Haryana Urban Development Authority, Karnal vs M/S. Mehta Construction Company & Anr.
- SCC(2022) 5 SCC 432
- Neutral2022 INSC 372
- SCR[2022] 1 SCR 847
Ratio decidendi
The rule this decision rests on
The court may condone a delay of up to thirty days in filing an application to set aside an arbitral award under Section 34(3) of the Arbitration and Conciliation Act, 1996, where the applicant has provided a sufficiently plausible explanation for the delay and the explanation demonstrates prevention by sufficient cause, even where the lower courts have found the explanation inadequate without properly considering the proviso. Courts examining objections to arbitral awards under Section 34 of the Arbitration and Conciliation Act, 1996 must conduct a substantive and in-depth examination of those objections by reference to the relevant statutory provisions, including the Limitation Act, 1963, and applicable grounds for setting aside awards, rather than dismissing them with cryptic, perfunctory, or generalized reasoning that does not engage with specific issues and contentions raised by the objector.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2693 OF 2022 (SPECIAL LEAVE PETITION (CIVIL) NO. 6137 OF 2022) (DIARY NO. 23287 OF 2020)
HARYANA URBAN DEVELOPMENT AUTHORITY, KARNAL ..... APPELLANT(S)
VERSUS
M/S. MEHTA CONSTRUCTION COMPANY AND ANOTHER ..... RESPONDENT(S)
ORDER
Delay condoned. Leave granted.
2. The appellant before us – Haryana Urban Development Authority,
Karnal, Haryana, and the respondent – M/s. Mehta Construction
Company, on 6th July 1998, had entered into an agreement
whereby the respondent was to construct water body, water body
fall, pedestrian bridge, backwall of deck, pump chamber (partly
above and partly below the GI pipe), lay CI and RCC pipes and all
Signature Not Verified other works contingent thereto for development of town park in Digitally signed by DEEPAK SINGH Date: 2022.04.02 14:09:26 IST Reason: Sector 8 and 9 (Phase – II), Karnal, for an amount not exceeding
Civil Appeal @ Diary No. 23287 of 2020 Page 1 of 8 Rs.32.50 lakhs. The scope of the work was enhanced to
Rs.40,23,962/- and then to Rs.45,87,326/-.
3. The contractual work was completed on 24 th August 1999. It is the
case of the appellant that the respondent had failed to comply with
the terms and conditions of the contract and complete the work
within the contractual period, whereas it is the case of the
respondent that the appellant was responsible for the delay in
completion of the work.
4. In April 2012, the respondent filed an application before the
Punjab and Haryana High Court under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (for short, the ‘Act’) for
appointment of an arbitrator for adjudication of disputes in the
subject contract.
5. The application was disposed of vide order dated 19 th October
2012 with a direction to the parties to approach the Arbitrator-cum-
Superintending Engineer, HUDA Circle, Karnal in terms of Clause
25-A of the agreement for settlement of disputes.
6. The sole arbitrator passed an award dated 20 th December 2013
awarding an amount of Rs.1,19,69,945/- along with interest @
18% per annum on the delayed payments.
Civil Appeal @ Diary No. 23287 of 2020 Page 2 of 8
7. On 28th March 2014, the appellant filed objections to the award
before the Additional District Judge, Karnal, under Section 34 of
the Act along with an application for condonation of delay. Upon
notice, the respondent filed reply to both the objections under
Section 34 and the application seeking condonation of delay.
8. By order dated 8th January 2018, the Additional District Judge,
Karnal, held that the objections were barred by limitation and no
plausible explanation was given to explain the delay. On the other
hand, the respondents had duly proved the issues by “leading
cogent and convincing evidence”. He also held that the award
dated 20th December 2013 is perfect and a legal one and the fact
that the respondent had completed the work after thirteen and a
half months proved that the respondent was not able to comply
with the terms and conditions of the contract. The appellant had
granted extension for completion of work time and again without
imposing penalty. Further, it was an admitted case that time was
essence of the contract as there was a default clause.
9. The appellant preferred an appeal under Section 37 of the Act,
which has been dismissed by the impugned judgment dated 11 th
December 2019 passed by the Single Judge of the Punjab and
Civil Appeal @ Diary No. 23287 of 2020 Page 3 of 8 Haryana High Court. The reasoning given by the High Court reads
as under:
“5. The Addl. District Judge, Karnal, while dismissing the objections filed by the appellant under Section 34 of the Act has observed that the arbitration award dated 20.12.2013 passed by the arbitrator is perfect and legal one and there is no ground proved on the file at the instance of the objector that the award suffers from any infirmities at all. It was further observed that the objections filed by the objector are barred by limitation as the same were not filed within the prescribed period. No plausible explanation could be given by the objector, for filing the objections at a belated stage. The Addl. District Judge, Karnal came to hold that the objections filed by the objector are not maintainable and the objections are also barred by limitation. Counsel for the appellant fails to point out any perversity in the findings returned by the court below. Counsel for the appellant miserably failed to point out as to how the objections filed by the appellant were within limitation.”
