of informing himself or refreshing his memory on any point on which he might find it necessary so to do. In this case according to the affidavit of sellers they did take the point before the Arbitrator that the Southern African market has slumped. Whether the buyers contested that statement does not appear but an experienced Arbitrator would know or have the means of knowing whether that was so or not and to what extent and I see no reason why in principle he should be required to have evidence on this point any more than on any other question relating to a particular trade. It must be taken I think that in fixing the amount that he has, he has acted on his own knowledge and experience. The day has long gone by when the Courts looked with jealousy on the jurisdiction of the Arbitrators. The modern tendency is in my opinion more especially in commercial arbitrations, to endeavor to uphold awards of the skilled persons that the parties themselves have selected to decide the questions at issue between them. If an arbitrator has acted within the terms of his submission and has not violated any rules of what is so often called natural justice the Courts should be slow indeed to set aside his award."

12. Apart from this ground, by the application of Section 55 of the Contract Act and Clause 5 of the General Conditions of Contract the claim for damages cannot be entertained also for the reason that the parties ought to have put each other to caution/notice that the contract would be performed subject to claims for damages. The stipulated date of completion of the project was 9-10-1992. The contract envisaged the construction of three blocks but the possession of the site was given in piecemeal from January 1991 till as late as September 1992. Obviously, the construction could not possibly have been completed within one month atleast in respect of one block. The Contractor should have, but did not, lodge a caveat or protest that the contract would be continued with subject to his claim for damages. The NDMC should have similarly recorded that whilst agreeing to grant an extension of time, it had reserved its rights to claim damages for delay which in its opinion was attributable to the Contractor. Notification of claims contemporaneously is salutary for very practical reasons, foremost amongst which is the certainty that at that point of time the parties would have come to an understanding on all controversial issues. Commercial pragmatism would prevail upon either side to adopt a realistic stance. Section 55 of the Contract Act, 1872 incorporates that "if, in case of a contract avoidable on account of the promisor's failure to perform his promise at the time agreed, the promisee accepts performance of such promise at any time other than agreed, the promisecannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of acceptance, he gives notice to the promisor of his intention to do so." Moreover, extension of time for completion of a project is essentially a novation in the contract, and by application of Section 62 and 63 of the Contract Act, relieves the opposite party from performing the obligations pertaining to time as contained in the original contract. Where the extension of time is unconditional, the original date is substituted by the extended date sans any liability.

13. The decision of the Privy Council in Muhammad Habidullah v. Bird and Company, AIR 1922 Privy Council 178, is topically illustrative. The parties had entered into a contract for the supply of 4000 sleepers of a special pattern at any station on the Bengal-Nagpur Railway by May 31, 1913. Only 1746 sleepers were delivered and passed inspection. The time for delivery was extended, but no more deliveries were made. The supplier raised on action for (1) the return of deposit and (2) damages in respect of his profit on the balance of sleepers not supplied. The Respondents counterclaimed for damages in respect of sleepers not delivered. Sections 55 and 63 of the Contract Act were considered and applied by the Privy Council. It opined that the promisewas not entitled to claim damages for non-performance at the original agreed time, but was not precluded from claiming damages for non-performance at the extended time. The Court further held that the effect of Section 55 is, "where the party having the option elects not to avoid, to put agreement after the original date on the same footing as an agreement just before the original date." A somewhat similar question arose in Chalisgaon Shri Laxmi Narayan Mills Co. Ltd. v. Amritlal Kalidas Kanji, , in which Section 55 of the Contract Act was applied. The following passage is self instructive:

