Miss Lucy
← All judgments

H. Lathakumari vs Vamanapuram Block Panchayat & Ors

Supreme Court7 July 2009J M Panchal · R V Raveendran

Ratio decidendi

The rule this decision rests on

Where a government department or statutory body has not itself deleted an arbitration clause from the standard specifications forming part of a contract, but instead entered into a new contract expressly incorporating those specifications without excluding the arbitration clause, the arbitration clause remains valid and enforceable as part of the contract, notwithstanding a Government Order that applied only to a specific department (the Public Works Department) and left other departments free to make their own decisions about deletion.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 4152 OF 2009 (Arising out of SLP [C] No.7656 of 2006)

H.Lathakumari ... Appellant

Vs.

Vamanapuram Block Panchayat & Ors. ... Respondents

JUDGMENT

R.V. RAVEENDRAN, J.

Leave granted. Heard both parties.

2. The Vamanapuram Block Panchayat, first respondent herein, entered

into a "contract agreement" dated 15.3.1999 with the appellant under which

the work of "RIDF-III, Pangode Sivakshetram - Thannichal Road

improvements" was entrusted to her as per the articles of agreement, plans,

specifications and conditions of contract approved by the Superintending

Engineer, Commissionerate of Rural Development, State of Kerala. The 2

Articles of agreement confirmed that the contractor had also signed the copy

of the Madras Detailed Standard Specifications (for short `MDSS') and

addenda volume thereto in acknowledgement of being bound by all the

conditions of the clauses. The MDSS which thus became a part of the

contract between the parties, provided for settlement of disputes by

arbitration vide clause 73 which is extracted below :

"73. Arbitration.--In case of any dispute or difference between the parties to the contract either during the progress or after the completion of the works or after the determination, abandonment, or breach of the contract as to the interpretation of the contract, or as to any matter or thing arising thereunder except as to the matters left to the sole discretion of the Executive Engineer under clauses 20, 22, 27(c), 29, 36, 37 and 40 of the Preliminary Specification, or as to the withholding by the Executive Engineer of payment of any bill to which the contractor may claim to be entitled, then either party shall forthwith give to the other notice of such dispute or difference, and such dispute or difference shall be and is hereby referred to the arbitration of the Superintending Engineer of the nominated circle mentioned in the `Articles of Agreement" (hereinafter called the "arbitrator") and the award of such arbitrator shall be final and binding on the parties."

3. Certain disputes having arisen in respect of the said contract, the

appellant, by letter dated 28.12.2000, sought reference to arbitration of its

claims aggregating to Rs.13,06,936/- in terms of the aforesaid arbitration

clause contained in the MDSS forming part of the agreement. The Block

Development Officer, Vamanapuram Panchayat, sent a reply dated 4.1.2001

denying the claims and informing the contractor that if she did not resume

the work, the contract would be terminated at her risk and cost. The 3

respondents, however, did not deny the existence of the arbitration

agreement in the said reply.

4. Thereafter, the appellant filed an application under section 11 of the

Arbitration & Conciliation Act, 1996 (`Act' for short) seeking appointment

of an Arbitrator. The first respondent filed a counter denying the claims and

also contending that there was no arbitration agreement. The said application

was dismissed by the designate of the Chief Justice of the High Court by

order dated 13.1.2003. He considered the contention of the appellant that

there was an arbitration agreement in terms of clause 73 of MDSS for

resolving the disputes. He also referred to the contention of the

respondents that the government had decided to scrap arbitration by

Government Order dated 19.11.1988, relevant portions of which read as

under :

"On a detailed examination of the matter, Government finds that the system of arbitration has generally gone against the interests of the government and therefore, government has decided to stop altogether the system of referring the disputes for arbitration under any circumstances.

Accordingly, Government orders the following :

(1) xxxxxxxx

(2) Disputes and differences arising between the department and the

contractors in the PWD contracts shall not be referred to arbitration hereafter and all provisions relating to arbitration in the tender documents shall be deleted or scored off under the signature of the executing parties. However, if any work is financed by an agency and that agency insists to have provision for arbitration, 4

provision for arbitration may be provided in the agreement in respect of such work.

(3) xxxxx

(4) The question of adopting the above procedure in other departments

and organizations like Kerala State Electricity Board will be examined by the concerned department."

[emphasis supplied]

The learned Designate of the Chief Justice accepted the said contention of

the respondents and held as follows :

"In view of the above notification (Government Order?) the arbitration clause in the tender documents and in the agreement shall stand deleted or scored off. When the above arbitration clause from the tender documents had been specifically deleted by the above notification, the applicant cannot again rely on the above arbitration clause and seek an order for appointing an arbitrator. As the above arbitration clause has been deleted by the above notification, the prayer for appointing an arbitrator for resolving the disputes and differences between the parties cannot be allowed."

5. The said order is challenged in this appeal by special leave. The

question therefore is whether there is an arbitration agreement between the

parties? The first respondent did not deny the existence of an arbitration

clause in terms of clause 73 of MDSS, which was admittedly a part of the

agreement. The contention was that the said arbitration clause stood deleted

from contracts in view of the G.O. dated 19.11.1988. The question is

whether the arbitration clause has, in fact, stood deleted. A reading of the

said order dated 19.11.1988 clearly shows that the deletion of the arbitration 5

clause was directed only in regard to the Public Work Department contracts.

In fact, it specifically provided that the question of adopting such deletion by

other departments of the Government or by statutory bodies would be

examined by the concerned department/statutory body. It is thus clear that

the deletion of clause 73 of MDSS from the contract was made applicable

only in regard to the contracts entered into by the Public Works Department

of the State of Kerala and the question whether other governmental or quasi-

governmental agencies should delete such a provision, was left to the

individual decision/discretion of the respective authorities.

6. Admittedly, neither the first respondent nor the Panchayat Raj

Department, decided to delete the arbitration clause. On the other hand, the

first respondent entered into an agreement with the appellant long after the

said Government Order dated 19.11.1988, that is, on 15.3.1999 and did not

choose to delete clause 73 from the MDSS made part of the agreement. If

the first respondent wanted to delete the arbitration agreement, it ought to

have scored out clause 73 from the MDSS which was signed and made a

part of the agreement or included a clause in the agreement that clause 73 of

MDSS would not apply or that there shall be no arbitration. That was not

done. In fact, in PWD contracts, to which the bar on arbitration was applied,

the printed form of Articles of Agreement was amended to include a clause 6

which confirmed that the "contractor has also signed the copy of the Madras

Detailed Standard Specifications excluding clause 73 and other clauses

relating to arbitration......" Significantly such an exclusion is not made in

the articles of Agreement entered by the first respondent Panchayat. It is thus

clear that the arbitration clause was intended to form a part of the contract

between the parties. Therefore, the disputes between the parties are

referable to arbitration in terms of the said arbitration agreement. No other

objection to the arbitration is raised.

7. In view of the above, the appeal is allowed and the first respondent is

directed to refer the disputes to the Superintending Engineer in terms of the

arbitration agreement contained in clause 73 of MDSS within six weeks

from today. Nothing stated above shall be construed as an expression of any

opinion on the merits of the claim.

..............................J. (R V Raveendran)

New Delhi; .............................J. July 7, 2009. (J M Panchal)

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free