Jai Parkash Power Ventures Ltd. now known as Himachal Baspa Company Power Limited vs State of H.P. & Anr.
- Citation2017 SCC OnLine HP 2363
Ratio decidendi
The rule this decision rests on
An award under Section 34 of the Arbitration and Conciliation Act, 1996, may be set aside only if it is contrary to the fundamental policy of Indian law, the interest of India, justice or morality, or is patently illegal in a manner that goes to the root of the matter rather than being trivial in nature; such review does not entail re-appreciation of evidence, and the court cannot sit in appeal over the arbitrator's findings and decisions. The provisions of the Indian Evidence Act, specifically Sections 91 and 92, do not apply to arbitration proceedings by virtue of Section 1 read with Section 19 of the Arbitration and Conciliation Act, 1996, which exempts the arbitral tribunal from the obligation to follow the Code of Civil Procedure or the Evidence Act; however, the principles of natural justice requiring fairness and reasonableness must still be observed. A party who executes a written contractual undertaking is bound by its terms, and there is a presumption that it has read and understood the document unless it proves force or fraud; in the absence of any timely challenge to the undertaking or withdrawal of it, the plea that it was executed under economic duress is not available at a later stage. The plea of economic coercion vitiating a contract must be specifically pleaded with full particulars including names, dates, times, and the precise manner of the influence exercised, and must be supported by cogent evidence; a general or vague allegation of coercion raised for the first time in rejoinder without prior notice to the opposing party does not meet the requirements of law and cannot be entertained. An arbitral award signed by a majority of the arbitrators in arbitral proceedings with multiple arbitrators, where all arbitrators have jointly participated in deliberations on crucial questions and there is no express or implied dissent by any arbitrator, satisfies the requirements of Section 29 and Section 31(2) of the Arbitration and Conciliation Act, 1996, and cannot be challenged merely because one arbitrator did not sign certain procedural proceedings. A party that has participated in arbitration proceedings without objection to the procedure adopted is estopped from challenging the award on the ground of procedural irregularity, particularly where it has failed to demonstrate any prejudice resulting from such procedure. A person aggrieving the arbitrator of legal misconduct must show from the record of the proceedings itself that such misconduct vitiated the award and, absent such foundation in the arbitration record, cannot raise the plea of misconduct for the first time in the objection proceedings under Section 34.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA Arb.C. No. 93 of 2016 Reserved on: 01.11.2017 Decided on: 29.11.2017
.
Jai Parkash Power Ventures Ltd. now known as Himachal Baspa Company Power Limited ...Petitioner Versus State of H.P. & Anr. ...Respondents
Coram The Hon'ble Mr.Justice Tarlok Singh Chauhan, Judge. Whether approved for reporting? Yes.
For the petitioner: Mr. R.L. Sood, Sr. Advocate with Mr. Sunil Mohan Goel and Mr. Ashish Jamalta, Advocates.
For the respondents: Mr. Neeraj K. Sharma, Advocate, for
respondent No. 1.
Mr. J.S. Bhogal, Sr. Advocate, with Mr. Suneet Goel, Advocate, for respondent No. 2.
Justice Tarlok Singh Chauhan, Judge
This petition has been filed under Section 34 of the
Arbitration and Conciliation Act, 1996 (for short the Act) against the
award dated 20.05.2016.
2. Brief facts necessary for the adjudication of this petition
are that an Implementation Agreement (Annexure C-2) was entered
into on 01.10.1992 between the petitioner Company with the
government of Himachal Pradesh (Respondent No. 1 herein) for the
implementation of 300 MW Baspa Hydro Electric Project, Stage-II (for
short 'Project'), in District Kinnaur Himachal Pradesh.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 2 3. As per this Implementation Agreement (for short the
'Agreement'), the petitioner being a generating Company was
granted right to establish, own, operate and maintain this project
.
subject to the approval of the Central Electricity Authority, including
transmission system upto Jhakri Sub Station of Nathpa Jhakri Hydro
Electric Project and permission to generate and sell power from the
above mentioned project for an initial period of 40 years from the
date of commissioning of project extendable for further period of 20
years.
4. As per Clauses 6 and 7 of the agreement, the
government was to acquire land for the company, such private
lands within the state of Himachal Pradesh as may be required by
the Company for the construction, operation and maintenance of
the project.
5. Clause 38 contained an arbitration clause wherein it
was provided that all disputes or differences out of or relating to or in
connection with the agreement, which could not be settled
amicably by the parties were to be referred to and settle by
arbitration.
6. Consequent upon the signing of the agreement, a
meeting was held in the office of Chairman of Himachal Pradesh
State Electricity Board (for short 'HPSEB') (Respondent No. 2) on
11.12.1992, wherein, as per para-3 of the record of discussion, it was
mentioned that:
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 3 "It was pointed out that the case for transfer of 48 bighas of land in possession of Himachal Pradesh State Electricity Board to the claimant company had been submitted to the Government for approval and it was decided that 48 bighas of land in possession of HPSEB may be transferred to the
.
petitioner Company w.e.f. 01.01.1993 on lease basis."
7. As per record of discussion, the rate of lease and other
formalities were to be worked out with respondent No. 1 and the
rate of lease was to be applicable from the date when possession of
the land would be handed over to the petitioner.
8. That pursuant to the above, the Chief Engineer
(Projects), HPSEB vide his letter No. CEP/PBT-13/285/92-17974-75
dated 31.3.1993 (Annexure C-4) and letter No. CEP/PBT-13-285-93-
7451 dated 14.10.1993 (Annexure C-5) informed that the lease
charges shall be at the rate of 18% of the market rate per annum.
However, since the market rate had not been determined, the
petitioner deposited ` 50,000/- immediately which were to be
adjusted as and when the market rates were determined by the
Deputy Commissioner, Kinnaur.
9. Thereafter, a Status Review Committee meeting was
held on 25.03.1998 in the office of the Chairman, HPSEB,
(Respondent No. 2), which was attended to by the representatives
of the claimant Company also. The minutes of the said meeting
were circulated by the Chief Engineer (P&M) of the Himachal
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 4
Pradesh State Electricity Board dated 17.04.1998. Para-3 of the said
Minutes of the Meeting reads as under:-
"Land Acquisition:- Shri Aggarwal requested Government of Himachal Pradesh to help in expediting the lease agreement
.
and 48.1 bighas land at Sholtu. In this regard, it was intimated
that as the land belongs to the Department of MPP & Power, necessary formalities with regard to the signing of lease
agreement will be done by Joint Secretary (Board). The Company is to provide necessary lease papers on standard format to the JS (P) through the concerned Deputy Commissioner."
10. In the meanwhile, the petitioner company which was
earlier known as M/s Jaiparkash Industries Ltd. came to be changed
to that of M/s Jaiparkash Hydro Power Limited (JHPL)
11. Consequent to the aforesaid meeting, land measuring
48 bighas and 1 biswa i.e. 03-61-57 hectares comprised in Khasra No.
87, 88, 94, 97, 107, 121/1, 195, 197, 199, 200, 201, 202, 203, 204, 205,
209, 210, 211, 211/1, 228, 235, 242, 257, 207, 216, 217 & 218 kitta 27
measuring 3-61-57 hectare in Sholtu, District Kinnaur was handed
over to the petitioner Company on 16.01.1993. Later on land
measuring 27 bighas 7 biswas (02-04-20 hectares) comprised in
Khasra No. 99, 100, 194, 190, 187, 188, 189, 189/1, 229, 230, 231, 232,
233, 236, 283, 185, 109, 110, 112, 141, 89, 70, 76, 78, 84, 85, 220, 225,
248, 244, 240, 239, 237, 184, 243, 241, 238, 247, 83 & 250 kitta 40
measuring 2-04-20 hectare was handed over to the claimant
Company on 21.09.1998. Thus, in all, total land measuring 75 bighas 3
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 5
biswas (05-65-77 hectares) at Up Muhal, Punang (Sholtu) was
handed over to the petitioner Company.
12. Earlier to that land measuring 00-69-75 hectares
.
comprised in Khasra No. 425, 426, 427, 428, 429, 430, 431, 432, 434,
435, 436 & 437 Kitta 12 measuring 0-69-75 hectare at Kuppa, District
Kinnaur was also handed over to the petitioner Company on
16.02.1993 by respondent No. 2.