"19... As the contract between the parties was for sale of goods, the time for delivery must be held to be essenceof the contract. The time for delivery in this case expired on July 31, 1951. The plaintiff accordingly was entitled to avoid the contract altogether and not accept delivery at any time subsequently in the correspondence the plaintiff stated that he would charge t he defendants the expenses incurred towards export duty as also damages that would ensue if late delivery was effected. The defendants refused to give delivery to the Plaintiff if he insisted upon the above conditions. In fact the export duty was imposed in April 1951. Even so and in spite of the defendants having informed the plaintiff that the defendants would not pay any amount of the export duty, the time for performance was by consent of parties extended to July 31, 1951. By agreeing to the above extension, the plaintiff, must be held to have given up and waived any right to payment of the export duty as damages. Upon extension of the due date to July 31, 1951, the parties proceeded on the footing that for all purposes the plaintiff would have to pay and bear the export duty for himself. The plaintiff cannot, therefore, be entitled to recovery the sum of Rs. 10,649-4-0 which he expended in connection with the export duty for consignment of the 49,693 yards that were delivered to the plaintiff in July 1952."

14. Ordinarily, the Court should assume that the correspondence between the parties has been perused by the Arbitrator. Letters emanating from the Respondents such as those dated 23.4.99, 6.5.1991, 10.3.1991, 19.6.1991, 14.6.1991 etc. are indicative of the position that the NDMC had partially performed its obligations and that some delay was also attributable to the Contractor. On 9.10.1992, i.e. the stipulated date of completion, the NDMC had the necessary cause of action to make a claim for damages on account of alleged delay by the Contractor. In permitting an extension of time it must be held to have waived its right to make any claim, since notice as contemplated by Section 55, had not been given. Conversely, the contractor also had the necessary cause of action to claim damages if the delay cold rightly be placed at the door of the NDMC. A notional breach of contract had therefore occurred. However, both the parties had unconditionally agreed to continue to perform their respective obligations. On the Contractor's part, this was to complete the project on the terms contained in the principal document. On the part of the NDMC, it was to make the payments as envisaged in this document. Having solicited and invited each other to perform their respective contractual obligations, even under the principle of estoppel, (which have in essence been articulated in Chapter IV of the Contract Act), the respective performances had been accepted. Section 62 of the Contract Act enunciates that "if the parties to a contract agree to substitute a new contract need not be performed." In the present scenario, the parties had agreed to set time at large by altering or rescinding the initially stipulated date of completion of 9.10.1992. Since this must be held, in the circumstances of the case, to have been by mutual consent, a new contract had come into effect making the original contract redundant in respect of the stipulated date of completion. Section 63 of the Contract Act states "that every promisemay dispense with or remit, wholly or in part, the performance of the promise made to him, or may extended the time for such performance, or may accept instead of it any satisfaction which he thinks fit." On a combined reading of these Sections, owing to the absence of any contemporaneous writing or evidence neither party would be entitled to claim damages on account of delay. In order to elucidate that this was the situation prevailing at the relevant time, reference to paragraph 4 of the Appeal would be of relevance. In this paragraph the Contractor has stated that the "work got spilled over the stipulated contract period and the appellants/claimants were made to incur additional expense on account of abnormal rise in price with reference to the quantum of work executed between the period 9/10/1992 till actual completion. Besides this, the appellants were subjected to additional expense on account of establishment during the prolonged period of execution of work beyond the stipulated contract period. The Appellants claimed the said additional expense by way of compensation which the Respondents did not agree to pay. Accordingly the disputes arose and the reference was made to the Arbitrator in terms of arbitration agreement." However, as has been discussed above, no claim was lodged by either party at the crucial and critical time, i.e. on 9.10.1992 when parties mutually agreed to enlarge the time for completion of the project. Therefore, the Arbitrator was justified in rejection the claims of both the parties.

15. Considerable argument has been generated before us on the interesting question of whether the sundry clauses of the Contract between the parties excluded the claim of Rs. 25 lakhs on account of loss of business and damages allegedly suffered by the Contractor for work executed during and beyond the stipulated date of completion. The stand of the NDMC is that such a claim is barred by the terms of the Contract. Reliance had been placed by Mr. Shah on the decision of a Division Bench of this Court in Delhi Development Authority v. U. Kashyap, 1999 (1) Arb. LR 88. In that case the net value of work done after the stipulated date of completion, after deducting the cost of materials supplied by the DDA, was Rs. 52,86,520/-. It was alleged that an effective increase of 18.3% over cost of construction during the stipulated period of completion had occurred. The Claimant claimed compensation of Rs. 4,82,010, after adjusting the amount allowed to him under Clause 10CC from the total damages computed as Rs. 9,67,433/-. The Award for the said sum of Rs. 4,82,010 was set aside. The Bench had considered the previous decisions of this Court in M/s. Metro Electric Co. New Delhi v. DDA, , Rawla Construction Co. v. Union of India, 1982 RLR 20, Hyderabad Municipal Corporation v. M. Krishnaswami Mudaliar and Anr., , P.M. Puri v.

