Jyoti Ltd vs Prasad & Company (Project Works) Ltd
- CitationCompany Appeal (AT) (Insolvency) No. 288 of 2019
Ratio decidendi
The rule this decision rests on
Where an application under Section 9 of the Insolvency and Bankruptcy Code rests on a purchase order issued by a joint venture, and the joint venture is neither a party to the application nor impleaded as a co-applicant, the operational creditor cannot establish the debt and default required for admission against a corporate debtor that was not the contracting party, and the application is not maintainable on that footing. Where the existence of the debt is genuinely disputed on the facts, the appellate tribunal will not interfere with the adjudicating authority's refusal to admit the application, since a dispute over payment of the debt goes against the operational creditor's entitlement to initiation.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
NATIONAL COMPANY LAW APPELLATE TRIBUNAL NEW DELHI Company Appeal (AT) (Insolvency) No. 288 of 2019 [ arising out of Order dated 20th February, 2019 by NCLT, Hyderabad Bench, Hyderabad in CP (IB) No. 413/9/HDB/2018 ]
IN THE MATTER OF:
M/s. Jyoti Ltd. ...Appellant
Versus
M/s. Prasad & Company (Project Works) Ltd. ...Respondent
Present:
For Appellant : Mr. Alok Dhir, Ms. Varsha Banerjee and Ms. Juhi Bhambhani, Advocates
For Respondent: Mr. Abhay Kolte, Advocate
JUDGMENT
SUDHANSU JYOTI MUKHOPADHAYA, J.
The Appellant - 'M/s. Jyoti Limited' (Operational Creditor) filed an
application under Section 9 of the 'Insolvency and Bankruptcy Code, 2016
(for short, 'the I&B Code') for initiation of 'Corporate Insolvency Resolution
Process' against 'M/s. Prasad & Company (Project Works) Limited' (Corporate
Debtor) alleging the default on the part of the 'Corporate Debtor' for repaying
a sum of Rs.2,97,79,977.24 as on 10th December, 2016 along with interest
w.e.f. 25th May, 2018 till date of realization. The Adjudicating Authority
(National Company Law Tribunal), Hyderabad Bench, Hyderabad by
impugned order dated 20th February, 2019 rejected the application with the
following observations :
2
"FINDINGS
14. It is not in dispute 25% of the retention money to be paid after erection, commissioning and trial run. The rest of the purchase Order was completed. 75% of the amount covered by the Purchase order was also paid. The contention of Operational Creditor, as completion of project was delayed only on account of Corporate Debtor, then it is entitled to claim retention money as per the terms of payment. It is the duty of Operational Creditor to prove that there is a debt due by the Corporate Debtor and it has committed default. The money deducted towards 25% of the purchase Order under each invoice was calculated and contended this amount became due and payable by the Corporate Debtor in terms of Purchase Order. The contention of Counsel for Operational Creditor that it is not in dispute Corporate Debtor had not paid 25% of the retention money. However, Corporate Debtor is contending that the Operational Creditor has not completed the rest of the contract as per Purchase order and therefore, there was no liability to pay the same to the Operational Creditor.
15. The contention of the Learned Counsel for Operational Creditor that it is not responsible for any delay. Counsel contended, Operational Creditor is ready to erect, commission and trial run the equipment as per the terms of payment but site is not handed over to the Operational Creditor by Corporate Debtor. If delay is occurred on account of Corporate Debtor then Operational Creditor is
Company Appeal (AT) (Insolvency) No. 288 of 2019 3
entitled at least 20% of the retention money in terms of payment of the purchase order. The question whether delay occurred on account of Corporate Debtor. Admittedly, Corporate Debtor was given contract for completing the project for Majalgaon Lift Irrigation System on Turn Key Basis and equipment was transported to the project site. At that stage authorities of Government of Maharashtra issued order suspending the work. It is an unforeseen event. Parties to the Purchase order did not visualize such an event will take place. In the normal course if there is no suspension order, Operational Creditor can erect, commission and trial run the equipment. In case in the normal course, delay occurred on account of Corporate Debtor for completing the project on any ground other than the ground now referred to, then it can be said the retention money becomes due up to 20% and if not paid it amounts to default.
16. The situation is otherwise. Without any fault from the side of Corporate Debtor concerned authorities of Government of Maharashtra issued order of suspension of the project work. The Corporate Debtor cannot be blamed for the suspension order passed by the authorities of Government of Maharashtra. The suspension order does not show that it was issued on account of failure on the part of Corporate Debtor to perform its part of the contract given to it by the Government of Maharashtra.
17. In fact, it is the case of Corporate Debtor it filed applications to the concerned authorities of Government of Maharashtra to lift the suspension
Company Appeal (AT) (Insolvency) No. 288 of 2019 4
order and allow it to complete the contract. The Authorities of Government of Maharashtra are yet to take a decision. It can be safely said that Corporate Debtor was no way responsible for passing suspension order by the authorities of Government of Maharashtra. Therefore, Corporate Debtor cannot be found fault for the delay.
18. The Operational Creditor becomes entitled to retention money of 25% or 20% as the case may be only if it completes the terms of purchase order, especially erection, commissioning and trial run. This part of the contract was not completed. The amount becomes due only if Operational Creditor completes the remaining part of the Purchase Order. Till then, the amount does not become due. When the amount does not become due, then there is no question of default. When there is no debt within the meaning of 3 (12) of IBC, then there is no question of default. Thus, Operational Creditor failed to establish that there is a debt due and payable and it was committed default. As far as IBC is concerned, the Operational Creditor to establish debt as well as default. When these two are not established then petition cannot be admitted. Thus, the petition is liable to be rejected."