13. According to the petitioner, the aforesaid lands were
handed over to the petitioner Company on the terms and
conditions to be decided by the Himachal Pradesh Government
according to Himachal Pradesh Lease Rules, 1993, for which purpose
it had been constantly pursuing the matter with the government and
eventually the lease deeds were finalized and signed between
respondent No. 2 and the petitioner vide Annexure C-7.
14. As per lease deed so executed, the lease money for the
land measuring 03-61-57 hectares in Sholtu was fixed @ ` 1241/- per
annum on the basis of the rates so fixed by the Deputy
Commissioner, Kinnaur. This lease was for a period of 50 years and
deemed to have commenced from 16.01.1993. Similarly, lease deed
for area measuring 02-04-20 hectares in Punang (Sholtu) was
executed for lease money of `47,458/- per annum, on the bases of
the rates so fixed by the Deputy commissioner, Kinnaur. This lease
deed was for a period of 45 years and was deemed to have
commenced from 21.09.1998. As far as, third lease deed of the land
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 6
at Kuppa is concerned, the lease was for a period of 50 years and
was deemed to have commenced from 16.02.1993. However, lease
amount for this land was not determined as no rates were intimated
.
by the Deputy Commissioner, Kinnaur at the time of signing of the
lease deed and the same was to be intimated subsequently.
15. After signing of the aforesaid lease deed, the petitioner
approached respondent No. 2 for grant of 'No Objection
Certificate' for mortgaging the land with the financial
institutions/banks vide letter dated 04.01.2001. At that stage, it was
insisted by respondent No. 2 that the petitioner will have to give an
undertaking to permit the respondent No. 2 to revise the lease deed
on the ground that the rent had not been fixed by the Deputy
Commissioner in case of one out of three lease deeds. Consequent
upon the signing of such undertaking the respondent No. 2 issued
desired 'No Objection Certificate'.
16. According to the petitioner, as per the undertaking
given by it to respondent No. 2 before issuance of 'No Objection
Certificate', notification permitting the petitioner to mortgage the
land in favour of the financial institutions/banks, revised rates were to
be determined by the Electricity Board by 31.03.2001. However, no
such rates were determined or fixed by the Board or ever informed
to the petitioner Company by respondent No. 2 on or before
31.03.2001. On the contrary, the Chief Engineer (PSP&SO) of the
respondent-Board vide his letter dated 07.08.2001 sent draft lease to
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 7
the petitioner, which according to it, in violation of the terms and
conditions and spirit of lease agreement signed on 30.12.2000, which
was to hold good for the period mentioned therein. Rates/revised
.
rates which were now assessed and mentioned in the draft lease
deeds were extremely on the higher side, exaggerated or without
any basis or justification. The computation, calculation and
formulation of revised lease deeds and the rates contained therein
were done unilaterally and suo motu by respondent No. 2 and the
petitioner was not at all associated in preparation of the said revised
draft lease deeds. The revised draft lease deeds sent by respondent
No. 2 provided for the lease rent as mentioned below:-
Sl. Location Area in Lease money as per Amount as per No. Hectare original lease deeds revised lease signed on 30.12.2000 on deeds on the basis the basis of rates of DC, of HPSEB's own Kinnaur rates sent on 07.08.2001
1. Sholtu (Patch 03-61-57 ` 1241/- p.a ` 2,24,033/- p.a. No.1)
2. Sholtu 02-04-20 ` 47,458/- p.a. ` 2,48,641/- p.a
(Patch No.2)
3. Land at 00-69-75 Amount not intimated by ` 58,270/- p.a. Kuppa DC, Kinnaur at the time of
signing of lease deeds. It was to be intimated later on.
17. According to the petitioner, written undertaking
furnished by it as a principal condition for issuance of 'No Objection
Certificate' by respondent No. 2 did not confer upon it any arbitrary
right to increase the lease amount upto 180 times on the originally
fixed amount and, therefore, in these circumstances, it refused to
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 8
accept the arbitrary conditions and took up the matter with the
Chairman of the respondent-Board, who, in turn, directed the Chief
Engineer (PSP) of respondent No. 2 to get the rates fixed as per the
.
Himachal Pradesh Lease Rules, 1993.
18. Accordingly, the Chief Engineer (PSP) addressed a letter
to the Deputy Commissioner, Kinnaur dated 24.08.2002, who, in turn,
sent the requisite rates vide his letter dated 14.11.2002. However, the
petitioner did not receive any information in this behalf from the
respondent-Board and, therefore, it independently took exercise to
work out the lease rent amount as per calculated rates given by the
Deputy Commissioner, Kinnaur. According to the petitioner, the
lease rent amount worked out to ` 14,73,455/- up to 31.12.2013.
19. In addition to the above said amount of lease, the
petitioner also took on rent basis accommodations from respondent
No.2, the details whereof are as under:-
a) Four sets of one room each at Sholtu
b) One set of three rooms at Sholtu.
c) Repair shop at Kuppa.
d) Store shed at Kuppa.
20. Respondent No. 2 vide its letter dated 13.08.2003 urged
the petitioner to deposit the lease rent of the aforesaid
accommodation, which according to the petitioner was found to
be higher side and accordingly it made a representation to this
effect.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 9 21. The petitioner has drawn a comparative table of the
rent worked out by HPSEB and the rent worked out by HPPWD to
show that the rates are excessive, which reads thus:-
.
Sl. Name of Building Plinth Annual Rent Annual Rent No. Area in as Charged as per HPPWD
Sqm. by HPSEB norms 1. Store shed at Kuppa (The 126.90 80,867/- 19,195 building was totally damaged on 31.03.2011 due to land slide
during the snowfall.) 2. Repair shop at Kuppa 61.08 72,948/- 9,208/- 15,789/- 3. Three room one set at Sholtu 70.00 21,550/- 10,794/- 4. One room four set at Sholtu 134.00 46,164/- 20,970/-
22. However regardless of the representation, respondent
No. 2 issued a final notice asking the petitioner to deposit lease rent
amounting to ` 3,95,40,698/- up to 31.12.2009 vide letter dated
09.09.2010.
23. In response, the petitioner made representation to the
Chairman of respondent No. 2 vide letter dated 18.09.2010 for
review of the amount as the same was unreasonable. However,
without acceding to the request of the petitioner, respondent No. 2
deducted the aforesaid amount of ` 3,95,40,698/- from the payment
of energy bill of the petitioner for the month of September, 2010 for
which according to the petitioner there was no such provisions in the
Power Purchase Agreement or the Implementation Agreement.
24. Subsequently, on 14.03.2014, respondent No. 2 again
sent a bill of lease rental charges of land and accommodation at
Sholtu and Kuppa amounting to `12,49,59,514/- for the period
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 10
01.01.2010 to 31.12.2013. This constrained the petitioner to take up
the matter with respondent No. 2 and the government on various
occasions from time to time. However, respondent-Board did not
.
accede to the said requests and kept on issuing bills for the lease
rental charges.
25. This constrained the petitioner to approach this Court by
way of petition under Section 9 of the Arbitration and Conciliation
Act, 1996 for interim measures of protection. This petition came up
for consideration on 10.12.2014 and instead of passing any interim
order, the Court proceed to appoint Arbitral Tribunal to adjudicate
the dispute between the parties, in view of the Arbitration Clause in
the Implementation Agreement.
26. Consequent upon the matter having been referred to
the Arbitral Tribunal, the petitioner filed its claim, however, during the
pendency of the claim petition, the respondent No. 2 deducted an
amount of `12,49,59,514/- as the lease rental from the energy bill,
constraining the petitioner to file supplementary claim.
27. The details of the claim including the supplementary
claim filed by the petitioner reads thus:-
Claim No. 1 - Declare the lease rentals as are being asked to be deposited by the respondent No. 2 HPSEBL for the land and accommodation taken on lease to be bad in law, exorbitant, exaggerated and not in consonance with the H.P. Lease Rules, 1993 as also H.P. Lease Rules, 2013 and prevailing market rates of the leased land and quash annexure C-19 and also set aside Bill dated 14.03.2014 (Annexure C-17), i.e.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 11
bill of lease rent charges of land and accommodation at Sholtu & Kuppa amounting to Rs.12,49,59,514/- from 01.01.2010 to 31.12.2013.