Union of India 1989 (2) Arb. LR 215, Uttam Singh Duggal and Co. v. Union of India, 1988 (2) Arb. LR 225, Villayati Ram Mittal v. Union of India 1986 (1) Arb. LR 328, Himachal Pradesh Nagar Vikas Pradhikaran v. Aggarwal and Co. 1997 (1) Arb. LR 275, Suresh Chander v. DDA. 1997 (1) Arb. LR 536 and also an unreported decision in M/s. Express Engineering & Construction Co. v. Delhi Development Authority, Suit No. 843/91, 2613/91, dated 4.10.1994. It was ultimately poignantly pointed out that "since Clause 10CC extracted above of the agreement provides for the escalation in the price of material and labour during the extended period of work as per the formula set out therein, none of the aforementioned decisions have any applicability." In Kashyap's case (supra) the Bench was primarily concerned with the propriety of the Arbitrator formulating his own formulae for computing damages, and not following the method and manner laid down in Clause 10CC. For this reason Kashyap's case (supra) is not an authority for the proposition that Clause 10CC covers each and every claim that may result from a delay in the completion of the project.

16. Kashyap's case (supra) came up for consideration by another Division Bench of this Court in Delhi Development Authority v. S.S. Jetley 2001 (1) Arb. LR 289 (Delhi) in which the Bench observed that "the respondent had preferred separate claim namely, Claim No. 19 under Clause 10CC of the agreement and there is no dispute that the said claim was entertained and adjudicated upon, keeping in view the provisions of Clause 10CC of the agreement between the parties. The Claim No. 17 is in fact founded on different premise altogether. It was the case of the respondent that because of prolongation of the Contract due to the fault on the part of the appellant, the respondent was made to incur the expenditure on idle labour, staff, machinery centring, shuttering and other ancillary requirements like electricity, water, petroleum, etc. It was the case of the respondent that it was necessary for the respondent to keep regular establishment including graduate engineer at site till the work is completed as required under Clause 36 of the agreement. The Arbitrator found that the respondent had in fact incurred expenditure on the aforesaid grounds and awarded the claim @ 5,000 per month for the period of delay which was 44 months and on this basis a sum of Rs. 2,20,000 was awarded. It was clear, therefore, that Claim No. 17 was for damages on account of prolongation of Contract inasmuch as respondent was made to incur unnecessary expenditure due to the fault of the appellant in prolonging the contract. This claim is, therefore, maintainable as per Sections 73 and 74 of the Contract Act which gave entitlement to the respondent to claim damages/loss suffered due to breach of contract by the appellant. The award of Claim No. 17 was, therefore, justified and we see no merit in the aforesaid contention raised by the appellant." We are in respectful agreement with the views of the Division Bench in Both Kashyap's case as well as Jetley's case (supra).

