Jay Bhagwani Construction Co vs Haware Engineers And Builders Pvt. Ltd
- CitationAIRONLINE 2018 BOM 1133
Ratio decidendi
The rule this decision rests on
A contractual clause requiring disputes to be resolved by a party's managing director, with a decision "final and binding," followed by the statement that "any dispute shall be referred to arbitration or any court," constitutes a valid arbitration agreement where the clause must be read harmoniously as a whole without rendering any part otiose or surplusage. The presence of the word "arbitration" in such a clause, read in context with the managing director's decision-making authority, demonstrates the parties' clear intention to submit disputes to arbitration, even where the clause does not prescribe adjudication procedures or requirements of natural justice. When interpreting an arbitration agreement, courts must adopt a pragmatic, common-sense approach reflecting the intention of business parties rather than a pedantic or legalistic construction; the court must encourage arbitration by making an ostensibly unworkable clause workable within the permissible limits of law, and in cases of ambiguity in a clause drafted by one party, the benefit of doubt must be given to the other party. Where a named arbitrator in an arbitration clause falls within the categories specified in the Seventh Schedule to the Arbitration and Conciliation Act, 1996 (rendering the person ineligible to act as arbitrator under Section 12(5)), the court has ample power under Section 11(6) of that Act to appoint an independent arbitrator in place of the ineligible named arbitrator to adjudicate the dispute. A clause requiring settlement through one mechanism followed by alternative options to arbitration or litigation does not negate the existence of an arbitration agreement where the clause refers to "arbitration" as one of the alternative dispute resolution mechanisms and the parties' intention to arbitrate can be discerned from reading the entire clause harmoniously.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
ppn 1 carap-121.18(j).doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL ARBITRATION APPLICATION NO.121 OF 2018
M/s. Jay Bhagwati Construction Co. ) a partnership firm registered under ) The Indian Partnership Act, 1932 ) (Regn. No.MU 000003339) and having ) its head office at II No.6, Shastri Nagar, ) Near Samaj Mandir Hall, Bandra (East), ) Mumbai - 400 051 through its Partner ) Mr.Chandan Mithbavkar ) .. Applicant
Versus
Haware Engineers & Builders Pvt. Ltd. ) A Company registered under the ) Indian Companies Act, 1956, ) having its registered address at ) 416, Vardhaman Market, Sector-17, ) Vashi, Navi Mumbai - 400 705. ) .. Respondent ---
Mr.Aditya Thakkar a/w Ms.Rishika Harish a/w Mr.Deepak Shukla a/w Ms.Swapna Samant i/by Vinod Mistry Co. for the applicant.
Mr.Atul Rajadhyaksha, Senior Advocate a/w Mr.Nishant Tripathi a/w Mr.Somnath Iyer i/by M. Tripathi & Co. for the respondent. --- CORAM : R.D. DHANUKA, J.
RESERVED ON : 19th October 2018 PRONOUNCED ON : 25th October 2018
Judgment :-
. By this application filed under Section 11(6) of the
Arbitration and Conciliation Act, 1996, the applicant seeks appointment
of a sole arbitrator to adjudicate upon the disputes and differences
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:06 ::: ppn 2 carap-121.18(j).doc
between the parties under the Work Order dated 18th June 2013 by
invoking Clause 32 of the said work order annexed at Exhibit-A to the
arbitration application. Some of the relevant facts for the purpose of
deciding this application are as under : -
2. The respondent issue a Work Order dated 18th June 2013
thereby appointing the applicant as a Contractor for certain works in
respect of the development of a building at Kasar Wadavali, Ghodbunder
Road, Thane. Clause 32 of the said work order is extracted as under : -
"Incase of any dispute, our Managing Director's decision will be final and binding on both the parties any dispute shall be referred to arbitration or any court."