Claim No. 2 - Declare the act of the respondent No. 2 of fixing the lease rental of the land measuring 3-61-57 hectares
.
comprised in Khasra No. 87, 88, 94, 97, 107, 121/1, 195, 197,
199, 200, 201, 202, 203, 204, 205, 209, 210, 211, 211/1, 228, 235, 242, 257, 207, 216, 217 & 218 Kita 27 and of land measuring
02-04-20 hectares comprised in Khasra No. 99, 100, 194, 190, 187, 188, 189, 189/1, 229, 230, 231, 232, 233, 236, 283, 185, 109, 110, 112, 141, 89, 70, 76, 78, 84, 85, 220, 225, 248, 244, 240, 239, 237, 184, 243, 241, 238, 247, 83 & 250 Kita 40 as arbitrary,
without jurisdiction for the reason that the Deputy Commissioner, Kinnaur had already fixed the lease rentals for these pieces of land and the respondent No. 2 HPSEBL had
no authority to fix arbitrarily exorbitant rates for these pieces
of land leased to the claimant and that too behind the back of the claimant.
Claim No. 3 - Direct the respondent No. 2 HPSEBL to refund to the claimant an amount of Rs.3,95,40,698/- which was
wrongly and illegally deducted by respondent No. 2 from the energy bills of claimant company for the month of September, 2010 alongwith interest @ 18% per annum.
Claim No. 4 - Declare the deduction made from energy bills
by respondent No. 2 Board of Rs.12,49,59,514/- as lease rental from 01.01.2010 to 31.03.2013 and communicated to the claimant company, vide letter dated 06.02.2015 as annexure
C-21 as arbitrary, illegal and wholly unjustified since the respondent no. 2 is not entitled to the said amount. As such the said deduction by respondent No. 2 Board is bad in law and the claimant company is entitled to be refunded back the said amount of Rs.12,49,59,514/- from the date of recovery/adjustment till the date of actual payment of 18% per annum.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 12 28. Respondent No. 1 - State of Himachal Pradesh despite
service did not put in appearance and was proceeded ex parte
vide order dated 18.07.2015, while respondent No. 2 appeared and
.
contested the petition by filing reply wherein it raised various
preliminary issues/points to the effect that the statement of claim
had not been filed by a competent person on behalf of the
petitioner company, therefore, the same was liable to be dismissed.
It was stated that the claim petition was hopelessly barred by time
and the petitioner was stopped by its own acts, deeds and conduct
from filing the present claim petition and that the petitioner did not
have any cause of action against respondent No. 2.
29. In addition thereto, a preliminary objection was also
taken to the effect that declaration as sought by the petitioner
being a specific relief could only be granted by the regular Court
and the Tribunal, therefore, had no jurisdiction to try the case on this
count.
30. On merit, respondent No. 2 denied that the land, which
was transferred by the petitioner, was purchased by the State of
Himachal Pradesh on the payment of `2,08,053/- as alleged by the
petitioner and it was clarified that the land was in fact purchased by
respondent No. 2 itself from the Industry Department for a total
consideration of ` 5,29,564.65 paise. It was denied that the terms of
the lease were to be decided in accordance with the H.P. Lease
Rules, 1993 and it was rather clarified that while handing over the
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 13
land to the claimant, it had been made clear that "Rate of the lease
and other formalities can be worked out in consultation with the
Government of H.P. as per minutes of meetings dated 11.12.1992
.
(Annexure C-3)". It was further stated that the lease deed dated
30.12.2000 (Annexure C-7), was followed by an undertaking on the
same day i.e. 30.12.2000 (Annexure C-10). It was further stated that
after execution of the lease deed the petitioner had sought to
secure permission/no objection of respondent No. 2 to mortgage the
lease rights with financial institutions, which it would have not done
for the meagre value of the land as is being claimed by the
petitioner and it is on this count that petitioner had very cleverly not
mentioned the amount for which it had mortgaged the lease hold
rights with the financial institutions.
31. It was further submitted that even though the possession
of two tracts of land had been taken in 1993 and one part in 1998
respectively, yet the petitioner kept on delaying the execution of the
lease despite repeated requests from the respondent. The
undertaking (Annexure C-10) was given by the petitioner on the
same day i.e. 30.12.2000 when the lease deed was signed and in
terms thereof, respondent No. 2 was to fix the lease rates by
31.03.2001. However, the said rates were fixed on 31.05.2001 vide
annexure R-3. It has been specifically denied that the draft lease
deed sent vide letter dated 07.08.2001 was in violation of the terms
of the original agreement. In terms of the undertaking executed by
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 14
the petitioner the rates of the lease were to be fixed by respondent
No. 2 in respect of three parcels of land including built up portion.
After the rates had been fixed the petitioner did not
.
challenge/question the same at any point of time as the petitioner
had failed to pay due and outstanding amount. It was averred that
respondent No. 2 in the given circumstances was well within its right
to recover the said amount by deducting the same from the energy
bills of the petitioner.
32. The petitioner filed rejoinder wherein the contents of the
reply were denied and the contents of the petition were reiterated.
It was reiterated that the statement of claim had been filed by a
competent person. Likewise, the legal pleas as raised by respondent
No. 2 in its reply were also denied. It was reiterated that the rates of
the lease of the land which was handed over to the petitioner were
to be decided in accordance with the Himachal Pradesh Lease
Rules, 1993. It was also submitted that the undertaking filed by the
petitioner was being read out of context by the replying respondents
wherein the intent of the undertaking and the same had been given
by the petitioner on the instance of the respondents as 'No
Objection Certificate' was issued by it to mortgage the land to
financial institutions for achieving financial closure of the project itself
explains that the undertaking was to the satisfaction of the
respondents. It was further reiterated that the lease amount which
had been arrived at by respondent No. 2 were not only on higher
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 15
side but also arbitrary and even arrived at unilaterally by respondent
No. 2 by applying parameters unknown to law.
33. The petitioner also annexed copy of award dated
.
05.05.2011 in support of his contention that the actual cost of land
was only `42,567/- per biswa and not `1,04,000/- per biswa as had
been worked out by respondents that too not on the basis of the
actual value of ` 42,567/- as find mentioned in the award though
itself to be the matter of settlement arrived at between owner of the
land and HPPCL for whose benefit land was acquired wherein the
mutually settled rate of `1,04,000/- per biswa, which in no
circumstance can be said to be the actual value which remain at `
42,567/-. The petitioner has further reiterated that respondent No. 2
had no jurisdiction to deduct the lease amount from the energy bills
of the petitioner.
34. On the basis of the aforesaid pleadings, the Arbitral
Tribunal proceeded to determine the lis wherein only the petitioner
led evidence while respondent No. 2 did not chose to lead
evidence.
35. After recording evidence of the petitioner and
evaluating the same, the learned Tribunal at the time of its final
decision formulated the following points for determination:-
1. Whether the claim as filed on behalf of the claimant company is not by a competent person, if so, what is the effect?
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 16 2. Whether the relief of declaration as sought by the claimant is not arbitral and the Tribunal has no jurisdiction to adjudicate upon the same?
3. Whether the claim is barred by time?
4. Whether the claimant is estopped by its act and conduct
.
from filing the present claim?
5. Whether the claimant is entitled to the relief as laid under claim No. 1 and claim No. 2?
6. Whether respondent No. 2 was justified in deducting the amount of Rs.3,95,40,698/- and Rs.12,49,59,514/- respectively from the energy bills of the claimant company as alleged and if not whether the amounts are
liable to be refunded to the claimant?
36. Points No. 1, 3, 4, 5 and 6 were answered in favour of
respondent No. 2 and against the petitioner, whereas point No. 2
was answered in favour of the petitioner and against respondent No.
2.
37. Admittedly, respondent No. 2 has not assailed the
finding on point No. 2 and the same has thus attained finality.
I have heard learned counsel for the parties and have
gone through the records of the case.
