When the Central Government remits a matter to the Medical Council of India for compliance verification of deficiencies pointed out in an earlier inspection report, the distinction between "open remand" and "limited remand" as understood within the framework of the Code of Civil Procedure does not apply; the Assessors conducting compliance verification are not constrained to examine only the previously identified deficiencies and may identify and report additional deficiencies that come to their notice during the inspection, provided the scope is not wholly different from the order of remand. An order by the Central Government approving or disapproving a medical college's permission for admission under Section 10-A of the Indian Medical Council Act, 1956 must be a reasoned order that ascribes reasons for the decision; an order that lacks reasons is susceptible to challenge and is not enforceable without the Central Government providing those reasons through a fresh opportunity of hearing to the applicant.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL ORIGINAL JURISDICTION

WRIT PETITION (CIVIL) NO. 502 OF 2017

IQ City Foundation & Anr. Petitioner(s)

Versus

Union of India & Ors. Respondent(s)

JUDGMENT

Dipak Misra, J.

In this Writ Petition preferred under Article 32 of the

Constitution of India the petitioners have prayed for issue of

a writ of certiorari for quashment of the order dated

31.05.2017 passed under Section 10-A of the Indian

Medical Council Act, 1956 (for brevity, ‘the Act”) by the

Secretary, Ministry of Health and Family Welfare, the 1 st

respondent herein, and further issue a direction to the said

respondent to grant permission to the petitioner College for

Signature Not Verified 4th renewal for the academic year 2017-2018 to facilitate Digitally signed by GULSHAN KUMAR ARORA Date: 2017.08.01 11:31:01 IST Reason: admission of the 5th batch (150 students) MBBS Course. 2

2. The expose’ of facts essential for adjudication of the

controversy are that IQ City Medical College attached to the

teaching hospital, namely, IQ City Narayana Multispecialty

Hospital was established in the year 2013 by the petitioners

with an intake of 150 (one hundred and fifty) seats MBBS

Course. The Medical Council of India (MCI) conducted an

inspection and granted the Letter of Permission (LOP) on

15.07.2013 for the establishment of the new medical college

at Burdwan, West Bengal with an annual intake of 150

students with effect from the academic year 2013-14. Vide

letters dated 04.07.2014, 10.06.2015 and 15.12.2015

renewals of permission for the 2 nd (1st renewal), 3rd (2nd

renewal) and 4th (3rd renewal) batches of MBBS students at

the petitioner College for the academic years 2014-15,

2015-16 and 2016-17 respectively were granted by the

respondent No. 1. On 06.07.2016, petitioner-College

submitted its scheme along with the requisite fees for the 4 th

renewal for the academic year 2017-18 which pertains to

admission of the 5th batch of 150 students in MBBS course.