3. The dispute arose between the parties. The applicant vide its
advocate's letter dated 15th September 2017 called upon the respondent
to pay a sum of Rs.5,13,29,560.49 and with interest @ 18% p.a. In
paragraph 28 of the said letter, the applicant pointed out clause 32 of
the said work order stating that the said clause was an arbitration clause
and the applicant reserved their rights to invoke the said clause. There
was no response to the said letter addressed by the applicant through its
advocate.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 3 carap-121.18(j).doc
4. On 16th October 2017, the applicant through its advocate
invoked clause 32 of the said work order and nominated a counsel of
this Court to be the sole arbitrator and called upon the respondent to
confirm the same within a period of 30 days from the date of the receipt
of the said letter. In response to the said letter invoking clause 32, the
respondent through its advocate's letter denied that clause 32 of the
work order was an arbitration agreement. It was contended that first part
of the said clause contemplates a reconciliation process whereby the
decision of the Managing Director was given a finality. In the event of
the dispute still persisting, the parties had option either to agree for
arbitration or seek remedies through he judicial process. Clause 32 does
not reveal any concluded arbitration agreement. Since the respondent
refused to appoint an arbitrator, the applicant filed this application under
Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short
"the said Act") inter alia praying for appointment of a sole arbitrator.
5. Mr.Thakkar, learned counsel for the applicant invited my
attention to clause 32 of the work order dated 18th June 2013 and the
correspondence exchanged between the parties including the notice
invoking clause 32 by the applicant, response of the respondent thereto
and would submit that the said clause 32 clearly contemplated an
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 4 carap-121.18(j).doc
arbitration agreement between the parties. He submits that first part of
the said clause refers to dispute, decision of the managing director upon
the such dispute being final and binding on both the parties and the
second part of the said clause refers to arbitration or any Court. He
submits that the intention of the parties is thus absolutely clear that in
case of any dispute between the parties, such dispute was required to be
referred to the arbitration of the Managing Director of the respondent.
He submits that however, in view of Section 12(5) read with Seventh
Schedule of the Arbitration and Conciliation Act, 1996, the managing
director of the respondent who was the named arbitrator would be
ineligible to act an arbitrator. The applicant has thus suggested the name
of a counsel of this Court to be appointed as a sole arbitrator and the said
appointment shall be confirmed within a period of 30 days from the
receipt of the said notice failing which the applicant would adopt
appropriate remedy for seeking such appointment. He submits that the
managing director of the respondent thus could not have been appointed
as an arbitrator in view of the said provision under Section 12(5) read
with Seventh Schedule of the said Act.
6. Learned counsel placed reliance on an unreported judgment
of this Court delivered on 19th March 2015 in the case of Tatva Global
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 5 carap-121.18(j).doc
Environment (Deonar) Ltd. Vs. The Municipal Corporation of Gr.
Mumbai in Arbitration Application No.15 of 2014 and would submit that
this Court after considering a similar arbitration clause and after adverting
to the judgment of the Hon'ble Supreme Court in the case of Bihar State
Mineral Development Corporation & Anr. Vs. Encon Builders (I) (P)
Ltd., (2003) 7 SCC 418 and another judgment of the Hon'ble Supreme
Court in the case of Jagdish Chander Vs. Ramesh Chander & Ors.,
(2007) 5 SCC 719 and in case of Datar Switchgears Ltd. Vs. Tata
Finance Ltd., (2000) 8 SCC 151 and in the case of Deep Trading
Company Vs. Indian Oil Corporation, (2013) 4 SCC 35 has held that
there existed a valid and subsisting arbitration agreement between the
parties. He submits that the respondent did not agree to the name
suggested by the applicant within a period of 30 days and did not even
suggest any other name to the applicant for appointment of a sole
arbitrator by consensus of the parties within the time prescribed, this
Court has an ample power to appoint an independent arbitrator.
7. Learned counsel for the applicant placed reliance on the
judgment of the Hon'ble Supreme Court in the case of Zhejiang Bonly
Elevator Guide Rail Manufacture Co. Ltd. Vs. Jada Elevator
Components, 2018 SCC OnLine SC 1503 and in particular paragraphs
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 6 carap-121.18(j).doc
4, 10 and 11 thereof and would submit that the Hon'ble Supreme Court
has considered the identical arbitration clause and has held that the
intention of the parties to have their disputes resolved by arbitration was
clear and thus the Hon'ble Supreme Court has appointed an arbitrator on
interpretation of the said clause.
8. Mr.Rajadhyaksha, learned senior counsel for the respondent,
on the other hand, invited my attention to the averments made in
paragraphs 4, 5, 27 and 29 of the arbitration application and also affidavit
in rejoinder filed by the applicant and would submit that it is the case of
the applicant that the dispute between the parties was required to be
referred to the arbitration of the named arbitrator who was the
managing director of the respondent.