Scope and ambit of Section 34
38. The scope and ambit of Section 34 of the Act has been
considered by a Coordinate Bench of this Court in Arbitration Case
No. 60 of 2015, titled as Sh. Ashok Kumar Thakur versus State of
Himachal Pradesh & Anr., decided on 09.03.2016, 2016 (2) SLJ 640 =
2016 (2) ILR HP, and it was observed as under:-
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 17 "3. It is settled proposition of law that award can be set aside only within the exceptions stipulated under Section 34, which has to be read in conjunction with Section 5 of the Act, wherein it is provided that no judicial authority shall intervene with the award, save and except as provided in Part - I of the
.
Act, wherein Section 34 also finds place.
4. Courts cannot proceed to comparatively adjudicate merits of the decision. What is to be seen is as to whether
award is in conflict with the Public Policy of India. Merits are to be looked into only under certain specified circumstances i.e. being against the Public Policy of India, which connotes public good and public interest. Award which is ex facie and
patently in violation of the statutory provisions cannot be said to be in public interest.
5. In Oil & Natural Gas Corporation Ltd. Vs. Saw Pipes Ltd.
(2003) 5 SCC 705 the Court reiterated the principle laid down
in Renusagar Power Co. Ltd. vs. General Electric Co., 1994 Supp (1) SCC 644 holding that the award can be set aside if it is contrary to: (a) the fundamental policy of Indian law; or (b) the interest of India; or (c) justice or morality, or (d) in
addition, if it is patently illegal. However, such illegality must go to the root of the matter and if it is trivial in nature, then it cannot be said to be against public policy. Only such of
those awards which, being unfair and unreasonable, shocks
the conscious of the court can be interfered with.
6. The principles continued to be reiterated by the apex
Court in McDermott International Inc. vs. Burn Standard Co.
Ltd. (2006) 11 SCC 181 and Centrotrade Minerals & Metals Inc. vs. Hindustan Copper Ltd. (2006) 11 SCC 245.
7. Eventually in DDA vs. R. S. Sharma and Co. (2008) 13 SCC 80 the Court culled out the following principles:
"21. From the above decisions, the following principles emerge:
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 18 (a) An award, which is
(i) contrary to substantive provisions of law; or
(ii) the provisions of the Arbitration and Conciliation Act, 1996; or
(iii) against the terms of the respective contract; or
.
(iv) patently illegal; or
(v) prejudicial to the rights of the parties;
is open to interference by the court under Section 34(2) of the Act.
(b) The award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality.
(c) The award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court.
r (d) It is open to the court to consider whether the award is against the specific terms of contract and if so, interfere with
it on the ground that it is patently illegal and opposed to the public policy of India."
8. Recently the apex Court in Associate Builders vs. Delhi
Development Authority (2015) 3 SCC 49 has further explained the meaning of the words "fundamental policy of Indian
law"; "the interest of India"; "justice or morality"; and "patently illegal". Fundamental policy of Indian law has been
held to include judicial approach, non violation of principles of natural justice and such decisions which are just, fair and reasonable. Conversely such decisions which are perverse or
so irrational that no reasonable person would arrive at, are held to be unsustainable in a court of law. The Court observed that:-
"29. It is clear that the juristic principle of a "judicial approach" demands that a decision be fair, reasonable and objective. On the obverse side, anything arbitrary and
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 19
whimsical would obviously not be a determination which would either be fair, reasonable or objective.
30. The audi alteram partem principle which is undoubtedly is a fundamental juristic principle in Indian law is also contained in Sections 18 and 34 (2)(a) (iii) of the Arbitration
.
and Conciliation Act. These sections read as follows:
"18. Equal treatment of parties. - The parties shall be treated with equality and each party shall be given
a full opportunity to present his case.
* * *
34. Application for setting aside arbitral award. - (1) * * *
(2) An arbitral award may be set aside by the court only if -
(a) the party making the application furnishes proof that -
r ***
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case'"
31. The third juristic principle is that a decision which is
perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where:
(i) a finding is based on no evidence, or
(ii) an Arbitral Tribunal takes into account something
irrelevant to the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision,
such decision would necessarily be perverse."
9. Further, in the very same decision, while relying upon Excise and Taxation Officer-cum-Assessing Authority vs. Gopi Nath & Sons, 1992 Supp (2) SCC 312; Kuldeep Singh vs. Commr. of Police, (1999) 2 SCC 10; and P. R. Shah, Shares & Stock Brokers (P) Ltd. vs. B.H.H. Securities (P) Ltd., (2012) 1 SCC 594, the Court clarified the meaning of the expression 'perverse'
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 20
so as to include a situation where the Arbitrator proceeds to ignore or exclude relevant material or takes into consideration irrelevant material resulting into findings which are so outrageous, that it defies logic and suffers from the vice of irrationality. What would be "patent illegality" was
.
clarified in the following terms:-
"42. In the 1996 Act, this principle is substituted by the "patent illegality" principle which, in turn, contains three
subheads:
42.1. (a) A contravention of the substantive law of India would result in the death knell of an arbitral award. This must be understood in the sense that such illegality must go to the root of the matter and cannot be a of a trivial nature.
This again is really a contravention of Section 28(1)(a) of the Act, which reads as under:
"28. Rules applicable to substance of dispute. - (1) Where the place of arbitration is situated in India - r (a) in an arbitration other than an international commercial arbitration, the Arbitral Tribunal shall
decide the dispute submitted to arbitration in accordance with the substantive law for the time being in force in India;"
42.2. (b) A contravention of the Arbitration Act itself
would be regarded as a patent illegality - for example if an arbitrator gives no reasons for an award in contravention of Section 31(3) of the Act, such award will be liable to be set aside.
42.3.(c) Equally, the third subhead of patent illegality is really a contravention of Section 28(3) of the Arbitration Act, which reads as under:
"28. Rules applicable to substance of dispute. -
(1) - (2) * * *
(3) In all cases, the Arbitral Tribunal shall decide in accordance with the terms of the contract and shall take into account the usages of the trade applicable to the transaction."
This last contravention must be understood with a caveat. An Arbitral Tribunal must decide in accordance with the terms of the contract, but if an arbitrator construes a term of the contract in a reasonable manner, it will not mean that the award
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 21
can be set aside on this ground. Construction of the terms of a contract is primarily for an arbitrator to decide unless the arbitrator construes the contract in such a way that it could be said to be something that no fair-minded or reasonable person could do.
43. In McDermott International Inc. vs. Burn Standard Co. Ltd. (2006) 11 SCC 181, this Court held as under:
.
"112. It is trite that the terms of the contract can be express or implied. The conduct of the parties would also be a relevant factor in the matter of construction of a contract. The
construction of the contract agreement is within the jurisdiction of the arbitrators having regard to the wide nature, scope and ambit of the arbitration agreement and they cannot be said to have misdirected themselves in passing the award by taking
into consideration the conduct of the parties. It is also trite that correspondences exchanged by the parties are required to be taken into consideration for the purpose of construction of a contract. Interpretation of a contract is a matter for the arbitrator to r determine, even if it gives rise to determination of a question of law. [See: Pure
Helium India (P) Ltd. v. Oil and Natural Gas Commission, (2003) 8 SCC 593 and D.D. Sharma v. Union of India, (2004) 5 SCC 325].
113. Once, thus, it is held that the arbitrator
had the jurisdiction, no further question shall be raised and the court will not exercise its jurisdiction unless it is found that there exists any bar on the face of the award."
44. In MSK Projects (I) (JV) Ltd. v. State of Rajasthan, (2011) 10 SCC 573, the Court held:
"17. If the arbitrator commits an error in the construction of the contract, that is an error within his jurisdiction. But if he wanders outside the contract and deals with matters
not allotted to him, he commits a jurisdictional error. Extrinsic evidence is admissible in such cases because the dispute is not something which arises under or in relation to the contract or dependent on the construction of the contract or to be determined within the award. The ambiguity of the award can, in such cases, be resolved by admitting extrinsic evidence. The rationale of this rule is that the nature of the dispute is something which has to be determined outside and independent of what appears in
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 22
the award. Such a jurisdictional error needs to be proved by evidence extrinsic to the award. [See: Gobardhan Das v. Lachhmi Ram, AIR 1954 (SC) 689, Thawardas Pherumal v. Union of India, AIR 1955 (SC) 468, Union of India v. Kishorilal Gupta & Bros., AIR 1959 (SC) 1362, Alopi Parshad & Sons Ltd. v. Union of India, AIR 1960 (SC) 588, Jivarajbhai Ujamshi
.