17. It is now firmly entrenched in arbitral jurisprudence that standard form agreement, and in particular exclusion clauses contained therein, must be strictly construed against the party responsible for its drafting. This is the principle of contra preferentem, and has been given statutory recognition by the Unfair Contract Terms Act 1977 in the U.K. In Schroeder Publishing Co. Ltd. v. Macauly (1974) 1 W.L.R. 1308 it has been opined thus - "The terms of this kind of standard form contract have not been the subject of negotiation between the parties to it, or approved by any organisation representing the interests of the weaker party. They have been dictated by that party whose bargaining power, either exercised alone or in conjunction with others providing similar goods or services, enables him to say: 'If you want these goods or services at all, these are the only terms on which they are obtainable. Take it or leave it.' To be in a position to adopt this attitude towards a party desirous of entering into a contract to obtain goods or services provides a classic instance of superior bargaining power..... The fact that the appellants' bargaining power vis-a-vis the respondent was strong enough to enable them to adopt this take-it-or-leave-it attitude raises no presumption that they used it to drive an unconscionable bargain with him, but in the field of restraint of trade it calls for vigilance on the part of the court to see that they did not." If the intention of the NDMC was that no claim whatsoever could be allowed on account of the delay attributable to it, it should have clearly stated so. Clause 10CC only deals with the eventuality of increase of 'prices of materials and wages of labour'. It cannot be stretched to such an extremity as to exhaust all claims, irrespective whether they are confined to increase in prices of material or wages of labour, or beyond them. However, even this view does not advance the case of the Contractor before us, for the reason that there is a clear finding of fact by the Arbitrator that damages had not been proved. It is so also because notice for a claim for damages had not been reserved at the time when the completion period was agreed to be enlarged.

18. Before venturing to the next point, we would like to observe that foreign judgments and authorities cannot be extrapolated upon every case which falls to be decided in this country. Mr. Lakhanpal has relied on the following observation in Hudson's 492 9th Edition that -

"where the cause of delay is due to breach of contract by the employer, and there is also an applicable power to extend the time, the exercise of that power will not, in the absence of the clearest possible language, deprive the Contractor of his right to damages for his breach." Since this exposition of law runs counter to the provisions of the Section 55 of Indian Contract Act dealt with above, we are of the view that it is too widely stated for ubiquitous application.

19. Clause I of the Special Conditions of Contract came up for interpretation before a Single Bench in Shri Sunder Lal Khatri v. Delhi Development Authority, 1994 (2) Arb. LR 479. The learned Single Judge had found no impropriety with the grant of damages on account of overhead expenses incurred on establishment for the execution of the award during the prolonging period. The provisions of the Contract Act however, were not placed before the learned Single Judge.

20. The controversy cannot be allowed to rest only on the above discussion. Between the period March 1991 and the preparation of the Final Bill in March 1995 a total sum of Rs. 2,64,98,812/- was paid in the running account against the work done and the sum of Rs. 34,07,302.50 paise was paid under Clause 10CC. Not satisfied with these payments the Contractor had raised a demand for arbitration which was referred to Shri V.K. Sharma, as already detailed above. By this time the first Arbitration had come to its culmination in terms of the Award of Shri Dharwadker dated 5.11.1993 which had also been approved and the Learned Single Judge by his impugned judgment dated 25.2.1996. The Award passed by Shri Sharma compromised between the parties for the sum of Rs. 17 lakhs. Mr. Shah, learned Counsel for the respondent has contended that with this payment, all the Contractor's claims were extinguished/satisfied, including those which had been turned down by Shri Dharwadker in the first Award. Mr. Lakhanpal, however, contends that the two claims are totally distinct and for this reason, while offering the compromise for a settlement at Rs. 17 lakhs, no reference was made to the first Claim/Award. In order to ascertain whether there is any difference between the Claims in the two Arbitrations, it would be necessary to compare the wordings of Claim 19 in the second Reference with the first and third Claims raised in the Contractor's first demand for arbitration. It should also be recalled that the Administrator had declined to include Claim No. 3 in the Reference made to Shri Dharwadker. Claim No. 19, before Shri V.K. Sharma, reads as follows:

"Claim No. 19 On account of loss of profit.

The Claimants could state that the aforesaid work was awarded to them with stipulated date of commencement as 11/01/1991 and contract period being 21 months, the stipulated date of completion was 10/10/1992. The contract value for the work awarded was Rs. 2,77,53,295/-. The work was actually recorded to be completed on 30/10/1993. The execution of work was got delayed on account of miserable failures on the part of the respondents in fulfillling their obligations at the relevant time in such a manner so that claimants could execute the work smoothly and speedily so as to achieve completion within the stipulated contract period. The said failures on the part of the Respondents in not making available complete site free of hindrances, handing over the required design/drawings and releasing payments etc. at the relevant time is borne out from the documents placed on record.