On 09.07.2016, the 2nd respondent informed the College

that the assessment for renewal of permission for the 3

academic year 2017-18 would be undertaken by the

Assessors appointed by it at any time after 15.07.2016 and

the petitioners were asked to fill in the Standard Inspection

Form A, Form B and Declaration Form for the academic

year 2017-18 and keep them ready for scrutiny at the time

of assessment. There was also a direction for submission of

the soft copies of the said Forms. As averred, the petitioners

duly submitted a compact disc containing soft copies of

Form A, Form B and Declaration Form and upon receipt of

the necessary documents, the 2nd respondent constituted a

team of Assessors and directed them to carry out the

assessment inspection of the College. The inspection team,

that is, the Assessors, conducted a surprise inspection of

the College on 03.11.2016 and 04.11.2016. The Assessors

pointed out certain deficiencies to the College and noted the

same in the assessment report dated 04.11.2016. It is put

forth in the Regular Inspection Report that the shortfall in

Teaching Faculty and Resident Doctors were only 4.5% and

3.50% respectively which were well within the prescribed

limit. Two other deficiencies that were pointed out, as

asserted, were completely remediable and were duly 4

remedied by the College. On 22.12.2016 the Executive

Committee of the respondent No. 2 considered the

Assessment Report of the Assessors and decided to

recommend to the respondent No. 1 not to renew the

permission to the College for the 4th renewal for the

academic year 2017-18

3. As further set forth, the 1st respondent by its letter

dated 03.02.2017 communicated to the College the

recommendation dated 28.01.2017 of the respondent No. 2

for disapproving the permission to the College for the 4 th

renewal for the academic year 2017-18 and called upon the

College to submit a detailed point-wise compliance with

documentary evidence. The College was further intimated

about the hearing that was to be held on 09.02.2017 before

the Hearing Committee. A team of representatives of the

College appeared before the Hearing Committee on the date

fixed and submitted the compliance report of the remarks

and observations made by the Assessors of the respondent

No. 2. In the second week of March, 2017, the petitioners

received a copy of order dated 01.03.2017 issued by the 1 st

respondent recording the recommendations/order passed 5

by the Hearing Committee of the respondent No. 1 under

Section 10-A(4) of the Act. The recommendation of the

Hearing Committee was to the effect that the deficiencies

pointed out by the 2nd respondent were not such to warrant

disapproval at that stage. Despite the aforesaid findings of

the Hearing Committee, the 1st respondent, instead of taking

a final decision, referred the matter back to the respondent

No. 2 to review the same in the light of the

recommendations/ findings of the Hearing Committee

alongwith documents submitted by the petitioners and to

furnish its recommendation.

4. On receipt of the said communication, the 2 nd

respondent on 17.03.2017 constituted a team to carry out a

Compliance Verification Assessment of the College. The

team of Assessors instead of carrying out a compliance

verification, on 21.03.2017 conducted a regular inspection

in a random manner and instead of limiting to their scope of

reviewing the compliance of the remarks/observations of the

Hearing Committee proceeded to make a different kind of

assessment.

6

5. It is contended that though the Compliance Inspection

Report was submitted, the Assessors required the College to

submit a representation and accordingly, the College

submitted the necessary representation to the respondent

No. 2. The Assessors, as per the stand of the petitioners,

noted certain deficiencies in their Compliance Verification.

Executive Committee of the respondent No. 2 held its

meeting on 28.04.2017 but Minutes of the meeting were not

uploaded on the official website of the respondent No. 2

until 29.05.2017 and were not communicated to the

petitioners.

6. It is the stand of the petitioners that on 20.05.2017,

the petitioners approached the 1 st respondent and

submitted a detailed representation on that day with regard

to Compliance Verification and deficiencies found by the

Assessors appointed by the respondent No. 2. The 1 st

respondent, by the impugned order dated 31.05.2017,

accepted the recommendation of the 2nd respondent and

rejected the scheme of permission of renewal for the 4 th

renewal (admission of the 5th batch, 150 student) MBBS

Course for the academic year 2017-18. It is alleged that the 7

order dated 31.05.2017 was communicated to the College

on 30.06.2017.

7. A counter affidavit has been filed by MCI contending,

inter alia, that if the permission is granted after 31.05.2017

it has to be for the subsequent academic year as per order

passed by the Court in Dr. Ashish Ranjan and others v.

Union of India & others1 and subsequent orders passed in

the said case. The Hearing Committee, according to MCI,

was constituted by the Central Government and its

members were eminent personalities and considering the

report of Assessors, LOP for the academic year 2017-18 has

been denied. The stand that the renewal has been illegally

rejected is not correct as there are gross deficiencies. It is

the stand of the MCI that question of “open remand” and

“limited remand” does not arise. Once an inspection is

conducted by the Assessors, it has to be done wholly and

appropriately so that the standard of an institution that

imparts medical education is maintained and the said

standard is non-variable. The stand that the Assessors

report dated 21.03.2017 pointed out certain deficiencies

1 (2016) 11 SCC 225 8

which were not mentioned in the previous assessment

report dated 04.11.2016 is neither acceptable nor tenable,

for the reason it is the solemn duty of the Assessors to

ensure that there is no deficiency in the medical college and

they cannot ignore the deficiencies and, therefore, the plea

that it exceeded the mandate is not only mercurial but

wholly inconceivable.