Sheth v. Chintamanrao Balaji, AIR 1965 (SC)
214 and Renusagar Power Co. Ltd. v. General Electric Co., (1984) 4 SCC 679.]"
45. In Rashtriya Ispat Nigam Ltd. v. Dewan Chand
Ram Saran, (2012) 5 SCC 306, the Court held:
"43. In any case, assuming that Clause 9.3 was capable of two interpretations, the view taken by the arbitrator was clearly a possible if not a plausible one. It is not possible to say that the
arbitrator had travelled outside his jurisdiction, or that the view taken by him was against the terms of contract. That being the position, the High Court had no reason to interfere with the award and substitute its view in place of the interpretation accepted by the arbitrator.
44. The legal position in this behalf has been
summarised in para 18 of the judgment of this Court in SAIL v. Gupta Brother Steel Tubes Ltd., (2009) 10 SCC 63 and which has been referred to above. Similar view has been taken later in Sumitomo Heavy Industries Ltd. v. ONGC Ltd.,
(2010) 11 SCC 296 to which one of us (Gokhale, J.) was a party. The observations in para 43 thereof are instructive in this behalf.
45. This para 43 reads as follows: (Sumitomo case,
(2010) 11 SCC 296, SCC p. 313)
'43. ... The umpire has considered the fact
situation and placed a construction on the clauses of the agreement which according to him was the correct one. One may at the highest say that one would have preferred
another construction of Clause 17.3 but that cannot make the award in any way perverse. Nor can one substitute one's own view in such a situation, in place of the one taken by the umpire, which would amount to sitting in appeal. As held by this Court in Kwality Mfg. Corpn. v. Central Warehousing Corpn., (2009) 5 SCC 142 the Court while considering challenge to arbitral award does not sit in appeal over the findings and decision of the arbitrator, which is what the High Court has practically done in this matter.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 23 The umpire is legitimately entitled to take the view which he holds to be the correct one after considering the material before him and after interpreting the provisions of the agreement. If he does so, the decision of the umpire has to be accepted as final and binding.' " "
.
39. At the outset, it may be observed that even though this
Court held marathon hearings but most of the points as raised by the
petitioner were never raised before the learned Arbitrator and some
of the objections have only been raised for the first time in the oral
arguments before the Court.
No procedure followed by Arbitral Tribunal
40. It is vehemently argued by Shri R.L. Sood, Sr. Advocate,
duly assisted by Mr. Sunil Mohan Goel, Advocate, that the arbitral
award on the face of it, is not sustainable, as the Tribunal has failed
to follow any procedure and even the procedure so followed and
adopted was never informed to the parties. That apart, even the
points of determination were only formulated at the time of
arguments.
41. Section 19 of the Act determines the rules of procedure
of the Arbitral Tribunal, which reads thus:-
"19. Determination of rules of procedure.- (1) The arbitral tribunal shall not be bound by the Code of Civil Procedure, 1908 (2 of 1905) or the Indian Evidence Act, 1872 (1 of 1872). (2) Subject to this Part, the parties are free to agree on the procedure to be followed by the arbitral tribunal in conducting its proceedings.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 24 (3) Failing any agreement referred to in sub-section (2), the arbitral tribunal may, subject to this Part, conduct the proceedings in the manner it considers appropriate. (4) The power of the arbitral tribunal under sub-section (3) includes the power to determine the admissibility, relevance,
.
materiality and weight of any evidence."
42. Noticeably, the petitioner right through the entire
proceedings never ever objected to the procedure being followed
by the Arbitral Tribunal and having participated without any demure
is estopped from laying challenge to the award on this count.
Moreover, the petitioner has also not been in a position to show any
prejudice much less serious prejudice caused to it on account of
procedure followed by the Tribunal which in the instant case was
that of any civil proceeding.
Award not passed by majority
43. It is then argued by the petitioner that the award passed
by the Tribunal cannot be said to be an award by majority as two
members out of three members of the Tribunal were only dummies.
Even otherwise the petitioner was entitled to the benefit of
knowledge, wisdom and experience of all the arbitrators which
should have been reflected in the award. He further argued that in
absence of any joint deliberation, the mere signing of the award by
the two co-arbitrators would not make it an award passed by a
majority. In support of such contention, the petitioner has relied upon
the following judgments:-
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 25 1.Abu Hamid versus Gulam Sarvar, (1918) Cal 865 (866)
2.Sheikh Abdhulla versus MVRS Firm and Sons, 1924 Rangoon 153 (154).
3. Moti versus Sheroo (2009) 6 MHLJ 535
4.Maharashtra State Electricity Distribution Company versus
.
Deltron Electronics, 2016 SCC Online Bom. 9521
5.Maganlal Gangaram vs. Ramaji Bondarji, AIR 1966 Madhya Pradesh 177 D.B.
6. Kuldeep Krishan Sood vs. Gulmohar Tourist Complex, 2012 SCC Online HP 157 DB
7. Maharashtra State Electricity distribution Company Ltd. vs. Deltron Electronics, 2016 SCC Online Bombay 9521
44.
Even these contentions are simply without merit for the
reason that the award is duly signed by the Principal Arbitrator as
also two co-arbitrators. Nowhere have the co-arbitrators or any one
of them expressed even the slightest dissent to the award. The joint
deliberations between the arbitrators are amply proved from the
fact that all the arbitrators have joined in the deliberations and have
attended the important meetings in which the crucial questions for
decision were deliberated. No doubt one of the arbitrators had not
attended or has not signed the proceedings on 20.9.2015, 8.10.2015,
6.12.2015, 17.12.2015 and 15.1.2016 but even on those dates no
crucial questions for decision were deliberated upon. The judgments
relied upon by the petitioner would only apply in case there had
been implied or express dissent or disagreement by any one or both
of the co arbitrators with the Principal Arbitrator. In absence of any
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 26
material to suggest even remotely that there was any dissent, the
judgments relied upon by the petitioner are of no avail.
45. All the authorities as relied upon by the learned counsel
.
for the petitioner only deal with the question that all the arbitrators
must join, act, deliberate and participate in all the proceedings and
must have discussion before making the award. How the ratio laid
down in those judgments helps the petitioner is anybody's guess as
there is nothing even remotely to suggest that there was no joint
deliberation of all the arbitrators before making the award, rather it
has specifically come on record that all the arbitrators had
participated in the effective hearings.
46. In fact, the Hon'ble Bombay High Court in Moti's case
(supra) as was relied upon by the learned counsel for the petitioner
has gone to the extent of holding that even if there was a failure of
one of the arbitrators to sign the arbitral award, the same would not
have any effect on the validity of the award. The reason being that
when the arbitral proceedings have been conducted by all the
arbitrators sitting together as a body and there is a joint participation
of all the arbitrators, then one arbitrator cannot stultify the
proceedings by inaction, though a majority has agreed upon and
signed its award.
47. The learned Division Bench of Bombay High Court has
taken note of the judgment of the Patna High Court in Raghubir
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 27
Pandey and another vs. Kaiilesar Pandey and others, 1945 AIR(Pat)
140. In that case, though all the three arbitrators had jointly
deliberated upon the matter in controversy, one of the arbitrators
.
had not signed the arbitral award though as a matter of fact, he
was in agreement with the view of the majority. The Court rejected
the challenge to the validity of the arbitral award holding that the
fact that one of the arbitrators had not signed the award would not
impinge upon the validity of the award. The Court held thus:-
"......... A review of all these cases satisfies me that the true principle upon which the matter is to be decided is to find in a particular case whether all the arbitrators have joined in rthe deliberation or have attended the important meetings in
which the crucial questions for decision were deliberated. If one or more of the arbitrators have not joined in the deliberation, the award is invalid if it is not signed by an
arbitrator even though he may choose to sign it later on. Again, if all the arbitrators have joined in the deliberation and there is a distinct provision in the agreement between the
parties that the award of the majority will be binding, in that case the failure, deliberate or accidental, of one of the
arbitrators to sign the award will not make it invalid......."
48. The Division Bench further held that signing of the award
was not a judicial act but was merely a record of that which had
already been done in the judicial exercise of the functions of the
arbitrators.