9. It is submitted that the said clause 32 cannot be construed as
an arbitration agreement. The managing director was not required to act
judicially or to exercise any power to resolve the dispute between the
parties. The said clause 32 does not indicate any adjudication of dispute
by complying with the provisions of law and principles of natural
justice. The said clause 32 does not postulate a binding agreement
between the parties contemplating appointment of an arbitrator. The said
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 7 carap-121.18(j).doc
clause has to be read in totality. The said clause when read in its totality
does not constitute a binding obligation to refer the dispute to arbitration,
but merely contemplates a possibility of going to arbitration subject to
a further agreement between the parties in that regard. The said procedure
contemplated under clause 32 was for primary and secondary approaches
to the dispute resolution. When the dispute was not resolved at the
execution level, it becomes inevitable that the administrative head
intervened to amicably resole the same.
10. It is submitted that the first part of the said clause 32 has to
be read in context which was engrafted merely to avoid delay and
stoppage of work and for the purpose of smooth carrying on of the
works. He submits that if the managing director fails to resolve the
dispute, the parties have option either to refer the dispute to arbitration
or seeks remedies through the judicial process. At the most, the second
part of the said clause 32 shows that it was not the intention of the parties
that the arbitration be the sole dispute resolution mechanism. He
submits that the parties have not arrived at an agreement to refer the
dispute to arbitration and thus the dispute cannot be referred to
arbitration.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 8 carap-121.18(j).doc
11. Learned senior counsel for the respondent placed reliance on
the judgment of the Hon'ble Supreme Court in the case of National
Agricultural Coop. Marketing Federation India Ltd. Vs.Gains Trading
Ltd., (2007) 5 SCC 692 in support to the submission that the said
clause 32 refers to "arbitration or court" and thus the rules of
interpretation required the clause to be read in the ordinary and natural
sense, except where that would lead to an absurdity. No part of a term or
clause should be considered as a meaningless, surplusage, when it is in
consonance with the other parts of the clause and expresses the specific
intention of the parties.
12. Learned senior counsel placed reliance on an unreported
judgment delivered on 10th September 2009 in the case of Dr.Arun
Subrao Prabhu Vs. M/s.Rizvi Builders & Ors. in Suit No.1336 of 1988
and in particular paragraphs 6, 11 and 14 thereof in support of the
submission that while interpreting the words of a contract, the efforts
of the Court must be to read all the provisions harmoniously. A
construction which results in any part of the contract being rendered
otiose must be avoided.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 9 carap-121.18(j).doc
13. Learned senior counsel placed reliance on the judgment of
the Hon'ble Supreme Court in the case of Jagdish Chander Vs.Ramesh
Chander & Ors. (supra) and in particular paragraphs 2 and 8 thereof
and would submit that the Hon'ble Supreme Court after adverting to
several earlier judgments on interpretation of the arbitration agreement
which has specifically included the words "arbitration or court," has
held that such clause cannot be construed as an arbitration agreement in
view of there being uncertainty, the said clause gives a chance to both
the parties whether to go to the arbitration or court in the event of
dispute having arisen between the parties. The applicant thus could not
have applied for appointment of an arbitrator in view of there being no
further agreement between the parties for referring the dispute to the
arbitration.
14. Learned senior counsel placed reliance on the judgment of
the Hon'ble Supreme Court in the case of Karnataka Power
Transmission Corporation Limited & Anr. Vs.Deepak Cables (India)
Limited, (2014) 11 SCC 148 and more particularly paragraphs 2, 3, 5,
9 to 11, 21, 22, 23 and 26 thereof. He submits that there was no
procedure contemplated in clause 32 for following the principles of
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 10 carap-121.18(j).doc
natural justice. The managing director was not required to act judicially
and thus clause 32 empowering the managing director to resolve the
dispute could not be construed as an arbitration agreement.
15. Learned senior counsel for the respondent placed reliance on
the judgment of this Court in the case of Voltas Limited Vs. M.P.
Entertainment & Developers Pvt. Ltd., 2016 SCC OnLine Bom 7664
and in particular paragraphs 13, 17 and 18 in support of the submission
that since the said clause 32 also provides the expression "court," the
expression "arbitration" mentioned in the same clause cannot be enforced
unless both the parties give consent for the same.