8. We have heard Mr. Mukul Rohatgi, learned senior

counsel for the petitioners, Mr. Maninder Singh, learned

Additional Solicitor General for the Union of India and Mr.

Vikas Singh, learned senior counsel for the MCI.

9. It is submitted by Mr. Rohatgi, learned senior counsel

for the petitioners that the 1st respondent could not have

sent back the matter to the MCI as it was obligatory on its

part to take the final decision and further, it should not

have agreed with the opinion of the Executive Committee, as

the Assessors transgressed the order of remand. That apart,

submits Mr. Rohatgi, there was no justification to take a

decision on the last date, that is, 31.05.2017. 9

10. Mr. Singh, learned senior counsel appearing for the

MCI, referring to Section 10-A of the Act submits that an

institution has to maintain consistency in imparting

education and where major deficiencies are distinctly

evident during compliance verification, an institution cannot

be allowed to lean upon the earlier assessment report.

According to Mr. Singh, institution has to remain ever

compliant and it cannot be in an oscillating position.

According to him, one day it can have faculty members and

remain dutiful to the statute and another day in total

disregard play truant with the provision, for such a

situation would crucify the sanctity of the medical

education.

11. To have a complete projection of the factual matrix, we

think it necessary to refer to the opinion of the Executive

Committee recorded on 22.12.2016 on the Regular

Verification. The said report reads as follows:

“46. Renewal of permission for MBBS course for 5th batch (150 students) IQ City Medical College, Burdwan, West Bengal under West Bengal University of Health Sciences, Kolkata u/s 10A of the IMC Act, 1956 for the academic year 2017-18.

10 Read: the matter with regard to renewal of permission for MBBS course for 5th batch (150 seats) of IQ City Medical College, Burdwan, West Bengal under West Bengal under West Bengal University of Health Sciences, Kolkata u/s 10A of the IMC Act, 1956 for the academic year 2017-18.

The Executive Committee of the Council considered the assessment report (3rd and 4th November, 2016) and noted the following:-

1. Although the number of patients admitted amounted to the bed occupancy of 80% but on actual verification most admissions were found to be fresh and new.

2. Central Library: It is not air-conditioned. Reading room for Residents is not available.

3. Students’ Hostel: In Boys’ hostel, Visitors’ room A.C. study room with Computer & Internet, Recreation room are not available. Hygiene in Girls’ is very poor.

4. Residents’ Hostel: Available accommodation is 48 against requirement of 85.

5. Anatomy department: Available mounted specimens are 45.

6. Pharmacology department: In 1 Demonstration room, there are only 15 chairs with tables.

7. RHTC: Residential accommodation is not available.

8. Other deficiencies as pointed out in the assessment report.

In view of above, the Executive Committee of the Council decided to recommend to the Central Govt. not to renew the permission for admission of 5th batch of 150 MBBS students at IQ City Medical College, Burdwan, West Bengal under 11

West Bengal under West Bengal University of Health Sciences, Kolkata u/s 10A of the IMC Act, 1956 for the academic year 2017-18.”

12. After receipt of the report of the Executive Committee,

the 1st respondent vide communication dated 03.02.2017

enclosing thereto the letter dated 28.01.2017 of respondent

No. 2, intimated the College that:

“Subject: Renewal of Permission for admission of 5th batch of 150 MBBs students for the academic session 2017-18 – Hearing to the applicant u/s 10A(4) of IMC, 1956 – reg.

Sir/Madam

I am directed to forward herewith a copy of MCI’s letter dated 28.01.2017 recommending disapproval in respect of renewal permission at your College for the academic session 2017-18.

2. In pursuance to the provisions contained in Section 10A(4) of IMC Act, 1956, it has been decided to grant you hearing on 09.02.2017 at 10:30 AM by the Committee constituted by this Ministry for this purpose in Room No. 243, A-Wing, Nirman Bhawan, Maulana Azad Road, New Delhi.