::: Downloaded on - 30/11/2017 23:54:30 :::HCHP 28 49. Similar observations have been made by the Division
Bench of the Hon'ble High Court of Calcutta in Ramtaran Das vs.
Adhar Chandra Das and others, 1953 AIR(Cal) 646 and by Division
.
Bench of the Madras High Court in Johara Bibi and others vs.
Mohammad Sadak Thambi Marakayar and others, 1951 AIR(Mad)
997, wherein the Court held that the signing of the award is only a
formality once it was demonstrated that the arbitrator who refused
to sign the award had taken part in the arbitration proceedings
throughout and was a party to the decision.
50. Section 29 of the Arbitration and Conciliation Act, 1996
provides that - unless otherwise agreed by the parties, in arbitral
proceedings with more than one arbitrator, any decision of the
arbitral tribunal shall be made by a majority of its members.
51. Sub Section (1) of Section 31 provides that an arbitral
award shall be made in writing and shall be signed by the members
of the Arbitral Tribunal. While sub section (2) lays down that the
purposes of sub section (1), in arbitral proceedings with more than
one arbitrator, the signature of the majority of all members of the
Arbitral Tribunal shall be sufficient so long as the reason for any
omitted signature is stated.
52. Indubitably in the present case, the award is unanimous
and there is no dissent by any of the arbitrators. It has also come on
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 29
record that the proceedings were conducted by all the arbitrators
sitting together as a body and there was a joint participation of all
the arbitrators, therefore, none of the judgments as cited by the
.
learned counsel for the petitioner has any application to the fact
situation obtaining in the instant case.
Arbitral Tribunal acted against fundamental Policy of Law
53. Learned senior counsel for the petitioner would then
vehemently argue that learned Tribunal has erred in law and acted
against the declared fundamental policy of law in relying upon the
undertaking obtained from the petitioner by respondent No. 2 as the
same was in violation of Sections 91 and 92 of the Evidence Act as
the lease deed dated 30.12.2000 had been reduced to the form of
a document as required under law, the terms whereof were
protected and governed by Section 91 of the Indian Evidence Act.
As such the undertaking (Annexure C-10) could not have been read
in evidence to permit the respondent to revise/increase arbitrarily
the lease rental mentioned therein. In any case, the lease rental had
to be determined at the then prevailing rates i.e. at the time when
possession of the land was handed over by respondent No. 2 to the
petitioner.
54. On the other hand, Shri J.S. Bhogal, Senior Counsel,
would submit that the undertaking (Annexure C-10) given by the
petitioner authorizing the replying respondent to revise/increase the
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 30
lease rental so executed by the petitioner knowing fully well that the
lease rate on the basis of the rate fixed by the Deputy Commissioner,
Kinnaur were on the lower side compared to the value of the land
.
leased out to the petitioner. The petitioner was also aware that on
account of the fact that there were very few sales in the area, it was
not possible for the Deputy Commissioner, Kinnaur to assess the fair
volition market rate and on that basis the petitioner had out of its
own free will and agreed to have the rate fixed by the answering
respondent. The provisions of the Evidence Act relied upon by the
petitioner are otherwise not applicable to the arbitration
proceedings in terms of Section 19 of the Arbitration and
Conciliation Act and, therefore, reliance placed on such provisions
by the petitioner is totally misplaced. The learned Tribunal has rightly
considered the contention of the petitioner in this regard and
thereafter passed the impugned award, which deserves to be
upheld.
55. Having regard to Section 1 read with Section 19 of the
Arbitration Act, this Court has no difficulty in concluding that the
provisions of the Evidence Act have not been made applicable to
the arbitral proceedings and, therefore, the bar created under
Sections 91 and 92 of the Evidence Act cannot by its own force
apply to the arbitration proceedings. Even though the basic
principle of judicial determination applied to such proceedings,
which would include the principles of natural justice as are required
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 31
to be followed so as to ensure and maintain fairness and
reasonableness of procedure.
56. However, the learned counsel for the petitioner would
.
still maintain that no amount of oral evidence can be permitted to
be led by respondent wherein the terms of the lease deed and
further that Section 92 prohibits only the bearing of the dispositive
operative terms of the document and not the memorandum or
recital of facts contained therein. Therefore, Section 92 is a
substantive law and not a procedural law and consequently Section
92 of the Evidence Act will have application even in respect of
arbitration proceedings and it was, therefore, not open to the
second respondent to place reliance on the so called 'undertakings'
furnished by the petitioner.
57. Even though the learned counsel for the petitioner has
cited a number of judgments like Chanderbhan vs. Ganpatrai and
sons 1944 Cal. 127, Aboobkaker Latif vs. Reception Committee, 1937
Bim. 410, 416, Bengal Jute Mill vs. Lal Chand, 1963 Cal. D.B. 405 and
Roop Kumar vs. Mohan Thedani (2003) 6 SCC 595, in support of his
contentions with regard to scope and ambit of Sections 91 and 92 of
the Evidence Act, however, he has failed to convince this Court as
to how the provisions and thereafter the ratio of the judgment would
apply to the facts of the instant case, particularly, when it is not the
case of the petitioner that it did not execute the undertaking
(Annexure C-10) on 30.12.2000 thereby undertaking to pay the lease
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 32
rental to respondent No. 2 at the rate as would be determined by
respondent No. 2 as is evident from clause 1 of the undertaking
which reads thus:-
.
"The lessee shall pay the lease rental to Himachal Pradesh
State Electricity Board at the rates as shall be determined by the Himachal Pradesh State Electricity Board by 31st March, 2001. Lease rentals shall be payable by lessee for the period
commencing from the date of handing over of the possession of land to the lessee."
58. As has rightly been observed and taken note of by the
Tribunal, the petitioner had never questioned the undertaking and
the only protest made by it vide its letter dated 18.09.2010 and even
thereafter was with regard to levy of compound interest @ 16% per
annum as would be evident from perusal of the aforesaid letter. The
relevant portion whereof reads thus:-
"1) Levy of Compound interest @ 16% per annum:
A copy of Clause 19 of the Implementation Agreement is
enclosed herewith as Annexure -"B". The levy of compound interest @ 16% is applicable to the one time payments
regarding investigation and infrastructure works of the Project. It is not applicable to recurring payments such as
lease rent, the payment of which is to be governed by lease deeds, in which there is no such provision.
2) In the discussions of various meeting held with the Committee constituted by HPSEB, we had pointed out that cost of construction of 22 KV Transmission Line from Jeori to Nigulsari, Nigulsari to Nichar and Nichar to Sholtu costing Rs.3,18,277.50 had been included in the cost of the land for working out of lease rent. We have requested this to be
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 33
deleted. Similarly escalation has also been added on watch and ward establishment charges, which is unreasonable."
59. Notably, thereafter even in September, 2010, the
petitioner did not question the deduction of ` 3,95,40,698/- made by
.
respondent No. 2 as is clearly evident from the letter dated
14.12.2010 addressed by the petitioner to respondent, which reads
thus:-
"We are to bring to your kind notice that n amount of Rs.3,95,40,698/- has been deducted from our energy bill for
the month of Sept.' 2010. This deduction is not acceptable to us, as the issue of lease rent of HPSEB land and accommodation at Sholtu and Kuppa is under dispute and
yet to be finalized.
In this connection, a meeting was held with the Chief Engineer (Project-cum-Arb.) and other Officers of HPSEB Ltd. on 12.11.2010. Next meeting is now scheduled to be held on 19th January 2011. The payment for energy bill for the month
of Sept.' 2010 has been received by us under protest."
Pending final decision of the above issue, we request you to kindly make us the payment of Rs.3,95,40,698/- alongwith up-
to-date interest at the earliest.
60. Even though a faint protest was made by the petitioner
vide communication dated 14.12.2010 (Annexure C-16) but no steps
were taken by it to assail such recoveries and it is only in the year
2014 when the rentals were increased, the appellant approached
the Court by raising initially three claims out of which claim of rent
upto the period of September, 2010 being claims No. 2 and 3 were
held to be barred by limitation and as regards claim No. 1 rental
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 34
w.e.f. 2010 to 2014, it was clearly held that the appellant had no
cause of action as it had itself agreed to pay the 18% of the market
value towards the lease amount and this position is not even
.
disputed before the Court.