16. Learned senior counsel placed reliance on the judgment of
the Hon'ble Supreme Court in the case of Kerala State Electricity
Board & Anr. Vs. Kurien E. Kalathil & Anr., (2018) 4 SCC 793 and in
particular paragraph 14 thereof and would submit that referring the
parties to arbitration has serious civil consequences procedurally and
substantively and if there is no arbitration agreement between the parties,
without a joint memo or a joint application of the parties, this Court
cannot refer the parties to the arbitration.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 11 carap-121.18(j).doc
17. In so far as the judgment of the Hon'ble Supreme Court in
the case of Zhejiang Bonly Elevator Guide Rail Manufacture Co.
Ltd. (supra) relied upon by the learned counsel for the applicant is
concerned, it is submitted by the learned senior counsel for the
respondent that the said judgment cannot be considered as a binding
precedent in this matter. The view taken by the Hon'ble Supreme Court
in that matter is based on the facts of that case. In support of his
submission, the learned senior counsel placed reliance on the judgment of
the Hon'ble Supreme Court in the case of Haryana Financial
Corporation and Ors. Vs. Jagdamba Oil Mills & Ors., AIR 2002 SC
834 and would submit that the observations made by the Hon'ble
Supreme Court in the case of Zhejiang Bonly Elevator Guide Rail
Manufacture Co. Ltd. (supra) must be read in context in which those
observations appear to the facts of this case. The judgments of Courts
are not to be construed as statutes.
18. Learned senior counsel for the respondent placed reliance
on the judgment of the Hon'ble Supreme Court in the case of Bank of
India & Anr. Vs. K.Mohandas & Ors., (2009) 5 SCC 313 and in
particular paragraphs 54 to 61 in support of the submission that the
Court has to apply the judgment to the facts of each case. A case is only
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 12 carap-121.18(j).doc
an authority for what it actually decides. He submits that the judgment
in the case of Zhejiang Bonly Elevator Guide Rail Manufacture Co.
Ltd. (supra) is thus clearly distinguishable in the facts of this case and
cannot be construed as a precedent.
19. Mr.Thakkar, learned counsel for the applicant in rejoinder
submits that the second part of clause 32 of the work order clearly
supports the first part. This Court has to read both the parts harmoniously
so as to ascertain the true and correct meaning thereof and the intention
of both the parties.
20. Learned counsel for the applicant distinguishes the judgment
of the Hon'ble Supreme Court in the case of Jagdish Chander
Vs.Ramesh Chander & Ors. (supra) and would submit that all the
attributes and elements of an arbitration agreement exist in clause 32 of
the work order. The arbitration agreement is admittedly in writing. The
parties have agreed to refer the disputes to arbitration. The arbitrator is
empowered to adjudicate upon the dispute. The parties have also agreed
that the decision of the managing director of the respondent would be
final and binding. He submits that the said judgment would support the
case of the applicant and not the respondent. He submits that in that case,
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 13 carap-121.18(j).doc
the Hon'ble Supreme Court had set aside the appointment of the arbitrator
on rendering a finding that the parties had agreed to enter into an
arbitration agreement in future which is not the clause in this matter.
21. Learned counsel for the applicant distinguishes the judgment
of the Hon'ble Supreme Court in the case of Karnataka Power
Transmission Corporation Limited & Anr. (supra) relied upon by the
learned senior counsel for the respondent on the ground that in this case,
the arbitration clause recorded in clause 32 of the work order does not
contemplate the process of resolution at two stages as was the case
before the Hon'ble Supreme Court. He submits that clause under
consideration of the Hon'ble Supreme Court was totally different.
22. Learned counsel for the applicant distinguishes the judgment
of this Court in the case of Voltas Limited (supra) relied upon by the
learned senior counsel for the respondent on the ground that the
arbitration clause in that matter was depending upon the contingencies
provided therein. It was provided that if the matter was referred to
arbitration then, it would be resolved by dual arbitrators, one by client
and another by contractor. He relied upon paragraphs 13, 17 and 18 of
the said judgment while distinguishing the said judgment. ::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 14 carap-121.18(j).doc
23. In so far as the judgment of the Hon'ble Supreme Court in
the case of Kerala State Electricity Board & Anr. (supra) relied upon
by the learned senior counsel for the respondent is concerned, learned
counsel for the applicant distinguishes the said judgment on the ground
that the Hon'ble Supreme Court had considered the powers of Court
under Section 89 of the Code of Civil Procedure, 1908 when there was
no arbitration agreement entered into between the parties and in that
context had held that referring the parties to arbitration has serious civil
consequences procedurally and substantively and if there is no arbitration
agreement between the parties, without a joint memo or a joint
application of the parties, this Court cannot refer the parties to the
arbitration.