3. You are requested to appear in person or depute an authorized representative to present the case of your Trust/Society vis-à-vis the disapproval letter of the MCI alogwith the requisite information in the enclosed format on the specified date & time failing which the scheme will be decided ex-parte. You are also requested to bring two hard copies and one softcopy of the information/material you propose to present 12

before the committee in the attached format in MS Word. You are also requested to send a letter of confirmation of participation by e-mail sujeet.charan@nic.in.”

13. In pursuance of the communication made by the 1 st

respondent, a team of representatives of the petitioner

College appeared before the Hearing Committee on

09.02.2017 and clarified point-wise compliance of the

remarks/observations made by the Assessors and produced

documentary evidence in that regard. In the second week of

March, 2017, as stated earlier, the petitioners received the

letter dated 01.03.2017 issued by the 1 st respondent

recording the recommendations/orders passed by the

Hearing Committee. Relevant extract of the communication

containing the recommendations of the Hearing Committee

is reproduced below:

“IQ City Medical There is no College, Burwan, West deficiency of faculty, Bengal, [Renewal of residents and clinical Permission of 5th Batch material. (150 seats)] Photographic evidence submitted by the college suggests that the deficiencies relating to air-conditioning in 13

Central library / student’s hostel, resident hostel/RHTC accommodation and specimen have been rectified.

The deficiencies are not such to warrant disapproval at this stage of college.”

14. Though the Hearing Committee had sent the aforesaid

recommendation, yet the 1st respondent thought it

appropriate to refer the matter back to MCI and the manner

of reference is as follows:

“4 IQ City Medical There is no deficiency . College, of faculty, residents Burdwan, West and clinical material.

Bengal Photographic evidence submitted by the Renewal of college suggests that Permission of 5th the deficiencies batch (150 seats) relating to air-conditioning in Central library/ student’s hostel, resident hostel / RHTC accommodation and specimens have been rectified. The deficiencies are not such to warrant disapproval at this stage of college. 14

2. In view of the above, MCI is requested to review the above schemes in light of the recommendations of Hearing Committee alongwith documents submitted by the applicant Colleges and furnish its recommendation accordingly to this Ministry. The compliance submitted by the applicant College are enclosed herewith in original.”

15. It needs to be clarified that the communication also

referred to some other colleges but we are only concerned

with the petitioner College for which we have reproduced the

relevant extract.

16. The team of Assessors who went for compliance

verification conducted a surprise verification on 21.03.2017

and noted certain deficiencies to which we shall refer to at a

later stage.

17. After receipt of the said report, the 1st respondent on

31.05.2017 accepted the Report of the MCI and denied LOP

for the academic year 2017-18. It is the stand of the

petitioners that the said letter was received on 21.06.2017.

Whether letter was received on that day or not is not

relevant in praesenti. What is pertinent is to appreciate the

communication dated 31.05.2017. It reads as follows: 15

“To,

The Principal/Dean, IQ City Medical College, Savapur, Bijra Road, Jemua, Durgapur, West Bengal- 713206

Subject: Renewal of permission for MBBS course for 5th Batch of 150 students at IQ City Medical College, Burdwan, West Bengal for the academic session 2017-18 u/s 10A of IMC Act, 1956 – reg.

Ref No. 12012/127/2016-ME.I(FTS.3084749) dated 31st May, 2017.

Sir,

Drawing reference to the above subject you are directed to submit a present status report of the deficiencies and recommendation of Medical Council of India that were not complied by your Institute and for which the Central Government has directed you NOT to admit any students in MBBS course for academic year 2017-18.

You are further directed to submit Action Taken Report in this regard immediately.”

18. In Dr. Ashish Ranjan and others (supra), the Court,

dealing with establishment of medical college, has stated

thus:

“2. In the “Establishment of Medical College Regulations, 1999”, in “SCHEDULE FOR RECEIPT OF APPLICATIONS FOR ESTABLISHMENT OF NEW MEDICAL COLLEGES AND PROCESSING OF THE APPLICATIONS BY THE CENTRAL GOVERNMENT AND THE MEDICAL COUNCIL OF INDIA” the following shall be substituted as under:

16 TIME SCHEDULE FOR RECEIPT OF APPLICATIONS FOR ESTABLISHMENT OF NEW MEDICAL COLLEGES/RENEWAL OF PERMISSION AND PROCESSING OF THE APPLICATIONS BY THE CENTRAL GOVERNMENT AND THE MEDICAL COUNCIL OF INDIA

Sl. Stage of processing Last Date Nos.