61. It is settled law that a person who signed a document
which contains contractual terms is normally bound by them even
though he is ignorant of the precise legal effect. (Ref: Bihar State
Electricity Board vs. M/s Green Rubber, AIR 1990 SC 699, Jharkhand
Power Corporation Ltd. vs. ASP Sealing Products Ltd. 2009 (9) SCC
701).
62. In Grasim Industries & others vs. Aggarwal Steel, AIR 2010
SCC 291 (Supp.), it was held that when a person signs a document,
there is a presumption, unless there is proof of force or fraud, that he
has read document property and understood it and only then he
has affixed his signature thereon, otherwise no signature on
document can ever be accepted. It would be difficult to accept
that the parties had signed the document under some mistake. In
particular, businessmen, being careful people (since their money is
involved) would have ordinarily read and understood a document
before signing it. Hence the presumption would be even stronger in
their case.
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 35 Arbitral Tribunal ignored Section 17 of the Registration Act
63. The learned senior counsel for the petitioner would then
bank upon and rely on the provisions of Section 17 of the Registration
.
Act to canvass that the subsequent and unregistered documents in
the teeth of registered documents could not be looked into and
moreover it is settled that a document which varies the essential
terms of the existing lease deeds such as the amount of rent must be
registered. In support of such contention he has cited the following
judgments:-
r1. Atul Krishna Bose vs. Zahed Mandal, 1941 Cal 102 (103 Sec 91)
2. Brahama Nand vs. Roshni Devi, 1989 HP Page 11
3. Lalit Mohan Gosh vs. The Gopali Chuck Coal Company (1911-12) 16 Cwn 55
4. Sunil Kumar Roy vs. Bhwara Kankanee Colories Limited
64. However, this question need not be gone into as the
same was neither raised before the Arbitrator nor does it find
mention in the memorandum of objection.
65. Even otherwise invoking of applicability of Section 17 of
the Registration Act is not a pure question of law and is a mixed
question of fact and law, therefore, in absence of any foundation,
this question cannot be gone into and is clearly an after thought.
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 36 Legal misconduct
66. It is then vehemently argued by the learned counsel for
the petitioner that the learned Arbitrators by ignoring and rejecting
.
the registered lease deed and further by not considering relevant
papers and documents have misconducted themselves. In support
of such submissions, reliance is placed on following judgments:-
1. Aboobaker Latif vs. Reception Committee, 1937 Bombay Page 411 and 414
2. FCI vs. Chandu Constructions (2007) 4 SCC 697
3. K.P. Poulose vs. State of Kerala (1975) 2 SCC 236 (239)
4. Sikkim Subba Associates vs. State of Sikkim, 2001 (5) SCC 629
5. Associate Builders vs. Delhi Development Authority
(2015) 3 SCC 49
67. A person urging the grounds of misconduct has to satisfy
the Court from the record of the arbitral proceedings that there has
been legal misconduct on the part of the arbitrator as a
consequence of which the award came to be vitiated. The question
of adducing any kind of oral evidence to substantiate the plea or
stand does not arise, it has to be shown from the proceedings
carried on before the arbitrator and the evidence adduced before
the arbitrator. However, nonetheless the person aggrieved should
have at least raised the plea of misconduct in the objection petition
under Section 34 of the Act. In absence of any grounds, I am afraid
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 37
that the ground of legal misconduct cannot be permitted to be
raised for the first time in arguments.
Novation of Contract
.
68. It is then contended by the petitioner that the Arbitrator
while answering point No. 3 have decided that there was novation
of contract when the petitioner executed undertaking (Annexure C-
10) subsequently to the execution of the lease deed. It is contended
that the undertaking at best was a condition subject to the
determination of the lease rental which had to be positively done
and conveyed on or before 31.03.2011.
69. I am afraid that even such contention on behalf of the
petitioner is not tenable as the petitioner out of his own volition and
free will has executed the undertaking even though the petitioner
would contend that it was on account of economic duress and
coercion that it was forced to execute such undertaking.
70. As already observed above, the petitioner has virtually
never objected to or disowned the undertaking more specifically
before the competent Court within the prescribed period of
limitation and therefore in absence of any challenge that too within
the prescribed period such plea is clearly not tenable at this stage.
71. That apart, it would be noticed that in the instant case
there were no sale exemplars and the three lease deeds so
executed were only as a temporary measures because the actual
amount was only to be worked out later on as is clearly evident from
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 38
the letter dated 14.10.1993 (Annexure C-5). The rates were
determined and communicated to the petitioner vide letter dated
07.08.2001 (Annexure C-11) alongwith which three drafts of
.
supplementary lease deeds were also annexed.
72. Admittedly, it was the petitioner who neither executed
the sale deed nor sought legal recourse either against the
undertaking so furnished by it or against the action of the
respondents asking it to execute the supplementary lease deed in
terms of the undertaking so furnished by it. Therefore, in such
circumstances all the pleas as are now being sought to be raised, be
it with respect to the legal misconduct, estoppels, undue investment,
applicability of Sections 91 and 92 of the Evidence Act, Section 17 of
the Registration Act, misconduct of the arbitrator etc., are nothing
but clearly an afterthought.
73. It needs to be reiterated that nowhere in the petition,
the plea of financial duress being raised nor the undertaking
(Annexure C-10) being questioned. Even the objections raised by the
petitioner in its letter dated 14.04.2010 Ex.RX-1 is with respect to the
bill of lease rental amounting to ` 3,95,40,698/- up to 31.12.2009 and
even thereafter no steps were taken by the petitioner to assail the
demand so raised.
74. On the other hand, the letter dated 31.01.2007 Ex. RX-6
clearly shows that a bill amounting to ` 2,19,01,490/- was prepared
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 39
against the petitioner for which again no lawful recourse was taken
by the petitioner within the prescribed time.
Restitution and unjust enrichment
.
75. At this stage, it may be observed that the petitioner has
also taken up the plea of restitution and unjust enrichment, but I
really wonder how such plea is available to the petitioner.
76. Admittedly, the petitioner has not placed on record any
document on record to even remotely indicate as to what was the
actual loan amount availed by it on the three properties that had
been leased out by respondent No. 2 in its favour, so that the
Arbitrator or for that matter this Court could get a fair idea of the
market value of the properties. After all it was these documents
which alone could have gone a long way and proved the actual
market value.
77. This is despite the fact that respondent No. 2 had served
upon the petitioner a notice under Order 12 Rule 8 read with Section
151 CPC calling upon it to produce documents, wherein, apart from
the original lease deed dated 31.12.2000, respondent No. 2 had
asked the petitioner to produce the documents pertaining to the
monetary assistance given to it by financial institutions/banks against
the leased properties.
78. No doubt, reply was filed to this application but even
therein the petitioner had only stated that it was not in a position to
produce original lease deed dated 31.12.2000 and as regards the
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 40
other documents regarding financial assistance it was stated that
these documents have no relevance whatsoever with the issue.
79. Obviously, the petitioner has concealed material
.
documents or else there was no reason why it should have not
produced the desired documents and then furnished a reply as if it
was the adjudicatory authority. Therefore, in the given
circumstances, the Court essentially is required to draw an adverse
inference against the petitioner for withholding the best evidence.
Would the petitioner have really been prejudiced by the
undertaking whereby it had been asked to cough-up more amount
than the one agreed to, then there was no occasion why the
petitioner would not have produced these documents, more
particularly, in teeth of the allegation of respondent No. 2 that the
properties valued therein was about ` 70-80 crores. This further
assumes significance as the parties are ad idem that the rate of rent
as per the lease deed was to be worked out @ 18% of the cost of the
land. If respondent No. 2 had charged more than this amount then
nothing prevented the petitioner from producing cogent and
convincing evidence to this effect. However, having deliberately
and willfully withheld the best evidence, the petitioner cannot claim
any relief and can blame no one except itself.
Award against Public Policy of India
80. The petitioner would then argue that the award is
declared against the public policy of India by contending that the
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 41
award passed by the learned Tribunal below is blatant being against
the statutory provisions, thereby violating the fundamental policy of
Indian law and therefore deserves to be set aside.
.