2. Learned counsel appearing on behalf of the Appellant submitted that
the Adjudicating Authority cannot give a specific finding with regard to claim
and counter-claim made by the parties. According to him, there is a 'debt'
and 'default' and Form 5 with the application under Section 9 is complete, the
Adjudicating Authority was required to admit the application.
Company Appeal (AT) (Insolvency) No. 288 of 2019 5
3. It was contended that against the total invoice amount of
Rs.8,93,47,703/- and an amount of Rs.6,65,26,600/- has been received
leaving balance of Rs.2,28,21,103/-
4. It was submitted that the Adjudicating Authority failed to notice that
the Appellant established the liability of the Respondent for the outstanding
amount due payable by it to the Appellant as mentioned in 'Part-IV of 'I&B
Code' of Form 5. Initially, 2 orders namely a purchase order of mechanical
components i.e. VT Pump sets along with its equipments etc. and a work order
to store, erect, test and commission the mechanical components dated 6th
July, 2013 were placed by the Appellant to a Joint Venture 'Prasad-Shreehari
(JV)'. The total consideration of the purchase order was agreed to the tune of
Rs.17,55,25,790/- and the total consideration for the work order was agreed
to the tune of Rs. 9,65,39,184.50.
5. Thereafter, an amendment to the 'Purchase Order' as well as the work
order was done by the Appellant and the 'Joint Venture' on 26th February,
2014 and 10th March, 2014 respectively. In terms of the said amendments,
the purchase order and work orders were issued on behalf of the 'Corporate
Debtor' independently and the total consideration of the purchase order was
agreed to the tune of Rs.9,65,39,184.50 and total consideration for the work
order was agreed to the tune of Rs. 34,50,815.50. In terms of the said
purchase order dated 26th February, 2014, the payments were to be made in
different instalments, as per the details given in the affidavit. However, it is
not necessary to discuss all such details at this stage. As the question arises
whether a 'debt' is payable and there is a 'dispute' and there is a 'default' and
Company Appeal (AT) (Insolvency) No. 288 of 2019 6
if so, whether the application filed under Section 9 of the 'I&B Code' is barred
by limitation.
6. The Respondent - 'Corporate Debtor' has taken plea that in terms of the
agreed payment 10% advance along with the purchase order were to be made.
65% against supply of equipment at the site after confirmation of 3rd party
inspection against LC was to be made within 60 days period. Thereafter, 12%
against erection of equipment within 30 days was payable. Followed by 13%
payable at the stage of trial, commission and completion of three months trial
operation of equipment of 30 days. If commissioning gets delayed from the
side of 'Corporate Debtor' beyond six months, then 8% was to be released and
5% amount was required to be retained till completion of commissioning.
7. The Respondent accepted that the Appellant raised the invoices and
stated that it had deducted 12% amount against erection and 13% amount to
be payable after completion of the trial operation. In all the invoices, the
Appellant has lastly shown an amount which is stated to be "now Balance
Payable". Further according to the Respondent, it has paid the entire amount
as shown as "now Balance Payable" by the Appellant in each of the invoices
and total invoices amount of Rs. 8,93,47,704/-. The amount equal to 75% of
the said amount comes to Rs.6,70,10,780/- but the Respondent has actually
paid more than the same i.e. Rs.6,67,58,301/- to the Appellant as per details
Company Appeal (AT) (Insolvency) No. 288 of 2019 7
given below
8. In the aforesaid background plea has been taken that there is no unpaid
invoice, in absence of performance of the Appellant, the Appellant cannot
claim payment.
9. Having heard the learned counsel for the parties and from perusal of
the records, we find that the application under Section 9 was filed by the
Appellant only with a view to realise the amount and not for the purpose of
'Corporate Insolvency Resolution Process'
10. Apart from the aforesaid facts that we find that the agreement was
reached between the Appellant and a work of Joint Venture i.e. 'Prasad-
Company Appeal (AT) (Insolvency) No. 288 of 2019 8
Shreehari' but in the petition 'M/s. Prasad & Company (Project Works)
Limited has been impleaded as the party-respondent and not the joint
venture.
11. Enclosure to Form 5 which has been relied upon by the Appellant before
the Adjudicating Authority to claim the dues contains one 'Purchase Order'
dated 6th July, 2013 which has been sent by 'Prasad-Shreehari (Joint
Venture), extract of which mentioned below:
Company Appeal (AT) (Insolvency) No. 288 of 2019 9
12. In view of the aforesaid fact, as we find that there is a disputed question
of fact relating to payment of 'debts' and the purchase order was issued by
'Joint Venture' dated 6th July, 2013 relied by the Appellant was issued by the
Joint Venture i.e. 'Prasad - Shreehari (J.V.)' which is not a party to this appeal
Company Appeal (AT) (Insolvency) No. 288 of 2019 10
or was not impleaded as the co-applicant in the application filed under Section
9 of the 'I&B Code', we are not inclined to grant any relief to the Appellant.
The appeal is accordingly dismissed. No costs.
[Justice S.J. Mukhopadhaya] Chairperson
[ Justice A.I.S. Cheema ] Member (Judicial)
[ Kanthi Narahari ] Member (Technical) New Delhi
18th November, 2019
//ns//
Company Appeal (AT) (Insolvency) No. 288 of 2019
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free