24. In so far as the the other judgments relied upon by the
learned senior counsel for the respondent in support of the submission
that the judgment of the Hon'ble Supreme Court relied upon by the
applicant cannot be considered as a precedent is concerned, it is
submitted by the learned counsel for the applicant that there is no dispute
about the propositions of law laid down by the Hon'ble Supreme Court or
by the High Court in those judgments relied upon by the learned senior
counsel for the respondent. He however, submits that the judgment of the
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 15 carap-121.18(j).doc
Hon'ble Supreme Court in the case of Zhejiang Bonly Elevator Guide
Rail Manufacture Co. Ltd. (supra) would squarely apply to the facts of
this case in view of the Hon'ble Supreme Court interpreting the identical
arbitration clause which had the expression "dispute should be settled by
arbitration body for arbitration or court."
25. It is submitted that in clause 32 of the work order also the
expression "arbitration or court," both are recorded. After interpreting
such arbitration clause, the Hon'ble Supreme Court held that the said
clause refers to the arbitration or court. Since there was an option and the
applicant had invoked the arbitration clause, the Hon'ble Supreme Court
has no hesitation to appoint an arbitrator to adjudicate upon the dispute
between the parties. The Hon'ble Supreme Court adverted to the earlier
judgment in the case of Indtel Technical Services Private Limited Vs.
W.S. Atkins Rail Limited, (2008) 10 SCC 308 and held that the parties
had intended to resolve their disputes through arbitration and thus the
petition for appointment of an arbitrator was accordingly allowed.
REASONS AND CONCLUSIONS :-
26. A short question arises for consideration of this Court is
whether clause 32 of the work order dated 18th June 2013 constitutes an
arbitration agreement between the parties or not.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 16 carap-121.18(j).doc
27. A perusal of clause 32 of the work order indicates that the
said clause refers to the expression "dispute" and also refers to the
decision of the Managing Director of the respondent, in case of such
dispute, will be final and binding on both the parties. There is no
punctuation between the words "both the parties" and "any disputes shall
be referred to Arbitration or any Court." It is not the case of the
respondent that the dispute does not exist between the parties. The
application for appointment of an arbitrator is opposed mainly on the
ground that the said clause 32 did not provide for any procedure, for
complying with the principles of natural justice or adjudication of
disputes in a judicial manner by the managing director. It is the case of
the respondent that the said clause would only indicate that inspite of
intervention of the managing director, if the dispute between the parties
is not resolved, in that event, the parties have option either to refer the
dispute to arbitration or seeks remedies through the judicial process and
thus it was not the intention of the parties that the arbitration be the sole
dispute resolution mechanism. In paragraph 6.4 of the affidavit-in-
reply filed by the respondent, it is the contention of the respondent that
at the most, the said clause 32 is only a reflection of a possibility of the
parties agreeing to arbitration in the future. On the other hand, it is the
case of the applicant that the managing director of the respondent was a
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 17 carap-121.18(j).doc
named arbitrator under the said clause 32 for the purpose of resolution
of disputes and differences between the parties.
28. Section 12(1)(a) of the Arbitration and Conciliation Act,
1996 provides that when a person is approached in connection with his
possible appointment as an arbitrator, he shall disclose in writing any
circumstances such as the existence either direct or indirect, of any past
or present relationship with or interest in any of the parties or in relation
to the subject matter in dispute, whether financial, business, professional
or other kind, which is likely to give rise to justifiable doubts as to his
independence or impartiality. Explanation (1) is added to the said
provision which provides that the grounds stated in the Fifth Schedule
shall guide in determining whether circumstances exist which give rise
to justifiable doubts as to the independence or impartiality of the
arbitrator.
29. Section 12(5) of the Arbitration and Conciliation Act, 1996
provides that Notwithstanding any prior agreement to the contrary, any
person whose relationship, with the parties or counsel or the subject
matter of the dispute, falls under any of the categories specified in the
Seventh Schedule shall be ineligible to be appointed as an arbitrator.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 18 carap-121.18(j).doc
30. The first part of clause 32 of the work order dated 18 th June
2013 is extracted as under :-
"Incase of any dispute, our Managing Director's decision will be final and binding on both the parties."