10. As per sub-section (3) to Section 34 of the Act, an application for
setting aside an award is to be made within three months from the
date on which a party filing objections under sub-section (1) to
Section 34 has received the arbitral award; or, if a request has
been made under Section 33, from the date on which that request
has been disposed of by the arbitral tribunal. However, the proviso
states that the court may condone delay of a period up to thirty
days in filing of the objections if it is satisfied that the applicant is
prevented by sufficient cause from making an application under
Section 34(1) of the Act.
Civil Appeal @ Diary No. 23287 of 2020 Page 4 of 8
11. In the present case, it is an accepted position that the application
for setting aside of the award dated 20 th December 2013 was
made on 28th March 2014 accompanied by an application for
condonation of delay. The court, therefore, had the power to
condone the eight days’ delay, which was less than thirty days, in
terms of the proviso to sub-section (3) to Section 34 of the Act. In
the application seeking condonation of delay, it was inter alia
stated that after receiving a copy of the award at about 6:50 p.m.
on 20th March 2014, the appellant had engaged an empanelled
advocate and the records pertaining to the arbitration case were
constructed and examined. The short delay had also occurred as
sanctions and approvals were required from the higher/competent
authority.
12. Given the aforesaid background and the short condonable delay
which had occurred, we do not think that the High Court and the
Additional District Judge, Karnal were justified in refusing to
condone the delay. The application for condonation of delay in
filing of the objections should have been allowed.
13. Learned counsel for the respondent, however, contends that the
Additional District Judge, Karnal had also dismissed the objections
on merits. We have considered this contention but observe that
Civil Appeal @ Diary No. 23287 of 2020 Page 5 of 8 the observation and findings recorded by the Additional District
Judge are cryptic and perfunctory. The same is equally true of the
reasoning given by the High Court in the impugned order, which is
full of generalisation and does not deal with specific issues and
contentions raised by the appellant in the objections. In particular,
the objection that the claims of the respondent were barred by
limitation.
14. Sub-section (1) to Section 43 of the Act states that the Limitation
Act, 1963 shall apply to arbitrations as it applies to the
proceedings in court. Sub-section (2) to Section 43 states that for
the purpose of Section 43 and Limitation Act, an arbitration shall
be deemed to have commenced on the date referred to in Section
21 of the Act.1 In the context of the present case, several issues
would arise for consideration, including the date on which the
respondent had invoked the arbitration clause, and whether there
was delay thereafter in filing the application under Section 11(6) of
the Act, the legal effect and consequences of the delay, the effect
of the order dated 19th October 2012, etc.
15. Sub-section (2)(a) to Section 34 of the Act inserted with effect
from 23rd October 2015 states that the arbitral award may be set
1 For the purpose of this decision, we need not refer to sub-section (3) to Section 43 of the Act, which provision, if relied, can be examined.
Civil Appeal @ Diary No. 23287 of 2020 Page 6 of 8 aside by the court if the court finds the award is vitiated by patent
illegality appearing on the face of the award. The proviso
stipulates that the award shall not be set aside merely on the
ground of erroneous application of law or by misappreciation of
evidence. An award can also be set aside under sub-clause (ii) to
clause (b) of Section 34(2) on the ground that it is in conflict with
the public policy of India, which expression has been explained in
the Explanation(s) to the said Section.
16. We have briefly noted the provisions of the Act only to highlight
that the objections under Section 34 of the Act did require
consideration and in-depth examination and should not have been
dismissed without proper and full application of mind with
reference to the provisions of the Limitation Act and the Act.
17. In these circumstances, and for the reasons stated, we have no
option but to allow the present appeal and set aside the impugned
order dated 11th December 2019 passed by the High Court as well
as the order dated 8th January 2018 passed by the Additional
District Judge, Karnal.
18. We would remit the matter to the file of the Additional District
Judge, Karnal, who would hear the objections afresh and on
merits without being influenced by the earlier orders and also the
Civil Appeal @ Diary No. 23287 of 2020 Page 7 of 8 present order. We clarify that the observations made in this order
are for the disposal of the present appeal and would not be
treated as observations that are binding on the Additional District
Judge, Karnal, when he examines and decides the objections
under Section 34 of the Act on merits.
19. The appeal is allowed in the above terms with no order as to
costs.
......................................J. (AJAY RASTOGI)
......................................J. (SANJIV KHANNA) NEW DELHI;
MARCH 30, 2022.
Civil Appeal @ Diary No. 23287 of 2020 Page 8 of 8
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free