0.2 Taking into consideration the contract value and the contract period, the quantum of work which was expected to be executed per month was Rs. 13,21,585/-. The claimants on its part on award of contract had made all the arrangements immediately so as to take up the execution of work in right earnest and proceed with the execution of the same smoothly, speedily with a view to complete the work within the stipulated contract period. The claimants on their part while tendering had taken into consideration the element of profit to be 10% of the value according to the norms prevailing in the trade. It is pertinent to put in on record that even the Respondents while preparing the estimate for the invitation of tenders had taken the element of contractors' profit to be 10%.

0.3. Since the execution of work got prolonged beyond the stipulated contract period because of respondents having committed breach of contract, the claimants were made to stay at site of work for a period of 12.53 months longer than the stipulated contract period.

For the prolonged period the claimants have been deprived of the expected profit they would have earned on execution of work. The respondents are liable to and the claimants are entitled to compensation towards deprivation of profit i.e. loss to which they have been subjected to during the period of prolonged stay at site. However, the respondents failed to appreciate the complete facts and circumstances in its true perspective which made them liable to compensate the claimants according to settled principles in the trade and that of law.

It is therefore, most respectfully prayed that considering the complete facts and circumstances in its true perspective, the learned Arbitrator be pleased to allow the amount found due and payable on the basis of settled principles as per details enclosed in annexure 'I'.

21. We are unable to find any distinguishing feature between the above claim and Claim No. 3 for a sum of Rs. 25,00,000/- which had not been referred for arbitration to Shri Dharwadker by the Administrator, NDMC. That Claim was in the following words - "the Claimant claims loss of business and damages suffered during stipulated period due to non-handing of full site." It is remarkable that although Claim No. 3 had not been referred to arbitration vide the letter dated 17th December, 1992 of the Administrator, NDMC, the same claim was subsequently referred to arbitration before Shri V.K. Sharma in 1998. We can only speculate that this was because of oversight. The principle of res judicata prohibits a fresh consideration of the same claim since the refusal to refer the aforementioned Claim No. 3 had not been assailed by the Contractor in 1992. The subject matter of the second arbitral Award has been settled between the parties at the lump-sum figure of Rs. 17 lakhs which is inclusive of Claim No. 19. Thus, large sum of Rs. 11,18,588/- was awarded against Claim No. 19 on account of loss of profit. Since the gravamen of the argument of Mr. Lakhanpal raised before us was that claims under Clause 10CC are necessarily restricted only to an increase in the price of material and wages, and not loss of profits, Claim No. 19 was essentially and intrinsically in the nature of loss of profits, which had not been referred for arbitration to the first Arbitrator, despite the Contractor's demand. It has not been argued before us that this Claim was subsequently referred due to a change the circumstances or in the thinking of the parties. Its adjudication before Shri Sharma, arguably, was legally impermissible.

22. Be that as it may, when Claim No. 1 before Shri Dharwadker is considered, it would clearly fall within the observations of the previous Division Benches in Kashyap's case as well as in Jetley's case (supra). What is sought to be claimed by the Contractor in Claim 1 before Shri Dharwadker is enhancement of rates at a percentage different to that as envisaged under Clause 10CC, it is clearly legally untenable. Mindful of this impediment in his path, the Claimant has now given the colour of damages to Claim No. 1 before Shir Dharwadker. We find merit in the submission of Mr. Shah that the effort of the Contractor is to change the nature of Claim No. 1 from an increase in percentage to a claim for damages. In either case, we find no error in the impugned Award and reject the appeal.