The said provision thus clearly contemplates that in case of any dispute,
the same shall be referred to the Manging Director whose decision will
be final and binding on both the parties. The managing director referred
to in the said clause obviously refers to the managing director of the
respondent.
31. The second part of clause 32 of the work order dated 18 th
June 2013 is extracted as under :-
"any dispute shall be referred to arbitration or any court."
If the argument of the learned senior counsel for the respondent is
accepted that this clause did not amount to an arbitration agreement, the
words "any dispute shall be referred to arbitration" would be
surplusage or otiose. Even if the argument of the respondent is accepted
that the role of the managing director provided in first part of clause 32
was not adjudicatory, the words "any dispute shall be referred to
arbitration" would be surplusage or otiose. I am thus inclined to accept
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 19 carap-121.18(j).doc
the submission of the learned counsel for the applicant that the parties
had clearly intended that the dispute, if any, between the parties shall be
referred to arbitration of the managing director. In my view, the
managing director would thus fall under Serial Nos.1 and 2 of the
Seventh Schedule i.e. (1) The arbitrator is an employee, consultant,
advisor or has any other past or present business relationship with a party
or (2) The arbitrator currently represents or advises one of the parties
or an affiliate of one of the parties. In my view, Serial Nos.1 and 2 of
the Seventh Schedule have to be read with Section 12(5) of the said Act.
In my view, inspite of this agreement, in this case, which was entered into
on 18th June 2013 i.e. prior to the date of insertion of Section 12(5) w.e.f.
23rd October 2015, the managing director would not be eligible to act as
an arbitrator. Since the managing director himself is not eligible to act as
an arbitrator, he also will not be eligible to appoint any other arbitrator.
In that event, the Court has ample powers under Section 11(6) of the said
Act to appoint an independent arbitrator to adjudicate upon the dispute
between the parties.
32. This Court in the case of Tatva Global Environment
(Deonar) Ltd.(supra) has considered a clause which empowered the
Additional Municipal Commissioner to constitute a committee
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 20 carap-121.18(j).doc
comprising of three officers to resolve the disputes, differences or claim
arising out of the agreement. The said clause further contemplated an
appeal before the committee comprising of three Additional Municipal
Commissioners. This Court rejected the plea of the Municipal
Corporation that the said clause could not be construed as an arbitration
agreement after adverting to several judgments of the Hon'ble Supreme
Court. This Court held that the said clause which provides that the
decision given by the committee shall be final and binding upon the
parties establishes that the said clause has to be construed as an
arbitration agreement and not a mere internal procedure.
33. The Hon'ble Supreme Court in the case of Zhejiang Bonly
Elevator Guide Rail Manufacture Co. Ltd. (supra) has considered the
clause 15 which is extracted as under :-
"15.Dispute handling :
Common processing contract disputes, the parties should be settled through consultation; consultation fails by treatment of to the arbitration body for arbitration or the court."
The Hon'ble Supreme Court held that the intention of the parties, as it
flows from the clause, is that efforts have to be made to settle the
disputes in an amicable manner and, therefore, two options were
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 21 carap-121.18(j).doc
available, either to go for arbitration or for litigation in a court of law.
After adverting to the earlier judgment of the Hon'ble Supreme Court in
the case of Indtel Technical Services Private Limited (supra), the
Hon'ble Supreme Court held that the intention of the parties to have their
disputes resolved by arbitration has to be considered. In the case at hand
before the Hon'ble Supreme Court, the Hon'ble Supreme Court held that
the said clause 15 refers to the arbitration or court. There is thus an
option for the petitioner to invoke the arbitration clause and, therefore,
the Court has no hesitation, in the obtaining factual matrix of the case, for
appointment of an arbitrator and, accordingly, appointed a retired Judge
of the Hon'ble Supreme Court as a sole arbitrator. In my view, in this
case also, the expression "arbitration or court" is incorporated in the said
clause 32 in addition to the words "dispute" and "decision of the
managing director." In my view, the said judgment of the Hon'ble
Supreme Court in the case of Zhejiang Bonly Elevator Guide Rail
Manufacture Co. Ltd. (supra) would squarely apply to the facts of this
case. I am respectfully bound by the said judgment. The entire clause
has to be read harmoniously.