1. Receipt of applications by Between 15th the Central Government June to 7th July (both days inclusive) of any year

2. Forwarding application by By 15th July the Central Government to the Medical Council of India

3. Technical scrutiny, By 15th assessment and December recommendations for letter of permission by the Medical Council of India

4. Receipt of Two months reply/compliance from the from receipt of applicant by the Central recommendatio Government and for n from MCI but personal hearing thereto, if not beyond 31st any, and forwarding of January compliance by the Central Government to the Medical Council of India

5. Final recommendations for By 30th April the letter of permission by the Medical Council of India

6. Issue of letter of By 31st May permission by the Central 17

Government

Note 1.- In case of renewal of permission, the applicants shall submit the application to the Medical Council of India by 15th July.”

19. In Manohar Lal Sharma v. Medical Council of

India and others2, it has been held:

“19. MCI on the basis of the reports, regular and compliance, is legally obliged to form an opinion with regard to the capacity of the college to provide necessary facilities in respect of staff, equipments, accommodation, training and other facilities to ensure proper functioning of the medical college or for increase of admission capacity.”

20. Thereafter, the Court referred to Section 10-A of the

Act and the Establishment of Medical College Regulations,

1999 framed thereunder and ruled:

“24. Surprise inspection, in this case, was conducted to ascertain whether compliance report could be accepted and to ascertain whether the deficiencies pointed out in the regular inspection were rectified or not. By pointing out the deficiencies, MCI is giving an opportunity to the College to rectify the deficiencies, if any noticed by the inspection team. It is the duty of the College to submit the compliance report, after rectifying the deficiencies. MCI can conduct a surprise inspection to ascertain whether the deficiencies

2 (2013) 10 SCC 60 18

had been rectified and the compliance report be accepted or not.”

Eventually, the Court held:

“27. We are also of the view that such an order is not vitiated by violation of principles of natural justice, especially, when no allegation of bias or mala fide has been attributed against the two doctors who constituted the inspection team, which conducted the surprise inspection on 6-7-2013. When the inspection team consists of two doctors of unquestionable integrity and reputation, who are experts in the field, there is no reason to discard the report of such inspection. In such circumstances, we are of the view that MCI has rightly passed the order rejecting the approval for renewal of permission for the third batch of 150 MBBS students granted for the academic year 2013-2014.”

21. In Medical Council of India v. Kalinga Institute of

Medical Sciences (KIMS) and others3, the Court rejected

the stand of the respondents therein. It observed:

“24. Medical education must be taken very seriously and when an expert body certifies that the facilities in a medical college are inadequate, the courts are not equipped to take a different view in the matter except for very cogent jurisdictional reasons such as mala fides of the Inspection Team, ex facie perversity in the inspection report, jurisdictional error on the part of MCI, etc. Under no circumstance should the High Court examine the report as an appellate body — this is simply not the function of the High Court. In the present case there was no ground 3 (2016) 11 SCC 530 19

made out at law for setting aside the report of the Inspection Team.

x x x x x

26. It appears to us that both MCI and the Central Government each having twice considered the inspection report submitted by neutral Medical Professors, with the Central Government having given a personal hearing to KIMS on the second occasion (and perhaps on the first occasion as well) the matter ought to have been given a quietus by the High Court at least for the academic year 2015-2016.”