23. It has also been contended by Mr. Lakhanpal that the approach of Shri Dharwadker was legally faulty inasmuch as it has been observed by him in the impugned Award that there is no explanation of the material on the basis of which the Arbitrator has returned the finding that "it could not also be ruled out that part of the delay is attributable to the Claimants themselves. I, therefore, in the absence of information on the exact contribution by the two sides, hold them both equally responsible for the delay and the consequent award/damages." The Hon'ble Supreme Court has time and again observed that the Court is expected to adopt an approach which would affirm the legal propriety of an Award. Equally-well settled is the preposition that the Arbitrator, not having the benefit of legal training, is not expected to writ an Award with the meticulous detail and reasoning to which lawyers are accustomed. Semantic consideration must not thwart implementation of Awards. As we see it, after referring to the evidence placed before him both the adversaries the Arbitrator returned a finding of fact that neither side had proved the fault of the other or the extent of damages. The Award must not be read in a pedantic manner; if not so done the Arbitrator's conclusion cannot be faulted.

24. Mr. Lakhanpal has sought to press in his favor the decision in K.P. Poulose v. State of Kerala and Another, in support of his contention that the Arbitrator should have himself gathered evidence in connection with the Claim for damages. We are unable to read this decision as an authority for the extreme proposition put forward by Mr. Lakhanpal. Firstly, it cannot be understood how an arbitrator can possibly collect evidence which is non-existence. Secondly, the duty to prove the case cannot possibly rest on the Arbitrator but must lie on the parties themselves. In Poulose's case (supra) two very material documents, Ext. P-11 and P-16 were ignored by the Arbitrator. The counter argument was that these documents were not even marked before the Arbitrator; but that they were marked only before the Subordinate Judge. The Hon'ble Supreme Court was of the opinion, on being taken through Exts. P-11 and P-16 that they were the material documents to arrive at a just and fair decision to resolve the controversy between the department and the contractor. It, therefore, held that "in the background of the controversy in this case even if the department did not produce the documents before the Arbitrator it would be incumbent upon him to pursue the relevant documents including Ext.P-11 and P-16 for the purpose of justice." The Apex Court had restricted its observations to the facts of that case as is evident from the words emphasised above. Furthermore, both the documents were available on the arbitral record, and since they were relevant, ought not to have been ignored merely because they had not been formally exhibited. Strict and punctilious adherence to rules of evidence are not expected in arbitration proceedings. This is all that the Hon'ble Supreme Court was emphasising in Poulose's case (supra). It is too far fetched to cite this case as obligate the Arbitrator to gather evidence not placed before him, or beyond his ken.

25. We feel constrained to observe that the Contractor had failed to inform this Court about the receipt of the payment of Rs. 17 lakhs against the second Award. This has been brought to our notice by learned counsel for the Respondent. It is also significant that in arriving at the compromise of Rs. 17 lakhs the Contractor had sagaciously not made any reference or drawn attention to the first Award. This must have been deliberately done since otherwise the second Award may have also been assailed, for the reasons mentioned above, namely that they could not be adjudicated since they had already been declined to be preferred in 1992; and that Claim No. 1 would be barred by the operation of Clause 10CC. This case exemplifies the vulnerability of Governmental authorities in preparing a proper defense to claims levelled against them; or to allow inadmissible and legally untenable claims for reasons which every one suspects. This is a fit case, and we recommend so, for the Administrator to institute an inquiry to fix the responsibility of the negligence and inaptitudes of its officers in defending the NDMC. While the application of principle of res judicata may be of some legal intricacy calling for it to be overlooked, the failure of the officials of the NDMC to link the Dharwadkar Award with the subsequent Sharma Award, prima facie, indicates a drastic dereliction of duty. But for the diligence and the assiduous preparation of the case by Mr. Shah, learned Counsel for the Respondent, the overlapping of the claim of the first and second set of claims might may have gone unnoticed.

26. The appeal is dismissed with exemplary costs of Rs. 25,000/- payable by the appellant to the Prime Minister's Relief Fund. These costs have been imposed because of the male fide conduct of the Claimant not only before Shri V.K. Sharma, Arbitrator and the NDMC, but also before us inasmuch as it had failed, of its own, to clarify the factum of the receipt of Rs. 17 lakhs. This fact ought to have been disclosed in writing, before hearings in the Appeal had commenced, even if the Appellant was of the opinion that the scope of two Arbitrations were totally distinct.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free