34. Learned senior counsel for the respondent though relied
upon various judgments in support of his submission that the judgment
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 22 carap-121.18(j).doc
of the Hon'ble Supreme Court in the case of Zhejiang Bonly Elevator
Guide Rail Manufacture Co. Ltd. (supra) cannot be considered as a
precedent and was delivered in the facts of that case, in my view, there
is no dispute about the propositions of law laid down by the Hon'ble
Supreme Court in those judgments relied upon by the learned senior
counsel for the respondent. In this case, clause 32 of the work order is
similar to clause 15 of the said clause which fell for consideration of the
Hon'ble Supreme Court. After interpreting the said clause, the Hon'ble
Supreme Court held that the said clause which refers to the 'arbitration'
or 'court', it would amount to an arbitration clause. The judgments thus
relied upon by the learned senior counsel for the respondent would not
assist the case of the respondent. In my view, the judgment of the Hon'ble
Supreme Court in the case of Zhejiang Bonly Elevator Guide Rail
Manufacture Co. Ltd. (supra) is clear authority on the propositions of
law interpreting the identical arbitration clause and thus would be a
precedent under Article 141 of the Constitution of India and being
applicable to the facts of this case would be binding on this matter.
35. A perusal of the reply dated 2nd July 2018 addressed by the
respondent through its advocate in response to the letter dated 15 th
September 2017 and 16th October 2017 addressed by the applicant
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 23 carap-121.18(j).doc
through its advocate indicates that the respondent had contended that the
first part of clause 32 contemplates a reconciliation process whereby the
decision of the managing director of the respondent was given a finality
and in the event of dispute still persisting, the parties had option either
to agree for arbitration or seek remedies through the judicial process.
Similar contention is also raised in the affidavit-in-reply filed by the
respondent. It is also contended in the affidavit-in-reply that the said
clause at the very highest is the clause which reflects a possibility of the
parties agreeing to arbitration in the future. This Submission of the
learned senior counsel for the respondent is contrary to the principles of
law laid down by the Hon'ble Supreme Court in the case of Zhejiang
Bonly Elevator Guide Rail Manufacture Co. Ltd. (supra).
36. In so far as the judgment of the Hon'ble Supreme Court in
the case of National Agricultural Coop. Marketing Federation India
Ltd. (supra) relied upon by the learned senior counsel for the respondent
is concerned, it has been held by the Hon'ble Supreme Court that no part
of a term or clause should be considered as a meaningless, surplusage,
when it is in consonance with the other parts of the clause and expresses
the specific intention of the parties.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 24 carap-121.18(j).doc
37. The Hon'ble Supreme Court in the case of Enercon (India)
Limited & Ors. Vs. Enercon GMBH & Anr., (2014) 5 SCC 1 after
adverting to several earlier judgments of the Hon'ble Supreme Court has
held that the courts have to adopt a pragmatic approach and not a
pedantic or technical approach while interpreting or construing an
arbitration agreement or arbitration clause. Therefore, when faced with a
seemingly unworkable arbitration clause, it would be the duty of the court
to make the same workable within the permissible limits of the law,
without stretching it beyond the boundaries of recognition. It is held that
a common sense approach has to be adopted to give effect to the intention
of the parties to arbitrate. It is held that the court ought to adopt the
attitude of a reasonable business person, having business common sense
as well as being equipped with the knowledge that maybe peculiar to the
business venture. The arbitrate clause cannot be construed with a purely
legalistic mindset, as if one is construing a provision in a statute. The
Hon'ble Supreme Court in the said judgment adverted to the UNCITRAL
Model Law and held that the Courts play a supportive role in encouraging
the arbitration to proceed rather than letting it come to a grinding halt. In
my view, the principles of law laid down by the Hon'ble Supreme Court
in case of Enercon (India) Limited & Ors. (supra) would squarely apply
to the facts of this case. I am respectfully bound by the said judgment. ::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 25 carap-121.18(j).doc
38. In my view, the intention of both the parties was clear that
the matter shall be referred to the arbitration if the dispute arises
between the parties and decision of such arbitrator will be final and
binding on the parties. The Court has to adopt a common sense approach
to give effect to the intention of the parties to arbitrate. In my view, this
Court cannot interpret the said clause 32 as a statute and cannot accept
the interpretation as sought to be canvassed by the learned senior counsel
for the respondent. The Court has to encourage the parties to refer the
dispute to the arbitration and while interpreting an arbitration clause has
to adopt a liberal approach. The judgment of the Hon'ble Supreme Court
in the case of National Agricultural Coop. Marketing Federation India
Ltd. (supra) thus would not assist the case of the respondent.