22. Be it noted, in the said case, the two-Judge Bench took

note of the status of the Assessors and echoed the note that

was sounded in Manohar Lal Sharma (supra) which we

think it apt to reproduce:

“6. Our attention was also drawn to the decision of this Court in Manohar Lal Sharma v. Medical Council of India (supra) wherein it was held that since the inspection is taken by “doctors of unquestionable integrity and reputation, who are experts in the field, there is no reason to discard the report of such an inspection”. In the present appeal, there is no allegation made by KIMS of any mala fides of the inspection team or any perversity in the inspection report and hence, there is no question of challenging the conclusions of a neutral, randomly selected inspection team in its assessment.”

23. In the case at hand, what is urged by Mr. Rohatgi,

learned senior counsel appearing for the petitioners, is that 20

Assessors travelled beyond the order of remand and that

singularly makes the inspection perverse and thereby

vulnerable. At this juncture, it is seemly to refer the

remarks of the Assessors which relate to the following

aspects:

“a. Deficiency of faculty is 15.90% as detailed in the report.

b. Shortage of Residents is 25.88% as detailed in the report.

c. On the day of inspection the number shown is not tallying with number actually present in the hospital. At random verification at 3, OPD registration counters at 12.45 pm, is only 110 (40,30 and 40 new patients). Many patients in the ward are admitted with minor complaints like cough, cold, itching, and the case sheets are not filled up, the bed occupancy is not tallying with number submitted.

d. Students’ Hostels: In Boys’ hostel, Visitors’ room, A.C. Study room with Computer & Internet, Recreation room are not available. e. In Anatomy department, some specimens are not mounted but kept in buckets.”

24. It has also found certain other deficiencies with regard

to casualty attendance, operating work, etc. The College

has replied to the same which is as follows:

“In connection with the above subject I would like to submit the following paragraph for your kind consideration.

1. That during the last MCI inspection held on 3 and 4th Nov 2016 our Faculty & Resident rd 21

deficiency was 2.18 and 3.38 respectively.

However on 21.03.2017 surprise inspection and due to their personal commitment they could not come by 11 AM and could not appear before the assessors.

2. Secondly, the State NEET Post Graduate counseling and the Diplomat in National Board (DNB) counseling in process, many of the senior and Junior Residents and few faculty members had gone to KOLKATA for their counseling hence were not able to appear in the inspection conducted on 21.03.2017.

3. Thirdly most of these faculties and residents are working with us since long time and kind of documentary proof for the same can be submitted, but because of the counseling they were unable to make it.

4. It will not be out of place to mention here that our faculties and residents had gone to attend medical camps in suburban areas as such they could not reach by 11 AM to appear before the assessors.

Hence their absence may kindly be considered to offset the faculty and resident deficiency.”

25. As the facts have unrolled, there is no dispute that the

petitioner College had submitted a scheme for 2017-18 for

intake of 150 candidates. There is also controversy that

there was an inspection and the Hearing Committee had

given certain recommendations and the Central Government

thought it appropriate to send it back to the MCI for the

compliance verification report. Section 10-A of the Act deals 22

with permission for establishment of new medical college,

new course of study, etc. and sub-section (7) thereof deals

with as to what steps have to be taken by MCI while making

its recommendation to the Central Government either

approving or disapproving. Sub-section (7) reads as follows:

“10-A. Permission for establishment of new medical college, new course of study, etc.— (1)-(6) * * * (7) The Council, while making its recommendations under clause (b) of sub-section (3) and the Central Government, while passing an order, either approving or disapproving the scheme under sub-section (4), shall have due regard to the following factors, namely—

(a) whether the proposed medical college or the existing medical college seeking to open a new or higher course of study or training, would be in a position to offer the minimum standards of medical education as prescribed by the Council under Section 19A or, as the case may be, under Section 20 in the case of postgraduate medical education.

(b) whether the person seeking to establish a medical college or the existing medical college seeking to open a new or higher course of study or training or to increase its admission capacity has adequate financial resources;

(c) whether necessary facilities in respect of staff, equipment, accommodation, training and other facilities to ensure proper functioning of the medical college or conducting the new course or study or training or accommodating the increased admission capacity, have been provided or would be provided within the time-limit specified in the scheme;

23 (d) whether adequate hospital facilities, having regard to the number of students likely to attend such medical college or course of study or training or as a result of the increased admission capacity, have been provided or would be provided within the time-limit specified in the scheme;

(e) whether any arrangement has been made or programme drawn to impart proper training to students likely to attend such medical college or course of study or training by persons having the recognised medical qualifications;

(f) the requirement of manpower in the field of practice of medicine; and

(g) any other factors as may be prescribed.”