81. This contention is clearly without any merit as this Court
has already observed that the majority of the objections as raised by
the petitioner are nothing but an afterthought and otherwise not
tenable in the eyes of law. It needs to be reiterated that during the
entire course of the arbitration proceedings till the passing of the
award, the petitioner did not raise even a little finger questioning the
procedure being adopted by the Arbitral Tribunal and therefore, the
procedure adopted by the Tribunal is not open to challenge at this
stage.
82. It is more than settled that this Court while deciding an
application under Section 34 of the Act which is in the nature of the
objections to the arbitral award, cannot re-appreciate evidence.
Moreover, it has been established on record that it was pursuant to
the undertaking given by the petitioner that the bills were raised by
respondent No. 2 and such bills except for the levy of compound
interest were never challenged by the petitioner.
83. Further, it is not in dispute that the majority of the
recoveries already stood effected in the year, 2010 while the arbitral
proceedings came to be initiated only in the year, 2014 and was
thus clearly barred by limitation.
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 42 Economic Coercion
84. It is more than settled that burden to prove coercion
and contract lies on the party seeking to deny the contract on the
.
ground of coercion. The plea of coercion is required to be
specifically pleaded and in absence of any pleadings except a
remote mention therein in para 10 of the rejoinder (to which
respondent has no right of rebuttal) such plea is not tenable. It was
incumbent upon the petitioner to have specifically pleaded the
details of such coercion so that respondent No. 2 was required to
answer, must have full details and, therefore, would not be taken by
surprise. Therefore, raising the plea that too for the first time in
rejoinder does not meet and rather falls short of the requirement of
law.
85. In Bishundeo Narain & another vs. Seogeni Rai & others,
AIR (38) 1951 SC 280, the Constitutional Bench of the Hon'ble
Supreme Court observed as under:-
"25. It is also to be observed that no proper particulars have been furnished. Now if there is one rule which is better established than any other, it is that in cases of fraud, undue
influence and coercion, the parties pleading it must set forth full particulars and the case can only be decided on the particulars as laid. There can be no departure from them in evidence. General allegations are insufficient even to amount to an averment of fraud of which any Court ought to take notice, however strong the language in which they are couched may be, and the same applies to undue influence and coercion."
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 43 86. The said principle was followed in a later decision
rendered by another Constitutional Bench of the Hon'ble Supreme
.
Court in Ladli Parshad Jaiswal vs. The Karnal Distillery Co., Ltd. &
others, AIR 1963 SC 1279, wherein it was observed as under:-
"That a plea that a transaction is vitiated because of undue
influence of the other party thereto, gives notice merely that one or more of a variety of insidious forms of influence were brought to bear upon the party pleading undue influence and by exercising such influence, an unfair advantage was obtained
over him by the other. But the object of a pleading is to bring the parties to a trial by concentrating their attention on the matter in dispute, so as to narrow the controversy to precise
issues, and to give notice to parties of the nature of testimony required on either side in support of their respective case. A
vague or general plea can never serve this purpose; the party pleading must therefore be required to plead the precise nature of the influence exercised, the manner of use of the influence,
and the unfair advantage obtained by the other. This rule has been evolved with a view to narrow the issue and protect the party charged with improper conduct from being taken by
surprise. A plea of undue influence must, to serve that dual purpose, be precise and all necessary particulars in support of
the plea must be embodied in the pleading; if the particulars stated in the pleading are not sufficient and specific the Court
should, before proceeding with the trial of the suit, insist upon the particulars, which give adequate notice to the other side of the case intended to be set up."
87. The said principle was again reiterated in Subhash
Chandra Das vs. Ganga Parsad Das, AIR 1967 SC 878 and
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 44
Varanasaya Sanskrit Vishwavidalaya vs. Dr. Raj Kishore Tripathi, AIR
1977 SC 615.
88. Even otherwise the undertaking furnished by the
.
petitioner was consensual because the same was neither
challenged nor withdrawn and this fact has been specifically
admitted by the Joint President of the petitioner company who while
appearing as PW1 has in his cross-examination deposed as under:-
"It is correct the company has not laid any challenge for the undertaking Annexure R-2 before the initiation of present
arbitration proceedings."
89. It is a settled law that there should be clear pleadings
pertaining to coercion and it must be specifically pleaded i.e. the
names, date, time etc., so that the party who is required to answer,
must have full details and is not taken by surprise. That apart, cogent
evidence should be adduced by the party to establish that case.
Lease not in accordance with H.P. Lease Rules, 1993
90. As a last ditch effort, the petitioner would contend that
the lease deeds were to be executed in terms of the H.P. Lease
Rules, 1993 and it was for this precise reason that even the format
upon which the lease deeds were executed was the one prescribed
under the Rules.
91. I am afraid that even this contention is not available to
the petitioner as it has failed to place on record any material which
would even remotely go to indicate that the lease to be executed
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 45
by respondent No. 2 was to be in accordance with H.P. Lease Rules,
1993. To the contrary, respondent No. 2 has led sufficient evidence
on record to the effect that the land which was leased out to the
.
petitioner belongs to it after the same had been purchased from the
Industries department and it was thereafter that the same was
leased out as per mutual understanding of the parties coupled with
the undertaking (Annexure C-10) furnished by the petitioner.
92. In view of the aforesaid discussion, I find no merit in this
petition and the same is accordingly dismissed.
Claim not filed by a competent person
93. However, before parting, it needs to be observed that
the Arbitral Tribunal had decided Point No. 1 relating to the claim not
being filed by competent person against the petitioner. However, I
find the said finding to be unsustainable. PW1 Major General (Retd.)
Shyamdas Chaudhary has placed on record power of attorney
dated 01.08.2000 (Ex.C1) executed in his favour and therefore in
absence of anything to the contrary there was no reason much less
a valid or legal reason for the Tribunal to arrive at the aforesaid
conclusion. Even otherwise, it is more than settled that technical
plea has no place in suits instituted or defended by jurisdic person
like banks, corporation etc. as was so held by the Hon'ble Supreme
Court more than two decades back in United Bank of India vs.
Naresh Kumar, 1996 (6) SCC 660, wherein it was observed as under:-
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 46 "10. It cannot be disputed that a company like the appellant can sue and be sued in its own name. Under Order 6 Rule 14 of the Code of Civil Procedure a pleading is required to be signed by the party and its pleader, if any. As a company is a juristic entity, it is obvious that some person has to sign the
.
pleadings on behalf of the company. Order 29 Rule 1 of the
Code of Civil Procedure, therefore, provides that in a suit by or against a corporation the Secretary or any Director or
other Principal Officer of the corporation who is able to depose to the facts of the case might sign and verify on behalf of the company. Reading Order 6, Rule 14 together with Order 29, Rule 1 of the Code of Civil Procedure it would
appear that even in the absence of any formal letter of authority or power of attorney having been executed a person referred to in Rule 1 of Order 29 can, by virtue of the
office which he holds, sign and verify the pleadings on behalf
of the corporation. In addition thereto and dehors Order 29, Rule 1 of the Code of Civil Procedure, as a company is a juristic entity, it can duly authorise any person to sign the plaint or the written statement on its behalf and this would be
regarded as sufficient compliance with the provisions of Order 6, Rule 14 of the Code of Civil Procedure. A person may be expressly authorised to sign the pleadings on behalf
of the company, for example, by the Board of Directors
passing a resolution to that effect or by a power of attorney being executed in favour, of any individual. In absence thereof and in cases where pleadings have been signed by
one of its officers a Corporation can ratify the said action of its officer in signing the pleadings. Such ratification can be express or implied. The Court can on the basis of the evidence on record, and after taking all the circumstances of the case, specially with regard to the conduct of the trial, come to the conclusion that the corporation had ratified the act of signing of the pleading by its officer."
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP 47 94. In view of the aforesaid discussion, even while
accepting the plea that the claim petition was filed by the petitioner
through a competent person, I, however, find no merit in the
.
application/objections and the same is accordingly dismissed,
leaving the parties to bear their costs. Pending application(s), if any,
stands disposed of.
(Tarlok Singh Chauhan), Judge.
November 29, 2017 sanjeev
r to
::: Downloaded on - 30/11/2017 23:54:31 :::HCHP
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free