39. In so far as the unreported judgment of this Court in the
case of Dr.Arun Subrao Prabhu Vs. M/s.Rizvi Builders & Ors.
(supra) relied upon by the learned senior counsel for the respondent is
concerned, this Court had interpreted two clauses in the contract which
were ex facie contrary to each other. This Court in the said suit,
accordingly, held that while interpreting the words of a contract, the
effort of the Court must be to read all the provisions harmoniously. A
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 26 carap-121.18(j).doc
construction which results in any part of the contract being rendered
otiose must be avoided. In my view, the argument of the learned senior
counsel for the respondent that the expression "arbitration or court,"
both are referred in clause 32 and thus the expression "court" would be
otiose if the matter is referred to the arbitration is concerned, is without
any merit. The Court has to interpret the said clause which is entered
into between two business men having business common sense and has
to adopt an attitude of a reasonable business person while interpreting the
said provision. The draft man of the said work order was undoubtedly the
respondent. The benefit of doubt in case of any ambiguity thus has to be
given to other side. The said unreported judgment of this Court in the
case of Dr.Arun Subrao Prabhu Vs. M/s.Rizvi Builders & Ors. (supra)
thus would not assist the case of the respondent.
40. In so far as the judgment of the Hon'ble Supreme Court in
the case of Jagdish Chander Vs.Ramesh Chander & Ors. (supra)
relied upon by the learned senior counsel for the respondent is concerned,
the said judgment interpreted the clause which is extracted as under :-
"(16) If during the continuance of the partnership or at any time afterwards any dispute touching the partnership arises between the partners, the same shall be mutually
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 27 carap-121.18(j).doc
decided by the partners or shall be referred for arbitration if the parties so determine."
After construing the aforesaid clause 16, the Hon'ble Supreme Court
came to the conclusion that the said clause had contemplated that it is not
an arbitration agreement but a provision which enables arbitration only if
the parties mutually decide after due consideration as to whether the
disputes should be referred to arbitration or not and thus the said clause
required the consent of parties before the disputes could be referred to
arbitration and thus could not be construed as an arbitration agreement.
In my view, clause 32 of the work order does not contemplate any such
mutual consent subsequently after arising of dispute between the parties.
The said judgment of the Hon'ble Supreme Court in the case of Jagdish
Chander Vs.Ramesh Chander & Ors. (supra) is thus clearly
distinguishable in the facts of this case.
41. In so far as the judgments of the Hon'ble Supreme Court in
the case of Haryana Financial Corporation and Ors. Vs. Jagdamba
Oil Mills & Ors.(supra) and in the case of Bank of India & Anr. Vs.
K.Mohandas & Ors.(supra) relied upon by the learned senior counsel
for the respondent are concerned, there is dispute about the propositions
of law laid down by the Hon'ble Supreme Court in the said judgment. In
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 ::: ppn 28 carap-121.18(j).doc
this case, the judgment of the Hon'ble Supreme Court in the case of
Zhejiang Bonly Elevator Guide Rail Manufacture Co. Ltd. (supra)
would squarely apply to the facts of this case.
42. For the reasons recorded aforesaid, in my view, the
arbitration agreement exists between the parties. Since the respondent
had failed to appoint an arbitrator, this application filed under Section
11(6) of the Arbitration and Conciliation Act, 1996 is maintainable.
43. I therefore pass the following order :-
(i) I propose to appoint Shri Justice J.P. Devadhar, a former
Judge of this Court having address at 311, Churchgate Chambers, 5, New
Marine Lines, Next to American Centre, Churchgate, Mumbai- 400 020
as a sole arbitrator.
(ii) Learned prospective arbitrator is requested to file a statement
of disclosure in terms of Section 11(8) read with Section 12(1) of the
Arbitration and Conciliation Act, 1996 on or before the next date.
(iii) The applicant is permitted to obtain statement of disclosure
from the learned prospective arbitrator and to tender the same before this
Court on the next date.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
ppn 29 carap-121.18(j).doc
(iv) If the learned prospective arbitrator is appointed, fees and
expenses of the learned arbitrator shall be borne by both the parties
equally at the first instance.
44. Place the arbitration application on supplementary board for
'Directions' on 30th October 2018.
R.D. DHANUKA, J.
::: Uploaded on - 25/10/2018 ::: Downloaded on - 27/10/2018 02:52:07 :::
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free