26. In Manohar Lal Sharma (supra), the Court has

referred to Indian Medical Council (Amendment) Act, 2010

which confers powers on the Board of Governors as per

Section 3-B(b). The said provision reads thus:

“3-B. Certain modifications of the Act.— During the period when the Council stands superseded— * * *

(b) The Board of Governors shall—

(i) exercise the powers and discharge the functions of the Council under this Act and for this purpose, the provisions of this Act shall have effect subject to the modification that references therein to the Council shall be construed as references to the Board of Governors;

(ii) grant independently permission for establishment of new medical colleges or opening a new or higher course of study or training or increase in admission capacity in any course of study or training referred to in Section 10A or giving the person or college concerned a 24

reasonable opportunity of being heard as provided under Section 10A without prior permission of the Central Government under that section, including exercise of the power to finally approve or disapprove the same; and

(iii) dispose of the matters pending with the Central Government under Section 10A upon receipt of the same from it.”

27. Interpreting Section 3-B(b), the Court held thus:

“22. MCI, with the previous sanction by the Central Government, in exercise of its powers conferred by Sections 10-A and 33 of the Indian Medical Council Act, 1956, made the Regulations known as the Establishment of Medical College Regulations, 1999. Regulation 8 of the 1999 Regulations deals with grant of permission for establishment of new college. Application/ Scheme submitted by the applicants is evaluated and the verification takes place by conducting physical inspection by the team of inspectors of MCI. The Board of Governors may grant LoP to the applicant for making admissions in the first year of MBBS course in the medical college and the permission is renewed every year subject to the college achieving the yearly target mentioned in “Minimum Standard Requirements for the Medical College for 150 Admissions Annually Regulations, 1999”. Schedule I of the abovementioned Regulation provides for accommodation in the medical college and its teaching hospital. Schedule II deals with equipment required for various departments in the college and hospital. The requirements are statutorily prescribed and, therefore, the Board of Governors has no power to dilute the statutory requirements mentioned in the abovementioned Regulations.” 25

28. At this stage, we may usefully refer to the directions

enumerated in Royal Medical Trust (Registered) and

another v. Union of India and another4, wherein a

three-Judge Bench was dealing with justifiability of the

communications issued by the Central Government

recommending disapproval of applications preferred in

respect of Medical Colleges of the applicants for the

academic year 2014-15. The Court, referring to Section 10-A

of the Act and the Regulations framed by the MCI and

further adverting to various aspects, ruled:

“31. MCI and the Central Government have been vested with monitoring powers under Section 10A and the Regulations. It is expected of these authorities to discharge their functions well within the statutory confines as well as in conformity with the Schedule to the Regulations. If there is inaction on their part or non-observance of the time schedule, it is bound to have adverse effect on all concerned. The affidavit filed on behalf of the Union of India shows that though the number of seats had risen, obviously because of permissions granted for establishment of new colleges, because of disapproval of renewal cases the resultant effect was net loss in terms of number of seats available for the academic year. It thus not only caused loss of opportunity to the students community but at the same time caused loss to the society in terms of less number of doctors being available. MCI and the Central Government must therefore

4 (2015) 10 SCC 19 26

show due diligence right from the day when the applications are received. The Schedule giving various stages and time-limits must accommodate every possible eventuality and at the same time must comply with the requirements of observance of natural justice at various levels. In our view the Schedule must ideally take care of:

(A) Initial assessment of the application at the first level should comprise of checking necessary requirements such as essentiality certificate, consent for affiliation and physical features like land and hospital requirement. If an applicant fails to fulfil these requirements, the application on the face of it, would be incomplete and be rejected. Those who fulfil the basic requirements would be considered at the next stage. (B) Inspection should then be conducted by the Inspectors of MCI. By very nature such inspection must have an element of surprise.

Therefore sufficient time of about three to four months ought to be given to MCI to cause inspection at any time and such inspection should normally be undertaken latest by January. Surprise inspection would ensure that the required facilities and infrastructure are always in place and not borrowed or put in temporarily.

(C) Intimation of the result or outcome of the inspection would then be communicated. If the infrastructure and facilities are in order, the medical college concerned should be given requisite permission/renewal. However, if there are any deficiencies or shortcomings, MCI must, after pointing out the deficiencies, grant to the college concerned sufficient time to report compliance.

(D) If compliance is reported and the applicant states that the deficiencies stand removed, MCI must cause compliance verification. It is possible 27

that such compliance could be accepted even without actual physical verification but that assessment be left entirely to the discretion of MCI and the Central Government. In cases where actual physical verification is required, MCI and the Central Government must cause such verification before the deadline.

(E) The result of such verification if positive in favour of the medical college concerned, the applicant ought to be given requisite permission/renewal. But if the deficiencies still persist or had not been removed, the applicant will stand disentitled so far as that academic year is concerned.” [Emphasis added]

29. On a reading of Section 10-A of the Act, Rules and the

Regulations, as has been referred to in Manohar Lal

Sharma (supra), and the view expressed in Royal Medical

Trust (supra), it would be inapposite to restrict the power of

the MCI by laying down as an absolute principle that once

the Central Government sends back the matter to MCI for

compliance verification and the Assessors visit the College

they shall only verify the mentioned items and turn a

Nelson’s eye even if they perceive certain other deficiencies.

It would be playing possum. The direction of the Central

Government for compliance verification report should not be

construed as a limited remand as is understood within the

framework of Code of Civil Procedure or any other law. The 28

distinction between the principles of open remand and

limited remand, we are disposed to think, is not attracted. Be it clearly stated, the said principle also does not flow

from the authority in Royal Medical Trust (supra). In this

context, the objectivity of the Hearing Committee and the

role of the Central Government assume great significance.

The real compliant institutions should not always be kept

under the sword of Damocles. Stability can be brought by

affirmative role played by the Central Government. And the

stability and objectivity would be perceptible if reasons are

ascribed while expressing a view and absence of reasons

makes the decision sensitively susceptible.

30. Having said this, we are not inclined to close the

matter. The petitioners have been running the College since

2013-14. We have been apprised that students who have

been continuing their education shall continue for 2017-18.

As we find the order of the Central Government is not a

reasoned one. It is obligatory on its part to ascribe reasons.

For the said purpose, we would like the Central Government

to afford a further opportunity of hearing to the petitioners

and also take the assistance of the newly constituted 29

Oversight Committee as per the order dated July 18, 2017

passed by the Constitution Bench in Writ Petition (Civil) No.

408 of 2017 titled Amma Chandravati Educational and

Charitable Trust and others v. Union of India and

another and thereafter take a decision within two weeks.

Needless to say, the decision shall contain reasons. We

repeat at the cost of repetition that the decision must be an

informed one.

31. Before parting with the case for the present, it is

warrantable to state that “health”, a six letter word, when

appositely spelt and pronounced, makes the body and mind

holistic and an individual feels victorious. Apart from habit

and nature, some external aid is necessary. And that is

why, it is essential to have institutions which are worthy to

impart medical education so that the society has not only

qualified doctors but doctors with impeccable and sensitive

qualities. A lapse has the potentiality to invite a calamity.

Not for nothing, Hippocrates had said, “A wise man ought to

realize that health is his most valuable possession.”

Therefore, the emphasis is on the compliant institutions

that can really educate doctors by imparting quality 30

education so that they will have the inherent as well as

cultivated attributes of excellence.

32. List the matter on 24th August, 2017 awaiting the

decision of the Central Government.

………………………….J. (Dipak Misra)

………………………….J. (Amitava Roy)

………………………….J. (A.M. Khanwilkar) New Delhi.

August 01, 2017

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free